Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Mayores Trabajos N 01 Imprimir
Mayores Trabajos N 01 Imprimir
ENERO 2019
OBRA
: “CREACION E IMPLEMENTACION DEL CAMAL MUNICIPAL DEL DISTRITO ESPINAR, PROVINCIA DE ESPINAR - CUSCO"
PRESUPUESTO BASE S/. 19,946,071.66 (INCL. IGV) ADELANTO DIRECTO ( INCL. IGV ) S/. - 0.00%
PRESUPUESTO CONTRATADO S/. 19,933,413.12 (INCL. IGV) ADELANTO POR MATERIALES ( INCL. IGV ) S/. - 0.00%
FACTOR DE RELACION: 0.99936536175
1.00 VALORIZACION
Componente 01 : ADECUADA INFRAESTRUCTURA PARA BENEFICO Y MANEJO DEL CAMAL 1,035,625.49 1,027,161.05 8,464.44 1,035,625.49 0.00
Componente 02 : ADECUADO EQUIPAMIENTO Y MAQUINARIA PARA EL BENEFICIO DEL CAMAL 141,827.59 139,512.30 2,315.29 141,827.59 0.00
Componente 03 : ADECUADA CAPACITACION EN EL MANEJO DEL EQUIPO E INFRAESTRUCTURA 1,080,942.36 1,056,599.16 24,343.20 1,080,942.36 0.00
DEL CAMAL
4.00 AMORTIZACIONES
OTORGADO
Amortizacion de Adelanto Directo 0.00 0.00 0.00 0.00 0.00
Amortizacion de Adelanto por Materiales 0.00 0.00 0.00 0.00 0.00
TOTAL ADELANTOS 0.00 0.00 0.00 0.00 0.00
OBRA : “CREACION E IMPLEMENTACION DEL CAMAL MUNICIPAL DEL DISTRITO ESPINAR, PROVINCIA DE ESPINAR - CUSCO"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE ESPINAR
EMPRESA PRIVADA : COMPAÑÍA MINERA ANTAPACCAY SA
CONTRATISTA : CONSORCIO EDUCATIVO ESPINAR
RESIDENTE : ING. CESAR YABAR VELAZCO
SUPERVISOR : BISONTE INGENIEROS CONTRATISTAS
JEFE DE SUPERVISION : ING. JUAN ROGER QUINTANILLA ANYAIPOMA
1.01 Componente 01 : RELLENO CON MATERIAL DE PRESTAMO S/. 1,035,625.49 S/. 1,027,161.05 S/. 8,464.44 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,035,625.49
1.02 Componente 02 : MURO DE CONTENCION DE CERCO PERIMETRICO S/. 141,827.59 S/. 139,512.30 S/. 2,315.29 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 141,827.59
1.03 Componente 03 : PAVIMENTO DE CONCRETO F´C=245KG/CM2 S/. 1,080,942.36 S/. 1,056,599.16 S/. 24,343.20 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 1,080,942.36
4.00 VALORIZACION BRUTA (VB = V+R-D) S/. 2,258,395.44 S/. 2,223,272.51 S/. 8,464.44 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 2,258,395.44
6.00 VALORIZACION NETA (VN = VB-A-D) S/. 2,258,395.44 S/. 2,223,272.51 S/. 8,464.44 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 2,258,395.44
I.G.V. (18%) S/. 406,511.18 S/. 400,189.05 S/. 1,523.60 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 406,511.18
MONTO TOTAL A FACTURAR S/. 2,663,215.37 S/. 2,621,796.61 S/. 9,981.71 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 2,663,215.37
RESUMEN DE VALORIZACIÓN DE MAYORES TRABAJOS 01
ENERO 2019
