Id EDT Nombre de tarea Duración Costo Comienzo Fin 11 abr '16 18 abr '16 25 abr '16 02 may '16 09 may '16 16 may '16 23 may '16 30 may '16 06 jun '16 13 jun '16 20 jun '16 27 jun '16 04 jul '16 11 jul '16 18 jul '16 25 jul '16
X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L
0 0 Proyecto Construcción MI CASA 50.89 días $22,731.00 15/04/16 20/06/16
1 1 Fase Cimientos 4 días $3,808.00 15/04/16 20/04/16
2 1.1 Preparar terreno 1 día $144.00 15/04/16 15/04/16 Julio Rosas;Pablo Samaniego
3 1.2 Hacer la base 3 días $3,664.00 16/04/16 20/04/16 Julio Rosas;Pablo Samaniego;Mario Hinojoza;Ricardo Merino;Cemeto (bulto x 50kg)[50 (bulto x 50kg)];Arena (bulto x 50kg)[150 (bulto x 50kg)]
4 1.3 Fin de la Fase Cimientos 0 días $0.00 20/04/16 20/04/16 20/04
5 2 Fase Estructural 24.67 días $15,135.00 20/04/16 23/05/16
6 2.1 Columnas y vigas 1 sem $3,380.00 20/04/16 27/04/16 Mario Hinojoza;Ricardo Merino;Oscar Paredes;Nicolás Mendoza;Cemeto (bulto x 50kg)[30 (bulto x 50kg)];Arena (bulto x 50kg)[90 (bulto x 50kg)]
7 2.2 Paredes 2 sem. $3,460.00 27/04/16 12/05/16 Oscar Paredes;Nicolás Mendoza;Cemeto (bulto x 50kg)[10 (bulto x 50kg)];Arena (bulto x 50kg)[30 (bulto x 50kg)];Ladrillos (por millar)[5 (millar)]
8 2.3 Piso 2 días $3,548.00 27/04/16 29/04/16 Mario Hinojoza;Ricardo Merino;Oscar Paredes;Loseta (metro2)[100 (m2)];Cemeto (bulto x 50kg)[30 (bulto x 50kg)];Arena (bulto x 50kg)[90 (bulto x 50kg)]
9 2.4 Encofrado Techo 7 días $1,512.00 12/05/16 20/05/16 Julio Rosas;Pablo Samaniego;Mario Hinojoza
10 2.5 Llenado Techo 1 día $3,235.00 20/05/16 23/05/16 Julio Rosas[1.5];Pablo Samaniego[1.5];Mario Hinojoza[1.5];Ricardo Merino[1.5];Oscar Paredes[1.5];Nicolás Mendoza[1.5];Cemeto (bulto x 50kg)[40 (bulto x 50kg)];Arena (bul
11 2.6 Fin de la Fase Estructural 0 días $0.00 23/05/16 23/05/16 23/05
12 3 Fase Mecánica 11.22 días $1,994.00 28/05/16 11/06/16
13 3.1 Plomería 1.3 sem. $1,374.00 28/05/16 07/06/16 Pedro Martínez;Leoncio Haro;Cemeto (bulto x 50kg)[1.5 (bulto x 50kg)];Arena (bulto x 50kg)[4.5 (bulto x 50kg)];Tubería de agua (m)[3
14 3.2 Electricidad 4 días $620.00 07/06/16 11/06/16 Juan Salas;Cable eléctrico (m)[50 (m)]
15 3.3 Fin de la Fase Mecánica 0 días $0.00 11/06/16 11/06/16 11/06
16 4 Fase Acabado Exterior e Interior 6 días $1,794.00 11/06/16 20/06/16
17 4.1 Colocar Puertas 3 días $726.00 11/06/16 15/06/16 Luis Soria;Manuel Peña;Madera (pies2)[40 (p2)]
18 4.2 Colocar Ventanas 4 días $768.00 11/06/16 16/06/16 Luis Soria;Manuel Peña;Madera (pies2)[20 (p2)]
19 4.3 Decoración 3 días $160.00 14/06/16 17/06/16 Rosa Perez;Computador
20 4.4 Fin de la Fase Acabado Ext e Int 1 día $140.00 17/06/16 20/06/16 Asado[$100.00];Transporte[$40.00]
Tarea Resumen Hito inactivo solo duración solo el comienzo Hito externo División crítica
Proyecto: Proyecto Construcció
División Resumen del proyecto Resumen inactivo Informe de resumen manual solo fin Fecha límite Progreso
Fecha: 10/08/20
Hito Tarea inactiva Tarea manual Resumen manual Tareas externas Tareas críticas Progreso manual