Está en la página 1de 7

HOJA DE METRADOS

04.00.00 OBRAS DE ARTE Y DRENAJE


04.07.00 BADENES
04.07.05 CONCRETO f'c = 245 Kg / cm2

PAÑOS DE 5.00x6.00
LOSA (M3/PAÑO)
ALTO ANCHO LONGITUD VOLUMEN No. VECES VOLUMEN (m3)
0.25 5.00 6.00 7.50 1.00 7.50
Total 7.50

UÑA EN LOSA DE APROXIMACION (M3/ML)


ESPESOR ANCHO1 ANCHO2 PROMEDIO LONGITUD VOLUMEN (m3)
0.750 0.50 0.25 0.38 1.00 0.28
Total 0.28

AFIRMADO (M3/PAÑO)
ESPESOR ANCHO LONGITUD VOLUMEN No. VECES VOLUMEN (m3)
0.150 4.53 6.00 4.07 1.00 4.07
Total 4.07

ALIVIADERO DE PIEDRA EMBOQUILLADA


ESPESOR ANCHO LONGITUD AREA No. VECES AREA (m2)
0.300 6.00 6.00 10.80 1.00 10.80
Total 10.80

ADECUACIÓN Y ACTUALIZACIÓN DE LOS ESTUDIOS DEFINITIVOS DE INGENIERIA PARA LA REHABILITACIÓN Y


MEJORAMIENTO DE LA CARRETERA: PUENTE PAUCARTAMBO – OXAPAMPA.
HOJA DE METRADOS
04.00.00 OBRAS DE ARTE Y DRENAJE
04.07.00 BADENES
04.07.04 ACERO DE REFUERZO f'y = 4200 Kg / cm 2

REFUERZO EN LA LOSA
TIPO DESCRIPCION Ø LONG/PIEZA BARRA/PIEZA CANTIDAD BARRAS LONGITUD @ Nº de veces

B1 .15 1/2 5.00 5/9 42 23.33 6 0.30 2


4.85

B2 0.20 1/2 6.40 3/4 36 27 5 0.30 2

B6 5/8 6.00 2/3 4 2.67

B7 0.15 3/8 0.80 1/9 36 4 5 0.30 2

0.15

5.00
B8 5/8 5.00 5/9 8 4.44 2

61.44
REFUERZO EN UÑA
TIPO DESCRIPCION Ø LONG/PIEZA BARRA/PIEZA CANTIDAD BARRAS LONGITUD @ Nº de veces

6.00
B3 1/2" 6.00 2/3 2 1.33

6.00

B4 3/8" 6.00 2/3 2 1.33

0.30 0.30

B5 .90 .95 3/8" 2.61 3/9 31 10.33 6 0.2 1

0.16

ADECUACIÓN Y ACTUALIZACIÓN DE LOS ESTUDIOS DEFINITIVOS DE INGENIERIA PARA LA REHABILITACIÓN Y MEJORAMIENTO DE LA CARRETERA:
PUENTE PAUCARTAMBO – OXAPAMPA.
HOJA DE METRADOS
04.00.00 OBRAS DE ARTE Y DRENAJE
04.07.00 BADENES
04.07.04 ACERO DE REFUERZO f'y = 4200 Kg / cm 2

BARRA LISA EN JUNTAS


TIPO DESCRIPCION Ø LONG/PIEZA BARRA/PIEZA CANTIDAD BARRAS LONGITUD @ Nº de veces

1.20
LONG. 3/4" 1.20 1/6 21 3.5 6 0.3 1

1.40

TRANSV 3/4" 1.40 1/6 17 2.83 5 0.3 1

ARMADURA x PAÑO de 5m. x 6m.


DESCRIPCION 3/8" 1/2" 5/8" 3/4" 1"
Peso (Kg/m) 0.56 1 1.55 2.24 3.97

LOSA 4 50 1/3 4 4/9

TOTAL VARILLAS 4.0 50.3 4.4 0.0 0.0


KG 20.2 453.0 62.0 0.0 0.0
TOTAL 535.16 KG.

UÑA x 6 ml
DESCRIPCION 3/8" 1/2" 5/8" 3/4" 1"
Peso (Kg/m) 0.56 1 1.55 2.24 3.97

UÑA 11 2/3 1 1/3

TOTAL VARILLAS 11.7 1.3


KG 58.8 12.0
TOTAL 70.80 KG.