OBRA : “CREACION E IMPLEMENTACION DEL CAMAL MUNICIPAL DEL DISTRITO ESPINAR, PROVINCIA DE ESPINAR - CUSCO"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE ESPINAR
RESIDENTE : ING. CESAR YABAR VELAZCO
SUPERVISOR : BISONTE INGENIEROS CONTRATISTAS
JEFE DE SUPERVISION: ING. JUAN ROGER QUINTANILLA ANYAIPOMA
PRESUPUESTO BASE ACUMULADO ANTERIOR VALORIZACIÓN DEL MES ACUMULADO ACTUAL SALDO POR VALORIZAR
ITEMS DESCRIPCION
MONTO % MONTO % MONTO % MONTO % MONTO %
02.00 RELLENO EN EXTERIORES 17.34% 100.00% 0.00 0.00% 347,229.07 100.00% 0.00 0.00%
347,229.07 347,229.07
03.00 VARIOS 16,779.20 0.84% 16,625.20 99.08% 154.00 0.92% 16,779.20 100.00% 0.00 0.00%
01.00 CORTE EN TERRENO CON MAQUINARIA 1009.35 0.05% 1009.3512 100.00% 0.00 0.00% 1,009.35 100.00% 0.00 0.00%
02.00 PERFILADO Y NIVELACION INTERIOR 976.42 0.05% 976.4238 100.00% 0.00 0.00% 976.42 100.00% 0.00 0.00%
03.00 ACARREO Y ELIMINACION DE MAT. EXCEDENTE DP=30 mts 1931.65 0.10% 1931.6502 100.00% 0.00 0.00% 1,931.65 100.00% 0.00 0.00%
04.00 ELIMINACION DE MATERIAL EXCEDENTE 2633.19 0.13% 2633.1879 100.00% 0.00 0.00% 2,633.19 100.00% 0.00 0.00%
05.00 RELLENO PROTECTOR EN EXTERIOR 7447.51 0.37% 5541.3 74.40% 1,906.21 25.60% 7,447.51 100.00% 0.00 0.00%
06.00 SOLADO PARA ZAPATA 1760.35 0.09% 1760.3529 100.00% 0.00 0.00% 1,760.35 100.00% 0.00 0.00%
07.00 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 42696.38 2.13% 42696.3812 100.00% 0.00 0.00% 42,696.38 100.00% 0.00 0.00%
08.00 CONCRETO PARA F´C=210KG/CM2 PARA MUROS DE CONTENCION 35025.07 1.75% 35025.0668 100.00% 0.00 0.00% 35,025.07 100.00% 0.00 0.00%
09.00 ENCOFRADO Y DESENCOFRADO DE MUROS DE CONTENCION 31038.28 1.55% 31038.283 100.00% 0.00 0.00% 31,038.28 100.00% 0.00 0.00%
10.00 CURADO DE CONCRETO 916.94 0.05% 916.943 100.00% 0.00 0.00% 916.94 100.00% 0.00 0.00%
11.00 PRUEBAS DE CONTROL DE CALIDAD DEL CONCRETO 330.48 0.02% 183.6 55.56% 146.88 44.44% 330.48 100.00% 0.00 0.00%
01.00 TRABAJOS PRELIMINARES Y OBRAS PROVISIONALES 44,163.75 2.21% 44,163.75 100.00% 0.00 0.00% 44,163.75 100.00% 0.00 0.00%
02.00 MOVIMIENTO DE TIERRAS 200,830.90 10.03% 200,830.90 100.00% 0.00 0.00% 200,830.90 100.00% 0.00 0.00%
03.00 PAVIMENTO REFORZADO 712,704.82 35.59% 691,944.70 97.09% 20,760.13 2.91% 712,704.83 100.00% 0.00 0.00%
04.00 PRUEBAS DE CALIDAD 826.20 0.04% 0.00 0.00% 826.20 100.00% 826.20 100.00% 0.00 0.00%
COSTO DIRECTO 2,002,632.22 100.00% S/. 1,971,486.96 98.44% S/. 31,145.26 1.56% S/. 2,002,632.22 100.00% S/. - 0.00%
FR 0.9994
TOTAL S/. 2,663,215.37 S/. 2,621,796.62 S/. 41,418.75 S/. 2,663,215.37 S/. -
VALORIZACIÓN DE OBRA Nº 01 - MAYORES TRABAJOS 01
ENERO 2019
