PROGRAMACION FISICA - FINANCIERA AMPLIACION DE PLAZO N°04

"MEJORAMIENTO DE LA GESTION DE LOS RESIDUOS SOLIDOS EN EL CENTRO POBLADO DE KITENI, DISTRITO DE ECHARATI - LA CONVENCION - CUSCO"
RESIDENTE: ING. BENJAMIN R. TELLO LUDEÑA
INSPECTOR: ING. WALTHER I. VALDIVIA DUEÑAS

ACUMULADO ACTUALIZADO SALDO ACTUALIZDO


Item Descripción Unid. Cant. Precio Parcial Sub Total SEP OCT NOV DIC ENE FEBR MAR ABR MAY JUN JUL AGO ACUMULADO SALDO
PRESUPUESTO REFORMULADO PRESUPUESTO REFORMLADO
metr val % metr val % metr val % metr val % metr val % metr val % metr val % metr val % metr val % metr val % metr val % metr val % metr val % metr val %
1 ADECUADO EQUIPAMIENTO E IMPLEMENTACION 415494.52
1.1 EQUIPAMIENTO E IMPLEMENTACION 415494.52
1.1.1 COMPRA DE VEHICULO COMPACTADOR glb 1 300000 300000 0.00 0.00 0.00% 1.00 300,000.00 100.00% 1.00 300,000 100% 1.00 300,000.00 100% 0.0 0.00 0.0
115494.5
1.1.2 COMPRA DE VESTUARIO Y HERRAMIENTAS glb 1 115494.52 1.00 115,494.52 100.00% 0.00 0.00 0.00% 1.00 115,494.52 100% 0.0 0.00 0.0
2
2 ADECUADO DISPOSICION TEMPORAL Y FINAL 154800
2.1 ADECUADA DISPOSICION TEMPORAL Y FINAL 154800
2.1.1 COMPRA DE TERRENO glb 1 125000 125000 1 125,000.00 100.00% 0 0.00 0.00% 1.00 125,000.00 100% 0.0 0.00 0.0
2.1.2 COMPRA DE TACHOS und 16 125 2000 16 2,000.00 100.00% 0 0.00 0.00% 16.00 2,000.00 100% 0.0 0.00 0.0
2.1.3 TASACION DE TERRENO und 1 6000 6000 1 6,000.00 100.00% 0 0.00 0.00% 1.00 6,000.00 100% 0.0 0.00 0.0
2.1.4 CONTENEDORES CON TAPA und 4 1100 4400 4 4,400.00 100.00% 0 0.00 0.00% 4.00 4,400.00 100% 0.0 0.00 0.0
2.1.5 COMPRA DE TACHOS DE BASURA PUBLICOS und 10 1200 12000 10 12,000.00 100.00% 0 0.00 0.00% 10.00 12,000.00 100% 0.0 0.00 0.0
2.1.6 DOBLES DE
TACHOS FIBRA DE
GRANDES VIDRIO
CON RUEDA Y TAPA und 20 220 4400 20 4,400.00 100.00% 0 0.00 0.00% 20.00 4,400.00 100% 0.0 0.00 0.0
2.1.7 TACHOS MEDIANOS CON TAPA und 40 25 1000 40 1,000.00 100.00% 0 0.00 0.00% 40.00 1,000.00 100% 0.0 0.00 0.0
3 ADEACUADOS HABITOS DE HIGIENE 582132.72
3.1 ADECUADS HABITOS DE HIGIENEN Y 582132.72
3.1.1 CAPACITACION
SENCIBILIZACION Y CAPACITACION 85442.9
3.1.1.1 CAPACITACION glb 1 3081.9 3081.9 1 3,081.90 100.00% 0 0.00 0.00% 1.00 3,081.90 100% 0.0 0.00 0.0
3.1.1.2 SENCIBILIZACION glb 1 20415 20415 1 20,415.00 100.00% 0 0.00 0.00% 1.00 20,415.00 100% 0.0 0.00 0.0
3.1.1.3 DIFUSION RADIAL Y TELEVISIVA glb 1 33600 33600 1 33,600.00 100.00% 0 0.00 0.00% 1.00 33,600.00 100% 0.0 0.00 0.0
3.1.1.4 INSTALACION DE CARTELES AMBIENTALES und 3 552 1656 3 1,656.00 100.00% 0 0.00 0.00% 3.00 1,656.00 100% 0.0 0.00 0.0
3.1.1.5 MONITOREO DE AGUA Y AIRE und 1 18000 18000 1 18,000.00 100.00% 0 0.00 0.00% 1.00 18,000.00 100% 0.0 0.00 0.0
3.1.1.6 CAPACITACION EN RESIDUOS SOLIDOS und 1 7000 7000 1 7,000.00 100.00% 0 0.00 0.00% 1.00 7,000.00 100% 0.0 0.00 0.0
3.1.1.7 COMPRA DE EQUIPOS DE PERIFONEO und 1 1690 1690 1 1,690.00 100.00% 0 0.00 0.00% 1.00 1,690.00 100% 0.0 0.00 0.0
3.1.2 (AMPLIFICADOR Y BOCINAS)
CIERRE DEL BOTADERO ACTUAL 78720
3.1.2.1 CORTE DE MATERIAL SUELTO M3. 12000 6.56 78720 12000 78,720.00 100.00% 0 0.00 0.00% 12,000.00 78,720.00 100% 0.0 0.00 0.0
3.1.3 PLAN DE GESTION Y MANEJO DE RESIDUOS 158742.4
SOLIDOS DE MOTOCARGAS
3.1.3.1 COMPRA und 1 12000 12000 0 0.00 0.00% 1 12,000.00 100.00% 1 12,000.00 100% 1.00 12,000.00 100% 0.0 0.00 0.0
3.1.3.2 OPERACION Y MANTENIMIENTO und 1 91693.65 91693.65 1 91,693.65 100.00% 0 0.00 0.00% 1.00 91,693.65 100% 0.0 0.00 0%
3.1.4 APERTURA DE TROCHA PARA BOTADERO 64904.97
PROVISIONAL
3.1.4.1 ROCE Y LIMPIEZA ha 2 860.4 1720.8 2 1,720.80 100.00% 0 0.00 0.00% 2.00 1,720.80 100% 0.0 0.00 0.0
3.1.4.2 CORTE DE MATERIAL SUELTO M3. 3000 7.45 22350 3000 22,350.00 100.00% 0 0.00 0.00% 3,000.00 22,350.00 100% 0.0 0.00 0.0
3.1.4.3 RELLENO CON MATERIAL PROPIO M3. 2000 10.46 20920 2000 20,920.00 100.00% 0 0.00 0.00% 2,000.00 20,920.00 100% 0.0 0.00 0.0
3.1.4.4 ELIMINACION DE MATERIAL EXCEDENTE (CON M3. 1474.03 13.51 19914.17 1474.03 19,914.17 100.00% 0 0.00 0.00% 1,474.03 19,914.15 100% 0.0 0.00 0.0
3.1.5 EQUIPO D =DE
APERTURA 1) TRINCHERA PROVISIONAL 139034.21
3.1.5.1 TRAZO Y REPLANTEO PRELIMINAR M2. 525.6 2.92 1534.74 525.6 1,534.75 100.00% 0 0.00 0.00% 525.60 1,534.75 100% 0.0 0.00 0.0
3.1.5.2 ROCE Y LIMPIEZA ha 2 860.4 1720.8 2 1,720.80 100.00% 0 0.00 0.00% 2.00 1,720.80 100% 0.0 0.00 0.0
3.1.5.3 CORTE DE MATERIAL SUELTO M3. 4840.84 6.56 31755.9 4840.84 31,755.91 100.00% 0 0.00 0.00% 4,840.84 31,755.91 100% 0.0 0.00 0.0
3.1.5.4 RELLENO CON MATERIAL PROPIO M3. 2899.22 10.46 30325.84 2899.22 30,325.84 100.00% 0 0.00 0.00% 2,899.22 30,325.84 100% 0.0 0.00 0.0
3.1.5.5 ELIMINACION DE MATERIAL EXCEDENTE (CON M3. 1996.22 13.51 26968.96 1996.22 26,968.93 100.00% 0 0.00 0.00% 1,996.22 26,968.93 100% 0.0 0.00 0.0
EQUIPO D DE
3.1.5.6 SELLADO = 1)TRINCHERA PROVISIONAL CON M2. 1650 28.32 46727.97 1650 46,728.00 100.00% 0 0.00 0.00% 1,650.00 46,728.00 100% 0.0 0.00 0.0
3.1.6 MATERIALDE
LIMPIEZA DEDESHIERVE
PRESTAMODE AREAS LIBRES POR 55288.24
EFECTOS YDE
3.1.6.1 LIMPIEZA PARALIZACION
DESHIERVE DE AREAS LIBRES ha 7 7898.32 55288.24 2 15,796.64 28.57% 5 39,491.60 71.43% 0.3 2408.99 4.357% 2.86 22,565.50 0.41 1.8 14,517.11 26% 7.00 55,288.24 100% 0.0 0.00 0.0
4 ADECUADA INFRAESTRUCTURA 2792331.15
4.1 OBRAS PROVISIONALES 22394.65
4.1.1 ACONDICIONAMIENTO CAMPAMENTO glb 1 8012.07 8012.07 1 8,012.07 100.00% 0 0.00 0.00% 1.00 8,012.07 100% 0.0 0.00 0.0
4.1.2 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPOS glb 1 10000 10000 1 10,000.00 100.00% 0 0.00 0.00% 1.00 10,000.00 100% 0.0 0.00 0.0
4.1.3 CARTEL DE OBRA y PLACA RECORDATORIA und 1 1280 1280 0.6 768.00 60.00% 0.4 512.00 40.00% 0.4 512.00 40% 1.00 1,280.00 100% 0.0 0.00 0.0
4.1.4 LETRINA PROVISIONAL DE OBRA und 1 3102.58 3102.58 1 3,102.58 100.00% 0 0.00 0.00% 1.00 3,102.58 100% 0.0 0.00 0.0
4.2 CONSTRUCCIÓN EN AREAS ADMINISTRATIVAS 266046.34
4.2.1 TRABAJOS PRELIMINARES 163955.21
4.2.1.1 CORTE DE MATERIAL PARA PLATAFORMA m³ 6186.4 10.05 62173.32 6186.4 62,173.32 100.00% 0 0.00 0.00% 6,186.40 62,173.32 100% 0.0 0.00 0.0
4.2.1.2 ELIMINACION DE MATERIAL EXCEDENTE C/MAQ. (5 m³ 7423.68 12.41 92127.87 7423.68 92,127.87 100.00% 0 0.00 0.00% 7,423.68 92,127.87 100% 0.0 0.00 0.0
4.2.1.3 Km.)
TRAZO Y REPLANTEO PRELIMINAR m² 79.25 2.92 231.41 79.25 231.41 100.00% 0 0.00 0.00% 79.25 231.41 100% 0.0 0.00 0.0
4.2.1.4 LIMPIEZA DE TERRENO m² 79.25 0.98 77.67 79.25 77.67 99.99% 0 0.00 0.00% 79.25 77.67 100% 0.0 0.00 0.0
4.2.1.5 DEMOLICION CONSTRUCCION DE ADOBE M3. 159.47 58.6 9344.94 159.47 9,344.94 100.00% 0 0.00 0.00% 159.47 9,344.94 100% 0.0 0.00 0.0
4.2.2 MOVIMIENTO DE TIERRAS 8163.36
4.2.2.1 EXCAVACIONES MASIVAS MANUALES m³ 82.68 97.91 8095.2 82.68 8,095.20 100.00% 0 0.00 0.00% 82.68 8,095.20 100% 0.0 0.00 0.0
4.2.2.2 NIVELACION, APISONADO, REFINE, Y M2. 79.25 0.86 68.16 79.25 68.16 99.99% 0 0.00 0.00% 79.25 68.16 100% 0.0 0.00 0.0
COMPACTADO
4.2.3 CONCRETO SIMPLE 10946.26
4.2.3.1 CIMIENTO CORRIDO C:H, 1.10+30% PIEDRA M3. 12.3 271.01 3333.42 12.3 3,333.42 100.00% 0 0.00 0.00% 12.30 3,333.42 100% 0.0 0.00 0.0
GRANDE
4.2.3.2 COMPACTACION CON EQUIPO LIVIANO m² 79.25 7.14 565.85 79.25 565.85 100.00% 0 0.00 0.00% 79.25 565.85 100% 0.0 0.00 0.0
4.2.3.3 CONCRETO FALSO PISO 1:8 CON PIEDRA MEDIANA M3. 12.78 279.79 3575.72 12.78 3,575.72 100.00% 0 0.00 0.00% 12.78 3,575.72 100% 0.0 0.00 0.0
4.2.3.4 CONCRETO 1:8 PARA SOBRECIMIENTO M3. 3.84 269.76 1035.87 3.84 1,035.88 100.00% 0 0.00 0.00% 3.84 1,035.88 100% 0.0 0.00 0.0
4.2.3.5 ENCOFRADO Y DESENCOFRADO m² 51.25 47.04 2410.8 51.25 2,410.80 100.00% 0 0.00 0.00% 51.25 2,410.80 100% 0.0 0.00 0.0
4.2.3.6 CURADO DE CONCRETO M2. 51.25 0.48 24.6 51.25 24.60 100.00% 0 0.00 0.00% 51.25 24.60 100% 0.0 0.00 0.0
4.2.4 CONCRETO ARMADO 5062.31
4.2.4.1 CONCRETO F'C=175 KG/CM2 m³ 4.14 432.99 1792.58 4.14 1,792.58 100.00% 0 0.00 0.00% 4.14 1,792.58 100% 0.0 0.00 0.0
4.2.4.2 ENCOFRADO Y DESENCOFRADO OBRAS DE ARTE m² 47.52 31.82 1512.09 47.52 1,512.09 100.00% 0 0.00 0.00% 47.52 1,512.09 100% 0.0 0.00 0.0
4.2.4.3 ACERO DE REFUERZO FY=4200 KG/CM2 (3/8'') kg 201.2 6.01 1209.21 201.2 1,209.21 100.00% 0 0.00 0.00% 201.20 1,209.21 100% 0.0 0.00 0.0
4.2.4.4 ACERO DE REFUERZO FY=4200 KG/CM2 (1/4'') kg 89.2 5.9 526.29 89.2 526.28 100.00% 0 0.00 0.00% 89.20 526.28 100% 0.0 0.00 0.0
4.2.4.5 CURADO DE CONCRETO M2. 46.13 0.48 22.14 46.13 22.14 100.01% 0 0.00 0.00% 46.13 22.14 100% 0.0 0.00 0.0
4.2.5 ALBAÑILERIA 4834.29
4.2.5.1 MURO DE BLOQUETAS M2. 87.12 55.49 4834.29 87.12 4,834.29 100.00% 0 0.00 0.00% 87.12 4,834.29 100% 0.0 0.00 0.0
4.2.6 REVOQUES Y ENLUCIDOS 7809.03
