Zapata Aislada y Combinada
Zapata Aislada y Combinada
ACI 318S-08
Col: 3A
Pd = 42417.92 Kg
Pl = 13527.36 Kg
Df = 1.20 m
S/C = 500 Kg/m²
t1 = 0.75 m
t2 = 0.30 m
hc = 0.20 m
ϒm = 1900 Kg/m³
σt = 0.90 Kg/cm²
f'c = 210 Kg/cm²
f'c = 280 Kg/cm²
fy = 4200 Kg/cm²
𝜎_𝑛=𝜎_𝑡−𝛾_𝑝𝑜𝑚∙ℎ_𝑓−ℎ_𝑧∙𝛾_(𝑐−)
1° Esfuerzo Neto del Terreno 𝑆/𝐶
σn = 0.57 Kg/cm²
T = 3.35 m 3.35 m
S = 2.89 m 2.90 m
● Por Punzonamiento
𝑉_𝑈≤ 〖∅∙𝑉〗 φ = 0.75
_𝐶- 0.75(75 + d)(30 + d)
Vu = 72545.28
φVc =
1.06∙∅∙√(𝑓^′ 𝑐)∙𝑏_𝑜∙𝑑
d = 20.66 cm
𝑏_𝑜=2∙(𝑡1+𝑑)+2∙(𝑡2+𝑑)
r = 7.5 cm
Diametro de Varilla φ : 5/8" hz = 30 cm hz = 30 cm
dprom = 20.9125 cm
Vu/φVc = 0.92
𝑙_𝑑𝑐=0.075∙𝑓_𝑦/(𝜆∙√(𝑓_𝑐^ ldcmin = 20 cm
′ ))∙𝑑_𝑏
● En la Columna 𝑙_𝑑𝑐=0.0044∙𝑓_𝑦∙𝑑_𝑏
ldc = 23.9 cm
● En la Zapata ldc = 27.6 cm Valor Predominante
Longitud disponible para el Desarrollo de las Barras o Dowels a compresión = 30 - 7.5 - 3.175 - 1.27
= 19
Aumentar la Altura de la Zapata o cambiar el Diamtro de las Barras(Dowels) para garantizar el desarrollo ldc
𝑙_𝑑=(𝑓𝑦/(3.51∙𝜆∙√(𝑓^′
(𝑐_𝑏+𝑘_𝑡𝑟)/𝑑_𝑏
𝑐))∙(𝜓_𝑡∙𝜓_𝑒∙𝜓_𝑠)/(((𝑐_𝑏+𝑘_𝑡𝑟)/𝑑_𝑏 ) 𝑘_𝑡𝑟=(40∙𝐴_𝑡𝑟)/𝑠
))∙𝑑_𝑏 ≤2.5 𝑛
Cb = 1.80 cm
Ktr = 0.00 No hay Estribos 1.1 1.1
db = 1.5875 cm
(𝑐_𝑏+𝑘_𝑡𝑟)/
Ψt = 1 𝑑_𝑏 ≤
Ψe = 1.0 Ψt*Ψe = 1 < 1.7
Ψs = 0.8
λ = 1.0 C° de Peso Normal
ld = 92 cm
ldmin = 30 cm
Lv1 = Lv2 =
𝐿_𝑉−𝑟 1.3𝐿_𝑉1=(𝑇−𝑡_1)/2
m Λ
𝐿_𝑉2=(𝑆−𝑡_2)/2
Longitud de Desarrollo disponible en ambos sentidos Ld = 1.23
3635298.1849
20.66
92266.854844
√(𝐴_2/𝐴_1
)≤2
_𝑛𝑏=0.85∙𝑓_𝑐^′∙𝐴_𝑂
ldc1 = 23.9 cm
ldc2 = 23.5 cm
ldc1 = 27.6 cm
ldc2 = 23.5 cm
Distancia medida del centro de una barra o alambre a la superficie mas cercana del conc
Cb =
La mitad de la separación centro a centro de las barras o alambres que se desarrollan
30 - 7.5 - 3.175 - 1.27 Nota: Colocar la Primera Capa de Refuerzo en la Dirección Corta y la Segunda Capa
cm en la Dirección Larga
garantizar el desarrollo ldc
Direccion Longitudinal
5.08
7.5 + 1.5*1.5875
𝑐_𝑏=𝑟+ 〖 1.5∙𝑑
〗 _𝑏
Direccion Transversal
m 13.201041667
Cb = 8.3 𝑐_𝑏=𝑟+𝑑_𝑏
𝑐_𝑏=(𝑆−2∙(𝑟+𝑑_𝑏 ))/(2∙(𝑛−1) ) /2
335 - 2*(7.5 + 1.5875)
24
PERALTE Rigidez Resorte
(m) (Tn/m)
𝑏=𝑟+𝑑_𝑏
7.5 + 1.5875/2
𝑐_𝑏=𝑟+𝑑_𝑏