ADECUACIÓN Y ACTUALIZACIÓN DE LOS ESTUDIOS DEFINITIVOS DE INGENIERIA PARA LA REHABILITACIÓN Y MEJORAMIENTO DE LA CARRETERA:
PUENTE PAUCARTAMBO – OXAPAMPA.
HOJA DE METRADOS
04.00.00 OBRAS DE ARTE
04.07.00 BADENES
04.07.03 ENCOFRADO Y DESENCOFRADO

ENCOFRADO DE BADENES
DESCRIPCION LARGO ALTURA No. VECES AREA ANCHO ALTURA No. VECES AREA TOTAL
LOSA
4x5x6 20.00 0.25 3.00 15.00 10.00 0.25 5.00 12.50 27.50
4x5x4 27.50
LOSA
4x5x6 15.00 0.25 3.00 11.25 10.00 0.25 5.00 12.50 23.75
4x5x1.5 23.75
LOSA
4x5x6 25.00 0.25 3.00 18.75 10.00 0.25 5.00 12.50 31.25
4x5x6.5 31.25
LOSA
8x5x6 30.00 0.25 3.00 22.50 10.00 0.25 7.00 17.50 40.00
4x5x3 40.00
LOSA
12x5x6 40.00 0.25 3.00 30.00 10.00 0.25 9.00 22.50 52.50
4x5x2 52.50

UÑAx ML
TAPAS 0.50 0.25 0.38 0.75 1.00 0.28
LATERAL 1 1.00 0.75 1.00 0.75

ADECUACIÓN Y ACTUALIZACIÓN DE LOS ESTUDIOS DEFINITIVOS DE INGENIERIA PARA LA REHABILITACIÓN Y MEJORAMIENTO DE LA


CARRETERA: PUENTE PAUCARTAMBO – OXAPAMPA.
HOJA DE METRADOS
04.00.00 OBRAS DE ARTE Y DRENAJE
04.07.00 BADENES
04.07.01 EXCAVACION PARA ESTRUCTURAS
04.07.02 BASE
04.07.06 JUNTA ASFALTICA LONGITUDINAL

EXCAVACION RELLENO PAÑOS ACERO (kg) ENCOFRADO (m2) CONCRETO f'c=245 (m3) JUNTAS AFIRMADO (M3)
PROGRESIVA DESCRIPCION LARGO ANCHO ALTO
m3 m3 5x6 5 x Var. LOSA UÑA Barra Lisa LOSA UÑA LOSA UÑA (ml) e=0.15
2+518.00 BADENES 20 10 0.25 16.31 0.00 4x5x6 4x5x4 3,567.73 696.20 496.38 27.50 45.75 50.00 16.24 50.00 27.00
5+589.00 BADENES 15 10 0.25 13.5 0.00 4x5x6 4 x 5 x 1.5 2,675.80 578.20 450.69 23.75 38.25 37.50 13.44 45.00 20.25
5+715.00 BADENES 20 10 0.25 16.31 0.00 4x5x6 4x5x4 3,567.73 696.20 496.38 27.50 45.75 50.00 16.24 50.00 27.00
6+184.00 BADENES 30 10 0.25 21.94 0.00 8x5x6 4x5x3 5,351.60 932.20 794.15 40.00 61.88 75.00 21.84 80.00 40.50
7+675.00 BADENES 25 10 0.25 19.13 0.00 4x5x6 4 x 5 x 6.5 4,459.67 814.20 414.40 31.25 53.25 62.50 19.04 55.00 33.75
8+386.00 BADENES 15 10 0.25 13.5 0.00 4x5x6 4 x 5 x 1.5 2,675.80 578.20 450.69 23.75 38.25 50.00 13.44 45.00 20.25
10+277.00 BADENES 25 10 0.25 19.13 0.00 4x5x6 4 x 5 x 6.5 4,459.67 814.20 539.39 31.25 53.25 62.50 19.04 55.00 33.75
12+232.00 BADENES 30 10 0.25 21.94 0.00 8x5x6 4x5x3 5,351.60 932.20 794.15 40.00 61.88 75.00 21.84 80.00 40.50
13+726.00 BADENES 30 10 0.25 21.94 0.00 8x5x6 4x5x3 5,351.60 932.20 794.15 40.00 61.88 75.00 21.84 80.00 40.50
15+710.00 BADENES 20 10 0.25 16.31 0.00 4x5x6 4x5x4 3,567.73 696.20 496.38 27.50 45.75 50.00 16.24 50.00 27.00
20+785.00 BADENES 20 10 0.25 16.31 0.00 4x5x6 4x5x4 3,567.73 696.20 496.38 27.50 45.75 50.00 16.24 50.00 27.00
21+050.00 BADENES 40 10 0.25 27.56 0.00 12 x 5 x 6 4x5x2 7,135.47 1,168.20 1,091.93 52.50 78.00 100.00 27.44 110.00 54.00
22+860.00 BADENES 20 10 0.25 16.31 0.00 4x5x6 4x5x4 3,567.73 696.20 496.38 27.50 45.75 50.00 16.24 50.00 27.00
23+304.00 BADENES 20 10 0.25 16.31 0.00 4x5x6 4x5x4 3,567.73 696.20 496.38 27.50 45.75 50.00 16.24 50.00 27.00
23+507.00 BADENES 25 10 0.25 19.13 0.00 4x5x6 4 x 5 x 6.5 4,459.67 814.20 539.39 31.25 53.25 62.50 19.04 55.00 33.75
23+738.00 BADENES 25 10 0.25 19.13 0.00 4x5x6 4 x 5 x 6.5 4,459.67 814.20 539.39 31.25 53.25 62.50 19.04 55.00 33.75
26+355.00 BADENES 30 10 0.25 21.94 0.00 8x5x6 4x5x3 5,351.60 932.20 794.15 40.00 61.88 80.00 21.84 80.00 40.50
30+845.00 BADENES 20 10 0.25 16.31 0.00 4x5x6 4x5x4 3,567.73 696.20 496.38 27.50 45.75 50.00 16.24 50.00 27.00
38+821.00 BADENES 20 10 0.25 16.31 0.00 4x5x6 4x5x4 3,567.73 696.20 496.38 27.50 45.75 50.00 16.24 50.00 27.00
39+388.00 BADENES 15 10 0.25 13.5 0.00 4x5x6 4 x 5 x 1.5 2,675.80 578.20 450.69 23.75 38.25 37.50 13.44 45.00 20.25
39+840.00 BADENES 20 10 0.25 16.31 0.00 4x5x6 4x5x4 3,567.73 696.20 496.38 27.50 45.75 50.00 16.24 50.00 27.00
40+965.00 BADENES 15 10 0.25 13.5 0.00 4x5x6 4 x 5 x 1.5 2,675.80 578.20 450.69 23.75 38.25 37.50 13.44 45.00 20.25
TOTAL 500 392.63 0.00 89,193.33 16,732.40 12,571.28 680.00 1,103.27 1,267.50 390.88 1,280.00 675.00