4.2.6.1 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:2 m² 174.25 32.28 5624.79 174.25 5,624.79 100.00% 0 0.00 0.00% 174.25 5,624.79 100% 0.0 0.00 0.0
4.2.6.2 REVESTIDO CON CERAMICO COLOR 30X30 m² 38 57.48 2184.24 38 2,184.24 100.00% 0 0.00 0.00% 38.00 2,184.24 100% 0.0 0.00 0.0
4.2.7 PISOS Y PAVIMENTOS 9897.26
4.2.7.1 COMPACTACION CON EQUIPO LIVIANO m² 57.51 7.14 410.62 57.51 410.62 100.00% 0 0.00 0.00% 57.51 410.62 100% 0.0 0.00 0.0
4.2.7.2 VEREDAS DE CONCRETO M2. 46.13 129.09 5954.92 46.13 5,954.92 100.00% 0 0.00 0.00% 46.13 5,954.92 100% 0.0 0.00 0.0
4.2.7.3 ACABADO FROTACHADO DE PISO m² 57.51 33.26 1912.79 57.51 1,912.78 100.00% 0 0.00 0.00% 57.51 1,912.78 100% 0.0 0.00 0.0
4.2.7.4 RELLENO Y COMPACTADO DE PISO m² 57.51 12.22 702.77 57.51 702.77 100.00% 0 0.00 0.00% 57.51 702.77 100% 0.0 0.00 0.0
4.2.7.5 PISO DE CERAMICO COLOR 30X30 m² 16 57.26 916.16 16 916.16 100.00% 0 0.00 0.00% 16.00 916.16 100% 0.0 0.00 0.0
4.2.8 CARPINTERIA, VIDRIOS, CERRAJERIA Y PINTURA 15445.85
4.2.8.1 PUERTA DE MADERA und 8 722.98 5783.84 8 5,783.84 100.00% 0 0.00 0.00% 8.00 5,783.84 100% 0.0 0.00 0.0
4.2.8.2 VENTANA DE MADERA und 6 579.76 3478.56 6 3,478.56 100.00% 0 0.00 0.00% 6.00 3,478.56 100% 0.0 0.00 0.0
4.2.8.3 VIDRIO SEMI DOBLE NACIONAL INCOLORO p² 44.44 6.45 286.64 44.44 286.64 100.00% 0 0.00 0.00% 44.44 286.64 100% 0.0 0.00 0.0
4.2.8.4 PINTURA MUROS EXTERIORES VINILATEX m² 174.25 8.59 1496.81 174.25 1,496.81 100.00% 0 0.00 0.00% 174.25 1,496.81 100% 0.0 0.00 0.0
4.2.8.5 PINTURA MURAL EXTERIORES M2. 22 200 4400 22 4,400.00 100.00% 0 0.00 0.00% 22.00 4,400.00 100% 0.0 0.00 0.0
ACUMULADO ACTUALIZADO SALDO ACTUALIZDO
Item Descripción Unid. Cant. Precio Parcial Sub Total SEP OCT NOV DIC ENE FEBR MAR ABR MAY JUN JUL AGO ACUMULADO SALDO
PRESUPUESTO REFORMULADO PRESUPUESTO REFORMLADO
4.2.9 COBERTURAS 22852.62
4.2.9.1 TIJERAL DE MADERA PARA CUBIERTA und 10 497.89 4978.9 10 4,978.90 100.00% 0 0.00 0.00% 10.00 4,978.90 100% 0.0 0.00 0.0
4.2.9.2 CORREAS DE MADERA PARA CUBIERTA M.L 100 52.21 5221 100 5,221.00 100.00% 0 0.00 0.00% 100.00 5,221.00 100% 0.0 0.00 0.0
4.2.9.3 TIJERAL DE MADERA PARA CUBIERTA und 10 497.89 4978.9 10 4,978.90 100.00% 0 0.00 0.00% 10.00 4,978.90 100% 0.0 0.00 0.0
4.2.9.4 COBERTURA CON PLANCHA ONDULADA FLEXIBLE M2. 73 52.6 3839.8 73 3,839.80 100.00% 0 0.00 0.00% 73.00 3,839.80 100% 0.0 0.00 0.0
4.2.9.5 DE COLOR DE PLANCHA F°G° INCLUYE
CANALETA m 28 31.22 874.16 28 874.16 100.00% 0 0.00 0.00% 28.00 874.16 100% 0.0 0.00 0.0
4.2.9.6 COLOCACION
FALSA COLUNNA PARA MONTANTE DE EVAC DE m 12 165.05 1980.6 12 1,980.60 100.00% 0 0.00 0.00% 12.00 1,980.60 100% 0.0 0.00 0.0
4.2.9.7 AGUAS PLUVIALES
ENCOFRADO Y DESENCOFRADO M2. 5.4 58.06 313.52 5.4 313.52 100.00% 0 0.00 0.00% 5.40 313.52 100% 0.0 0.00 0.0
4.2.9.8 TUBERIA PARA MONTANTE DE PVC SAL 3" m 12 34.71 416.52 12 416.52 100.00% 0 0.00 0.00% 12.00 416.52 100% 0.0 0.00 0.0
4.2.9.9 ACCESORIOS PARA MONTANTE DE PVC SAL DE 3" und 4 36.77 147.08 4 147.08 100.00% 0 0.00 0.00% 4.00 147.08 100% 0.0 0.00 0.0
4.2.9.1 EXCAVACION MANUAL DE ZANJAS PARA TENDIDO M3. 1.28 26.04 33.33 1.28 33.33 100.00% 0 0.00 0.00% 1.28 33.33 100% 0.0 0.00 0.0
04.2.9.1 DE TUBERIAS
RELLENO Y COMPACTACION MANUAL DE ZANJAS M3. 1.28 53.76 68.81 1.28 68.81 100.00% 0 0.00 0.00% 1.28 68.81 100% 0.0 0.00 0.0
1
4.2.10 PARA TUBERIAS ELECTRICAS
INSTALACIONES 5868.27
4.2.10. CONEXION A RED ELECTRICA Y PUESTA A TIERRA SEÑ 1 1445.16 1445.16 1 1,445.16 100.00% 0 0.00 0.00% 1.00 1,445.16 100% 0.0 0.00 0.0
14.2.10. SALIDA PARA CENTROS DE LUZ Y und 15 283.12 4246.8 15 4,246.80 100.00% 0 0.00 0.00% 15.00 4,246.80 100% 0.0 0.00 0.0
24.2.10. TOMACORRIENTES
TABLERO ELECTRICO DE DISTRIBUCION und 1 176.31 176.31 1 176.31 100.00% 0 0.00 0.00% 1.00 176.31 100% 0.0 0.00 0.0
34.2.11 SISTEMA DE AGUA FRIA 778.92
4.2.11. SALIDA DE AGUA FRIA CON TUBERIA DE PVC SAP und 5 107.36 536.8 5 536.80 100.00% 0 0.00 0.00% 5.00 536.80 100% 0.0 0.00 0.0
14.2.11. 1/2"
VALVULA GLOBO DE BRONCE DE UNION ROSCADA und 3 31.19 93.57 3 93.57 100.00% 0 0.00 0.00% 3.00 93.57 100% 0.0 0.00 0.0
2
4.2.11. DE 1/2"
CAJA DE VALVULAS pza 1 148.55 148.55 1 148.55 100.00% 0 0.00 0.00% 1.00 148.55 100% 0.0 0.00 0.0
3
4.2.12 SISTEMA DE DESAGUE 1460.05
4.2.12. SALIDA DE DESAGUE EN PVC DE 2" pto 5 106.2 531 5 531.00 100.00% 0 0.00 0.00% 5.00 531.00 100% 0.0 0.00 0.0
14.2.12. SALIDA DE DESAGUE EN PVC DE 4" pto 5 75.2 376 5 376.00 100.00% 0 0.00 0.00% 5.00 376.00 100% 0.0 0.00 0.0
2
4.2.12. SUMIDERO CROMADO DE 2" PROVISION Y und 5 55.17 275.85 5 275.85 100.00% 0 0.00 0.00% 5.00 275.85 100% 0.0 0.00 0.0
3
4.2.12. COLOCACION
REGISTRO ROSCADO CROMADO DE 2" PROVISION und 5 34.43 172.15 5 172.15 100.00% 0 0.00 0.00% 5.00 172.15 100% 0.0 0.00 0.0
44.2.12. Y COLOCACION
SOMBRERO DE VENTILACION pza 5 21.01 105.05 5 105.05 100.00% 0 0.00 0.00% 5.00 105.05 100% 0.0 0.00 0.0
54.2.13 ACOMETIDA DE DESAGUE 786.7
4.2.13. EXCAVACION MANUAL DE ZANJAS PARA TENDIDO M3. 0.81 26.04 21 0.81 21.0000000 100.00% 0 0.0000000 0.00% 0.81 21.09 100% 0.0 0.00 0.0
14.2.13. TUBERIA
DE TUBERIA
PVC SAL DE 4" m 21 25.96 545.16 21 545.16 100.00% 0 0.00 0.00% 21.00 545.16 100% 0.0 0.00 0.0
2
4.2.13. CAJA DE REGSITRO DE DESAGUE 12" X 24" und 1 185.82 185.82 1 185.82 100.00% 0 0.00 0.00% 1.00 185.82 100% 0.0 0.00 0.0
3
4.2.13. RELLENO Y COMPACTACION MANUAL DE ZANJAS m 3.2 10.85 34.72 3.2 34.72 100.00% 0 0.00 0.00% 3.20 34.72 100% 0.0 0.00 0.0
44.2.14 PARA TUBERIA
TANQUE ELEVADO 1158.22
4.2.14. TANQUE ELEVADO DE 500 LITROS pza 1 871 871 0 0.00 0.00% 1 871.00 100.00% 1 871.00 100% 1.00 871.00 100% 0.0 0.00 0.0
14.2.14. ACCESORIOS PARA TANQUE ELEVADO pza 1 287.22 287.22 0 0.00 0.00% 1 287.22 100.00% 1 287.22 100% 1.00 287.22 100% 0.0 0.00 0.0
24.2.15 ESTRUCTURA PARA TANQUE ELEVADO 1263.07
4.2.15. CONCRETO F'C=175 KG/CM2 m³ 1.25 432.99 541.24 0 0.00 0.00% 1.25 541.24 100.00% 1.3 541.24 100% 1.25 541.24 100% 0.0 0.00 0.0
14.2.15. ENCOFRADO Y DESENCOFRADO OBRAS DE ARTE m² 13.47 31.82 428.62 0 0.00 0.00% 13.5 428.62 100.00% 13 428.62 100% 13.47 428.62 100% 0.0 0.00 0.0
2
4.2.15. ACERO DE REFUERZO FY=4200 KG/CM2 (3/8'') kg 32.2 6.01 193.52 0 0.00 0.00% 32.2 193.52 100.00% 32 193.52 100% 32.20 193.52 100% 0.0 0.00 0.0
3
4.2.15. ACERO DE REFUERZO FY=4200 KG/CM2 (1/4'') kg 15.8 5.9 93.22 0 0.00 0.00% 15.8 93.22 100.00% 16 93.22 100% 15.80 93.22 100% 0.0 0.00 0.0
44.2.15. CURADO DE CONCRETO M2. 13.47 0.48 6.47 0 0.00 0.00% 13.5 6.47 99.93% 13 6.47 100% 13.47 6.47 100% 0.0 0.00 0.0
5
4.2.16 SISTEMA DE TRATAMIENTO DE DESAGUE 514.92
4.2.16. TRABAJOS PRELIMINARES DE BIODIGESTOR 21.88
14.2.16. LIMPIEZA DE TERRENO MANUAL M2. 4 1.86 7.44 4 7.44 100.00% 0 0.00 0.00% 4.00 7.44 100% 0.0 0.00 0.0
1.1
4.2.16. TRAZO NIVELACION Y REPLANTEO PRELIMINAR M2. 4 3.61 14.44 4 14.44 100.00% 0 0.00 0.00% 4.00 14.44 100% 0.0 0.00 0.0
1.2
4.2.16. MOVIMIENTO DE TIERRAS BIODIGESTOR 235.58
24.2.16. EXCAVACION MANUAL HASTA H = 1M M3. 6 21.7 130.2 6 130.20 100.00% 0 0.00 0.00% 6.00 130.20 100% 0.0 0.00 0.0
2.1
4.2.16. ELIMINACION DE MATERIAL EXCEDENTE (CON M3. 7.8 13.51 105.38 7.8 105.38 100.00% 0 0.00 0.00% 7.80 105.38 100% 0.0 0.00 0.0
2.2
4.2.16. EQUIPO,
TRABAJOSD=1KM)
PRELIMINARES PERCOLADOR 21.88
34.2.16. LIMPIEZA DE TERRENO MANUAL M2. 4 1.86 7.44 4 7.44 100.00% 0 0.00 0.00% 4.00 7.44 100% 0.0 0.00 0.0
3.1
4.2.16. TRAZO NIVELACION Y REPLANTEO PRELIMINAR M2. 4 3.61 14.44 4 14.44 100.00% 0 0.00 0.00% 4.00 14.44 100% 0.0 0.00 0.0
3.2
4.2.16. MOVIMIENTO DE TIERRAS PERCOLADOR 235.58
44.2.16. EXCAVACION MANUAL HASTA H = 1M M3. 6 21.7 130.2 6 130.20 100.00% 0 0.00 0.00% 6.00 130.20 100% 0.0 0.00 0.0
4.1
4.2.16. ELIMINACION DE MATERIAL EXCEDENTE (CON M3. 7.8 13.51 105.38 7.8 105.38 100.00% 0 0.00 0.00% 7.80 105.38 100% 0.0 0.00 0.0
4.2
4.2.17 EQUIPO,
OTROS D=1KM) 5250
4.2.17. COMPRA DE GENERADOR Y TABLERO und 1 5250 5250 0 0.00 0.00% 1 5,250.00 100.00% 1 5,250.00 100% 1.00 5,250.00 100% 0.0 0.00 0.0
14.3 INSTALACIONES SANITARIAS 81064.63
4.3.1 CAPTACION LADERA L.C.=3/4" (Q=0.25-1.2 LTS) und 1 2926.44 2926.44 1 2,926.44 100.00% 0 0.00 0.00% 1.00 2,926.44 100% 0.0 0.00 0.0
4.3.2 TRAZO Y REPLANTEO, EXCAV. EN TIERRA, ML 992.5 47.94 47580.45 992.5 47,580.45 100.00% 0 0.00 0.00% 992.50 47,580.45 100% 0.0 0.00 0.0
4.3.3 RELLENO Y COMPACTACION
LIN.CONDUCCION: SUM. E INST. DE TUB. PVC-SAP ML 667.7 8.98 5995.95 667.7 5,995.95 100.00% 0 0.00 0.00% 667.70 5,995.95 100% 0.0 0.00 0.0
4.3.4 C=10 3/4"
CAM. ROMPEPRESIONES EN LINEA DE und 2 1212.09 2424.18 2 2,424.18 100.00% 0 0.00 0.00% 2.00 2,424.18 100% 0.0 0.00 0.0
4.3.5 CONDUCCION
VALVULA L.C.= 3/4"