OBRA : “CREACION E IMPLEMENTACION DEL CAMAL MUNICIPAL DEL DISTRITO ESPINAR, PROVINCIA DE ESPINAR - CUSCO"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE ESPINAR
RESIDENTE : ING. CESAR YABAR VELAZCO
SUPERVISOR : BISONTE INGENIEROS CONTRATISTAS
JEFE DE SUP : ING. JUAN ROGER QUINTANILLA ANYAIPOMA
MAYORES TRABAJOS 01
01.01 ESTRUCTURAS
01.01.01.01 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m3 4,098.27 90.41 370,524.59 4,098.27 370,524.59 100.00% - - 0.00% 4,098.27 370,524.59 100.00% - - 0.00%
01.01.01.02 ACARREO DE MATERIAL A AMBIENTES INTERIORES m3 5,327.77 20.57 109,592.23 5,327.77 109,592.23 100.00% - - 0.00% 5,327.77 109,592.23 100.00% - - 0.00%
01.01.01.03 ELIMINACION DE MATERIAL LIMO ARENOSO, NO APTO PARA RELLENOS m3 5,327.77 13.93 74,215.84 4,800.00 66,864.00 90.09% 527.77 7,351.84 9.91% 5,327.77 74,215.84 100.00% - - 0.00%
01.01.02.01.01 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO EXTERIOR m3 4,029.50 84.57 340,774.82 4,029.50 340,774.82 100.00% - - 0.00% 4,029.50 340,774.82 100.00% - - 0.00%
01.01.02.01.02 NIVELACION Y COMPACTADO C/EQUIPO m2 267.42 6.26 1,674.05 267.42 1,674.05 100.00% - - 0.00% 267.42 1,674.05 100.00% - - 0.00%
01.01.02.01.03 TRANSPORTE DE MATERIAL A ZONAS PERIMETRALES m3 334.28 14.30 4,780.20 334.28 4,780.20 100.00% - - 0.00% 334.28 4,780.20 100.00% - - 0.00%
01.01.02.02.01 MOVILIZACION Y DESMOVILIZACION DE RODILLO LISO VIBR AUTOP 70-100 HP 7-9 TN vje 1.00 7,966.10 7,966.10 1.00 7,966.10 100.00% - - 0.00% 1.00 7,966.10 100.00% - - 0.00%
01.01.02.02.02 MOVILIZACION Y DESMOVILIZACION DE MOTONIVELADORA 130 - 135 HP vje 1.00 7,966.10 7,966.10 1.00 7,966.10 100.00% - - 0.00% 1.00 7,966.10 100.00% - - 0.00%
01.01.02.02.03 PRUEBAS DE COMPACTACION EN RELLENOS EXTERIORES und 22.00 38.50 847.00 18.00 693.00 81.82% 4.00 154.00 18.18% 22.00 847.00 100.00% - - 0.00%
0.00
COSTO DIRECTO 918,340.93 910,835.09 7,505.84 918,340.93 0.00
GASTOS GENERALES (10.00%) 91,834.09 91,083.51 750.58 91,834.09 0.00
UTILIDAD (2.77%) 25,450.47 25,242.45 208.01 25,450.47 0.00
SUBTOTAL 1,035,625.49 1,027,161.05 8,464.44 1,035,625.49 0.00
IMPUESTO I.G.V. (18.00%) 186,412.59 184,888.99 1,523.60 186,412.59 0.00
COSTO EJECUCION DE LA OBRA 1,222,038.08 1,212,050.04 9,988.04 1,222,038.08 0.00
COSTO CON FR=0.999365361750637 1,221,262.53 1,211,280.83 9,981.70 1,221,262.53 0.00
% DE EJECUCIÓN CONTRACTUAL 99.18% 0.82% 100.00% 0.00%
VALORIZACIÓN DE OBRA Nº 01 - MAYORES TRABAJOS 01
ENERO 2019
OBRA : “CREACION E IMPLEMENTACION DEL CAMAL MUNICIPAL DEL DISTRITO ESPINAR, PROVINCIA DE ESPINAR - CUSCO"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE ESPINAR
