ITEM DESCRIPCIÓN UNIDAD METRADO PRECIO (S/.) (S/.) AL


100%

01 LOCALIDAD SANTA LUCIA


01.01 CONSTRUCCIONES PROVISIONALES
01.01.01 OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y VESTUARIOS m2 100.00 44.55 4,455.00
01.01.02 ALQUILER DE PREDIOS PARA CAMPAMENTOS Y ALMACENES mes 6.00 500.00 3,000.00
01.01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20 m und 1.00 1,539.82 1,539.82
01.02 CAPTACION TIPO LADERA (ROBLEMONTE)
01.02.01 TRABAJOS PRELIMINARES
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49 24.01
01.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
01.02.02 MOVIMIENTO DE TIERRAS
01.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 16.23 39.86 646.93
01.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO C/PISON m3 2.55 29.50 75.23
01.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95 214.65
01.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 17.10 25.69 439.30
01.02.03 CONCRETO SIMPLE
01.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17 706.52
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48 117.43
01.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55
01.02.04 CONCRETO ARMADO
01.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84 811.87
01.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48 797.53
01.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35 296.06
01.02.05 REVOQUES Y ENLUCIDOS
01.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3 e=1.5cm m2 5.53 32.48 179.61
01.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76 358.61
01.02.06 PINTURA
01.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 13.23 159.42
01.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
01.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85 265.53
01.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77 25.86
01.02.08 CARPINTERIA METALICA
01.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 179.83 179.83
01.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53 281.53
01.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO HIDRAULICO y VENTILACION
01.02.09.01 und 1.00 501.29 501.29
Ø=2")
01.02.10 CERCO PERIMETRICO EN CAPTACION
01.02.10.01 TRABAJOS PRELIMINARES
01.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84 44.16
01.02.10.02 MOVIMIENTO DE TIERRAS
01.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86 23.52
01.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
01.02.10.03 CONCRETO SIMPLE
01.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98 210.03
01.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
01.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
01.02.10.05 COLOCADO DE ROLLIZOS
01.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
01.02.10.06 PINTURA EN CERCO PERIMETRICO
01.02.10.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 33.80 3.80 128.44
01.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
01.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22 533.28
01.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
01.02.10.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10
01.03 LINEA DE CONDUCCION (L=1102.00 m)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,102.00 0.49 539.98
01.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 1,102.00 1.53 1,686.06
01.03.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 1,102.00 1.53 1,686.06
01.03.02 MOVIMIENTO DE TIERRAS
01.03.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 396.72 49.82 19,764.59
01.03.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 44.08 55.80 2,459.66
01.03.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 1,102.00 1.81 1,994.62
01.03.02.04 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 110.20 6.08 670.02
01.03.02.05 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 165.30 36.40 6,016.92
01.03.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.50 m m3 27.55 65.17 1,795.43
01.03.02.07 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 27.55 25.69 707.76
01.03.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SP C-10, Ø=1" m 1,102.00 7.19 7,923.38
01.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 140.33 140.33
01.03.04 PRUEBA HIDRAULICA
01.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 1,102.00 1.51 1,664.02
01.03.05 CAMARA ROMPE PRESION T-6 (01 UND)
01.03.05.01 OBRAS PRELIMINARES
01.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.44 0.49 0.71
01.03.05.01.02 TRAZO Y REPLANTEO m2 1.44 1.84 2.65
01.03.05.02 MOVIMIENTO DE TIERRAS
01.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.58 39.86 62.98
01.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.98 25.69 50.87
01.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 1.44 7.95 11.45
01.03.05.03 OBRAS DE CONCRETO SIMPLE
01.03.05.03.01 SOLADO E=4" m3 1.21 35.81 43.33
01.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13
01.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90
01.03.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55
01.03.05.04 OBRAS DE CONCRETO ARMADO
01.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 0.79 546.69 431.89
01.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.10 44.48 360.29
01.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 37.23 4.35 161.95
01.03.05.05 REVOQUES Y ENLUCIDOS
01.03.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 2.52 32.48 81.85
01.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.24 29.76 96.42
01.03.05.06 PINTURA
01.03.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 3.24 11.18 36.22
01.03.05.07 CARPINTERIA METALICA
01.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 1.00 213.73 213.73
01.03.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.03.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T6, INGRESO Ø=1" y SALIDA Ø=1" und 1.00 299.60 299.60
01.03.06 VALVULA DE PURGA TIPO I (1 UND)
01.03.06.01 OBRAS PRELIMINARES
01.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 0.49 0.49
01.03.06.01.02 TRAZO Y REPLANTEO m2 1.00 1.84 1.84
01.03.06.02 MOVIMIENTO DE TIERRAS
01.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.51 39.86 20.33
01.03.06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 0.51 13.11 6.69
01.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.49 7.95 3.90
01.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 0.64 25.69 16.44
01.03.06.03 OBRAS DE CONCRETO SIMPLE
01.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.02 413.17 8.26
01.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.24 44.48 10.68
01.03.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.27 121.10 32.70
01.03.06.04 OBRAS DE CONCRETO ARMADO
01.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.35 546.69 191.34
01.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.72 44.48 165.47
01.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 14.94 4.35 64.99
01.03.06.05 REVOQUES Y ENLUCIDOS
01.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 1.44 32.48 46.77
01.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.36 29.76 99.99
01.03.06.06 PINTURA
01.03.06.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 2.16 11.18 24.15
01.03.06.07 CARPINTERIA METALICA
01.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 1.00 214.83 214.83
01.03.06.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.03.06.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO I, Ø=1" und 1.00 153.06 153.06
01.04 RESERVORIO (V=8.00 m3, 01 UND)
01.04.01 OBRAS PRELIMINARES
01.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49 17.64
01.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
01.04.02 MOVIMIENTO DE TIERRAS
01.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 51.43 39.86 2,050.00
01.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 11.41 7.95 90.71
01.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 64.29 25.69 1,651.61
01.04.03 CONCRETO SIMPLE
01.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13
01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90
01.04.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55
01.04.04 OBRAS DE CONCRETO ARMADO
01.04.04.01 SOLADO PARA LOSA FONDO m2 11.41 40.87 466.33
01.04.04.02 CONCRETO f'c=210 kg/cm2 m3 11.27 546.69 6,161.20
01.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 51.29 44.48 2,281.38
01.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 322.94 4.35 1,404.79
01.04.05 REVOQUES Y ENLUCIDOS
01.04.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 31.32 32.48 1,017.27
01.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 40.61 29.76 1,208.55
01.04.06 PINTURA
01.04.06.01 PINTURA ESMALTE EN MUROS EXTERIORES DE RESERVORIO m2 34.92 13.23 461.99
01.04.07 CARPINTERIA METALICA
01.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46
01.04.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.04.08.01 SUMINISTRO E INSTALACIONES DE ACCESORIOS EN RESERVORIO (ING. 1 ", SAL.1") und 1.00 1,745.47 1,745.47
01.04.09 CERCO PERIMETRICO EN RESERVORIO
01.04.09.01 TRABAJOS PRELIMINARES
01.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84 66.24
01.04.09.02 MOVIMIENTO DE TIERRAS
01.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86 27.90
01.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
01.04.09.03 CONCRETO SIMPLE
01.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98 249.19
01.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
01.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
01.04.09.05 COLOCADO DE ROLLIZOS
01.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
01.04.09.06 PINTURA EN CERCO PERIMETRICO
01.04.09.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 66.40 3.80 252.32
01.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
01.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22 515.50
01.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
01.04.09.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10
01.04.10 CLORADOR POR GOTEO
01.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
01.04.10.01.01 CASETA DE MURO DE LADRILLO -CLORADOR POR GOTEO
01.04.10.01.01.0
MURO DE LADRILLO PANDERETA (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 7.52 54.96 413.30
1
01.04.10.01.01.0
MURO DE LADRILLO PANDERETA INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 4.48 49.36 221.13
2
01.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
01.04.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 29.07 174.42
1
01.04.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 34.08 203.80
2
01.04.10.01.03 REVOQUES Y ENLUCIDOS
01.04.10.01.03.0
TARRAJEO MUROS DE INTERIORES Y EXTERIORES, CEMENTO : ARENA, 1:5 m2 14.98 30.00 449.40
1
01.04.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.78 55.12
2
01.04.10.01.04 CARPINTERIA METALICA
01.04.10.01.04.0
SUMINISTRO E INSTALACION DE PUERTA METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO und 1.00 367.18 367.18
1
01.04.10.01.05 PINTURAS
01.04.10.01.05.0
PINTURA ESMALTE EN MUROS INTERIORES Y EXTERIORES m2 14.98 11.18 167.48
1
01.04.10.01.05.0
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 12.25 49.00
2
01.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
01.04.10.02.01 SUMINISTRO E INSTALACION DE TANQUE DE POLIETILENO, CAP=250 LTRS. und 1.00 435.06 435.06
01.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
01.04.10.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS Y ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO GLB 1.00 939.22 939.22
01.05 RED DE ADUCCION Y DISTRIBUCION (L=4,375.00m)
01.05.01 TRABAJOS PRELIMINARES
01.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,187.50 0.49 1,071.88
01.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 4,375.00 1.53 6,693.75
01.05.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 4,375.00 1.53 6,693.75
01.05.02 MOVIMIENTO DE TIERRAS
01.05.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 525.00 39.86 20,926.50
01.05.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 1,137.50 49.82 56,670.25
01.05.02.03 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 87.50 55.80 4,882.50
01.05.02.04 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 4,375.00 1.81 7,918.75
01.05.02.05 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 4,375.00 6.08 26,600.00
01.05.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 623.44 36.40 22,693.22
01.05.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 32.81 65.17 2,138.23
01.05.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 1,181.25 25.07 29,613.94
01.05.02.09 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 142.19 62.16 8,838.53
01.05.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 87.50 25.69 2,247.88
01.05.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 1,820.00 8.05 14,651.00
01.05.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 3/4" m 2,555.00 4.84 12,366.20
01.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 137.74 137.74
01.05.04 PRUEBA HIDRAULICA
01.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 4,375.00 1.51 6,606.25
01.05.05 CAMARA ROMPE PRESION T-7 (11 UND)
01.05.05.01 OBRAS PRELIMINARES
01.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 22.77 0.49 11.16
01.05.05.01.02 TRAZO Y REPLANTEO m2 22.77 1.84 41.90
01.05.05.02 MOVIMIENTO DE TIERRAS
01.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 14.32 39.86 570.80
01.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 9.55 40.95 391.07
01.05.05.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 2.39 13.11 31.33
01.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 21.62 7.95 171.88
01.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.28 59.44 76.08
01.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 9.84 25.69 252.79
01.05.05.03 OBRAS DE CONCRETO SIMPLE
01.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.13 413.17 53.71
01.05.05.03.02 SOLADO E=4" m3 1.82 35.81 65.17
01.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.20 44.48 97.86
01.05.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 2.97 121.10 359.67
01.05.05.04 OBRAS DE CONCRETO ARMADO
01.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 14.96 546.69 8,178.48
01.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 153.14 44.48 6,811.67
01.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,164.62 4.35 9,416.10
01.05.05.05 REVOQUES Y ENLUCIDOS
01.05.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 47.52 32.48 1,543.45
01.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 102.98 29.76 3,064.68
01.05.05.06 PINTURA
01.05.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 66.00 11.18 737.88
01.05.05.07 CARPINTERIA METALICA
01.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 11.00 179.83 1,978.13
01.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 11.00 213.73 2,351.03
01.05.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=1" und 7.00 384.08 2,688.56
01.05.05.08.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=3/4" und 5.00 379.18 1,895.90
01.05.06 VALVULA DE CONTROL (05 UND)
01.05.06.01 OBRAS PRELIMINARES
01.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49 2.45
01.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.84 9.20
01.05.06.02 MOVIMIENTO DE TIERRAS
01.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 39.86 199.30
01.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 25.69 160.56
01.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.95 39.75
01.05.06.03 OBRAS DE CONCRETO ARMADO
01.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 546.69 1,350.32
01.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 44.48 947.42
01.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.35 668.94
01.05.06.04 REVOQUES Y ENLUCIDOS
01.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 32.48 233.86
01.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 29.76 321.41
01.05.06.05 PINTURA
01.05.06.05.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 6.48 11.18 72.45
01.05.06.06 CARPINTERIA METALICA
01.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 162.88 814.40
01.05.06.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=1" und 1.00 90.28 90.28
01.05.06.07.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=3/4" und 4.00 79.02 316.08
01.05.07 VALVULA DE PURGA TIPO II (08 UND)
01.05.07.01 OBRAS PRELIMINARES
01.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.00 0.49 3.92
01.05.07.01.02 TRAZO Y REPLANTEO m2 8.00 1.84 14.72
01.05.07.02 MOVIMIENTO DE TIERRAS
01.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 12.23 39.86 487.49
01.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 4.08 49.82 203.27
01.05.07.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 4.08 13.11 53.49
01.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 3.92 7.95 31.16
01.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.92 25.69 100.70
01.05.07.03 OBRAS DE CONCRETO SIMPLE
01.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 2.45 413.17 1,012.27
01.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.92 44.48 85.40
01.05.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 1.02 121.10 123.52
01.05.07.04 OBRAS DE CONCRETO ARMADO
01.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 2.80 546.69 1,530.73
01.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 29.76 44.48 1,323.72
01.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 119.53 4.35 519.96
01.05.07.05 REVOQUES Y ENLUCIDOS
01.05.07.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 11.52 32.48 374.17
01.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 26.88 29.76 799.95
01.05.07.06 PINTURA
01.05.07.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 12.96 11.18 144.89
01.05.07.07 CARPINTERIA METALICA
01.05.07.07.01 MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE 0.60x0.40m. und 8.00 213.73 1,709.84
01.05.07.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.07.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=1" und 1.00 149.25 149.25
01.05.07.08.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4" und 7.00 132.94 930.58
01.05.08 CONEXIONES DOMICILIARIAS (92 UND)
01.05.08.01 OBRAS PRELIMINARES
01.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 824.32 0.49 403.92
01.05.08.01.02 TRAZO Y REPLANTEO m2 1,236.48 1.84 2,275.12
01.05.08.02 MOVIMIENTO DE TIERRAS
01.05.08.02.01 EXCAVACION A MANO DE ZANJA MANUAL TERRENO NORMAL m3 989.18 39.86 39,428.71
01.05.08.02.02 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO CLASIFICADO m3 989.18 33.00 32,642.94
01.05.08.02.03 SUMINISTRO Y COLOCACION DE GRAVA SELECCIONADA m3 103.04 209.11 21,546.69
01.05.08.03 OBRAS DE CONCRETO SIMPLE
01.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 6.82 413.17 2,817.82
01.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 34.04 44.48 1,514.10
01.05.08.04 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND) und 92.00 80.77 7,430.84
01.05.08.04.02 TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON LLAVE TIPO BUJIA und 92.00 155.21 14,279.32
01.05.08.04.03 SUMINISTRO E INSTALACIONES DE ACOMETIDA DOMICILIARIA RANGO 2 - 50 M. m 736.00 3.50 2,576.00
02 LOCALIDAD PUEBLO LIBRE
02.01 CONSTRUCCIONES PROVISIONALES
02.01.01 OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y VESTUARIOS m2 100.00 44.55 4,455.00
02.01.02 ALQUILER DE PREDIOS PARA CAMPAMENTOS Y ALMACENES mes 6.00 500.00 3,000.00
02.01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20 m und 1.00 1,539.82 1,539.82
02.02 CAPTACION TIPO LADERA (YACUPACCARI)
02.02.01 TRABAJOS PRELIMINARES
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49 24.01
02.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 22.53 39.86 898.05
02.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO C/PISON m3 2.55 29.50 75.23
02.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95 214.65
02.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 25.05 25.69 643.53
02.02.03 CONCRETO SIMPLE
02.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17 706.52
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48 117.43
02.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55
02.02.04 CONCRETO ARMADO
02.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84 811.87
02.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48 797.53
02.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35 296.06
02.02.05 REVOQUES Y ENLUCIDOS
02.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3 e=1.5cm m2 5.53 32.48 179.61
02.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76 358.61
02.02.06 PINTURA
02.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 13.23 159.42
02.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
02.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85 265.53
02.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77 25.86
02.02.08 CARPINTERIA METALICA
02.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 180.93 180.93
02.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53 281.53
02.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO HIDRAULICO y VENTILACION
02.02.09.01 und 1.00 501.29 501.29
Ø=2"
02.02.10 CERCO PERIMETRICO EN CAPTACION
02.02.10.01 TRABAJOS PRELIMINARES
02.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84 44.16
02.02.10.02 MOVIMIENTO DE TIERRAS
02.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86 23.52
02.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
02.02.10.03 CONCRETO SIMPLE
02.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98 210.03
02.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
02.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
02.02.10.05 COLOCADO DE ROLLIZOS
02.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
02.02.10.06 PINTURA EN CERCO PERIMETRICO
02.02.10.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 33.80 3.80 128.44
02.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
02.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22 533.28
02.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
02.02.10.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10
02.03 CRUCE AEREO DE L=6.00 ML. (01 UNIDAD)
02.03.01 OBRAS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 22.40 0.49 10.98
02.03.01.02 TRAZO Y REPLANTEO m2 22.40 1.84 41.22
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION A MANO TERRENO NORMAL m3 2.57 39.86 102.44
02.03.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.21 25.69 82.46
02.03.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 3.28 7.95 26.08
02.03.03 OBRAS DE CONCRETO SIMPLE
02.03.03.01 CONCRETO F'C=100 KG/CM2.PARA SOLADOS m3 0.13 403.78 52.49
02.03.04 OBRAS DE CONCRETO ARMADO
02.03.04.01 CONCRETO FC=210 KG/CM2 m3 2.72 466.07 1,267.71
02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.50 44.48 111.20
02.03.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 40.12 4.35 174.52
02.03.05 REVOQUES Y ENLUCIDOS
02.03.05.01 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 2.50 29.76 74.40
02.03.06 PINTURA
02.03.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 2.50 19.51 48.78
02.03.07 TUBERIA TN ISO 65 SERIE LIVIANA (L)
02.03.07.01 SUMINISTRO E INSTALACION DE TUBERIA TN ISO 65 Ø 1" m 11.70 312.13 3,651.92
02.03.08 CABLE DE ACERO PRINCIPAL Ø 3/8" TIPO BOA
02.03.08.01 TENDIDO DE CABLE PRINCIPAL TIPO BOA Ø 3/8 m 7.86 37.33 293.41
02.03.09 PENDOLAS
02.03.09.01 PENDOLAS CON F° LISO Ø 1/4" m 14.40 35.37 509.33
02.03.10 ACCESORIOS
02.03.10.01 ACCESORIOS PARA ACUEDUCTO COLGANTE, ARGOLLA Ø 1", L=6.00ml und 1.00 934.94 934.94
02.04 LINEA DE CONDUCCION (L=2153.00 m)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,153.00 0.49 1,054.97
02.04.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 2,153.00 1.53 3,294.09
02.04.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 2,153.00 1.53 3,294.09
02.04.02 MOVIMIENTO DE TIERRAS
02.04.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 86.12 39.86 3,432.74
02.04.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 775.08 49.82 38,614.49
02.04.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 2,153.00 1.81 3,896.93
02.04.02.04 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 2,153.00 4.28 9,214.84
02.04.02.05 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 322.95 36.40 11,755.38
02.04.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 538.25 25.07 13,493.93
02.04.02.07 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 26.91 25.69 691.32
02.04.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.04.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 2,153.00 5.94 12,788.82
02.04.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 215.53 215.53
02.04.04 PRUEBA HIDRAULICA
02.04.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 2,153.00 1.51 3,251.03
02.04.05 CAMARA ROMPE PRESION T-6 (06 UND)
02.04.05.01 OBRAS PRELIMINARES
02.04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.64 0.49 4.23
02.04.05.01.02 TRAZO Y REPLANTEO m2 8.64 1.84 15.90
02.04.05.02 MOVIMIENTO DE TIERRAS
02.04.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 9.50 39.86 378.67
02.04.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.88 25.69 305.20
02.04.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 8.64 7.95 68.69
02.04.05.03 OBRAS DE CONCRETO SIMPLE
02.04.05.03.01 SOLADO E=4" m3 7.26 35.81 259.98
02.04.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.07 413.17 28.92
02.04.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 44.48 53.38
02.04.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 3.00 121.10 363.30
02.04.05.04 OBRAS DE CONCRETO ARMADO
02.04.05.04.01 CONCRETO f'c=210 kg/cm2 m3 4.74 546.69 2,591.31
02.04.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 48.60 44.48 2,161.73
02.04.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 223.37 4.35 971.66
02.04.05.05 REVOQUES Y ENLUCIDOS
02.04.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 15.12 32.48 491.10
02.04.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 19.44 29.76 578.53
02.04.05.06 PINTURA
02.04.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 19.44 11.18 217.34
02.04.05.07 CARPINTERIA METALICA
02.04.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 6.00 213.73 1,282.38
02.04.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.04.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T6, INGRESO Ø=1 1/2" y SALIDA Ø=1 1/2" und 6.00 299.60 1,797.60
02.04.06 VALVULA DE PURGA TIPO I (2 UND)
02.04.06.01 OBRAS PRELIMINARES
02.04.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.00 0.49 0.98
02.04.06.01.02 TRAZO Y REPLANTEO m2 2.00 1.84 3.68
02.04.06.02 MOVIMIENTO DE TIERRAS
02.04.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.02 39.86 40.66
02.04.06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 1.02 13.11 13.37
02.04.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.98 7.95 7.79
02.04.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1.27 25.69 32.63
02.04.06.03 OBRAS DE CONCRETO SIMPLE
02.04.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.04 413.17 16.53
02.04.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.48 44.48 21.35
02.04.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.54 121.10 65.39
02.04.06.04 OBRAS DE CONCRETO ARMADO
02.04.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.70 546.69 382.68
02.04.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.44 44.48 330.93
02.04.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 29.88 4.35 129.98
02.04.06.05 REVOQUES Y ENLUCIDOS
02.04.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 2.88 32.48 93.54
02.04.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.72 29.76 199.99
02.04.06.06 PINTURA
02.04.06.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 4.32 11.18 48.30
02.04.06.07 CARPINTERIA METALICA
02.04.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 2.00 214.83 429.66
02.04.06.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.04.06.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO I, Ø=1 1/2" und 2.00 153.06 306.12
02.05 RESERVORIO (V=10.00 m3, 01 UND)
02.05.01 OBRAS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49 17.64
02.05.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 79.30 39.86 3,160.90
02.05.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 11.41 7.95 90.71
02.05.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 99.13 25.69 2,546.65
02.05.03 CONCRETO SIMPLE
02.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13
02.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90
02.05.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 SOLADO PARA LOSA FONDO m2 11.41 40.87 466.33
02.05.04.02 CONCRETO f'c=210 kg/cm2 m3 13.50 546.69 7,380.32
02.05.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 57.48 44.48 2,556.71
02.05.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 349.49 4.35 1,520.28
02.05.05 REVOQUES Y ENLUCIDOS
02.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 32.94 32.48 1,069.89
02.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 57.14 29.76 1,700.49
02.05.06 PINTURA
02.05.06.01 PINTURA ESMALTE EN MUROS EXTERIORES DE RESERVORIO m2 51.45 13.23 680.68
02.05.07 CARPINTERIA METALICA
02.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46
02.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.05.08.01 SUMINISTRO E INSTALACIONES DE ACCESORIOS EN RESERVORIO (ING. 1", SAL.1") und 1.00 1,745.47 1,745.47
02.05.09 CERCO PERIMETRICO EN RESERVORIO
02.05.09.01 TRABAJOS PRELIMINARES
02.05.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84 66.24
02.05.09.02 MOVIMIENTO DE TIERRAS
02.05.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86 27.90
02.05.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
02.05.09.03 CONCRETO SIMPLE
02.05.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98 249.19
02.05.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
02.05.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
02.05.09.05 COLOCADO DE ROLLIZOS
02.05.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
02.05.09.06 PINTURA EN CERCO PERIMETRICO
02.05.09.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 66.40 3.80 252.32
02.05.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
02.05.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22 515.50
02.05.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
02.05.09.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10
02.05.10 CLORADOR POR GOTEO
02.05.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
02.05.10.01.01 CASETA DE MURO DE LADRILLO -CLORADOR POR GOTEO
02.05.10.01.01.0
MURO DE LADRILLO PANDERETA (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 7.52 54.96 413.30
1
02.05.10.01.01.0
MURO DE LADRILLO PANDERETA INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 4.48 49.36 221.13
2
02.05.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
02.05.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 29.07 174.42
1
02.05.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 34.08 203.80
2
02.05.10.01.03 REVOQUES Y ENLUCIDOS
02.05.10.01.03.0
TARRAJEO MUROS DE INTERIORES Y EXTERIORES, CEMENTO : ARENA, 1:5 m2 14.98 30.00 449.40
1
02.05.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.78 55.12
2
02.05.10.01.04 CARPINTERIA METALICA
02.05.10.01.04.0
SUMINISTRO E INSTALACION DE PUERTA METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO und 1.00 367.18 367.18
1
02.05.10.01.05 PINTURAS
02.05.10.01.05.0
PINTURA ESMALTE EN MUROS INTERIORES Y EXTERIORES m2 14.98 11.18 167.48
1
02.05.10.01.05.0
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 12.25 49.00
2
02.05.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
02.05.10.02.01 SUMINISTRO E INSTALACION DE TANQUE DE POLIETILENO, CAP=250 LTRS. und 1.00 435.06 435.06
02.05.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
02.05.10.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS Y ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO GLB 1.00 939.22 939.22
02.06 RED DE ADUCCION Y DISTRIBUCION (L=5,678.00 m)
02.06.01 TRABAJOS PRELIMINARES
02.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,839.00 0.49 1,391.11
02.06.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 5,678.00 1.53 8,687.34
02.06.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 5,678.00 1.53 8,687.34
02.06.02 MOVIMIENTO DE TIERRAS
02.06.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 1,362.72 49.82 67,890.71
02.06.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 908.48 55.80 50,693.18
02.06.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 5,678.00 1.81 10,277.18
02.06.02.04 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 2,271.20 6.08 13,808.90
02.06.02.05 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 511.02 36.40 18,601.13
02.06.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 567.80 65.17 37,003.53
02.06.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 1,987.30 25.07 49,821.61
02.06.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 1,135.60 62.16 70,588.90
02.06.02.09 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 567.80 25.69 14,586.78
02.06.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 1,146.00 8.05 9,225.30
02.06.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 3/4" m 4,533.00 4.84 21,939.72
02.06.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 351.43 351.43
02.06.04 PRUEBA HIDRAULICA
02.06.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 5,678.00 1.51 8,573.78
02.06.05 CAMARA ROMPE PRESION T-7 (16 UND)
02.06.05.01 OBRAS PRELIMINARES
02.06.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 33.12 0.49 16.23
02.06.05.01.02 TRAZO Y REPLANTEO m2 33.12 1.84 60.94
02.06.05.02 MOVIMIENTO DE TIERRAS
02.06.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 22.91 39.86 913.19
02.06.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 15.27 40.95 625.31
02.06.05.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 3.82 13.11 50.08
02.06.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 31.44 7.95 249.95
02.06.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.86 59.44 110.56
02.06.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 22.91 25.69 588.56
02.06.05.03 OBRAS DE CONCRETO SIMPLE
02.06.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.19 413.17 78.50
02.06.05.03.02 SOLADO E=4" m3 2.64 35.81 94.54
02.06.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.20 44.48 142.34
02.06.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 4.32 121.10 523.15
02.06.05.04 OBRAS DE CONCRETO ARMADO
02.06.05.04.01 CONCRETO f'c=210 kg/cm2 m3 21.74 546.69 11,885.04
02.06.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 222.76 44.48 9,908.36
02.06.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 3,148.54 4.35 13,696.15
02.06.05.05 REVOQUES Y ENLUCIDOS
02.06.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 69.12 32.48 2,245.02
02.06.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 149.79 29.76 4,457.75
02.06.05.06 PINTURA
02.06.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 96.00 11.18 1,073.28
02.06.05.07 CARPINTERIA METALICA
02.06.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 16.00 179.83 2,877.28
02.06.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 16.00 213.73 3,419.68
02.06.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=1" und 3.00 384.08 1,152.24
02.06.05.08.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=3/4" und 13.00 379.18 4,929.34
02.06.06 VALVULA DE CONTROL (05 UND)
02.06.06.01 OBRAS PRELIMINARES
02.06.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.00 0.49 2.94
02.06.06.01.02 TRAZO Y REPLANTEO m2 6.00 1.84 11.04
02.06.06.02 MOVIMIENTO DE TIERRAS
02.06.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 6.00 39.86 239.16
02.06.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 7.50 25.69 192.68
02.06.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 6.00 7.95 47.70
02.06.06.03 OBRAS DE CONCRETO ARMADO
02.06.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.96 546.69 1,618.20
02.06.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 25.56 44.48 1,136.91
02.06.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 184.53 4.35 802.71
02.06.06.04 REVOQUES Y ENLUCIDOS
02.06.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 8.64 32.48 280.63
02.06.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 12.96 29.76 385.69
02.06.06.05 PINTURA
02.06.06.05.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 12.96 11.18 144.89
02.06.06.06 CARPINTERIA METALICA
02.06.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 6.00 162.88 977.28
02.06.06.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=1" und 2.00 90.28 180.56
02.06.06.07.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=3/4" und 4.00 79.02 316.08
02.06.07 VALVULA DE PURGA TIPO II (03 UND)
02.06.07.01 OBRAS PRELIMINARES
02.06.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 3.00 0.49 1.47
02.06.07.01.02 TRAZO Y REPLANTEO m2 3.00 1.84 5.52
02.06.07.02 MOVIMIENTO DE TIERRAS
02.06.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 4.59 39.86 182.96
02.06.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 1.53 49.82 76.22
02.06.07.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 1.53 13.11 20.06
02.06.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 1.47 7.95 11.69
02.06.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.47 25.69 37.76
02.06.07.03 OBRAS DE CONCRETO SIMPLE
02.06.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.92 413.17 380.12
02.06.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.72 44.48 32.03
02.06.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.38 121.10 46.02
02.06.07.04 OBRAS DE CONCRETO ARMADO
02.06.07.04.01 CONCRETO f'c=210 kg/cm2 m3 1.05 546.69 574.02
02.06.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 11.16 44.48 496.40
02.06.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 44.82 4.35 194.97
02.06.07.05 REVOQUES Y ENLUCIDOS
02.06.07.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 4.32 32.48 140.31
02.06.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.08 29.76 299.98
02.06.07.06 PINTURA
02.06.07.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 4.84 11.18 54.11
02.06.07.07 CARPINTERIA METALICA
02.06.07.07.01 MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE 0.60x0.40m. und 3.00 213.73 641.19
02.06.07.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.07.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4" und 3.00 132.94 398.82
02.06.08 CONEXIONES DOMICILIARIAS (125 UND)
02.06.08.01 OBRAS PRELIMINARES
02.06.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,120.00 0.49 548.80
02.06.08.01.02 TRAZO Y REPLANTEO m2 1,680.00 1.84 3,091.20
02.06.08.02 MOVIMIENTO DE TIERRAS
02.06.08.02.01 EXCAVACION A MANO DE ZANJA MANUAL TERRENO NORMAL m3 1,344.00 39.86 53,571.84
02.06.08.02.02 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO CLASIFICADO m3 1,344.00 33.00 44,352.00
02.06.08.02.03 SUMINISTRO Y COLOCACION DE GRAVA SELECCIONADA m3 140.00 209.11 29,275.40
02.06.08.03 OBRAS DE CONCRETO SIMPLE
02.06.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 9.27 413.17 3,830.09
02.06.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 46.25 44.48 2,057.20
02.06.08.04 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND) und 125.00 80.77 10,096.25
02.06.08.04.02 TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON LLAVE TIPO BUJIA und 125.00 155.21 19,401.25
02.06.08.04.03 SUMINISTRO E INSTALACIONES DE ACOMETIDA DOMICILIARIA RANGO 2 - 20 M. m 1,125.00 3.50 3,937.50
03 LOCALIDAD TANCARPATA
03.01 CONSTRUCCIONES PROVISIONALES
03.01.01 OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y VESTUARIOS m2 100.00 44.55 4,455.00
03.01.02 ALQUILER DE PREDIOS PARA CAMPAMENTOS Y ALMACENES mes 6.00 500.00 3,000.00
03.01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20 m und 1.00 1,539.82 1,539.82
03.02 CAPTACION A TIPO LADERA YACUTOCCYAC (01 UND)
03.02.01 TRABAJOS PRELIMINARES
03.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49 24.01
03.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
03.02.02 MOVIMIENTO DE TIERRAS
03.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 15.03 39.86 599.10
03.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO C/PISON m3 2.55 29.50 75.23
03.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95 214.65
03.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.60 25.69 400.76
03.02.03 CONCRETO SIMPLE
03.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17 706.52
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48 117.43
03.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55
03.02.04 CONCRETO ARMADO
03.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84 811.87
03.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48 797.53
03.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35 296.06
03.02.05 REVOQUES Y ENLUCIDOS
03.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3 e=1.5cm m2 5.53 32.48 179.61
03.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76 358.61
03.02.06 PINTURA
03.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 13.23 159.42
03.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
03.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85 265.53
03.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77 25.86
03.02.08 CARPINTERIA METALICA
03.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 180.93 180.93
03.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53 281.53
03.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO HIDRAULICO y VENTILACION
03.02.09.01 und 1.00 497.69 497.69
Ø=2")
03.02.10 CERCO PERIMETRICO EN CAPTACION
03.02.10.01 TRABAJOS PRELIMINARES
03.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84 44.16
03.02.10.02 MOVIMIENTO DE TIERRAS
03.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86 23.52
03.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
03.02.10.03 CONCRETO SIMPLE
03.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98 210.03
03.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
03.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
03.02.10.05 COLOCADO DE ROLLIZOS
03.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
03.02.10.06 PINTURA EN CERCO PERIMETRICO
03.02.10.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 33.80 3.80 128.44
03.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
03.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22 533.28
03.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
03.02.10.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10
03.03 LINEA DE CONDUCCION (L=196.00 m)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 196.00 0.49 96.04
03.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 196.00 1.53 299.88
03.03.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 196.00 1.53 299.88
03.03.02 MOVIMIENTO DE TIERRAS
03.03.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 72.13 49.82 3,593.52
03.03.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 6.27 55.80 349.87
03.03.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 196.00 1.81 354.76
03.03.02.04 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 196.00 6.08 1,191.68
03.03.02.05 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 196.00 4.28 838.88
03.03.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 27.05 36.40 984.62
03.03.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 2.35 65.17 153.15
03.03.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 45.05 25.07 1,129.40
03.03.02.09 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 3.92 62.16 243.67
03.03.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.92 25.69 100.70
03.03.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 196.00 5.94 1,164.24
03.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 160.91 160.91
03.03.04 PRUEBA HIDRAULICA
03.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 180.36 1.51 272.34
03.03.05 CAMARA ROMPE PRESION T-6 (01 UND)
03.03.05.01 OBRAS PRELIMINARES
03.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.44 0.49 0.71
03.03.05.01.02 TRAZO Y REPLANTEO m2 1.44 1.84 2.65
03.03.05.02 MOVIMIENTO DE TIERRAS
03.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.58 39.86 62.98
03.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.98 25.69 50.87
03.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 1.44 7.95 11.45
03.03.05.03 OBRAS DE CONCRETO SIMPLE
03.03.05.03.01 SOLADO E=4" m3 1.21 35.81 43.33
03.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13
03.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90
03.03.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55
03.03.05.04 OBRAS DE CONCRETO ARMADO
03.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 0.79 546.69 431.89
03.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.10 44.48 360.29
03.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 37.23 4.35 161.95
03.03.05.05 REVOQUES Y ENLUCIDOS
03.03.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 2.52 32.48 81.85
03.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.24 29.76 96.42
03.03.05.06 PINTURA
03.03.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 3.24 11.18 36.22
03.03.05.07 CARPINTERIA METALICA
03.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 1.00 213.73 213.73
03.03.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.03.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T6, INGRESO Ø=1 y SALIDA Ø=1 " und 1.00 299.60 299.60
03.03.06 VALVULA DE PURGA TIPO I (1 UND)
03.03.06.01 OBRAS PRELIMINARES
03.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 0.49 0.49
03.03.06.01.02 TRAZO Y REPLANTEO m2 1.00 1.84 1.84
03.03.06.02 MOVIMIENTO DE TIERRAS
03.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.51 39.86 20.33
03.03.06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 0.51 13.11 6.69
03.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.49 7.95 3.90
03.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 0.64 25.69 16.44
03.03.06.03 OBRAS DE CONCRETO SIMPLE
03.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.20 413.17 82.63
03.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.24 44.48 10.68
03.03.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.27 121.10 32.70
03.03.06.04 OBRAS DE CONCRETO ARMADO
03.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.35 546.69 191.34
03.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.72 44.48 165.47
03.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 14.94 4.35 64.99
03.03.06.05 REVOQUES Y ENLUCIDOS
03.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 1.44 32.48 46.77
03.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.36 29.76 99.99
03.03.06.06 PINTURA
03.03.06.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 2.16 11.18 24.15
03.03.06.07 CARPINTERIA METALICA
03.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 1.00 214.83 214.83
03.03.06.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.03.06.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO I, Ø=1" und 1.00 153.06 153.06
03.04 RESERVORIO (V=5.00 m3, 01 UND)
03.04.01 OBRAS PRELIMINARES
03.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49 17.64
03.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
03.04.02 MOVIMIENTO DE TIERRAS
03.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 60.95 39.86 2,429.47
03.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 8.05 7.95 64.00
03.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 76.19 25.69 1,957.32
03.04.03 CONCRETO SIMPLE
03.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13
03.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90
03.04.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 SOLADO PARA LOSA FONDO m2 8.05 40.87 329.00
03.04.04.02 CONCRETO f'c=210 kg/cm2 m3 9.51 546.69 5,199.02
03.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 49.52 44.48 2,202.65
03.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 254.64 4.35 1,107.68
03.04.05 REVOQUES Y ENLUCIDOS
03.04.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 31.00 32.48 1,006.88
03.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 35.50 29.76 1,056.48
03.04.06 PINTURA
03.04.06.01 PINTURA ESMALTE EN MUROS EXTERIORES DE RESERVORIO m2 29.15 13.23 385.65
03.04.07 CARPINTERIA METALICA
03.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46
03.04.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.04.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN RESERVORIO (INGRESO Ø 1"-LIMPIA, REBOSE y SELLO HIDR. Ø 2"-VENTILAC. Ø 3") und 1.00 1,618.16 1,618.16
03.04.09 CERCO PERIMETRICO EN RESERVORIO
03.04.09.01 TRABAJOS PRELIMINARES
03.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84 66.24
03.04.09.02 MOVIMIENTO DE TIERRAS
03.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86 27.90
03.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
03.04.09.03 CONCRETO SIMPLE
03.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98 249.19
03.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
03.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
03.04.09.05 COLOCADO DE ROLLIZOS
03.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
03.04.09.06 PINTURA EN CERCO PERIMETRICO
03.04.09.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 66.40 3.80 252.32
03.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
03.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22 515.50
03.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
03.04.09.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10
03.04.10 CLORADOR POR GOTEO
03.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
03.04.10.01.01 CASETA DE MURO DE LADRILLO -CLORADOR POR GOTEO
03.04.10.01.01.0
MURO DE LADRILLO PANDERETA (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 7.52 54.96 413.30
1
03.04.10.01.01.0
MURO DE LADRILLO PANDERETA INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 4.48 49.36 221.13
2
03.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
03.04.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 29.07 174.42
1
03.04.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 34.08 203.80
2
03.04.10.01.03 REVOQUES Y ENLUCIDOS
03.04.10.01.03.0
TARRAJEO MUROS DE INTERIORES Y EXTERIORES, CEMENTO : ARENA, 1:5 m2 14.98 30.00 449.40
1
03.04.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.78 55.12
2
03.04.10.01.04 CARPINTERIA METALICA
03.04.10.01.04.0
SUMINISTRO E INSTALACION DE PUERTA METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO und 1.00 367.18 367.18
1
03.04.10.01.05 PINTURAS
03.04.10.01.05.0
PINTURA ESMALTE EN MUROS INTERIORES Y EXTERIORES m2 14.98 11.18 167.48
1
03.04.10.01.05.0
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 12.25 49.00
2
03.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
03.04.10.02.01 SUMINISTRO E INSTALACION DE TANQUE DE POLIETILENO, CAP=250 LTRS. und 1.00 435.06 435.06
03.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
03.04.10.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS Y ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO GLB 1.00 939.22 939.22
03.05 RED DE ADUCCION Y DISTRIBUCION (L=2,740.00 m)
03.05.01 TRABAJOS PRELIMINARES
03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,370.00 0.49 671.30
03.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 2,740.00 1.53 4,192.20
03.05.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 2,740.00 1.53 4,192.20
03.05.02 MOVIMIENTO DE TIERRAS
03.05.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 1,041.20 49.82 51,872.58
03.05.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 54.80 55.80 3,057.84
03.05.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 2,740.00 1.81 4,959.40
03.05.02.04 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 137.00 6.08 832.96
03.05.02.05 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 390.45 36.40 14,212.38
03.05.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 20.55 65.17 1,339.24
03.05.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 719.25 25.07 18,031.60
03.05.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 68.50 62.16 4,257.96
03.05.02.09 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 34.25 25.69 879.88
03.05.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 4.00 8.05 32.20
03.05.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 3/4" m 2,736.00 4.84 13,242.24
03.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 96.63 96.63
03.05.04 PRUEBA HIDRAULICA
03.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 2,740.00 1.51 4,137.40
03.05.05 CAMARA ROMPE PRESION T-7 (09 UND)
03.05.05.01 OBRAS PRELIMINARES
03.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 18.63 0.49 9.13
03.05.05.01.02 TRAZO Y REPLANTEO m2 18.63 1.84 34.28
03.05.05.02 MOVIMIENTO DE TIERRAS
03.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 14.32 39.86 570.80
03.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 7.16 40.95 293.20
03.05.05.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 2.39 13.11 31.33
03.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 17.69 7.95 140.64
03.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.06 59.44 63.01
03.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 8.06 25.69 207.06
03.05.05.03 OBRAS DE CONCRETO SIMPLE
03.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.11 413.17 45.45
03.05.05.03.02 SOLADO E=4" m3 1.49 35.81 53.36
03.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.80 44.48 80.06
03.05.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 2.43 121.10 294.27
03.05.05.04 OBRAS DE CONCRETO ARMADO
03.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 12.23 546.69 6,686.02
03.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 125.30 44.48 5,573.34
03.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,771.06 4.35 7,704.11
03.05.05.05 REVOQUES Y ENLUCIDOS
03.05.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 38.88 32.48 1,262.82
03.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 84.26 29.76 2,507.58
03.05.05.06 PINTURA
03.05.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 54.00 11.18 603.72
03.05.05.07 CARPINTERIA METALICA
03.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 9.00 179.83 1,618.47
03.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 9.00 213.73 1,923.57
03.05.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=3/4" und 9.00 379.18 3,412.62
03.05.06 VALVULA DE CONTROL (05 UND)
03.05.06.01 OBRAS PRELIMINARES
03.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49 2.45
03.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.84 9.20
03.05.06.02 MOVIMIENTO DE TIERRAS
03.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 39.86 199.30
03.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 25.69 160.56
03.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.95 39.75
03.05.06.03 OBRAS DE CONCRETO ARMADO
03.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 546.69 1,350.32
03.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 44.48 947.42
03.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.35 668.94
03.05.06.04 REVOQUES Y ENLUCIDOS
03.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 32.48 233.86
03.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 29.76 321.41
03.05.06.05 PINTURA
03.05.06.05.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 10.80 11.18 120.74
03.05.06.06 CARPINTERIA METALICA
03.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 162.88 814.40
03.05.06.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=3/4" und 5.00 79.02 395.10
03.05.07 VALVULA DE PURGA TIPO II (06 UND)
03.05.07.01 OBRAS PRELIMINARES
03.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.00 0.49 2.94
03.05.07.01.02 TRAZO Y REPLANTEO m2 6.00 1.84 11.04
03.05.07.02 MOVIMIENTO DE TIERRAS
03.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 9.17 39.86 365.52
03.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 3.06 49.82 152.45
03.05.07.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 3.06 13.11 40.12
03.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 2.94 7.95 23.37
03.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 2.94 25.69 75.53
03.05.07.03 OBRAS DE CONCRETO SIMPLE
03.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 1.84 413.17 760.23
03.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.44 44.48 64.05
03.05.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.77 121.10 93.25
03.05.07.04 OBRAS DE CONCRETO ARMADO
03.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 2.10 546.69 1,148.05
03.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 23.32 44.48 1,037.27
03.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 86.64 4.35 376.88
03.05.07.05 REVOQUES Y ENLUCIDOS
03.05.07.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 8.64 32.48 280.63
03.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 20.16 29.76 599.96
03.05.07.06 PINTURA
03.05.07.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 9.72 11.18 108.67
03.05.07.07 CARPINTERIA METALICA
03.05.07.07.01 MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE 0.60x0.40m. und 6.00 213.73 1,282.38
03.05.07.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.07.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4" und 6.00 132.94 797.64
03.05.08 CONEXIONES DOMICILIARIAS (53 UND)
03.05.08.01 OBRAS PRELIMINARES
03.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 474.88 0.49 232.69
03.05.08.01.02 TRAZO Y REPLANTEO m2 712.32 1.84 1,310.67
03.05.08.02 MOVIMIENTO DE TIERRAS
03.05.08.02.01 EXCAVACION A MANO DE ZANJA MANUAL TERRENO NORMAL m3 569.86 39.86 22,714.62
03.05.08.02.02 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO CLASIFICADO m3 569.86 33.00 18,805.38
03.05.08.02.03 SUMINISTRO Y COLOCACION DE GRAVA SELECCIONADA m3 50.36 209.11 10,530.78
03.05.08.03 OBRAS DE CONCRETO SIMPLE
03.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 3.93 413.17 1,623.76
03.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.61 44.48 872.25
03.05.08.04 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND) und 53.00 80.77 4,280.81
03.05.08.04.02 TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON LLAVE TIPO BUJIA und 53.00 155.21 8,226.13
03.05.08.04.03 SUMINISTRO E INSTALACIONES DE ACOMETIDA DOMICILIARIA RANGO 2 - 20 M. m 530.00 3.50 1,855.00
04 LOCALIDAD TARACA
04.01 CONSTRUCCIONES PROVISIONALES
04.01.01 OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y VESTUARIOS m2 100.00 44.55 4,455.00
04.01.02 ALQUILER DE PREDIOS PARA CAMPAMENTOS Y ALMACENES mes 6.00 500.00 3,000.00
04.01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20 m und 1.00 1,539.82 1,539.82
04.02 CAPTACION A TIPO LADERA YACUTOCCYAC (01 UND)
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49 24.01
04.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
04.02.02 MOVIMIENTO DE TIERRAS
04.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 17.55 39.86 699.54
04.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO C/PISON m3 2.55 29.50 75.23
04.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95 214.65
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.60 25.69 400.76
04.02.03 CONCRETO SIMPLE
04.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17 706.52
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48 117.43
04.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55
04.02.04 CONCRETO ARMADO
04.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84 811.87
04.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48 797.53
04.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35 296.06
04.02.05 REVOQUES Y ENLUCIDOS
04.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3 e=1.5cm m2 5.53 32.48 179.61
04.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76 358.61
04.02.06 PINTURA
04.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 13.23 159.42
04.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
04.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85 265.53
04.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77 25.86
04.02.08 CARPINTERIA METALICA
04.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 180.93 180.93
04.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53 281.53
04.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO HIDRAULICO y VENTILACION
04.02.09.01 und 1.00 497.69 497.69
Ø=2")
04.02.10 CERCO PERIMETRICO EN CAPTACION
04.02.10.01 TRABAJOS PRELIMINARES
04.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84 44.16
04.02.10.02 MOVIMIENTO DE TIERRAS
04.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86 23.52
04.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
04.02.10.03 CONCRETO SIMPLE
04.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98 210.03
04.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
04.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
04.02.10.05 COLOCADO DE ROLLIZOS
04.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
04.02.10.06 PINTURA EN CERCO PERIMETRICO
04.02.10.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 33.80 3.80 128.44
04.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
04.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22 533.28
04.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
04.02.10.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10
04.03 LINEA DE CONDUCCION (L=1231.00 m)
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,231.00 0.49 603.19
04.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 1,231.00 1.53 1,883.43
04.03.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 1,231.00 1.53 1,883.43
04.03.02 MOVIMIENTO DE TIERRAS
04.03.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 392.92 39.86 15,661.79
04.03.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 73.86 49.82 3,679.71
04.03.02.03 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 15.39 55.80 858.76
04.03.02.04 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 1,231.00 1.81 2,228.11
04.03.02.05 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 61.55 6.08 374.22
04.03.02.06 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 1,231.00 4.28 5,268.68
04.03.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 175.42 36.40 6,385.29
04.03.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 9.23 65.17 601.52
04.03.02.09 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 292.36 25.07 7,329.47
04.03.02.10 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 6.16 62.16 382.91
04.03.02.11 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.39 25.69 395.37
04.03.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 1,231.00 5.94 7,312.14
04.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 157.71 157.71
04.03.04 PRUEBA HIDRAULICA
04.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 1,231.00 1.51 1,858.81
04.03.05 CAMARA ROMPE PRESION T-6 (02 UND)
04.03.05.01 OBRAS PRELIMINARES
04.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.88 0.49 1.41
04.03.05.01.02 TRAZO Y REPLANTEO m2 2.88 1.84 5.30
04.03.05.02 MOVIMIENTO DE TIERRAS
04.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 3.17 39.86 126.36
04.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 7.92 25.69 203.46
04.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 2.88 7.95 22.90
04.03.05.03 OBRAS DE CONCRETO SIMPLE
04.03.05.03.01 SOLADO E=4" m3 2.42 35.81 86.66
04.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.02 413.17 8.26
04.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.40 44.48 17.79
04.03.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 1.00 121.10 121.10
04.03.05.04 OBRAS DE CONCRETO ARMADO
04.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 546.69 863.77
04.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 16.20 44.48 720.58
04.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 74.46 4.35 323.90
04.03.05.05 REVOQUES Y ENLUCIDOS
04.03.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 5.04 32.48 163.70
04.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.48 29.76 192.84
04.03.05.06 PINTURA
04.03.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 6.48 11.18 72.45
04.03.05.07 CARPINTERIA METALICA
04.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46
04.03.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.03.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T6, INGRESO Ø=1 y SALIDA Ø=1 " und 2.00 299.60 599.20
04.03.06 VALVULA DE PURGA TIPO I (1 UND)
04.03.06.01 OBRAS PRELIMINARES
04.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.00 0.49 0.98
04.03.06.01.02 TRAZO Y REPLANTEO m2 2.00 1.84 3.68
04.03.06.02 MOVIMIENTO DE TIERRAS
04.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.02 39.86 40.66
04.03.06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 1.02 13.11 13.37
04.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.98 7.95 7.79
04.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1.27 25.69 32.63
04.03.06.03 OBRAS DE CONCRETO SIMPLE
04.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.04 413.17 16.53
04.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.48 44.48 21.35
04.03.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.54 121.10 65.39
04.03.06.04 OBRAS DE CONCRETO ARMADO
04.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.70 546.69 382.68
04.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.44 44.48 330.93
04.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 29.88 4.35 129.98
04.03.06.05 REVOQUES Y ENLUCIDOS
04.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 2.88 32.48 93.54
04.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.72 29.76 199.99
04.03.06.06 PINTURA
04.03.06.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 4.32 11.18 48.30
04.03.06.07 CARPINTERIA METALICA
04.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 2.00 214.83 429.66
04.03.06.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.03.06.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO I, Ø=1" und 2.00 153.06 306.12
04.04 RESERVORIO (V=5.00 m3, 01 UND)
04.04.01 OBRAS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49 17.64
04.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 36.02 39.86 1,435.76
04.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 8.05 7.95 64.00
04.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 45.02 25.69 1,156.56
04.04.03 CONCRETO SIMPLE
04.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13
04.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90
04.04.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55
04.04.04 OBRAS DE CONCRETO ARMADO
04.04.04.01 SOLADO PARA LOSA FONDO m2 8.05 40.87 329.00
04.04.04.02 CONCRETO f'c=210 kg/cm2 m3 9.51 546.69 5,199.02
04.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 49.52 44.48 2,202.65
04.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 254.64 4.35 1,107.68
04.04.05 REVOQUES Y ENLUCIDOS
04.04.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 31.00 32.48 1,006.88
04.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 35.50 29.76 1,056.48
04.04.06 PINTURA
04.04.06.01 PINTURA ESMALTE EN MUROS EXTERIORES DE RESERVORIO m2 29.15 13.23 385.65
04.04.07 CARPINTERIA METALICA
04.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46
04.04.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.04.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN RESERVORIO (INGRESO Ø 1"-LIMPIA, REBOSE y SELLO HIDR. Ø 2"-VENTILAC. Ø 3") und 1.00 1,618.16 1,618.16
04.04.09 CERCO PERIMETRICO EN RESERVORIO
04.04.09.01 TRABAJOS PRELIMINARES
04.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84 66.24
04.04.09.02 MOVIMIENTO DE TIERRAS
04.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86 27.90
04.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
04.04.09.03 CONCRETO SIMPLE
04.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98 249.19
04.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
04.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
04.04.09.05 COLOCADO DE ROLLIZOS
04.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
04.04.09.06 PINTURA EN CERCO PERIMETRICO
04.04.09.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 66.40 3.80 252.32
04.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
04.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22 515.50
04.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
04.04.09.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10
04.04.10 CLORADOR POR GOTEO
04.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
04.04.10.01.01 CASETA DE MURO DE LADRILLO -CLORADOR POR GOTEO
04.04.10.01.01.0
MURO DE LADRILLO PANDERETA (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 7.52 54.96 413.30
1
04.04.10.01.01.0
MURO DE LADRILLO PANDERETA INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 4.48 49.36 221.13
2
04.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
04.04.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 29.07 174.42
1
04.04.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 34.08 203.80
2
04.04.10.01.03 REVOQUES Y ENLUCIDOS
04.04.10.01.03.0
TARRAJEO MUROS DE INTERIORES Y EXTERIORES, CEMENTO : ARENA, 1:5 m2 14.98 30.00 449.40
1
04.04.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.78 55.12
2
04.04.10.01.04 CARPINTERIA METALICA
04.04.10.01.04.0
SUMINISTRO E INSTALACION DE PUERTA METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO und 1.00 367.18 367.18
1
04.04.10.01.05 PINTURAS
04.04.10.01.05.0
PINTURA ESMALTE EN MUROS INTERIORES Y EXTERIORES m2 14.98 11.18 167.48
1
04.04.10.01.05.0
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 12.25 49.00
2
04.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
04.04.10.02.01 SUMINISTRO E INSTALACION DE TANQUE DE POLIETILENO, CAP=250 LTRS. und 1.00 435.06 435.06
04.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
04.04.10.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS Y ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO GLB 1.00 939.22 939.22
04.05 RED DE ADUCCION Y DISTRIBUCION (L=3,674.00 m)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,837.00 0.49 900.13
04.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 3,674.00 1.53 5,621.22
04.05.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 3,674.00 1.53 5,621.22
04.05.02 MOVIMIENTO DE TIERRAS
04.05.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 73.48 39.86 2,928.91
04.05.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 1,352.03 49.82 67,358.13
04.05.02.03 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 44.09 55.80 2,460.22
04.05.02.04 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 3,674.00 1.81 6,649.94
04.05.02.05 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 110.22 6.08 670.14
04.05.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 534.57 36.40 19,458.35
04.05.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 16.53 65.17 1,077.26
04.05.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 946.06 25.07 23,717.72
04.05.02.09 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.20 m m3 55.11 62.16 3,425.64
04.05.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 27.56 25.69 708.02
04.05.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 104.00 8.05 837.20
04.05.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 3/4" m 3,570.00 4.84 17,278.80
04.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 87.97 87.97
04.05.04 PRUEBA HIDRAULICA
04.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 3,674.00 1.51 5,547.74
04.05.05 CAMARA ROMPE PRESION T-7 (12 UND)
04.05.05.01 OBRAS PRELIMINARES
04.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 24.84 0.49 12.17
04.05.05.01.02 TRAZO Y REPLANTEO m2 24.84 1.84 45.71
04.05.05.02 MOVIMIENTO DE TIERRAS
04.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 16.71 39.86 666.06
04.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 9.55 40.95 391.07
04.05.05.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 2.39 13.11 31.33
04.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 23.58 7.95 187.46
04.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.39 59.44 82.62
04.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 12.53 25.69 321.90
04.05.05.03 OBRAS DE CONCRETO SIMPLE
04.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.14 413.17 57.84
04.05.05.03.02 SOLADO E=4" m3 1.98 35.81 70.90
04.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.40 44.48 106.75
04.05.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 3.24 121.10 392.36
04.05.05.04 OBRAS DE CONCRETO ARMADO
04.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 16.30 546.69 8,911.05
04.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 167.06 44.48 7,430.83
04.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,361.41 4.35 10,272.13
04.05.05.05 REVOQUES Y ENLUCIDOS
04.05.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 51.84 32.48 1,683.76
04.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 112.34 29.76 3,343.24
04.05.05.06 PINTURA
04.05.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 72.00 11.18 804.96
04.05.05.07 CARPINTERIA METALICA
04.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 12.00 179.83 2,157.96
04.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 12.00 213.73 2,564.76
04.05.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=3/4" und 12.00 379.18 4,550.16
04.05.06 VALVULA DE CONTROL (05 UND)
04.05.06.01 OBRAS PRELIMINARES
04.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49 2.45
04.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.84 9.20
04.05.06.02 MOVIMIENTO DE TIERRAS
04.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 39.86 199.30
04.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 25.69 160.56
04.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.95 39.75
04.05.06.03 OBRAS DE CONCRETO ARMADO
04.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 546.69 1,350.32
04.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 44.48 947.42
04.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.35 668.94
04.05.06.04 REVOQUES Y ENLUCIDOS
04.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 32.48 233.86
04.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 29.76 321.41
04.05.06.05 PINTURA
04.05.06.05.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 10.80 11.18 120.74
04.05.06.06 CARPINTERIA METALICA
04.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 162.88 814.40
04.05.06.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=3/4" und 5.00 79.02 395.10
04.05.07 VALVULA DE PURGA TIPO II (05 UND)
04.05.07.01 OBRAS PRELIMINARES
04.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49 2.45
04.05.07.01.02 TRAZO Y REPLANTEO m2 5.00 1.84 9.20
04.05.07.02 MOVIMIENTO DE TIERRAS
04.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 7.64 39.86 304.53
04.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 2.55 49.82 127.04
04.05.07.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 2.55 13.11 33.43
04.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 2.45 7.95 19.48
04.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 2.45 25.69 62.94
04.05.07.03 OBRAS DE CONCRETO SIMPLE
04.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 1.53 413.17 632.15
04.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 44.48 53.38
04.05.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.64 121.10 77.50
04.05.07.04 OBRAS DE CONCRETO ARMADO
04.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 1.75 546.69 956.71
04.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 18.60 44.48 827.33
04.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 74.70 4.35 324.95
04.05.07.05 REVOQUES Y ENLUCIDOS
04.05.07.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 7.20 32.48 233.86
04.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 16.80 29.76 499.97
04.05.07.06 PINTURA
04.05.07.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 8.10 11.18 90.56
04.05.07.07 CARPINTERIA METALICA
04.05.07.07.01 MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE 0.60x0.40m. und 5.00 213.73 1,068.65
04.05.07.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.07.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4" und 5.00 132.94 664.70
04.05.08 CONEXIONES DOMICILIARIAS (53 UND)
04.05.08.01 OBRAS PRELIMINARES
04.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 474.88 0.49 232.69
04.05.08.01.02 TRAZO Y REPLANTEO m2 712.32 1.84 1,310.67
04.05.08.02 MOVIMIENTO DE TIERRAS
04.05.08.02.01 EXCAVACION A MANO DE ZANJA TERRENO NORMAL m3 596.86 40.95 24,441.42
04.05.08.02.02 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO CLASIFICADO m3 569.86 33.00 18,805.38
04.05.08.02.03 SUMINISTRO Y COLOCACION DE GRAVA SELECCIONADA m3 59.36 209.11 12,412.77
04.05.08.03 OBRAS DE CONCRETO SIMPLE
04.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 3.93 413.17 1,623.76
04.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.61 44.48 872.25
04.05.08.04 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND) und 53.00 80.77 4,280.81
04.05.08.04.02 TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON LLAVE TIPO BUJIA und 53.00 155.21 8,226.13
04.05.08.04.03 SUMINISTRO E INSTALACIONES DE ACOMETIDA DOMICILIARIA RANGO 2 - 20 M. m 636.00 3.50 2,226.00