DE PURGA+ACCESORIOS 3/4" (INC. jgo 1 474.5 474.5 1 474.50 100.00% 0 0.00 0.00% 1.00 474.50 100% 0.0 0.00 0.0
4.3.6 SUMIN E INSTALAC.)
RESERVORIO C° ARMADO 5 M3 und 1 7141.18 7141.18 1 7,141.18 100.00% 0 0.00 0.00% 1.00 7,141.18 100% 0.0 0.00 0.0
4.3.7 CAMARA DE VALVULAS 3/4"-3/4" und 1 2429.36 2429.36 1 2,429.36 100.00% 0 0.00 0.00% 1.00 2,429.36 100% 0.0 0.00 0.0
4.3.8 EQUIPO HIPOCLORADOR:SUMINISTRO E und 1 197.7 197.7 1 197.70 100.00% 0 0.00 0.00% 1.00 197.70 100% 0.0 0.00 0.0
4.3.9 INSTALACION
RED DIST.:SUMINISTRO E INSTALACION TUB. PVC- ML 324.8 7.33 2380.78 324.8 2,380.78 100.00% 0 0.00 0.00% 324.80 2,380.78 100% 0.0 0.00 0.0
4.3.10 SAP C=10HIDRAULICA
PRUEBA 3/4" EN TUBERIA PVC SAP 3/4" ML 992.5 1.56 1548.3 992.5 1,548.30 100.00% 0 0.00 0.00% 992.50 1,548.30 100% 0.0 0.00 0.0
4.3.11 CONEX.DOMICIL.: VALVULA ESFERICA pto 2 262.35 524.7 2 524.70 100.00% 0 0.00 0.00% 2.00 524.70 100% 0.0 0.00 0.0
1/2"(TUB.MATRIZ
4.3.12 PILETA 3/4")
DOMICILIARIA und 1 589.04 589.04 1 589.04 100.00% 0 0.00 0.00% 1.00 589.04 100% 0.0 0.00 0.0
4.3.13 TANQUE BIODIGESTOR und 1 4108.57 4108.57 1 4,108.57 100.00% 0 0.00 0.00% 1.00 4,108.57 100% 0.0 0.00 0.0
4.3.14 POZO PERCOLADOR RELLENO und 2 535.58 1071.16 2 1,071.16 100.00% 0 0.00 0.00% 2.00 1,071.16 100% 0.0 0.00 0.0
4.3.15 INSTALACION DE ACCESORIOS EN SSHH glb 1 1322.32 1322.32 1 1,322.32 100.00% 0 0.00 0.00% 1.00 1,322.32 100% 0.0 0.00 0.0
4.3.16 CASILLERO METALICO DE 6 GAVETAS und 1 350 350 0 0.00 0.00% 1 350.00 100.00% 1 350.00 100% 1.00 350.00 100% 0.0 0.00 0.0
4.4 HABILITACIÓN DE CELDA DE SEGURIDAD 1830.42
4.4.1 TRAZO Y REPLANTEO PRELIMINAR m² 469.34 2.92 1370.47 469.34 1,370.47 100.00% 0 0.00 0.00% 469.34 1,370.47 100% 0.0 0.00 0.0
4.4.2 LIMPIEZA DE TERRENO m² 469.34 0.98 459.95 469.34 459.95 100.00% 0 0.00 0.00% 469.34 459.95 100% 0.0 0.00 0.0
4.5 HABILITACION DE TRINCHERAS 979287.52
4.5.1 HABILITACION DE PLATAFORMA PARA TRINCHERA 564660
4.5.1.1 CORTE DE MATERIAL SUELTO m³ 18000 10.05 180900 18000 180,900.00 100.00% 0 0.00 0.00% 18,000.00 180,900.00 100% 0.0 0.00 0.0
4.5.1.2 ELIMINACION DE MATERIAL EXCEDENTE C/MAQ. (5 m³ 26000 14.76 383760 26000 383,760.00 100.00% 0 0.00 0.00% 26,000.00 383,760.00 100% 0.0 0.00 0.0
Km.)
4.5.2 HABILITACION 321029.77
4.5.2.1 TRAZO Y REPLANTEO PRELIMINAR m² 3540 2.92 10336.8 3540 10,336.80 100.00% 0 0.00 0.00% 3,540.000 10,336.80 100% 0.0 0.00 0.0
4.5.2.2 LIMPIEZA DE TERRENO m² 3540 0.98 3469.2 3540 3,469.20 100.00% 0 0.00 0.00% 3,540.000 3,469.20 100% 0.0 0.00 0.0
4.5.2.3 CORTE DE MATERIAL SUELTO m³ 5392.92 10.05 54198.85 2149.04 21,597.85 39.85% 3244 32,600.99 60.15% 1081 10,867.00 0.20 #### 21,734.00 40% 5,392.920 54,198.85 100% 0.0 0.00 0.0
4.5.2.4 ELIMINACION DE MATERIAL EXCEDENTE C/MAQ. (5 m³ 6471.5 14.76 95519.34 2793.752 41,235.78 43.17% 3678 54,283.56 56.83% 1298 19,151.87 0.20 #### 35,131.69 37% 6,471.500 95,519.34 100% 0.0 0.00 0.0
4.5.2.5 Km.)
REFINE, NIVELACION Y FONDOS M2. 3457.5 0.86 2973.45 950 817.00 27.48% 2508 2,156.45 72.52% 842 723.69 0.24 #### 1,432.76 48% 3,457.500 2,973.45 100% 0.0 0.00 0.0
4.5.2.6 CONFORMACION DE BASE DE SOPORTE CON EL m² 962.5 3.91 3763.38 203 793.73 21.09% 760 2,969.65 78.91% 203 793.73 0.21 557 2,175.92 58% 962.500 3,763.38 100% 0.0 0.00 0.0
MISMO MATERIAL
4.5.2.7 REFINE DEL TERRENO
DE COSTADOS Y REVESTIMIENTO CON m² 825 29.15 24048.75 0.00 0.00% 825 24,048.75 100.00% 825 24048.75 100% 825.000 24,048.75 100% 0.0 0.00 0.0
CAPA DE ARCILLA
4.5.2.8 INSTALACION E=0.10
DE GEOTEXTIL m² 3300 18 59400 1683 30,294.00 51.00% 1617 29,106.00 49.00% #### 29,106.00 49% 3,300.000 59,400.00 100% 0.0 0.00 0.0
4.5.2.9 INSTALACION DE GEOMEMBRANA m² 3300 20.4 67320 1683 34,333.20 51.00% 1617 32,986.80 49.00% #### 32,986.80 49% 3,300.000 67,320.00 100% 0.0 0.00 0.0
4.5.3 MOVIMIENTO DE TIERRAS 18073.44
4.5.3.1 COMPACTACION, CON EQUIPO LIVIANO M2. 1008 17.93 18073.44 1008 18,073.44 100.00% 0 0.00 0.00% 1,008.000 18,073.44 100% 0.0 0.00 0.0
4.5.4 MEJORA DE SUELO 71811.6
4.5.4.1 COMPRA Y COLOCACION DE GEODREN und 2051.76 35 71811.6 1025.88 35,905.80 50.00% 1026 35,905.80 50.00% #### 35,905.80 50% 2,051.760 71,811.60 100% 0.0 0.00 0.0
ACUMULADO ACTUALIZADO SALDO ACTUALIZDO
Item Descripción Unid. Cant. Precio Parcial Sub Total SEP OCT NOV DIC ENE FEBR MAR ABR MAY JUN JUL AGO ACUMULADO SALDO
PRESUPUESTO REFORMULADO PRESUPUESTO REFORMLADO
4.5.5 CHIMENEAS DE VENTILACION 4441.5
4.5.5.1 CONFORMACION DE CHIMENEAS und 9 493.5 4441.5 3 1,480.50 33.33% 6 2,961.00 66.67% 6 2,961.00 67% 9.000 4,441.50 100% 0.0 0.00 0.0
4.5.6 HABILITACION DE ACCESO A TRINCHERA N° 03 23319.96
4.5.6.1 CORTE DE MATERIAL SUELTO M3. 905.7 6.56 5941.39 0 0.00 0.00% 906 5,941.39 100.00% 906 5,941.39 1.00 905.700 5,941.39 100% 0.0 0.00 0.0
4.5.6.2 ELIMINACION DE MATERIAL EXCEDENTE C/MAQ. (5 m³ 1177.41 14.76 17378.57 0 0.00 0.00% 1177 17,378.57 100.00% 1177 17,378.57 1.00 1,177.410 17,378.57 100% 0.0 0.00 0.0
4.6 Km.)
SISTEMA DE CONDUCCION DE LIXIVIADOS 32545.81
4.6.1 TRAZO Y REPLANTEO PRELIMINAR m² 132.1 2.92 385.73 86.1 251.41 65.18% 46 134.32 34.82% 46 134.32 35% 132.100 385.73 100% 0.0 0.00 0.0
4.6.2 EXCAVACIONES MASIVAS MANUALES m³ 75.33 97.91 7375.56 49.1 4,807.38 65.18% 26.2 2,568.18 34.82% 26.23 2,568.18 35% 75.330 7,375.56 100% 0.0 0.00 0.0
4.6.3 ELIMINACION DE MATERIAL EXCEDENTE C/MAQ. (5 m³ 94.17 12.41 1168.65 61.38 761.73 65.18% 32.8 406.92 34.82% 32.79 406.92 35% 94.170 1,168.65 100% 0.0 0.00 0.0
4.6.4 Km.)
RELLENO INTERIOR DE DRENES M3. 49.71 63.25 3144.16 32.4 2,049.30 65.18% 17.3 1,094.86 34.82% 17.31 1,094.86 35% 49.710 3,144.16 100% 0.0 0.00 0.0
4.6.5 SUMINISTRO E INST. TUB. PVC 200MM S-25 m 134.24 88.9 11933.94 87.5 7,778.75 65.18% 46.7 4,155.19 34.82% 46.74 4,155.19 35% 134.240 11,933.94 100% 0.0 0.00 0.0
4.6.6 P/DESAGUE CRIBADA
SUMINISTRO E INST. TUB. PVC 200MM S-25 m 71.18 83.4 5936.41 46.4 3,869.76 65.19% 24.8 2,066.65 34.81% 24.78 2,066.65 35% 71.180 5,936.41 100% 0.0 0.00 0.0
4.6.7 P/DESAGUE
SUMINISTRO DE ACCESORIOS glb 1.53 1671.39 2557.23 1 1,671.39 65.36% 0.53 885.84 34.64% 0.53 885.84 35% 1.530 2,557.23 100% 0.0 0.00 0.0
4.6.8 PRUEBA HIDRAULICA EN TUBERIA PVC m 71.18 0.62 44.13 46.4 28.77 65.19% 24.8 15.36 34.81% 24.78 15.36 35% 71.180 44.13 100% 0.0 0.00 0.0
4.7 POZAS DE ALMACENAMIENTO DE LIXIVIADO 81640.81
4.7.1 POZAS 52286.52
4.7.1.1 TRAZO Y REPLANTEO PRELIMINAR m² 96 2.92 280.32 96 280.32 100.00% 0 0.00 0.00% 96.000 280.32 100% 0.0 0.00 0.0
4.7.1.2 LIMPIEZA DE TERRENO m² 96 0.98 94.08 96 94.08 100.00% 0 0.00 0.00% 96.000 94.08 100% 0.0 0.00 0.0
4.7.1.3 EXCAVACIONES MASIVAS MANUALES m³ 136 97.91 13315.76 136 13,315.76 100.00% 0 0.00 0.00% 136.000 13,315.76 100% 0.0 0.00 0.0
4.7.1.4 ELIMINACION DE MATERIAL EXCEDENTE C/MAQ. (5 m³ 136 12.41 1687.76 136 1,687.76 100.00% 0 0.00 0.00% 136.000 1,687.76 100% 0.0 0.00 0.0
Km.)
4.7.1.5 REFINE, NIVELACION Y FONDOS M2. 80 0.86 68.8 80 68.80 100.00% 0 0.00 0.00% 80.000 68.80 100% 0.0 0.00 0.0
4.7.1.6 CONCRETO F'C=175 KG/CM2 m³ 40.8 432.99 17666 40.8 17,665.99 100.00% 0 0.00 0.00% 40.800 17,665.99 100% 0.0 0.00 0.0
4.7.1.7 ACERO DE REFUERZO FY=4200 KG/CM2 (3/8'') (M) kg 2395.22 5.55 13293.47 2395.22 13,293.47 100.00% 0 0.00 0.00% 2,395.220 13,293.47 100% 0.0 0.00 0.0
4.7.1.8 ENCOFRADO Y DESENCOFRADO OBRAS DE ARTE m² 184.8 31.82 5880.33 184.8 5,880.34 100.00% 0 0.00 0.00% 184.800 5,880.34 100% 0.0 0.00 0.0
4.7.2 CONCRETO ARMADO 88.7
4.7.2.1 CURADO DE CONCRETO M2. 184.8 0.48 88.7 184.8 88.70 100.00% 0 0.00 0.00% 184.800 88.70 100% 0.0 0.00 0.0
4.7.3 PARANTES 1845.6
4.7.3.1 PARANTES DE TUBO DE PVC 3" VACIADO CON und 16 115.35 1845.6 16 1,845.60 100.00% 0 0.00 0.00% 16.000 1,845.60 100% 0.0 0.00 0.0
CONCRETO Y FIERRO
4.7.4 COBERTURAS 24118.49
4.7.4.1 TIJERAL DE MADERA PARA CUBIERTA POZAS und 16 677.1 10833.6 16 10,833.60 100.00% 0 0.00 0.00% 16.000 10,833.60 100% 0.0 0.00 0.0
LIXIVIADO DE MADERA PARA CUBIERTA
4.7.4.2 CORREAS m 125.2 48.45 6065.85 125.2 6,065.94 100.00% 0 0.00 0.00% 125.200 6,065.94 100% 0.0 0.00 0.0
4.7.4.3 COBERTURA CON PLANCHA ONDULADA M2. 132 43.88 5792.16 132 5,792.16 100.00% 0 0.00 0.00% 132.000 5,792.16 100% 0.0 0.00 0.0
TRANSPARENTE
4.7.4.4 CUMBRERA PLANCHA ONDULADA TRANSPARENTE m 22.4 32.48 727.55 22.4 727.55 100.00% 0 0.00 0.00% 22.400 727.55 100% 0.0 0.00 0.0
4.7.4.5 CANALETA DE PLANCHA F°G° INCLUYE m 22.4 31.22 699.33 22.4 699.33 100.00% 0 0.00 0.00% 22.400 699.33 100% 0.0 0.00 0.0
4.7.5 COLOCACION
COBERTURA INTERIOR DE POZOS DE LIXIVIADOS 3301.5
4.7.5.1 MALLA DE CERRAMIENTO M2. 75 44.02 3301.5 75 3,301.50 100.00% 0 0.00 0.00% 75.000 3,301.50 100% 0.0 0.00 0.0
4.8 POZOS DE MONITOREO 4049
4.8.1 INSTALACIONES 2614.6
4.8.1.1 INSTALACION DE TUBERIA PARA POZO DE und 3 610.44 1831.32 3 1,831.32 100.00% 0 0.00 0.00% 3.000 1,831.32 100% 0.0 0.00 0.0
INSPECCION
4.8.1.2 EXCAVACIONES MASIVAS MANUALES m³ 8 97.91 783.28 8 783.28 100.00% 0 0.00 0.00% 8.000 783.28 100% 0.0 0.00 0.0
4.8.2 MOVIMIENTO DE TIERRAS 1434.4
4.8.2.1 COMPACTACION CON EQUIPO LIVIANO M2. 80 17.93 1434.4 80 1,434.40 100.00% 0 0.00 0.00% 80.000 1,434.40 100% 0.0 0.00 0.0
4.9 CUNETAS DE CORONACIÓN 8549.91
4.9.1 TRAZO Y REPLANTEO PRELIMINAR m² 124 2.92 362.08 124 362.08 100.00% 0 0.00 0.00% 124.000 362.08 100% 0.0 0.00 0.0
4.9.2 LIMPIEZA DE TERRENO m² 124 0.98 121.52 124 121.52 100.00% 0 0.00 0.00% 124.000 121.52 100% 0.0 0.00 0.0
4.9.3 EXCAVACIONES MASIVAS MANUALES m³ 70.53 97.91 6905.59 70.53 6,905.59 100.00% 0 0.00 0.00% 70.530 6,905.59 100% 0.0 0.00 0.0
4.9.4 ELIMINACION DE MATERIAL EXCEDENTE C/MAQ. (5 m³ 88.16 12.41 1094.07 88.16 1,094.07 100.00% 0 0.00 0.00% 88.160 1,094.07 100% 0.0 0.00 0.0