/2
MX MY MZ Story Point Load FX
162.178 -1524.115 -0.195 BASE 6 PL -973.11
-138.388 -897.621 -0.195 BASE 7 PL -624.31
-801.235 -24.105 -0.195 BASE 12 PL -9.29
-596.644 -432.078 -0.304 BASE 14 PL -327.73
-604.555 300.476 -0.304 BASE 15 PL 248.2
-526.417 -95.846 -0.304 BASE 17 PL -53.69
-530.826 -285.386 -0.224 BASE 18 PL -212.71
-526.705 148.317 -0.224 BASE 19 PL 112.89
-326.672 -183.01 -0.224 BASE 21 PL -113.14
-100.121 154.655 -0.224 BASE 24 PL 105.54
354.18 287.375 -0.195 BASE 25 PL 180.24
-4.263 420.525 -0.195 BASE 26 PL 292.44
256.495 255.912 -0.195 BASE 29 PL 161.98
328.67 23.446 -0.224 BASE 30 PL 23.34
239.313 -331.614 -0.332 BASE 32 PL -230.63
227.933 -496.367 -0.304 BASE 33 PL -346.37
268.857 -358.424 -0.264 BASE 35 PL -246.41
379.685 -261.457 -0.195 BASE 36 PL -183.32
420.641 134.303 -0.195 BASE 37 PL 102.99
-55.229 52.489 -0.97 BASE 60 PL 17.28
-59.134 -4.974 -0.97 BASE 62 PL -7.25
-31.261 -262.431 -0.97 BASE 64 PL -107.66
154.932 -342.691 -0.97 BASE 67 PL -110.38
-39.379 -356.149 -0.97 BASE 69 PL -116.82
104.205 -262.093 -0.97 BASE 71 PL -84.24
-285.507 -692.354 -17.108 BASE 72 PL 4059
-2241.497 1165.386 94.151 BASE 73 PL -4551.42
1206.807 -822.372 -19.996 BASE 76 PL 4631.58
2276.929 1321.682 -58.432 BASE 77 PL -5565.29
19.477 -1301.459 -18.573 BASE 78 PL 5909.83
449.103
1049.105 370.393
-1353.964 -18.931
24.615 BASE
BASE 79
80 PL
PL -7005.12
6113.75
478.121 405.821 5.309 BASE 81 PL -7339.2
-1429.826 6108.612 -0.97 BASE 93 PL 2143.83
868.825 -3189.12 -0.97 BASE 94 PL -1008.34
-30.557 439.818 -0.97 BASE 95 PL 177.31
-56.741 673.841 -0.97 BASE 96 PL 259.03
106.753 735.224 -0.97 BASE 97 PL 279.47
-327.166 -171.147 -0.97 BASE 98 PL -50.24
14.574 -64.768 -0.97 BASE 99 PL -16.61
-786.741 -1932.965 -0.97 BASE 100 PL -682.99
-1146.464 2606.407 -0.97 BASE 101 PL 822.01
-1453.711 1558.098 -0.97 BASE 102 PL 592.78
12.759 -61.482 -0.97 BASE 103 PL -12.3
-174.399 41.018 -0.97 BASE 104 PL 24.82
276.933 16.223 -0.97 BASE 105 PL 15.61
-1339.511 1436.021 -0.97 BASE 106 PL 545.94
-455.073 -1587.566 -0.97 BASE 107 PL -586.29