01 LOCALIDAD SANTA LUCIA


01.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
01.01.01 TRABAJOS PRELIMINARES
01.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 465.00 0.49 227.85
01.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 465.00 1.84 855.60
01.01.02 MOVIMIENTO DE TIERRAS
01.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 231.57 39.86 9,230.38
01.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 40.92 29.66 1,213.69
01.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 238.08 25.69 6,116.28
01.01.03 CONCRETO SIMPLE
01.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 279.00 373.75 104,276.25
01.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 40.92 398.69 16,314.39
01.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 678.90 44.48 30,197.47
01.01.03.04 CONCRETO f'c=175 kg/cm2 m3 28.83 448.85 12,940.35
01.01.04 MURO DE LADRILLO
01.01.04.01 MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE SOGA C/M 1:4 x 1.5cm m2 1,354.08 58.10 78,672.05
01.01.04.02 EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-6" m2 26.04 70.33 1,831.39
01.01.05 REVOQUES Y ENLUCIDOS
01.01.05.01 TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre hidraulico) m2 1,272.24 16.34 20,788.40
01.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 20.46 36.55 747.81
01.01.06 PINTURA
01.01.06.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE COLOR MARFIL m2 767.25 11.53 8,846.39
01.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO ETERNIT(1,14x0.72x0.005m)
01.01.07.01 m2 605.43 66.22 40,091.57
01.01.08 CARPINTERIA METALICA
01.01.08.01 SUMINISTRO E INSTALACION DE PUERTA METALICA 1.80x0.70m, INCL. MARCO Y PINTADO und 93.00 363.74 33,827.82
01.01.09 CARPINTERIA DE MADERA
01.01.09.01 VENTANA DE MADERA TORNILLO INC. MALLA MOSQUITERA m2 16.74 75.90 1,270.57
01.01.09.02 COBERTURA DE MADERA PARA TECHO und 93.00 97.95 9,109.35
01.01.10 SISTEMA DE AGUA FRIA
01.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 880.71 3.65 3,214.59
01.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
01.01.11.01 TEE PVC-SAP 1/2" pza 186.00 20.85 3,878.10
01.01.11.02 CODO PVC SAP 1/2" pza 558.00 15.59 8,699.22
01.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 186.00 51.25 9,532.50
01.01.11.04 SUMINISTRO E INSTALACION DE DUCHA INCLUIDO ACCESORIOS und 93.00 33.08 3,076.44
01.01.12 SISTEMA DE DESAGUE
01.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 897.45 4.02 3,607.75
01.01.12.02 TUBERIA Ø=4" PVC SAL m 339.45 3.65 1,238.99
01.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
01.01.13.01 CODO PVC SAL 2"X90° pza 651.00 11.77 7,662.27
01.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 93.00 15.53 1,444.29
01.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 279.00 16.11 4,494.69
01.01.14 ADITAMIENTOS VARIOS
01.01.14.01 SUMIDEROS DE BRONCE 2" und 93.00 12.25 1,139.25
01.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 186.00 11.09 2,062.74
01.01.14.03 INODORO DE LOZA VITRIFICADA COLOR BLANCO INCLUYE TANQUE und 93.00 147.40 13,708.20
01.01.14.04 ACCESORIOS DE LOZA und 93.00 64.86 6,031.98
01.01.14.05 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y ACCESORIOS GLB 93.00 29.15 2,710.95
01.01.14.06 SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA COLOR BLANCO INCLUIDO ACCESORIOS und 93.00 124.59 11,586.87
01.01.14.07 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE 12"x24" und 186.00 129.89 24,159.54
01.01.15 INSTALACIONES ELECTRICAS
01.01.15.01 SALIDA DE CENTRO DE LUZ pto 93.00 49.14 4,570.02
01.01.15.02 TUBERIA PVC SEL 5/8" m 213.90 4.15 887.69
01.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 520.80 2.28 1,187.42
01.01.15.04 TABLEROS DISTRIBUCION pza 93.00 89.04 8,280.72
01.01.16 CONSTRUCCION POZO PERCOLADOR
01.01.16.01 TRABAJOS PRELIMINARES
01.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 292.02 0.49 143.09
01.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 292.02 1.84 537.32
01.01.16.02 MOVIMIENTO DE TIERRAS
01.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 150.66 39.86 6,005.31
01.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 22.32 29.66 662.01
01.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 80.91 89.30 7,225.26
01.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 188.79 25.69 4,850.02
01.01.16.03 TAPA DE CONCRETO
01.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 18.81 448.85 8,442.87
01.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 196.26 44.48 8,729.64
01.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,957.65 4.35 8,515.78
01.01.16.04 ANILLO DE CONCRETO
01.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 6.51 355.98 2,317.43
01.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 111.60 44.48 4,963.97
01.01.16.05 MURO DE LADRILLO
01.01.16.05.01 MURO DE LADRILLO ARTESANAL AMARRE DE SOGA, JUNTA 1.5 CM MORTERO 1:1:5 m2 388.74 48.94 19,024.94
01.01.16.06 SISTEMA DE DESAGUE LLEGADA
01.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 181.35 4.02 729.03
01.01.16.06.02 CODO PVC SAL 2"X90° pza 93.00 11.77 1,094.61
01.01.17 INSTALACION DEL BIODIGESTOR
01.01.17.01 TRABAJOS PRELIMINARES
01.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 351.54 0.49 172.25
01.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 351.54 1.84 646.83
01.01.17.02 MOVIMIENTO DE TIERRAS
01.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 281.20 39.86 11,208.63
01.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 211.97 29.66 6,287.03
01.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 351.50 25.69 9,030.04
01.01.17.03 CONCRETO SIMPLE
01.01.17.03.01 SOLADO E=4" m2 60.45 39.68 2,398.66
01.01.17.04 CONCRETO ARMADO
01.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 66.96 448.85 30,055.00
01.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 420.36 44.48 18,697.61
01.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 518.01 4.35 2,253.34
01.01.17.05 BIODIGESTOR
01.01.17.05.01 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 600 LTS und 91.00 779.59 70,942.69
01.01.17.05.02 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 1300 LTS und 2.00 1,320.79 2,641.58
01.01.17.06 REVOQUES Y ENLUCIDOS
01.01.17.06.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 332.01 32.48 10,783.68
01.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
01.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 93.00 4.02 373.86
01.01.17.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 93.00 29.86 2,776.98
01.02 LAVADERO INTRADOMICILIARIO (91 UND)
01.02.01 OBRAS PRELIMINARES
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 460.46 0.49 225.63
01.02.01.02 TRAZO Y REPLANTEO m2 460.46 1.84 847.25
01.02.02 MOVIMIENTO DE TIERRAS
01.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 103.03 37.48 3,861.56
01.02.02.02 RELLENO Y COMPACTADO DE ZANJA CON MATERIAL PROPIO CLASIFICADO m3 84.63 13.11 1,109.50
01.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 21.16 25.69 543.60
01.02.03 OBRAS DE CONCRETO ARMADO
01.02.03.01 CONCRETO f'c=175 kg/cm2 m3 9.57 448.85 4,295.49
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 304.63 44.48 13,549.94
01.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 359.91 4.35 1,565.61
01.02.04 MURO DE LADRILLO
01.02.04.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 60.17 47.74 2,872.52
01.02.05 REVOQUES Y ENLUCIDOS
01.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 107.29 32.48 3,484.78
01.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 205.30 29.76 6,109.73
01.02.06 ACCESORIOS Y VALVULAS
01.02.06.01 SUMINISTRO E INSTALACION DE LAVADERO INTRADOMICILIARIA und 91.00 136.31 12,404.21
01.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
01.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 455.00 3.35 1,524.25
01.03 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55
01.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84 20.83
01.03.02 MOVIMIENTO DE TIERRAS
01.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48 102.70
01.03.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02 11.55
01.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
01.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69 34.42
01.03.03 OBRAS DE CONCRETO SIMPLE
01.03.03.01 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.20 48.96 107.71
01.03.04 OBRAS DE CONCRETO ARMADO
01.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35 36.32
01.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 44.01 180.00
01.03.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.21 448.85 94.26
01.03.05 REVOQUES Y REVESTIMIENTOS
01.03.05.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 2.49 32.96 82.07
01.03.05.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 2.11 23.98 50.60
01.03.06 ACCESORIOS Y VALVULAS
01.03.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO I.E. INICIAL und 1.00 176.99 176.99
01.03.06.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00
01.03.06.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77
01.03.06.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19
01.03.07 TUBERIA PVC INTRADOMICILIARIO
01.03.07.01 INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20
01.03.07.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50
02 LOCALIDAD PUEBLO LIBRE (130 UND)
02.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 650.00 0.49 318.50
02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 650.00 1.84 1,196.00
02.01.02 MOVIMIENTO DE TIERRAS
02.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 323.70 39.86 12,902.68
02.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 57.20 29.66 1,696.55
02.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 332.80 25.69 8,549.63
02.01.03 CONCRETO SIMPLE
02.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 390.00 373.75 145,762.50
02.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 57.20 398.69 22,805.07
02.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 949.00 44.48 42,211.52
02.01.03.04 CONCRETO f'c=175 kg/cm2 m3 40.30 448.85 18,088.66
02.01.04 MURO DE LADRILLO
02.01.04.01 MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE SOGA C/M 1:4 x 1.5cm m2 1,892.80 58.10 109,971.68
02.01.04.02 EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-6" m2 36.40 70.33 2,560.01
02.01.05 REVOQUES Y ENLUCIDOS
02.01.05.01 TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre hidraulico) m2 1,778.40 16.34 29,059.06
02.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 28.60 36.55 1,045.33
02.01.06 PINTURA
02.01.06.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE COLOR MARFIL m2 1,072.50 11.53 12,365.93
02.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO ETERNIT(1,14x0.72x0.005m)
02.01.07.01 m2 846.60 66.22 56,061.85
02.01.08 CARPINTERIA METALICA
02.01.08.01 SUMINISTRO E INSTALACION DE PUERTA METALICA 1.80x0.70m, INCL. MARCO Y PINTADO und 130.00 363.74 47,286.20
02.01.09 CARPINTERIA DE MADERA
02.01.09.01 VENTANA DE MADERA TORNILLO INC. MALLA MOSQUITERA m2 23.40 75.90 1,776.06
02.01.09.02 COBERTURA DE MADERA PARA TECHO und 130.00 97.95 12,733.50
02.01.10 SISTEMA DE AGUA FRIA
02.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 1,231.00 3.65 4,493.15
02.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
02.01.11.01 TEE PVC-SAP 1/2" pza 260.00 20.85 5,421.00
02.01.11.02 CODO PVC SAP 1/2" pza 780.00 15.59 12,160.20
02.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 260.00 51.25 13,325.00
02.01.11.04 SUMINISTRO E INSTALACION DE DUCHA INCLUIDO ACCESORIOS und 130.00 33.08 4,300.40
02.01.12 SISTEMA DE DESAGUE
02.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 1,254.50 4.02 5,043.09
02.01.12.02 TUBERIA Ø=4" PVC SAL m 474.50 3.65 1,731.93
02.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
02.01.13.01 CODO PVC SAL 2"X90° pza 910.00 11.77 10,710.70
02.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 130.00 15.53 2,018.90
02.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 390.00 16.11 6,282.90
02.01.14 ADITAMIENTOS VARIOS
02.01.14.01 SUMIDEROS DE BRONCE 2" und 130.00 12.25 1,592.50
02.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 260.00 11.09 2,883.40
02.01.14.03 INODORO DE LOZA VITRIFICADA COLOR BLANCO INCLUYE TANQUE und 130.00 147.40 19,162.00
02.01.14.04 ACCESORIOS DE LOZA und 130.00 64.86 8,431.80
02.01.14.05 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y ACCESORIOS GLB 130.00 29.15 3,789.50
02.01.14.06 SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA COLOR BLANCO INCLUIDO ACCESORIOS und 130.00 124.59 16,196.70
02.01.14.07 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE 12"x24" und 260.00 129.89 33,771.40
02.01.15 INSTALACIONES ELECTRICAS
02.01.15.01 SALIDA DE CENTRO DE LUZ pto 130.00 49.14 6,388.20
02.01.15.02 TUBERIA PVC SEL 5/8" m 299.00 4.15 1,240.85
02.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 728.00 2.28 1,659.84
02.01.15.04 TABLEROS DISTRIBUCION pza 130.00 89.04 11,575.20
02.01.16 CONSTRUCCION POZO PERCOLADOR
02.01.16.01 TRABAJOS PRELIMINARES
02.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 408.20 0.49 200.02
02.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 408.20 1.84 751.09
02.01.16.02 MOVIMIENTO DE TIERRAS
02.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 210.60 39.86 8,394.52
02.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 31.20 29.66 925.39
02.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 113.10 89.30 10,099.83
02.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 163.90 25.69 4,210.59
02.01.16.03 TAPA DE CONCRETO
02.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 22.10 448.85 9,919.59
02.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 236.60 44.48 10,523.97
02.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,736.50 4.35 11,903.78
02.01.16.04 ANILLO DE CONCRETO
02.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 9.10 355.98 3,239.42
02.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 156.00 44.48 6,938.88
02.01.16.05 MURO DE LADRILLO
02.01.16.05.01 MURO DE LADRILLO ARTESANAL AMARRE DE SOGA, JUNTA 1.5 CM MORTERO 1:1:5 m2 543.40 48.94 26,594.00
02.01.16.06 SISTEMA DE DESAGUE LLEGADA
02.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 253.50 4.02 1,019.07
02.01.16.06.02 CODO PVC SAL 2"X90° pza 130.00 11.77 1,530.10
02.01.17 INSTALACION DEL BIODIGESTOR
02.01.17.01 TRABAJOS PRELIMINARES
02.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 491.40 0.49 240.79
02.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 491.40 1.84 904.18
02.01.17.02 MOVIMIENTO DE TIERRAS
02.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 396.70 39.86 15,812.46
02.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 299.24 29.66 8,875.46
02.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 504.11 25.69 12,950.59
02.01.17.03 CONCRETO SIMPLE
02.01.17.03.01 SOLADO E=4" m2 84.50 39.68 3,352.96
02.01.17.04 CONCRETO ARMADO
02.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 93.60 448.85 42,012.36
02.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 587.60 44.48 26,136.45
02.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 724.10 4.35 3,149.84
02.01.17.05 BIODIGESTOR
02.01.17.05.01 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 600 LTS und 121.00 779.59 94,330.39
02.01.17.05.02 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 1300 LTS und 9.00 1,320.79 11,887.11
02.01.17.06 REVOQUES Y ENLUCIDOS
02.01.17.06.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 464.10 32.48 15,073.97
02.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
02.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 130.00 4.02 522.60
02.01.17.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 130.00 29.86 3,881.80
02.02 LAVADERO INTRADOMICILIARIO (121 UND)
02.02.01 OBRAS PRELIMINARES
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 612.26 0.49 300.01
02.02.01.02 TRAZO Y REPLANTEO m2 612.26 1.84 1,126.56
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 137.00 37.48 5,134.76
02.02.02.02 RELLENO Y COMPACTADO DE ZANJA CON MATERIAL PROPIO CLASIFICADO m3 112.53 13.11 1,475.27
02.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 28.14 25.69 722.92
02.02.03 OBRAS DE CONCRETO ARMADO
02.02.03.01 CONCRETO f'c=175 kg/cm2 m3 12.72 448.85 5,709.37
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 405.06 44.48 18,017.07
02.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 478.56 4.35 2,081.74
02.02.04 MURO DE LADRILLO
02.02.04.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 80.01 47.74 3,819.68
02.02.05 REVOQUES Y ENLUCIDOS
02.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 142.66 32.48 4,633.60
02.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 272.98 29.76 8,123.88
02.02.06 ACCESORIOS Y VALVULAS
02.02.06.01 SUMINISTRO E INSTALACION DE LAVADERO INTRADOMICILIARIA und 121.00 136.31 16,493.51
02.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
02.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 605.00 3.35 2,026.75
02.03 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
02.03.01 TRABAJOS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55
02.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84 20.83
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48 102.70
02.03.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02 11.55
02.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
02.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69 34.42
02.03.03 OBRAS DE CONCRETO SIMPLE
02.03.03.01 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.20 48.96 107.71
02.03.04 OBRAS DE CONCRETO ARMADO
02.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35 36.32
02.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 44.01 180.00
02.03.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.21 448.85 94.26
02.03.05 REVOQUES Y REVESTIMIENTOS
02.03.05.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 2.49 32.96 82.07
02.03.05.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 2.11 23.98 50.60
02.03.06 ACCESORIOS Y VALVULAS
02.03.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO I.E. INICIAL und 1.00 176.99 176.99
02.03.06.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00
02.03.06.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77
02.03.06.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19
02.03.07 TUBERIA PVC INTRADOMICILIARIO
02.03.07.01 INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20
02.03.07.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50
02.04 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01 UND)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.49 5.87
02.04.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.84 22.04
02.04.02 MOVIMIENTO DE TIERRAS
02.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 37.48 104.94
02.04.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.98 1.02 12.22
02.04.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
02.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 25.69 36.22
02.04.03 OBRAS DE CONCRETO SIMPLE
02.04.03.01 CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6") EN LAVADERO C/MEZCLADORA m3 0.06 339.60 20.38
02.04.03.02 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.86 48.96 140.03
02.04.04 OBRAS DE CONCRETO ARMADO
02.04.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.35 49.98
02.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 44.01 190.56
02.04.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.31 448.85 139.14
02.04.05 ALBAÑILERIA
02.04.05.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 0.36 58.08 20.91
02.04.06 REVOQUES Y REVESTIMIENTOS
02.04.06.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 3.51 32.96 115.69
02.04.06.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 3.29 23.98 78.89
02.04.07 ACCESORIOS Y VALVULAS
02.04.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO TIPO I.E. PRIMARIA und 1.00 176.99 176.99
02.04.07.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00
02.04.07.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77
02.04.07.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19
02.04.08 TUBERIA PVC INTRADOMICILIARIO
02.04.08.01 INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20
02.04.08.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50
02.05 LAVADERO I.E. SECUNDARIA (01 UND)
02.05.01 TRABAJOS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55
02.05.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84 20.83
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 3.70 37.48 138.68
02.05.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02 11.55
02.05.02.03 RELLENO CON MATERIAL PROPIO m3 2.64 29.50 77.88
02.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.27 25.69 32.63
02.05.03 OBRAS DE CONCRETO SIMPLE
02.05.03.01 CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6") EN LAVADERO C/MEZCLADORA m3 0.08 339.60 27.17
02.05.03.02 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 0.22 48.96 10.77
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 0.26 4.35 1.13
02.05.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 5.20 44.01 228.85
02.05.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 12.73 448.85 5,713.86
02.05.05 ALBAÑILERIA
02.05.05.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 1.04 58.08 60.40
02.05.06 REVOQUES Y REVESTIMIENTOS
02.05.06.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 3.13 32.96 103.16
02.05.06.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 4.41 23.98 105.75
02.05.07 ACCESORIOS Y VALVULAS
02.05.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO TIPO I.E. PRIMARIA und 1.00 176.99 176.99
02.05.07.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00
02.05.07.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77
02.05.07.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19
02.05.08 TUBERIA PVC INTRADOMICILIARIO
02.05.08.01 INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20
02.05.08.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50
03 LOCALIDAD TANCARPATA (55 UND)
03.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
03.01.01 TRABAJOS PRELIMINARES
03.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 275.00 0.49 134.75
03.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 275.00 1.84 506.00
03.01.02 MOVIMIENTO DE TIERRAS
03.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 136.95 39.86 5,458.83
03.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 24.20 29.66 717.77
03.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 140.80 25.69 3,617.15
03.01.03 CONCRETO SIMPLE
03.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 165.00 373.75 61,668.75
03.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 24.20 398.69 9,648.30
03.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 401.50 44.48 17,858.72
03.01.03.04 CONCRETO f'c=175 kg/cm2 m3 17.05 448.85 7,652.89
03.01.04 MURO DE LADRILLO
03.01.04.01 MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE SOGA C/M 1:4 x 1.5cm m2 800.80 58.10 46,526.48
03.01.04.02 EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-6" m2 15.40 70.33 1,083.08
03.01.05 REVOQUES Y ENLUCIDOS
03.01.05.01 TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre hidraulico) m2 752.40 16.34 12,294.22
03.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 12.10 36.55 442.26
03.01.06 PINTURA
03.01.06.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE COLOR MARFIL m2 453.75 11.53 5,231.74
03.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO ETERNIT(1,14x0.72x0.005m)
03.01.07.01 m2 358.05 66.22 23,710.07
03.01.08 CARPINTERIA METALICA
03.01.08.01 SUMINISTRO E INSTALACION DE PUERTA METALICA 1.80x0.70m, INCL. MARCO Y PINTADO und 55.00 363.74 20,005.70
03.01.09 CARPINTERIA DE MADERA
03.01.09.01 VENTANA DE MADERA TORNILLO INC. MALLA MOSQUITERA m2 9.90 75.90 751.41
03.01.09.02 COBERTURA DE MADERA PARA TECHO und 55.00 97.95 5,387.25
03.01.10 SISTEMA DE AGUA FRIA
03.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 520.85 3.65 1,901.10
03.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
03.01.11.01 TEE PVC-SAP 1/2" pza 110.00 20.85 2,293.50
03.01.11.02 CODO PVC SAP 1/2" pza 330.00 15.59 5,144.70
03.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 110.00 51.25 5,637.50
03.01.11.04 SUMINISTRO E INSTALACION DE DUCHA INCLUIDO ACCESORIOS und 55.00 33.08 1,819.40
03.01.12 SISTEMA DE DESAGUE
03.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 530.75 4.02 2,133.62
03.01.12.02 TUBERIA Ø=4" PVC SAL m 200.75 3.65 732.74
03.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
03.01.13.01 CODO PVC SAL 2"X90° pza 385.00 11.77 4,531.45
03.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 55.00 15.53 854.15
03.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 165.00 16.11 2,658.15
03.01.14 ADITAMIENTOS VARIOS
03.01.14.01 SUMIDEROS DE BRONCE 2" und 55.00 12.25 673.75
03.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 110.00 11.09 1,219.90
03.01.14.03 INODORO DE LOZA VITRIFICADA COLOR BLANCO INCLUYE TANQUE und 55.00 147.40 8,107.00
03.01.14.04 ACCESORIOS DE LOZA und 55.00 64.86 3,567.30
03.01.14.05 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y ACCESORIOS GLB 55.00 29.15 1,603.25
03.01.14.06 SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA COLOR BLANCO INCLUIDO ACCESORIOS und 55.00 124.59 6,852.45
03.01.14.07 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE 12"x24" und 110.00 129.89 14,287.90
03.01.15 INSTALACIONES ELECTRICAS
03.01.15.01 SALIDA DE CENTRO DE LUZ pto 55.00 49.14 2,702.70
03.01.15.02 TUBERIA PVC SEL 5/8" m 126.50 4.15 524.98
03.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 308.00 2.28 702.24
03.01.15.04 TABLEROS DISTRIBUCION pza 55.00 89.04 4,897.20
03.01.16 CONSTRUCCION POZO PERCOLADOR
03.01.16.01 TRABAJOS PRELIMINARES
03.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 172.70 0.49 84.62
03.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 172.20 1.84 316.85
03.01.16.02 MOVIMIENTO DE TIERRAS
03.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 89.10 39.86 3,551.53
03.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 13.20 29.66 391.51
03.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 47.85 89.30 4,273.01
03.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 111.65 25.69 2,868.29
03.01.16.03 TAPA DE CONCRETO
03.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 9.35 448.85 4,196.75
03.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 100.10 44.48 4,452.45
03.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,157.75 4.35 5,036.21
03.01.16.04 ANILLO DE CONCRETO
03.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 3.85 355.98 1,370.52
03.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.00 44.48 2,935.68
03.01.16.05 MURO DE LADRILLO
03.01.16.05.01 MURO DE LADRILLO ARTESANAL AMARRE DE SOGA, JUNTA 1.5 CM MORTERO 1:1:5 m2 229.90 48.94 11,251.31
03.01.16.06 SISTEMA DE DESAGUE LLEGADA
03.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 107.25 4.02 431.15
03.01.16.06.02 CODO PVC SAL 2"X90° pza 55.00 11.77 647.35
03.01.17 INSTALACION DEL BIODIGESTOR
03.01.17.01 TRABAJOS PRELIMINARES
03.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 207.90 0.49 101.87
03.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 207.90 1.84 382.54
03.01.17.02 MOVIMIENTO DE TIERRAS
03.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 170.94 39.86 6,813.67
03.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 129.10 29.66 3,829.11
03.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 213.67 25.69 5,489.18
03.01.17.03 CONCRETO SIMPLE
03.01.17.03.01 SOLADO E=4" m2 35.75 39.68 1,418.56
03.01.17.04 CONCRETO ARMADO
03.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 39.60 448.85 17,774.46
03.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.60 44.48 11,057.73
03.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 306.35 4.35 1,332.62
03.01.17.05 BIODIGESTOR
03.01.17.05.01 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 600 LTS und 51.00 779.59 39,759.09
03.01.17.05.02 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 1300 LTS und 4.00 1,320.79 5,283.16
03.01.17.06 REVOQUES Y ENLUCIDOS
03.01.17.06.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 196.35 32.48 6,377.45
03.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
03.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 55.00 4.02 221.10
03.01.17.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 55.00 29.86 1,642.30
03.02 LAVADERO INTRADOMICILIARIO (51 UND)
03.02.01 OBRAS PRELIMINARES
03.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 258.06 0.49 126.45
03.02.01.02 TRAZO Y REPLANTEO m2 258.06 1.84 474.83
03.02.02 MOVIMIENTO DE TIERRAS
03.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 57.74 37.48 2,164.10
03.02.02.02 RELLENO Y COMPACTADO DE ZANJA CON MATERIAL PROPIO CLASIFICADO m3 47.43 13.11 621.81
03.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.86 25.69 304.68
03.02.03 OBRAS DE CONCRETO ARMADO
03.02.03.01 CONCRETO f'c=175 kg/cm2 m3 5.36 448.85 2,405.84
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 170.73 44.48 7,594.07
03.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 201.71 4.35 877.44
03.02.04 MURO DE LADRILLO
03.02.04.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 33.72 47.74 1,609.79
03.02.05 REVOQUES Y ENLUCIDOS
03.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 60.13 32.48 1,953.02
03.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 115.06 29.76 3,424.19
03.02.06 ACCESORIOS Y VALVULAS
03.02.06.01 SUMINISTRO E INSTALACION DE LAVADERO INTRADOMICILIARIA und 51.00 136.31 6,951.81
03.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
03.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 255.00 3.35 854.25
03.03 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55
03.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84 20.83
03.03.02 MOVIMIENTO DE TIERRAS
03.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48 102.70
03.03.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02 11.55
03.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
03.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69 34.42
03.03.03 OBRAS DE CONCRETO SIMPLE
03.03.03.01 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.20 48.96 107.71
03.03.04 OBRAS DE CONCRETO ARMADO
03.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35 36.32
03.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 44.01 180.00
03.03.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.21 448.85 94.26
03.03.05 REVOQUES Y REVESTIMIENTOS
03.03.05.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 2.49 32.96 82.07
03.03.05.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 2.11 23.98 50.60
03.03.06 ACCESORIOS Y VALVULAS
03.03.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO I.E. INICIAL und 1.00 176.99 176.99
03.03.06.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00
03.03.06.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77
03.03.06.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19
03.03.07 TUBERIA PVC INTRADOMICILIARIO
03.03.07.01 INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20
03.03.07.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50
03.04 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01 UND)
03.04.01 TRABAJOS PRELIMINARES
03.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.49 5.87
03.04.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.84 22.04
03.04.02 MOVIMIENTO DE TIERRAS
03.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 37.48 104.94
03.04.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.98 1.02 12.22
03.04.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
03.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 25.69 36.22
03.04.03 OBRAS DE CONCRETO SIMPLE
03.04.03.01 CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6") EN LAVADERO C/MEZCLADORA m3 0.06 339.60 20.38
03.04.03.02 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.86 48.96 140.03
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.35 49.98
03.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 44.01 190.56
03.04.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.31 448.85 139.14
03.04.05 ALBAÑILERIA
03.04.05.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 0.36 58.08 20.91
03.04.06 REVOQUES Y REVESTIMIENTOS
03.04.06.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 3.51 32.96 115.69
03.04.06.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 3.29 23.98 78.89
03.04.07 ACCESORIOS Y VALVULAS
03.04.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO TIPO I.E. PRIMARIA und 1.00 176.99 176.99
03.04.07.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00
03.04.07.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77
03.04.07.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19
03.04.08 TUBERIA PVC INTRADOMICILIARIO
03.04.08.01 INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20
03.04.08.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50
04 LOCALIDAD TARACA (55 UND)
04.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
04.01.01 TRABAJOS PRELIMINARES
04.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 275.00 0.49 134.75
04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 275.00 1.84 506.00
04.01.02 MOVIMIENTO DE TIERRAS
04.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 136.95 39.86 5,458.83
04.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 24.20 29.66 717.77
04.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 140.80 25.69 3,617.15
04.01.03 CONCRETO SIMPLE
04.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 165.00 373.75 61,668.75
04.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 24.20 398.69 9,648.30
04.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 401.50 44.48 17,858.72
04.01.03.04 CONCRETO f'c=175 kg/cm2 m3 17.05 448.85 7,652.89
04.01.04 MURO DE LADRILLO
04.01.04.01 MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE SOGA C/M 1:4 x 1.5cm m2 800.80 58.10 46,526.48
04.01.04.02 EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-6" m2 15.40 70.33 1,083.08
04.01.05 REVOQUES Y ENLUCIDOS
04.01.05.01 TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre hidraulico) m2 752.40 16.34 12,294.22
04.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 12.10 36.55 442.26
04.01.06 PINTURA
04.01.06.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE COLOR MARFIL m2 453.75 11.53 5,231.74
04.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO ETERNIT(1,14x0.72x0.005m)
04.01.07.01 m2 358.05 66.22 23,710.07
04.01.08 CARPINTERIA METALICA
04.01.08.01 SUMINISTRO E INSTALACION DE PUERTA METALICA 1.80x0.70m, INCL. MARCO Y PINTADO und 55.00 363.74 20,005.70
04.01.09 CARPINTERIA DE MADERA
04.01.09.01 VENTANA DE MADERA TORNILLO INC. MALLA MOSQUITERA m2 9.90 75.90 751.41
04.01.09.02 COBERTURA DE MADERA PARA TECHO und 55.00 97.95 5,387.25
04.01.10 SISTEMA DE AGUA FRIA
04.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 520.85 3.65 1,901.10
04.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
04.01.11.01 TEE PVC-SAP 1/2" pza 110.00 20.85 2,293.50
04.01.11.02 CODO PVC SAP 1/2" pza 330.00 15.59 5,144.70
04.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 110.00 51.25 5,637.50
04.01.11.04 SUMINISTRO E INSTALACION DE DUCHA INCLUIDO ACCESORIOS und 55.00 33.08 1,819.40
04.01.12 SISTEMA DE DESAGUE
04.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 530.75 4.02 2,133.62
04.01.12.02 TUBERIA Ø=4" PVC SAL m 200.75 3.65 732.74
04.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
04.01.13.01 CODO PVC SAL 2"X90° pza 385.00 11.77 4,531.45
04.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 55.00 15.53 854.15
04.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 165.00 16.11 2,658.15
04.01.14 ADITAMIENTOS VARIOS
04.01.14.01 SUMIDEROS DE BRONCE 2" und 55.00 12.25 673.75
04.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 110.00 11.09 1,219.90
04.01.14.03 INODORO DE LOZA VITRIFICADA COLOR BLANCO INCLUYE TANQUE und 55.00 147.40 8,107.00
04.01.14.04 ACCESORIOS DE LOZA und 55.00 64.86 3,567.30
04.01.14.05 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y ACCESORIOS GLB 55.00 29.15 1,603.25
04.01.14.06 SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA COLOR BLANCO INCLUIDO ACCESORIOS und 55.00 124.59 6,852.45
04.01.14.07 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE 12"x24" und 110.00 129.89 14,287.90
04.01.15 INSTALACIONES ELECTRICAS
04.01.15.01 SALIDA DE CENTRO DE LUZ pto 55.00 49.14 2,702.70
04.01.15.02 TUBERIA PVC SEL 5/8" m 126.50 4.15 524.98
04.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 308.00 2.28 702.24
04.01.15.04 TABLEROS DISTRIBUCION pza 55.00 89.04 4,897.20
04.02 CONSTRUCCION POZO PERCOLADOR
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 172.70 0.49 84.62
04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 172.20 1.84 316.85
04.02.02 MOVIMIENTO DE TIERRAS
04.02.02.01 EXCAVACION A MANO TERRENO NORMAL m3 89.10 39.86 3,551.53
04.02.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 13.20 29.66 391.51
04.02.02.03 FILTRO DE GRAVA CLASIFICADA m3 47.85 89.30 4,273.01
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 111.65 25.69 2,868.29
04.02.03 TAPA DE CONCRETO
04.02.03.01 CONCRETO f'c=175 kg/cm2 m3 9.35 448.85 4,196.75
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 100.10 44.48 4,452.45
04.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,157.75 4.35 5,036.21
04.02.04 ANILLO DE CONCRETO
04.02.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 3.85 355.98 1,370.52
04.02.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.00 44.48 2,935.68
04.02.05 MURO DE LADRILLO
04.02.05.01 MURO DE LADRILLO ARTESANAL AMARRE DE SOGA, JUNTA 1.5 CM MORTERO 1:1:5 m2 229.90 48.94 11,251.31
04.02.06 SISTEMA DE DESAGUE LLEGADA
04.02.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 107.25 4.02 431.15
04.02.06.02 CODO PVC SAL 2"X90° pza 55.00 11.77 647.35
04.03 INSTALACION DEL BIODIGESTOR
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 207.90 0.49 101.87
04.03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 207.90 1.84 382.54
04.03.02 MOVIMIENTO DE TIERRAS
04.03.02.01 EXCAVACION A MANO TERRENO NORMAL m3 170.94 39.86 6,813.67
04.03.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 129.10 29.66 3,829.11
04.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 213.67 25.69 5,489.18
04.03.03 CONCRETO SIMPLE
04.03.03.01 SOLADO E=4" m2 35.75 39.68 1,418.56
04.03.04 CONCRETO ARMADO
04.03.04.01 CONCRETO f'c=175 kg/cm2 m3 39.60 448.85 17,774.46
04.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.60 44.48 11,057.73
04.03.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 306.35 4.35 1,332.62
04.03.05 BIODIGESTOR
04.03.05.01 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 600 LTS und 51.00 779.59 39,759.09
04.03.05.02 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 1300 LTS und 4.00 1,320.79 5,283.16
04.03.06 REVOQUES Y ENLUCIDOS
04.03.06.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 196.35 32.48 6,377.45
04.03.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
04.03.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 55.00 4.02 221.10
04.03.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 55.00 29.86 1,642.30
04.04 LAVADERO INTRADOMICILIARIO (51 UND)
04.04.01 OBRAS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 258.06 0.49 126.45
04.04.01.02 TRAZO Y REPLANTEO m2 258.06 1.84 474.83
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 57.74 37.48 2,164.10
04.04.02.02 RELLENO Y COMPACTADO DE ZANJA CON MATERIAL PROPIO CLASIFICADO m3 47.43 13.11 621.81
04.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.86 25.69 304.68
04.04.03 OBRAS DE CONCRETO ARMADO
04.04.03.01 CONCRETO f'c=175 kg/cm2 m3 5.36 448.85 2,405.84
04.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 170.73 44.48 7,594.07
04.04.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 201.71 4.35 877.44
04.04.04 MURO DE LADRILLO
04.04.04.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 33.72 47.74 1,609.79
04.04.05 REVOQUES Y ENLUCIDOS
04.04.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 60.13 32.48 1,953.02
04.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 115.06 29.76 3,424.19
04.04.06 ACCESORIOS Y VALVULAS
04.04.06.01 SUMINISTRO E INSTALACION DE LAVADERO INTRADOMICILIARIA und 51.00 136.31 6,951.81
04.04.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
04.04.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 255.00 3.35 854.25
04.05 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55
04.05.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84 20.83
04.05.02 MOVIMIENTO DE TIERRAS
04.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48 102.70
04.05.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02 11.55
04.05.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
04.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69 34.42
04.05.03 OBRAS DE CONCRETO SIMPLE
04.05.03.01 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.20 48.96 107.71
04.05.04 OBRAS DE CONCRETO ARMADO
04.05.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35 36.32
04.05.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 44.01 180.00
04.05.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.21 448.85 94.26
04.05.05 REVOQUES Y REVESTIMIENTOS
04.05.05.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 2.49 32.96 82.07
04.05.05.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 2.11 23.98 50.60
04.05.06 ACCESORIOS Y VALVULAS
04.05.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO I.E. INICIAL und 1.00 176.99 176.99
04.05.06.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00
04.05.06.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77
04.05.06.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19
04.05.07 TUBERIA PVC INTRADOMICILIARIO
04.05.07.01 INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20
04.05.07.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50
04.06 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01 UND)
04.06.01 TRABAJOS PRELIMINARES
04.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.49 5.87
04.06.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.84 22.04
04.06.02 MOVIMIENTO DE TIERRAS
04.06.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 37.48 104.94
04.06.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.98 1.02 12.22
04.06.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
04.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 25.69 36.22
04.06.03 OBRAS DE CONCRETO SIMPLE
04.06.03.01 CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6") EN LAVADERO C/MEZCLADORA m3 0.06 339.60 20.38
04.06.03.02 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.86 48.96 140.03
04.06.04 OBRAS DE CONCRETO ARMADO
04.06.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.35 49.98
04.06.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 44.01 190.56
04.06.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.31 448.85 139.14
04.06.05 ALBAÑILERIA
04.06.05.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 0.36 58.08 20.91
04.06.06 REVOQUES Y REVESTIMIENTOS
04.06.06.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 3.51 32.96 115.69
04.06.06.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 3.29 23.98 78.89
04.06.07 ACCESORIOS Y VALVULAS
04.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO TIPO I.E. PRIMARIA und 1.00 176.99 176.99
04.06.07.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00
04.06.07.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77
04.06.07.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19
04.06.08 TUBERIA PVC INTRADOMICILIARIO
04.06.08.01 INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20
04.06.08.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50