4.9.5 Km.)
REFINE, NIVELACION Y FONDOS M2. 77.5 0.86 66.65 77.5 66.65 100.00% 0 0.00 0.00% 77.500 66.65 100% 0.0 0.00 0.0
4.1 ALMACENES PARA PLASTICOS Y PARA 56136.79
CARTONESPREVIOS
4.10.1 TRABAJOS Y PAPELES 31514.93
4.10.1. TRAZO Y REPLANTEO PRELIMINAR m² 100 2.92 292 100 292.00 100.00% 0 0.00 0.00% 100.000 292.00 100% 0.0 0.00 0.0
14.10.1. LIMPIEZA DE TERRENO m² 100 0.98 98 100 98.00 100.00% 0 0.00 0.00% 100.000 98.00 100% 0.0 0.00 0.0
24.10.1. EXCAVACIONES MASIVAS MANUALES m³ 34.4 97.91 3368.1 34.4 3,368.10 100.00% 0 0.00 0.00% 34.400 3,368.10 100% 0.0 0.00 0.0
34.10.1. CIMIENTO CORRIDO C:H, 1:10 +50% PIEDRA M3. 14.4 271.01 3902.54 14.4 3,902.54 100.00% 0 0.00 0.00% 14.400 3,902.54 100% 0.0 0.00 0.0
44.10.1. GRANDE
COMPACTACION CON EQUIPO LIVIANO m² 100 7.14 714 100 714.00 100.00% 0 0.00 0.00% 100.000 714.00 100% 0.0 0.00 0.0
54.10.1. CONCRETO FALSO PISO 1:8 CON PIEDRA MEDIANA M3. 15 279.79 4196.85 15 4,196.85 100.00% 0 0.00 0.00% 15.000 4,196.85 100% 0.0 0.00 0.0
6
4.10.1. CONCRETO 1:8 PARA SOBRECIMIENTO M3. 3.34 269.76 901 3.34 901.00 100.00% 0 0.00 0.00% 3.340 901.00 100% 0.0 0.00 0.0
74.10.1. ENCOFRADO Y DESENCOFRADO m² 48 47.04 2257.92 48 2,257.92 100.00% 0 0.00 0.00% 48.000 2,257.92 100% 0.0 0.00 0.0
8
4.10.1. MALLA DE CERRAMIENTO ALMACEN INC. PUERTA M2. 102 154.75 15784.52 0 0.00 0.00% 102 15,784.50 100.00% 102 15,784.50 100% 102.000 15,784.50 100% 0.0 0.00 0.0
9
4.10.2 MOVIMIENTO DE TIERRAS 53.2
4.10.2. REFINE, NIVELACION Y FONDOS M2. 70 0.76 53.2 70 53.20 100.00% 0 0.00 0.00% 70.000 53.20 100% 0.0 0.00 0.0
14.10.3 CONCRETO ARMADO 10770.71
4.10.3. CONCRETO F´C = 175 KG/CM2 M3. 2.63 550.28 1447.24 2.63 1,447.24 100.00% 0 0.00 0.00% 2.630 1,447.24 100% 0.0 0.00 0.0
14.10.3. ACERO DE REFUERZO FY = 4200 KG/CM2 kg 588.51 8.03 4725.74 588.51 4,725.74 100.00% 0 0.00 0.00% 588.510 4,725.74 100% 0.0 0.00 0.0
24.10.3. ENCOFRADO Y DESENCOFRADO M2. 78.54 58.06 4560.03 78.54 4,560.03 100.00% 0 0.00 0.00% 78.540 4,560.03 100% 0.0 0.00 0.0
34.10.3. CURADO DE CONCRETO M2. 78.54 0.48 37.7 78.54 37.70 100.00% 0 0.00 0.00% 78.540 37.70 100% 0.0 0.00 0.0
44.10.4 REVOQUES Y ENLUCIDOS 1571.59
4.10.4. TARRAJEO EXTERIOR E = 1.5 MEZCLA 1:2 M2. 40.8 32.59 1329.67 40.8 1,329.67 100.00% 0 0.00 0.00% 40.800 1,329.67 100% 0.0 0.00 0.0
14.10.4. BRUÑAS EN TARRAJEO CEMENTO:ARENA m 12 20.16 241.92 12 241.92 100.00% 0 0.00 0.00% 12.000 241.92 100% 0.0 0.00 0.0
2
4.10.5 PISOS Y PAVIMENTOS 345.1
4.10.5. ACABADO Y FROTACHADO DE PISO M2. 70 4.93 345.1 70 345.10 100.00% 0 0.00 0.00% 70.000 345.10 100% 0.0 0.00 0.0
14.10.6 PINTURA 509.59
4.10.6. PINTURA MUROS EXTERIORES VINILATEX M2. 40.8 12.49 509.59 40.8 509.59 100.00% 0 0.00 0.00% 40.800 509.59 100% 0.0 0.00 0.0
14.10.7 COBERTURAS 8533.76
4.10.7. COBERTURA CON PLANCHA ONDULADA FLEXIBLE M2. 108 52.6 5680.8 108 5,680.80 100.00% 0 0.00 0.00% 108.000 5,680.80 100% 0.0 0.00 0.0
14.10.7. CANALETA
DE COLOR DE PLANCHA F°G° INCLUYE m 40 31.22 1248.8 40 1,248.80 100.00% 0 0.00 0.00% 40.000 1,248.80 100% 0.0 0.00 0.0
2
4.10.7. COLOCACION
TUBERIA PARA MONTANTE DE PVC SAL 3" m 20 34.71 694.2 20 694.20 100.00% 0 0.00 0.00% 20.000 694.20 100% 0.0 0.00 0.0
3
4.10.7. ACCESORIOS PARA MONTANTE DE PVC SAL DE 3" und 12 36.77 441.24 12 441.24 100.00% 0 0.00 0.00% 12.000 441.24 100% 0.0 0.00 0.0
44.10.7. EXCAVACION MANUAL DE ZANJAS PARA TENDIDO M3. 18 26.04 468.72 18 468.72 100.00% 0 0.00 0.00% 18.000 468.72 100% 0.0 0.00 0.0
5
4.10.8 DE TUBERIAS
ALBAÑILERÍA 2837.91
4.10.8. MURO DE BLOQUE HUECO DE CONCRETO E = M2. 37.4 75.88 2837.91 37.4 2,837.91 100.00% 0 0.00 0.00% 37.400 2,837.91 100% 0.0 0.00 0.0
14.11 ZONA
15CM MEZCLA 1:5 Y SEGREGACION
DE DESCARGA 29408.36
4.11.1 INORGANICOS
TRABAJOS PREVIOS 9438.25
4.11.1. TRAZO Y REPLANTEO PRELIMINAR m² 60 2.92 175.2 60 175.20 100.00% 0 0.00 0.00% 60.000 175.20 100% 0.0 0.00 0.0
14.11.1. LIMPIEZA DE TERRENO m² 60 0.98 58.8 60 58.80 100.00% 0 0.00 0.00% 60.000 58.80 100% 0.0 0.00 0.0
24.11.1. EXCAVACIONES MASIVAS MANUALES m³ 20.64 97.91 2020.86 20.64 2,020.86 100.00% 0 0.00 0.00% 20.640 2,020.86 100% 0.0 0.00 0.0
3
4.11.1. CIMIENTO CORRIDO C:H, 1:10 +50% PIEDRA M3. 8.64 271.01 2341.53 8.64 2,341.53 100.00% 0 0.00 0.00% 8.640 2,341.53 100% 0.0 0.00 0.0
44.11.1. GRANDE
COMPACTACION CON EQUIPO LIVIANO m² 60 7.14 428.4 60 428.40 100.00% 0 0.00 0.00% 60.000 428.40 100% 0.0 0.00 0.0
5
4.11.1. CONCRETO FALSO PISO 1:8 CON PIEDRA MEDIANA M3. 9 279.79 2518.11 9 2,518.11 100.00% 0 0.00 0.00% 9.000 2,518.11 100% 0.0 0.00 0.0
6
4.11.1. CONCRETO 1:8 PARA SOBRECIMIENTO M3. 2 269.76 540.6 2 539.52 99.80% 0 0.00 0.00% 2.000 539.52 100% 0.0 0.00 0.0
74.11.1. ENCOFRADO Y DESENCOFRADO m² 28.8 47.04 1354.75 28.8 1,354.75 100.00% 0 0.00 0.00% 28.800 1,354.75 100% 0.0 0.00 0.0
84.11.2 MOVIMIENTO DE TIERRAS 31.92
4.11.2. REFINE, NIVELACION Y FONDOS M2. 42 0.76 31.92 42 31.92 100.00% 0 0.00 0.00% 42.000 31.92 100% 0.0 0.00 0.0
1
ACUMULADO ACTUALIZADO SALDO ACTUALIZDO
Item Descripción Unid. Cant. Precio Parcial Sub Total SEP OCT NOV DIC ENE FEBR MAR ABR MAY JUN JUL AGO ACUMULADO SALDO
PRESUPUESTO REFORMULADO PRESUPUESTO REFORMLADO
4.11.3 CONCRETO ARMADO 10770.71
4.11.3. CONCRETO F´C = 175 KG/CM2 M3. 2.63 550.28 1447.24 2.63 1,447.24 100.00% 0 0.00 0.00% 2.630 1,447.24 100% 0.0 0.00 0.0
14.11.3. ACERO DE REFUERZO FY = 4200 KG/CM2 kg 588.51 8.03 4725.74 588.51 4,725.74 100.00% 0 0.00 0.00% 588.510 4,725.74 100% 0.0 0.00 0.0
24.11.3. ENCOFRADO Y DESENCOFRADO M2. 78.54 58.06 4560.03 78.54 4,560.03 100.00% 0 0.00 0.00% 78.540 4,560.03 100% 0.0 0.00 0.0
3
4.11.3. CURADO DE CONCRETO M2. 78.54 0.48 37.7 78.54 37.70 100.00% 0 0.00 0.00% 78.540 37.70 100% 0.0 0.00 0.0
44.11.4 REVOQUES Y ENLUCIDOS 942.95
4.11.4. TARRAJEO EXTERIOR E = 1.5 MEZCLA 1:2 M2. 24.48 32.59 797.8 24.48 797.80 100.00% 0 0.00 0.00% 24.480 797.80 100% 0.0 0.00 0.0
14.11.4. BRUÑAS EN TARRAJEO CEMENTO:ARENA m 7.2 20.16 145.15 7.2 145.15 100.00% 0 0.00 0.00% 7.200 145.15 100% 0.0 0.00 0.0
2
4.11.5 PISOS Y PAVIMENTOS 207.06
4.11.5. ACABADO Y FROTACHADO DE PISO M2. 42 4.93 207.06 42 207.06 100.00% 0 0.00 0.00% 42.000 207.06 100% 0.0 0.00 0.0
14.11.6 PINTURA 305.76
4.11.6. PINTURA MUROS EXTERIORES VINILATEX M2. 24.48 12.49 305.76 24.48 305.76 100.00% 0 0.00 0.00% 24.480 305.76 100% 0.0 0.00 0.0
14.11.7 COBERTURAS 6008.96
4.11.7. COBERTURA CON PLANCHA ONDULADA FLEXIBLE M2. 60 52.6 3156 60 3,156.00 100.00% 0 0.00 0.00% 60.000 3,156.00 100% 0.0 0.00 0.0
14.11.7. CANALETA
DE COLOR DE PLANCHA F°G° INCLUYE m 40 31.22 1248.8 40 1,248.80 100.00% 0 0.00 0.00% 40.000 1,248.80 100% 0.0 0.00 0.0
24.11.7. COLOCACION
TUBERIA PARA MONTANTE DE PVC SAL 3" m 20 34.71 694.2 20 694.20 100.00% 0 0.00 0.00% 20.000 694.20 100% 0.0 0.00 0.0
34.11.7. ACCESORIOS PARA MONTANTE DE PVC SAL DE 3" und 12 36.77 441.24 12 441.24 100.00% 0 0.00 0.00% 12.000 441.24 100% 0.0 0.00 0.0
44.11.7. EXCAVACION MANUAL DE ZANJAS PARA TENDIDO M3. 18 26.04 468.72 18 468.72 100.00% 0 0.00 0.00% 18.000 468.72 100% 0.0 0.00 0.0
5
4.11.8 DE TUBERIAS
ALBAÑILERÍA 1702.75
4.11.8. MURO DE BLOQUE HUECO DE CONCRETO E = M2. 22.44 75.88 1702.75 22.44 1,702.75 100.00% 0 0.00 0.00% 22.440 1,702.75 100% 0.0 0.00 0.0
14.12 15CM MEZCLA 1:5
COMPOSTERA PARA ORGANICOS 311104.12
4.12.1 TRABAJOS PREVIOS 206590.91
4.12.1. TRAZO Y REPLANTEO PRELIMINAR m² 764.4 2.92 2232.05 764.4 2,232.05 100.00% 0 0.00 0.00% 764.400 2,232.05 100% 0.0 0.00 0.0
14.12.1. LIMPIEZA DE TERRENO m² 764.4 0.98 749.11 764.4 749.11 100.00% 0 0.00 0.00% 764.400 749.11 100% 0.0 0.00 0.0
24.12.1. EXCAVACIONES MASIVAS MANUALES m³ 132.94 97.91 13016.16 132.94 13,016.16 100.00% 0 0.00 0.00% 132.940 13,016.16 100% 0.0 0.00 0.0
34.12.1. CORTE DE MATERIAL SUELTO m³ 3035.03 8.55 25949.51 3035.03 25,949.51 100.00% 0 0.00 0.00% 3,035.030 25,949.51 100% 0.0 0.00 0.0
44.12.1. ELIMINACION DE MATERIAL EXCEDENTE C/MAQ. (5 m³ 3959.97 12.41 49143.23 3959.97 49,143.23 100.00% 0 0.00 0.00% 3,959.970 49,143.23 100% 0.0 0.00 0.0