260.682 -1879.183 -0.97 BASE 108 PL -804.41
-2103.792 -3339.122 -0.97 BASE 109 PL -1207.23
-1122.182 1893.973 -0.97 BASE 110 PL 667.34
681.579 -673.256 -0.97 BASE 111 PL -124.74
-1250.795 1710.358 -0.97 BASE 112 PL 595.33
-712.578 -4873.559 -0.97 BASE 113 PL -1628.94
-36.546 523.452 -0.97 BASE 114 PL 208.49
-2561.754 -2092.198 -0.97 BASE 115 PL -703.27
-643.263 539.472 -0.97 BASE 116 PL 205.76
-38.937 983.414 -0.97 BASE 117 PL 366.61
-3469.313 2691.067 -0.97 BASE 118 PL 974.93
-672.179 -208.35 -0.97 BASE 119 PL -63.81
2373.965 -3015.379 -0.97 BASE 120 PL -1102.07
-1264.026 -2636.173 -0.97 BASE 121 PL -978.4
3338.728 4.209 -0.97 BASE 122 PL -6.77
-305.363 -465.604 -1.115 BASE 123 PL -83.87
347.749 -2108.817 -1.115 BASE 124 PL -364.77
-1531.998 -3290.31 -0.97 BASE 125 PL -947.65
-195.198 -602.802 -0.97 BASE 126 PL -201.52
2820.85 -1933.877 -0.97 BASE 127 PL -658.27
148.241 75.58 -0.256 BASE 191 PL 52.96
FY FZ MX MY MZ
-124.07 23817.8 72.937 -698.479 -0.115
92.64 24781.59 -64.857 -449.44 -0.115
569.62 29262.12 -409.884 -5.664 -0.115
424.84 21544.07 -305.359 -194.715 -0.211
430.91 27088.38 -310.336 148.261 -0.211
379.1 19863.83 -272.735 -31.569 -0.211
389.28 23682.68 -279.986 -137.472 -0.156
388.03 23985.48 -279.289 73.327 -0.156
242.63 13527.36 -174.522 -73.101 -0.156
103.05 9893.91 -66.001 75.08 -0.156
-236.89 13020.35 154.921 131.345 -0.115
6.11 21912.1 -1.753 210.159 -0.115
-169.54 14537.78 122 104.872 -0.115
-227.19 14182.28 163.481 15.113 -0.156
-161.48 9422.75 116.197 -137.338 -0.247
-152.72 18478.28 109.893 -206.26 -0.211
-176.39 17091.1 126.93 -146.738 -0.155
-270.08 23039.97 194.346 -118.687 -0.115
-297.67 23605.28 214.202 66.679 -0.115
21.23 73040.52 -29.335 6.233 -0.57
21.2 71294.14 -29.293 -25.908 -0.57
10.47 71656.86 -14.626 -161.717 -0.57
-48.08 80507.27 77.646 -168.187 -0.57
22.18 77494.73 -18.342 -175.606 -0.57
-32.83 77357.45 56.815 -129.715 -0.57
40.97 22402.92 -35.603 -353.241 1.621
401.67 26554.96 -812.587 603.051 34.278
-486.34 25052.55 604.636 -411.368 -14.562
-804.7 32616.78 1343.473 679.272 -40.229
14.61 32360.05 -80.775 -654.651 -14.975
