Está en la página 1de 20

Actual 01-06-2020

ARMADURA [KG] (01-06-2020)

CUBICACIÓN
ELEMENTO
TOTAL [KG]

SALA 5 153,037
SALA 2/6 135,600
SALA 1A 22,539
SIST. PRODUCTOS QUIMICOS 33,550
H
I CLARIFICADOR 448,432
T CENTRIFUGA LODOS 24,300
O ESTANQUE DE LODOS 15,331
PISCINA AGUAS FRESCAS 285,000
1
FILTROS TGV 539,367
RED CONTRA INCENDIO 16,519
FUNDACION PB-07 19,740
TOTAL 1,693,415
EVAPORADORES 1,364,402
SALA 7 403,342
TORRES DE ENFRIAMIENTO 985,054
R TURBO GENERADOR 174,386
E PIPE RACK PB-01 192,433
S
T TIE IN LINEAS DE AGUA 11,137
O CLARIFICADOR 386,884
FILTROS TGV 454,620
TOTAL 3,972,259
TOTAL HITO + RESTO 5,665,673

REVISAR LO VERDE CON EL NU


ARMADURA [KG] (01-06-2020)
ACERO ACERO % TOTAL DE en sector clarificadores y tg
LLEGADO A LA ACERO EN PISO
FALTANTE EN INSTALADO ACERO 100% del total de horm
FECHA [KG] [KG]
OBRA [KG] [KG] INSTALADO
150,845 2,192 83,315 67,530 54%
121,607 13,993 42,998 78,609 32%
22,539 - 14,100 8,439 63%
31,566 1,984 - 31,566 0% FACTOR
447,420 1,012 262,349 185,071 59% 54%
22,842 1,458 7,573 15,269 31% FIERRO
15,331 - - 15,331 0% 835,436
285,000 - 228,000 57,000 80% 448,552
529,032 10,335 259,444 269,588 48% 54
- 16,519 - - 0% 835,436
9,823 9,917 7,983 1,840 40% 386,884
1,636,005 57,410 905,762 730,243 53%
1,284,665 79,737 1,161,542 123,123 85%
331,476 71,866 - 331,476 0% CUBIC TOTAL
979,810 5,244 359,927 619,883 37% 835,436
174,386 - 103,922 70,464 60% 448,552
158,824 33,609 150,729 8,095 78% 386,884
11,137 - 1,250 9,887 11%
338,951 47,933 226,281 112,670 58% 46%
446,296 8,324 218,679 227,617 48% 46
3,725,545 246,714 2,222,330 1,503,215 56%
5,361,550 304,124 3,128,092 2,233,458 55%

REVISAR LO VERDE CON EL NUEVO CONSOLIDADO QUE LLEGÓ


sector clarificadores y tgv se realizó una regla para determinar la enfierradura, se sabe que en clarificadores, para el HITO 1, se debe tene
100% del total de hormigones destinado a clarificadores. por lo tanto se dijo.. en clarificadores para un total de 3.563 se necesita 835.43
ponderó con el hormigón necesario para completar el HITO 1 en hormigones. lo mismo se h

Clarificador TGV
HORMIGON FIERRO HORMIGON
3563 993,987 3894
54% HITO 1
1913 539,367 2113

3563 993,987 3894


46% RESTO
1650 454,620 1781

CLARI TGV
LLEGADO A OBRA FALTANTE INSTALADO EN PISO % PONDERADO CUBIC TOTALLLEGADO A O
731,929 103,507 488,630 243,299 58% 993,987 970,410
392,978 55,574 262,349 130,629 58% 539,367 526,573
338,951 47,933 226,281 112,670 58% 454,620 443,837

392,978 -
338,951 -
-

970410 975328
4918 2459
dores, para el HITO 1, se debe tener 3.563 metros cubicos de hormigon, esto corresponde a un
n total de 3.563 se necesita 835.436 kg de enfierradura. Ante esos dos datos anteriores se
TO 1 en hormigones. lo mismo se hizo en TGV.