5
4.12.1. Km.)
COMPACTACION CON EQUIPO LIVIANO m² 658 7.14 4698.12 658 4,698.12 100.00% 0 0.00 0.00% 658.000 4,698.12 100% 0.0 0.00 0.0
6
4.12.1. CONCRETO FALSO PISO 1:8 CON PIEDRA MEDIANA M3. 379.96 279.79 106309 379.96 106,309.01 100.00% 0 0.00 0.00% 379.960 106,309.01 100% 0.0 0.00 0.0
74.12.1. CONCRETO F'C=175 KG/CM2 m³ 0.7 432.99 303.09 0.7 303.09 100.00% 0 0.00 0.00% 0.700 303.09 100% 0.0 0.00 0.0
8
4.12.1. ENCOFRADO Y DESENCOFRADO OBRAS DE ARTE m² 4.32 31.82 137.46 4.32 137.46 100.00% 0 0.00 0.00% 4.320 137.46 100% 0.0 0.00 0.0
9
4.12.1. SUMINISTRO DE ACCESORIOS PARA POZOS glb 1 61.98 61.98 1 61.98 100.00% 0 0.00 0.00% 1.000 61.98 100% 0.0 0.00 0.0
10
4.12.1. CORREAS DE MADERA DE 2" x 2" ML 60 24.94 1496.4 60 1,496.40 100.00% 0 0.00 0.00% 60.000 1,496.40 100% 0.0 0.00 0.0
11
4.12.1. VIGAS DE MADERA DE 3" ML 90 27.72 2494.8 90 2,494.80 100.00% 0 0.00 0.00% 90.000 2,494.80 100% 0.0 0.00 0.0
12
4.12.2 TRABAJOS PRELIMINARES 1371.66
4.12.2. TRAZO NIVELACION Y REPLANTEO PRELIMINAR M2. 379.96 3.61 1371.66 379.96 1,371.66 100.00% 0 0.00 0.00% 379.960 1,371.66 100% 0.0 0.00 0.0
14.12.3 MOVIMIENTO DE TIERRAS 1692.24
4.12.3. REFINE NIVELACION Y FONDOS M2. 35.2 3.25 114.4 35.2 114.40 100.00% 0 0.00 0.00% 35.200 114.40 100% 0.0 0.00 0.0
14.12.3. COMPACTACION, CON EQUIPO LIVIANO M2. 88 17.93 1577.84 88 1,577.84 100.00% 0 0.00 0.00% 88.000 1,577.84 100% 0.0 0.00 0.0
24.12.4 CONCRETO SIMPLE 35520.61
4.12.4. CIMIENTO CORRIDO C:H 1.10+30% PIEDRA GRANDE M3. 126.95 279.8 35520.61 126.95 35,520.61 100.00% 0 0.00 0.00% 126.950 35,520.61 100% 0.0 0.00 0.0
14.12.5 CONCRETO ARMADO 16889.02
4.12.5. CONCRETO F´C = 175 KG/CM2 M3. 17.15 550.28 9437.3 17.15 9,437.30 100.00% 0 0.00 0.00% 17.150 9,437.30 100% 0.0 0.00 0.0
14.12.5. ACERO DE REFUERZO FY = 4200 KG/CM2 kg 575.19 8.03 4618.78 575.19 4,618.78 100.00% 0 0.00 0.00% 575.190 4,618.78 100% 0.0 0.00 0.0
24.12.5. ENCOFRADO Y DESENCOFRADO M2. 46.7 58.06 2711.4 46.7 2,711.40 100.00% 0 0.00 0.00% 46.700 2,711.40 100% 0.0 0.00 0.0
34.12.5. CURADO DE CONCRETO M2. 253.21 0.48 121.54 253.21 121.54 100.00% 0 0.00 0.00% 253.210 121.54 100% 0.0 0.00 0.0
44.12.6 PARANTES 6921
4.12.6. PARANTES DE TUBO DE PVC 3" VACIADO CON und 60 115.35 6921 60 6,921.00 100.00% 0 0.00 0.00% 60.000 6,921.00 100% 0.0 0.00 0.0
14.12.7 REVOQUES
CONCRETO YY ENLUCIDOS
FIERRO 9945.55
4.12.7. TARRAJEO EXTERIOR E = 1.5 CM MEZCLA 1:2 M2. 253.21 32.59 8252.11 253.21 8,252.11 100.00% 0 0.00 0.00% 253.210 8,252.11 100% 0.0 0.00 0.0
14.12.7. BRUÑAS EN TARRAJEO CEMENTO:ARENA m 84 20.16 1693.44 84 1,693.44 100.00% 0 0.00 0.00% 84.000 1,693.44 100% 0.0 0.00 0.0
2
4.12.8 PISOS Y PAVIMENTOS 1564.68
4.12.8. ACABADO Y FROTACHADO DE PISO M2. 317.38 4.93 1564.68 317.38 1,564.68 100.00% 0 0.00 0.00% 317.380 1,564.68 100% 0.0 0.00 0.0
14.12.9 PINTURA 810.27
4.12.9. PINTURA MUROS EXTERIORES m² 253.21 3.2 810.27 253.21 810.27 100.00% 0 0.00 0.00% 253.210 810.27 100% 0.0 0.00 0.0
14.12.1 COBERTURAS 28683.26
04.12.1 COBERTURA CON PLANCHA ONDULADA FLEXIBLE M2. 317.38 52.6 16694.19 317.38 16,694.19 100.00% 0 0.00 0.00% 317.380 16,694.19 100% 0.0 0.00 0.0
0.1
4.12.1 DE COLOR PLANCHA ONDULADA FLEXIBLE
CUMBRERA m 60 12.68 760.8 60 760.80 100.00% 0 0.00 0.00% 60.000 760.80 100% 0.0 0.00 0.0
0.2
4.12.1 COLOR
CANALETA DE PLANCHA F°G° INCLUYE m 96.6 31.22 3015.85 96.6 3,015.85 100.00% 0 0.00 0.00% 96.600 3,015.85 100% 0.0 0.00 0.0
0.3
4.12.1 COLOCACION
FALSA COLUNNA PARA MONTANTE DE EVAC DE m 18 165.05 2970.9 18 2,970.90 100.00% 0 0.00 0.00% 18.000 2,970.90 100% 0.0 0.00 0.0
0.4
4.12.1 AGUAS PLUVIALES
ENCOFRADO Y DESENCOFRADO M2. 14.4 58.06 836.05 14.4 836.06 100.00% 0 0.00 0.00% 14.400 836.06 100% 0.0 0.00 0.0
0.5
4.12.1 TUBERIA PARA MONTANTE DE PVC SAL 3" m 48 34.71 1666.08 48 1,666.08 100.00% 0 0.00 0.00% 48.000 1,666.08 100% 0.0 0.00 0.0
0.6
4.12.1 ACCESORIOS PARA MONTANTE DE PVC SAL DE 3" und 12 36.77 441.24 12 441.24 100.00% 0 0.00 0.00% 12.000 441.24 100% 0.0 0.00 0.0
0.7
4.12.1 EXCAVACION MANUAL DE ZANJAS PARA TENDIDO M3. 28.8 26.04 749.92 28.8 749.95 100.00% 0 0.00 0.00% 28.800 749.95 100% 0.0 0.00 0.0
0.8
4.12.1 DE TUBERIAS
RELLENO Y COMPACTACION MANUAL DE ZANJAS M3. 28.8 53.76 1548.23 28.8 1,548.29 100.00% 0 0.00 0.00% 28.800 1,548.29 100% 0.0 0.00 0.0
0.9
4.12.1 PARA TUBERIAS
ACCESORIOS 1114.92
1
4.12.1 CAJA DE REGSITRO DE DESAGUE 12" X 24" und 6 185.82 1114.92 6 1,114.92 100.00% 0 0.00 0.00% 6.000 1,114.92 100% 0.0 0.00 0.0
1.1
4.13 ZONA DE DESCARGA Y SEGREGACION 47740.91
ORGANICOS
4.13.1 TRABAJOS PREVIOS 21099.82
4.13.1. TRAZO Y REPLANTEO PRELIMINAR m² 112 2.92 327.04 112 327.04 100.00% 0 0.00 0.00% 112.000 327.04 100% 0.0 0.00 0.0
14.13.1. LIMPIEZA DE TERRENO m² 112 0.98 109.76 112 109.76 100.00% 0 0.00 0.00% 112.000 109.76 100% 0.0 0.00 0.0
24.13.1. EXCAVACIONES MASIVAS MANUALES m³ 16.5 97.91 1615.52 16.5 1,615.52 100.00% 0 0.00 0.00% 16.500 1,615.52 100% 0.0 0.00 0.0
34.13.1. ELIMINACION DE MATERIAL EXCEDENTE C/MAQ. (5 m³ 16.5 12.41 204.77 16.5 204.77 100.00% 0 0.00 0.00% 16.500 204.77 100% 0.0 0.00 0.0
44.13.1. Km.)
REFINE, NIVELACION Y FONDOS M2. 59.74 0.86 51.38 59.74 51.38 99.99% 0 0.00 0.00% 59.740 51.38 100% 0.0 0.00 0.0
54.13.1. COMPACTACION CON EQUIPO LIVIANO m² 59.74 7.14 426.54 59.74 426.54 100.00% 0 0.00 0.00% 59.740 426.54 100% 0.0 0.00 0.0
6
4.13.1. CONCRETO FALSO PISO 1:8 CON PIEDRA MEDIANA M3. 55 279.79 15388.45 55 15,388.45 100.00% 0 0.00 0.00% 55.000 15,388.45 100% 0.0 0.00 0.0
74.13.1. CORREAS DE MADERA DE 2" x 2" ML 96 24.94 2394.24 96 2,394.24 100.00% 0 0.00 0.00% 96.000 2,394.24 100% 0.0 0.00 0.0
8
4.13.1. VIGAS DE MADERA DE 3" ML 21 27.72 582.12 21 582.12 100.00% 0 0.00 0.00% 21.000 582.12 100% 0.0 0.00 0.0
9
4.13.2 TRABAJOS PRELIMINARES 404.32
4.13.2. TRAZO NIVELACION Y REPLANTEO PRELIMINAR M2. 112 3.61 404.32 112 404.32 100.00% 0 0.00 0.00% 112.000 404.32 100% 0.0 0.00 0.0
14.13.3 MOVIMIENTO DE TIERRAS 1265.3
4.13.3. REFINE NIVELACION Y FONDOS M2. 59.74 3.25 194.16 59.74 194.16 100.00% 0 0.00 0.00% 59.740 194.16 100% 0.0 0.00 0.0
14.13.3. COMPACTACION, CON EQUIPO LIVIANO M2. 59.74 17.93 1071.14 59.74 1,071.14 100.00% 0 0.00 0.00% 59.740 1,071.14 100% 0.0 0.00 0.0
24.13.4 CONCRETO SIMPLE 5848.66
4.13.4. CIMIENTO CORRIDO C:H 1.10+30% PIEDRA GRANDE M3. 5.28 279.8 1477.34 5.28 1,477.34 100.00% 0 0.00 0.00% 5.280 1,477.34 100% 0.0 0.00 0.0
14.13.4. CONCRETO F´C = 175 KG/CM2 M3. 2.68 550.28 1474.75 2.68 1,474.75 100.00% 0 0.00 0.00% 2.680 1,474.75 100% 0.0 0.00 0.0
2
4.13.4. ACERO DE REFUERZO FY = 4200 KG/CM2 kg 100 8.03 803 100 803.00 100.00% 0 0.00 0.00% 100.000 803.00 100% 0.0 0.00 0.0
3
4.13.4. ENCOFRADO Y DESENCOFRADO M2. 35.7 58.06 2072.74 35.7 2,072.74 100.00% 0 0.00 0.00% 35.700 2,072.74 100% 0.0 0.00 0.0
44.13.4. CURADO DE CONCRETO M2. 43.4 0.48 20.83 43.4 20.83 100.01% 0 0.00 0.00% 43.400 20.83 100% 0.0 0.00 0.0
54.13.5 PARANTES 1365.84
4.13.5. PARANTES DE TUBO DE PVC 6" VACIADO CON und 8 170.73 1365.84 8 1,365.84 100.00% 0 0.00 0.00% 8.000 1,365.84 100% 0.0 0.00 0.0
14.13.6 CONCRETO
REVOQUES YY ENLUCIDOS
FIERRO 1615.04
ACUMULADO ACTUALIZADO SALDO ACTUALIZDO
Item Descripción Unid. Cant. Precio Parcial Sub Total SEP OCT NOV DIC ENE FEBR MAR ABR MAY JUN JUL AGO ACUMULADO SALDO
PRESUPUESTO REFORMULADO PRESUPUESTO REFORMLADO
4.13.6. TARRAJEO EXTERIOR E = 1.5 CM MEZCLA 1:2 M2. 35.7 32.59 1163.46 35.7 1,163.46 100.00% 0 0.00 0.00% 35.700 1,163.46 100% 0.0 0.00 0.0
14.13.6. BRUÑAS EN TARRAJEO CEMENTO:ARENA m 22.4 20.16 451.58 22.4 451.58 100.00% 0 0.00 0.00% 22.400 451.58 100% 0.0 0.00 0.0
2
4.13.7 PISOS Y PAVIMENTOS 271.15
4.13.7. ACABADO Y FROTACHADO DE PISO M2. 55 4.93 271.15 55 271.15 100.00% 0 0.00 0.00% 55.000 271.15 100% 0.0 0.00 0.0
14.13.8 PINTURA 114.24
4.13.8. PINTURA MUROS EXTERIORES m² 35.7 3.2 114.24 35.7 114.24 100.00% 0 0.00 0.00% 35.700 114.24 100% 0.0 0.00 0.0
14.13.9 COBERTURAS 15756.54
4.13.9. COBERTURA CON PLANCHA ONDULADA FLEXIBLE M2. 92.4 52.6 4860.24 92.4 4,860.24 100.00% 0 0.00 0.00% 92.400 4,860.24 100% 0.0 0.00 0.0
14.13.9. DE COLOR PLANCHA ONDULADA FLEXIBLE
CUMBRERA m 12 12.68 152.16 12 152.16 100.00% 0 0.00 0.00% 12.000 152.16 100% 0.0 0.00 0.0
2
4.13.9. COLOR DE MADERA PARA CUBIERTA POZAS
TIJERAL und 9 677.1 6093.9 9 6,093.90 100.00% 0 0.00 0.00% 9.000 6,093.90 100% 0.0 0.00 0.0
3
4.13.9. LIXIVIADO
CORREAS DE MADERA PARA CUBIERTA m 96 48.44 4650.24 96 4,650.24 100.00% 0 0.00 0.00% 96.000 4,650.24 100% 0.0 0.00 0.0
44.14 ZONA DE ALMACENAMIENTO DE BIOL 11647.55
4.14.1 TRABAJOS PRELIMINARES 97.93
4.14.1. LIMPIEZA DE TERRENO und 20.88 1.08 22.55 20.88 22.55 100.00% 0 0.00 0.00% 20.880 22.55 100% 0.0 0.00 0.0
14.14.1. TRAZO NIVELACION Y REPLANTEO PRELIMINAR M2. 20.88 3.61 75.38 20.88 75.38 100.00% 0 0.00 0.00% 20.880 75.38 100% 0.0 0.00 0.0
24.14.2 MOVIMIENTO DE TIERRAS 1583.59
4.14.2. EXCAVACION MANUAL HASTA H = 1M M3. 2.52 21.7 54.68 2.52 54.68 100.01% 0 0.00 0.00% 2.520 54.68 100% 0.0 0.00 0.0
14.14.2. ELIMINACION DE MATERIAL EXCEDENTE (CON M3. 100 13.51 1351 100 1,351.00 100.00% 0 0.00 0.00% 100.000 1,351.00 100% 0.0 0.00 0.0
2