-116.28
-384.18 35918.04
33411.03 256.871
656.793 193.47
-679.736 -12.934
19.75
-167.16 37777.72 199.203 211.776 7.713
506.98 41919.71 -693.331 2894.026 -0.57
-259.46 65441.12 348.067 -1387.513 -0.57
8.72 59578.25 -16.367 226.238 -0.57
17.6 56329.39 -28.498 339.256 -0.57
-42.2 53297.74 53.203 368.568 -0.57
125.47 54383.59 -172.886 -87.123 -0.57
-9.09 60854.82 10.029 -35.943 -0.57
285.41 61635.68 -388.128 -946.869 -0.57
357.37 68900.73 -485.903 1103.591 -0.57
543.02 72614.51 -736.074 786.563 -0.57
-3.11 84050.16 5.994 -34.184 -0.57
65.89 85190.97 -88.285 17.902 -0.57
-103.14 84172.89 142.647 6.694 -0.57
494.91 83747.92 -670.709 728.498 -0.57
164.45 68480.72 -219.621 -815.478 -0.57
-39.43 53687.88 57.4 -1109.039 -0.57
777.46 78909.89 -1052.55 -1653.601 -0.57
465.96 63093.02 -627.395 887.877 -0.57
-187.88 22957.87 261.002 -185.543 -0.57
379.17 72505.6 -509.481 795.594 -0.57
329.29 61810.93 -439.316 -2232.166 -0.57
19.06 54507.93 -17.79 267.226 -0.57
942.38 75346.58 -1272.347 -968.856 -0.57
245.94 61769.58 -326.107 262.316 -0.57
20.87 71137.81 -18.611 484.863 -0.57
1295.08 74400.18 -1749.735 1311.372 -0.57
258.2 67312.89 -340.789 -105.977 -0.57
-876.2 68908.72 1202.534 -1510.721 -0.57
473.13 54865.68 -628.839 -1348.259 -0.57
-1231.9 58546.76 1687.855 -22.49 -0.57
61.05 32570.92 -157.843 -250.296 -0.776
-98.52 42182.34 286.007 -1030.118 -0.776
632.37 44255.49 -845.085 -1306.436 -0.57
81.48 61996.06 -95.36 -289.943 -0.57
-1034.79 53983.52 1422.022 -907.71 -0.57
-116.43 6424.37 81.78 37.197 -0.178
ZAPATA COMBINADA RECTANGULAR
ACI 318S-08
Cimentación
Columna Izquierda Columna Derecha hf = 1.50 m
Pd = 75000 Kg Pd = 125000 Kg S/C = 500 Kg/m2
Pl = 35000 Kg Pl = 50000 Kg hc = 0.10 m
t1 = 0.50 m t1 = 0.65 m ϒm = 2100 Kg/m3
t2 = 0.50 m t2 = 0.65 m σt = 2.00 Kg/cm2
f'c = 210 Kg/cm2 f'c = 210 Kg/cm2 f'c = 175 Kg/cm2
fy = 4200 Kg/cm2
l1 = 5.00 m
σn = 1.61 Kg/cm2
𝐴_𝑧𝑎𝑝=𝑃_
2° Area de la Zapata 𝑇/𝜎_𝑛
Pt = 285000 Kg
Azap = 177019 cm2
Xo = 3.67 m
Lz = 7.34 m 7.35 m
lv = 1.20 m
b = 240.842 cm 240 cm
𝑊_𝑁𝑈=(𝑃_1𝑈+𝑃_ 𝑊_𝑛𝑢=𝑊_𝑁𝑈/𝑏
3° Reacción Neta del Terreno