RESIDENTE : ING. CESAR YABAR VELAZCO
SUPERVISOR : BISONTE INGENIEROS CONTRATISTAS
JEFE DE SUP : ING. JUAN ROGER QUINTANILLA ANYAIPOMA
MAYORES TRABAJOS 01
02.01 CORTE EN TERRENO CON MAQUINARIA m3 97.24 10.38 1,009.35 97.24 1,009.35 100.00% - - 0.00% 97.24 1,009.35 100.00% - - 0.00%
02.02 PERFILADO Y NIVELACION INTERIOR m2 96.58 10.11 976.42 96.58 976.42 100.00% - - 0.00% 96.58 976.42 100.00% - - 0.00%
02.03 ACARREO Y ELIMINACION DE MAT. EXCEDENTE DP=30 mts m3 76.38 25.29 1,931.65 76.38 1,931.65 100.00% - - 0.00% 76.38 1,931.65 100.00% - - 0.00%
02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 189.03 13.93 2,633.19 189.03 2,633.19 100.00% - - 0.00% 189.03 2,633.19 100.00% - - 0.00%
02.05 RELLENO PROTECTOR EN EXTERIOR m3 120.96 61.57 7,447.51 90.00 5,541.30 74.40% 30.96 1,906.21 25.60% 120.96 7,447.51 100.00% - - 0.00%
02.06 SOLADO PARA ZAPATA m2 75.91 23.19 1,760.35 75.91 1,760.35 100.00% - - 0.00% 75.91 1,760.35 100.00% - - 0.00%
02.07 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 8,438.02 5.06 42,696.38 8,438.02 42,696.38 100.00% - - 0.00% 8,438.02 42,696.38 100.00% - - 0.00%
02.08 CONCRETO PARA F´C=210KG/CM2 PARA MUROS DE CONTENCION m3 83.78 418.06 35,025.07 83.78 35,025.07 100.00% - - 0.00% 83.78 35,025.07 100.00% - - 0.00%
02.09 ENCOFRADO Y DESENCOFRADO DE MUROS DE CONTENCION m2 475.10 65.33 31,038.28 475.10 31,038.28 100.00% - - 0.00% 475.10 31,038.28 100.00% - - 0.00%
02.10 CURADO DE CONCRETO m2 475.10 1.93 916.94 475.10 916.94 100.00% - - 0.00% 475.10 916.94 100.00% - - 0.00%
02.11 VARIOS -
02.11.01 PRUEBAS DE CONTROL DE CALIDAD DEL CONCRETO und 18.00 18.36 330.48 10.00 183.60 55.56% 8.00 146.88 44.44% 18.00 330.48 100.00% - - 0.00%
0.00
COSTO DIRECTO 125,765.62 123,712.54 2,053.08 125,765.62 0.00
GASTOS GENERALES (10.00%) 12,576.56 12,371.25 205.31 12,576.56 0.00
UTILIDAD (2.77%) 3,485.41 3,428.51 56.90 3,485.41 0.00
SUBTOTAL 141,827.59 139,512.30 2,315.29 141,827.59 0.00
IMPUESTO I.G.V. (18.00%) 25,528.97 25,112.21 416.76 25,528.96 0.00
COSTO EJECUCION DE LA OBRA 167,356.56 164,624.51 2,732.05 167,356.55 0.00
COSTO CON FR=0.999365361750637 167,250.35 164,520.04 2,730.32 167,250.35 0.00
% DE EJECUCIÓN CONTRACTUAL 98.37% 1.63% 100.00% 0.00%
VALORIZACIÓN DE OBRA Nº 01 - MAYORES TRABAJOS 01
ENERO 2019
OBRA : “CREACION E IMPLEMENTACION DEL CAMAL MUNICIPAL DEL DISTRITO ESPINAR, PROVINCIA DE ESPINAR - CUSCO"
ENTIDA: MUNICIPALIDAD PROVINCIAL DE ESPINAR
RESIDE : ING. CESAR YABAR VELAZCO
SUPERV: BISONTE INGENIEROS CONTRATISTAS
JEFE DE: ING. JUAN ROGER QUINTANILLA ANYAIPOMA
MAYORES TRABAJOS 01