01 LOCALIDAD SANTA LUCIA


01.01 CAPACITACION EN EDUCACION SANITARIA, PROMOCION DE LA SALUD Y AOM
01.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
01.01.01.01 TALLER IMPORTANCIA DE LA ORGANIZACION Y PARTICIPACION CIUDADANA Tall 1.00 940.60 940.60
01.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60 940.60
01.01.02 EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y SALUD)
01.01.02.01 TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y SALUD (Valoracion del agua) Tall 1.00 940.61 940.61
01.01.02.02 TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION DE EXCRETAS Tall 1.00 940.61 940.61
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL HOGAR Y
01.01.02.03 Tall 1.00 940.61 940.61
COMUNAL
01.01.02.04 CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE. Tall 1.00 940.61 940.61
01.01.02.05 DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y SANEAMIENTO (SPOT PUBLICITARIO) Men 2.00 84.74 169.48
01.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
01.01.03.01 TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS Tall 1.00 940.61 940.61
01.01.03.02 TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA POTABLE Tall 1.00 940.61 940.61
01.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61 940.61
01.01.03.04 TALLER DE CLORACION Y DESINFECCION DE AGUA PARA CONSUMO HUMANO Tall 1.00 1,110.11 1,110.11
01.02 FLETE
01.02.01 FLETE RURAL
01.02.01.01 FLETE RURAL GLB 1.00 25,395.57 25,395.57
01.02.02 FLETE TERRESTRE
01.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00 4,725.00
01.02.02.02 FLETE TERRESTRE GLB 1.00 10,576.27 10,576.27
01.03 MITIGACION AMBIENTAL
01.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00 2,840.00
01.03.02 PROGRAMA DE CONSERVACION, RESTAURACION Y COMPESACION DE COBERTURA VEGETAL (REFORESTACION) GLB 1.00 1,712.00 1,712.00
01.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00 3,400.00
01.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00 1,000.00
01.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 500.00 500.00
01.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00 3,600.00
01.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00 600.00
01.04 CONTROL Y SEGURIDAD EN OBRA
01.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 6,959.68 6,959.68
02 LOCALIDAD PUEBLO LIBRE
02.01 CAPACITACION EN EDUCACION SANITARIA, PROMOCION DE LA SALUD Y AOM
02.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
02.01.01.01 TALLER IMPORTANCIA DE LA ORGANIZACION Y PARTICIPACION CIUDADANA Tall 1.00 940.60 940.60
02.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60 940.60
02.01.02 EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y SALUD)
02.01.02.01 TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y SALUD (Valoracion del agua) Tall 1.00 940.61 940.61
02.01.02.02 TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION DE EXCRETAS Tall 1.00 940.61 940.61
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL HOGAR Y
02.01.02.03 Tall 1.00 940.61 940.61
COMUNAL
02.01.02.04 CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE. Tall 1.00 940.61 940.61
02.01.02.05 DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y SANEAMIENTO (SPOT PUBLICITARIO) Men 2.00 84.74 169.48
02.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
02.01.03.01 TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS Tall 1.00 940.61 940.61
02.01.03.02 TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA POTABLE Tall 1.00 940.61 940.61
02.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61 940.61
02.01.03.04 TALLER DE CLORACION Y DESINFECCION DE AGUA PARA CONSUMO HUMANO Tall 1.00 1,110.11 1,110.11
02.02 FLETE
02.02.01 FLETE RURAL
02.02.01.01 FLETE RURAL GLB 1.00 34,884.02 34,884.02
02.02.02 FLETE TERRESTRE
02.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00 4,725.00
02.02.02.02 FLETE TERRESTRE GLB 1.00 17,338.98 17,338.98
02.02.03 MITIGACION AMBIENTAL
02.02.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00 2,840.00
02.02.03.02 PROGRAMA DE CONSERVACION, RESTAURACION Y COMPESACION DE COBERTURA VEGETAL (REFORESTACION) GLB 1.00 1,712.00 1,712.00
02.02.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00 3,400.00
02.02.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00 1,000.00
02.02.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 500.00 500.00
02.02.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00 3,600.00
02.02.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00 600.00
02.02.04 CONTROL Y SEGURIDAD EN OBRA
02.02.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 9,221.36 9,221.36
03 LOCALIDAD TANCARPATA
03.01 CAPACITACION EN EDUCACION SANITARIA, PROMOCION DE LA SALUD Y AOM
03.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
03.01.01.01 TALLER IMPORTANCIA DE LA ORGANIZACION Y PARTICIPACION CIUDADANA Tall 1.00 940.60 940.60
03.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60 940.60
03.01.02 EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y SALUD)
03.01.02.01 TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y SALUD (Valoracion del agua) Tall 1.00 940.61 940.61
03.01.02.02 TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION DE EXCRETAS Tall 1.00 940.61 940.61
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL HOGAR Y
03.01.02.03 Tall 1.00 940.61 940.61
COMUNAL
03.01.02.04 CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE. Tall 1.00 940.61 940.61
03.01.02.05 DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y SANEAMIENTO (SPOT PUBLICITARIO) Men 2.00 84.74 169.48
03.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
03.01.03.01 TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS Tall 1.00 940.61 940.61
03.01.03.02 TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA POTABLE Tall 1.00 940.61 940.61
03.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61 940.61
03.01.03.04 TALLER DE CLORACION Y DESINFECCION DE AGUA PARA CONSUMO HUMANO Tall 1.00 1,110.11 1,110.11
03.02 FLETE
03.02.01 FLETE RURAL
03.02.01.01 FLETE RURAL GLB 1.00 15,348.97 15,348.97
03.02.02 FLETE TERRESTRE
03.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00 4,725.00
03.02.02.02 FLETE TERRESTRE GLB 1.00 6,864.41 6,864.41
03.03 MITIGACION AMBIENTAL
03.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00 2,840.00
03.03.02 PROGRAMA DE CONSERVACION, RESTAURACION Y COMPESACION DE COBERTURA VEGETAL (REFORESTACION) GLB 1.00 1,712.00 1,712.00
03.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00 3,400.00
03.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00 1,000.00
03.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 500.00 500.00
03.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00 3,600.00
03.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00 600.00
03.04 CONTROL Y SEGURIDAD EN OBRA
03.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 4,564.96 4,564.96
04 LOCALIDAD TARACA
04.01 CAPACITACION EN EDUCACION SANITARIA, PROMOCION DE LA SALUD Y AOM
04.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
04.01.01.01 TALLER IMPORTANCIA DE LA ORGANIZACION Y PARTICIPACION CIUDADANA Tall 1.00 940.60 940.60
04.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60 940.60
04.01.02 EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y SALUD)
04.01.02.01 TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y SALUD (Valoracion del agua) Tall 1.00 940.61 940.61
04.01.02.02 TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION DE EXCRETAS Tall 1.00 940.61 940.61
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL HOGAR Y
04.01.02.03 Tall 1.00 940.61 940.61
COMUNAL
04.01.02.04 CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE. Tall 1.00 940.61 940.61
04.01.02.05 DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y SANEAMIENTO (SPOT PUBLICITARIO) Men 2.00 84.74 169.48
04.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
04.01.03.01 TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS Tall 1.00 940.61 940.61
04.01.03.02 TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA POTABLE Tall 1.00 940.61 940.61
04.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61 940.61
04.01.03.04 TALLER DE CLORACION Y DESINFECCION DE AGUA PARA CONSUMO HUMANO Tall 1.00 1,110.11 1,110.11
04.02 FLETE
04.02.01 FLETE RURAL
04.02.01.01 FLETE RURAL GLB 1.00 15,348.97 15,348.97
04.02.02 FLETE TERRESTRE
04.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00 4,725.00
04.02.02.02 FLETE TERRESTRE GLB 1.00 7,372.78 7,372.78
04.03 MITIGACION AMBIENTAL
04.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,839.85 2,839.85
04.03.02 PROGRAMA DE CONSERVACION, RESTAURACION Y COMPESACION DE COBERTURA VEGETAL (REFORESTACION) GLB 1.00 1,712.00 1,712.00
04.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00 3,400.00
04.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00 1,000.00
04.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 500.00 500.00
04.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00 3,600.00
04.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00 600.00
04.04 CONTROL Y SEGURIDAD EN OBRA
04.04.01 IMPLEMENTOS DE SEGURIDAD PUEBLO LIBRE GLB 1.00 4,564.96 4,564.96