TGV

54%

46%

TGV
FALTANTE INSTALADO EN PISO % PONDERADO
23,577 478,123 492,287 48%
12,794 259,444 267,130 48%
10,783 218,679 225,157 48%
HORMIGÓN 28-05-2020
G-35 03-06-2020

ULTIMOS HORMIGONES TRASPASADOS ELEMENTO TOTAL A LA FECHA


1/2 muro 2do piso SALA 5 1,366 965
1/2 muros primer piso(sala 2) SALA 2/6 1,385 748
2/2 muros 2do piso SALA 1A 251 207
DOSIFICADOR 310 0
H
solo fundaciones I CLARIFICADOR 1,913 497
solo fundaciones T CENTRIFUGA LODOS 228 67
O ESTANQUE DE LODOS 143 0
1/2 m7, 1/2 m5, m1p
1 PISCINA AGUAS FRESCAS 1,302 1,146
muro m1 FILTROS TGV 2,113 1,393
RED CONTRA INCENDIO 219 0
FUNDACION PB-07 111 17
TOTAL 9,341 5,040
EVAPORADORES 9,879 5,495
SALA 7 772 0
basing E3, E4 BASIN 722.B 4,509 989.5
R
E TURBO GENERADOR 3,822 780
S PIPE RACK PB-01 1,757 1,577
T PIPE RACK PB-21 762 762
O
1/2 FUNDACIÓN FILTROS TGV 1781 1140
CLARIFICADOR 1650 994
TOTAL 21,501 9,604
TOTAL HITO + RESTO 30,842 14,644
05-2020 PROYECCIÓN PARA TERMINO HITO 1
6-2020
% 01-06-2020 08-06-2020 15-06-2020 22-06-2020 29-06-2020 06-07-2020
SALDO INSTALADO 07-06-2020 14-06-2020 21-06-2020 28-06-2020 05-07-20200 12-07-2020
401 71% 131.0 54.0 54.0 54.0 54.0 54.0
637 54% 90.0 109.4 109.4 109.4 109.4 109.4
44 82% - 8.8 8.8 8.8 8.8 8.8
310 0% 205.0 21.0 21.0 21.0 21.0 21.0
1,416 26% 262.0 230.8 230.8 230.8 230.8 230.8
161 29% - 32.2 32.2 32.2 32.2 32.2
143 0% 63.0 16.0 16.0 16.0 16.0 16.0
156 88% - 31.2 31.2 31.2 31.2 31.2
720 66% 164.0 111.2 111.2 111.2 111.2 111.2
219 0% - 43.8 43.8 43.8 43.8 43.8
94 15% - 18.8 18.8 18.8 18.8 18.8
4,301 54% 915.0 677.2 677.2 677.2 677.2 677.2
4,384 56% TOTAL: 4.931
772 0%
4,509 22%
3,042 20%
180 90%
- 100%
641 64%
656 60%
12,887 45%
17,188 47%

2,533
total realizado falta
tgv hito 1 2458 972
3,894 tgv normal
2,533
Hormigón Proyectado Semana 45

Area Elemento
1/3 Muro M9
Muro M1
Clarificadores
Muro M2
1/3 Muro M10
1/3 Muro M8
2/3 Muro M8
3/3 Muro M8
2/3 Muro M2
Filtros TGV
3/3 Muro M2
Muro 2/2 M4
Muro M10 A Y M10 B
Muro M11
Sector Bombas Sur Hormigon M19, M18, M18A
1/2 Muro 2do piso
Sala Eléctrica N°5
Losa cielo 2do piso ciclo 1/2
Edificio Centrifuga de Lodos Muros Edificio
Edificio Quimico Fundación
Sector Bocatoma F02
Sala Eléctrica N°2 Muros Edificio
TOTAL
M³ a Instalar
EN SEMANA
45 M3 CORRESPONDIENTE A HITO 1
69 69
71 71
65 65
57 57
37
39
39 39
25
25 25
25 25
19
36 36
39 39
56 56
75 75
63 63
205 205
50
90 90
1,085
SEMANA N° HORMIGÓN DESDE HORMIGÓN HASTA Hormigón Proyectado Hormigón Real
40 4/27/2020 5/3/2020 1,983 1588.5
41 5/4/2020 5/10/2020 1,845 909
42 5/11/2020 5/17/2020 1,707 486
43 5/18/2020 5/24/2020 1,134 532.5
44 5/25/2020 5/31/2020 1,559 1101
45 6/1/2020 6/7/2020 1085 914
46 6/8/2020 6/14/2020 803
47 6/15/2020 6/21/2020 803
48 6/22/2020 6/28/2020 803
49 6/29/2020 7/5/2020 803
50 7/6/2020 7/12/2020 803
51
52
53
54