03.01.02 TRAZO NIVELES Y REPLANTEO m2 4,159.95 3.23 13,436.64 4,159.95 13,436.64 100.00% - - 0.00% 4,159.95 13,436.64 100.00% - - 0.00%
03.01.03 TRAZO, NIVELES, REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO mes 1.00 4,831.63 4,831.63 1.00 4,831.63 100.00% - - 0.00% 1.00 4,831.63 100.00% - - 0.00%
03.01.04 RIEGO Y ABASTECIMIENTO DE AGUA CON CISTERNA m2 4,159.95 4.31 17,929.38 4,159.95 17,929.38 100.00% - - 0.00% 4,159.95 17,929.38 100.00% - - 0.00%
03.02.01 CORTE EN TERRENO CON MAQUINARIA m3 1,985.80 10.38 20,612.60 1,985.80 20,612.60 100.00% - - 0.00% 1,985.80 20,612.60 100.00% - - 0.00%
03.02.02 CONFORMACION DE SUB-BASE GRANULAR E=25CM m3 1,039.99 122.15 127,034.78 1,039.99 127,034.78 100.00% - - 1,039.99 127,034.78 100.00% - - 0.00%
03.02.03 EXCAVACION MANUAL PARA CONFINAMIENTOS LATERALES m3 88.30 50.57 4,465.33 88.30 4,465.33 100.00% - - 0.00% 88.30 4,465.33 100.00% - - 0.00%
03.02.04 PEFILADO DEL TERRENO MANUAL m2 1,103.69 10.11 11,158.31 1,103.69 11,158.31 100.00% - - 0.00% 1,103.69 11,158.31 100.00% - - 0.00%
03.02.05 ELIMINACION DE MATERIAL EXCEDENTE m3 2,696.33 13.93 37,559.88 2,696.33 37,559.88 100.00% - - 0.00% 2,696.33 37,559.88 100.00% - - 0.00%
03.03.01 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 3,349.83 5.06 16,950.14 3,010.25 15,231.87 89.86% 339.58 1,718.27 10.14% 3,349.83 16,950.14 100.00% - - 0.00%
03.03.02 ENCOFRADO Y DESENCOFRADO DE LOSA DE PAVIMENTACION m2 389.02 40.67 15,821.44 389.02 15,821.44 100.00% - - 0.00% 389.02 15,821.44 100.00% - - 0.00%
03.03.03 CONCRETO F´C=245KG/CM2 EN LOSA DE PAVIMENTO RIGIDO m3 1,025.71 443.42 454,820.33 1,025.71 454,820.33 100.00% - - 0.00% 1,025.71 454,820.33 100.00% - - 0.00%
03.03.04 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 PARA MALLA DE TEMPERATUDA 1/4" @2 kg 13,173.18 5.06 66,656.29 13,173.18 66,656.29 100.00% - - 0.00% 13,173.18 66,656.29 100.00% - - 0.00%
03.03.05 CORTE DE LOSAS m 2,597.85 8.44 21,925.85 2,597.85 21,925.85 100.00% - - 0.00% 2,597.85 21,925.85 100.00% - - 0.00%
03.03.06 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO (GRAVA) m3 430.26 123.90 53,309.21 330.00 40,887.00 76.70% 100.26 12,422.21 23.30% 430.26 53,309.21 100.00% - - 0.00%
03.03.07.01 JUNTA DE TIPO A m 61.18 84.52 5,170.93 61.18 5,170.93 100.00% - - 0.00% 61.18 5,170.93 100.00% - - 0.00%
03.03.07.02 JUNTA DE TIPO B m 24.60 76.51 1,882.15 24.60 1,882.15 100.00% - - 0.00% 24.60 1,882.15 100.00% - - 0.00%
03.03.07.03 JUNTA DE TIPO C m 33.63 21.96 738.51 33.63 738.51 100.00% - - 0.00% 33.63 738.51 100.00% - - 0.00%
03.03.07.04 JUNTA DE TIPO D m 2,218.19 21.96 48,711.45 1,980.00 43,480.80 89.26% 238.19 5,230.65 10.74% 2,218.19 48,711.45 100.00% - - 0.00%