COSTO DIRECTO 5,121,687.34

GASTOS GENERALES (8%) 408,710.65

UTILIDAD (7%) 358,518.11

==================

SUB TOTAL 5,888,916.09

IGV (18%) 1,060,004.90

==================

PRESUPUESTO DE OBRA 6,948,921.00


PARCIAL PARCIAL
ITEM DESCRIPCIÓN UNIDAD METRADO PRECIO (S/.) (S/.) AL (S/.) AL
100% 97%

01 LOCALIDAD SANTA LUCIA


01.01 CONSTRUCCIONES PROVISIONALES
01.01.01 OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y VESTUARIOS m2 100.00 44.55 4,455.00 4,321.35
01.01.02 ALQUILER DE PREDIOS PARA CAMPAMENTOS Y ALMACENES mes 6.00 500.00 3,000.00 2,910.00
01.01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20 m und 1.00 1,539.82 1,539.82 1,493.63
01.02 CAPTACION TIPO LADERA (ROBLEMONTE)
01.02.01 TRABAJOS PRELIMINARES
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49 24.01 23.29
01.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24 64.25
01.02.02 MOVIMIENTO DE TIERRAS
01.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 16.23 39.86 646.93 627.52
01.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO C/PISON m3 2.55 29.50 75.23 72.97
01.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95 214.65 208.21
01.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 17.10 25.69 439.30 426.12
01.02.03 CONCRETO SIMPLE
01.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17 706.52 685.32
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48 117.43 113.91
01.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55 58.73
01.02.04 CONCRETO ARMADO
01.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84 811.87 787.51
01.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48 797.53 773.60
01.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35 296.06 287.18
01.02.05 REVOQUES Y ENLUCIDOS
01.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3 e=1.5cm m2 5.53 32.48 179.61 174.22
01.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76 358.61 347.85
01.02.06 PINTURA
01.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 13.23 159.42 154.64
01.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
01.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85 265.53 257.56
01.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77 25.86 25.08
01.02.08 CARPINTERIA METALICA
01.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 179.83 179.83 174.44
01.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53 281.53 273.08
01.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO HIDRAULICO y VENTILACION
01.02.09.01 und 1.00 501.29 501.29 486.25
Ø=2")
01.02.10 CERCO PERIMETRICO EN CAPTACION
01.02.10.01 TRABAJOS PRELIMINARES
01.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84 44.16 42.84
01.02.10.02 MOVIMIENTO DE TIERRAS
01.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86 23.52 22.81
01.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75 18.19
01.02.10.03 CONCRETO SIMPLE
01.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98 210.03 203.73
01.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
01.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39 67.31
01.02.10.05 COLOCADO DE ROLLIZOS
01.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79 540.09
01.02.10.06 PINTURA EN CERCO PERIMETRICO
01.02.10.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 33.80 3.80 128.44 124.59
01.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
01.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22 533.28 517.28
01.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
01.02.10.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10 188.28
01.03 LINEA DE CONDUCCION (L=1102.00 m)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,102.00 0.49 539.98 523.78
01.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 1,102.00 1.53 1,686.06 1,635.48
01.03.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 1,102.00 1.53 1,686.06 1,635.48
01.03.02 MOVIMIENTO DE TIERRAS
01.03.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 396.72 49.82 19,764.59 19,171.65
01.03.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 44.08 55.80 2,459.66 2,385.87
01.03.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 1,102.00 1.81 1,994.62 1,934.78
01.03.02.04 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 110.20 6.08 670.02 649.92
01.03.02.05 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 165.30 36.40 6,016.92 5,836.41
01.03.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.50 m m3 27.55 65.17 1,795.43 1,741.57
01.03.02.07 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 27.55 25.69 707.76 686.53
01.03.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SP C-10, Ø=1" m 1,102.00 7.19 7,923.38 7,685.68
01.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 140.33 140.33 136.12
01.03.04 PRUEBA HIDRAULICA
01.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 1,102.00 1.51 1,664.02 1,614.10
01.03.05 CAMARA ROMPE PRESION T-6 (01 UND)
01.03.05.01 OBRAS PRELIMINARES
01.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.44 0.49 0.71 0.69
01.03.05.01.02 TRAZO Y REPLANTEO m2 1.44 1.84 2.65 2.57
01.03.05.02 MOVIMIENTO DE TIERRAS
01.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.58 39.86 62.98 61.09
01.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.98 25.69 50.87 49.34
01.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 1.44 7.95 11.45 11.11
01.03.05.03 OBRAS DE CONCRETO SIMPLE
01.03.05.03.01 SOLADO E=4" m3 1.21 35.81 43.33 42.03
01.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13 4.01
01.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90 8.63
01.03.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55 58.73
01.03.05.04 OBRAS DE CONCRETO ARMADO
01.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 0.79 546.69 431.89 418.93
01.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.10 44.48 360.29 349.48
01.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 37.23 4.35 161.95 157.09
01.03.05.05 REVOQUES Y ENLUCIDOS
01.03.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 2.52 32.48 81.85 79.39
01.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.24 29.76 96.42 93.53
01.03.05.06 PINTURA
01.03.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 3.24 11.18 36.22 35.13
01.03.05.07 CARPINTERIA METALICA
01.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 1.00 213.73 213.73 207.32
01.03.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.03.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T6, INGRESO Ø=1" y SALIDA Ø=1" und 1.00 299.60 299.60 290.61
01.03.06 VALVULA DE PURGA TIPO I (1 UND)
01.03.06.01 OBRAS PRELIMINARES
01.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 0.49 0.49 0.48
01.03.06.01.02 TRAZO Y REPLANTEO m2 1.00 1.84 1.84 1.78
01.03.06.02 MOVIMIENTO DE TIERRAS
01.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.51 39.86 20.33 19.72
01.03.06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 0.51 13.11 6.69 6.49
01.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.49 7.95 3.90 3.78
01.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 0.64 25.69 16.44 15.95
01.03.06.03 OBRAS DE CONCRETO SIMPLE
01.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.02 413.17 8.26 8.01
01.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.24 44.48 10.68 10.36
01.03.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.27 121.10 32.70 31.72
01.03.06.04 OBRAS DE CONCRETO ARMADO
01.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.35 546.69 191.34 185.60
01.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.72 44.48 165.47 160.51
01.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 14.94 4.35 64.99 63.04
01.03.06.05 REVOQUES Y ENLUCIDOS
01.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 1.44 32.48 46.77 45.37
01.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.36 29.76 99.99 96.99
01.03.06.06 PINTURA
01.03.06.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 2.16 11.18 24.15 23.43
01.03.06.07 CARPINTERIA METALICA
01.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 1.00 214.83 214.83 208.39
01.03.06.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.03.06.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO I, Ø=1" und 1.00 153.06 153.06 148.47
01.04 RESERVORIO (V=8.00 m3, 01 UND)
01.04.01 OBRAS PRELIMINARES
01.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49 17.64 17.11
01.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24 64.25
01.04.02 MOVIMIENTO DE TIERRAS
01.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 51.43 39.86 2,050.00 1,988.50
01.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 11.41 7.95 90.71 87.99
01.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 64.29 25.69 1,651.61 1,602.06
01.04.03 CONCRETO SIMPLE
01.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13 4.01
01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90 8.63
01.04.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55 58.73
01.04.04 OBRAS DE CONCRETO ARMADO
01.04.04.01 SOLADO PARA LOSA FONDO m2 11.41 40.87 466.33 452.34
01.04.04.02 CONCRETO f'c=210 kg/cm2 m3 11.27 546.69 6,161.20 5,976.36
01.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 51.29 44.48 2,281.38 2,212.94
01.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 322.94 4.35 1,404.79 1,362.65
01.04.05 REVOQUES Y ENLUCIDOS
01.04.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 31.32 32.48 1,017.27 986.75
01.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 40.61 29.76 1,208.55 1,172.29
01.04.06 PINTURA
01.04.06.01 PINTURA ESMALTE EN MUROS EXTERIORES DE RESERVORIO m2 34.92 13.23 461.99 448.13
01.04.07 CARPINTERIA METALICA
01.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46 414.64
01.04.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.04.08.01 SUMINISTRO E INSTALACIONES DE ACCESORIOS EN RESERVORIO (ING. 1 ", SAL.1") und 1.00 1,745.47 1,745.47 1,693.11
01.04.09 CERCO PERIMETRICO EN RESERVORIO
01.04.09.01 TRABAJOS PRELIMINARES
01.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84 66.24 64.25
01.04.09.02 MOVIMIENTO DE TIERRAS
01.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86 27.90 27.06
01.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75 18.19
01.04.09.03 CONCRETO SIMPLE
01.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98 249.19 241.71
01.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
01.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39 67.31
01.04.09.05 COLOCADO DE ROLLIZOS
01.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79 540.09
01.04.09.06 PINTURA EN CERCO PERIMETRICO
01.04.09.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 66.40 3.80 252.32 244.75
01.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
01.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22 515.50 500.04
01.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
01.04.09.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10 188.28
01.04.10 CLORADOR POR GOTEO
01.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
01.04.10.01.01 CASETA DE MURO DE LADRILLO -CLORADOR POR GOTEO
01.04.10.01.01.0
MURO DE LADRILLO PANDERETA (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 7.52 54.96 413.30 400.90
1
01.04.10.01.01.0
MURO DE LADRILLO PANDERETA INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 4.48 49.36 221.13 214.50
2
01.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
01.04.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 29.07 174.42 169.19
1
01.04.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 34.08 203.80 197.69
2
01.04.10.01.03 REVOQUES Y ENLUCIDOS
01.04.10.01.03.0
TARRAJEO MUROS DE INTERIORES Y EXTERIORES, CEMENTO : ARENA, 1:5 m2 14.98 30.00 449.40 435.92
1
01.04.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.78 55.12 53.47
2
01.04.10.01.04 CARPINTERIA METALICA
01.04.10.01.04.0
SUMINISTRO E INSTALACION DE PUERTA METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO und 1.00 367.18 367.18 356.16
1
01.04.10.01.05 PINTURAS
01.04.10.01.05.0
PINTURA ESMALTE EN MUROS INTERIORES Y EXTERIORES m2 14.98 11.18 167.48 162.46
1
01.04.10.01.05.0
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 12.25 49.00 47.53
2
01.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
01.04.10.02.01 SUMINISTRO E INSTALACION DE TANQUE DE POLIETILENO, CAP=250 LTRS. und 1.00 435.06 435.06 422.01
01.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
01.04.10.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS Y ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO GLB 1.00 939.22 939.22 911.04
01.05 RED DE ADUCCION Y DISTRIBUCION (L=4,375.00m)
01.05.01 TRABAJOS PRELIMINARES
01.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,187.50 0.49 1,071.88 1,039.72
01.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 4,375.00 1.53 6,693.75 6,492.94
01.05.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 4,375.00 1.53 6,693.75 6,492.94
01.05.02 MOVIMIENTO DE TIERRAS
01.05.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 525.00 39.86 20,926.50 20,298.71
01.05.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 1,137.50 49.82 56,670.25 54,970.14
01.05.02.03 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 87.50 55.80 4,882.50 4,736.03
01.05.02.04 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 4,375.00 1.81 7,918.75 7,681.19
01.05.02.05 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 4,375.00 6.08 26,600.00 25,802.00
01.05.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 623.44 36.40 22,693.22 22,012.42
01.05.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 32.81 65.17 2,138.23 2,074.08
01.05.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 1,181.25 25.07 29,613.94 28,725.52
01.05.02.09 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 142.19 62.16 8,838.53 8,573.37
01.05.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 87.50 25.69 2,247.88 2,180.44
01.05.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 1,820.00 8.05 14,651.00 14,211.47
01.05.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 3/4" m 2,555.00 4.84 12,366.20 11,995.21
01.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 137.74 137.74 133.61
01.05.04 PRUEBA HIDRAULICA
01.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 4,375.00 1.51 6,606.25 6,408.06
01.05.05 CAMARA ROMPE PRESION T-7 (11 UND)
01.05.05.01 OBRAS PRELIMINARES
01.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 22.77 0.49 11.16 10.83
01.05.05.01.02 TRAZO Y REPLANTEO m2 22.77 1.84 41.90 40.64
01.05.05.02 MOVIMIENTO DE TIERRAS
01.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 14.32 39.86 570.80 553.68
01.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 9.55 40.95 391.07 379.34
01.05.05.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 2.39 13.11 31.33 30.39
01.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 21.62 7.95 171.88 166.72
01.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.28 59.44 76.08 73.80
01.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 9.84 25.69 252.79 245.21
01.05.05.03 OBRAS DE CONCRETO SIMPLE
01.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.13 413.17 53.71 52.10
01.05.05.03.02 SOLADO E=4" m3 1.82 35.81 65.17 63.21
01.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.20 44.48 97.86 94.92
01.05.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 2.97 121.10 359.67 348.88
01.05.05.04 OBRAS DE CONCRETO ARMADO
01.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 14.96 546.69 8,178.48 7,933.13
01.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 153.14 44.48 6,811.67 6,607.32
01.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,164.62 4.35 9,416.10 9,133.62
01.05.05.05 REVOQUES Y ENLUCIDOS
01.05.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 47.52 32.48 1,543.45 1,497.15
01.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 102.98 29.76 3,064.68 2,972.74
01.05.05.06 PINTURA
01.05.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 66.00 11.18 737.88 715.74
01.05.05.07 CARPINTERIA METALICA
01.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 11.00 179.83 1,978.13 1,918.79
01.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 11.00 213.73 2,351.03 2,280.50
01.05.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=1" und 7.00 384.08 2,688.56 2,607.90
01.05.05.08.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=3/4" und 5.00 379.18 1,895.90 1,839.02
01.05.06 VALVULA DE CONTROL (05 UND)
01.05.06.01 OBRAS PRELIMINARES
01.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49 2.45 2.38
01.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.84 9.20 8.92
01.05.06.02 MOVIMIENTO DE TIERRAS
01.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 39.86 199.30 193.32
01.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 25.69 160.56 155.74
01.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.95 39.75 38.56
01.05.06.03 OBRAS DE CONCRETO ARMADO
01.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 546.69 1,350.32 1,309.81
01.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 44.48 947.42 919.00
01.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.35 668.94 648.87
01.05.06.04 REVOQUES Y ENLUCIDOS
01.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 32.48 233.86 226.84
01.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 29.76 321.41 311.77
01.05.06.05 PINTURA
01.05.06.05.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 6.48 11.18 72.45 70.28
01.05.06.06 CARPINTERIA METALICA
01.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 162.88 814.40 789.97
01.05.06.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=1" und 1.00 90.28 90.28 87.57
01.05.06.07.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=3/4" und 4.00 79.02 316.08 306.60
01.05.07 VALVULA DE PURGA TIPO II (08 UND)
01.05.07.01 OBRAS PRELIMINARES
01.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.00 0.49 3.92 3.80
01.05.07.01.02 TRAZO Y REPLANTEO m2 8.00 1.84 14.72 14.28
01.05.07.02 MOVIMIENTO DE TIERRAS
01.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 12.23 39.86 487.49 472.87
01.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 4.08 49.82 203.27 197.17
01.05.07.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 4.08 13.11 53.49 51.89
01.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 3.92 7.95 31.16 30.23
01.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.92 25.69 100.70 97.68
01.05.07.03 OBRAS DE CONCRETO SIMPLE
01.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 2.45 413.17 1,012.27 981.90
01.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.92 44.48 85.40 82.84
01.05.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 1.02 121.10 123.52 119.81
01.05.07.04 OBRAS DE CONCRETO ARMADO
01.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 2.80 546.69 1,530.73 1,484.81
01.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 29.76 44.48 1,323.72 1,284.01
01.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 119.53 4.35 519.96 504.36
01.05.07.05 REVOQUES Y ENLUCIDOS
01.05.07.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 11.52 32.48 374.17 362.94
01.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 26.88 29.76 799.95 775.95
01.05.07.06 PINTURA
01.05.07.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 12.96 11.18 144.89 140.54
01.05.07.07 CARPINTERIA METALICA
01.05.07.07.01 MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE 0.60x0.40m. und 8.00 213.73 1,709.84 1,658.54
01.05.07.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.07.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=1" und 1.00 149.25 149.25 144.77
01.05.07.08.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4" und 7.00 132.94 930.58 902.66
01.05.08 CONEXIONES DOMICILIARIAS (92 UND)
01.05.08.01 OBRAS PRELIMINARES
01.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 824.32 0.49 403.92 391.80
01.05.08.01.02 TRAZO Y REPLANTEO m2 1,236.48 1.84 2,275.12 2,206.87
01.05.08.02 MOVIMIENTO DE TIERRAS
01.05.08.02.01 EXCAVACION A MANO DE ZANJA MANUAL TERRENO NORMAL m3 989.18 39.86 39,428.71 38,245.85
01.05.08.02.02 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO CLASIFICADO m3 989.18 33.00 32,642.94 31,663.65
01.05.08.02.03 SUMINISTRO Y COLOCACION DE GRAVA SELECCIONADA m3 103.04 209.11 21,546.69 20,900.29
01.05.08.03 OBRAS DE CONCRETO SIMPLE
01.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 6.82 413.17 2,817.82 2,733.29
01.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 34.04 44.48 1,514.10 1,468.68
01.05.08.04 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND) und 92.00 80.77 7,430.84 7,207.91
01.05.08.04.02 TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON LLAVE TIPO BUJIA und 92.00 155.21 14,279.32 13,850.94
01.05.08.04.03 SUMINISTRO E INSTALACIONES DE ACOMETIDA DOMICILIARIA RANGO 2 - 50 M. m 736.00 3.50 2,576.00 2,498.72
02 LOCALIDAD PUEBLO LIBRE
02.01 CONSTRUCCIONES PROVISIONALES
02.01.01 OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y VESTUARIOS m2 100.00 44.55 4,455.00 4,321.35
02.01.02 ALQUILER DE PREDIOS PARA CAMPAMENTOS Y ALMACENES mes 6.00 500.00 3,000.00 2,910.00
02.01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20 m und 1.00 1,539.82 1,539.82 1,493.63
02.02 CAPTACION TIPO LADERA (YACUPACCARI)
02.02.01 TRABAJOS PRELIMINARES
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49 24.01 23.29
02.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24 64.25
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 22.53 39.86 898.05 871.11
02.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO C/PISON m3 2.55 29.50 75.23 72.97
02.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95 214.65 208.21
02.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 25.05 25.69 643.53 624.22
02.02.03 CONCRETO SIMPLE
02.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17 706.52 685.32
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48 117.43 113.91
02.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55 58.73
02.02.04 CONCRETO ARMADO
02.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84 811.87 787.51
02.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48 797.53 773.60
02.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35 296.06 287.18
02.02.05 REVOQUES Y ENLUCIDOS
02.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3 e=1.5cm m2 5.53 32.48 179.61 174.22
02.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76 358.61 347.85
02.02.06 PINTURA
02.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 13.23 159.42 154.64
02.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
02.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85 265.53 257.56
02.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77 25.86 25.08
02.02.08 CARPINTERIA METALICA
02.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 180.93 180.93 175.50
02.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53 281.53 273.08
02.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO HIDRAULICO y VENTILACION
02.02.09.01 und 1.00 501.29 501.29 486.25
Ø=2"
02.02.10 CERCO PERIMETRICO EN CAPTACION
02.02.10.01 TRABAJOS PRELIMINARES
02.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84 44.16 42.84
02.02.10.02 MOVIMIENTO DE TIERRAS
02.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86 23.52 22.81
02.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75 18.19
02.02.10.03 CONCRETO SIMPLE
02.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98 210.03 203.73
02.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
02.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39 67.31
02.02.10.05 COLOCADO DE ROLLIZOS
02.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79 540.09
02.02.10.06 PINTURA EN CERCO PERIMETRICO
02.02.10.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 33.80 3.80 128.44 124.59
02.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
02.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22 533.28 517.28
02.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
02.02.10.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10 188.28
02.03 CRUCE AEREO DE L=6.00 ML. (01 UNIDAD)
02.03.01 OBRAS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 22.40 0.49 10.98 10.65
02.03.01.02 TRAZO Y REPLANTEO m2 22.40 1.84 41.22 39.98
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION A MANO TERRENO NORMAL m3 2.57 39.86 102.44 99.37
02.03.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.21 25.69 82.46 79.99
02.03.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 3.28 7.95 26.08 25.30
02.03.03 OBRAS DE CONCRETO SIMPLE
02.03.03.01 CONCRETO F'C=100 KG/CM2.PARA SOLADOS m3 0.13 403.78 52.49 50.92
02.03.04 OBRAS DE CONCRETO ARMADO
02.03.04.01 CONCRETO FC=210 KG/CM2 m3 2.72 466.07 1,267.71 1,229.68
02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.50 44.48 111.20 107.86
02.03.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 40.12 4.35 174.52 169.28
02.03.05 REVOQUES Y ENLUCIDOS
02.03.05.01 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 2.50 29.76 74.40 72.17
02.03.06 PINTURA
02.03.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 2.50 19.51 48.78 47.32
02.03.07 TUBERIA TN ISO 65 SERIE LIVIANA (L)
02.03.07.01 SUMINISTRO E INSTALACION DE TUBERIA TN ISO 65 Ø 1" m 11.70 312.13 3,651.92 3,542.36
02.03.08 CABLE DE ACERO PRINCIPAL Ø 3/8" TIPO BOA
02.03.08.01 TENDIDO DE CABLE PRINCIPAL TIPO BOA Ø 3/8 m 7.86 37.33 293.41 284.61
02.03.09 PENDOLAS
02.03.09.01 PENDOLAS CON F° LISO Ø 1/4" m 14.40 35.37 509.33 494.05
02.03.10 ACCESORIOS
02.03.10.01 ACCESORIOS PARA ACUEDUCTO COLGANTE, ARGOLLA Ø 1", L=6.00ml und 1.00 934.94 934.94 906.89
02.04 LINEA DE CONDUCCION (L=2153.00 m)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,153.00 0.49 1,054.97 1,023.32
02.04.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 2,153.00 1.53 3,294.09 3,195.27
02.04.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 2,153.00 1.53 3,294.09 3,195.27
02.04.02 MOVIMIENTO DE TIERRAS
02.04.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 86.12 39.86 3,432.74 3,329.76
02.04.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 775.08 49.82 38,614.49 37,456.06
02.04.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 2,153.00 1.81 3,896.93 3,780.02
02.04.02.04 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 2,153.00 4.28 9,214.84 8,938.39
02.04.02.05 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 322.95 36.40 11,755.38 11,402.72
02.04.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 538.25 25.07 13,493.93 13,089.11
02.04.02.07 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 26.91 25.69 691.32 670.58
02.04.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.04.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 2,153.00 5.94 12,788.82 12,405.16
02.04.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 215.53 215.53 209.06
02.04.04 PRUEBA HIDRAULICA
02.04.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 2,153.00 1.51 3,251.03 3,153.50
02.04.05 CAMARA ROMPE PRESION T-6 (06 UND)
02.04.05.01 OBRAS PRELIMINARES
02.04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.64 0.49 4.23 4.10
02.04.05.01.02 TRAZO Y REPLANTEO m2 8.64 1.84 15.90 15.42
02.04.05.02 MOVIMIENTO DE TIERRAS
02.04.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 9.50 39.86 378.67 367.31
02.04.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.88 25.69 305.20 296.04
02.04.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 8.64 7.95 68.69 66.63
02.04.05.03 OBRAS DE CONCRETO SIMPLE
02.04.05.03.01 SOLADO E=4" m3 7.26 35.81 259.98 252.18
02.04.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.07 413.17 28.92 28.05
02.04.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 44.48 53.38 51.78
02.04.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 3.00 121.10 363.30 352.40
02.04.05.04 OBRAS DE CONCRETO ARMADO
02.04.05.04.01 CONCRETO f'c=210 kg/cm2 m3 4.74 546.69 2,591.31 2,513.57
02.04.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 48.60 44.48 2,161.73 2,096.88
02.04.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 223.37 4.35 971.66 942.51
02.04.05.05 REVOQUES Y ENLUCIDOS
02.04.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 15.12 32.48 491.10 476.37
02.04.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 19.44 29.76 578.53 561.17
02.04.05.06 PINTURA
02.04.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 19.44 11.18 217.34 210.82
02.04.05.07 CARPINTERIA METALICA
02.04.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 6.00 213.73 1,282.38 1,243.91
02.04.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.04.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T6, INGRESO Ø=1 1/2" y SALIDA Ø=1 1/2" und 6.00 299.60 1,797.60 1,743.67
02.04.06 VALVULA DE PURGA TIPO I (2 UND)
02.04.06.01 OBRAS PRELIMINARES
02.04.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.00 0.49 0.98 0.95
02.04.06.01.02 TRAZO Y REPLANTEO m2 2.00 1.84 3.68 3.57
02.04.06.02 MOVIMIENTO DE TIERRAS
02.04.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.02 39.86 40.66 39.44
02.04.06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 1.02 13.11 13.37 12.97
02.04.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.98 7.95 7.79 7.56
02.04.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1.27 25.69 32.63 31.65
02.04.06.03 OBRAS DE CONCRETO SIMPLE
02.04.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.04 413.17 16.53 16.03
02.04.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.48 44.48 21.35 20.71
02.04.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.54 121.10 65.39 63.43
02.04.06.04 OBRAS DE CONCRETO ARMADO
02.04.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.70 546.69 382.68 371.20
02.04.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.44 44.48 330.93 321.00
02.04.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 29.88 4.35 129.98 126.08
02.04.06.05 REVOQUES Y ENLUCIDOS
02.04.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 2.88 32.48 93.54 90.73
02.04.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.72 29.76 199.99 193.99
02.04.06.06 PINTURA
02.04.06.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 4.32 11.18 48.30 46.85
02.04.06.07 CARPINTERIA METALICA
02.04.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 2.00 214.83 429.66 416.77
02.04.06.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.04.06.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO I, Ø=1 1/2" und 2.00 153.06 306.12 296.94
02.05 RESERVORIO (V=10.00 m3, 01 UND)
02.05.01 OBRAS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49 17.64 17.11
02.05.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24 64.25
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 79.30 39.86 3,160.90 3,066.07
02.05.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 11.41 7.95 90.71 87.99
02.05.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 99.13 25.69 2,546.65 2,470.25
02.05.03 CONCRETO SIMPLE
02.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13 4.01
02.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90 8.63
02.05.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55 58.73
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 SOLADO PARA LOSA FONDO m2 11.41 40.87 466.33 452.34
02.05.04.02 CONCRETO f'c=210 kg/cm2 m3 13.50 546.69 7,380.32 7,158.91
02.05.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 57.48 44.48 2,556.71 2,480.01
02.05.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 349.49 4.35 1,520.28 1,474.67
02.05.05 REVOQUES Y ENLUCIDOS
02.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 32.94 32.48 1,069.89 1,037.79
02.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 57.14 29.76 1,700.49 1,649.48
02.05.06 PINTURA
02.05.06.01 PINTURA ESMALTE EN MUROS EXTERIORES DE RESERVORIO m2 51.45 13.23 680.68 660.26
02.05.07 CARPINTERIA METALICA
02.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46 414.64
02.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.05.08.01 SUMINISTRO E INSTALACIONES DE ACCESORIOS EN RESERVORIO (ING. 1", SAL.1") und 1.00 1,745.47 1,745.47 1,693.11
02.05.09 CERCO PERIMETRICO EN RESERVORIO
02.05.09.01 TRABAJOS PRELIMINARES
02.05.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84 66.24 64.25
02.05.09.02 MOVIMIENTO DE TIERRAS
02.05.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86 27.90 27.06
02.05.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75 18.19
02.05.09.03 CONCRETO SIMPLE
02.05.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98 249.19 241.71
02.05.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
02.05.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39 67.31
02.05.09.05 COLOCADO DE ROLLIZOS
02.05.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79 540.09
02.05.09.06 PINTURA EN CERCO PERIMETRICO
02.05.09.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 66.40 3.80 252.32 244.75
02.05.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
02.05.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22 515.50 500.04
02.05.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
02.05.09.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10 188.28
02.05.10 CLORADOR POR GOTEO
02.05.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
02.05.10.01.01 CASETA DE MURO DE LADRILLO -CLORADOR POR GOTEO
02.05.10.01.01.0
MURO DE LADRILLO PANDERETA (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 7.52 54.96 413.30 400.90
1
02.05.10.01.01.0
MURO DE LADRILLO PANDERETA INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 4.48 49.36 221.13 214.50
2
02.05.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
02.05.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 29.07 174.42 169.19
1
02.05.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 34.08 203.80 197.69
2
02.05.10.01.03 REVOQUES Y ENLUCIDOS
02.05.10.01.03.0
TARRAJEO MUROS DE INTERIORES Y EXTERIORES, CEMENTO : ARENA, 1:5 m2 14.98 30.00 449.40 435.92
1
02.05.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.78 55.12 53.47
2
02.05.10.01.04 CARPINTERIA METALICA
02.05.10.01.04.0
SUMINISTRO E INSTALACION DE PUERTA METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO und 1.00 367.18 367.18 356.16
1
02.05.10.01.05 PINTURAS
02.05.10.01.05.0
PINTURA ESMALTE EN MUROS INTERIORES Y EXTERIORES m2 14.98 11.18 167.48 162.46
1
02.05.10.01.05.0
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 12.25 49.00 47.53
2
02.05.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
02.05.10.02.01 SUMINISTRO E INSTALACION DE TANQUE DE POLIETILENO, CAP=250 LTRS. und 1.00 435.06 435.06 422.01
02.05.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
02.05.10.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS Y ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO GLB 1.00 939.22 939.22 911.04
02.06 RED DE ADUCCION Y DISTRIBUCION (L=5,678.00 m)
02.06.01 TRABAJOS PRELIMINARES
02.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,839.00 0.49 1,391.11 1,349.38
02.06.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 5,678.00 1.53 8,687.34 8,426.72
02.06.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 5,678.00 1.53 8,687.34 8,426.72
02.06.02 MOVIMIENTO DE TIERRAS
02.06.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 1,362.72 49.82 67,890.71 65,853.99
02.06.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 908.48 55.80 50,693.18 49,172.38
02.06.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 5,678.00 1.81 10,277.18 9,968.86
02.06.02.04 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 2,271.20 6.08 13,808.90 13,394.63
02.06.02.05 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 511.02 36.40 18,601.13 18,043.10
02.06.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 567.80 65.17 37,003.53 35,893.42
02.06.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 1,987.30 25.07 49,821.61 48,326.96
02.06.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 1,135.60 62.16 70,588.90 68,471.23
02.06.02.09 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 567.80 25.69 14,586.78 14,149.18
02.06.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 1,146.00 8.05 9,225.30 8,948.54
02.06.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 3/4" m 4,533.00 4.84 21,939.72 21,281.53
02.06.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 351.43 351.43 340.89
02.06.04 PRUEBA HIDRAULICA
02.06.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 5,678.00 1.51 8,573.78 8,316.57
02.06.05 CAMARA ROMPE PRESION T-7 (16 UND)
02.06.05.01 OBRAS PRELIMINARES
02.06.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 33.12 0.49 16.23 15.74
02.06.05.01.02 TRAZO Y REPLANTEO m2 33.12 1.84 60.94 59.11
02.06.05.02 MOVIMIENTO DE TIERRAS
02.06.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 22.91 39.86 913.19 885.79
02.06.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 15.27 40.95 625.31 606.55
02.06.05.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 3.82 13.11 50.08 48.58
02.06.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 31.44 7.95 249.95 242.45
02.06.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.86 59.44 110.56 107.24
02.06.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 22.91 25.69 588.56 570.90
02.06.05.03 OBRAS DE CONCRETO SIMPLE
02.06.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.19 413.17 78.50 76.15
02.06.05.03.02 SOLADO E=4" m3 2.64 35.81 94.54 91.70
02.06.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.20 44.48 142.34 138.07
02.06.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 4.32 121.10 523.15 507.46
02.06.05.04 OBRAS DE CONCRETO ARMADO
02.06.05.04.01 CONCRETO f'c=210 kg/cm2 m3 21.74 546.69 11,885.04 11,528.49
02.06.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 222.76 44.48 9,908.36 9,611.11
02.06.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 3,148.54 4.35 13,696.15 13,285.27
02.06.05.05 REVOQUES Y ENLUCIDOS
02.06.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 69.12 32.48 2,245.02 2,177.67
02.06.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 149.79 29.76 4,457.75 4,324.02
02.06.05.06 PINTURA
02.06.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 96.00 11.18 1,073.28 1,041.08
02.06.05.07 CARPINTERIA METALICA
02.06.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 16.00 179.83 2,877.28 2,790.96
02.06.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 16.00 213.73 3,419.68 3,317.09
02.06.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=1" und 3.00 384.08 1,152.24 1,117.67
02.06.05.08.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=3/4" und 13.00 379.18 4,929.34 4,781.46
02.06.06 VALVULA DE CONTROL (05 UND)
02.06.06.01 OBRAS PRELIMINARES
02.06.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.00 0.49 2.94 2.85
02.06.06.01.02 TRAZO Y REPLANTEO m2 6.00 1.84 11.04 10.71
02.06.06.02 MOVIMIENTO DE TIERRAS
02.06.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 6.00 39.86 239.16 231.99
02.06.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 7.50 25.69 192.68 186.90
02.06.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 6.00 7.95 47.70 46.27
02.06.06.03 OBRAS DE CONCRETO ARMADO
02.06.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.96 546.69 1,618.20 1,569.65
02.06.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 25.56 44.48 1,136.91 1,102.80
02.06.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 184.53 4.35 802.71 778.63
02.06.06.04 REVOQUES Y ENLUCIDOS
02.06.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 8.64 32.48 280.63 272.21
02.06.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 12.96 29.76 385.69 374.12
02.06.06.05 PINTURA
02.06.06.05.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 12.96 11.18 144.89 140.54
02.06.06.06 CARPINTERIA METALICA
02.06.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 6.00 162.88 977.28 947.96
02.06.06.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=1" und 2.00 90.28 180.56 175.14
02.06.06.07.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=3/4" und 4.00 79.02 316.08 306.60
02.06.07 VALVULA DE PURGA TIPO II (03 UND)
02.06.07.01 OBRAS PRELIMINARES
02.06.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 3.00 0.49 1.47 1.43
02.06.07.01.02 TRAZO Y REPLANTEO m2 3.00 1.84 5.52 5.35
02.06.07.02 MOVIMIENTO DE TIERRAS
02.06.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 4.59 39.86 182.96 177.47
02.06.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 1.53 49.82 76.22 73.93
02.06.07.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 1.53 13.11 20.06 19.46
02.06.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 1.47 7.95 11.69 11.34
02.06.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.47 25.69 37.76 36.63
02.06.07.03 OBRAS DE CONCRETO SIMPLE
02.06.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.92 413.17 380.12 368.72
02.06.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.72 44.48 32.03 31.07
02.06.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.38 121.10 46.02 44.64
02.06.07.04 OBRAS DE CONCRETO ARMADO
02.06.07.04.01 CONCRETO f'c=210 kg/cm2 m3 1.05 546.69 574.02 556.80
02.06.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 11.16 44.48 496.40 481.51
02.06.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 44.82 4.35 194.97 189.12
02.06.07.05 REVOQUES Y ENLUCIDOS
02.06.07.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 4.32 32.48 140.31 136.10
02.06.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.08 29.76 299.98 290.98
02.06.07.06 PINTURA
02.06.07.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 4.84 11.18 54.11 52.49
02.06.07.07 CARPINTERIA METALICA
02.06.07.07.01 MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE 0.60x0.40m. und 3.00 213.73 641.19 621.95
02.06.07.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.07.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4" und 3.00 132.94 398.82 386.86
02.06.08 CONEXIONES DOMICILIARIAS (125 UND)
02.06.08.01 OBRAS PRELIMINARES
02.06.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,120.00 0.49 548.80 532.34
02.06.08.01.02 TRAZO Y REPLANTEO m2 1,680.00 1.84 3,091.20 2,998.46
02.06.08.02 MOVIMIENTO DE TIERRAS
02.06.08.02.01 EXCAVACION A MANO DE ZANJA MANUAL TERRENO NORMAL m3 1,344.00 39.86 53,571.84 51,964.68
02.06.08.02.02 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO CLASIFICADO m3 1,344.00 33.00 44,352.00 43,021.44
02.06.08.02.03 SUMINISTRO Y COLOCACION DE GRAVA SELECCIONADA m3 140.00 209.11 29,275.40 28,397.14
02.06.08.03 OBRAS DE CONCRETO SIMPLE
02.06.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 9.27 413.17 3,830.09 3,715.19
02.06.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 46.25 44.48 2,057.20 1,995.48
02.06.08.04 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND) und 125.00 80.77 10,096.25 9,793.36
02.06.08.04.02 TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON LLAVE TIPO BUJIA und 125.00 155.21 19,401.25 18,819.21
02.06.08.04.03 SUMINISTRO E INSTALACIONES DE ACOMETIDA DOMICILIARIA RANGO 2 - 20 M. m 1,125.00 3.50 3,937.50 3,819.38
03 LOCALIDAD TANCARPATA
03.01 CONSTRUCCIONES PROVISIONALES
03.01.01 OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y VESTUARIOS m2 100.00 44.55 4,455.00 4,321.35
03.01.02 ALQUILER DE PREDIOS PARA CAMPAMENTOS Y ALMACENES mes 6.00 500.00 3,000.00 2,910.00
03.01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20 m und 1.00 1,539.82 1,539.82 1,493.63
03.02 CAPTACION A TIPO LADERA YACUTOCCYAC (01 UND)
03.02.01 TRABAJOS PRELIMINARES
03.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49 24.01 23.29
03.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24 64.25
03.02.02 MOVIMIENTO DE TIERRAS
03.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 15.03 39.86 599.10 581.13
03.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO C/PISON m3 2.55 29.50 75.23 72.97
03.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95 214.65 208.21
03.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.60 25.69 400.76 388.74
03.02.03 CONCRETO SIMPLE
03.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17 706.52 685.32
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48 117.43 113.91
03.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55 58.73
03.02.04 CONCRETO ARMADO
03.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84 811.87 787.51
03.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48 797.53 773.60
03.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35 296.06 287.18
03.02.05 REVOQUES Y ENLUCIDOS
03.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3 e=1.5cm m2 5.53 32.48 179.61 174.22
03.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76 358.61 347.85
03.02.06 PINTURA
03.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 13.23 159.42 154.64
03.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
03.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85 265.53 257.56
03.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77 25.86 25.08
03.02.08 CARPINTERIA METALICA
03.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 180.93 180.93 175.50
03.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53 281.53 273.08
03.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO HIDRAULICO y VENTILACION
03.02.09.01 und 1.00 497.69 497.69 482.76
Ø=2")
03.02.10 CERCO PERIMETRICO EN CAPTACION
03.02.10.01 TRABAJOS PRELIMINARES
03.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84 44.16 42.84
03.02.10.02 MOVIMIENTO DE TIERRAS
03.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86 23.52 22.81
03.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75 18.19
03.02.10.03 CONCRETO SIMPLE
03.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98 210.03 203.73
03.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
03.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39 67.31
03.02.10.05 COLOCADO DE ROLLIZOS
03.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79 540.09
03.02.10.06 PINTURA EN CERCO PERIMETRICO
03.02.10.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 33.80 3.80 128.44 124.59
03.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
03.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22 533.28 517.28
03.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
03.02.10.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10 188.28
03.03 LINEA DE CONDUCCION (L=196.00 m)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 196.00 0.49 96.04 93.16
03.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 196.00 1.53 299.88 290.88
03.03.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 196.00 1.53 299.88 290.88
03.03.02 MOVIMIENTO DE TIERRAS
03.03.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 72.13 49.82 3,593.52 3,485.71
03.03.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 6.27 55.80 349.87 339.37
03.03.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 196.00 1.81 354.76 344.12
03.03.02.04 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 196.00 6.08 1,191.68 1,155.93
03.03.02.05 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 196.00 4.28 838.88 813.71
03.03.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 27.05 36.40 984.62 955.08
03.03.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 2.35 65.17 153.15 148.56
03.03.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 45.05 25.07 1,129.40 1,095.52
03.03.02.09 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 3.92 62.16 243.67 236.36
03.03.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.92 25.69 100.70 97.68
03.03.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 196.00 5.94 1,164.24 1,129.31
03.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 160.91 160.91 156.08
03.03.04 PRUEBA HIDRAULICA
03.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 180.36 1.51 272.34 264.17
03.03.05 CAMARA ROMPE PRESION T-6 (01 UND)
03.03.05.01 OBRAS PRELIMINARES
03.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.44 0.49 0.71 0.69
03.03.05.01.02 TRAZO Y REPLANTEO m2 1.44 1.84 2.65 2.57
03.03.05.02 MOVIMIENTO DE TIERRAS
03.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.58 39.86 62.98 61.09
03.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.98 25.69 50.87 49.34
03.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 1.44 7.95 11.45 11.11
03.03.05.03 OBRAS DE CONCRETO SIMPLE
03.03.05.03.01 SOLADO E=4" m3 1.21 35.81 43.33 42.03
03.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13 4.01
03.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90 8.63
03.03.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55 58.73
03.03.05.04 OBRAS DE CONCRETO ARMADO
03.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 0.79 546.69 431.89 418.93
03.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.10 44.48 360.29 349.48
03.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 37.23 4.35 161.95 157.09
03.03.05.05 REVOQUES Y ENLUCIDOS
03.03.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 2.52 32.48 81.85 79.39
03.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.24 29.76 96.42 93.53
03.03.05.06 PINTURA
03.03.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 3.24 11.18 36.22 35.13
03.03.05.07 CARPINTERIA METALICA
03.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 1.00 213.73 213.73 207.32
03.03.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.03.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T6, INGRESO Ø=1 y SALIDA Ø=1 " und 1.00 299.60 299.60 290.61
03.03.06 VALVULA DE PURGA TIPO I (1 UND)
03.03.06.01 OBRAS PRELIMINARES
03.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 0.49 0.49 0.48
03.03.06.01.02 TRAZO Y REPLANTEO m2 1.00 1.84 1.84 1.78
03.03.06.02 MOVIMIENTO DE TIERRAS
03.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.51 39.86 20.33 19.72
03.03.06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 0.51 13.11 6.69 6.49
03.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.49 7.95 3.90 3.78
03.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 0.64 25.69 16.44 15.95
03.03.06.03 OBRAS DE CONCRETO SIMPLE
03.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.20 413.17 82.63 80.15
03.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.24 44.48 10.68 10.36
03.03.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.27 121.10 32.70 31.72
03.03.06.04 OBRAS DE CONCRETO ARMADO
03.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.35 546.69 191.34 185.60
03.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.72 44.48 165.47 160.51
03.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 14.94 4.35 64.99 63.04
03.03.06.05 REVOQUES Y ENLUCIDOS
03.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 1.44 32.48 46.77 45.37
03.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.36 29.76 99.99 96.99
03.03.06.06 PINTURA
03.03.06.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 2.16 11.18 24.15 23.43
03.03.06.07 CARPINTERIA METALICA
03.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 1.00 214.83 214.83 208.39
03.03.06.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.03.06.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO I, Ø=1" und 1.00 153.06 153.06 148.47
03.04 RESERVORIO (V=5.00 m3, 01 UND)
03.04.01 OBRAS PRELIMINARES
03.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49 17.64 17.11
03.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24 64.25
03.04.02 MOVIMIENTO DE TIERRAS
03.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 60.95 39.86 2,429.47 2,356.59
03.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 8.05 7.95 64.00 62.08
03.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 76.19 25.69 1,957.32 1,898.60
03.04.03 CONCRETO SIMPLE
03.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13 4.01
03.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90 8.63
03.04.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55 58.73
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 SOLADO PARA LOSA FONDO m2 8.05 40.87 329.00 319.13
03.04.04.02 CONCRETO f'c=210 kg/cm2 m3 9.51 546.69 5,199.02 5,043.05
03.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 49.52 44.48 2,202.65 2,136.57
03.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 254.64 4.35 1,107.68 1,074.45
03.04.05 REVOQUES Y ENLUCIDOS
03.04.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 31.00 32.48 1,006.88 976.67
03.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 35.50 29.76 1,056.48 1,024.79
03.04.06 PINTURA
03.04.06.01 PINTURA ESMALTE EN MUROS EXTERIORES DE RESERVORIO m2 29.15 13.23 385.65 374.08
03.04.07 CARPINTERIA METALICA
03.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46 414.64
03.04.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.04.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN RESERVORIO (INGRESO Ø 1"-LIMPIA, REBOSE y SELLO HIDR. Ø 2"-VENTILAC. Ø 3") und 1.00 1,618.16 1,618.16 1,569.62
03.04.09 CERCO PERIMETRICO EN RESERVORIO
03.04.09.01 TRABAJOS PRELIMINARES
03.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84 66.24 64.25
03.04.09.02 MOVIMIENTO DE TIERRAS
03.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86 27.90 27.06
03.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75 18.19
03.04.09.03 CONCRETO SIMPLE
03.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98 249.19 241.71
03.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
03.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39 67.31
03.04.09.05 COLOCADO DE ROLLIZOS
03.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79 540.09
03.04.09.06 PINTURA EN CERCO PERIMETRICO
03.04.09.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 66.40 3.80 252.32 244.75
03.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
03.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22 515.50 500.04
03.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
03.04.09.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10 188.28
03.04.10 CLORADOR POR GOTEO
03.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
03.04.10.01.01 CASETA DE MURO DE LADRILLO -CLORADOR POR GOTEO
03.04.10.01.01.0
MURO DE LADRILLO PANDERETA (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 7.52 54.96 413.30 400.90
1
03.04.10.01.01.0
MURO DE LADRILLO PANDERETA INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 4.48 49.36 221.13 214.50
2
03.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
03.04.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 29.07 174.42 169.19
1
03.04.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 34.08 203.80 197.69
2
03.04.10.01.03 REVOQUES Y ENLUCIDOS
03.04.10.01.03.0
TARRAJEO MUROS DE INTERIORES Y EXTERIORES, CEMENTO : ARENA, 1:5 m2 14.98 30.00 449.40 435.92
1
03.04.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.78 55.12 53.47
2
03.04.10.01.04 CARPINTERIA METALICA
03.04.10.01.04.0
SUMINISTRO E INSTALACION DE PUERTA METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO und 1.00 367.18 367.18 356.16
1
03.04.10.01.05 PINTURAS
03.04.10.01.05.0
PINTURA ESMALTE EN MUROS INTERIORES Y EXTERIORES m2 14.98 11.18 167.48 162.46
1
03.04.10.01.05.0
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 12.25 49.00 47.53
2
03.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
03.04.10.02.01 SUMINISTRO E INSTALACION DE TANQUE DE POLIETILENO, CAP=250 LTRS. und 1.00 435.06 435.06 422.01
03.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
03.04.10.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS Y ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO GLB 1.00 939.22 939.22 911.04
03.05 RED DE ADUCCION Y DISTRIBUCION (L=2,740.00 m)
03.05.01 TRABAJOS PRELIMINARES
03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,370.00 0.49 671.30 651.16
03.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 2,740.00 1.53 4,192.20 4,066.43
03.05.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 2,740.00 1.53 4,192.20 4,066.43
03.05.02 MOVIMIENTO DE TIERRAS
03.05.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 1,041.20 49.82 51,872.58 50,316.40
03.05.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 54.80 55.80 3,057.84 2,966.10
03.05.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 2,740.00 1.81 4,959.40 4,810.62
03.05.02.04 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 137.00 6.08 832.96 807.97
03.05.02.05 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 390.45 36.40 14,212.38 13,786.01
03.05.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 20.55 65.17 1,339.24 1,299.06
03.05.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 719.25 25.07 18,031.60 17,490.65
03.05.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 68.50 62.16 4,257.96 4,130.22
03.05.02.09 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 34.25 25.69 879.88 853.48
03.05.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 4.00 8.05 32.20 31.23
03.05.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 3/4" m 2,736.00 4.84 13,242.24 12,844.97
03.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 96.63 96.63 93.73
03.05.04 PRUEBA HIDRAULICA
03.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 2,740.00 1.51 4,137.40 4,013.28
03.05.05 CAMARA ROMPE PRESION T-7 (09 UND)
03.05.05.01 OBRAS PRELIMINARES
03.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 18.63 0.49 9.13 8.86
03.05.05.01.02 TRAZO Y REPLANTEO m2 18.63 1.84 34.28 33.25
03.05.05.02 MOVIMIENTO DE TIERRAS
03.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 14.32 39.86 570.80 553.68
03.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 7.16 40.95 293.20 284.40
03.05.05.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 2.39 13.11 31.33 30.39
03.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 17.69 7.95 140.64 136.42
03.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.06 59.44 63.01 61.12
03.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 8.06 25.69 207.06 200.85
03.05.05.03 OBRAS DE CONCRETO SIMPLE
03.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.11 413.17 45.45 44.09
03.05.05.03.02 SOLADO E=4" m3 1.49 35.81 53.36 51.76
03.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.80 44.48 80.06 77.66
03.05.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 2.43 121.10 294.27 285.44
03.05.05.04 OBRAS DE CONCRETO ARMADO
03.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 12.23 546.69 6,686.02 6,485.44
03.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 125.30 44.48 5,573.34 5,406.14
03.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,771.06 4.35 7,704.11 7,472.99
03.05.05.05 REVOQUES Y ENLUCIDOS
03.05.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 38.88 32.48 1,262.82 1,224.94
03.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 84.26 29.76 2,507.58 2,432.35
03.05.05.06 PINTURA
03.05.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 54.00 11.18 603.72 585.61
03.05.05.07 CARPINTERIA METALICA
03.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 9.00 179.83 1,618.47 1,569.92
03.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 9.00 213.73 1,923.57 1,865.86
03.05.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=3/4" und 9.00 379.18 3,412.62 3,310.24
03.05.06 VALVULA DE CONTROL (05 UND)
03.05.06.01 OBRAS PRELIMINARES
03.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49 2.45 2.38
03.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.84 9.20 8.92
03.05.06.02 MOVIMIENTO DE TIERRAS
03.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 39.86 199.30 193.32
03.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 25.69 160.56 155.74
03.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.95 39.75 38.56
03.05.06.03 OBRAS DE CONCRETO ARMADO
03.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 546.69 1,350.32 1,309.81
03.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 44.48 947.42 919.00
03.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.35 668.94 648.87
03.05.06.04 REVOQUES Y ENLUCIDOS
03.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 32.48 233.86 226.84
03.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 29.76 321.41 311.77
03.05.06.05 PINTURA
03.05.06.05.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 10.80 11.18 120.74 117.12
03.05.06.06 CARPINTERIA METALICA
03.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 162.88 814.40 789.97
03.05.06.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=3/4" und 5.00 79.02 395.10 383.25
03.05.07 VALVULA DE PURGA TIPO II (06 UND)
03.05.07.01 OBRAS PRELIMINARES
03.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.00 0.49 2.94 2.85
03.05.07.01.02 TRAZO Y REPLANTEO m2 6.00 1.84 11.04 10.71
03.05.07.02 MOVIMIENTO DE TIERRAS
03.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 9.17 39.86 365.52 354.55
03.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 3.06 49.82 152.45 147.88
03.05.07.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 3.06 13.11 40.12 38.92
03.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 2.94 7.95 23.37 22.67
03.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 2.94 25.69 75.53 73.26
03.05.07.03 OBRAS DE CONCRETO SIMPLE
03.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 1.84 413.17 760.23 737.42
03.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.44 44.48 64.05 62.13
03.05.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.77 121.10 93.25 90.45
03.05.07.04 OBRAS DE CONCRETO ARMADO
03.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 2.10 546.69 1,148.05 1,113.61
03.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 23.32 44.48 1,037.27 1,006.15
03.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 86.64 4.35 376.88 365.57
03.05.07.05 REVOQUES Y ENLUCIDOS
03.05.07.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 8.64 32.48 280.63 272.21
03.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 20.16 29.76 599.96 581.96
03.05.07.06 PINTURA
03.05.07.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 9.72 11.18 108.67 105.41
03.05.07.07 CARPINTERIA METALICA
03.05.07.07.01 MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE 0.60x0.40m. und 6.00 213.73 1,282.38 1,243.91
03.05.07.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.07.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4" und 6.00 132.94 797.64 773.71
03.05.08 CONEXIONES DOMICILIARIAS (53 UND)
03.05.08.01 OBRAS PRELIMINARES
03.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 474.88 0.49 232.69 225.71
03.05.08.01.02 TRAZO Y REPLANTEO m2 712.32 1.84 1,310.67 1,271.35
03.05.08.02 MOVIMIENTO DE TIERRAS
03.05.08.02.01 EXCAVACION A MANO DE ZANJA MANUAL TERRENO NORMAL m3 569.86 39.86 22,714.62 22,033.18
03.05.08.02.02 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO CLASIFICADO m3 569.86 33.00 18,805.38 18,241.22
03.05.08.02.03 SUMINISTRO Y COLOCACION DE GRAVA SELECCIONADA m3 50.36 209.11 10,530.78 10,214.86
03.05.08.03 OBRAS DE CONCRETO SIMPLE
03.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 3.93 413.17 1,623.76 1,575.05
03.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.61 44.48 872.25 846.08
03.05.08.04 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND) und 53.00 80.77 4,280.81 4,152.39
03.05.08.04.02 TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON LLAVE TIPO BUJIA und 53.00 155.21 8,226.13 7,979.35
03.05.08.04.03 SUMINISTRO E INSTALACIONES DE ACOMETIDA DOMICILIARIA RANGO 2 - 20 M. m 530.00 3.50 1,855.00 1,799.35
04 LOCALIDAD TARACA
04.01 CONSTRUCCIONES PROVISIONALES
04.01.01 OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y VESTUARIOS m2 100.00 44.55 4,455.00 4,321.35
04.01.02 ALQUILER DE PREDIOS PARA CAMPAMENTOS Y ALMACENES mes 6.00 500.00 3,000.00 2,910.00
04.01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20 m und 1.00 1,539.82 1,539.82 1,493.63
04.02 CAPTACION A TIPO LADERA YACUTOCCYAC (01 UND)
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49 24.01 23.29
04.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24 64.25
04.02.02 MOVIMIENTO DE TIERRAS
04.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 17.55 39.86 699.54 678.55
04.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO C/PISON m3 2.55 29.50 75.23 72.97
04.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95 214.65 208.21
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.60 25.69 400.76 388.74
04.02.03 CONCRETO SIMPLE
04.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17 706.52 685.32
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48 117.43 113.91
04.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55 58.73
04.02.04 CONCRETO ARMADO
04.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84 811.87 787.51
04.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48 797.53 773.60
04.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35 296.06 287.18
04.02.05 REVOQUES Y ENLUCIDOS
04.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3 e=1.5cm m2 5.53 32.48 179.61 174.22
04.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76 358.61 347.85
04.02.06 PINTURA
04.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 13.23 159.42 154.64
04.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
04.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85 265.53 257.56
04.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77 25.86 25.08
04.02.08 CARPINTERIA METALICA
04.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 180.93 180.93 175.50
04.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53 281.53 273.08
04.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO HIDRAULICO y VENTILACION
04.02.09.01 und 1.00 497.69 497.69 482.76
Ø=2")
04.02.10 CERCO PERIMETRICO EN CAPTACION
04.02.10.01 TRABAJOS PRELIMINARES
04.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84 44.16 42.84
04.02.10.02 MOVIMIENTO DE TIERRAS
04.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86 23.52 22.81
04.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75 18.19
04.02.10.03 CONCRETO SIMPLE
04.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98 210.03 203.73
04.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
04.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39 67.31
04.02.10.05 COLOCADO DE ROLLIZOS
04.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79 540.09
04.02.10.06 PINTURA EN CERCO PERIMETRICO
04.02.10.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 33.80 3.80 128.44 124.59
04.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
04.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22 533.28 517.28
04.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
04.02.10.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10 188.28
04.03 LINEA DE CONDUCCION (L=1231.00 m)
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,231.00 0.49 603.19 585.09
04.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 1,231.00 1.53 1,883.43 1,826.93
04.03.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 1,231.00 1.53 1,883.43 1,826.93
04.03.02 MOVIMIENTO DE TIERRAS
04.03.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 392.92 39.86 15,661.79 15,191.94
04.03.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 73.86 49.82 3,679.71 3,569.32
04.03.02.03 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 15.39 55.80 858.76 833.00
04.03.02.04 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 1,231.00 1.81 2,228.11 2,161.27
04.03.02.05 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 61.55 6.08 374.22 362.99
04.03.02.06 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 1,231.00 4.28 5,268.68 5,110.62
04.03.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 175.42 36.40 6,385.29 6,193.73
04.03.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 9.23 65.17 601.52 583.47
04.03.02.09 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 292.36 25.07 7,329.47 7,109.59
04.03.02.10 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 6.16 62.16 382.91 371.42
04.03.02.11 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.39 25.69 395.37 383.51
04.03.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 1,231.00 5.94 7,312.14 7,092.78
04.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 157.71 157.71 152.98
04.03.04 PRUEBA HIDRAULICA
04.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 1,231.00 1.51 1,858.81 1,803.05
04.03.05 CAMARA ROMPE PRESION T-6 (02 UND)
04.03.05.01 OBRAS PRELIMINARES
04.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.88 0.49 1.41 1.37
04.03.05.01.02 TRAZO Y REPLANTEO m2 2.88 1.84 5.30 5.14
04.03.05.02 MOVIMIENTO DE TIERRAS
04.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 3.17 39.86 126.36 122.57
04.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 7.92 25.69 203.46 197.36
04.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 2.88 7.95 22.90 22.21
04.03.05.03 OBRAS DE CONCRETO SIMPLE
04.03.05.03.01 SOLADO E=4" m3 2.42 35.81 86.66 84.06
04.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.02 413.17 8.26 8.01
04.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.40 44.48 17.79 17.26
04.03.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 1.00 121.10 121.10 117.47
04.03.05.04 OBRAS DE CONCRETO ARMADO
04.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 546.69 863.77 837.86
04.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 16.20 44.48 720.58 698.96
04.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 74.46 4.35 323.90 314.18
04.03.05.05 REVOQUES Y ENLUCIDOS
04.03.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 5.04 32.48 163.70 158.79
04.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.48 29.76 192.84 187.05
04.03.05.06 PINTURA
04.03.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 6.48 11.18 72.45 70.28
04.03.05.07 CARPINTERIA METALICA
04.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46 414.64
04.03.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.03.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T6, INGRESO Ø=1 y SALIDA Ø=1 " und 2.00 299.60 599.20 581.22
04.03.06 VALVULA DE PURGA TIPO I (1 UND)
04.03.06.01 OBRAS PRELIMINARES
04.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.00 0.49 0.98 0.95
04.03.06.01.02 TRAZO Y REPLANTEO m2 2.00 1.84 3.68 3.57
04.03.06.02 MOVIMIENTO DE TIERRAS
04.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.02 39.86 40.66 39.44
04.03.06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 1.02 13.11 13.37 12.97
04.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.98 7.95 7.79 7.56
04.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1.27 25.69 32.63 31.65
04.03.06.03 OBRAS DE CONCRETO SIMPLE
04.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.04 413.17 16.53 16.03
04.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.48 44.48 21.35 20.71
04.03.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.54 121.10 65.39 63.43
04.03.06.04 OBRAS DE CONCRETO ARMADO
04.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.70 546.69 382.68 371.20
04.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.44 44.48 330.93 321.00
04.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 29.88 4.35 129.98 126.08
04.03.06.05 REVOQUES Y ENLUCIDOS
04.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 2.88 32.48 93.54 90.73
04.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.72 29.76 199.99 193.99
04.03.06.06 PINTURA
04.03.06.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 4.32 11.18 48.30 46.85
04.03.06.07 CARPINTERIA METALICA
04.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 2.00 214.83 429.66 416.77
04.03.06.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.03.06.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO I, Ø=1" und 2.00 153.06 306.12 296.94
04.04 RESERVORIO (V=5.00 m3, 01 UND)
04.04.01 OBRAS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49 17.64 17.11
04.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24 64.25
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 36.02 39.86 1,435.76 1,392.69
04.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 8.05 7.95 64.00 62.08
04.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 45.02 25.69 1,156.56 1,121.86
04.04.03 CONCRETO SIMPLE
04.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13 4.01
04.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90 8.63
04.04.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10 60.55 58.73
04.04.04 OBRAS DE CONCRETO ARMADO
04.04.04.01 SOLADO PARA LOSA FONDO m2 8.05 40.87 329.00 319.13
04.04.04.02 CONCRETO f'c=210 kg/cm2 m3 9.51 546.69 5,199.02 5,043.05
04.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 49.52 44.48 2,202.65 2,136.57
04.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 254.64 4.35 1,107.68 1,074.45
04.04.05 REVOQUES Y ENLUCIDOS
04.04.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 31.00 32.48 1,006.88 976.67
04.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 35.50 29.76 1,056.48 1,024.79
04.04.06 PINTURA
04.04.06.01 PINTURA ESMALTE EN MUROS EXTERIORES DE RESERVORIO m2 29.15 13.23 385.65 374.08
04.04.07 CARPINTERIA METALICA
04.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46 414.64
04.04.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.04.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN RESERVORIO (INGRESO Ø 1"-LIMPIA, REBOSE y SELLO HIDR. Ø 2"-VENTILAC. Ø 3") und 1.00 1,618.16 1,618.16 1,569.62
04.04.09 CERCO PERIMETRICO EN RESERVORIO
04.04.09.01 TRABAJOS PRELIMINARES
04.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84 66.24 64.25
04.04.09.02 MOVIMIENTO DE TIERRAS
04.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86 27.90 27.06
04.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75 18.19
04.04.09.03 CONCRETO SIMPLE
04.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98 249.19 241.71
04.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
04.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39 67.31
04.04.09.05 COLOCADO DE ROLLIZOS
04.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79 540.09
04.04.09.06 PINTURA EN CERCO PERIMETRICO
04.04.09.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 66.40 3.80 252.32 244.75
04.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
04.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22 515.50 500.04
04.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
04.04.09.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10 194.10 188.28
04.04.10 CLORADOR POR GOTEO
04.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
04.04.10.01.01 CASETA DE MURO DE LADRILLO -CLORADOR POR GOTEO
04.04.10.01.01.0
MURO DE LADRILLO PANDERETA (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 7.52 54.96 413.30 400.90
1
04.04.10.01.01.0
MURO DE LADRILLO PANDERETA INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 4.48 49.36 221.13 214.50
2
04.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
04.04.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 29.07 174.42 169.19
1
04.04.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 34.08 203.80 197.69
2
04.04.10.01.03 REVOQUES Y ENLUCIDOS
04.04.10.01.03.0
TARRAJEO MUROS DE INTERIORES Y EXTERIORES, CEMENTO : ARENA, 1:5 m2 14.98 30.00 449.40 435.92
1
04.04.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.78 55.12 53.47
2
04.04.10.01.04 CARPINTERIA METALICA
04.04.10.01.04.0
SUMINISTRO E INSTALACION DE PUERTA METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO und 1.00 367.18 367.18 356.16
1
04.04.10.01.05 PINTURAS
04.04.10.01.05.0
PINTURA ESMALTE EN MUROS INTERIORES Y EXTERIORES m2 14.98 11.18 167.48 162.46
1
04.04.10.01.05.0
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 12.25 49.00 47.53
2
04.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
04.04.10.02.01 SUMINISTRO E INSTALACION DE TANQUE DE POLIETILENO, CAP=250 LTRS. und 1.00 435.06 435.06 422.01
04.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
04.04.10.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS Y ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO GLB 1.00 939.22 939.22 911.04
04.05 RED DE ADUCCION Y DISTRIBUCION (L=3,674.00 m)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,837.00 0.49 900.13 873.13
04.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 3,674.00 1.53 5,621.22 5,452.58
04.05.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 3,674.00 1.53 5,621.22 5,452.58
04.05.02 MOVIMIENTO DE TIERRAS
04.05.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 73.48 39.86 2,928.91 2,841.04
04.05.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 1,352.03 49.82 67,358.13 65,337.39
04.05.02.03 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 44.09 55.80 2,460.22 2,386.41
04.05.02.04 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 3,674.00 1.81 6,649.94 6,450.44
04.05.02.05 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 110.22 6.08 670.14 650.04
04.05.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 534.57 36.40 19,458.35 18,874.60
04.05.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 16.53 65.17 1,077.26 1,044.94
04.05.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 946.06 25.07 23,717.72 23,006.19
04.05.02.09 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.20 m m3 55.11 62.16 3,425.64 3,322.87
04.05.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 27.56 25.69 708.02 686.78
04.05.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 104.00 8.05 837.20 812.08
04.05.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 3/4" m 3,570.00 4.84 17,278.80 16,760.44
04.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 87.97 87.97 85.33
04.05.04 PRUEBA HIDRAULICA
04.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 3,674.00 1.51 5,547.74 5,381.31
04.05.05 CAMARA ROMPE PRESION T-7 (12 UND)
04.05.05.01 OBRAS PRELIMINARES
04.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 24.84 0.49 12.17 11.80
04.05.05.01.02 TRAZO Y REPLANTEO m2 24.84 1.84 45.71 44.34
04.05.05.02 MOVIMIENTO DE TIERRAS
04.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 16.71 39.86 666.06 646.08
04.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 9.55 40.95 391.07 379.34
04.05.05.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 2.39 13.11 31.33 30.39
04.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 23.58 7.95 187.46 181.84
04.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.39 59.44 82.62 80.14
04.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 12.53 25.69 321.90 312.24
04.05.05.03 OBRAS DE CONCRETO SIMPLE
04.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.14 413.17 57.84 56.10
04.05.05.03.02 SOLADO E=4" m3 1.98 35.81 70.90 68.77
04.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.40 44.48 106.75 103.55
04.05.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 3.24 121.10 392.36 380.59
04.05.05.04 OBRAS DE CONCRETO ARMADO
04.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 16.30 546.69 8,911.05 8,643.72
04.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 167.06 44.48 7,430.83 7,207.91
04.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,361.41 4.35 10,272.13 9,963.97
04.05.05.05 REVOQUES Y ENLUCIDOS
04.05.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 51.84 32.48 1,683.76 1,633.25
04.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 112.34 29.76 3,343.24 3,242.94
04.05.05.06 PINTURA
04.05.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 72.00 11.18 804.96 780.81
04.05.05.07 CARPINTERIA METALICA
04.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 12.00 179.83 2,157.96 2,093.22
04.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 12.00 213.73 2,564.76 2,487.82
04.05.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=3/4" und 12.00 379.18 4,550.16 4,413.66
04.05.06 VALVULA DE CONTROL (05 UND)
04.05.06.01 OBRAS PRELIMINARES
04.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49 2.45 2.38
04.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.84 9.20 8.92
04.05.06.02 MOVIMIENTO DE TIERRAS
04.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 39.86 199.30 193.32
04.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 25.69 160.56 155.74
04.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.95 39.75 38.56
04.05.06.03 OBRAS DE CONCRETO ARMADO
04.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 546.69 1,350.32 1,309.81
04.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 44.48 947.42 919.00
04.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.35 668.94 648.87
04.05.06.04 REVOQUES Y ENLUCIDOS
04.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 32.48 233.86 226.84
04.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 29.76 321.41 311.77
04.05.06.05 PINTURA
04.05.06.05.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 10.80 11.18 120.74 117.12
04.05.06.06 CARPINTERIA METALICA
04.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 162.88 814.40 789.97
04.05.06.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=3/4" und 5.00 79.02 395.10 383.25
04.05.07 VALVULA DE PURGA TIPO II (05 UND)
04.05.07.01 OBRAS PRELIMINARES
04.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49 2.45 2.38
04.05.07.01.02 TRAZO Y REPLANTEO m2 5.00 1.84 9.20 8.92
04.05.07.02 MOVIMIENTO DE TIERRAS
04.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 7.64 39.86 304.53 295.39
04.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 2.55 49.82 127.04 123.23
04.05.07.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 2.55 13.11 33.43 32.43
04.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 2.45 7.95 19.48 18.90
04.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 2.45 25.69 62.94 61.05
04.05.07.03 OBRAS DE CONCRETO SIMPLE
04.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 1.53 413.17 632.15 613.19
04.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 44.48 53.38 51.78
04.05.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.64 121.10 77.50 75.18
04.05.07.04 OBRAS DE CONCRETO ARMADO
04.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 1.75 546.69 956.71 928.01
04.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 18.60 44.48 827.33 802.51
04.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 74.70 4.35 324.95 315.20
04.05.07.05 REVOQUES Y ENLUCIDOS
04.05.07.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 7.20 32.48 233.86 226.84
04.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 16.80 29.76 499.97 484.97
04.05.07.06 PINTURA
04.05.07.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 8.10 11.18 90.56 87.84
04.05.07.07 CARPINTERIA METALICA
04.05.07.07.01 MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE 0.60x0.40m. und 5.00 213.73 1,068.65 1,036.59
04.05.07.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.07.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4" und 5.00 132.94 664.70 644.76
04.05.08 CONEXIONES DOMICILIARIAS (53 UND)
04.05.08.01 OBRAS PRELIMINARES
04.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 474.88 0.49 232.69 225.71
04.05.08.01.02 TRAZO Y REPLANTEO m2 712.32 1.84 1,310.67 1,271.35
04.05.08.02 MOVIMIENTO DE TIERRAS
04.05.08.02.01 EXCAVACION A MANO DE ZANJA TERRENO NORMAL m3 596.86 40.95 24,441.42 23,708.18
04.05.08.02.02 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO CLASIFICADO m3 569.86 33.00 18,805.38 18,241.22
04.05.08.02.03 SUMINISTRO Y COLOCACION DE GRAVA SELECCIONADA m3 59.36 209.11 12,412.77 12,040.39
04.05.08.03 OBRAS DE CONCRETO SIMPLE
04.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 3.93 413.17 1,623.76 1,575.05
04.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.61 44.48 872.25 846.08
04.05.08.04 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND) und 53.00 80.77 4,280.81 4,152.39
04.05.08.04.02 TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON LLAVE TIPO BUJIA und 53.00 155.21 8,226.13 7,979.35
04.05.08.04.03 SUMINISTRO E INSTALACIONES DE ACOMETIDA DOMICILIARIA RANGO 2 - 20 M. m 636.00 3.50 2,226.00 2,159.22