4.14.2. EQUIPO NIVELACION
REFINE D = 1) Y FONDOS M2. 8.4 3.25 27.3 8.4 27.30 100.00% 0 0.00 0.00% 8.400 27.30 100% 0.0 0.00 0.0
3
4.14.2. COMPACTACION, CON EQUIPO LIVIANO M2. 8.4 17.93 150.61 8.4 150.61 100.00% 0 0.00 0.00% 8.400 150.61 100% 0.0 0.00 0.0
44.14.3 CONCRETO SIMPLE 3939.59
4.14.3. CONCRETO FALSO PISO 1:8 CON PIEDRA MEDIANA M3. 2.88 343.27 988.62 2.88 988.62 100.00% 0 0.00 0.00% 2.880 988.62 100% 0.0 0.00 0.0
14.14.3. CIMIENTO CORRIDO C:H 1.10+30% PIEDRA GRANDE M3. 1.15 279.8 321.77 1.15 321.77 100.00% 0 0.00 0.00% 1.150 321.77 100% 0.0 0.00 0.0
24.14.3. CONCRETO F´C = 175 KG/CM2 M3. 1.62 550.28 891.45 1.62 891.45 100.00% 0 0.00 0.00% 1.620 891.45 100% 0.0 0.00 0.0
3
4.14.3. ACERO DE REFUERZO FY = 4200 KG/CM2 kg 27.22 8.03 218.58 27.22 218.58 100.00% 0 0.00 0.00% 27.220 218.58 100% 0.0 0.00 0.0
44.14.3. ENCOFRADO Y DESENCOFRADO M2. 17.28 58.06 1003.28 17.28 1,003.28 100.00% 0 0.00 0.00% 17.280 1,003.28 100% 0.0 0.00 0.0
54.14.3. CURADO DE CONCRETO M2. 17.28 0.48 8.29 17.28 8.29 100.05% 0 0.00 0.00% 17.280 8.29 100% 0.0 0.00 0.0
6
4.14.3. CONCRETO 1:8 PARA SOBRECIMIENTO M3. 1.73 293.41 507.6 1.73 507.60 100.00% 0 0.00 0.00% 1.730 507.60 100% 0.0 0.00 0.0
74.14.4 PARANTES 461.4
4.14.4. PARANTES DE TUBO DE PVC 3" VACIADO CON und 4 115.35 461.4 4 461.40 100.00% 0 0.00 0.00% 4.000 461.40 100% 0.0 0.00 0.0
14.14.5 REVOQUES
CONCRETO YY ENLUCIDOS
FIERRO 756.7
4.14.5. TARRAJEO EXTERIOR E = 1.5 CM MEZCLA 1:2 M2. 17.28 32.59 563.16 17.28 563.16 100.00% 0 0.00 0.00% 17.280 563.16 100% 0.0 0.00 0.0
14.14.5. BRUÑAS EN TARRAJEO CEMENTO:ARENA m 9.6 20.16 193.54 9.6 193.54 100.00% 0 0.00 0.00% 9.600 193.54 100% 0.0 0.00 0.0
2
4.14.6 PINTURA 215.83
4.14.6. PINTURA MUROS EXTERIORES VINILATEX M2. 17.28 12.49 215.83 0 0.00 0.00% 17.3 215.83 100.00% 17.28 215.83 100% 17.280 215.83 100% 0.0 0.00 0.0
14.14.7 COBERTURAS 4592.51
4.14.7. COBERTURA CON PLANCHA ONDULADA FLEXIBLE M2. 20.88 52.6 1098.29 0 0.00 0.00% 20.9 1,098.29 100.00% 20.88 1,098.29 100% 20.880 1,098.29 100% 0.0 0.00 0.0
14.14.7. DE COLOR PLANCHA ONDULADA FLEXIBLE
CUMBRERA m 3 12.68 38.04 0 0.00 0.00% 3 38.04 100.00% 3 38.04 100% 3.000 38.04 100% 0.0 0.00 0.0
2
4.14.7. COLOR
CANALETA DE PLANCHA F°G° INCLUYE m 6 31.22 187.32 0 0.00 0.00% 6 187.32 100.00% 6 187.32 100% 6.000 187.32 100% 0.0 0.00 0.0
3
4.14.7. COLOCACION
FALSA COLUNNA PARA MONTANTE DE EVAC DE m 3 165.05 495.15 0 0.00 0.00% 3 495.15 100.00% 3 495.15 100% 3.000 495.15 100% 0.0 0.00 0.0
44.14.7. AGUAS PLUVIALES
ENCOFRADO Y DESENCOFRADO M2. 2.4 58.06 139.34 0 0.00 0.00% 2.4 139.34 100.00% 2.4 139.34 100% 2.400 139.34 100% 0.0 0.00 0.0
54.14.7. TUBERIA PARA MONTANTE DE PVC SAL 3" m 8 34.71 277.68 0 0.00 0.00% 8 277.68 100.00% 8 277.68 100% 8.000 277.68 100% 0.0 0.00 0.0
6
4.14.7. ACCESORIOS PARA MONTANTE DE PVC SAL DE 3" und 2 36.77 73.54 0 0.00 0.00% 2 73.54 100.00% 2 73.54 100% 2.000 73.54 100% 0.0 0.00 0.0
74.14.7. EXCAVACION MANUAL DE ZANJAS PARA TENDIDO M3. 1.6 26.04 41.66 0 0.00 0.00% 1.6 41.66 100.01% 1.6 41.66 100% 1.600 41.66 100% 0.0 0.00 0.0
84.14.7. DE TUBERIAS
RELLENO Y COMPACTACION MANUAL DE ZANJAS M3. 1.6 53.76 86.01 0 0.00 0.00% 1.6 86.02 100.01% 1.6 86.02 100% 1.600 86.02 100% 0.0 0.00 0.0
94.14.7. PARA TUBERIAS
TIJERAL DE MADERA PARA POZA DE BIOL und 4 393.55 1574.2 0 0.00 0.00% 4 1,574.20 100.00% 4 1,574.20 100% 4.000 1,574.20 100% 0.0 0.00 0.0
10
4.14.7. CORREAS DE MADERA PARA CUBIERTA m 12 48.44 581.28 0 0.00 0.00% 12 581.28 100.00% 12 581.28 100% 12.000 581.28 100% 0.0 0.00 0.0
11
4.15 SERVICIOS HIGIÉNICOS 11064.19
4.15.1 TRABAJOS PRELIMINARES 25.32
4.15.1. LIMPIEZA DE TERRENO und 5.4 1.08 5.83 5.4 5.83 100.03% 0 0.00 0.00% 5.400 5.83 100% 0.0 0.00 0.0
14.15.1. TRAZO NIVELACION Y REPLANTEO PRELIMINAR M2. 5.4 3.61 19.49 5.4 19.49 100.02% 0 0.00 0.00% 5.400 19.49 100% 0.0 0.00 0.0
24.15.2 MOVIMIENTO DE TIERRAS 194.91
4.15.2. EXCAVACION MANUAL HASTA H = 1M M3. 1.62 21.7 35.15 1.62 35.15 100.01% 0 0.00 0.00% 1.620 35.15 100% 0.0 0.00 0.0
14.15.2. ELIMINACION DE MATERIAL EXCEDENTE (CON M3. 2.11 13.51 28.51 2.11 28.51 99.99% 0 0.00 0.00% 2.110 28.51 100% 0.0 0.00 0.0
24.15.2. EQUIPO D = 1)
COMPACTACION, CON EQUIPO LIVIANO M2. 7.32 17.93 131.25 7.32 131.25 100.00% 0 0.00 0.00% 7.320 131.25 100% 0.0 0.00 0.0
34.15.3 CONCRETO SIMPLE 2759.68
4.15.3. CIMIENTO CORRIDO C:H 1.10+30% PIEDRA GRANDE M3. 1.28 279.8 358.14 1.28 358.14 100.00% 0 0.00 0.00% 1.280 358.14 100% 0.0 0.00 0.0
14.15.3. COMPACTACION, CON EQUIPO LIVIANO M2. 5.4 17.93 96.82 5.4 96.82 100.00% 0 0.00 0.00% 5.400 96.82 100% 0.0 0.00 0.0
24.15.3. CONCRETO FALSO PISO 1:8 CON PIEDRA MEDIANA M3. 5.4 343.27 1853.66 5.4 1,853.66 100.00% 0 0.00 0.00% 5.400 1,853.66 100% 0.0 0.00 0.0
3
4.15.3. CONCRETO 1:8 PARA SOBRECIMIENTO M3. 0.42 293.41 123.23 0.42 123.23 100.00% 0 0.00 0.00% 0.420 123.23 100% 0.0 0.00 0.0
44.15.3. ENCOFRADO Y DESENCOFRADO M2. 5.6 58.06 325.14 5.6 325.14 100.00% 0 0.00 0.00% 5.600 325.14 100% 0.0 0.00 0.0
5
4.15.3. CURADO DE CONCRETO M2. 5.6 0.48 2.69 5.6 2.69 99.93% 0 0.00 0.00% 5.600 2.69 100% 0.0 0.00 0.0
6
4.15.4 CONCRETO ARMADO 1150.4
4.15.4. CONCRETO F´C = 175 KG/CM2 M3. 0.38 550.28 209.11 0.38 209.11 100.00% 0 0.00 0.00% 0.380 209.11 100% 0.0 0.00 0.0
14.15.4. ENCOFRADO Y DESENCOFRADO M2. 5.04 58.06 292.62 5.04 292.62 100.00% 0 0.00 0.00% 5.040 292.62 100% 0.0 0.00 0.0
24.15.4. ACERO DE REFUERZO FY = 4200 KG/CM2 kg 80.48 8.03 646.25 80.48 646.25 100.00% 0 0.00 0.00% 80.480 646.25 100% 0.0 0.00 0.0
3
4.15.4. CURADO DE CONCRETO M2. 5.04 0.48 2.42 5.04 2.42 99.97% 0 0.00 0.00% 5.040 2.42 100% 0.0 0.00 0.0
44.15.5 ALBAÑILERIA 773.39
4.15.5. MURO DE BLOQUETAS M2. 12.6 61.38 773.39 12.6 773.39 100.00% 0 0.00 0.00% 12.600 773.39 100% 0.0 0.00 0.0
14.15.6 REVOQUES Y ENLUCIDOS 1894.78
4.15.6. TARRAJEO EXTERIOR E = 1.5 CM MEZCLA 1:2 M2. 30.8 32.59 1003.77 30.8 1,003.77 100.00% 0 0.00 0.00% 30.800 1,003.77 100% 0.0 0.00 0.0
14.15.6. REVESTIDO CON CERAMICO COLOR 30 X 30 M2. 10.5 62.35 654.68 10.5 654.68 100.00% 0 0.00 0.00% 10.500 654.68 100% 0.0 0.00 0.0
24.15.6. PISO DE CERAMICO COLOR 30 X30 M2. 3.75 63.02 236.33 3.75 236.33 100.00% 0 0.00 0.00% 3.750 236.33 100% 0.0 0.00 0.0
34.15.7 CARPINTERIA, VIDRIOS, CERRAJERIA Y PINTURA 1945.57
4.15.7. PUERTA DE MADERA und 2 780.44 1560.88 2 1,560.88 100.00% 0 0.00 0.00% 2.000 1,560.88 100% 0.0 0.00 0.0
14.15.7. PINTURA MUROS EXTERIORES VINILATEX M2. 30.8 12.49 384.69 30.8 384.69 100.00% 0 0.00 0.00% 30.800 384.69 100% 0.0 0.00 0.0
2
4.15.8 COBERTURAS 769.63
4.15.8. CORREAS DE MADERA PARA CUBIERTA m 12 48.44 581.28 12 581.28 100.00% 0 0.00 0.00% 12.000 581.28 100% 0.0 0.00 0.0
14.15.8. COBERTURA DE CALAMINA SS.HH M2. 5.4 34.88 188.35 5.4 188.35 100.00% 0 0.00 0.00% 5.400 188.35 100% 0.0 0.00 0.0
2
4.15.9 SISTEMA DE AGUA FRIA 394.46
4.15.9. SALIDA DE AGUA FRIA CON TUBERIA DE PVC SAP und 2 107.36 214.72 2 214.72 100.00% 0 0.00 0.00% 2.000 214.72 100% 0.0 0.00 0.0
14.15.9. 1/2"
VALVULA GLOBO DE BRONCE DE UNION ROSCADA und 1 31.19 31.19 1 31.19 100.00% 0 0.00 0.00% 1.000 31.19 100% 0.0 0.00 0.0
24.15.9. DE 1/2"
CAJA DE VALVULAS pza 1 148.55 148.55 1 148.55 100.00% 0 0.00 0.00% 1.000 148.55 100% 0.0 0.00 0.0
34.15.1 SISTEMA DE DESAGUE 621.48
04.15.1 SALIDA DE DESAGUE EN PVC DE 2" pto 1 106.2 106.2 1 106.20 100.00% 0 0.00 0.00% 1.000 106.20 100% 0.0 0.00 0.0
0.1
4.15.1 SALIDA DE DESAGUE EN PVC DE 4" pto 4 75.2 300.8 4 300.80 100.00% 0 0.00 0.00% 4.000 300.80 100% 0.0 0.00 0.0
0.2
4.15.1 REGISTRO DE BRONCE 2", PROVISION Y und 3 44.49 133.47 3 133.47 100.00% 0 0.00 0.00% 3.000 133.47 100% 0.0 0.00 0.0
0.3 COLOCACION
4.15.1 TRAMPA "P" DE P.V.C. SAL PARA DESAGUE DE 2" und 3 20 60 3 60.00 100.00% 0 0.00 0.00% 3.000 60.00 100% 0.0 0.00 0.0
0.4
4.15.1 SOMBRERO DE VENTILACION pza 1 21.01 21.01 1 21.01 100.00% 0 0.00 0.00% 1.000 21.01 100% 0.0 0.00 0.0
0.5
4.15.1 ACOMETIDA DE DESAGUE 534.57
14.15.1 EXCAVACION DE ZANJA, TERRENO SEMIRROCOSO, m 1.6 12.42 19.87 1.6 19.87 100.01% 0 0.00 0.00% 1.600 19.87 100% 0.0 0.00 0.0
1.1
4.15.1 TUBERIA
TUBERIA 3DE- 6PVC SAL 4" m 12 25.96 311.52 12 311.52 100.00% 0 0.00 0.00% 12.000 311.52 100% 0.0 0.00 0.0
1.2
4.15.1 CAJA DE REGSITRO DE DESAGUE 12" X 24" und 1 185.82 185.82 1 185.82 100.00% 0 0.00 0.00% 1.000 185.82 100% 0.0 0.00 0.0
1.3
4.15.1 RELLENO Y COMPACTACION MANUAL DE ZANJAS m 1.6 10.85 17.36 1.6 17.36 100.00% 0 0.00 0.00% 1.600 17.36 100% 0.0 0.00 0.0
1.4 PARA TUBERIA
ACUMULADO ACTUALIZADO SALDO ACTUALIZDO
Item Descripción Unid. Cant. Precio Parcial Sub Total SEP OCT NOV DIC ENE FEBR MAR ABR MAY JUN JUL AGO ACUMULADO SALDO
PRESUPUESTO REFORMULADO PRESUPUESTO REFORMLADO
4.16 HABILITACION DE LOMBRICERAS 57562.3
4.16.1 TRABAJOS PRELIMINARES 1153.36
4.16.1. LIMPIEZA DE TERRENO und 245.92 1.08 265.59 245.92 265.59 100.00% 0 0.00 0.00% 245.920 265.59 100% 0.0 0.00 0.0
14.16.1. TRAZO NIVELACION Y REPLANTEO PRELIMINAR M2. 245.92 3.61 887.77 245.92 887.77 100.00% 0 0.00 0.00% 245.920 887.77 100% 0.0 0.00 0.0
24.16.2 MOVIMIENTO DE TIERRAS 4459.44
4.16.2. EXCAVACION MANUAL HASTA H = 1M M3. 73.78 21.7 1601.03 73.78 1,601.03 100.00% 0 0.00 0.00% 73.780 1,601.03 100% 0.0 0.00 0.0