03.03.07.05 JUNTA DE TIPO E m 346.03 21.96 7,598.82 346.03 7,598.82 100.00% - - 0.00% 346.03 7,598.82 100.00% - - 0.00%
03.03.07.06 JUNTA DE TIPO F m 137.18 80.85 11,091.00 120.00 9,702.00 87.48% 17.18 1,389.00 12.52% 137.18 11,091.00 100.00% - - 0.00%
03.03.08 CURADO DE CONCRETO m2 4,159.95 1.93 8,028.70 4,159.95 8,028.70 100.00% - - 0.00% 4,159.95 8,028.70 100.00% - - 0.00%
03.03.09.01 PRUEBAS DE CONTROL DE CALIDAD DEL CONCRETO und 45.00 18.36 826.20 - - 0.00% 45.00 826.20 100.00% 45.00 826.20 100.00% - - 0.00%
0.00
COSTO DIRECTO 958,525.67 936,939.34 21,586.33 958,525.67 0.00
GASTOS GENERALES (10.00%) 95,852.57 93,693.93 2,158.63 95,852.57 0.00
UTILIDAD (2.77%) 26,564.13 25,965.89 598.23 26,564.13 0.00
SUBTOTAL 1,080,942.36 1,056,599.16 24,343.19 1,080,942.36 0.00
IMPUESTO I.G.V. (18.00%) 194,569.62 190,187.85 4,381.77 194,569.62 0.00
COSTO EJECUCION DE LA OBRA 1,275,511.98 1,246,787.01 28,724.96 1,275,511.98 0.00
COSTO CON FR=0.999365361750637 1,274,702.50 1,245,995.76 28,706.73 1,274,702.50 0.00
% DE EJECUCIÓN CONTRACTUAL 97.75% 2.25% 100.00% 0.00%
CALCULO DE REAJUSTE
ENERO 2019
OBRA : “CREACION E IMPLEMENTACION DEL CAMAL MUNICIPAL DEL DISTRITO ESPINAR, PROVINCIA DE ESPINAR - CUSCO"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE ESPINAR
EMPRESA PRIVADA : COMPAÑÍA MINERA ANTAPACCAY SA
CONTRATISTA : JERGO SAC
RESIDENTE : ING. CESAR YABAR VELAZCO
SUPERVISOR : BISONTE INGENIEROS CONTRATISTAS
JEFE DE SUPERVISION : ING. JUAN ROGER QUINTANILLA ANYAIPOMA
VALORIZACIÓN AVANCE MENSUAL FACTOR REAJUSTE PROGRAMADO REAJUSTE VALORIZADO REAJUSTE RECONOCIDO
REAJUSTE
Programado Ejecutado Programado Valorizado
Nº Periodo Fecha de reajuste (*) Acumulado Acumulado Del Mes Acumulado
Mensual (A) Acumulado Mensual (B) Acumulado K F = A *(K-1) G = B *(K-1)
1 AL 31 DIC 18 Nov - 2018 1,430,317.11 1,430,317.11 35,122.92 35,122.92 1.021 30,036.66 30,036.66 737.58 737.58 737.58 737.58
2 AL 11 ENE 19 Dic - 2018 828,078.33 2,258,395.44 0.00 35,122.92 1.021 17,389.64 47,426.30 0.00 737.58 - 737.58
Nota: Este mes el monto del reajuste es la suma de los reajustes de las especialidades de estructuras, arquitectura, sanitarias y electricas, equipamiento y charlas de capacitación
con los indices al mes de noviembre, que son los conocidos a la fecha del reajuste
CALCULO DE COEFICIENTE DE REAJUSTE "K"
ENERO 2019
OBRA : “MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I.E TENIENTE CORONEL PEDRO RUIZ GALLO NIVEL SECUNDARIO DEL DISTRITO DE ESPINAR, PROVINCIA DE ESPINAR - CUSCO"
F. POLINOMICA :
K= 0.214*(Mr / Mo) + 0.188*(Mr / Mo) + 0.113*(Ir / Io) + 0.076*(Dr / Do) + 0.309*(AAPr / AAPo) +