01 LOCALIDAD SANTA LUCIA


01.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
01.01.01 TRABAJOS PRELIMINARES
01.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 465.00 0.49 227.85 221.01
01.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 465.00 1.84 855.60 829.93
01.01.02 MOVIMIENTO DE TIERRAS
01.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 231.57 39.86 9,230.38 8,953.47
01.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 40.92 29.66 1,213.69 1,177.28
01.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 238.08 25.69 6,116.28 5,932.79
01.01.03 CONCRETO SIMPLE
01.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 279.00 373.75 104,276.25 101,147.96
01.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 40.92 398.69 16,314.39 15,824.96
01.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 678.90 44.48 30,197.47 29,291.55
01.01.03.04 CONCRETO f'c=175 kg/cm2 m3 28.83 448.85 12,940.35 12,552.14
01.01.04 MURO DE LADRILLO
01.01.04.01 MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE SOGA C/M 1:4 x 1.5cm m2 1,354.08 58.10 78,672.05 76,311.89
01.01.04.02 EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-6" m2 26.04 70.33 1,831.39 1,776.45
01.01.05 REVOQUES Y ENLUCIDOS
01.01.05.01 TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre hidraulico) m2 1,272.24 16.34 20,788.40 20,164.75
01.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 20.46 36.55 747.81 725.38
01.01.06 PINTURA
01.01.06.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE COLOR MARFIL m2 767.25 11.53 8,846.39 8,581.00
01.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO ETERNIT(1,14x0.72x0.005m)
01.01.07.01 m2 605.43 66.22 40,091.57 38,888.82
01.01.08 CARPINTERIA METALICA
01.01.08.01 SUMINISTRO E INSTALACION DE PUERTA METALICA 1.80x0.70m, INCL. MARCO Y PINTADO und 93.00 363.74 33,827.82 32,812.99
01.01.09 CARPINTERIA DE MADERA
01.01.09.01 VENTANA DE MADERA TORNILLO INC. MALLA MOSQUITERA m2 16.74 75.90 1,270.57 1,232.45
01.01.09.02 COBERTURA DE MADERA PARA TECHO und 93.00 97.95 9,109.35 8,836.07
01.01.10 SISTEMA DE AGUA FRIA
01.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 880.71 3.65 3,214.59 3,118.15
01.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
01.01.11.01 TEE PVC-SAP 1/2" pza 186.00 20.85 3,878.10 3,761.76
01.01.11.02 CODO PVC SAP 1/2" pza 558.00 15.59 8,699.22 8,438.24
01.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 186.00 51.25 9,532.50 9,246.53
01.01.11.04 SUMINISTRO E INSTALACION DE DUCHA INCLUIDO ACCESORIOS und 93.00 33.08 3,076.44 2,984.15
01.01.12 SISTEMA DE DESAGUE
01.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 897.45 4.02 3,607.75 3,499.52
01.01.12.02 TUBERIA Ø=4" PVC SAL m 339.45 3.65 1,238.99 1,201.82
01.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
01.01.13.01 CODO PVC SAL 2"X90° pza 651.00 11.77 7,662.27 7,432.40
01.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 93.00 15.53 1,444.29 1,400.96
01.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 279.00 16.11 4,494.69 4,359.85
01.01.14 ADITAMIENTOS VARIOS
01.01.14.01 SUMIDEROS DE BRONCE 2" und 93.00 12.25 1,139.25 1,105.07
01.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 186.00 11.09 2,062.74 2,000.86
01.01.14.03 INODORO DE LOZA VITRIFICADA COLOR BLANCO INCLUYE TANQUE und 93.00 147.40 13,708.20 13,296.95
01.01.14.04 ACCESORIOS DE LOZA und 93.00 64.86 6,031.98 5,851.02
01.01.14.05 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y ACCESORIOS GLB 93.00 29.15 2,710.95 2,629.62
01.01.14.06 SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA COLOR BLANCO INCLUIDO ACCESORIOS und 93.00 124.59 11,586.87 11,239.26
01.01.14.07 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE 12"x24" und 186.00 129.89 24,159.54 23,434.75
01.01.15 INSTALACIONES ELECTRICAS
01.01.15.01 SALIDA DE CENTRO DE LUZ pto 93.00 49.14 4,570.02 4,432.92
01.01.15.02 TUBERIA PVC SEL 5/8" m 213.90 4.15 887.69 861.06
01.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 520.80 2.28 1,187.42 1,151.80
01.01.15.04 TABLEROS DISTRIBUCION pza 93.00 89.04 8,280.72 8,032.30
01.01.16 CONSTRUCCION POZO PERCOLADOR
01.01.16.01 TRABAJOS PRELIMINARES
01.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 292.02 0.49 143.09 138.80
01.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 292.02 1.84 537.32 521.20
01.01.16.02 MOVIMIENTO DE TIERRAS
01.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 150.66 39.86 6,005.31 5,825.15
01.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 22.32 29.66 662.01 642.15
01.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 80.91 89.30 7,225.26 7,008.50
01.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 188.79 25.69 4,850.02 4,704.52
01.01.16.03 TAPA DE CONCRETO
01.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 18.81 448.85 8,442.87 8,189.58
01.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 196.26 44.48 8,729.64 8,467.75
01.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,957.65 4.35 8,515.78 8,260.31
01.01.16.04 ANILLO DE CONCRETO
01.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 6.51 355.98 2,317.43 2,247.91
01.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 111.60 44.48 4,963.97 4,815.05
01.01.16.05 MURO DE LADRILLO
01.01.16.05.01 MURO DE LADRILLO ARTESANAL AMARRE DE SOGA, JUNTA 1.5 CM MORTERO 1:1:5 m2 388.74 48.94 19,024.94 18,454.19
01.01.16.06 SISTEMA DE DESAGUE LLEGADA
01.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 181.35 4.02 729.03 707.16
01.01.16.06.02 CODO PVC SAL 2"X90° pza 93.00 11.77 1,094.61 1,061.77
01.01.17 INSTALACION DEL BIODIGESTOR
01.01.17.01 TRABAJOS PRELIMINARES
01.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 351.54 0.49 172.25 167.08
01.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 351.54 1.84 646.83 627.43
01.01.17.02 MOVIMIENTO DE TIERRAS
01.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 281.20 39.86 11,208.63 10,872.37
01.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 211.97 29.66 6,287.03 6,098.42
01.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 351.50 25.69 9,030.04 8,759.14
01.01.17.03 CONCRETO SIMPLE
01.01.17.03.01 SOLADO E=4" m2 60.45 39.68 2,398.66 2,326.70
01.01.17.04 CONCRETO ARMADO
01.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 66.96 448.85 30,055.00 29,153.35
01.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 420.36 44.48 18,697.61 18,136.68
01.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 518.01 4.35 2,253.34 2,185.74
01.01.17.05 BIODIGESTOR
01.01.17.05.01 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 600 LTS und 91.00 779.59 70,942.69 68,814.41
01.01.17.05.02 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 1300 LTS und 2.00 1,320.79 2,641.58 2,562.33
01.01.17.06 REVOQUES Y ENLUCIDOS
01.01.17.06.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 332.01 32.48 10,783.68 10,460.17
01.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
01.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 93.00 4.02 373.86 362.64
01.01.17.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 93.00 29.86 2,776.98 2,693.67
01.02 LAVADERO INTRADOMICILIARIO (91 UND)
01.02.01 OBRAS PRELIMINARES
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 460.46 0.49 225.63 218.86
01.02.01.02 TRAZO Y REPLANTEO m2 460.46 1.84 847.25 821.83
01.02.02 MOVIMIENTO DE TIERRAS
01.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 103.03 37.48 3,861.56 3,745.71
01.02.02.02 RELLENO Y COMPACTADO DE ZANJA CON MATERIAL PROPIO CLASIFICADO m3 84.63 13.11 1,109.50 1,076.22
01.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 21.16 25.69 543.60 527.29
01.02.03 OBRAS DE CONCRETO ARMADO
01.02.03.01 CONCRETO f'c=175 kg/cm2 m3 9.57 448.85 4,295.49 4,166.63
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 304.63 44.48 13,549.94 13,143.44
01.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 359.91 4.35 1,565.61 1,518.64
01.02.04 MURO DE LADRILLO
01.02.04.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 60.17 47.74 2,872.52 2,786.34
01.02.05 REVOQUES Y ENLUCIDOS
01.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 107.29 32.48 3,484.78 3,380.24
01.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 205.30 29.76 6,109.73 5,926.44
01.02.06 ACCESORIOS Y VALVULAS
01.02.06.01 SUMINISTRO E INSTALACION DE LAVADERO INTRADOMICILIARIA und 91.00 136.31 12,404.21 12,032.08
01.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
01.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 455.00 3.35 1,524.25 1,478.52
01.03 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55 5.38
01.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84 20.83 20.21
01.03.02 MOVIMIENTO DE TIERRAS
01.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48 102.70 99.62
01.03.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02 11.55 11.20
01.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79 46.36
01.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69 34.42 33.39
01.03.03 OBRAS DE CONCRETO SIMPLE
01.03.03.01 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.20 48.96 107.71 104.48
01.03.04 OBRAS DE CONCRETO ARMADO
01.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35 36.32 35.23
01.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 44.01 180.00 174.60
01.03.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.21 448.85 94.26 91.43
01.03.05 REVOQUES Y REVESTIMIENTOS
01.03.05.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 2.49 32.96 82.07 79.61
01.03.05.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 2.11 23.98 50.60 49.08
01.03.06 ACCESORIOS Y VALVULAS
01.03.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO I.E. INICIAL und 1.00 176.99 176.99 171.68
01.03.06.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00 276.45
01.03.06.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77 56.04
01.03.06.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19 46.74
01.03.07 TUBERIA PVC INTRADOMICILIARIO
01.03.07.01 INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20 73.91
01.03.07.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50 64.51
02 LOCALIDAD PUEBLO LIBRE (130 UND)
02.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 650.00 0.49 318.50 308.95
02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 650.00 1.84 1,196.00 1,160.12
02.01.02 MOVIMIENTO DE TIERRAS
02.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 323.70 39.86 12,902.68 12,515.60
02.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 57.20 29.66 1,696.55 1,645.65
02.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 332.80 25.69 8,549.63 8,293.14
02.01.03 CONCRETO SIMPLE
02.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 390.00 373.75 145,762.50 141,389.63
02.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 57.20 398.69 22,805.07 22,120.92
02.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 949.00 44.48 42,211.52 40,945.17
02.01.03.04 CONCRETO f'c=175 kg/cm2 m3 40.30 448.85 18,088.66 17,546.00
02.01.04 MURO DE LADRILLO
02.01.04.01 MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE SOGA C/M 1:4 x 1.5cm m2 1,892.80 58.10 109,971.68 106,672.53
02.01.04.02 EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-6" m2 36.40 70.33 2,560.01 2,483.21
02.01.05 REVOQUES Y ENLUCIDOS
02.01.05.01 TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre hidraulico) m2 1,778.40 16.34 29,059.06 28,187.29
02.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 28.60 36.55 1,045.33 1,013.97
02.01.06 PINTURA
02.01.06.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE COLOR MARFIL m2 1,072.50 11.53 12,365.93 11,994.95
02.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO ETERNIT(1,14x0.72x0.005m)
02.01.07.01 m2 846.60 66.22 56,061.85 54,379.99
02.01.08 CARPINTERIA METALICA
02.01.08.01 SUMINISTRO E INSTALACION DE PUERTA METALICA 1.80x0.70m, INCL. MARCO Y PINTADO und 130.00 363.74 47,286.20 45,867.61
02.01.09 CARPINTERIA DE MADERA
02.01.09.01 VENTANA DE MADERA TORNILLO INC. MALLA MOSQUITERA m2 23.40 75.90 1,776.06 1,722.78
02.01.09.02 COBERTURA DE MADERA PARA TECHO und 130.00 97.95 12,733.50 12,351.50
02.01.10 SISTEMA DE AGUA FRIA
02.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 1,231.00 3.65 4,493.15 4,358.36
02.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
02.01.11.01 TEE PVC-SAP 1/2" pza 260.00 20.85 5,421.00 5,258.37
02.01.11.02 CODO PVC SAP 1/2" pza 780.00 15.59 12,160.20 11,795.39
02.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 260.00 51.25 13,325.00 12,925.25
02.01.11.04 SUMINISTRO E INSTALACION DE DUCHA INCLUIDO ACCESORIOS und 130.00 33.08 4,300.40 4,171.39
02.01.12 SISTEMA DE DESAGUE
02.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 1,254.50 4.02 5,043.09 4,891.80
02.01.12.02 TUBERIA Ø=4" PVC SAL m 474.50 3.65 1,731.93 1,679.97
02.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
02.01.13.01 CODO PVC SAL 2"X90° pza 910.00 11.77 10,710.70 10,389.38
02.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 130.00 15.53 2,018.90 1,958.33
02.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 390.00 16.11 6,282.90 6,094.41
02.01.14 ADITAMIENTOS VARIOS
02.01.14.01 SUMIDEROS DE BRONCE 2" und 130.00 12.25 1,592.50 1,544.73
02.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 260.00 11.09 2,883.40 2,796.90
02.01.14.03 INODORO DE LOZA VITRIFICADA COLOR BLANCO INCLUYE TANQUE und 130.00 147.40 19,162.00 18,587.14
02.01.14.04 ACCESORIOS DE LOZA und 130.00 64.86 8,431.80 8,178.85
02.01.14.05 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y ACCESORIOS GLB 130.00 29.15 3,789.50 3,675.82
02.01.14.06 SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA COLOR BLANCO INCLUIDO ACCESORIOS und 130.00 124.59 16,196.70 15,710.80
02.01.14.07 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE 12"x24" und 260.00 129.89 33,771.40 32,758.26
02.01.15 INSTALACIONES ELECTRICAS
02.01.15.01 SALIDA DE CENTRO DE LUZ pto 130.00 49.14 6,388.20 6,196.55
02.01.15.02 TUBERIA PVC SEL 5/8" m 299.00 4.15 1,240.85 1,203.62
02.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 728.00 2.28 1,659.84 1,610.04
02.01.15.04 TABLEROS DISTRIBUCION pza 130.00 89.04 11,575.20 11,227.94
02.01.16 CONSTRUCCION POZO PERCOLADOR
02.01.16.01 TRABAJOS PRELIMINARES
02.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 408.20 0.49 200.02 194.02
02.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 408.20 1.84 751.09 728.56
02.01.16.02 MOVIMIENTO DE TIERRAS
02.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 210.60 39.86 8,394.52 8,142.68
02.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 31.20 29.66 925.39 897.63
02.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 113.10 89.30 10,099.83 9,796.84
02.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 163.90 25.69 4,210.59 4,084.27
02.01.16.03 TAPA DE CONCRETO
02.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 22.10 448.85 9,919.59 9,622.00
02.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 236.60 44.48 10,523.97 10,208.25
02.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,736.50 4.35 11,903.78 11,546.67
02.01.16.04 ANILLO DE CONCRETO
02.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 9.10 355.98 3,239.42 3,142.24
02.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 156.00 44.48 6,938.88 6,730.71
02.01.16.05 MURO DE LADRILLO
02.01.16.05.01 MURO DE LADRILLO ARTESANAL AMARRE DE SOGA, JUNTA 1.5 CM MORTERO 1:1:5 m2 543.40 48.94 26,594.00 25,796.18
02.01.16.06 SISTEMA DE DESAGUE LLEGADA
02.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 253.50 4.02 1,019.07 988.50
02.01.16.06.02 CODO PVC SAL 2"X90° pza 130.00 11.77 1,530.10 1,484.20
02.01.17 INSTALACION DEL BIODIGESTOR
02.01.17.01 TRABAJOS PRELIMINARES
02.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 491.40 0.49 240.79 233.57
02.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 491.40 1.84 904.18 877.05
02.01.17.02 MOVIMIENTO DE TIERRAS
02.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 396.70 39.86 15,812.46 15,338.09
02.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 299.24 29.66 8,875.46 8,609.20
02.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 504.11 25.69 12,950.59 12,562.07
02.01.17.03 CONCRETO SIMPLE
02.01.17.03.01 SOLADO E=4" m2 84.50 39.68 3,352.96 3,252.37
02.01.17.04 CONCRETO ARMADO
02.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 93.60 448.85 42,012.36 40,751.99
02.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 587.60 44.48 26,136.45 25,352.36
02.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 724.10 4.35 3,149.84 3,055.34
02.01.17.05 BIODIGESTOR
02.01.17.05.01 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 600 LTS und 121.00 779.59 94,330.39 91,500.48
02.01.17.05.02 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 1300 LTS und 9.00 1,320.79 11,887.11 11,530.50
02.01.17.06 REVOQUES Y ENLUCIDOS
02.01.17.06.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 464.10 32.48 15,073.97 14,621.75
02.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
02.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 130.00 4.02 522.60 506.92
02.01.17.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 130.00 29.86 3,881.80 3,765.35
02.02 LAVADERO INTRADOMICILIARIO (121 UND)
02.02.01 OBRAS PRELIMINARES
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 612.26 0.49 300.01 291.01
02.02.01.02 TRAZO Y REPLANTEO m2 612.26 1.84 1,126.56 1,092.76
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 137.00 37.48 5,134.76 4,980.72
02.02.02.02 RELLENO Y COMPACTADO DE ZANJA CON MATERIAL PROPIO CLASIFICADO m3 112.53 13.11 1,475.27 1,431.01
02.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 28.14 25.69 722.92 701.23
02.02.03 OBRAS DE CONCRETO ARMADO
02.02.03.01 CONCRETO f'c=175 kg/cm2 m3 12.72 448.85 5,709.37 5,538.09
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 405.06 44.48 18,017.07 17,476.56
02.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 478.56 4.35 2,081.74 2,019.29
02.02.04 MURO DE LADRILLO
02.02.04.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 80.01 47.74 3,819.68 3,705.09
02.02.05 REVOQUES Y ENLUCIDOS
02.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 142.66 32.48 4,633.60 4,494.59
02.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 272.98 29.76 8,123.88 7,880.16
02.02.06 ACCESORIOS Y VALVULAS
02.02.06.01 SUMINISTRO E INSTALACION DE LAVADERO INTRADOMICILIARIA und 121.00 136.31 16,493.51 15,998.70
02.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
02.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 605.00 3.35 2,026.75 1,965.95
02.03 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
02.03.01 TRABAJOS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55 5.38
02.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84 20.83 20.21
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48 102.70 99.62
02.03.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02 11.55 11.20
02.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79 46.36
02.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69 34.42 33.39
02.03.03 OBRAS DE CONCRETO SIMPLE
02.03.03.01 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.20 48.96 107.71 104.48
02.03.04 OBRAS DE CONCRETO ARMADO
02.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35 36.32 35.23
02.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 44.01 180.00 174.60
02.03.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.21 448.85 94.26 91.43
02.03.05 REVOQUES Y REVESTIMIENTOS
02.03.05.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 2.49 32.96 82.07 79.61
02.03.05.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 2.11 23.98 50.60 49.08
02.03.06 ACCESORIOS Y VALVULAS
02.03.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO I.E. INICIAL und 1.00 176.99 176.99 171.68
02.03.06.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00 276.45
02.03.06.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77 56.04
02.03.06.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19 46.74
02.03.07 TUBERIA PVC INTRADOMICILIARIO
02.03.07.01 INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20 73.91
02.03.07.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50 64.51
02.04 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01 UND)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.49 5.87 5.69
02.04.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.84 22.04 21.38
02.04.02 MOVIMIENTO DE TIERRAS
02.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 37.48 104.94 101.79
02.04.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.98 1.02 12.22 11.85
02.04.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79 46.36
02.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 25.69 36.22 35.13
02.04.03 OBRAS DE CONCRETO SIMPLE
02.04.03.01 CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6") EN LAVADERO C/MEZCLADORA m3 0.06 339.60 20.38 19.77
02.04.03.02 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.86 48.96 140.03 135.83
02.04.04 OBRAS DE CONCRETO ARMADO
02.04.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.35 49.98 48.48
02.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 44.01 190.56 184.84
02.04.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.31 448.85 139.14 134.97
02.04.05 ALBAÑILERIA
02.04.05.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 0.36 58.08 20.91 20.28
02.04.06 REVOQUES Y REVESTIMIENTOS
02.04.06.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 3.51 32.96 115.69 112.22
02.04.06.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 3.29 23.98 78.89 76.52
02.04.07 ACCESORIOS Y VALVULAS
02.04.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO TIPO I.E. PRIMARIA und 1.00 176.99 176.99 171.68
02.04.07.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00 276.45
02.04.07.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77 56.04
02.04.07.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19 46.74
02.04.08 TUBERIA PVC INTRADOMICILIARIO
02.04.08.01 INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20 73.91
02.04.08.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50 64.51
02.05 LAVADERO I.E. SECUNDARIA (01 UND)
02.05.01 TRABAJOS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55 5.38
02.05.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84 20.83 20.21
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 3.70 37.48 138.68 134.52
02.05.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02 11.55 11.20
02.05.02.03 RELLENO CON MATERIAL PROPIO m3 2.64 29.50 77.88 75.54
02.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.27 25.69 32.63 31.65
02.05.03 OBRAS DE CONCRETO SIMPLE
02.05.03.01 CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6") EN LAVADERO C/MEZCLADORA m3 0.08 339.60 27.17 26.35
02.05.03.02 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 0.22 48.96 10.77 10.45
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 0.26 4.35 1.13 1.10
02.05.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 5.20 44.01 228.85 221.98
02.05.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 12.73 448.85 5,713.86 5,542.44
02.05.05 ALBAÑILERIA
02.05.05.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 1.04 58.08 60.40 58.59
02.05.06 REVOQUES Y REVESTIMIENTOS
02.05.06.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 3.13 32.96 103.16 100.07
02.05.06.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 4.41 23.98 105.75 102.58
02.05.07 ACCESORIOS Y VALVULAS
02.05.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO TIPO I.E. PRIMARIA und 1.00 176.99 176.99 171.68
02.05.07.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00 276.45
02.05.07.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77 56.04
02.05.07.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19 46.74
02.05.08 TUBERIA PVC INTRADOMICILIARIO
02.05.08.01 INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20 73.91
02.05.08.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50 64.51
03 LOCALIDAD TANCARPATA (55 UND)
03.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
03.01.01 TRABAJOS PRELIMINARES
03.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 275.00 0.49 134.75 130.71
03.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 275.00 1.84 506.00 490.82
03.01.02 MOVIMIENTO DE TIERRAS
03.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 136.95 39.86 5,458.83 5,295.07
03.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 24.20 29.66 717.77 696.24
03.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 140.80 25.69 3,617.15 3,508.64
03.01.03 CONCRETO SIMPLE
03.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 165.00 373.75 61,668.75 59,818.69
03.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 24.20 398.69 9,648.30 9,358.85
03.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 401.50 44.48 17,858.72 17,322.96
03.01.03.04 CONCRETO f'c=175 kg/cm2 m3 17.05 448.85 7,652.89 7,423.30
03.01.04 MURO DE LADRILLO
03.01.04.01 MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE SOGA C/M 1:4 x 1.5cm m2 800.80 58.10 46,526.48 45,130.69
03.01.04.02 EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-6" m2 15.40 70.33 1,083.08 1,050.59
03.01.05 REVOQUES Y ENLUCIDOS
03.01.05.01 TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre hidraulico) m2 752.40 16.34 12,294.22 11,925.39
03.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 12.10 36.55 442.26 428.99
03.01.06 PINTURA
03.01.06.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE COLOR MARFIL m2 453.75 11.53 5,231.74 5,074.79
03.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO ETERNIT(1,14x0.72x0.005m)
03.01.07.01 m2 358.05 66.22 23,710.07 22,998.77
03.01.08 CARPINTERIA METALICA
03.01.08.01 SUMINISTRO E INSTALACION DE PUERTA METALICA 1.80x0.70m, INCL. MARCO Y PINTADO und 55.00 363.74 20,005.70 19,405.53
03.01.09 CARPINTERIA DE MADERA
03.01.09.01 VENTANA DE MADERA TORNILLO INC. MALLA MOSQUITERA m2 9.90 75.90 751.41 728.87
03.01.09.02 COBERTURA DE MADERA PARA TECHO und 55.00 97.95 5,387.25 5,225.63
03.01.10 SISTEMA DE AGUA FRIA
03.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 520.85 3.65 1,901.10 1,844.07
03.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
03.01.11.01 TEE PVC-SAP 1/2" pza 110.00 20.85 2,293.50 2,224.70
03.01.11.02 CODO PVC SAP 1/2" pza 330.00 15.59 5,144.70 4,990.36
03.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 110.00 51.25 5,637.50 5,468.38
03.01.11.04 SUMINISTRO E INSTALACION DE DUCHA INCLUIDO ACCESORIOS und 55.00 33.08 1,819.40 1,764.82
03.01.12 SISTEMA DE DESAGUE
03.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 530.75 4.02 2,133.62 2,069.61
03.01.12.02 TUBERIA Ø=4" PVC SAL m 200.75 3.65 732.74 710.76
03.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
03.01.13.01 CODO PVC SAL 2"X90° pza 385.00 11.77 4,531.45 4,395.51
03.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 55.00 15.53 854.15 828.53
03.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 165.00 16.11 2,658.15 2,578.41
03.01.14 ADITAMIENTOS VARIOS
03.01.14.01 SUMIDEROS DE BRONCE 2" und 55.00 12.25 673.75 653.54
03.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 110.00 11.09 1,219.90 1,183.30
03.01.14.03 INODORO DE LOZA VITRIFICADA COLOR BLANCO INCLUYE TANQUE und 55.00 147.40 8,107.00 7,863.79
03.01.14.04 ACCESORIOS DE LOZA und 55.00 64.86 3,567.30 3,460.28
03.01.14.05 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y ACCESORIOS GLB 55.00 29.15 1,603.25 1,555.15
03.01.14.06 SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA COLOR BLANCO INCLUIDO ACCESORIOS und 55.00 124.59 6,852.45 6,646.88
03.01.14.07 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE 12"x24" und 110.00 129.89 14,287.90 13,859.26
03.01.15 INSTALACIONES ELECTRICAS
03.01.15.01 SALIDA DE CENTRO DE LUZ pto 55.00 49.14 2,702.70 2,621.62
03.01.15.02 TUBERIA PVC SEL 5/8" m 126.50 4.15 524.98 509.23
03.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 308.00 2.28 702.24 681.17
03.01.15.04 TABLEROS DISTRIBUCION pza 55.00 89.04 4,897.20 4,750.28
03.01.16 CONSTRUCCION POZO PERCOLADOR
03.01.16.01 TRABAJOS PRELIMINARES
03.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 172.70 0.49 84.62 82.08
03.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 172.20 1.84 316.85 307.34
03.01.16.02 MOVIMIENTO DE TIERRAS
03.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 89.10 39.86 3,551.53 3,444.98
03.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 13.20 29.66 391.51 379.76
03.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 47.85 89.30 4,273.01 4,144.82
03.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 111.65 25.69 2,868.29 2,782.24
03.01.16.03 TAPA DE CONCRETO
03.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 9.35 448.85 4,196.75 4,070.85
03.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 100.10 44.48 4,452.45 4,318.88
03.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,157.75 4.35 5,036.21 4,885.12
03.01.16.04 ANILLO DE CONCRETO
03.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 3.85 355.98 1,370.52 1,329.40
03.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.00 44.48 2,935.68 2,847.61
03.01.16.05 MURO DE LADRILLO
03.01.16.05.01 MURO DE LADRILLO ARTESANAL AMARRE DE SOGA, JUNTA 1.5 CM MORTERO 1:1:5 m2 229.90 48.94 11,251.31 10,913.77
03.01.16.06 SISTEMA DE DESAGUE LLEGADA
03.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 107.25 4.02 431.15 418.22
03.01.16.06.02 CODO PVC SAL 2"X90° pza 55.00 11.77 647.35 627.93
03.01.17 INSTALACION DEL BIODIGESTOR
03.01.17.01 TRABAJOS PRELIMINARES
03.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 207.90 0.49 101.87 98.81
03.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 207.90 1.84 382.54 371.06
03.01.17.02 MOVIMIENTO DE TIERRAS
03.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 170.94 39.86 6,813.67 6,609.26
03.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 129.10 29.66 3,829.11 3,714.24
03.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 213.67 25.69 5,489.18 5,324.50
03.01.17.03 CONCRETO SIMPLE
03.01.17.03.01 SOLADO E=4" m2 35.75 39.68 1,418.56 1,376.00
03.01.17.04 CONCRETO ARMADO
03.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 39.60 448.85 17,774.46 17,241.23
03.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.60 44.48 11,057.73 10,726.00
03.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 306.35 4.35 1,332.62 1,292.64
03.01.17.05 BIODIGESTOR
03.01.17.05.01 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 600 LTS und 51.00 779.59 39,759.09 38,566.32
03.01.17.05.02 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 1300 LTS und 4.00 1,320.79 5,283.16 5,124.67
03.01.17.06 REVOQUES Y ENLUCIDOS
03.01.17.06.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 196.35 32.48 6,377.45 6,186.13
03.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
03.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 55.00 4.02 221.10 214.47
03.01.17.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 55.00 29.86 1,642.30 1,593.03
03.02 LAVADERO INTRADOMICILIARIO (51 UND)
03.02.01 OBRAS PRELIMINARES
03.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 258.06 0.49 126.45 122.66
03.02.01.02 TRAZO Y REPLANTEO m2 258.06 1.84 474.83 460.59
03.02.02 MOVIMIENTO DE TIERRAS
03.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 57.74 37.48 2,164.10 2,099.18
03.02.02.02 RELLENO Y COMPACTADO DE ZANJA CON MATERIAL PROPIO CLASIFICADO m3 47.43 13.11 621.81 603.16
03.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.86 25.69 304.68 295.54
03.02.03 OBRAS DE CONCRETO ARMADO
03.02.03.01 CONCRETO f'c=175 kg/cm2 m3 5.36 448.85 2,405.84 2,333.66
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 170.73 44.48 7,594.07 7,366.25
03.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 201.71 4.35 877.44 851.12
03.02.04 MURO DE LADRILLO
03.02.04.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 33.72 47.74 1,609.79 1,561.50
03.02.05 REVOQUES Y ENLUCIDOS
03.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 60.13 32.48 1,953.02 1,894.43
03.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 115.06 29.76 3,424.19 3,321.46
03.02.06 ACCESORIOS Y VALVULAS
03.02.06.01 SUMINISTRO E INSTALACION DE LAVADERO INTRADOMICILIARIA und 51.00 136.31 6,951.81 6,743.26
03.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
03.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 255.00 3.35 854.25 828.62
03.03 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55 5.38
03.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84 20.83 20.21
03.03.02 MOVIMIENTO DE TIERRAS
03.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48 102.70 99.62
03.03.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02 11.55 11.20
03.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79 46.36
03.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69 34.42 33.39
03.03.03 OBRAS DE CONCRETO SIMPLE
03.03.03.01 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.20 48.96 107.71 104.48
03.03.04 OBRAS DE CONCRETO ARMADO
03.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35 36.32 35.23
03.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 44.01 180.00 174.60
03.03.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.21 448.85 94.26 91.43
03.03.05 REVOQUES Y REVESTIMIENTOS
03.03.05.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 2.49 32.96 82.07 79.61
03.03.05.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 2.11 23.98 50.60 49.08
03.03.06 ACCESORIOS Y VALVULAS
03.03.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO I.E. INICIAL und 1.00 176.99 176.99 171.68
03.03.06.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00 276.45
03.03.06.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77 56.04
03.03.06.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19 46.74
03.03.07 TUBERIA PVC INTRADOMICILIARIO
03.03.07.01 INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20 73.91
03.03.07.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50 64.51
03.04 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01 UND)
03.04.01 TRABAJOS PRELIMINARES
03.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.49 5.87 5.69
03.04.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.84 22.04 21.38
03.04.02 MOVIMIENTO DE TIERRAS
03.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 37.48 104.94 101.79
03.04.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.98 1.02 12.22 11.85
03.04.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79 46.36
03.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 25.69 36.22 35.13
03.04.03 OBRAS DE CONCRETO SIMPLE
03.04.03.01 CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6") EN LAVADERO C/MEZCLADORA m3 0.06 339.60 20.38 19.77
03.04.03.02 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.86 48.96 140.03 135.83
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.35 49.98 48.48
03.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 44.01 190.56 184.84
03.04.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.31 448.85 139.14 134.97
03.04.05 ALBAÑILERIA
03.04.05.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 0.36 58.08 20.91 20.28
03.04.06 REVOQUES Y REVESTIMIENTOS
03.04.06.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 3.51 32.96 115.69 112.22
03.04.06.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 3.29 23.98 78.89 76.52
03.04.07 ACCESORIOS Y VALVULAS
03.04.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO TIPO I.E. PRIMARIA und 1.00 176.99 176.99 171.68
03.04.07.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00 276.45
03.04.07.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77 56.04
03.04.07.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19 46.74
03.04.08 TUBERIA PVC INTRADOMICILIARIO
03.04.08.01 INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20 73.91
03.04.08.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50 64.51
04 LOCALIDAD TARACA (55 UND)
04.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
04.01.01 TRABAJOS PRELIMINARES
04.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 275.00 0.49 134.75 130.71
04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 275.00 1.84 506.00 490.82
04.01.02 MOVIMIENTO DE TIERRAS
04.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 136.95 39.86 5,458.83 5,295.07
04.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 24.20 29.66 717.77 696.24
04.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 140.80 25.69 3,617.15 3,508.64
04.01.03 CONCRETO SIMPLE
04.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 165.00 373.75 61,668.75 59,818.69
04.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 24.20 398.69 9,648.30 9,358.85
04.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 401.50 44.48 17,858.72 17,322.96
04.01.03.04 CONCRETO f'c=175 kg/cm2 m3 17.05 448.85 7,652.89 7,423.30
04.01.04 MURO DE LADRILLO
04.01.04.01 MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE SOGA C/M 1:4 x 1.5cm m2 800.80 58.10 46,526.48 45,130.69
04.01.04.02 EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-6" m2 15.40 70.33 1,083.08 1,050.59
04.01.05 REVOQUES Y ENLUCIDOS
04.01.05.01 TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre hidraulico) m2 752.40 16.34 12,294.22 11,925.39
04.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 12.10 36.55 442.26 428.99
04.01.06 PINTURA
04.01.06.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE COLOR MARFIL m2 453.75 11.53 5,231.74 5,074.79
04.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO ETERNIT(1,14x0.72x0.005m)
04.01.07.01 m2 358.05 66.22 23,710.07 22,998.77
04.01.08 CARPINTERIA METALICA
04.01.08.01 SUMINISTRO E INSTALACION DE PUERTA METALICA 1.80x0.70m, INCL. MARCO Y PINTADO und 55.00 363.74 20,005.70 19,405.53
04.01.09 CARPINTERIA DE MADERA
04.01.09.01 VENTANA DE MADERA TORNILLO INC. MALLA MOSQUITERA m2 9.90 75.90 751.41 728.87
04.01.09.02 COBERTURA DE MADERA PARA TECHO und 55.00 97.95 5,387.25 5,225.63
04.01.10 SISTEMA DE AGUA FRIA
04.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 520.85 3.65 1,901.10 1,844.07
04.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
04.01.11.01 TEE PVC-SAP 1/2" pza 110.00 20.85 2,293.50 2,224.70
04.01.11.02 CODO PVC SAP 1/2" pza 330.00 15.59 5,144.70 4,990.36
04.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 110.00 51.25 5,637.50 5,468.38
04.01.11.04 SUMINISTRO E INSTALACION DE DUCHA INCLUIDO ACCESORIOS und 55.00 33.08 1,819.40 1,764.82
04.01.12 SISTEMA DE DESAGUE
04.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 530.75 4.02 2,133.62 2,069.61
04.01.12.02 TUBERIA Ø=4" PVC SAL m 200.75 3.65 732.74 710.76
04.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
04.01.13.01 CODO PVC SAL 2"X90° pza 385.00 11.77 4,531.45 4,395.51
04.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 55.00 15.53 854.15 828.53
04.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 165.00 16.11 2,658.15 2,578.41
04.01.14 ADITAMIENTOS VARIOS
04.01.14.01 SUMIDEROS DE BRONCE 2" und 55.00 12.25 673.75 653.54
04.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 110.00 11.09 1,219.90 1,183.30
04.01.14.03 INODORO DE LOZA VITRIFICADA COLOR BLANCO INCLUYE TANQUE und 55.00 147.40 8,107.00 7,863.79
04.01.14.04 ACCESORIOS DE LOZA und 55.00 64.86 3,567.30 3,460.28
04.01.14.05 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y ACCESORIOS GLB 55.00 29.15 1,603.25 1,555.15
04.01.14.06 SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA COLOR BLANCO INCLUIDO ACCESORIOS und 55.00 124.59 6,852.45 6,646.88
04.01.14.07 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE 12"x24" und 110.00 129.89 14,287.90 13,859.26
04.01.15 INSTALACIONES ELECTRICAS
04.01.15.01 SALIDA DE CENTRO DE LUZ pto 55.00 49.14 2,702.70 2,621.62
04.01.15.02 TUBERIA PVC SEL 5/8" m 126.50 4.15 524.98 509.23
04.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 308.00 2.28 702.24 681.17
04.01.15.04 TABLEROS DISTRIBUCION pza 55.00 89.04 4,897.20 4,750.28
04.02 CONSTRUCCION POZO PERCOLADOR
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 172.70 0.49 84.62 82.08
04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 172.20 1.84 316.85 307.34
04.02.02 MOVIMIENTO DE TIERRAS
04.02.02.01 EXCAVACION A MANO TERRENO NORMAL m3 89.10 39.86 3,551.53 3,444.98
04.02.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 13.20 29.66 391.51 379.76
04.02.02.03 FILTRO DE GRAVA CLASIFICADA m3 47.85 89.30 4,273.01 4,144.82
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 111.65 25.69 2,868.29 2,782.24
04.02.03 TAPA DE CONCRETO
04.02.03.01 CONCRETO f'c=175 kg/cm2 m3 9.35 448.85 4,196.75 4,070.85
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 100.10 44.48 4,452.45 4,318.88
04.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,157.75 4.35 5,036.21 4,885.12
04.02.04 ANILLO DE CONCRETO
04.02.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 3.85 355.98 1,370.52 1,329.40
04.02.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.00 44.48 2,935.68 2,847.61
04.02.05 MURO DE LADRILLO
04.02.05.01 MURO DE LADRILLO ARTESANAL AMARRE DE SOGA, JUNTA 1.5 CM MORTERO 1:1:5 m2 229.90 48.94 11,251.31 10,913.77
04.02.06 SISTEMA DE DESAGUE LLEGADA
04.02.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 107.25 4.02 431.15 418.22
04.02.06.02 CODO PVC SAL 2"X90° pza 55.00 11.77 647.35 627.93
04.03 INSTALACION DEL BIODIGESTOR
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 207.90 0.49 101.87 98.81
04.03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 207.90 1.84 382.54 371.06
04.03.02 MOVIMIENTO DE TIERRAS
04.03.02.01 EXCAVACION A MANO TERRENO NORMAL m3 170.94 39.86 6,813.67 6,609.26
04.03.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 129.10 29.66 3,829.11 3,714.24
04.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 213.67 25.69 5,489.18 5,324.50
04.03.03 CONCRETO SIMPLE
04.03.03.01 SOLADO E=4" m2 35.75 39.68 1,418.56 1,376.00
04.03.04 CONCRETO ARMADO
04.03.04.01 CONCRETO f'c=175 kg/cm2 m3 39.60 448.85 17,774.46 17,241.23
04.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.60 44.48 11,057.73 10,726.00
04.03.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 306.35 4.35 1,332.62 1,292.64
04.03.05 BIODIGESTOR
04.03.05.01 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 600 LTS und 51.00 779.59 39,759.09 38,566.32
04.03.05.02 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 1300 LTS und 4.00 1,320.79 5,283.16 5,124.67
04.03.06 REVOQUES Y ENLUCIDOS
04.03.06.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 196.35 32.48 6,377.45 6,186.13
04.03.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
04.03.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 55.00 4.02 221.10 214.47
04.03.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 55.00 29.86 1,642.30 1,593.03
04.04 LAVADERO INTRADOMICILIARIO (51 UND)
04.04.01 OBRAS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 258.06 0.49 126.45 122.66
04.04.01.02 TRAZO Y REPLANTEO m2 258.06 1.84 474.83 460.59
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 57.74 37.48 2,164.10 2,099.18
04.04.02.02 RELLENO Y COMPACTADO DE ZANJA CON MATERIAL PROPIO CLASIFICADO m3 47.43 13.11 621.81 603.16
04.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.86 25.69 304.68 295.54
04.04.03 OBRAS DE CONCRETO ARMADO
04.04.03.01 CONCRETO f'c=175 kg/cm2 m3 5.36 448.85 2,405.84 2,333.66
04.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 170.73 44.48 7,594.07 7,366.25
04.04.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 201.71 4.35 877.44 851.12
04.04.04 MURO DE LADRILLO
04.04.04.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 33.72 47.74 1,609.79 1,561.50
04.04.05 REVOQUES Y ENLUCIDOS
04.04.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 60.13 32.48 1,953.02 1,894.43
04.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 115.06 29.76 3,424.19 3,321.46
04.04.06 ACCESORIOS Y VALVULAS
04.04.06.01 SUMINISTRO E INSTALACION DE LAVADERO INTRADOMICILIARIA und 51.00 136.31 6,951.81 6,743.26
04.04.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
04.04.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 255.00 3.35 854.25 828.62
04.05 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55 5.38
04.05.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84 20.83 20.21
04.05.02 MOVIMIENTO DE TIERRAS
04.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48 102.70 99.62
04.05.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02 11.55 11.20
04.05.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79 46.36
04.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69 34.42 33.39
04.05.03 OBRAS DE CONCRETO SIMPLE
04.05.03.01 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.20 48.96 107.71 104.48
04.05.04 OBRAS DE CONCRETO ARMADO
04.05.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35 36.32 35.23
04.05.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 44.01 180.00 174.60
04.05.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.21 448.85 94.26 91.43
04.05.05 REVOQUES Y REVESTIMIENTOS
04.05.05.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 2.49 32.96 82.07 79.61
04.05.05.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 2.11 23.98 50.60 49.08
04.05.06 ACCESORIOS Y VALVULAS
04.05.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO I.E. INICIAL und 1.00 176.99 176.99 171.68
04.05.06.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00 276.45
04.05.06.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77 56.04
04.05.06.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19 46.74
04.05.07 TUBERIA PVC INTRADOMICILIARIO
04.05.07.01 INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20 73.91
04.05.07.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50 64.51
04.06 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01 UND)
04.06.01 TRABAJOS PRELIMINARES
04.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.49 5.87 5.69
04.06.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.84 22.04 21.38
04.06.02 MOVIMIENTO DE TIERRAS
04.06.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 37.48 104.94 101.79
04.06.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.98 1.02 12.22 11.85
04.06.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79 46.36
04.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 25.69 36.22 35.13
04.06.03 OBRAS DE CONCRETO SIMPLE
04.06.03.01 CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6") EN LAVADERO C/MEZCLADORA m3 0.06 339.60 20.38 19.77
04.06.03.02 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.86 48.96 140.03 135.83
04.06.04 OBRAS DE CONCRETO ARMADO
04.06.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.35 49.98 48.48
04.06.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 44.01 190.56 184.84
04.06.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.31 448.85 139.14 134.97
04.06.05 ALBAÑILERIA
04.06.05.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 0.36 58.08 20.91 20.28
04.06.06 REVOQUES Y REVESTIMIENTOS
04.06.06.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 3.51 32.96 115.69 112.22
04.06.06.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 3.29 23.98 78.89 76.52
04.06.07 ACCESORIOS Y VALVULAS
04.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO TIPO I.E. PRIMARIA und 1.00 176.99 176.99 171.68
04.06.07.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50 285.00 276.45
04.06.07.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77 57.77 56.04
04.06.07.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19 48.19 46.74
04.06.08 TUBERIA PVC INTRADOMICILIARIO
04.06.08.01 INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35 76.20 73.91
04.06.08.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65 66.50 64.51