2𝑈)/𝑙𝑧
● Por Unidad de Longitud ● Por Unidad de Area
𝑉_𝑧=−𝑃_1𝑈+𝑊_𝑁𝑈∙𝑋_𝑂=0 Xo = 2.854 m
Mmáx = -171841 Kg-m
𝑀_𝑚á𝑥=𝑊_𝑁𝑈∙(𝑋_𝑂^2)/2−𝑃_1𝑈∙(
𝑋_𝑂−𝑡_1/2) d = 74.46 cm
hz = 82 cm hz = 85 cm
𝑀_𝑈=∅∙𝜌∙𝑏∙𝑑^2∙𝑓𝑦∙(1−0.59∙𝜌∙𝑓𝑦/(𝑓^′ 𝑐))
4° Verificaciónes
Vn < Vc ……….(Conforme)
● Por Punzonamiento φ = 0.75
𝑉_𝑈1=𝑃_1𝑈−𝑊_𝑛𝑢∙(𝑡_1+𝑑/2)∙(𝑡_2+𝑑) Λ 𝑉_𝑈2=𝑃_𝑈2−𝑊_𝑛𝑢∙(𝑡_1+𝑑)∙(𝑡_2+𝑑)
0.27∙(2+4/𝛽)∙√(𝑓^′ 𝑐)∙𝑏_𝑜∙𝑑
0.27∙((𝛼_𝑠∙𝑑)/𝑏_𝑜 +2)∙√(𝑓^′
𝑉_𝐶≤ 𝑐)∙𝑏_𝑜∙𝑑
1.06∙√(𝑓^′
𝑐)∙𝑏_𝑜∙𝑑
a) Columna Exterior
Vu = 128989.6 Kg Vn = 171986 Kg
Vc1 = 404935.2 Kg
Vc2 = 799156.5 Kg Vc = 264957.6 Kg
Vc3 = 264957.6 Kg
Vn < Vc ……….(Conforme)
b) Columna Interior
Vu = 185997.8 Kg Vn = 247997 Kg
Vc1 = 404935.2 Kg
Vc2 = 1020549 Kg Vc = 264957.6 Kg
Vc3 = 264957.6 Kg
Vn < Vc ……….(Conforme)
5° Diseño por Flexión φ = 0.9
𝜌=(100∙∅∙𝑓^′ 𝑐∙𝑓𝑦−√((100∙∅∙𝑓^′ 𝑐∙𝑓𝑦)^2−23600∙∅∙𝑅_𝑈∙𝑓´𝑐∙ 〖𝑓𝑦〗 ^2 ))/
𝑅_𝑈=𝑀_𝑈/ (118∙∅∙ 〖𝑓𝑦〗 ^2 )
(𝑏∙𝑑^2 )
b1 = 89.37 cm 92 cm
b2 = 143.73 cm 150 cm
𝑀_𝑈=(𝑞_𝑁𝑈∙((𝑏−𝑡_2)
𝑞_𝑁𝑈=𝑃_𝑈 /2)^2)/2
/𝑏
● Zapata Exterior
● Zapata Interior
qNU = 95833 Kg/m Diámetro de Varilla φ1/2"
Mu = 36686 Kg-m Av = 1.27 cm2
Ru = 3.95 Kg/cm2 # var = 16.74 18 Varillas
ρ = 0.00106 Esp. S = 7.9 cm
ρmin = 0.0018
As = 21.26 cm2 Usar 18 φ 1/2" @ 7.9 cm
Coeficientes φ para Diseño Varilla Diámetro Area
Factores φ NTE E.060 ACI 318S-08 3/8" 0.9525 0.71 3
Tensión 0.90 0.90 1/2" 1.27 1.27 4
Compresión 0.70 0.65 5/8" 1.5875 1.98 5
Cortante 0.85 0.75 3/4" 1.905 2.85 6
1" 2.54 5.07 8
Combinaciones para Carga Estática 1 3/8" 3.4925 9.58 11
Coeficientes NTE E.060 ACI 318S-08
Carga Muerta 1.50 1.20
Carga Viva 1.80 1.60
Longitudes de Desarrollo
Factores Ψ
Ψt
Ψe
Ψs
λ
Descripción Valor
Varillas Superiores 1.30
Otras Varillas 1.00
Varillas o alambres con recubrimiento Expóxico con menos de
1.50
3db de recubrimiento o separación libre menor de 6db
Todas la Otras Varillas o Alambre con Recubrimiento Epóxico 1.20
Refuerzo sin Recubrimiento y con recubrimiento con zinc 1.00
Varillas o alambres menores o iguales a la #6 0.80
Varillas mayores o iguales a la #7 1.00
Concreto de Peso Liviano 0.75
𝑓_𝑐𝑡/(1.78∙√(𝑓^′
Cuando se especifica fct 𝑐))≤1.0