14.16.2. ELIMINACION DE MATERIAL EXCEDENTE (CON M3. 95.91 13.51 1295.74 95.91 1,295.74 100.00% 0 0.00 0.00% 95.910 1,295.74 100% 0.0 0.00 0.0
24.16.2. EQUIPO D = 1)
REFINE NIVELACION Y FONDOS M2. 73.78 3.25 239.79 73.78 239.79 100.00% 0 0.00 0.00% 73.780 239.79 100% 0.0 0.00 0.0
3
4.16.2. COMPACTACION, CON EQUIPO LIVIANO M2. 73.78 17.93 1322.88 73.78 1,322.88 100.00% 0 0.00 0.00% 73.780 1,322.88 100% 0.0 0.00 0.0
44.16.3 CONCRETO SIMPLE 37212.3
4.16.3. CONCRETO F´C = 175 KG/CM2 M3. 10.08 550.28 5546.82 10.08 5,546.82 100.00% 0 0.00 0.00% 10.080 5,546.82 100% 0.0 0.00 0.0
14.16.3. CIMIENTO CORRIDO C:H 1.10+30% PIEDRA GRANDE M3. 2.75 279.8 769.45 2.75 769.45 100.00% 0 0.00 0.00% 2.750 769.45 100% 0.0 0.00 0.0
24.16.3. ACERO DE REFUERZO FY = 4200 KG/CM2 kg 129 8.03 1035.87 129 1,035.87 100.00% 0 0.00 0.00% 129.000 1,035.87 100% 0.0 0.00 0.0
3
4.16.3. CONCRETO 1:8 PARA SOBRECIMIENTO M3. 4.13 293.41 1211.78 4.13 1,211.78 100.00% 0 0.00 0.00% 4.130 1,211.78 100% 0.0 0.00 0.0
44.16.3. CONCRETO FALSO PISO 1:8 CON PIEDRA MEDIANA M3. 73.96 343.27 25388.25 73.96 25,388.25 100.00% 0 0.00 0.00% 73.960 25,388.25 100% 0.0 0.00 0.0
54.16.3. ENCOFRADO Y DESENCOFRADO M2. 55.04 58.06 3195.62 55.04 3,195.62 100.00% 0 0.00 0.00% 55.040 3,195.62 100% 0.0 0.00 0.0
64.16.3. CURADO DE CONCRETO M2. 134.4 0.48 64.51 134.4 64.51 100.00% 0 0.00 0.00% 134.400 64.51 100% 0.0 0.00 0.0
74.16.4 PARANTES 1841.28
4.16.4. PARANTES DE MADERA RECTANGULAR DE 6" X 6" und 6 306.88 1841.28 6 1,841.28 100.00% 0 0.00 0.00% 6.000 1,841.28 100% 0.0 0.00 0.0
14.16.5 PISOS Y PAVIMENTOS 271.35
4.16.5. ACABADO Y FROTACHADO DE PISO M2. 55.04 4.93 271.35 55.04 271.35 100.00% 0 0.00 0.00% 55.040 271.35 100% 0.0 0.00 0.0
14.16.6 REVOQUES Y ENLUCIDOS 448.44
4.16.6. TARRAJEO EXTERIOR E = 1.5 CM MEZCLA 1:2 M2. 13.76 32.59 448.44 13.76 448.44 100.00% 0 0.00 0.00% 13.760 448.44 100% 0.0 0.00 0.0
14.16.7 PINTURA 176.13
4.16.7. PINTURA MUROS EXTERIORES m² 55.04 3.2 176.13 55.04 176.13 100.00% 0 0.00 0.00% 55.040 176.13 100% 0.0 0.00 0.0
14.16.8 COBERTURAS 12000
4.16.8. COBERTURA CON PALMERA KAPASHI M2. 200 60 12000 100 6,000.00 50.00% 100 6,000.00 50.00% 100 6,000.00 50% 200.000 12,000.00 100% 0.0 0.00 0.0
14.17 ALMACEN PARA HERRAMIENTAS Y ABONO 68534.77
ORGANICOPRELIMINARES
4.17.1 TRABAJOS 590.94
4.17.1. LIMPIEZA DE TERRENO und 126 1.08 136.08 126 136.08 100.00% 0 0.00 0.00% 126.000 136.08 100% 0.0 0.00 0.0
14.17.1. TRAZO NIVELACION Y REPLANTEO PRELIMINAR M2. 126 3.61 454.86 126 454.86 100.00% 0 0.00 0.00% 126.000 454.86 100% 0.0 0.00 0.0
24.17.2 MOVIMIENTO DE TIERRAS 2804.36
4.17.2. EXCAVACION MANUAL HASTA H = 1M M3. 37.8 21.7 820.26 37.8 820.26 100.00% 0 0.00 0.00% 37.800 820.26 100% 0.0 0.00 0.0
14.17.2. ELIMINACION DE MATERIAL EXCEDENTE (CON M3. 49.14 13.51 663.88 49.14 663.88 100.00% 0 0.00 0.00% 49.140 663.88 100% 0.0 0.00 0.0
24.17.2. EQUIPO D = 1)
REFINE NIVELACION Y FONDOS M2. 37.8 3.25 122.85 37.8 122.85 100.00% 0 0.00 0.00% 37.800 122.85 100% 0.0 0.00 0.0
34.17.2. COMPACTACION, CON EQUIPO LIVIANO M2. 66.78 17.93 1197.37 66.78 1,197.37 100.00% 0 0.00 0.00% 66.780 1,197.37 100% 0.0 0.00 0.0
44.17.3 CONCRETO SIMPLE 27728.57
4.17.3. CIMIENTO CORRIDO C:H 1.10+30% PIEDRA GRANDE M3. 7.04 279.8 1969.79 7.04 1,969.79 100.00% 0 0.00 0.00% 7.040 1,969.79 100% 0.0 0.00 0.0
14.17.3. CONCRETO FALSO PISO 1:8 CON PIEDRA MEDIANA M3. 66.78 343.27 22923.57 66.78 22,923.57 100.00% 0 0.00 0.00% 66.780 22,923.57 100% 0.0 0.00 0.0
2
4.17.3. CONCRETO 1:8 PARA SOBRECIMIENTO M3. 2.64 293.41 774.6 2.64 774.60 100.00% 0 0.00 0.00% 2.640 774.60 100% 0.0 0.00 0.0
3
4.17.3. ENCOFRADO Y DESENCOFRADO M2. 35.2 58.06 2043.71 35.2 2,043.71 100.00% 0 0.00 0.00% 35.200 2,043.71 100% 0.0 0.00 0.0
44.17.3. CURADO DE CONCRETO M2. 35.2 0.48 16.9 35.2 16.90 99.98% 0 0.00 0.00% 35.200 16.90 100% 0.0 0.00 0.0
54.17.4 PARANTES 1384.2
4.17.4. PARANTES DE TUBO DE PVC 3" VACIADO CON und 12 115.35 1384.2 12 1,384.20 100.00% 0 0.00 0.00% 12.000 1,384.20 100% 0.0 0.00 0.0
14.17.5 CONCRETO
REVOQUES YY ENLUCIDOS
FIERRO 4947
4.17.5. TARRAJEO EXTERIOR E = 1.5 CM MEZCLA 1:2 M2. 132 32.59 4301.88 132 4,301.88 100.00% 0 0.00 0.00% 132.000 4,301.88 100% 0.0 0.00 0.0
14.17.5. BRUÑAS EN TARRAJEO CEMENTO:ARENA m 32 20.16 645.12 32 645.12 100.00% 0 0.00 0.00% 32.000 645.12 100% 0.0 0.00 0.0
2
4.17.6 PISOS Y PAVIMENTOS 295.8
4.17.6. ACABADO Y FROTACHADO DE PISO M2. 60 4.93 295.8 60 295.80 100.00% 0 0.00 0.00% 60.000 295.80 100% 0.0 0.00 0.0
14.17.7 PINTURA 2017.38
4.17.7. PINTURA MUROS EXTERIORES VINILATEX M2. 161.52 12.49 2017.38 161.52 2,017.38 100.00% 0 0.00 0.00% 161.520 2,017.38 100% 0.0 0.00 0.0
14.17.8 COBERTURAS 21870.73
4.17.8. COBERTURA CON PLANCHA ONDULADA FLEXIBLE M2. 112 52.6 5891.2 112 5,891.20 100.00% 0 0.00 0.00% 112.000 5,891.20 100% 0.0 0.00 0.0
14.17.8. DE COLOR PLANCHA ONDULADA FLEXIBLE
CUMBRERA m 20 12.68 253.6 20 253.60 100.00% 0 0.00 0.00% 20.000 253.60 100% 0.0 0.00 0.0
24.17.8. COLOR
TIJERAL DE MADERA PARA ALMACEN und 10 447.78 4477.8 10 4,477.80 100.00% 0 0.00 0.00% 10.000 4,477.80 100% 0.0 0.00 0.0
34.17.8. CORREAS DE MADERA PARA CUBIERTA m 120 48.44 5812.8 120 5,812.80 100.00% 0 0.00 0.00% 120.000 5,812.80 100% 0.0 0.00 0.0
44.17.8. CANALETA DE PLANCHA F°G° INCLUYE m 40 31.22 1248.8 40 1,248.80 100.00% 0 0.00 0.00% 40.000 1,248.80 100% 0.0 0.00 0.0
5
4.17.8. COLOCACION
FALSA COLUNNA PARA MONTANTE DE EVAC DE m 12 165.05 1980.6 12 1,980.60 100.00% 0 0.00 0.00% 12.000 1,980.60 100% 0.0 0.00 0.0
6
4.17.8. AGUAS PLUVIALES
ENCOFRADO Y DESENCOFRADO M2. 7.2 58.06 418.02 7.2 418.03 100.00% 0 0.00 0.00% 7.200 418.03 100% 0.0 0.00 0.0
74.17.8. TUBERIA PARA MONTANTE DE PVC SAL 3" m 32 34.71 1110.72 32 1,110.72 100.00% 0 0.00 0.00% 32.000 1,110.72 100% 0.0 0.00 0.0
8
4.17.8. ACCESORIOS PARA MONTANTE DE PVC SAL DE 3" und 8 36.77 294.16 8 294.16 100.00% 0 0.00 0.00% 8.000 294.16 100% 0.0 0.00 0.0
9
4.17.8. EXCAVACION MANUAL DE ZANJAS PARA TENDIDO M3. 4.8 26.04 124.99 4.8 124.99 100.00% 0 0.00 0.00% 4.800 124.99 100% 0.0 0.00 0.0
10
4.17.8. DE TUBERIA
RELLENO Y COMPACTACION MANUAL DE ZANJAS M3. 4.8 53.76 258.04 4.8 258.05 100.00% 0 0.00 0.00% 4.800 258.05 100% 0.0 0.00 0.0
11
4.17.9 PARA
MUROSTUBERIAS
Y TABIQUES 5334.91
4.17.9. MURO DE BLOQUETAS M2. 48.4 61.38 2970.79 48.4 2,970.79 100.00% 0 0.00 0.00% 48.400 2,970.79 100% 0.0 0.00 0.0
14.17.9. MALLA DE CERRAMIENTO ALMACEN M2. 66 35.82 2364.12 0 0.00 0.00% 66 2,364.12 100.00% 66 2,364.12 100% 66.000 2,364.12 100% 0.0 0.00 0.0
2
4.17.1 CARPINTERIA, VIDRIOS, CERRAJERIA Y PINTURA 1560.88
0
4.17.1 PUERTA DE MADERA und 2 780.44 1560.88 2 1,560.88 100.00% 0 0.00 0.00% 2.000 1,560.88 100% 0.0 0.00 0.0
0.1
4.18 POZA DE ALMACENAMIENTO DE AGUA 6782.15
4.18.1 TRABAJOS PRELIMINARES 65.66
4.18.1. LIMPIEZA DE TERRENO und 14 1.08 15.12 14 15.12 100.00% 0 0.00 0.00% 14.000 15.12 100% 0.0 0.00 0.0
14.18.1. TRAZO NIVELACION Y REPLANTEO PRELIMINAR M2. 14 3.61 50.54 14 50.54 100.00% 0 0.00 0.00% 14.000 50.54 100% 0.0 0.00 0.0
24.18.2 MOVIMIENTO DE TIERRAS 1218.56
4.18.2. ELIMINACION DE MATERIAL EXCEDENTE (CON M3. 26.21 13.51 354.1 26.21 354.10 100.00% 0 0.00 0.00% 26.210 354.10 100% 0.0 0.00 0.0
14.18.2. EQUIPO D = 1)MANUAL HASTA H = 1M
EXCAVACION M3. 20.16 21.7 437.47 20.16 437.47 100.00% 0 0.00 0.00% 20.160 437.47 100% 0.0 0.00 0.0
2
4.18.2. REFINE NIVELACION Y FONDOS M2. 20.16 3.25 65.52 20.16 65.52 100.00% 0 0.00 0.00% 20.160 65.52 100% 0.0 0.00 0.0
3
4.18.2. COMPACTACION, CON EQUIPO LIVIANO M2. 20.16 17.93 361.47 20.16 361.47 100.00% 0 0.00 0.00% 20.160 361.47 100% 0.0 0.00 0.0
44.18.3 CONCRETO SIMPLE 2917.18
4.18.3. CIMIENTO CORRIDO C:H 1.10+30% PIEDRA GRANDE M3. 2.5 279.8 699.5 2.5 699.50 100.00% 0 0.00 0.00% 2.500 699.50 100% 0.0 0.00 0.0
14.18.3. CONCRETO FALSO PISO 1:8 CON PIEDRA MEDIANA M3. 2.8 343.27 961.16 2.8 961.16 100.00% 0 0.00 0.00% 2.800 961.16 100% 0.0 0.00 0.0
2
4.18.3. CONCRETO 1:8 PARA SOBRECIMIENTO M3. 1.17 293.41 343.29 1.17 343.29 100.00% 0 0.00 0.00% 1.170 343.29 100% 0.0 0.00 0.0
3
4.18.3. ENCOFRADO Y DESENCOFRADO M2. 15.6 58.06 905.74 15.6 905.74 100.00% 0 0.00 0.00% 15.600 905.74 100% 0.0 0.00 0.0
44.18.3. CURADO DE CONCRETO M2. 15.6 0.48 7.49 15.6 7.49 99.97% 0 0.00 0.00% 15.600 7.49 100% 0.0 0.00 0.0
54.18.4 REVOQUES Y ENLUCIDOS 1464.27
4.18.4. TARRAJEO EXTERIOR E = 1.5 CM MEZCLA 1:2 M2. 44.93 32.59 1464.27 44.93 1,464.27 100.00% 0 0.00 0.00% 44.930 1,464.27 100% 0.0 0.00 0.0
14.18.5 PISOS Y PAVIMENTOS 69.02
4.18.5. ACABADO Y FROTACHADO DE PISO M2. 14 4.93 69.02 0 0.00 0.00% 14 69.02 100.00% 14 69.02 100% 14.000 69.02 100% 0.0 0.00 0.0
14.18.6 PINTURA 89.93
4.18.6. PINTURA MUROS EXTERIORES VINILATEX M2. 7.2 12.49 89.93 7.2 89.93 100.00% 0 0.00 0.00% 7.200 89.93 100% 0.0 0.00 0.0
14.18.7 MUROS Y TABIQUES 957.53
4.18.7. MURO DE BLOQUETAS M2. 15.6 61.38 957.53 15.6 957.53 100.00% 0 0.00 0.00% 15.600 957.53 100% 0.0 0.00 0.0
14.19 FLETES Y OTROS 50000
4.19.1 TRANSPORTE glb 1 50000 50000 1 50,000.00 100.00% 0 0.00 0.00% 1.000 50,000.00 100% 0.0 0.00 0.0