01 LOCALIDAD SANTA LUCIA


01.01 CAPACITACION EN EDUCACION SANITARIA, PROMOCION DE LA SALUD Y AOM
01.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
01.01.01.01 TALLER IMPORTANCIA DE LA ORGANIZACION Y PARTICIPACION CIUDADANA Tall 1.00 940.60 940.60 912.38
01.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60 940.60 912.38
01.01.02 EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y SALUD)
01.01.02.01 TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y SALUD (Valoracion del agua) Tall 1.00 940.61 940.61 912.39
01.01.02.02 TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION DE EXCRETAS Tall 1.00 940.61 940.61 912.39
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL HOGAR Y
01.01.02.03 Tall 1.00 940.61 940.61 912.39
COMUNAL
01.01.02.04 CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE. Tall 1.00 940.61 940.61 912.39
01.01.02.05 DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y SANEAMIENTO (SPOT PUBLICITARIO) Men 2.00 84.74 169.48 164.40
01.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
01.01.03.01 TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS Tall 1.00 940.61 940.61 912.39
01.01.03.02 TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA POTABLE Tall 1.00 940.61 940.61 912.39
01.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61 940.61 912.39
01.01.03.04 TALLER DE CLORACION Y DESINFECCION DE AGUA PARA CONSUMO HUMANO Tall 1.00 1,110.11 1,110.11 1,076.81
01.02 FLETE
01.02.01 FLETE RURAL
01.02.01.01 FLETE RURAL GLB 1.00 25,395.57 25,395.57 24,633.70
01.02.02 FLETE TERRESTRE
01.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00 4,725.00 4,583.25
01.02.02.02 FLETE TERRESTRE GLB 1.00 10,576.27 10,576.27 10,258.98
01.03 MITIGACION AMBIENTAL
01.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00 2,840.00 2,754.80
01.03.02 PROGRAMA DE CONSERVACION, RESTAURACION Y COMPESACION DE COBERTURA VEGETAL (REFORESTACION) GLB 1.00 1,712.00 1,712.00 1,660.64
01.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00 3,400.00 3,298.00
01.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00 1,000.00 970.00
01.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 500.00 500.00 485.00
01.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00 3,600.00 3,492.00
01.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00 600.00 582.00
01.04 CONTROL Y SEGURIDAD EN OBRA
01.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 6,959.68 6,959.68 6,750.89
02 LOCALIDAD PUEBLO LIBRE
02.01 CAPACITACION EN EDUCACION SANITARIA, PROMOCION DE LA SALUD Y AOM
02.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
02.01.01.01 TALLER IMPORTANCIA DE LA ORGANIZACION Y PARTICIPACION CIUDADANA Tall 1.00 940.60 940.60 912.38
02.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60 940.60 912.38
02.01.02 EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y SALUD)
02.01.02.01 TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y SALUD (Valoracion del agua) Tall 1.00 940.61 940.61 912.39
02.01.02.02 TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION DE EXCRETAS Tall 1.00 940.61 940.61 912.39
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL HOGAR Y
02.01.02.03 Tall 1.00 940.61 940.61 912.39
COMUNAL
02.01.02.04 CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE. Tall 1.00 940.61 940.61 912.39
02.01.02.05 DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y SANEAMIENTO (SPOT PUBLICITARIO) Men 2.00 84.74 169.48 164.40
02.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
02.01.03.01 TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS Tall 1.00 940.61 940.61 912.39
02.01.03.02 TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA POTABLE Tall 1.00 940.61 940.61 912.39
02.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61 940.61 912.39
02.01.03.04 TALLER DE CLORACION Y DESINFECCION DE AGUA PARA CONSUMO HUMANO Tall 1.00 1,110.11 1,110.11 1,076.81
02.02 FLETE
02.02.01 FLETE RURAL
02.02.01.01 FLETE RURAL GLB 1.00 34,884.02 34,884.02 33,837.50
02.02.02 FLETE TERRESTRE
02.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00 4,725.00 4,583.25
02.02.02.02 FLETE TERRESTRE GLB 1.00 17,338.98 17,338.98 16,818.81
02.02.03 MITIGACION AMBIENTAL
02.02.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00 2,840.00 2,754.80
02.02.03.02 PROGRAMA DE CONSERVACION, RESTAURACION Y COMPESACION DE COBERTURA VEGETAL (REFORESTACION) GLB 1.00 1,712.00 1,712.00 1,660.64
02.02.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00 3,400.00 3,298.00
02.02.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00 1,000.00 970.00
02.02.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 500.00 500.00 485.00
02.02.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00 3,600.00 3,492.00
02.02.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00 600.00 582.00
02.02.04 CONTROL Y SEGURIDAD EN OBRA
02.02.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 9,221.36 9,221.36 8,944.72
03 LOCALIDAD TANCARPATA
03.01 CAPACITACION EN EDUCACION SANITARIA, PROMOCION DE LA SALUD Y AOM
03.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
03.01.01.01 TALLER IMPORTANCIA DE LA ORGANIZACION Y PARTICIPACION CIUDADANA Tall 1.00 940.60 940.60 912.38
03.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60 940.60 912.38
03.01.02 EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y SALUD)
03.01.02.01 TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y SALUD (Valoracion del agua) Tall 1.00 940.61 940.61 912.39
03.01.02.02 TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION DE EXCRETAS Tall 1.00 940.61 940.61 912.39
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL HOGAR Y
03.01.02.03 Tall 1.00 940.61 940.61 912.39
COMUNAL
03.01.02.04 CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE. Tall 1.00 940.61 940.61 912.39
03.01.02.05 DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y SANEAMIENTO (SPOT PUBLICITARIO) Men 2.00 84.74 169.48 164.40
03.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
03.01.03.01 TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS Tall 1.00 940.61 940.61 912.39
03.01.03.02 TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA POTABLE Tall 1.00 940.61 940.61 912.39
03.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61 940.61 912.39
03.01.03.04 TALLER DE CLORACION Y DESINFECCION DE AGUA PARA CONSUMO HUMANO Tall 1.00 1,110.11 1,110.11 1,076.81
03.02 FLETE
03.02.01 FLETE RURAL
03.02.01.01 FLETE RURAL GLB 1.00 15,348.97 15,348.97 14,888.50
03.02.02 FLETE TERRESTRE
03.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00 4,725.00 4,583.25
03.02.02.02 FLETE TERRESTRE GLB 1.00 6,864.41 6,864.41 6,658.48
03.03 MITIGACION AMBIENTAL
03.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00 2,840.00 2,754.80
03.03.02 PROGRAMA DE CONSERVACION, RESTAURACION Y COMPESACION DE COBERTURA VEGETAL (REFORESTACION) GLB 1.00 1,712.00 1,712.00 1,660.64
03.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00 3,400.00 3,298.00
03.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00 1,000.00 970.00
03.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 500.00 500.00 485.00
03.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00 3,600.00 3,492.00
03.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00 600.00 582.00
03.04 CONTROL Y SEGURIDAD EN OBRA
03.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 4,564.96 4,564.96 4,428.01
04 LOCALIDAD TARACA
04.01 CAPACITACION EN EDUCACION SANITARIA, PROMOCION DE LA SALUD Y AOM
04.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
04.01.01.01 TALLER IMPORTANCIA DE LA ORGANIZACION Y PARTICIPACION CIUDADANA Tall 1.00 940.60 940.60 912.38
04.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60 940.60 912.38
04.01.02 EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y SALUD)
04.01.02.01 TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y SALUD (Valoracion del agua) Tall 1.00 940.61 940.61 912.39
04.01.02.02 TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION DE EXCRETAS Tall 1.00 940.61 940.61 912.39
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL HOGAR Y
04.01.02.03 Tall 1.00 940.61 940.61 912.39
COMUNAL
04.01.02.04 CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE. Tall 1.00 940.61 940.61 912.39
04.01.02.05 DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y SANEAMIENTO (SPOT PUBLICITARIO) Men 2.00 84.74 169.48 164.40
04.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
04.01.03.01 TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS Tall 1.00 940.61 940.61 912.39
04.01.03.02 TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA POTABLE Tall 1.00 940.61 940.61 912.39
04.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61 940.61 912.39
04.01.03.04 TALLER DE CLORACION Y DESINFECCION DE AGUA PARA CONSUMO HUMANO Tall 1.00 1,110.11 1,110.11 1,076.81
04.02 FLETE
04.02.01 FLETE RURAL
04.02.01.01 FLETE RURAL GLB 1.00 15,348.97 15,348.97 14,888.50
04.02.02 FLETE TERRESTRE
04.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00 4,725.00 4,583.25
04.02.02.02 FLETE TERRESTRE GLB 1.00 7,372.78 7,372.78 7,151.60
04.03 MITIGACION AMBIENTAL
04.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,839.85 2,839.85 2,754.65
04.03.02 PROGRAMA DE CONSERVACION, RESTAURACION Y COMPESACION DE COBERTURA VEGETAL (REFORESTACION) GLB 1.00 1,712.00 1,712.00 1,660.64
04.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00 3,400.00 3,298.00
04.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00 1,000.00 970.00
04.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 500.00 500.00 485.00
04.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00 3,600.00 3,492.00
04.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00 600.00 582.00
04.04 CONTROL Y SEGURIDAD EN OBRA
04.04.01 IMPLEMENTOS DE SEGURIDAD PUEBLO LIBRE GLB 1.00 4,564.96 4,564.96 4,428.01

COSTO DIRECTO 5,121,687.34 4,968,036.72

GASTOS GENERALES (8%) 408,710.65 396,449.33

UTILIDAD (7%) 358,518.11 347,762.57

==================

SUB TOTAL 5,888,916.09 5,712,248.62

IGV (18%) 1,060,004.90 1,028,204.75

==================

PRESUPUESTO DE OBRA 6,948,921.00 6,740,453.37


ITEM DESCRIPCIÓN UNIDAD METRADO PRECIO (S/.)

01 LOCALIDAD SANTA LUCIA


01.01 CONSTRUCCIONES PROVISIONALES
01.01.01 OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y VESTUARIOS m2 100.00 44.55
01.01.02 ALQUILER DE PREDIOS PARA CAMPAMENTOS Y ALMACENES mes 6.00 500.00
01.01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20 m und 1.00 1,539.82
01.02 CAPTACION TIPO LADERA (ROBLEMONTE)
01.02.01 TRABAJOS PRELIMINARES
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49
01.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84
01.02.02 MOVIMIENTO DE TIERRAS
01.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 16.23 39.86
01.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO C/PISON m3 2.55 29.50
01.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95
01.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 17.10 25.69
01.02.03 CONCRETO SIMPLE
01.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48
01.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10
01.02.04 CONCRETO ARMADO
01.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84
01.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48
01.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35
01.02.05 REVOQUES Y ENLUCIDOS
01.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3 e=1.5cm m2 5.53 32.48
01.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76
01.02.06 PINTURA
01.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 13.23
01.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
01.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85
01.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77
01.02.08 CARPINTERIA METALICA
01.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 179.83
01.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53
01.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO HIDRAULICO y VENTILACION
01.02.09.01 und 1.00 501.29
Ø=2")
01.02.10 CERCO PERIMETRICO EN CAPTACION
01.02.10.01 TRABAJOS PRELIMINARES
01.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84
01.02.10.02 MOVIMIENTO DE TIERRAS
01.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86
01.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69
01.02.10.03 CONCRETO SIMPLE
01.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98
01.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
01.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48
01.02.10.05 COLOCADO DE ROLLIZOS
01.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83
01.02.10.06 PINTURA EN CERCO PERIMETRICO
01.02.10.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 33.80 3.80
01.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
01.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22
01.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
01.02.10.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10
01.03 LINEA DE CONDUCCION (L=1102.00 m)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,102.00 0.49
01.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 1,102.00 1.53
01.03.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 1,102.00 1.53
01.03.02 MOVIMIENTO DE TIERRAS
01.03.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 396.72 49.82
01.03.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 44.08 55.80
01.03.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 1,102.00 1.81
01.03.02.04 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 110.20 6.08
01.03.02.05 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 165.30 36.40
01.03.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.50 m m3 27.55 65.17
01.03.02.07 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 27.55 25.69
01.03.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SP C-10, Ø=1" m 1,102.00 7.19
01.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 140.33
01.03.04 PRUEBA HIDRAULICA
01.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 1,102.00 1.51
01.03.05 CAMARA ROMPE PRESION T-6 (01 UND)
01.03.05.01 OBRAS PRELIMINARES
01.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.44 0.49
01.03.05.01.02 TRAZO Y REPLANTEO m2 1.44 1.84
01.03.05.02 MOVIMIENTO DE TIERRAS
01.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.58 39.86
01.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.98 25.69
01.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 1.44 7.95
01.03.05.03 OBRAS DE CONCRETO SIMPLE
01.03.05.03.01 SOLADO E=4" m3 1.21 35.81
01.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17
01.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48
01.03.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10
01.03.05.04 OBRAS DE CONCRETO ARMADO
01.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 0.79 546.69
01.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.10 44.48
01.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 37.23 4.35
01.03.05.05 REVOQUES Y ENLUCIDOS
01.03.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 2.52 32.48
01.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.24 29.76
01.03.05.06 PINTURA
01.03.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 3.24 11.18
01.03.05.07 CARPINTERIA METALICA
01.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 1.00 213.73
01.03.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.03.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T6, INGRESO Ø=1" y SALIDA Ø=1" und 1.00 299.60
01.03.06 VALVULA DE PURGA TIPO I (1 UND)
01.03.06.01 OBRAS PRELIMINARES
01.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 0.49
01.03.06.01.02 TRAZO Y REPLANTEO m2 1.00 1.84
01.03.06.02 MOVIMIENTO DE TIERRAS
01.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.51 39.86
01.03.06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 0.51 13.11
01.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.49 7.95
01.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 0.64 25.69
01.03.06.03 OBRAS DE CONCRETO SIMPLE
01.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.02 413.17
01.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.24 44.48
01.03.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.27 121.10
01.03.06.04 OBRAS DE CONCRETO ARMADO
01.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.35 546.69
01.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.72 44.48
01.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 14.94 4.35
01.03.06.05 REVOQUES Y ENLUCIDOS
01.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 1.44 32.48
01.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.36 29.76
01.03.06.06 PINTURA
01.03.06.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 2.16 11.18
01.03.06.07 CARPINTERIA METALICA
01.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 1.00 214.83
01.03.06.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.03.06.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO I, Ø=1" und 1.00 153.06
01.04 RESERVORIO (V=8.00 m3, 01 UND)
01.04.01 OBRAS PRELIMINARES
01.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49
01.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.84
01.04.02 MOVIMIENTO DE TIERRAS
01.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 51.43 39.86
01.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 11.41 7.95
01.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 64.29 25.69
01.04.03 CONCRETO SIMPLE
01.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17
01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48
01.04.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10
01.04.04 OBRAS DE CONCRETO ARMADO
01.04.04.01 SOLADO PARA LOSA FONDO m2 11.41 40.87
01.04.04.02 CONCRETO f'c=210 kg/cm2 m3 11.27 546.69
01.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 51.29 44.48
01.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 322.94 4.35
01.04.05 REVOQUES Y ENLUCIDOS
01.04.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 31.32 32.48
01.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 40.61 29.76
01.04.06 PINTURA
01.04.06.01 PINTURA ESMALTE EN MUROS EXTERIORES DE RESERVORIO m2 34.92 13.23
01.04.07 CARPINTERIA METALICA
01.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73
01.04.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.04.08.01 SUMINISTRO E INSTALACIONES DE ACCESORIOS EN RESERVORIO (ING. 1 ", SAL.1") und 1.00 1,745.47
01.04.09 CERCO PERIMETRICO EN RESERVORIO
01.04.09.01 TRABAJOS PRELIMINARES
01.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84
01.04.09.02 MOVIMIENTO DE TIERRAS
01.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86
01.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69
01.04.09.03 CONCRETO SIMPLE
01.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98
01.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
01.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48
01.04.09.05 COLOCADO DE ROLLIZOS
01.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83
01.04.09.06 PINTURA EN CERCO PERIMETRICO
01.04.09.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 66.40 3.80
01.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
01.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22
01.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
01.04.09.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10
01.04.10 CLORADOR POR GOTEO
01.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
01.04.10.01.01 CASETA DE MURO DE LADRILLO -CLORADOR POR GOTEO
01.04.10.01.01.0
MURO DE LADRILLO PANDERETA (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 7.52 54.96
1
01.04.10.01.01.0
MURO DE LADRILLO PANDERETA INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 4.48 49.36
2
01.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
01.04.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 29.07
1
01.04.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 34.08
2
01.04.10.01.03 REVOQUES Y ENLUCIDOS
01.04.10.01.03.0
TARRAJEO MUROS DE INTERIORES Y EXTERIORES, CEMENTO : ARENA, 1:5 m2 14.98 30.00
1
01.04.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.78
2
01.04.10.01.04 CARPINTERIA METALICA
01.04.10.01.04.0
SUMINISTRO E INSTALACION DE PUERTA METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO und 1.00 367.18
1
01.04.10.01.05 PINTURAS
01.04.10.01.05.0
PINTURA ESMALTE EN MUROS INTERIORES Y EXTERIORES m2 14.98 11.18
1
01.04.10.01.05.0
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 12.25
2
01.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
01.04.10.02.01 SUMINISTRO E INSTALACION DE TANQUE DE POLIETILENO, CAP=250 LTRS. und 1.00 435.06
01.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
01.04.10.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS Y ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO GLB 1.00 939.22
01.05 RED DE ADUCCION Y DISTRIBUCION (L=4,375.00m)
01.05.01 TRABAJOS PRELIMINARES
01.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,187.50 0.49
01.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 4,375.00 1.53
01.05.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 4,375.00 1.53
01.05.02 MOVIMIENTO DE TIERRAS
01.05.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 525.00 39.86
01.05.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 1,137.50 49.82
01.05.02.03 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 87.50 55.80
01.05.02.04 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 4,375.00 1.81
01.05.02.05 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 4,375.00 6.08
01.05.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 623.44 36.40
01.05.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 32.81 65.17
01.05.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 1,181.25 25.07
01.05.02.09 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 142.19 62.16
01.05.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 87.50 25.69
01.05.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 1,820.00 8.05
01.05.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 3/4" m 2,555.00 4.84
01.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 137.74
01.05.04 PRUEBA HIDRAULICA
01.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 4,375.00 1.51
01.05.05 CAMARA ROMPE PRESION T-7 (11 UND)
01.05.05.01 OBRAS PRELIMINARES
01.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 22.77 0.49
01.05.05.01.02 TRAZO Y REPLANTEO m2 22.77 1.84
01.05.05.02 MOVIMIENTO DE TIERRAS
01.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 14.32 39.86
01.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 9.55 40.95
01.05.05.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 2.39 13.11
01.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 21.62 7.95
01.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.28 59.44
01.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 9.84 25.69
01.05.05.03 OBRAS DE CONCRETO SIMPLE
01.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.13 413.17
01.05.05.03.02 SOLADO E=4" m3 1.82 35.81
01.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.20 44.48
01.05.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 2.97 121.10
01.05.05.04 OBRAS DE CONCRETO ARMADO
01.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 14.96 546.69
01.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 153.14 44.48
01.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,164.62 4.35
01.05.05.05 REVOQUES Y ENLUCIDOS
01.05.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 47.52 32.48
01.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 102.98 29.76
01.05.05.06 PINTURA
01.05.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 66.00 11.18
01.05.05.07 CARPINTERIA METALICA
01.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 11.00 179.83
01.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 11.00 213.73
01.05.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=1" und 7.00 384.08
01.05.05.08.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=3/4" und 5.00 379.18
01.05.06 VALVULA DE CONTROL (05 UND)
01.05.06.01 OBRAS PRELIMINARES
01.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49
01.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.84
01.05.06.02 MOVIMIENTO DE TIERRAS
01.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 39.86
01.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 25.69
01.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.95
01.05.06.03 OBRAS DE CONCRETO ARMADO
01.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 546.69
01.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 44.48
01.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.35
01.05.06.04 REVOQUES Y ENLUCIDOS
01.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 32.48
01.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 29.76
01.05.06.05 PINTURA
01.05.06.05.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 6.48 11.18
01.05.06.06 CARPINTERIA METALICA
01.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 162.88
01.05.06.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=1" und 1.00 90.28
01.05.06.07.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=3/4" und 4.00 79.02
01.05.07 VALVULA DE PURGA TIPO II (08 UND)
01.05.07.01 OBRAS PRELIMINARES
01.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.00 0.49
01.05.07.01.02 TRAZO Y REPLANTEO m2 8.00 1.84
01.05.07.02 MOVIMIENTO DE TIERRAS
01.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 12.23 39.86
01.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 4.08 49.82
01.05.07.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 4.08 13.11
01.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 3.92 7.95
01.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.92 25.69
01.05.07.03 OBRAS DE CONCRETO SIMPLE
01.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 2.45 413.17
01.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.92 44.48
01.05.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 1.02 121.10
01.05.07.04 OBRAS DE CONCRETO ARMADO
01.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 2.80 546.69
01.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 29.76 44.48
01.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 119.53 4.35
01.05.07.05 REVOQUES Y ENLUCIDOS
01.05.07.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 11.52 32.48
01.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 26.88 29.76
01.05.07.06 PINTURA
01.05.07.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 12.96 11.18
01.05.07.07 CARPINTERIA METALICA
01.05.07.07.01 MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE 0.60x0.40m. und 8.00 213.73
01.05.07.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.07.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=1" und 1.00 149.25
01.05.07.08.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4" und 7.00 132.94
01.05.08 CONEXIONES DOMICILIARIAS (92 UND)
01.05.08.01 OBRAS PRELIMINARES
01.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 824.32 0.49
01.05.08.01.02 TRAZO Y REPLANTEO m2 1,236.48 1.84
01.05.08.02 MOVIMIENTO DE TIERRAS
01.05.08.02.01 EXCAVACION A MANO DE ZANJA MANUAL TERRENO NORMAL m3 989.18 39.86
01.05.08.02.02 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO CLASIFICADO m3 989.18 33.00
01.05.08.02.03 SUMINISTRO Y COLOCACION DE GRAVA SELECCIONADA m3 103.04 209.11
01.05.08.03 OBRAS DE CONCRETO SIMPLE
01.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 6.82 413.17
01.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 34.04 44.48
01.05.08.04 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
01.05.08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND) und 92.00 80.77
01.05.08.04.02 TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON LLAVE TIPO BUJIA und 92.00 155.21
01.05.08.04.03 SUMINISTRO E INSTALACIONES DE ACOMETIDA DOMICILIARIA RANGO 2 - 50 M. m 736.00 3.50
02 LOCALIDAD PUEBLO LIBRE
02.01 CONSTRUCCIONES PROVISIONALES
02.01.01 OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y VESTUARIOS m2 100.00 44.55
02.01.02 ALQUILER DE PREDIOS PARA CAMPAMENTOS Y ALMACENES mes 6.00 500.00
02.01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20 m und 1.00 1,539.82
02.02 CAPTACION TIPO LADERA (YACUPACCARI)
02.02.01 TRABAJOS PRELIMINARES
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49
02.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 22.53 39.86
02.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO C/PISON m3 2.55 29.50
02.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95
02.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 25.05 25.69
02.02.03 CONCRETO SIMPLE
02.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48
02.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10
02.02.04 CONCRETO ARMADO
02.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84
02.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48
02.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35
02.02.05 REVOQUES Y ENLUCIDOS
02.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3 e=1.5cm m2 5.53 32.48
02.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76
02.02.06 PINTURA
02.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 13.23
02.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
02.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85
02.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77
02.02.08 CARPINTERIA METALICA
02.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 180.93
02.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53
02.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO HIDRAULICO y VENTILACION
02.02.09.01 und 1.00 501.29
Ø=2"
02.02.10 CERCO PERIMETRICO EN CAPTACION
02.02.10.01 TRABAJOS PRELIMINARES
02.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84
02.02.10.02 MOVIMIENTO DE TIERRAS
02.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86
02.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69
02.02.10.03 CONCRETO SIMPLE
02.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98
02.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
02.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48
02.02.10.05 COLOCADO DE ROLLIZOS
02.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83
02.02.10.06 PINTURA EN CERCO PERIMETRICO
02.02.10.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 33.80 3.80
02.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
02.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22
02.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
02.02.10.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10
02.03 CRUCE AEREO DE L=6.00 ML. (01 UNIDAD)
02.03.01 OBRAS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 22.40 0.49
02.03.01.02 TRAZO Y REPLANTEO m2 22.40 1.84
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION A MANO TERRENO NORMAL m3 2.57 39.86
02.03.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.21 25.69
02.03.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 3.28 7.95
02.03.03 OBRAS DE CONCRETO SIMPLE
02.03.03.01 CONCRETO F'C=100 KG/CM2.PARA SOLADOS m3 0.13 403.78
02.03.04 OBRAS DE CONCRETO ARMADO
02.03.04.01 CONCRETO FC=210 KG/CM2 m3 2.72 466.07
02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.50 44.48
02.03.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 40.12 4.35
02.03.05 REVOQUES Y ENLUCIDOS
02.03.05.01 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 2.50 29.76
02.03.06 PINTURA
02.03.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 2.50 19.51
02.03.07 TUBERIA TN ISO 65 SERIE LIVIANA (L)
02.03.07.01 SUMINISTRO E INSTALACION DE TUBERIA TN ISO 65 Ø 1" m 11.70 312.13
02.03.08 CABLE DE ACERO PRINCIPAL Ø 3/8" TIPO BOA
02.03.08.01 TENDIDO DE CABLE PRINCIPAL TIPO BOA Ø 3/8 m 7.86 37.33
02.03.09 PENDOLAS
02.03.09.01 PENDOLAS CON F° LISO Ø 1/4" m 14.40 35.37
02.03.10 ACCESORIOS
02.03.10.01 ACCESORIOS PARA ACUEDUCTO COLGANTE, ARGOLLA Ø 1", L=6.00ml und 1.00 934.94
02.04 LINEA DE CONDUCCION (L=2153.00 m)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,153.00 0.49
02.04.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 2,153.00 1.53
02.04.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 2,153.00 1.53
02.04.02 MOVIMIENTO DE TIERRAS
02.04.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 86.12 39.86
02.04.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 775.08 49.82
02.04.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 2,153.00 1.81
02.04.02.04 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 2,153.00 4.28
02.04.02.05 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 322.95 36.40
02.04.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 538.25 25.07
02.04.02.07 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 26.91 25.69
02.04.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.04.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 2,153.00 5.94
02.04.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 215.53
02.04.04 PRUEBA HIDRAULICA
02.04.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 2,153.00 1.51
02.04.05 CAMARA ROMPE PRESION T-6 (06 UND)
02.04.05.01 OBRAS PRELIMINARES
02.04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.64 0.49
02.04.05.01.02 TRAZO Y REPLANTEO m2 8.64 1.84
02.04.05.02 MOVIMIENTO DE TIERRAS
02.04.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 9.50 39.86
02.04.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.88 25.69
02.04.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 8.64 7.95
02.04.05.03 OBRAS DE CONCRETO SIMPLE
02.04.05.03.01 SOLADO E=4" m3 7.26 35.81
02.04.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.07 413.17
02.04.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 44.48
02.04.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 3.00 121.10
02.04.05.04 OBRAS DE CONCRETO ARMADO
02.04.05.04.01 CONCRETO f'c=210 kg/cm2 m3 4.74 546.69
02.04.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 48.60 44.48
02.04.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 223.37 4.35
02.04.05.05 REVOQUES Y ENLUCIDOS
02.04.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 15.12 32.48
02.04.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 19.44 29.76
02.04.05.06 PINTURA
02.04.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 19.44 11.18
02.04.05.07 CARPINTERIA METALICA
02.04.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 6.00 213.73
02.04.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.04.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T6, INGRESO Ø=1 1/2" y SALIDA Ø=1 1/2" und 6.00 299.60
02.04.06 VALVULA DE PURGA TIPO I (2 UND)
02.04.06.01 OBRAS PRELIMINARES
02.04.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.00 0.49
02.04.06.01.02 TRAZO Y REPLANTEO m2 2.00 1.84
02.04.06.02 MOVIMIENTO DE TIERRAS
02.04.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.02 39.86
02.04.06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 1.02 13.11
02.04.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.98 7.95
02.04.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1.27 25.69
02.04.06.03 OBRAS DE CONCRETO SIMPLE
02.04.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.04 413.17
02.04.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.48 44.48
02.04.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.54 121.10
02.04.06.04 OBRAS DE CONCRETO ARMADO
02.04.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.70 546.69
02.04.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.44 44.48
02.04.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 29.88 4.35
02.04.06.05 REVOQUES Y ENLUCIDOS
02.04.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 2.88 32.48
02.04.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.72 29.76
02.04.06.06 PINTURA
02.04.06.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 4.32 11.18
02.04.06.07 CARPINTERIA METALICA
02.04.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 2.00 214.83
02.04.06.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.04.06.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO I, Ø=1 1/2" und 2.00 153.06
02.05 RESERVORIO (V=10.00 m3, 01 UND)
02.05.01 OBRAS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49
02.05.01.02 TRAZO Y REPLANTEO m2 36.00 1.84
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 79.30 39.86
02.05.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 11.41 7.95
02.05.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 99.13 25.69
02.05.03 CONCRETO SIMPLE
02.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17
02.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48
02.05.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 SOLADO PARA LOSA FONDO m2 11.41 40.87
02.05.04.02 CONCRETO f'c=210 kg/cm2 m3 13.50 546.69
02.05.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 57.48 44.48
02.05.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 349.49 4.35
02.05.05 REVOQUES Y ENLUCIDOS
02.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 32.94 32.48
02.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 57.14 29.76
02.05.06 PINTURA
02.05.06.01 PINTURA ESMALTE EN MUROS EXTERIORES DE RESERVORIO m2 51.45 13.23
02.05.07 CARPINTERIA METALICA
02.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73
02.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.05.08.01 SUMINISTRO E INSTALACIONES DE ACCESORIOS EN RESERVORIO (ING. 1", SAL.1") und 1.00 1,745.47
02.05.09 CERCO PERIMETRICO EN RESERVORIO
02.05.09.01 TRABAJOS PRELIMINARES
02.05.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84
02.05.09.02 MOVIMIENTO DE TIERRAS
02.05.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86
02.05.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69
02.05.09.03 CONCRETO SIMPLE
02.05.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98
02.05.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
02.05.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48
02.05.09.05 COLOCADO DE ROLLIZOS
02.05.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83
02.05.09.06 PINTURA EN CERCO PERIMETRICO
02.05.09.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 66.40 3.80
02.05.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
02.05.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22
02.05.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
02.05.09.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10
02.05.10 CLORADOR POR GOTEO
02.05.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
02.05.10.01.01 CASETA DE MURO DE LADRILLO -CLORADOR POR GOTEO
02.05.10.01.01.0
MURO DE LADRILLO PANDERETA (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 7.52 54.96
1
02.05.10.01.01.0
MURO DE LADRILLO PANDERETA INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 4.48 49.36
2
02.05.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
02.05.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 29.07
1
02.05.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 34.08
2
02.05.10.01.03 REVOQUES Y ENLUCIDOS
02.05.10.01.03.0
TARRAJEO MUROS DE INTERIORES Y EXTERIORES, CEMENTO : ARENA, 1:5 m2 14.98 30.00
1
02.05.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.78
2
02.05.10.01.04 CARPINTERIA METALICA
02.05.10.01.04.0
SUMINISTRO E INSTALACION DE PUERTA METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO und 1.00 367.18
1
02.05.10.01.05 PINTURAS
02.05.10.01.05.0
PINTURA ESMALTE EN MUROS INTERIORES Y EXTERIORES m2 14.98 11.18
1
02.05.10.01.05.0
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 12.25
2
02.05.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
02.05.10.02.01 SUMINISTRO E INSTALACION DE TANQUE DE POLIETILENO, CAP=250 LTRS. und 1.00 435.06
02.05.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
02.05.10.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS Y ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO GLB 1.00 939.22
02.06 RED DE ADUCCION Y DISTRIBUCION (L=5,678.00 m)
02.06.01 TRABAJOS PRELIMINARES
02.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,839.00 0.49
02.06.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 5,678.00 1.53
02.06.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 5,678.00 1.53
02.06.02 MOVIMIENTO DE TIERRAS
02.06.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 1,362.72 49.82
02.06.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 908.48 55.80
02.06.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 5,678.00 1.81
02.06.02.04 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 2,271.20 6.08
02.06.02.05 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 511.02 36.40
02.06.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 567.80 65.17
02.06.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 1,987.30 25.07
02.06.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 1,135.60 62.16
02.06.02.09 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 567.80 25.69
02.06.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 1,146.00 8.05
02.06.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 3/4" m 4,533.00 4.84
02.06.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 351.43
02.06.04 PRUEBA HIDRAULICA
02.06.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 5,678.00 1.51
02.06.05 CAMARA ROMPE PRESION T-7 (16 UND)
02.06.05.01 OBRAS PRELIMINARES
02.06.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 33.12 0.49
02.06.05.01.02 TRAZO Y REPLANTEO m2 33.12 1.84
02.06.05.02 MOVIMIENTO DE TIERRAS
02.06.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 22.91 39.86
02.06.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 15.27 40.95
02.06.05.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 3.82 13.11
02.06.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 31.44 7.95
02.06.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.86 59.44
02.06.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 22.91 25.69
02.06.05.03 OBRAS DE CONCRETO SIMPLE
02.06.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.19 413.17
02.06.05.03.02 SOLADO E=4" m3 2.64 35.81
02.06.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.20 44.48
02.06.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 4.32 121.10
02.06.05.04 OBRAS DE CONCRETO ARMADO
02.06.05.04.01 CONCRETO f'c=210 kg/cm2 m3 21.74 546.69
02.06.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 222.76 44.48
02.06.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 3,148.54 4.35
02.06.05.05 REVOQUES Y ENLUCIDOS
02.06.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 69.12 32.48
02.06.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 149.79 29.76
02.06.05.06 PINTURA
02.06.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 96.00 11.18
02.06.05.07 CARPINTERIA METALICA
02.06.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 16.00 179.83
02.06.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 16.00 213.73
02.06.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=1" und 3.00 384.08
02.06.05.08.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=3/4" und 13.00 379.18
02.06.06 VALVULA DE CONTROL (05 UND)
02.06.06.01 OBRAS PRELIMINARES
02.06.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.00 0.49
02.06.06.01.02 TRAZO Y REPLANTEO m2 6.00 1.84
02.06.06.02 MOVIMIENTO DE TIERRAS
02.06.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 6.00 39.86
02.06.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 7.50 25.69
02.06.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 6.00 7.95
02.06.06.03 OBRAS DE CONCRETO ARMADO
02.06.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.96 546.69
02.06.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 25.56 44.48
02.06.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 184.53 4.35
02.06.06.04 REVOQUES Y ENLUCIDOS
02.06.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 8.64 32.48
02.06.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 12.96 29.76
02.06.06.05 PINTURA
02.06.06.05.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 12.96 11.18
02.06.06.06 CARPINTERIA METALICA
02.06.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 6.00 162.88
02.06.06.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=1" und 2.00 90.28
02.06.06.07.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=3/4" und 4.00 79.02
02.06.07 VALVULA DE PURGA TIPO II (03 UND)
02.06.07.01 OBRAS PRELIMINARES
02.06.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 3.00 0.49
02.06.07.01.02 TRAZO Y REPLANTEO m2 3.00 1.84
02.06.07.02 MOVIMIENTO DE TIERRAS
02.06.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 4.59 39.86
02.06.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 1.53 49.82
02.06.07.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 1.53 13.11
02.06.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 1.47 7.95
02.06.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.47 25.69
02.06.07.03 OBRAS DE CONCRETO SIMPLE
02.06.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.92 413.17
02.06.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.72 44.48
02.06.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.38 121.10
02.06.07.04 OBRAS DE CONCRETO ARMADO
02.06.07.04.01 CONCRETO f'c=210 kg/cm2 m3 1.05 546.69
02.06.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 11.16 44.48
02.06.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 44.82 4.35
02.06.07.05 REVOQUES Y ENLUCIDOS
02.06.07.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 4.32 32.48
02.06.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.08 29.76
02.06.07.06 PINTURA
02.06.07.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 4.84 11.18
02.06.07.07 CARPINTERIA METALICA
02.06.07.07.01 MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE 0.60x0.40m. und 3.00 213.73
02.06.07.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.07.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4" und 3.00 132.94
02.06.08 CONEXIONES DOMICILIARIAS (125 UND)
02.06.08.01 OBRAS PRELIMINARES
02.06.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,120.00 0.49
02.06.08.01.02 TRAZO Y REPLANTEO m2 1,680.00 1.84
02.06.08.02 MOVIMIENTO DE TIERRAS
02.06.08.02.01 EXCAVACION A MANO DE ZANJA MANUAL TERRENO NORMAL m3 1,344.00 39.86
02.06.08.02.02 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO CLASIFICADO m3 1,344.00 33.00
02.06.08.02.03 SUMINISTRO Y COLOCACION DE GRAVA SELECCIONADA m3 140.00 209.11
02.06.08.03 OBRAS DE CONCRETO SIMPLE
02.06.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 9.27 413.17
02.06.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 46.25 44.48
02.06.08.04 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
02.06.08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND) und 125.00 80.77
02.06.08.04.02 TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON LLAVE TIPO BUJIA und 125.00 155.21
02.06.08.04.03 SUMINISTRO E INSTALACIONES DE ACOMETIDA DOMICILIARIA RANGO 2 - 20 M. m 1,125.00 3.50
03 LOCALIDAD TANCARPATA
03.01 CONSTRUCCIONES PROVISIONALES
03.01.01 OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y VESTUARIOS m2 100.00 44.55
03.01.02 ALQUILER DE PREDIOS PARA CAMPAMENTOS Y ALMACENES mes 6.00 500.00
03.01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20 m und 1.00 1,539.82
03.02 CAPTACION A TIPO LADERA YACUTOCCYAC (01 UND)
03.02.01 TRABAJOS PRELIMINARES
03.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49
03.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84
03.02.02 MOVIMIENTO DE TIERRAS
03.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 15.03 39.86
03.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO C/PISON m3 2.55 29.50
03.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95
03.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.60 25.69
03.02.03 CONCRETO SIMPLE
03.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48
03.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10
03.02.04 CONCRETO ARMADO
03.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84
03.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48
03.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35
03.02.05 REVOQUES Y ENLUCIDOS
03.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3 e=1.5cm m2 5.53 32.48
03.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76
03.02.06 PINTURA
03.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 13.23
03.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
03.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85
03.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77
03.02.08 CARPINTERIA METALICA
03.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 180.93
03.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53
03.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO HIDRAULICO y VENTILACION
03.02.09.01 und 1.00 497.69
Ø=2")
03.02.10 CERCO PERIMETRICO EN CAPTACION
03.02.10.01 TRABAJOS PRELIMINARES
03.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84
03.02.10.02 MOVIMIENTO DE TIERRAS
03.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86
03.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69
03.02.10.03 CONCRETO SIMPLE
03.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98
03.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
03.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48
03.02.10.05 COLOCADO DE ROLLIZOS
03.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83
03.02.10.06 PINTURA EN CERCO PERIMETRICO
03.02.10.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 33.80 3.80
03.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
03.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22
03.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
03.02.10.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10
03.03 LINEA DE CONDUCCION (L=196.00 m)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 196.00 0.49
03.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 196.00 1.53
03.03.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 196.00 1.53
03.03.02 MOVIMIENTO DE TIERRAS
03.03.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 72.13 49.82
03.03.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 6.27 55.80
03.03.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 196.00 1.81
03.03.02.04 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 196.00 6.08
03.03.02.05 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 196.00 4.28
03.03.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 27.05 36.40
03.03.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 2.35 65.17
03.03.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 45.05 25.07
03.03.02.09 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 3.92 62.16
03.03.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.92 25.69
03.03.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 196.00 5.94
03.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 160.91
03.03.04 PRUEBA HIDRAULICA
03.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 180.36 1.51
03.03.05 CAMARA ROMPE PRESION T-6 (01 UND)
03.03.05.01 OBRAS PRELIMINARES
03.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.44 0.49
03.03.05.01.02 TRAZO Y REPLANTEO m2 1.44 1.84
03.03.05.02 MOVIMIENTO DE TIERRAS
03.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.58 39.86
03.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.98 25.69
03.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 1.44 7.95
03.03.05.03 OBRAS DE CONCRETO SIMPLE
03.03.05.03.01 SOLADO E=4" m3 1.21 35.81
03.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17
03.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48
03.03.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10
03.03.05.04 OBRAS DE CONCRETO ARMADO
03.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 0.79 546.69
03.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.10 44.48
03.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 37.23 4.35
03.03.05.05 REVOQUES Y ENLUCIDOS
03.03.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 2.52 32.48
03.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.24 29.76
03.03.05.06 PINTURA
03.03.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 3.24 11.18
03.03.05.07 CARPINTERIA METALICA
03.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 1.00 213.73
03.03.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.03.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T6, INGRESO Ø=1 y SALIDA Ø=1 " und 1.00 299.60
03.03.06 VALVULA DE PURGA TIPO I (1 UND)
03.03.06.01 OBRAS PRELIMINARES
03.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 0.49
03.03.06.01.02 TRAZO Y REPLANTEO m2 1.00 1.84
03.03.06.02 MOVIMIENTO DE TIERRAS
03.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.51 39.86
03.03.06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 0.51 13.11
03.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.49 7.95
03.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 0.64 25.69
03.03.06.03 OBRAS DE CONCRETO SIMPLE
03.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.20 413.17
03.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.24 44.48
03.03.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.27 121.10
03.03.06.04 OBRAS DE CONCRETO ARMADO
03.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.35 546.69
03.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.72 44.48
03.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 14.94 4.35
03.03.06.05 REVOQUES Y ENLUCIDOS
03.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 1.44 32.48
03.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.36 29.76
03.03.06.06 PINTURA
03.03.06.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 2.16 11.18
03.03.06.07 CARPINTERIA METALICA
03.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 1.00 214.83
03.03.06.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.03.06.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO I, Ø=1" und 1.00 153.06
03.04 RESERVORIO (V=5.00 m3, 01 UND)
03.04.01 OBRAS PRELIMINARES
03.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49
03.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.84
03.04.02 MOVIMIENTO DE TIERRAS
03.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 60.95 39.86
03.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 8.05 7.95
03.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 76.19 25.69
03.04.03 CONCRETO SIMPLE
03.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17
03.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48
03.04.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 SOLADO PARA LOSA FONDO m2 8.05 40.87
03.04.04.02 CONCRETO f'c=210 kg/cm2 m3 9.51 546.69
03.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 49.52 44.48
03.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 254.64 4.35
03.04.05 REVOQUES Y ENLUCIDOS
03.04.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 31.00 32.48
03.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 35.50 29.76
03.04.06 PINTURA
03.04.06.01 PINTURA ESMALTE EN MUROS EXTERIORES DE RESERVORIO m2 29.15 13.23
03.04.07 CARPINTERIA METALICA
03.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73
03.04.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN RESERVORIO (INGRESO Ø 1"-LIMPIA, REBOSE y SELLO HIDR. Ø 2"-VENTILAC. Ø
03.04.08.01 und 1.00 1,618.16
3")
03.04.09 CERCO PERIMETRICO EN RESERVORIO
03.04.09.01 TRABAJOS PRELIMINARES
03.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84
03.04.09.02 MOVIMIENTO DE TIERRAS
03.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86
03.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69
03.04.09.03 CONCRETO SIMPLE
03.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98
03.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
03.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48
03.04.09.05 COLOCADO DE ROLLIZOS
03.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83
03.04.09.06 PINTURA EN CERCO PERIMETRICO
03.04.09.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 66.40 3.80
03.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
03.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22
03.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
03.04.09.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10
03.04.10 CLORADOR POR GOTEO
03.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
03.04.10.01.01 CASETA DE MURO DE LADRILLO -CLORADOR POR GOTEO
03.04.10.01.01.0
MURO DE LADRILLO PANDERETA (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 7.52 54.96
1
03.04.10.01.01.0
MURO DE LADRILLO PANDERETA INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 4.48 49.36
2
03.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
03.04.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 29.07
1
03.04.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 34.08
2
03.04.10.01.03 REVOQUES Y ENLUCIDOS
03.04.10.01.03.0
TARRAJEO MUROS DE INTERIORES Y EXTERIORES, CEMENTO : ARENA, 1:5 m2 14.98 30.00
1
03.04.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.78
2
03.04.10.01.04 CARPINTERIA METALICA
03.04.10.01.04.0
SUMINISTRO E INSTALACION DE PUERTA METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO und 1.00 367.18
1
03.04.10.01.05 PINTURAS
03.04.10.01.05.0
PINTURA ESMALTE EN MUROS INTERIORES Y EXTERIORES m2 14.98 11.18
1
03.04.10.01.05.0
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 12.25
2
03.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
03.04.10.02.01 SUMINISTRO E INSTALACION DE TANQUE DE POLIETILENO, CAP=250 LTRS. und 1.00 435.06
03.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
03.04.10.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS Y ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO GLB 1.00 939.22
03.05 RED DE ADUCCION Y DISTRIBUCION (L=2,740.00 m)
03.05.01 TRABAJOS PRELIMINARES
03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,370.00 0.49
03.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 2,740.00 1.53
03.05.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 2,740.00 1.53
03.05.02 MOVIMIENTO DE TIERRAS
03.05.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 1,041.20 49.82
03.05.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 54.80 55.80
03.05.02.03 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 2,740.00 1.81
03.05.02.04 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 137.00 6.08
03.05.02.05 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 390.45 36.40
03.05.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 20.55 65.17
03.05.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 719.25 25.07
03.05.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 68.50 62.16
03.05.02.09 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 34.25 25.69
03.05.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 4.00 8.05
03.05.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 3/4" m 2,736.00 4.84
03.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 96.63
03.05.04 PRUEBA HIDRAULICA
03.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 2,740.00 1.51
03.05.05 CAMARA ROMPE PRESION T-7 (09 UND)
03.05.05.01 OBRAS PRELIMINARES
03.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 18.63 0.49
03.05.05.01.02 TRAZO Y REPLANTEO m2 18.63 1.84
03.05.05.02 MOVIMIENTO DE TIERRAS
03.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 14.32 39.86
03.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 7.16 40.95
03.05.05.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 2.39 13.11
03.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 17.69 7.95
03.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.06 59.44
03.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 8.06 25.69
03.05.05.03 OBRAS DE CONCRETO SIMPLE
03.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.11 413.17
03.05.05.03.02 SOLADO E=4" m3 1.49 35.81
03.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.80 44.48
03.05.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 2.43 121.10
03.05.05.04 OBRAS DE CONCRETO ARMADO
03.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 12.23 546.69
03.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 125.30 44.48
03.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,771.06 4.35
03.05.05.05 REVOQUES Y ENLUCIDOS
03.05.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 38.88 32.48
03.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 84.26 29.76
03.05.05.06 PINTURA
03.05.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 54.00 11.18
03.05.05.07 CARPINTERIA METALICA
03.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 9.00 179.83
03.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 9.00 213.73
03.05.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=3/4" und 9.00 379.18
03.05.06 VALVULA DE CONTROL (05 UND)
03.05.06.01 OBRAS PRELIMINARES
03.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49
03.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.84
03.05.06.02 MOVIMIENTO DE TIERRAS
03.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 39.86
03.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 25.69
03.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.95
03.05.06.03 OBRAS DE CONCRETO ARMADO
03.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 546.69
03.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 44.48
03.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.35
03.05.06.04 REVOQUES Y ENLUCIDOS
03.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 32.48
03.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 29.76
03.05.06.05 PINTURA
03.05.06.05.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 10.80 11.18
03.05.06.06 CARPINTERIA METALICA
03.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 162.88
03.05.06.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=3/4" und 5.00 79.02
03.05.07 VALVULA DE PURGA TIPO II (06 UND)
03.05.07.01 OBRAS PRELIMINARES
03.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.00 0.49
03.05.07.01.02 TRAZO Y REPLANTEO m2 6.00 1.84
03.05.07.02 MOVIMIENTO DE TIERRAS
03.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 9.17 39.86
03.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 3.06 49.82
03.05.07.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 3.06 13.11
03.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 2.94 7.95
03.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 2.94 25.69
03.05.07.03 OBRAS DE CONCRETO SIMPLE
03.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 1.84 413.17
03.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.44 44.48
03.05.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.77 121.10
03.05.07.04 OBRAS DE CONCRETO ARMADO
03.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 2.10 546.69
03.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 23.32 44.48
03.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 86.64 4.35
03.05.07.05 REVOQUES Y ENLUCIDOS
03.05.07.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 8.64 32.48
03.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 20.16 29.76
03.05.07.06 PINTURA
03.05.07.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 9.72 11.18
03.05.07.07 CARPINTERIA METALICA
03.05.07.07.01 MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE 0.60x0.40m. und 6.00 213.73
03.05.07.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.07.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4" und 6.00 132.94
03.05.08 CONEXIONES DOMICILIARIAS (53 UND)
03.05.08.01 OBRAS PRELIMINARES
03.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 474.88 0.49
03.05.08.01.02 TRAZO Y REPLANTEO m2 712.32 1.84
03.05.08.02 MOVIMIENTO DE TIERRAS
03.05.08.02.01 EXCAVACION A MANO DE ZANJA MANUAL TERRENO NORMAL m3 569.86 39.86
03.05.08.02.02 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO CLASIFICADO m3 569.86 33.00
03.05.08.02.03 SUMINISTRO Y COLOCACION DE GRAVA SELECCIONADA m3 50.36 209.11
03.05.08.03 OBRAS DE CONCRETO SIMPLE
03.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 3.93 413.17
03.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.61 44.48
03.05.08.04 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
03.05.08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND) und 53.00 80.77
03.05.08.04.02 TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON LLAVE TIPO BUJIA und 53.00 155.21
03.05.08.04.03 SUMINISTRO E INSTALACIONES DE ACOMETIDA DOMICILIARIA RANGO 2 - 20 M. m 530.00 3.50
04 LOCALIDAD TARACA
04.01 CONSTRUCCIONES PROVISIONALES
04.01.01 OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y VESTUARIOS m2 100.00 44.55
04.01.02 ALQUILER DE PREDIOS PARA CAMPAMENTOS Y ALMACENES mes 6.00 500.00
04.01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20 m und 1.00 1,539.82
04.02 CAPTACION A TIPO LADERA YACUTOCCYAC (01 UND)
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49
04.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84
04.02.02 MOVIMIENTO DE TIERRAS
04.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 17.55 39.86
04.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO C/PISON m3 2.55 29.50
04.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.60 25.69
04.02.03 CONCRETO SIMPLE
04.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48
04.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10
04.02.04 CONCRETO ARMADO
04.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84
04.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48
04.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35
04.02.05 REVOQUES Y ENLUCIDOS
04.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3 e=1.5cm m2 5.53 32.48
04.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76
04.02.06 PINTURA
04.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 13.23
04.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
04.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85
04.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77
04.02.08 CARPINTERIA METALICA
04.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 180.93
04.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53
04.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO HIDRAULICO y VENTILACION
04.02.09.01 und 1.00 497.69
Ø=2")
04.02.10 CERCO PERIMETRICO EN CAPTACION
04.02.10.01 TRABAJOS PRELIMINARES
04.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84
04.02.10.02 MOVIMIENTO DE TIERRAS
04.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86
04.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69
04.02.10.03 CONCRETO SIMPLE
04.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98
04.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
04.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48
04.02.10.05 COLOCADO DE ROLLIZOS
04.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83
04.02.10.06 PINTURA EN CERCO PERIMETRICO
04.02.10.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 33.80 3.80
04.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
04.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22
04.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
04.02.10.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10
04.03 LINEA DE CONDUCCION (L=1231.00 m)
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,231.00 0.49
04.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 1,231.00 1.53
04.03.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 1,231.00 1.53
04.03.02 MOVIMIENTO DE TIERRAS
04.03.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 392.92 39.86
04.03.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 73.86 49.82
04.03.02.03 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 15.39 55.80
04.03.02.04 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 1,231.00 1.81
04.03.02.05 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 61.55 6.08
04.03.02.06 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 1,231.00 4.28
04.03.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 175.42 36.40
04.03.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 9.23 65.17
04.03.02.09 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 292.36 25.07
04.03.02.10 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m m3 6.16 62.16
04.03.02.11 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.39 25.69
04.03.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 1,231.00 5.94
04.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 157.71
04.03.04 PRUEBA HIDRAULICA
04.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 1,231.00 1.51
04.03.05 CAMARA ROMPE PRESION T-6 (02 UND)
04.03.05.01 OBRAS PRELIMINARES
04.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.88 0.49
04.03.05.01.02 TRAZO Y REPLANTEO m2 2.88 1.84
04.03.05.02 MOVIMIENTO DE TIERRAS
04.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 3.17 39.86
04.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 7.92 25.69
04.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 2.88 7.95
04.03.05.03 OBRAS DE CONCRETO SIMPLE
04.03.05.03.01 SOLADO E=4" m3 2.42 35.81
04.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.02 413.17
04.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.40 44.48
04.03.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 1.00 121.10
04.03.05.04 OBRAS DE CONCRETO ARMADO
04.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 546.69
04.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 16.20 44.48
04.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 74.46 4.35
04.03.05.05 REVOQUES Y ENLUCIDOS
04.03.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 5.04 32.48
04.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.48 29.76
04.03.05.06 PINTURA
04.03.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 6.48 11.18
04.03.05.07 CARPINTERIA METALICA
04.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73
04.03.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.03.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T6, INGRESO Ø=1 y SALIDA Ø=1 " und 2.00 299.60
04.03.06 VALVULA DE PURGA TIPO I (1 UND)
04.03.06.01 OBRAS PRELIMINARES
04.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.00 0.49
04.03.06.01.02 TRAZO Y REPLANTEO m2 2.00 1.84
04.03.06.02 MOVIMIENTO DE TIERRAS
04.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.02 39.86
04.03.06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 1.02 13.11
04.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.98 7.95
04.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1.27 25.69
04.03.06.03 OBRAS DE CONCRETO SIMPLE
04.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.04 413.17
04.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.48 44.48
04.03.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.54 121.10
04.03.06.04 OBRAS DE CONCRETO ARMADO
04.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.70 546.69
04.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.44 44.48
04.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 29.88 4.35
04.03.06.05 REVOQUES Y ENLUCIDOS
04.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 2.88 32.48
04.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.72 29.76
04.03.06.06 PINTURA
04.03.06.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 4.32 11.18
04.03.06.07 CARPINTERIA METALICA
04.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 2.00 214.83
04.03.06.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.03.06.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO I, Ø=1" und 2.00 153.06
04.04 RESERVORIO (V=5.00 m3, 01 UND)
04.04.01 OBRAS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49
04.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.84
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 36.02 39.86
04.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 8.05 7.95
04.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 45.02 25.69
04.04.03 CONCRETO SIMPLE
04.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17
04.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48
04.04.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 121.10
04.04.04 OBRAS DE CONCRETO ARMADO
04.04.04.01 SOLADO PARA LOSA FONDO m2 8.05 40.87
04.04.04.02 CONCRETO f'c=210 kg/cm2 m3 9.51 546.69
04.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 49.52 44.48
04.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 254.64 4.35
04.04.05 REVOQUES Y ENLUCIDOS
04.04.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 31.00 32.48
04.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 35.50 29.76
04.04.06 PINTURA
04.04.06.01 PINTURA ESMALTE EN MUROS EXTERIORES DE RESERVORIO m2 29.15 13.23
04.04.07 CARPINTERIA METALICA
04.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73
04.04.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN RESERVORIO (INGRESO Ø 1"-LIMPIA, REBOSE y SELLO HIDR. Ø 2"-VENTILAC. Ø
04.04.08.01 und 1.00 1,618.16
3")
04.04.09 CERCO PERIMETRICO EN RESERVORIO
04.04.09.01 TRABAJOS PRELIMINARES
04.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84
04.04.09.02 MOVIMIENTO DE TIERRAS
04.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86
04.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69
04.04.09.03 CONCRETO SIMPLE
04.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98
04.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
04.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48
04.04.09.05 COLOCADO DE ROLLIZOS
04.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83
04.04.09.06 PINTURA EN CERCO PERIMETRICO
04.04.09.06.01 PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS C/ESMALTE SINTETICO m 66.40 3.80
04.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
04.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22
04.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
04.04.09.08.01 SUM. E INST. PUERTA DE MADERA C/MALLA GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3" und 1.00 194.10
04.04.10 CLORADOR POR GOTEO
04.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
04.04.10.01.01 CASETA DE MURO DE LADRILLO -CLORADOR POR GOTEO
04.04.10.01.01.0
MURO DE LADRILLO PANDERETA (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 7.52 54.96
1
04.04.10.01.01.0
MURO DE LADRILLO PANDERETA INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm. m2 4.48 49.36
2
04.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
04.04.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 29.07
1
04.04.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 34.08
2
04.04.10.01.03 REVOQUES Y ENLUCIDOS
04.04.10.01.03.0
TARRAJEO MUROS DE INTERIORES Y EXTERIORES, CEMENTO : ARENA, 1:5 m2 14.98 30.00
1
04.04.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.78
2
04.04.10.01.04 CARPINTERIA METALICA
04.04.10.01.04.0
SUMINISTRO E INSTALACION DE PUERTA METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO und 1.00 367.18
1
04.04.10.01.05 PINTURAS
04.04.10.01.05.0
PINTURA ESMALTE EN MUROS INTERIORES Y EXTERIORES m2 14.98 11.18
1
04.04.10.01.05.0
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 12.25
2
04.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
04.04.10.02.01 SUMINISTRO E INSTALACION DE TANQUE DE POLIETILENO, CAP=250 LTRS. und 1.00 435.06
04.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
04.04.10.03.01 SUMINISTRO Y COLOCACION DE TUBERIAS Y ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO GLB 1.00 939.22
04.05 RED DE ADUCCION Y DISTRIBUCION (L=3,674.00 m)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,837.00 0.49
04.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 3,674.00 1.53
04.05.01.03 TRAZO Y NIVELACION DURANTE LA EJECUCION EN ZANJAS REDES Y LINEAS m 3,674.00 1.53
04.05.02 MOVIMIENTO DE TIERRAS
04.05.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 73.48 39.86
04.05.02.02 EXCAVACION MANUAL DE ZANJA EN MATERIAL CONGLOMERADO m3 1,352.03 49.82
04.05.02.03 EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA SUELTA m3 44.09 55.80
04.05.02.04 REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL P/TUBERIA m 3,674.00 1.81
04.05.02.05 PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y FIJA P/TUBERIA m 110.22 6.08
04.05.02.06 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 534.57 36.40
04.05.02.07 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m m3 16.53 65.17
04.05.02.08 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO P/TUBERIA, H=0.50 m m3 946.06 25.07
04.05.02.09 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL DE PRESTAMO P/TUBERIA, H=0.20 m m3 55.11 62.16
04.05.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 27.56 25.69
04.05.03 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 1" m 104.00 8.05
04.05.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10 DE 3/4" m 3,570.00 4.84
04.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 87.97
04.05.04 PRUEBA HIDRAULICA
04.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 3,674.00 1.51
04.05.05 CAMARA ROMPE PRESION T-7 (12 UND)
04.05.05.01 OBRAS PRELIMINARES
04.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 24.84 0.49
04.05.05.01.02 TRAZO Y REPLANTEO m2 24.84 1.84
04.05.05.02 MOVIMIENTO DE TIERRAS
04.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 16.71 39.86
04.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 9.55 40.95
04.05.05.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 2.39 13.11
04.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 23.58 7.95
04.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.39 59.44
04.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 12.53 25.69
04.05.05.03 OBRAS DE CONCRETO SIMPLE
04.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.14 413.17
04.05.05.03.02 SOLADO E=4" m3 1.98 35.81
04.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.40 44.48
04.05.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 3.24 121.10
04.05.05.04 OBRAS DE CONCRETO ARMADO
04.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 16.30 546.69
04.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 167.06 44.48
04.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,361.41 4.35
04.05.05.05 REVOQUES Y ENLUCIDOS
04.05.05.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 51.84 32.48
04.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 112.34 29.76
04.05.05.06 PINTURA
04.05.05.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 72.00 11.18
04.05.05.07 CARPINTERIA METALICA
04.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 12.00 179.83
04.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 12.00 213.73
04.05.05.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.05.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP T7, INGRESO Y SALIDA Ø=3/4" und 12.00 379.18
04.05.06 VALVULA DE CONTROL (05 UND)
04.05.06.01 OBRAS PRELIMINARES
04.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49
04.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.84
04.05.06.02 MOVIMIENTO DE TIERRAS
04.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 39.86
04.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 25.69
04.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.95
04.05.06.03 OBRAS DE CONCRETO ARMADO
04.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 546.69
04.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 44.48
04.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.35
04.05.06.04 REVOQUES Y ENLUCIDOS
04.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 32.48
04.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 29.76
04.05.06.05 PINTURA
04.05.06.05.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 10.80 11.18
04.05.06.06 CARPINTERIA METALICA
04.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 162.88
04.05.06.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE CONTROL, Ø=3/4" und 5.00 79.02
04.05.07 VALVULA DE PURGA TIPO II (05 UND)
04.05.07.01 OBRAS PRELIMINARES
04.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49
04.05.07.01.02 TRAZO Y REPLANTEO m2 5.00 1.84
04.05.07.02 MOVIMIENTO DE TIERRAS
04.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 7.64 39.86
04.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 2.55 49.82
04.05.07.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO A MANO m3 2.55 13.11
04.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 2.45 7.95
04.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 2.45 25.69
04.05.07.03 OBRAS DE CONCRETO SIMPLE
04.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 1.53 413.17
04.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 44.48
04.05.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.64 121.10
04.05.07.04 OBRAS DE CONCRETO ARMADO
04.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 1.75 546.69
04.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 18.60 44.48
04.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 74.70 4.35
04.05.07.05 REVOQUES Y ENLUCIDOS
04.05.07.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 7.20 32.48
04.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 16.80 29.76
04.05.07.06 PINTURA
04.05.07.06.01 PINTURA EN MUROS EXTERIORES CON ESMALTE-2 MANOS m2 8.10 11.18
04.05.07.07 CARPINTERIA METALICA
04.05.07.07.01 MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE 0.60x0.40m. und 5.00 213.73
04.05.07.08 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.07.08.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4" und 5.00 132.94
04.05.08 CONEXIONES DOMICILIARIAS (53 UND)
04.05.08.01 OBRAS PRELIMINARES
04.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 474.88 0.49
04.05.08.01.02 TRAZO Y REPLANTEO m2 712.32 1.84
04.05.08.02 MOVIMIENTO DE TIERRAS
04.05.08.02.01 EXCAVACION A MANO DE ZANJA TERRENO NORMAL m3 596.86 40.95
04.05.08.02.02 RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL PROPIO CLASIFICADO m3 569.86 33.00
04.05.08.02.03 SUMINISTRO Y COLOCACION DE GRAVA SELECCIONADA m3 59.36 209.11
04.05.08.03 OBRAS DE CONCRETO SIMPLE
04.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 3.93 413.17
04.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.61 44.48
04.05.08.04 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS
04.05.08.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND) und 53.00 80.77
04.05.08.04.02 TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON LLAVE TIPO BUJIA und 53.00 155.21
04.05.08.04.03 SUMINISTRO E INSTALACIONES DE ACOMETIDA DOMICILIARIA RANGO 2 - 20 M. m 636.00 3.50