MAYORES TRABAJOS 01 0.100*(Cr / Co)
F. P. Nº 01 Indice Pto. Base Ir (Diciembre 2018) Ir (Enero 2019) Ir (Febrero 2019) Ir (Marzo 2019) Ir (Abril 2019) Ir (Mayo 2019) Ir (Junio 2019)
Monomio I.U. SIMBOLO DESCRIPCION ÍNDICE UNIFICADO COEF. % INCID. Oct-17 Io Ir Ir/Io Ir Ir/Io Ir Ir/Io Ir Ir/Io Ir Ir/Io Ir Ir/Io Ir Ir/Io
Kr Kr Kr Kr Kr Kr Kr
1 2 3 4=(3x2) 5 6=(2*5/4) 5 6=(2*5/4) 5 6=(2*5/4) 5 6=(2*5/4) 6 6=(2*5/4) 6 6=(2*5/4) 6 6=(2*5/4)
1 47 M MANO DE OBRA INC. LEYES SOCIALES 0.214 100.00% 580.90 580.90 602.11 1.037 0.222 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
2 49 M MAQUINARIA Y EQUIPO IMPORTADO 0.188 100.00% 293.18 293.18 311.07 1.061 0.199 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
3 39 I INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.113 100.00% 442.48 442.48 451.18 1.020 0.115 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
4 30 D DOLAR (GENERAL PONDERADO) 0.076 100.00% 467.61 467.61 497.53 1.064 0.081 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
5 03 AAP ACERO DE CONSTRUCCION CORRUGADO 13.269% 469.92 469.92 539.69 1.149 0.001 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
5 05 AAP AGREGADO GRUESO 0.309 84.466% 632.37 632.37 628.13 0.993 0.315 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
5 56 AAP PLANCHA DE ACERO LAC 2.265% 488.10 488.10 591.47 1.212 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
6 21 C CEMENTO PORTLAND TIPO I 0.100 100.00% 410.96 410.96 416.28 0.886 0.089 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000 0.00 0.000 0.000
K (Noviembre 18)= 1.021 K (Diciembre 18)= - K (Enero 18)= - K (Febrero 18)= - K (Marzo 18)= - K (Abril 18)= - K (Mayo 18)= -
OBRA : “CREACION E IMPLEMENTACION DEL CAMAL MUNICIPAL DEL DISTRITO ESPINAR, PROVINCIA DE ESPINAR - CUSCO"
Area Geografica :6
MAYORES TRABAJOS 01 K= 0.214*(Mr / Mo) + 0.188*(Mr / Mo) + 0.113*(Ir / Io) + 0.076*(Dr / Do) + 0.309*(AAPr / AAPo) + 0.100*(Cr / Co)
(*) Para el I.U. del Presupuesto base de Mano de obra (Código 47), se consideró segun la Resolucion Jefatural Nº 258-2018-INEI
CURVA "S " - AVANCE DE EJECUCIÓN DE OBRA
ENERO 2019
OBRA : “CREACION E IMPLEMENTACION DEL CAMAL MUNICIPAL DEL DISTRITO ESPINAR, PROVINCIA DE ESPINAR - CUSCO"
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE ESPINAR
EMPRESA PRIVADA : COMPAÑÍA MINERA ANTAPACCAY SA
CONTRATISTA : JERGO SAC
RESIDENTE : ING. CESAR YABAR VELAZCO
SUPERVISOR : BISONTE INGENIEROS CONTRATISTAS
JEFE DE SUPERVISI : ING. JUAN ROGER QUINTANILLA ANYAIPOMA
SEGÚN CALENDARIO AVANCE DE OBRA INICIO MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08
TOTAL