ACUMULADO ACTUALIZADO SALDO ACTUALIZDO
Item Descripción Unid. Cant. Precio Parcial Sub Total SEP OCT NOV DIC ENE FEBR MAR ABR MAY JUN JUL AGO ACUMULADO SALDO
PRESUPUESTO REFORMULADO PRESUPUESTO REFORMLADO
4.2 TRABAJOS PRELIMINARES 17624.87
4.20.1 CARTEL DE IDENTIFICACION DE LA OBRA DE und 1 1106.9 1106.9 1 1,106.90 100.00% 0 0.00 0.00% 1.000 1,106.90 100% 0.0 0.00 0.0
2.40X3.60M
4.20.2 CONSTRUCCIÓN DE CAMPAMENTO PROVISIONAL m² 150 88.63 13294.5 150 13,294.50 100.00% 0 0.00 0.00% 150.000 13,294.50 100% 0.0 0.00 0.0
DE OBRA
4.20.3 TRAZO Y REPLANTEO DE EJE Y OBRAS DE km 1.46 911.14 1330.26 1.46 1,330.26 100.00% 0 0.00 0.00% 1.460 1,330.26 100% 0.0 0.00 0.0
DRENAJE
4.20.4 ROCE Y LIMPIEZA ha 1.01 1031.79 1042.11 1.01 1,042.11 100.00% 0 0.00 0.00% 1.010 1,042.11 100% 0.0 0.00 0.0
4.20.5 RAYADO DE TALUD km 1.46 308.97 451.1 1.46 451.10 100.00% 0 0.00 0.00% 1.460 451.10 100% 0.0 0.00 0.0
4.20.6 PLACA RECORDATORIA und 1 400 400 0 0.00 0.00% 1 400.00 100.00% 1 400.00 100% 1.000 400.00 100% 0.0 0.00 0.0
4.21 MOVIMIENTO DE TIERRAS 302956.43
4.21.1 CORTE DE MATERIAL SUELTO m³ 24388.95 6.56 159991.51 24388.95 159,991.51 100.00% 0 0.00 0.00% 24,388.950 159,991.51 100% 0.0 0.00 0.0
4.21.2 ELIMINACION DE MATERIAL EXCEDENTE (CON m³ 14709.68 8.53 125473.57 14709.68 125,473.57 100.00% 0 0.00 0.00% 14,709.680 125,473.57 100% 0.0 0.00 0.0
EQUIPO, D=1KM)
4.21.3 RELLENO CON MATERIAL PROPIO m³ 36.95 5.72 211.35 36.95 211.35 100.00% 0 0.00 0.00% 36.950 211.35 100% 0.0 0.00 0.0
4.21.4 BANQUETAS DE CORTE m³ 2880 6 17280 2880 17,280.00 100.00% 0 0.00 0.00% 2,880.000 17,280.00 100% 0.0 0.00 0.0
4.22 PAVIMENTOS 50696.28
4.22.1 PERFILADO Y COMPACTADO DE PLATAFORMAR A m² 5289.5 1.62 8568.99 5289.5 8,568.99 100.00% 0 0.00 0.00% 5,289.500 8,568.99 100% 0.0 0.00 0.0
NIVEL DE SUB-RASANTE
4.22.2 AFIRMADO DE e=0.15M (INCLUYE RIEGO) m² 5289.5 6.83 36127.29 4500 30,735.00 85.07% 790 5,392.29 14.93% 790 5,392.29 15% 5,289.500 36,127.29 100% 0.0 0.00 0.0
4.22.3 ALCANTARILLAS DE ALIVIADEROS glb 5 1200 6000 5 6,000.00 100.00% 0 0.00 0.00% 5.000 6,000.00 100% 0.0 0.00 0.0
4.23 OBRAS DE ARTE Y DRENAJE 8715.8
4.23.1 CUNETAS 2334.4
4.23.1. CONSTRUCCION DE CUNETAS EN MATERIAL m 1459 1.6 2334.4 1459 2,334.40 100.00% 0 0.00 0.00% 1,459.000 2,334.40 100% 0.0 0.00 0.0
14.23.2 ALIVIADEROS(05
COMPACTO UND) 4120.71
4.23.2. TRAZO Y REPLANTEO m² 101.25 1.45 146.81 101.25 146.81 100.00% 0 0.00 0.00% 101.250 146.81 100% 0.0 0.00 0.0
14.23.2. EXCAVACION MANUAL HASTA H=1.00 M m³ 37.12 25.3 939.14 37.12 939.14 100.00% 0 0.00 0.00% 37.120 939.14 100% 0.0 0.00 0.0
24.23.2. MAMPOSTERIA CONCRETO F´C=175 KG/CM2 + m² 51.12 56.67 2896.97 51.12 2,896.97 100.00% 0 0.00 0.00% 51.120 2,896.97 100% 0.0 0.00 0.0
3
4.23.2. 60% PM
EMPEDRADO E=20 CM m² 4.5 30.62 137.79 4.5 137.79 100.00% 0 0.00 0.00% 4.500 137.79 100% 0.0 0.00 0.0
44.23.3 SEÑALIZACIÓN 2260.69
4.23.3. EXCAVACION MANUAL HASTA H=1.00 M m³ 3.2 25.3 80.96 0 0.00 0.00% 3.2 80.96 100.00% 3.2 80.96 #### 3.200 80.96 100% 0.0 0.00 0.0
14.23.3. ENCOFRADO Y DESENCOFRADO m² 0.6 34.37 20.62 0 0.00 0.00% 0.6 20.62 100.01% 0.6 20.62 #### 0.600 20.62 100% 0.0 0.00 0.0
2
4.23.3. CONCRETO F´C=175 Kg/cm2 m³ 3.2 423.95 1356.64 0 0.00 0.00% 3.2 1,356.64 100.00% 3.2 1,356.64 #### 3.200 1,356.64 100% 0.0 0.00 0.0
3
4.23.3. ACERO Ø 3/8" FY=4200 Kg/cm2 kg 20.8 4.53 94.22 0 0.00 0.00% 20.8 94.22 100.00% 21 94.22 #### 20.800 94.22 100% 0.0 0.00 0.0
44.23.3. PANELES (INCLUYE ESTRUCTURA DE SOPORTE) und 3 211.21 633.63 0 0.00 0.00% 3 633.63 100.00% 3 633.63 #### 3.000 633.63 100% 0.0 0.00 0.0
54.23.3. PINTADO DE SEÑALES m² 10.6 7.04 74.62 0 0.00 0.00% 10.6 74.62 100.01% 11 74.62 #### 10.600 74.62 100% 0.0 0.00 0.0
6
4.24 VEREDAS Y ESCALINATAS 71696.75
4.24.1 VEREDA DE CONCRETO DE 4" SOBRE EMPEDRADO M2. 925 77.51 71696.75 925 71,696.75 100.00% 0 0.00 0.00% 925.000 71,696.75 100% 0.0 0.00 0.0
4.25 OBRAS COMPLEMENTARIAS Y DE 24195.65
4.25.1 HORNAMENTACION
FIGURAS DE CONCRETO 5566.64
4.25.1. EXCAVACION MANUAL HASTA H = 1M M3. 2 21.7 43.4 2 43.40 100.00% 0 0.00 0.00% 2.000 43.40 100% 0.0 0.00 0.0
14.25.1. CIMIENTO CORRIDO C:H 1.10+30% PIEDRA GRANDE M3. 2 279.8 559.6 2 559.60 100.00% 0 0.00 0.00% 2.000 559.60 100% 0.0 0.00 0.0
24.25.1. CONCRETO F´C = 175 KG/CM2 M3. 2 550.28 1100.56 2 1,100.56 100.00% 0 0.00 0.00% 2.000 1,100.56 100% 0.0 0.00 0.0
3
4.25.1. ACERO DE REFUERZO FY = 4200 KG/CM2 kg 20 8.03 160.6 20 160.60 100.00% 0 0.00 0.00% 20.000 160.60 100% 0.0 0.00 0.0
44.25.1. ENCOFRADO Y DESENCOFRADO M2. 12 58.06 696.72 12 696.72 100.00% 0 0.00 0.00% 12.000 696.72 100% 0.0 0.00 0.0
54.25.1. CURADO DE CONCRETO M2. 12 0.48 5.76 12 5.76 100.00% 0 0.00 0.00% 12.000 5.76 100% 0.0 0.00 0.0
6
4.25.1. VESTIDURA DE METAL und 2 1500 3000 2 3,000.00 100.00% 0 0.00 0.00% 2.000 3,000.00 100% 0.0 0.00 0.0
74.25.2 LETRAS DE CONCRETO 18629.01
4.25.2. EXCAVACION MANUAL HASTA H = 1M M3. 13.8 21.7 299.46 13.8 299.46 100.00% 0 0.00 0.00% 13.800 299.46 100% 0.0 0.00 0.0
14.25.2. CIMIENTO CORRIDO C:H 1.10+30% PIEDRA GRANDE M3. 13.8 279.8 3861.24 13.8 3,861.24 100.00% 0 0.00 0.00% 13.800 3,861.24 100% 0.0 0.00 0.0
24.25.2. CONCRETO F´C = 175 KG/CM2 M3. 13.8 550.28 7593.86 13.8 7,593.86 100.00% 0 0.00 0.00% 13.800 7,593.86 100% 0.0 0.00 0.0
3
4.25.2. ACERO DE REFUERZO FY = 4200 KG/CM2 kg 115.92 8.03 930.84 115.92 930.84 100.00% 0 0.00 0.00% 115.920 930.84 100% 0.0 0.00 0.0
44.25.2. ENCOFRADO Y DESENCOFRADO M2. 83.87 58.06 4869.7 82.8 4,807.37 98.72% 1.07 62.12 1.28% 1.07 62.12 1% 83.870 4,869.49 100% 0.0 0.00 0.0
54.25.2. CURADO DE CONCRETO M2. 82.8 0.48 39.74 82.8 39.74 100.01% 0 0.00 0.00% 82.800 39.74 100% 0.0 0.00 0.0
6
4.25.2. PINTURA MUROS EXTERIORES VINILATEX M2. 82.8 12.49 1034.17 82.8 1,034.17 100.00% 0 0.00 0.00% 82.800 1,034.17 100% 0.0 0.00 0.0
74.26 PROTECCION DE MEDIO AMBIENTE 8972.9
4.26.1 CONFORMACION Y CONTROL EROSIVO DE m³ 14709.68 0.61 8972.9 14709.68 8,972.90 100.00% 0 0.00 0.00% 14,709.680 8,972.90 100% 0.0 0.00 0.0
BOTADEROS
4.27 REFORESTACION 24123
4.27.1 REFORESTACION m² 5100 4.73 24123 5100 24,123.00 100.00% 0 0.00 0.00% 5,100.000 24,123.00 100% 0.0 0.00 0.0
4.28 GERENCIA ESPECIALIZADA EN EL SERVICIO 21700
4.28.1 GERENCIA ESPECIALIZADA EN EL SERVICIO glb 1 21700 21700 1 21,700.00 100.00% 0 0.00 0.00% 1.000 21,700.00 100% 0.0 0.00 0.0
4.29 SUPERVISION Y MONITOREO DEL SERVICIO 20820
4.29.1 SUPERVISION Y MONITOREO DEL SERVICIO glb 1 20820 20820 1 20,820.00 100.00% 0 0.00 0.00% 1.000 20,820.00 100% 0.0 0.00 0.0
4.3 FORMALIZACION DE RELLENO SANITARIO 31000
4.30.1 SERVICIO DE FORMALIZACION DE RELLENO glb 1 31000 31000 0 0.00 0.00% 1 31,000.00 100.00% 100% 31000.00 0% 1.000 31,000.00 100% 0.0 0.00 0.0
4.3 SANITARIODE COSTEO DE LOS SERVICIOS,
SISTEMA 97440
4.30.1 DETERMINACION DE ARBITRIOS
SISTEMA DE COSTEO COBRANZAS Y
DE LOS SERVICIOS, glb 1 97440 97440 1 97,440.00 100.00% 0 0.00 0.00% 1.000 97,440.00 100% 0.0 0.00 0.0
4.31 DETERMINACION DE ARBITRIOS COBRANZAS
FLETE 2177.46
4.31.1 FLETE TERRESTRE (CUSCO - OBRA) kg 8374.84 0.26 2177.46 8374.84 2,177.46 100.00% 0 0.00 0.00% 8,374.840 2,177.46 100% 0.0 0.00 0.0
4.32 INGRESO PRINCIPAL 13821.78
4.32.1 CONCRETO ARMADO 5821.78
4.32.1. CONCRETO F´C = 175 KG/CM2 M3. 3.5 550.28 1925.98 0 0.00 0.00% 3.5 1,925.98 100.00% 3.5 1,925.98 100% 3.500 1,925.98 100% 0.0 0.00 0.0
14.32.1. ACERO DE REFUERZO FY = 4200 KG/CM2 kg 230 8.03 1846.9 0 0.00 0.00% 230 1,846.90 100.00% 230 1,846.90 100% 230.000 1,846.90 100% 0.0 0.00 0.0
24.32.1. ENCOFRADO Y DESENCOFRADO M2. 35 58.06 2032.1 0 0.00 0.00% 35 2,032.10 100.00% 35 2,032.10 100% 35.000 2,032.10 100% 0.0 0.00 0.0
3
4.32.1. CURADO DE CONCRETO M2. 35 0.48 16.8 0 0.00 0.00% 35 16.80 100.00% 35 16.80 100% 35.000 16.80 100% 0.0 0.00 0.0
44.32.2 CUBIERTA DE INGRESO PRINCIPAL 3000
4.32.2. CUBIERTA DE INGRESO PRINCIPAL und 1 3000 3000 0 0.00 0.00% 1 3,000.00 100.00% 1 3,000.00 100% 1.000 3,000.00 100% 0.0 0.00 0.0
14.32.3 PORTON METALICO 5000
4.32.3. PORTON METALICO DE INGRESO und 1 5000 5000 0 0.00 0.00% 1 5,000.00 100.00% 1 5,000.00 100% 1.000 5,000.00 100% 0.0 0.00 0.0
1 I. COSTO DIRECTO ############ 3,944,758.39 100.0% 3,251,103.26 82.42% 693,655.13 17.58% 2408.99 77,421.75 181,455.24 54,237.21 16,777.81 306,304.29 24048.8 31000.00 3,944,758.39 0.00
I.I GASTOS GENERALES 17.78% 701,210.04 577907.70 123302.34 428.22 13762.29 32255.01 9641.07 2982.38 54448.05 4274.8 5510.48 701210.04 0.00
I.II SUPERVISIÓN 6.04% 238,226.96 196336.60 41890.36 145.48 4675.56 10958.22 3275.43 1013.22 18498.01 1452.3 1872.11 238226.96 0.00
I.III EXPEDIENTE TECNICO 2.52% 99,273.26 99273.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0 0.0 99273.26 0.00
I.IV LIQUIDACION 0.52% 20,552.50 20552.50 0.00 0.00 0.00 0.00 0.00 0.00 0.0 0.0 0.00 20552.50
II. COSTO INDIRECTO 1,059,262.76 100.0% 873517.56 82.46% 185745.20 17.54% 573.70 18437.85 43213.23 12916.49 3995.61 72946.06 5727.2 7382.59 1038710.26 20552.50
PRESUPUESTO TOTAL 5,004,021.15 100.0% 4,124,620.820 82.43% 879,400.325 17.57% 2982.68 95,859.597 224,668.479 67,153.705 20,773.417 ########### 29775.9 38382.59 4,983,468.645 20552.50