01 LOCALIDAD SANTA LUCIA


01.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
01.01.01 TRABAJOS PRELIMINARES
01.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 465.00 0.49
01.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 465.00 1.84
01.01.02 MOVIMIENTO DE TIERRAS
01.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 231.57 39.86
01.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 40.92 29.66
01.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 238.08 25.69
01.01.03 CONCRETO SIMPLE
01.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 279.00 373.75
01.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 40.92 398.69
01.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 678.90 44.48
01.01.03.04 CONCRETO f'c=175 kg/cm2 m3 28.83 448.85
01.01.04 MURO DE LADRILLO
01.01.04.01 MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE SOGA C/M 1:4 x 1.5cm m2 1,354.08 58.10
01.01.04.02 EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-6" m2 26.04 70.33
01.01.05 REVOQUES Y ENLUCIDOS
01.01.05.01 TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre hidraulico) m2 1,272.24 16.34
01.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 20.46 36.55
01.01.06 PINTURA
01.01.06.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE COLOR MARFIL m2 767.25 11.53
01.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO ETERNIT(1,14x0.72x0.005m)
01.01.07.01 m2 605.43 66.22
01.01.08 CARPINTERIA METALICA
01.01.08.01 SUMINISTRO E INSTALACION DE PUERTA METALICA 1.80x0.70m, INCL. MARCO Y PINTADO und 93.00 363.74
01.01.09 CARPINTERIA DE MADERA
01.01.09.01 VENTANA DE MADERA TORNILLO INC. MALLA MOSQUITERA m2 16.74 75.90
01.01.09.02 COBERTURA DE MADERA PARA TECHO und 93.00 97.95
01.01.10 SISTEMA DE AGUA FRIA
01.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 880.71 3.65
01.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
01.01.11.01 TEE PVC-SAP 1/2" pza 186.00 20.85
01.01.11.02 CODO PVC SAP 1/2" pza 558.00 15.59
01.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 186.00 51.25
01.01.11.04 SUMINISTRO E INSTALACION DE DUCHA INCLUIDO ACCESORIOS und 93.00 33.08
01.01.12 SISTEMA DE DESAGUE
01.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 897.45 4.02
01.01.12.02 TUBERIA Ø=4" PVC SAL m 339.45 3.65
01.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
01.01.13.01 CODO PVC SAL 2"X90° pza 651.00 11.77
01.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 93.00 15.53
01.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 279.00 16.11
01.01.14 ADITAMIENTOS VARIOS
01.01.14.01 SUMIDEROS DE BRONCE 2" und 93.00 12.25
01.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 186.00 11.09
01.01.14.03 INODORO DE LOZA VITRIFICADA COLOR BLANCO INCLUYE TANQUE und 93.00 147.40
01.01.14.04 ACCESORIOS DE LOZA und 93.00 64.86
01.01.14.05 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y ACCESORIOS GLB 93.00 29.15
01.01.14.06 SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA COLOR BLANCO INCLUIDO ACCESORIOS und 93.00 124.59
01.01.14.07 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE 12"x24" und 186.00 129.89
01.01.15 INSTALACIONES ELECTRICAS
01.01.15.01 SALIDA DE CENTRO DE LUZ pto 93.00 49.14
01.01.15.02 TUBERIA PVC SEL 5/8" m 213.90 4.15
01.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 520.80 2.28
01.01.15.04 TABLEROS DISTRIBUCION pza 93.00 89.04
01.01.16 CONSTRUCCION POZO PERCOLADOR
01.01.16.01 TRABAJOS PRELIMINARES
01.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 292.02 0.49
01.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 292.02 1.84
01.01.16.02 MOVIMIENTO DE TIERRAS
01.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 150.66 39.86
01.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 22.32 29.66
01.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 80.91 89.30
01.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 188.79 25.69
01.01.16.03 TAPA DE CONCRETO
01.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 18.81 448.85
01.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 196.26 44.48
01.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,957.65 4.35
01.01.16.04 ANILLO DE CONCRETO
01.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 6.51 355.98
01.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 111.60 44.48
01.01.16.05 MURO DE LADRILLO
01.01.16.05.01 MURO DE LADRILLO ARTESANAL AMARRE DE SOGA, JUNTA 1.5 CM MORTERO 1:1:5 m2 388.74 48.94
01.01.16.06 SISTEMA DE DESAGUE LLEGADA
01.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 181.35 4.02
01.01.16.06.02 CODO PVC SAL 2"X90° pza 93.00 11.77
01.01.17 INSTALACION DEL BIODIGESTOR
01.01.17.01 TRABAJOS PRELIMINARES
01.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 351.54 0.49
01.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 351.54 1.84
01.01.17.02 MOVIMIENTO DE TIERRAS
01.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 281.20 39.86
01.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 211.97 29.66
01.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 351.50 25.69
01.01.17.03 CONCRETO SIMPLE
01.01.17.03.01 SOLADO E=4" m2 60.45 39.68
01.01.17.04 CONCRETO ARMADO
01.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 66.96 448.85
01.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 420.36 44.48
01.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 518.01 4.35
01.01.17.05 BIODIGESTOR
01.01.17.05.01 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 600 LTS und 91.00 779.59
01.01.17.05.02 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 1300 LTS und 2.00 1,320.79
01.01.17.06 REVOQUES Y ENLUCIDOS
01.01.17.06.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 332.01 32.48
01.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
01.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 93.00 4.02
01.01.17.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 93.00 29.86
01.02 LAVADERO INTRADOMICILIARIO (91 UND)
01.02.01 OBRAS PRELIMINARES
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 460.46 0.49
01.02.01.02 TRAZO Y REPLANTEO m2 460.46 1.84
01.02.02 MOVIMIENTO DE TIERRAS
01.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 103.03 37.48
01.02.02.02 RELLENO Y COMPACTADO DE ZANJA CON MATERIAL PROPIO CLASIFICADO m3 84.63 13.11
01.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 21.16 25.69
01.02.03 OBRAS DE CONCRETO ARMADO
01.02.03.01 CONCRETO f'c=175 kg/cm2 m3 9.57 448.85
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 304.63 44.48
01.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 359.91 4.35
01.02.04 MURO DE LADRILLO
01.02.04.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 60.17 47.74
01.02.05 REVOQUES Y ENLUCIDOS
01.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 107.29 32.48
01.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 205.30 29.76
01.02.06 ACCESORIOS Y VALVULAS
01.02.06.01 SUMINISTRO E INSTALACION DE LAVADERO INTRADOMICILIARIA und 91.00 136.31
01.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
01.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 455.00 3.35
01.03 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49
01.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84
01.03.02 MOVIMIENTO DE TIERRAS
01.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48
01.03.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02
01.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50
01.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69
01.03.03 OBRAS DE CONCRETO SIMPLE
01.03.03.01 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.20 48.96
01.03.04 OBRAS DE CONCRETO ARMADO
01.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35
01.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 44.01
01.03.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.21 448.85
01.03.05 REVOQUES Y REVESTIMIENTOS
01.03.05.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 2.49 32.96
01.03.05.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 2.11 23.98
01.03.06 ACCESORIOS Y VALVULAS
01.03.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO I.E. INICIAL und 1.00 176.99
01.03.06.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50
01.03.06.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77
01.03.06.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19
01.03.07 TUBERIA PVC INTRADOMICILIARIO
01.03.07.01 INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35
01.03.07.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65
02 LOCALIDAD PUEBLO LIBRE (130 UND)
02.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 650.00 0.49
02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 650.00 1.84
02.01.02 MOVIMIENTO DE TIERRAS
02.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 323.70 39.86
02.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 57.20 29.66
02.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 332.80 25.69
02.01.03 CONCRETO SIMPLE
02.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 390.00 373.75
02.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 57.20 398.69
02.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 949.00 44.48
02.01.03.04 CONCRETO f'c=175 kg/cm2 m3 40.30 448.85
02.01.04 MURO DE LADRILLO
02.01.04.01 MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE SOGA C/M 1:4 x 1.5cm m2 1,892.80 58.10
02.01.04.02 EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-6" m2 36.40 70.33
02.01.05 REVOQUES Y ENLUCIDOS
02.01.05.01 TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre hidraulico) m2 1,778.40 16.34
02.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 28.60 36.55
02.01.06 PINTURA
02.01.06.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE COLOR MARFIL m2 1,072.50 11.53
02.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO ETERNIT(1,14x0.72x0.005m)
02.01.07.01 m2 846.60 66.22
02.01.08 CARPINTERIA METALICA
02.01.08.01 SUMINISTRO E INSTALACION DE PUERTA METALICA 1.80x0.70m, INCL. MARCO Y PINTADO und 130.00 363.74
02.01.09 CARPINTERIA DE MADERA
02.01.09.01 VENTANA DE MADERA TORNILLO INC. MALLA MOSQUITERA m2 23.40 75.90
02.01.09.02 COBERTURA DE MADERA PARA TECHO und 130.00 97.95
02.01.10 SISTEMA DE AGUA FRIA
02.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 1,231.00 3.65
02.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
02.01.11.01 TEE PVC-SAP 1/2" pza 260.00 20.85
02.01.11.02 CODO PVC SAP 1/2" pza 780.00 15.59
02.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 260.00 51.25
02.01.11.04 SUMINISTRO E INSTALACION DE DUCHA INCLUIDO ACCESORIOS und 130.00 33.08
02.01.12 SISTEMA DE DESAGUE
02.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 1,254.50 4.02
02.01.12.02 TUBERIA Ø=4" PVC SAL m 474.50 3.65
02.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
02.01.13.01 CODO PVC SAL 2"X90° pza 910.00 11.77
02.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 130.00 15.53
02.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 390.00 16.11
02.01.14 ADITAMIENTOS VARIOS
02.01.14.01 SUMIDEROS DE BRONCE 2" und 130.00 12.25
02.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 260.00 11.09
02.01.14.03 INODORO DE LOZA VITRIFICADA COLOR BLANCO INCLUYE TANQUE und 130.00 147.40
02.01.14.04 ACCESORIOS DE LOZA und 130.00 64.86
02.01.14.05 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y ACCESORIOS GLB 130.00 29.15
02.01.14.06 SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA COLOR BLANCO INCLUIDO ACCESORIOS und 130.00 124.59
02.01.14.07 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE 12"x24" und 260.00 129.89
02.01.15 INSTALACIONES ELECTRICAS
02.01.15.01 SALIDA DE CENTRO DE LUZ pto 130.00 49.14
02.01.15.02 TUBERIA PVC SEL 5/8" m 299.00 4.15
02.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 728.00 2.28
02.01.15.04 TABLEROS DISTRIBUCION pza 130.00 89.04
02.01.16 CONSTRUCCION POZO PERCOLADOR
02.01.16.01 TRABAJOS PRELIMINARES
02.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 408.20 0.49
02.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 408.20 1.84
02.01.16.02 MOVIMIENTO DE TIERRAS
02.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 210.60 39.86
02.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 31.20 29.66
02.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 113.10 89.30
02.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 163.90 25.69
02.01.16.03 TAPA DE CONCRETO
02.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 22.10 448.85
02.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 236.60 44.48
02.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,736.50 4.35
02.01.16.04 ANILLO DE CONCRETO
02.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 9.10 355.98
02.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 156.00 44.48
02.01.16.05 MURO DE LADRILLO
02.01.16.05.01 MURO DE LADRILLO ARTESANAL AMARRE DE SOGA, JUNTA 1.5 CM MORTERO 1:1:5 m2 543.40 48.94
02.01.16.06 SISTEMA DE DESAGUE LLEGADA
02.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 253.50 4.02
02.01.16.06.02 CODO PVC SAL 2"X90° pza 130.00 11.77
02.01.17 INSTALACION DEL BIODIGESTOR
02.01.17.01 TRABAJOS PRELIMINARES
02.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 491.40 0.49
02.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 491.40 1.84
02.01.17.02 MOVIMIENTO DE TIERRAS
02.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 396.70 39.86
02.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 299.24 29.66
02.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 504.11 25.69
02.01.17.03 CONCRETO SIMPLE
02.01.17.03.01 SOLADO E=4" m2 84.50 39.68
02.01.17.04 CONCRETO ARMADO
02.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 93.60 448.85
02.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 587.60 44.48
02.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 724.10 4.35
02.01.17.05 BIODIGESTOR
02.01.17.05.01 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 600 LTS und 121.00 779.59
02.01.17.05.02 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 1300 LTS und 9.00 1,320.79
02.01.17.06 REVOQUES Y ENLUCIDOS
02.01.17.06.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 464.10 32.48
02.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
02.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 130.00 4.02
02.01.17.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 130.00 29.86
02.02 LAVADERO INTRADOMICILIARIO (121 UND)
02.02.01 OBRAS PRELIMINARES
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 612.26 0.49
02.02.01.02 TRAZO Y REPLANTEO m2 612.26 1.84
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 137.00 37.48
02.02.02.02 RELLENO Y COMPACTADO DE ZANJA CON MATERIAL PROPIO CLASIFICADO m3 112.53 13.11
02.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 28.14 25.69
02.02.03 OBRAS DE CONCRETO ARMADO
02.02.03.01 CONCRETO f'c=175 kg/cm2 m3 12.72 448.85
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 405.06 44.48
02.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 478.56 4.35
02.02.04 MURO DE LADRILLO
02.02.04.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 80.01 47.74
02.02.05 REVOQUES Y ENLUCIDOS
02.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 142.66 32.48
02.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 272.98 29.76
02.02.06 ACCESORIOS Y VALVULAS
02.02.06.01 SUMINISTRO E INSTALACION DE LAVADERO INTRADOMICILIARIA und 121.00 136.31
02.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
02.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 605.00 3.35
02.03 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
02.03.01 TRABAJOS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49
02.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48
02.03.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02
02.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50
02.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69
02.03.03 OBRAS DE CONCRETO SIMPLE
02.03.03.01 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.20 48.96
02.03.04 OBRAS DE CONCRETO ARMADO
02.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35
02.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 44.01
02.03.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.21 448.85
02.03.05 REVOQUES Y REVESTIMIENTOS
02.03.05.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 2.49 32.96
02.03.05.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 2.11 23.98
02.03.06 ACCESORIOS Y VALVULAS
02.03.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO I.E. INICIAL und 1.00 176.99
02.03.06.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50
02.03.06.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77
02.03.06.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19
02.03.07 TUBERIA PVC INTRADOMICILIARIO
02.03.07.01 INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35
02.03.07.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65
02.04 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01 UND)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.49
02.04.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.84
02.04.02 MOVIMIENTO DE TIERRAS
02.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 37.48
02.04.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.98 1.02
02.04.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50
02.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 25.69
02.04.03 OBRAS DE CONCRETO SIMPLE
02.04.03.01 CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6") EN LAVADERO C/MEZCLADORA m3 0.06 339.60
02.04.03.02 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.86 48.96
02.04.04 OBRAS DE CONCRETO ARMADO
02.04.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.35
02.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 44.01
02.04.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.31 448.85
02.04.05 ALBAÑILERIA
02.04.05.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 0.36 58.08
02.04.06 REVOQUES Y REVESTIMIENTOS
02.04.06.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 3.51 32.96
02.04.06.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 3.29 23.98
02.04.07 ACCESORIOS Y VALVULAS
02.04.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO TIPO I.E. PRIMARIA und 1.00 176.99
02.04.07.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50
02.04.07.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77
02.04.07.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19
02.04.08 TUBERIA PVC INTRADOMICILIARIO
02.04.08.01 INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35
02.04.08.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65
02.05 LAVADERO I.E. SECUNDARIA (01 UND)
02.05.01 TRABAJOS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49
02.05.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 3.70 37.48
02.05.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02
02.05.02.03 RELLENO CON MATERIAL PROPIO m3 2.64 29.50
02.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.27 25.69
02.05.03 OBRAS DE CONCRETO SIMPLE
02.05.03.01 CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6") EN LAVADERO C/MEZCLADORA m3 0.08 339.60
02.05.03.02 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 0.22 48.96
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 0.26 4.35
02.05.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 5.20 44.01
02.05.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 12.73 448.85
02.05.05 ALBAÑILERIA
02.05.05.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 1.04 58.08
02.05.06 REVOQUES Y REVESTIMIENTOS
02.05.06.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 3.13 32.96
02.05.06.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 4.41 23.98
02.05.07 ACCESORIOS Y VALVULAS
02.05.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO TIPO I.E. PRIMARIA und 1.00 176.99
02.05.07.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50
02.05.07.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77
02.05.07.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19
02.05.08 TUBERIA PVC INTRADOMICILIARIO
02.05.08.01 INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35
02.05.08.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65
03 LOCALIDAD TANCARPATA (55 UND)
03.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
03.01.01 TRABAJOS PRELIMINARES
03.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 275.00 0.49
03.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 275.00 1.84
03.01.02 MOVIMIENTO DE TIERRAS
03.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 136.95 39.86
03.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 24.20 29.66
03.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 140.80 25.69
03.01.03 CONCRETO SIMPLE
03.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 165.00 373.75
03.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 24.20 398.69
03.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 401.50 44.48
03.01.03.04 CONCRETO f'c=175 kg/cm2 m3 17.05 448.85
03.01.04 MURO DE LADRILLO
03.01.04.01 MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE SOGA C/M 1:4 x 1.5cm m2 800.80 58.10
03.01.04.02 EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-6" m2 15.40 70.33
03.01.05 REVOQUES Y ENLUCIDOS
03.01.05.01 TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre hidraulico) m2 752.40 16.34
03.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 12.10 36.55
03.01.06 PINTURA
03.01.06.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE COLOR MARFIL m2 453.75 11.53
03.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO ETERNIT(1,14x0.72x0.005m)
03.01.07.01 m2 358.05 66.22
03.01.08 CARPINTERIA METALICA
03.01.08.01 SUMINISTRO E INSTALACION DE PUERTA METALICA 1.80x0.70m, INCL. MARCO Y PINTADO und 55.00 363.74
03.01.09 CARPINTERIA DE MADERA
03.01.09.01 VENTANA DE MADERA TORNILLO INC. MALLA MOSQUITERA m2 9.90 75.90
03.01.09.02 COBERTURA DE MADERA PARA TECHO und 55.00 97.95
03.01.10 SISTEMA DE AGUA FRIA
03.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 520.85 3.65
03.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
03.01.11.01 TEE PVC-SAP 1/2" pza 110.00 20.85
03.01.11.02 CODO PVC SAP 1/2" pza 330.00 15.59
03.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 110.00 51.25
03.01.11.04 SUMINISTRO E INSTALACION DE DUCHA INCLUIDO ACCESORIOS und 55.00 33.08
03.01.12 SISTEMA DE DESAGUE
03.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 530.75 4.02
03.01.12.02 TUBERIA Ø=4" PVC SAL m 200.75 3.65
03.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
03.01.13.01 CODO PVC SAL 2"X90° pza 385.00 11.77
03.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 55.00 15.53
03.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 165.00 16.11
03.01.14 ADITAMIENTOS VARIOS
03.01.14.01 SUMIDEROS DE BRONCE 2" und 55.00 12.25
03.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 110.00 11.09
03.01.14.03 INODORO DE LOZA VITRIFICADA COLOR BLANCO INCLUYE TANQUE und 55.00 147.40
03.01.14.04 ACCESORIOS DE LOZA und 55.00 64.86
03.01.14.05 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y ACCESORIOS GLB 55.00 29.15
03.01.14.06 SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA COLOR BLANCO INCLUIDO ACCESORIOS und 55.00 124.59
03.01.14.07 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE 12"x24" und 110.00 129.89
03.01.15 INSTALACIONES ELECTRICAS
03.01.15.01 SALIDA DE CENTRO DE LUZ pto 55.00 49.14
03.01.15.02 TUBERIA PVC SEL 5/8" m 126.50 4.15
03.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 308.00 2.28
03.01.15.04 TABLEROS DISTRIBUCION pza 55.00 89.04
03.01.16 CONSTRUCCION POZO PERCOLADOR
03.01.16.01 TRABAJOS PRELIMINARES
03.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 172.70 0.49
03.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 172.20 1.84
03.01.16.02 MOVIMIENTO DE TIERRAS
03.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 89.10 39.86
03.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 13.20 29.66
03.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 47.85 89.30
03.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 111.65 25.69
03.01.16.03 TAPA DE CONCRETO
03.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 9.35 448.85
03.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 100.10 44.48
03.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,157.75 4.35
03.01.16.04 ANILLO DE CONCRETO
03.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 3.85 355.98
03.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.00 44.48
03.01.16.05 MURO DE LADRILLO
03.01.16.05.01 MURO DE LADRILLO ARTESANAL AMARRE DE SOGA, JUNTA 1.5 CM MORTERO 1:1:5 m2 229.90 48.94
03.01.16.06 SISTEMA DE DESAGUE LLEGADA
03.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 107.25 4.02
03.01.16.06.02 CODO PVC SAL 2"X90° pza 55.00 11.77
03.01.17 INSTALACION DEL BIODIGESTOR
03.01.17.01 TRABAJOS PRELIMINARES
03.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 207.90 0.49
03.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 207.90 1.84
03.01.17.02 MOVIMIENTO DE TIERRAS
03.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 170.94 39.86
03.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 129.10 29.66
03.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 213.67 25.69
03.01.17.03 CONCRETO SIMPLE
03.01.17.03.01 SOLADO E=4" m2 35.75 39.68
03.01.17.04 CONCRETO ARMADO
03.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 39.60 448.85
03.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.60 44.48
03.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 306.35 4.35
03.01.17.05 BIODIGESTOR
03.01.17.05.01 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 600 LTS und 51.00 779.59
03.01.17.05.02 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 1300 LTS und 4.00 1,320.79
03.01.17.06 REVOQUES Y ENLUCIDOS
03.01.17.06.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 196.35 32.48
03.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
03.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 55.00 4.02
03.01.17.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 55.00 29.86
03.02 LAVADERO INTRADOMICILIARIO (51 UND)
03.02.01 OBRAS PRELIMINARES
03.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 258.06 0.49
03.02.01.02 TRAZO Y REPLANTEO m2 258.06 1.84
03.02.02 MOVIMIENTO DE TIERRAS
03.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 57.74 37.48
03.02.02.02 RELLENO Y COMPACTADO DE ZANJA CON MATERIAL PROPIO CLASIFICADO m3 47.43 13.11
03.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.86 25.69
03.02.03 OBRAS DE CONCRETO ARMADO
03.02.03.01 CONCRETO f'c=175 kg/cm2 m3 5.36 448.85
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 170.73 44.48
03.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 201.71 4.35
03.02.04 MURO DE LADRILLO
03.02.04.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 33.72 47.74
03.02.05 REVOQUES Y ENLUCIDOS
03.02.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 60.13 32.48
03.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 115.06 29.76
03.02.06 ACCESORIOS Y VALVULAS
03.02.06.01 SUMINISTRO E INSTALACION DE LAVADERO INTRADOMICILIARIA und 51.00 136.31
03.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
03.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 255.00 3.35
03.03 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49
03.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84
03.03.02 MOVIMIENTO DE TIERRAS
03.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48
03.03.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02
03.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50
03.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69
03.03.03 OBRAS DE CONCRETO SIMPLE
03.03.03.01 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.20 48.96
03.03.04 OBRAS DE CONCRETO ARMADO
03.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35
03.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 44.01
03.03.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.21 448.85
03.03.05 REVOQUES Y REVESTIMIENTOS
03.03.05.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 2.49 32.96
03.03.05.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 2.11 23.98
03.03.06 ACCESORIOS Y VALVULAS
03.03.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO I.E. INICIAL und 1.00 176.99
03.03.06.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50
03.03.06.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77
03.03.06.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19
03.03.07 TUBERIA PVC INTRADOMICILIARIO
03.03.07.01 INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35
03.03.07.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65
03.04 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01 UND)
03.04.01 TRABAJOS PRELIMINARES
03.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.49
03.04.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.84
03.04.02 MOVIMIENTO DE TIERRAS
03.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 37.48
03.04.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.98 1.02
03.04.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50
03.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 25.69
03.04.03 OBRAS DE CONCRETO SIMPLE
03.04.03.01 CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6") EN LAVADERO C/MEZCLADORA m3 0.06 339.60
03.04.03.02 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.86 48.96
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.35
03.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 44.01
03.04.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.31 448.85
03.04.05 ALBAÑILERIA
03.04.05.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 0.36 58.08
03.04.06 REVOQUES Y REVESTIMIENTOS
03.04.06.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 3.51 32.96
03.04.06.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 3.29 23.98
03.04.07 ACCESORIOS Y VALVULAS
03.04.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO TIPO I.E. PRIMARIA und 1.00 176.99
03.04.07.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50
03.04.07.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77
03.04.07.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19
03.04.08 TUBERIA PVC INTRADOMICILIARIO
03.04.08.01 INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35
03.04.08.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65
04 LOCALIDAD TARACA (55 UND)
04.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
04.01.01 TRABAJOS PRELIMINARES
04.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 275.00 0.49
04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 275.00 1.84
04.01.02 MOVIMIENTO DE TIERRAS
04.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 136.95 39.86
04.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 24.20 29.66
04.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 140.80 25.69
04.01.03 CONCRETO SIMPLE
04.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 165.00 373.75
04.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 24.20 398.69
04.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 401.50 44.48
04.01.03.04 CONCRETO f'c=175 kg/cm2 m3 17.05 448.85
04.01.04 MURO DE LADRILLO
04.01.04.01 MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE SOGA C/M 1:4 x 1.5cm m2 800.80 58.10
04.01.04.02 EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-6" m2 15.40 70.33
04.01.05 REVOQUES Y ENLUCIDOS
04.01.05.01 TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre hidraulico) m2 752.40 16.34
04.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 12.10 36.55
04.01.06 PINTURA
04.01.06.01 PINTURA EN MUROS INTERIORES C/LATEX LAVABLE COLOR MARFIL m2 453.75 11.53
04.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO ETERNIT(1,14x0.72x0.005m)
04.01.07.01 m2 358.05 66.22
04.01.08 CARPINTERIA METALICA
04.01.08.01 SUMINISTRO E INSTALACION DE PUERTA METALICA 1.80x0.70m, INCL. MARCO Y PINTADO und 55.00 363.74
04.01.09 CARPINTERIA DE MADERA
04.01.09.01 VENTANA DE MADERA TORNILLO INC. MALLA MOSQUITERA m2 9.90 75.90
04.01.09.02 COBERTURA DE MADERA PARA TECHO und 55.00 97.95
04.01.10 SISTEMA DE AGUA FRIA
04.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 520.85 3.65
04.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
04.01.11.01 TEE PVC-SAP 1/2" pza 110.00 20.85
04.01.11.02 CODO PVC SAP 1/2" pza 330.00 15.59
04.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 110.00 51.25
04.01.11.04 SUMINISTRO E INSTALACION DE DUCHA INCLUIDO ACCESORIOS und 55.00 33.08
04.01.12 SISTEMA DE DESAGUE
04.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 530.75 4.02
04.01.12.02 TUBERIA Ø=4" PVC SAL m 200.75 3.65
04.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
04.01.13.01 CODO PVC SAL 2"X90° pza 385.00 11.77
04.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 55.00 15.53
04.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 165.00 16.11
04.01.14 ADITAMIENTOS VARIOS
04.01.14.01 SUMIDEROS DE BRONCE 2" und 55.00 12.25
04.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 110.00 11.09
04.01.14.03 INODORO DE LOZA VITRIFICADA COLOR BLANCO INCLUYE TANQUE und 55.00 147.40
04.01.14.04 ACCESORIOS DE LOZA und 55.00 64.86
04.01.14.05 SUMINISTRO E INSTALACION DE TUBERIA DE VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y ACCESORIOS GLB 55.00 29.15
04.01.14.06 SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA COLOR BLANCO INCLUIDO ACCESORIOS und 55.00 124.59
04.01.14.07 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE 12"x24" und 110.00 129.89
04.01.15 INSTALACIONES ELECTRICAS
04.01.15.01 SALIDA DE CENTRO DE LUZ pto 55.00 49.14
04.01.15.02 TUBERIA PVC SEL 5/8" m 126.50 4.15
04.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 308.00 2.28
04.01.15.04 TABLEROS DISTRIBUCION pza 55.00 89.04
04.02 CONSTRUCCION POZO PERCOLADOR
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 172.70 0.49
04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 172.20 1.84
04.02.02 MOVIMIENTO DE TIERRAS
04.02.02.01 EXCAVACION A MANO TERRENO NORMAL m3 89.10 39.86
04.02.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 13.20 29.66
04.02.02.03 FILTRO DE GRAVA CLASIFICADA m3 47.85 89.30
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 111.65 25.69
04.02.03 TAPA DE CONCRETO
04.02.03.01 CONCRETO f'c=175 kg/cm2 m3 9.35 448.85
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 100.10 44.48
04.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,157.75 4.35
04.02.04 ANILLO DE CONCRETO
04.02.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 3.85 355.98
04.02.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.00 44.48
04.02.05 MURO DE LADRILLO
04.02.05.01 MURO DE LADRILLO ARTESANAL AMARRE DE SOGA, JUNTA 1.5 CM MORTERO 1:1:5 m2 229.90 48.94
04.02.06 SISTEMA DE DESAGUE LLEGADA
04.02.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 107.25 4.02
04.02.06.02 CODO PVC SAL 2"X90° pza 55.00 11.77
04.03 INSTALACION DEL BIODIGESTOR
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 207.90 0.49
04.03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 207.90 1.84
04.03.02 MOVIMIENTO DE TIERRAS
04.03.02.01 EXCAVACION A MANO TERRENO NORMAL m3 170.94 39.86
04.03.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 129.10 29.66
04.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 213.67 25.69
04.03.03 CONCRETO SIMPLE
04.03.03.01 SOLADO E=4" m2 35.75 39.68
04.03.04 CONCRETO ARMADO
04.03.04.01 CONCRETO f'c=175 kg/cm2 m3 39.60 448.85
04.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.60 44.48
04.03.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 306.35 4.35
04.03.05 BIODIGESTOR
04.03.05.01 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 600 LTS und 51.00 779.59
04.03.05.02 SUMINISTRO E INSTALACION DE BIODIGESTOR AUTOLIMPIABLE DE PVC DE 1300 LTS und 4.00 1,320.79
04.03.06 REVOQUES Y ENLUCIDOS
04.03.06.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 196.35 32.48
04.03.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
04.03.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 55.00 4.02
04.03.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 55.00 29.86
04.04 LAVADERO INTRADOMICILIARIO (51 UND)
04.04.01 OBRAS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 258.06 0.49
04.04.01.02 TRAZO Y REPLANTEO m2 258.06 1.84
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 57.74 37.48
04.04.02.02 RELLENO Y COMPACTADO DE ZANJA CON MATERIAL PROPIO CLASIFICADO m3 47.43 13.11
04.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.86 25.69
04.04.03 OBRAS DE CONCRETO ARMADO
04.04.03.01 CONCRETO f'c=175 kg/cm2 m3 5.36 448.85
04.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 170.73 44.48
04.04.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 201.71 4.35
04.04.04 MURO DE LADRILLO
04.04.04.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 33.72 47.74
04.04.05 REVOQUES Y ENLUCIDOS
04.04.05.01 TARRAJEO INTERIOR CON IMPERMEABILIZANTE MEZCLA 1:2 E=2 cm H=1.5 Max m2 60.13 32.48
04.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 115.06 29.76
04.04.06 ACCESORIOS Y VALVULAS
04.04.06.01 SUMINISTRO E INSTALACION DE LAVADERO INTRADOMICILIARIA und 51.00 136.31
04.04.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
04.04.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 255.00 3.35
04.05 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49
04.05.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.84
04.05.02 MOVIMIENTO DE TIERRAS
04.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48
04.05.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.32 1.02
04.05.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50
04.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69
04.05.03 OBRAS DE CONCRETO SIMPLE
04.05.03.01 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.20 48.96
04.05.04 OBRAS DE CONCRETO ARMADO
04.05.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35
04.05.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 44.01
04.05.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.21 448.85
04.05.05 REVOQUES Y REVESTIMIENTOS
04.05.05.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 2.49 32.96
04.05.05.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 2.11 23.98
04.05.06 ACCESORIOS Y VALVULAS
04.05.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO I.E. INICIAL und 1.00 176.99
04.05.06.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50
04.05.06.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77
04.05.06.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19
04.05.07 TUBERIA PVC INTRADOMICILIARIO
04.05.07.01 INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35
04.05.07.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65
04.06 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01 UND)
04.06.01 TRABAJOS PRELIMINARES
04.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.49
04.06.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.84
04.06.02 MOVIMIENTO DE TIERRAS
04.06.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 37.48
04.06.02.02 REFINE, NIVELACION Y COMPACTADO EN TERRENO NORMAL m2 11.98 1.02
04.06.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50
04.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 25.69
04.06.03 OBRAS DE CONCRETO SIMPLE
04.06.03.01 CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6") EN LAVADERO C/MEZCLADORA m3 0.06 339.60
04.06.03.02 VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M, FROTACHADO C/MEZCLADORA m2 2.86 48.96
04.06.04 OBRAS DE CONCRETO ARMADO
04.06.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.35
04.06.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 44.01
04.06.04.03 CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA LAVADEROS m3 0.31 448.85
04.06.05 ALBAÑILERIA
04.06.05.01 MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En Lavaderos) m2 0.36 58.08
04.06.06 REVOQUES Y REVESTIMIENTOS
04.06.06.01 TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2 cm, H=1.5 MAX m2 3.51 32.96
04.06.06.02 TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm, H=1.5 MAX m2 3.29 23.98
04.06.07 ACCESORIOS Y VALVULAS
04.06.07.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN LAVADERO TIPO I.E. PRIMARIA und 1.00 176.99
04.06.07.02 TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON LLAVE TIPO BUJIA und 2.00 142.50
04.06.07.03 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m (INTERIORES), E=0.05 und 1.00 57.77
04.06.07.04 CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m (INTERIORES), E=0.05 und 1.00 48.19
04.06.08 TUBERIA PVC INTRADOMICILIARIO
04.06.08.01 INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA CLASE 10 Ø=1/2", 5.0 M m 12.00 6.35
04.06.08.02 INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007 PARA DESAGUE Ø=2"x3 M m 10.00 6.65