2,500
M³ de Hormigón

2,000
1,983

1,845
1,707
1588.5
1,500

1,134

1,000
909

532.5
486
500
532.5
486
500

-
43954 43961 43968 43975
43948 43955 43962 43969
40 41 42 43
% Obtenido
80%
49%
28%
47%
71%
84%

1,707
1,559

1,134 1101 1,085

914
803 803 803

532.5
486
803 803 803

532.5
486

43968 43975 43982 43989 43996 44003 440


43962 43969 43976 43983 43990 43997 440
42 43 44 45 46 47 48
803 803 803 803
803 803 803 803

44003 44010 44017 44024


43997 44004 44011 44018
47 48 49 50
,

MOLDAJE PROYECTADO 18-05-2020 // 24-05-2020


CANTIDAD
AREA ELEMENTO CANTIDAD TOTAL PROGRAMA
DA
CLARIFICADOR 1/3 M9 230 115
CLARIFICADOR M1 236 118
CLARIFICADOR M2 218 109
CLARIFICADOR 1/3 M10 189 47
CLARIFICADOR M1A - M1B 318 318
PEDESTALES RETOLAVADO NORTE 76 76
RETROLAVADOR SUR M19,18,18A 311 207
722.1
FILTRO TGV 2/3 M2 111 67
FILTRO TGV M11 102 61
FILTRO TGV 1/3 M8 165 33
78
CENTRIFUGA DE LODOS 78
457
SALA ELECTRICA N°5, MUROS 2DO PISO 457
FUNDACIÓN ETAPA 3 60 60
PISCINA AGUAS FRESCAS 2/2 M5 309 120
722.B
PISCINA AGUAS FRESCAS 2/2 M7 300 116
PISCINA AGUAS FRESCAS M6 439 171
765 MUROS PRIMER PISO 779 779

TOTAL 4378 2933


AREA ELEMENTO CANTIDAD TOTAL

CLARIFICADOR 1/3 M9 230


CLARIFICADOR M1 236
CLARIFICADOR M2 218
CLARIFICADOR 1/3 M10 189
CLARIFICADOR M1A - M1B 318
PEDESTALES RETOLAVADO NORTE 76
722.1
RETROLAVADOR SUR M19,18,18A 311
FILTRO TGV 2/3 M2 111
FILTRO TGV M11 102
FILTRO TGV 1/3 M8 165
SALA ELECTRICA N°5 PISO 2 MUROS
414
CICLO 1 DE 2
MOLDAJE FUNDACIÓN ETAPA 4, SECTOR
60
TORRES DE ENFRIAMIENTO
722.2 PISCINA AGUAS FRESCAS 2/2 M5 309
PISCINA AGUAS FRESCAS 2/2 M7 300
PISCINA AGUAS FRESCAS M6 439
765 SALA ELÉCTRICA N°2, PRIMER PISO 1,092
SALA ELECTRICA N°1A Muros Camara 20
768
BANCO DUCTO SALA ELÉCTRICA N°1A 50
TOTAL 4,639
CANTIDAD
PROGRAMA
DA
230
236
218
189
106
76
311
111
102
165

248

60
155
150
219
364
20
50
3,009

También podría gustarte