Está en la página 1de 2

Id Modo de Nombre de tarea Duración Comienzo Fin tri 2, 2020 tri 3, 2020 tri 4, 2020

tarea feb mar abr may jun jul ago sep oct nov dic
0 Alfaro Cans Downgauge (Project SC41247) 35.7 sem. mar 03 mar '20 vie 06 nov '20
1 Car Approval 10.3 sem. mar 03 mar '20 mié 13 may '20
2 Approved CAR 0 sem. mié 13 may '20 mié 13 may '20 13/05
3 Generate orders to providers 1.4 sem. jue 14 may '20 vie 22 may '20
4 Providers orders generated 0 sem. vie 22 may '20 vie 22 may '20 22/05
5 3-5Kg 4 sem. lun 25 may '20 vie 19 jun '20
6 Minor welding jobs at cooler exit 4 sem. lun 25 may '20 vie 19 jun '20 Inelco
7 Modular conveyor belt at coller exit 4 sem. lun 25 may '20 vie 19 jun '20
8 Modular conveyor belt at coller exit mechanical 4 sem. lun 25 may '20 vie 19 jun '20 Inelco[€2,400.00]
modifications
9 Electrical Conections and programming 4 sem. lun 25 may '20 vie 19 jun '20 Comafer[€355.49]
10 3-5 Kg line modifications finished 0 sem. vie 19 jun '20 vie 19 jun '20 19/06
11 1/2Kg 8 sem. lun 01 jun '20 vie 24 jul '20
12 Cans transit from closer to coolers 8 sem. lun 01 jun '20 vie 24 jul '20
13 Modify inlet conveyor to 1/2Kg coolers 8 sem. lun 01 jun '20 vie 24 jul '20 Inelco[€10,600.00]
14 Electrical Conections and programming 8 sem. lun 01 jun '20 vie 24 jul '20 Comafer
15 Can dosing system 8 sem. lun 01 jun '20 vie 24 jul '20
16 Can dosing system using a cylinder on the 8 sem. lun 01 jun '20 vie 24 jul '20 Inelco[€1,350.00]
1/2Kg can return belt
17 Electrical Conections and programming 8 sem. lun 01 jun '20 vie 24 jul '20 Comafer
18 Double reject at tray pickup twist exit 1/2Kg cans 8 sem. lun 01 jun '20 vie 24 jul '20 Inelco[€800.00]

19 Speed reduction conveyor system 8 sem. lun 01 jun '20 vie 24 jul '20
20 Mechanical modification 8 sem. lun 01 jun '20 vie 24 jul '20 Inelco[€5,780.00]
21 Electrical Conections and programming 8 sem. lun 01 jun '20 vie 24 jul '20 Inelec
22 Cooler Inlet 8 sem. lun 01 jun '20 vie 24 jul '20
23 Entry form according to OF 0124 in the two 1/2 8 sem. lun 01 jun '20 vie 24 jul '20 Inelco[€14,200.00]
Kg coolers
24 Electrical Conections and programming 8 sem. lun 01 jun '20 vie 24 jul '20 Comafer[€339.69]
25 Clouser modifications 0.4 sem. lun 01 jun '20 mar 02 jun '20
26 Closure Maintenance 0.2 sem. lun 01 jun '20 lun 01 jun '20 Ezquerra
27 Rust removed in closure New format parts 0.2 sem. lun 01 jun '20 lun 01 jun '20 Ezquerra[€2,464.48]

28 Install new format 2 días lun 01 jun '20 mar 02 jun '20 Ezquerra
29 0.5 Kg line modiifcation finished 0 sem. vie 24 jul '20 vie 24 jul '20 24/07
30 1Kg 6 sem. lun 06 jul '20 vie 14 ago '20
31 Gap and break rectification in steel guides from 6 sem. lun 06 jul '20 vie 14 ago '20 Inelco
top to clouser
32 Cooler Inlet 6 sem. lun 06 jul '20 vie 14 ago '20
33 Inlet reform in the 1 Kg cooler according to OF 6 sem. lun 06 jul '20 vie 14 ago '20 Inelco[€6,900.00]
0124
34 Electrical Conections and programming 6 sem. lun 06 jul '20 vie 14 ago '20 Comafer[€679.37]

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite

Proyecto: Alfaro Cans Downgau División Tarea inactiva solo duración solo fin Progreso
Fecha: mar 02 jun '20 Hito Hito inactivo Informe de resumen manual Tareas externas Progreso manual

Resumen Resumen inactivo Resumen manual Hito externo

Página 1
Id Modo de Nombre de tarea Duración Comienzo Fin tri 2, 2020 tri 3, 2020 tri 4, 2020
tarea feb mar abr may jun jul ago sep oct nov dic
35 Brake to cushion the fall of the container in a 1 6 sem. lun 06 jul '20 vie 14 ago '20 Inelco[€500.00]
Kg in-line turner
36 Star modification at exit cooler 6 sem. lun 06 jul '20 vie 14 ago '20 Inelco[€650.00]
37 Installation of 2 pneumatic brakes in the fall of 6 sem. lun 06 jul '20 vie 14 ago '20 Inelco[€2,500.00]
the conveyor to cooker, for braking cans

38 Maintenance Closer Bearings 0.2 sem. lun 06 jul '20 lun 06 jul '20
39 Materials 0.2 sem. lun 06 jul '20 lun 06 jul '20 TCM
40 Work Hours 0.2 sem. lun 06 jul '20 lun 06 jul '20 TCM
41 1 Kg Line modification finished 0 sem. vie 14 ago '20 vie 14 ago '20 14/08
42 Mano de obra COMAFER 0 sem. vie 14 ago '20 vie 14 ago '20 14/08

43 Any modifications after production start 44 días lun 17 ago '20 jue 15 oct '20
44 Commisioning 1 sem vie 16 oct '20 jue 22 oct '20 22/10
45 SAT 1 sem vie 23 oct '20 jue 29 oct '20 29/10
46 Post Mortem 1 sem vie 30 oct '20 jue 05 nov '20 05/11
47 Project Closeout 1 día vie 06 nov '20 vie 06 nov '20 06/11

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha límite

Proyecto: Alfaro Cans Downgau División Tarea inactiva solo duración solo fin Progreso
Fecha: mar 02 jun '20 Hito Hito inactivo Informe de resumen manual Tareas externas Progreso manual

Resumen Resumen inactivo Resumen manual Hito externo