VALORIZADA (SIN IGV) INICIO DIC-18 ENERO-19 FEB-19 MAR-19 ABRIL-19 MAYO-19 JUNIO-19 JULIO-19
100.00%
% DE AVANCE OBRA
98.44%
100.00%
90.00%
80.00%
70.00%
63.33%
% Avance Programado
60.00% Acumulado
% Avance Ejecutado
50.00% Acumulado
40.00%
30.00%
20.00%
10.00%
0.00%
0.00%
0.00%
INICIO DIC-18 ENERO-19 FEB-19 MAR-19 ABRIL-19 MAYO-19 JUNIO-19 JULIO-19
Municipalidad Provincial de Espinar
Gerencia de Infraestructura Publica y Desarrollo Territorial
FORMATO - 05
EN EL PRESENTE MES DE MARZO SE TRABAJO EN EL VACIADO DE ELEMENTOS DE CONRETO ARMADO, COMO SON
COLUMNAS, VIGAS Y LOSAS ALIGERADAS, EN SU MAYORIA EN SEGUNDO NIVEL. TAMBIEN SE REALIZARON TRABAJOS DE
ARQUITECTURA COMO SON TARRAJEOS INTERIORES, COBERTURA CON TEJA ANDINA Y ACTIVIDADES COMO RELLENO Y
COMPACTADO EN BLOQUES TODOS LOS BLOQUES. ASIMISMO SE CONTINUARON CON LOS VACIADOS DE MUROS DE
CONTENCION Y MUROS EN CERCO PERIMETRICO.
Recomendaciones:
100.00%
80.00%
60.00%
Axis Title
40.00%
20.00%
0.00%
E E E E L E E E
TO BR BR BR BR ER
O
ER
O ZO RI AY
O
NI
O LIO TO BR BR BR
OS TU EN BR AR AB JU JU OS TU
AG IEM IEM IEM M M
AG IEM IEM
PT OC V IC FE P T OC V
SE NO D SE NO
AVANCE FINANCIERO PROGRAMADO Vs. AVANCE FINANCIERO EJECUTADO
(MARZO DEL 2018)
120.00%
100.00%
80.00%
60.00%
% AVANCE
40.00%
20.00%
0.00%
E E E E L E E E
TO BR BR BR BR ER
O
ER
O ZO RI AY
O
NI
O LIO TO BR BR BR
OS TU EN BR AR AB JU JU OS TU
AG TIEM C VIEM
C IEM
FE M M
AG TIEM C VIEM
P O DI P O
SE NO SE NO
Nota: El presente formato tiene carácter de Declaración Jurada (Ley 27444 - Ley del Procedimiento Administrativo).
FICHA DE OBRA FORMATO - 03
ANTECEDENTES:
NOMBRE DE LA OBRA MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS EN LA I. E. TENIENTE CORONEL PEDRO RUIZ GALLO DEL DISTRITO Y PROVINCIA DE ESPINAR, CUSCO
NOMBRE DE LA OBRA
MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS EN LA I. E. TENIENTE CORONEL PEDRO RUIZ GALLO DEL DISTRITO Y PROVINCIA DE ESPINAR, CUSCO
AVANCE:
BLOQUE I - FOTOS DE OBRA
CARPETA FOTOS CARPETA FOTOS
FOTO INICIO FOTO ACTUAL CARPETA FOTOS ADJUNTA UBICACIÓN GEOGRAFICA
ADJUNTA ADJUNTA
PROGRAMADO REAL
AVANCE FISICO OBRA
ACUMULADO - CON 15.73% 15.34%
IGV (%)
PROGRAMADO REAL
AVANCE VALORIZADO
OBRA ACUMULADO - S/. 3,973,633.24 S/. 3,874,011.21
CON IGV (S/.)
PROBLEMAS
PRESENTADOS
DURANTE EL PERIODO Al reporte del presente mes, no se tienen limitaciones en la obra.
RECOMENDACIONES:
ADJUNTAR DOCUMENTOS:
ADJUNTAR IMÁGENES: ARCHIVOS EN (*.DOC; *.DOCX; *.XLS; *.XLSX; *.PDF; *.PPT; *.PPTX)
NOTA: LA INFORMACION REGISTRADA DEBE SER ENTREGADA EN DIGITAL (EXCEL - WORD "para formatos"; FOTOS "*.jpg" - "*.gif") Y FISICO (INFORME N° __)