ADECUACIÓN Y ACTUALIZACIÓN DE LOS ESTUDIOS DEFINITIVOS DE INGENIERIA PARA LA REHABILITACIÓN Y MEJORAMIENTO DE LA CARRETERA: PUENTE PAUCARTAMBO – OXAPAMPA.
RESUMEN DE METRADOS - BADENES
04.07.00 BADENES

ITEM DESCRIPCION UNID CANTIDAD

MOVIMIENTO DE TIERRAS
04.07.01 Excavación Para estructuras m3 1158.69
04.07.02 Base (e = 0.15 m) m3 675
04.07.03 Encofrado y Desencofrado m2 1783.27

ACERO DE REFUERZO 118497.01


04.07.04 Acero Corrugado kg 105925.733
04.07.04 Acero Liso kg 12571.28

04.07.05 Concreto f'c=245 kg/cm2 m3 1658.38

04.07.06 Juntas Asfaltica Longitudinal ml 1280

04.07.07 Aliviadero de Piedra Emboquillada m2 612

ADECUACIÓN Y ACTUALIZACIÓN DE LOS ESTUDIOS DEFINITIVOS DE INGENIERIA PARA LA REHABILITACIÓN Y


MEJORAMIENTO DE LA CARRETERA: PUENTE PAUCARTAMBO – OXAPAMPA.
495201110.xls
MUROS
PROGRESIVA AREA ENCOFRADO (m2) Piedra Acomdada JUNTAS
DESCRIPCION TIPO LARGO ANCHO ALTO LADO 1 LADO 2
INICIO FIN UÑA MURO MURO TAPAS TOTAL m3 (ml)
2+505.00 2+528.00 BADENES 6 23.00 3.60 6 0.7 12.37 7.03 6.12 302.45 65.35 367.80 0.00 45.45
5+705.00 5+718.00 BADENES 4 13.00 2.4 4 0.7 5.28 5.02 4.02 117.52 17.94 135.46 0.00 10.64
8+375.00 8+388.00 BADENES 2 13.00 1.3 2 1.55 2.01 2.07 53.04 4.65 57.69 0.00 4.78
15+700.00 15+710.00 BADENES 2 10.00 1.3 2 1.55 2.01 2.07 40.80 4.65 45.45 0.00 4.78
22+844.00 22+865.00 BADENES 3 21.00 2 3 3.45 3.01 3.06 127.47 17.25 144.72 0.00 21.81
23+294.00 23+307.00 BADENES 4 13.00 2.4 4 0.7 5.28 5.02 4.02 117.52 17.94 135.46 0.00 10.64
23+725.00 23+745.00 BADENES 3 20.00 2 3 3.45 3.01 3.06 121.40 13.80 135.20 0.00 14.54
30+830.00 30+853.00 BADENES 6 23.00 3.6 6 0.7 12.37 7.03 6.12 302.45 65.35 367.80 0.00 45.45

TOTAL 136.00 1,389.58 0.00 158.09


(*) Los Muros Badenes no cuentan con Aliviaderos de piedra emboquillada se les colocará piedra acomodada