01 LOCALIDAD SANTA LUCIA


01.01 CAPACITACION EN EDUCACION SANITARIA, PROMOCION DE LA SALUD Y AOM
01.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
01.01.01.01 TALLER IMPORTANCIA DE LA ORGANIZACION Y PARTICIPACION CIUDADANA Tall 1.00 940.60
01.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60
01.01.02 EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y SALUD)
01.01.02.01 TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y SALUD (Valoracion del agua) Tall 1.00 940.61
01.01.02.02 TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION DE EXCRETAS Tall 1.00 940.61
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL HOGAR Y
01.01.02.03 Tall 1.00 940.61
COMUNAL
01.01.02.04 CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE. Tall 1.00 940.61
01.01.02.05 DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y SANEAMIENTO (SPOT PUBLICITARIO) Men 2.00 84.74
01.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
01.01.03.01 TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS Tall 1.00 940.61
01.01.03.02 TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA POTABLE Tall 1.00 940.61
01.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61
01.01.03.04 TALLER DE CLORACION Y DESINFECCION DE AGUA PARA CONSUMO HUMANO Tall 1.00 1,110.11
01.02 FLETE
01.02.01 FLETE RURAL
01.02.01.01 FLETE RURAL GLB 1.00 25,395.57
01.02.02 FLETE TERRESTRE
01.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00
01.02.02.02 FLETE TERRESTRE GLB 1.00 10,576.27
01.03 MITIGACION AMBIENTAL
01.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00
01.03.02 PROGRAMA DE CONSERVACION, RESTAURACION Y COMPESACION DE COBERTURA VEGETAL (REFORESTACION) GLB 1.00 1,712.00
01.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00
01.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00
01.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 500.00
01.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00
01.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00
01.04 CONTROL Y SEGURIDAD EN OBRA
01.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 6,959.68
02 LOCALIDAD PUEBLO LIBRE
02.01 CAPACITACION EN EDUCACION SANITARIA, PROMOCION DE LA SALUD Y AOM
02.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
02.01.01.01 TALLER IMPORTANCIA DE LA ORGANIZACION Y PARTICIPACION CIUDADANA Tall 1.00 940.60
02.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60
02.01.02 EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y SALUD)
02.01.02.01 TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y SALUD (Valoracion del agua) Tall 1.00 940.61
02.01.02.02 TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION DE EXCRETAS Tall 1.00 940.61
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL HOGAR Y
02.01.02.03 Tall 1.00 940.61
COMUNAL
02.01.02.04 CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE. Tall 1.00 940.61
02.01.02.05 DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y SANEAMIENTO (SPOT PUBLICITARIO) Men 2.00 84.74
02.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
02.01.03.01 TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS Tall 1.00 940.61
02.01.03.02 TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA POTABLE Tall 1.00 940.61
02.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61
02.01.03.04 TALLER DE CLORACION Y DESINFECCION DE AGUA PARA CONSUMO HUMANO Tall 1.00 1,110.11
02.02 FLETE
02.02.01 FLETE RURAL
02.02.01.01 FLETE RURAL GLB 1.00 34,884.02
02.02.02 FLETE TERRESTRE
02.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00
02.02.02.02 FLETE TERRESTRE GLB 1.00 17,338.98
02.02.03 MITIGACION AMBIENTAL
02.02.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00
02.02.03.02 PROGRAMA DE CONSERVACION, RESTAURACION Y COMPESACION DE COBERTURA VEGETAL (REFORESTACION) GLB 1.00 1,712.00
02.02.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00
02.02.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00
02.02.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 500.00
02.02.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00
02.02.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00
02.02.04 CONTROL Y SEGURIDAD EN OBRA
02.02.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 9,221.36
03 LOCALIDAD TANCARPATA
03.01 CAPACITACION EN EDUCACION SANITARIA, PROMOCION DE LA SALUD Y AOM
03.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
03.01.01.01 TALLER IMPORTANCIA DE LA ORGANIZACION Y PARTICIPACION CIUDADANA Tall 1.00 940.60
03.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60
03.01.02 EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y SALUD)
03.01.02.01 TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y SALUD (Valoracion del agua) Tall 1.00 940.61
03.01.02.02 TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION DE EXCRETAS Tall 1.00 940.61
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL HOGAR Y
03.01.02.03 Tall 1.00 940.61
COMUNAL
03.01.02.04 CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE. Tall 1.00 940.61
03.01.02.05 DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y SANEAMIENTO (SPOT PUBLICITARIO) Men 2.00 84.74
03.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
03.01.03.01 TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS Tall 1.00 940.61
03.01.03.02 TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA POTABLE Tall 1.00 940.61
03.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61
03.01.03.04 TALLER DE CLORACION Y DESINFECCION DE AGUA PARA CONSUMO HUMANO Tall 1.00 1,110.11
03.02 FLETE
03.02.01 FLETE RURAL
03.02.01.01 FLETE RURAL GLB 1.00 15,348.97
03.02.02 FLETE TERRESTRE
03.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00
03.02.02.02 FLETE TERRESTRE GLB 1.00 6,864.41
03.03 MITIGACION AMBIENTAL
03.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00
03.03.02 PROGRAMA DE CONSERVACION, RESTAURACION Y COMPESACION DE COBERTURA VEGETAL (REFORESTACION) GLB 1.00 1,712.00
03.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00
03.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00
03.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 500.00
03.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00
03.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00
03.04 CONTROL Y SEGURIDAD EN OBRA
03.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 4,564.96
04 LOCALIDAD TARACA
04.01 CAPACITACION EN EDUCACION SANITARIA, PROMOCION DE LA SALUD Y AOM
04.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
04.01.01.01 TALLER IMPORTANCIA DE LA ORGANIZACION Y PARTICIPACION CIUDADANA Tall 1.00 940.60
04.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60
04.01.02 EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y SALUD)
04.01.02.01 TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y SALUD (Valoracion del agua) Tall 1.00 940.61
04.01.02.02 TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION DE EXCRETAS Tall 1.00 940.61
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL HOGAR Y
04.01.02.03 Tall 1.00 940.61
COMUNAL
04.01.02.04 CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE. Tall 1.00 940.61
04.01.02.05 DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y SANEAMIENTO (SPOT PUBLICITARIO) Men 2.00 84.74
04.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
04.01.03.01 TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS Tall 1.00 940.61
04.01.03.02 TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA POTABLE Tall 1.00 940.61
04.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61
04.01.03.04 TALLER DE CLORACION Y DESINFECCION DE AGUA PARA CONSUMO HUMANO Tall 1.00 1,110.11
04.02 FLETE
04.02.01 FLETE RURAL
04.02.01.01 FLETE RURAL GLB 1.00 15,348.97
04.02.02 FLETE TERRESTRE
04.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00
04.02.02.02 FLETE TERRESTRE GLB 1.00 7,372.78
04.03 MITIGACION AMBIENTAL
04.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,839.85
04.03.02 PROGRAMA DE CONSERVACION, RESTAURACION Y COMPESACION DE COBERTURA VEGETAL (REFORESTACION) GLB 1.00 1,712.00
04.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00
04.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00
04.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 500.00
04.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00
04.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00
04.04 CONTROL Y SEGURIDAD EN OBRA
04.04.01 IMPLEMENTOS DE SEGURIDAD PUEBLO LIBRE GLB 1.00 4,564.96

COSTO DIRECTO

GASTOS GENERALES (8%)

UTILIDAD (7%)

SUB TOTAL

IGV (18%)

PRESUPUESTO DE OBRA
PARCIAL PARCIAL
(S/.) AL (S/.) AL
100% 90%

4,455.00 4,009.50
3,000.00 2,700.00
1,539.82 1,385.84

24.01 21.61
66.24 59.62

646.93 582.24
75.23 67.71
214.65 193.19
439.30 395.37

706.52 635.87
117.43 105.69
60.55 54.50

811.87 730.68
797.53 717.78
296.06 266.45

179.61 161.65
358.61 322.75

159.42 143.48

265.53 238.98
25.86 23.27

179.83 161.85
281.53 253.38
501.29 451.16

44.16 39.74

23.52 21.17
18.75 16.88

210.03 189.03

69.39 62.45

556.79 501.11

128.44 115.60

533.28 479.95

194.10 174.69

539.98 485.98
1,686.06 1,517.45
1,686.06 1,517.45

19,764.59 17,788.13
2,459.66 2,213.69
1,994.62 1,795.16
670.02 603.02
6,016.92 5,415.23
1,795.43 1,615.89
707.76 636.98

7,923.38 7,131.04
140.33 126.30
1,664.02 1,497.62

0.71 0.64
2.65 2.39

62.98 56.68
50.87 45.78
11.45 10.31

43.33 39.00
4.13 3.72
8.90 8.01
60.55 54.50

431.89 388.70
360.29 324.26
161.95 145.76

81.85 73.67
96.42 86.78

36.22 32.60

213.73 192.36

299.60 269.64

0.49 0.44
1.84 1.66

20.33 18.30
6.69 6.02
3.90 3.51
16.44 14.80
8.26 7.43
10.68 9.61
32.70 29.43

191.34 172.21
165.47 148.92
64.99 58.49

46.77 42.09
99.99 89.99

24.15 21.74

214.83 193.35

153.06 137.75

17.64 15.88
66.24 59.62

2,050.00 1,845.00
90.71 81.64
1,651.61 1,486.45

4.13 3.72
8.90 8.01
60.55 54.50

466.33 419.70
6,161.20 5,545.08
2,281.38 2,053.24
1,404.79 1,264.31

1,017.27 915.54
1,208.55 1,087.70
461.99 415.79

427.46 384.71

1,745.47 1,570.92

66.24 59.62

27.90 25.11
18.75 16.88

249.19 224.27

69.39 62.45

556.79 501.11

252.32 227.09

515.50 463.95

194.10 174.69

413.30 371.97
221.13 199.02

174.42 156.98
203.80 183.42

449.40 404.46
55.12 49.61

367.18 330.46
167.48 150.73
49.00 44.10

435.06 391.55

939.22 845.30

1,071.88 964.69
6,693.75 6,024.38
6,693.75 6,024.38

20,926.50 18,833.85
56,670.25 51,003.23
4,882.50 4,394.25
7,918.75 7,126.88
26,600.00 23,940.00
22,693.22 20,423.90
2,138.23 1,924.41
29,613.94 26,652.55
8,838.53 7,954.68
2,247.88 2,023.09

14,651.00 13,185.90
12,366.20 11,129.58
137.74 123.97

6,606.25 5,945.63

11.16 10.04
41.90 37.71

570.80 513.72
391.07 351.96
31.33 28.20
171.88 154.69
76.08 68.47
252.79 227.51

53.71 48.34
65.17 58.65
97.86 88.07
359.67 323.70

8,178.48 7,360.63
6,811.67 6,130.50
9,416.10 8,474.49

1,543.45 1,389.11
3,064.68 2,758.21

737.88 664.09

1,978.13 1,780.32
2,351.03 2,115.93

2,688.56 2,419.70
1,895.90 1,706.31

2.45 2.21
9.20 8.28

199.30 179.37
160.56 144.50
39.75 35.78

1,350.32 1,215.29
947.42 852.68
668.94 602.05

233.86 210.47
321.41 289.27
72.45 65.21

814.40 732.96

90.28 81.25
316.08 284.47

3.92 3.53
14.72 13.25

487.49 438.74
203.27 182.94
53.49 48.14
31.16 28.04
100.70 90.63

1,012.27 911.04
85.40 76.86
123.52 111.17

1,530.73 1,377.66
1,323.72 1,191.35
519.96 467.96

374.17 336.75
799.95 719.96

144.89 130.40

1,709.84 1,538.86

149.25 134.33
930.58 837.52
403.92 363.53
2,275.12 2,047.61

39,428.71 35,485.84
32,642.94 29,378.65
21,546.69 19,392.02

2,817.82 2,536.04
1,514.10 1,362.69

7,430.84 6,687.76
14,279.32 12,851.39
2,576.00 2,318.40

4,455.00 4,009.50
3,000.00 2,700.00
1,539.82 1,385.84

24.01 21.61
66.24 59.62

898.05 808.25
75.23 67.71
214.65 193.19
643.53 579.18

706.52 635.87
117.43 105.69
60.55 54.50

811.87 730.68
797.53 717.78
296.06 266.45

179.61 161.65
358.61 322.75

159.42 143.48

265.53 238.98
25.86 23.27

180.93 162.84
281.53 253.38

501.29 451.16

44.16 39.74

23.52 21.17
18.75 16.88

210.03 189.03

69.39 62.45

556.79 501.11

128.44 115.60

533.28 479.95

194.10 174.69

10.98 9.88
41.22 37.10

102.44 92.20
82.46 74.21
26.08 23.47
52.49 47.24

1,267.71 1,140.94
111.20 100.08
174.52 157.07

74.40 66.96

48.78 43.90

3,651.92 3,286.73

293.41 264.07

509.33 458.40

934.94 841.45

1,054.97 949.47
3,294.09 2,964.68
3,294.09 2,964.68

3,432.74 3,089.47
38,614.49 34,753.04
3,896.93 3,507.24
9,214.84 8,293.36
11,755.38 10,579.84
13,493.93 12,144.54
691.32 622.19

12,788.82 11,509.94
215.53 193.98

3,251.03 2,925.93
4.23 3.81
15.90 14.31

378.67 340.80
305.20 274.68
68.69 61.82

259.98 233.98
28.92 26.03
53.38 48.04
363.30 326.97

2,591.31 2,332.18
2,161.73 1,945.56
971.66 874.49

491.10 441.99
578.53 520.68

217.34 195.61

1,282.38 1,154.14

1,797.60 1,617.84

0.98 0.88
3.68 3.31

40.66 36.59
13.37 12.03
7.79 7.01
32.63 29.37

16.53 14.88
21.35 19.22
65.39 58.85

382.68 344.41
330.93 297.84
129.98 116.98

93.54 84.19
199.99 179.99

48.30 43.47

429.66 386.69

306.12 275.51

17.64 15.88
66.24 59.62

3,160.90 2,844.81
90.71 81.64
2,546.65 2,291.99

4.13 3.72
8.90 8.01
60.55 54.50

466.33 419.70
7,380.32 6,642.29
2,556.71 2,301.04
1,520.28 1,368.25

1,069.89 962.90
1,700.49 1,530.44

680.68 612.61
427.46 384.71

1,745.47 1,570.92

66.24 59.62

27.90 25.11
18.75 16.88

249.19 224.27

69.39 62.45

556.79 501.11

252.32 227.09

515.50 463.95

194.10 174.69

413.30 371.97
221.13 199.02

174.42 156.98
203.80 183.42

449.40 404.46
55.12 49.61

367.18 330.46

167.48 150.73
49.00 44.10
435.06 391.55

939.22 845.30

1,391.11 1,252.00
8,687.34 7,818.61
8,687.34 7,818.61

67,890.71 61,101.64
50,693.18 45,623.86
10,277.18 9,249.46
13,808.90 12,428.01
18,601.13 16,741.02
37,003.53 33,303.18
49,821.61 44,839.45
70,588.90 63,530.01
14,586.78 13,128.10

9,225.30 8,302.77
21,939.72 19,745.75
351.43 316.29

8,573.78 7,716.40

16.23 14.61
60.94 54.85

913.19 821.87
625.31 562.78
50.08 45.07
249.95 224.96
110.56 99.50
588.56 529.70
78.50 70.65
94.54 85.09
142.34 128.11
523.15 470.84

11,885.04 10,696.54
9,908.36 8,917.52
13,696.15 12,326.54

2,245.02 2,020.52
4,457.75 4,011.98

1,073.28 965.95

2,877.28 2,589.55
3,419.68 3,077.71

1,152.24 1,037.02
4,929.34 4,436.41

2.94 2.65
11.04 9.94

239.16 215.24
192.68 173.41
47.70 42.93

1,618.20 1,456.38
1,136.91 1,023.22
802.71 722.44

280.63 252.57
385.69 347.12

144.89 130.40
977.28 879.55

180.56 162.50
316.08 284.47

1.47 1.32
5.52 4.97

182.96 164.66
76.22 68.60
20.06 18.05
11.69 10.52
37.76 33.98

380.12 342.11
32.03 28.83
46.02 41.42

574.02 516.62
496.40 446.76
194.97 175.47

140.31 126.28
299.98 269.98

54.11 48.70

641.19 577.07

398.82 358.94

548.80 493.92
3,091.20 2,782.08

53,571.84 48,214.66
44,352.00 39,916.80
29,275.40 26,347.86

3,830.09 3,447.08
2,057.20 1,851.48

10,096.25 9,086.63
19,401.25 17,461.13
3,937.50 3,543.75

4,455.00 4,009.50
3,000.00 2,700.00
1,539.82 1,385.84

24.01 21.61
66.24 59.62

599.10 539.19
75.23 67.71
214.65 193.19
400.76 360.68

706.52 635.87
117.43 105.69
60.55 54.50

811.87 730.68
797.53 717.78
296.06 266.45

179.61 161.65
358.61 322.75

159.42 143.48
265.53 238.98
25.86 23.27

180.93 162.84
281.53 253.38

497.69 447.92

44.16 39.74

23.52 21.17
18.75 16.88

210.03 189.03

69.39 62.45

556.79 501.11

128.44 115.60

533.28 479.95

194.10 174.69

96.04 86.44
299.88 269.89
299.88 269.89

3,593.52 3,234.17
349.87 314.88
354.76 319.28
1,191.68 1,072.51
838.88 754.99
984.62 886.16
153.15 137.84
1,129.40 1,016.46
243.67 219.30
100.70 90.63

1,164.24 1,047.82
160.91 144.82

272.34 245.11

0.71 0.64
2.65 2.39

62.98 56.68
50.87 45.78
11.45 10.31

43.33 39.00
4.13 3.72
8.90 8.01
60.55 54.50

431.89 388.70
360.29 324.26
161.95 145.76

81.85 73.67
96.42 86.78

36.22 32.60

213.73 192.36

299.60 269.64
0.49 0.44
1.84 1.66

20.33 18.30
6.69 6.02
3.90 3.51
16.44 14.80

82.63 74.37
10.68 9.61
32.70 29.43

191.34 172.21
165.47 148.92
64.99 58.49

46.77 42.09
99.99 89.99

24.15 21.74

214.83 193.35

153.06 137.75

17.64 15.88
66.24 59.62

2,429.47 2,186.52
64.00 57.60
1,957.32 1,761.59

4.13 3.72
8.90 8.01
60.55 54.50
329.00 296.10
5,199.02 4,679.12
2,202.65 1,982.39
1,107.68 996.91

1,006.88 906.19
1,056.48 950.83

385.65 347.09

427.46 384.71

1,618.16 1,456.34

66.24 59.62

27.90 25.11
18.75 16.88

249.19 224.27

69.39 62.45

556.79 501.11

252.32 227.09

515.50 463.95

194.10 174.69

413.30 371.97
221.13 199.02
174.42 156.98
203.80 183.42

449.40 404.46
55.12 49.61

367.18 330.46

167.48 150.73
49.00 44.10

435.06 391.55

939.22 845.30

671.30 604.17
4,192.20 3,772.98
4,192.20 3,772.98

51,872.58 46,685.32
3,057.84 2,752.06
4,959.40 4,463.46
832.96 749.66
14,212.38 12,791.14
1,339.24 1,205.32
18,031.60 16,228.44
4,257.96 3,832.16
879.88 791.89

32.20 28.98
13,242.24 11,918.02
96.63 86.97

4,137.40 3,723.66
9.13 8.22
34.28 30.85

570.80 513.72
293.20 263.88
31.33 28.20
140.64 126.58
63.01 56.71
207.06 186.35

45.45 40.91
53.36 48.02
80.06 72.05
294.27 264.84

6,686.02 6,017.42
5,573.34 5,016.01
7,704.11 6,933.70

1,262.82 1,136.54
2,507.58 2,256.82

603.72 543.35

1,618.47 1,456.62
1,923.57 1,731.21

3,412.62 3,071.36

2.45 2.21
9.20 8.28

199.30 179.37
160.56 144.50
39.75 35.78
1,350.32 1,215.29
947.42 852.68
668.94 602.05

233.86 210.47
321.41 289.27

120.74 108.67

814.40 732.96

395.10 355.59

2.94 2.65
11.04 9.94

365.52 328.97
152.45 137.21
40.12 36.11
23.37 21.03
75.53 67.98

760.23 684.21
64.05 57.65
93.25 83.93

1,148.05 1,033.25
1,037.27 933.54
376.88 339.19

280.63 252.57
599.96 539.96

108.67 97.80

1,282.38 1,154.14
797.64 717.88

232.69 209.42
1,310.67 1,179.60

22,714.62 20,443.16
18,805.38 16,924.84
10,530.78 9,477.70

1,623.76 1,461.38
872.25 785.03

4,280.81 3,852.73
8,226.13 7,403.52
1,855.00 1,669.50

4,455.00 4,009.50
3,000.00 2,700.00
1,539.82 1,385.84

24.01 21.61
66.24 59.62

699.54 629.59
75.23 67.71
214.65 193.19
400.76 360.68

706.52 635.87
117.43 105.69
60.55 54.50

811.87 730.68
797.53 717.78
296.06 266.45

179.61 161.65
358.61 322.75

159.42 143.48

265.53 238.98
25.86 23.27

180.93 162.84
281.53 253.38

497.69 447.92

44.16 39.74

23.52 21.17
18.75 16.88

210.03 189.03

69.39 62.45

556.79 501.11

128.44 115.60

533.28 479.95

194.10 174.69

603.19 542.87
1,883.43 1,695.09
1,883.43 1,695.09

15,661.79 14,095.61
3,679.71 3,311.74
858.76 772.88
2,228.11 2,005.30
374.22 336.80
5,268.68 4,741.81
6,385.29 5,746.76
601.52 541.37
7,329.47 6,596.52
382.91 344.62
395.37 355.83

7,312.14 6,580.93
157.71 141.94

1,858.81 1,672.93

1.41 1.27
5.30 4.77

126.36 113.72
203.46 183.11
22.90 20.61

86.66 77.99
8.26 7.43
17.79 16.01
121.10 108.99

863.77 777.39
720.58 648.52
323.90 291.51

163.70 147.33
192.84 173.56

72.45 65.21

427.46 384.71

599.20 539.28

0.98 0.88
3.68 3.31

40.66 36.59
13.37 12.03
7.79 7.01
32.63 29.37

16.53 14.88
21.35 19.22
65.39 58.85

382.68 344.41
330.93 297.84
129.98 116.98

93.54 84.19
199.99 179.99

48.30 43.47

429.66 386.69

306.12 275.51

17.64 15.88
66.24 59.62
1,435.76 1,292.18
64.00 57.60
1,156.56 1,040.90

4.13 3.72
8.90 8.01
60.55 54.50

329.00 296.10
5,199.02 4,679.12
2,202.65 1,982.39
1,107.68 996.91

1,006.88 906.19
1,056.48 950.83

385.65 347.09

427.46 384.71

1,618.16 1,456.34

66.24 59.62

27.90 25.11
18.75 16.88

249.19 224.27

69.39 62.45

556.79 501.11

252.32 227.09
515.50 463.95

194.10 174.69

413.30 371.97
221.13 199.02

174.42 156.98
203.80 183.42

449.40 404.46
55.12 49.61

367.18 330.46

167.48 150.73
49.00 44.10

435.06 391.55

939.22 845.30

900.13 810.12
5,621.22 5,059.10
5,621.22 5,059.10

2,928.91 2,636.02
67,358.13 60,622.32
2,460.22 2,214.20
6,649.94 5,984.95
670.14 603.13
19,458.35 17,512.52
1,077.26 969.53
23,717.72 21,345.95
3,425.64 3,083.08
708.02 637.22

837.20 753.48
17,278.80 15,550.92
87.97 79.17

5,547.74 4,992.97

12.17 10.95
45.71 41.14

666.06 599.45
391.07 351.96
31.33 28.20
187.46 168.71
82.62 74.36
321.90 289.71

57.84 52.06
70.90 63.81
106.75 96.08
392.36 353.12

8,911.05 8,019.95
7,430.83 6,687.75
10,272.13 9,244.92

1,683.76 1,515.38
3,343.24 3,008.92

804.96 724.46

2,157.96 1,942.16
2,564.76 2,308.28
4,550.16 4,095.14

2.45 2.21
9.20 8.28

199.30 179.37
160.56 144.50
39.75 35.78

1,350.32 1,215.29
947.42 852.68
668.94 602.05

233.86 210.47
321.41 289.27

120.74 108.67

814.40 732.96

395.10 355.59

2.45 2.21
9.20 8.28

304.53 274.08
127.04 114.34
33.43 30.09
19.48 17.53
62.94 56.65

632.15 568.94
53.38 48.04
77.50 69.75
956.71 861.04
827.33 744.60
324.95 292.46

233.86 210.47
499.97 449.97

90.56 81.50

1,068.65 961.79

664.70 598.23

232.69 209.42
1,310.67 1,179.60

24,441.42 21,997.28
18,805.38 16,924.84
12,412.77 11,171.49

1,623.76 1,461.38
872.25 785.03

4,280.81 3,852.73
8,226.13 7,403.52
2,226.00 2,003.40

227.85 205.07
855.60 770.04

9,230.38 8,307.34
1,213.69 1,092.32
6,116.28 5,504.65
104,276.25 93,848.63
16,314.39 14,682.95
30,197.47 27,177.72
12,940.35 11,646.32

78,672.05 70,804.85
1,831.39 1,648.25

20,788.40 18,709.56
747.81 673.03

8,846.39 7,961.75

40,091.57 36,082.41

33,827.82 30,445.04

1,270.57 1,143.51
9,109.35 8,198.42

3,214.59 2,893.13

3,878.10 3,490.29
8,699.22 7,829.30
9,532.50 8,579.25
3,076.44 2,768.80

3,607.75 3,246.98
1,238.99 1,115.09

7,662.27 6,896.04
1,444.29 1,299.86
4,494.69 4,045.22

1,139.25 1,025.33
2,062.74 1,856.47
13,708.20 12,337.38
6,031.98 5,428.78
2,710.95 2,439.86
11,586.87 10,428.18
24,159.54 21,743.59

4,570.02 4,113.02
887.69 798.92
1,187.42 1,068.68
8,280.72 7,452.65

143.09 128.78
537.32 483.59

6,005.31 5,404.78
662.01 595.81
7,225.26 6,502.73
4,850.02 4,365.02

8,442.87 7,598.58
8,729.64 7,856.68
8,515.78 7,664.20

2,317.43 2,085.69
4,963.97 4,467.57

19,024.94 17,122.45

729.03 656.13
1,094.61 985.15

172.25 155.03
646.83 582.15

11,208.63 10,087.77
6,287.03 5,658.33
9,030.04 8,127.04

2,398.66 2,158.79

30,055.00 27,049.50
18,697.61 16,827.85
2,253.34 2,028.01

70,942.69 63,848.42
2,641.58 2,377.42

10,783.68 9,705.31

373.86 336.47
2,776.98 2,499.28

225.63 203.07
847.25 762.53

3,861.56 3,475.40
1,109.50 998.55
543.60 489.24

4,295.49 3,865.94
13,549.94 12,194.95
1,565.61 1,409.05

2,872.52 2,585.27

3,484.78 3,136.30
6,109.73 5,498.76

12,404.21 11,163.79

1,524.25 1,371.83
5.55 5.00
20.83 18.75

102.70 92.43
11.55 10.40
47.79 43.01
34.42 30.98

107.71 96.94

36.32 32.69
180.00 162.00
94.26 84.83

82.07 73.86
50.60 45.54

176.99 159.29
285.00 256.50
57.77 51.99
48.19 43.37

76.20 68.58
66.50 59.85

318.50 286.65
1,196.00 1,076.40

12,902.68 11,612.41
1,696.55 1,526.90
8,549.63 7,694.67

145,762.50 131,186.25
22,805.07 20,524.56
42,211.52 37,990.37
18,088.66 16,279.79

109,971.68 98,974.51
2,560.01 2,304.01

29,059.06 26,153.15
1,045.33 940.80

12,365.93 11,129.34

56,061.85 50,455.67

47,286.20 42,557.58

1,776.06 1,598.45
12,733.50 11,460.15

4,493.15 4,043.84

5,421.00 4,878.90
12,160.20 10,944.18
13,325.00 11,992.50
4,300.40 3,870.36

5,043.09 4,538.78
1,731.93 1,558.74

10,710.70 9,639.63
2,018.90 1,817.01
6,282.90 5,654.61

1,592.50 1,433.25
2,883.40 2,595.06
19,162.00 17,245.80
8,431.80 7,588.62
3,789.50 3,410.55
16,196.70 14,577.03
33,771.40 30,394.26

6,388.20 5,749.38
1,240.85 1,116.77
1,659.84 1,493.86
11,575.20 10,417.68

200.02 180.02
751.09 675.98

8,394.52 7,555.07
925.39 832.85
10,099.83 9,089.85
4,210.59 3,789.53

9,919.59 8,927.63
10,523.97 9,471.57
11,903.78 10,713.40

3,239.42 2,915.48
6,938.88 6,244.99

26,594.00 23,934.60

1,019.07 917.16
1,530.10 1,377.09

240.79 216.71
904.18 813.76

15,812.46 14,231.21
8,875.46 7,987.91
12,950.59 11,655.53
3,352.96 3,017.66

42,012.36 37,811.12
26,136.45 23,522.81
3,149.84 2,834.86

94,330.39 84,897.35
11,887.11 10,698.40

15,073.97 13,566.57

522.60 470.34
3,881.80 3,493.62

300.01 270.01
1,126.56 1,013.90

5,134.76 4,621.28
1,475.27 1,327.74
722.92 650.63

5,709.37 5,138.43
18,017.07 16,215.36
2,081.74 1,873.57

3,819.68 3,437.71

4,633.60 4,170.24
8,123.88 7,311.49

16,493.51 14,844.16

2,026.75 1,824.08
5.55 5.00
20.83 18.75

102.70 92.43
11.55 10.40
47.79 43.01
34.42 30.98

107.71 96.94

36.32 32.69
180.00 162.00
94.26 84.83

82.07 73.86
50.60 45.54

176.99 159.29
285.00 256.50
57.77 51.99
48.19 43.37

76.20 68.58
66.50 59.85

5.87 5.28
22.04 19.84

104.94 94.45
12.22 11.00
47.79 43.01
36.22 32.60

20.38 18.34
140.03 126.03
49.98 44.98
190.56 171.50
139.14 125.23

20.91 18.82

115.69 104.12
78.89 71.00

176.99 159.29
285.00 256.50
57.77 51.99
48.19 43.37

76.20 68.58
66.50 59.85

5.55 5.00
20.83 18.75

138.68 124.81
11.55 10.40
77.88 70.09
32.63 29.37

27.17 24.45
10.77 9.69

1.13 1.02
228.85 205.97
5,713.86 5,142.47

60.40 54.36

103.16 92.84
105.75 95.18
176.99 159.29
285.00 256.50
57.77 51.99
48.19 43.37

76.20 68.58
66.50 59.85

134.75 121.28
506.00 455.40

5,458.83 4,912.95
717.77 645.99
3,617.15 3,255.44

61,668.75 55,501.88
9,648.30 8,683.47
17,858.72 16,072.85
7,652.89 6,887.60

46,526.48 41,873.83
1,083.08 974.77

12,294.22 11,064.80
442.26 398.03

5,231.74 4,708.57

23,710.07 21,339.06

20,005.70 18,005.13

751.41 676.27
5,387.25 4,848.53
1,901.10 1,710.99

2,293.50 2,064.15
5,144.70 4,630.23
5,637.50 5,073.75
1,819.40 1,637.46

2,133.62 1,920.26
732.74 659.47

4,531.45 4,078.31
854.15 768.74
2,658.15 2,392.34

673.75 606.38
1,219.90 1,097.91
8,107.00 7,296.30
3,567.30 3,210.57
1,603.25 1,442.93
6,852.45 6,167.21
14,287.90 12,859.11

2,702.70 2,432.43
524.98 472.48
702.24 632.02
4,897.20 4,407.48

84.62 76.16
316.85 285.17

3,551.53 3,196.38
391.51 352.36
4,273.01 3,845.71
2,868.29 2,581.46
4,196.75 3,777.08
4,452.45 4,007.21
5,036.21 4,532.59

1,370.52 1,233.47
2,935.68 2,642.11

11,251.31 10,126.18

431.15 388.04
647.35 582.62

101.87 91.68
382.54 344.29

6,813.67 6,132.30
3,829.11 3,446.20
5,489.18 4,940.26

1,418.56 1,276.70

17,774.46 15,997.01
11,057.73 9,951.96
1,332.62 1,199.36

39,759.09 35,783.18
5,283.16 4,754.84

6,377.45 5,739.71

221.10 198.99
1,642.30 1,478.07

126.45 113.81
474.83 427.35
2,164.10 1,947.69
621.81 559.63
304.68 274.21

2,405.84 2,165.26
7,594.07 6,834.66
877.44 789.70

1,609.79 1,448.81

1,953.02 1,757.72
3,424.19 3,081.77

6,951.81 6,256.63

854.25 768.83

5.55 5.00
20.83 18.75

102.70 92.43
11.55 10.40
47.79 43.01
34.42 30.98

107.71 96.94

36.32 32.69
180.00 162.00
94.26 84.83

82.07 73.86
50.60 45.54

176.99 159.29
285.00 256.50
57.77 51.99
48.19 43.37

76.20 68.58
66.50 59.85

5.87 5.28
22.04 19.84

104.94 94.45
12.22 11.00
47.79 43.01
36.22 32.60

20.38 18.34
140.03 126.03

49.98 44.98
190.56 171.50
139.14 125.23

20.91 18.82

115.69 104.12
78.89 71.00

176.99 159.29
285.00 256.50
57.77 51.99
48.19 43.37

76.20 68.58
66.50 59.85
134.75 121.28
506.00 455.40

5,458.83 4,912.95
717.77 645.99
3,617.15 3,255.44

61,668.75 55,501.88
9,648.30 8,683.47
17,858.72 16,072.85
7,652.89 6,887.60

46,526.48 41,873.83
1,083.08 974.77

12,294.22 11,064.80
442.26 398.03

5,231.74 4,708.57

23,710.07 21,339.06

20,005.70 18,005.13

751.41 676.27
5,387.25 4,848.53

1,901.10 1,710.99

2,293.50 2,064.15
5,144.70 4,630.23
5,637.50 5,073.75
1,819.40 1,637.46

2,133.62 1,920.26
732.74 659.47
4,531.45 4,078.31
854.15 768.74
2,658.15 2,392.34

673.75 606.38
1,219.90 1,097.91
8,107.00 7,296.30
3,567.30 3,210.57
1,603.25 1,442.93
6,852.45 6,167.21
14,287.90 12,859.11

2,702.70 2,432.43
524.98 472.48
702.24 632.02
4,897.20 4,407.48

84.62 76.16
316.85 285.17

3,551.53 3,196.38
391.51 352.36
4,273.01 3,845.71
2,868.29 2,581.46

4,196.75 3,777.08
4,452.45 4,007.21
5,036.21 4,532.59

1,370.52 1,233.47
2,935.68 2,642.11

11,251.31 10,126.18

431.15 388.04
647.35 582.62

101.87 91.68
382.54 344.29

6,813.67 6,132.30
3,829.11 3,446.20
5,489.18 4,940.26

1,418.56 1,276.70

17,774.46 15,997.01
11,057.73 9,951.96
1,332.62 1,199.36

39,759.09 35,783.18
5,283.16 4,754.84

6,377.45 5,739.71

221.10 198.99
1,642.30 1,478.07

126.45 113.81
474.83 427.35

2,164.10 1,947.69
621.81 559.63
304.68 274.21

2,405.84 2,165.26
7,594.07 6,834.66
877.44 789.70

1,609.79 1,448.81
1,953.02 1,757.72
3,424.19 3,081.77

6,951.81 6,256.63

854.25 768.83

5.55 5.00
20.83 18.75

102.70 92.43
11.55 10.40
47.79 43.01
34.42 30.98

107.71 96.94

36.32 32.69
180.00 162.00
94.26 84.83

82.07 73.86
50.60 45.54

176.99 159.29
285.00 256.50
57.77 51.99
48.19 43.37

76.20 68.58
66.50 59.85

5.87 5.28
22.04 19.84
104.94 94.45
12.22 11.00
47.79 43.01
36.22 32.60

20.38 18.34
140.03 126.03

49.98 44.98
190.56 171.50
139.14 125.23

20.91 18.82

115.69 104.12
78.89 71.00

176.99 159.29
285.00 256.50
57.77 51.99
48.19 43.37

76.20 68.58
66.50 59.85

940.60 846.54
940.60 846.54

940.61 846.55
940.61 846.55
940.61 846.55
940.61 846.55
169.48 152.53
940.61 846.55
940.61 846.55
940.61 846.55
1,110.11 999.10

25,395.57 22,856.01

4,725.00 4,252.50
10,576.27 9,518.64

2,840.00 2,556.00
1,712.00 1,540.80
3,400.00 3,060.00
1,000.00 900.00
500.00 450.00
3,600.00 3,240.00
600.00 540.00

6,959.68 6,263.71

940.60 846.54
940.60 846.54

940.61 846.55
940.61 846.55
940.61 846.55
940.61 846.55
169.48 152.53

940.61 846.55
940.61 846.55
940.61 846.55
1,110.11 999.10
34,884.02 31,395.62

4,725.00 4,252.50
17,338.98 15,605.08

2,840.00 2,556.00
1,712.00 1,540.80
3,400.00 3,060.00
1,000.00 900.00
500.00 450.00
3,600.00 3,240.00
600.00 540.00

9,221.36 8,299.22

940.60 846.54
940.60 846.54

940.61 846.55
940.61 846.55
940.61 846.55
940.61 846.55
169.48 152.53

940.61 846.55
940.61 846.55
940.61 846.55
1,110.11 999.10

15,348.97 13,814.07

4,725.00 4,252.50
6,864.41 6,177.97

2,840.00 2,556.00
1,712.00 1,540.80
3,400.00 3,060.00
1,000.00 900.00
500.00 450.00
3,600.00 3,240.00
600.00 540.00

4,564.96 4,108.46

940.60 846.54
940.60 846.54

940.61 846.55
940.61 846.55
940.61 846.55
940.61 846.55
169.48 152.53

940.61 846.55
940.61 846.55
940.61 846.55
1,110.11 999.10

15,348.97 13,814.07

4,725.00 4,252.50
7,372.78 6,635.50

2,839.85 2,555.87
1,712.00 1,540.80
3,400.00 3,060.00
1,000.00 900.00
500.00 450.00
3,600.00 3,240.00
600.00 540.00

4,564.96 4,108.46

5,121,687.340 4,609,518.606

408,710.650 367,839.585

358,518.114 322,666.302

==================

5,888,916.094 5,300,024.493

1,060,004.897 954,004.409

==================

6,948,921.00 6,254,028.90
ITEM DESCRIPCIÓN UNIDAD METRADO PU SUB TOTAL

01 LOCALIDAD SANTA LUCIA

01.01 CONSTRUCCIONES PROVISIONALES


OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y
01.01.01 m2 100.00 44.55 4,455.00
VESTUARIOS
ALQUILER DE PREDIOS PARA CAMPAMENTOS Y
01.01.02 mes 6.00 500.00 3,000.00
ALMACENES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m
01.01.03 und 1.00 1,539.82 1,539.82
x 7.20 m
01.02 CAPTACION TIPO LADERA (ROBLEMONTE)
01.02.01 TRABAJOS PRELIMINARES
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49 24.01
01.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
01.02.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO
01.02.02.01 m3 16.23 39.86 646.93
CONGLOMERADO
RELLENO Y COMPACTADO CON MATERIAL
01.02.02.02 m3 2.55 29.50 75.23
PROPIO A MANO C/PISON
01.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95 214.65
01.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 17.10 25.69 439.30
01.02.03 CONCRETO SIMPLE
01.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17 706.52
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48 117.43
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
01.02.03.03 m2 0.50 121.10 60.55
80% PM
01.02.04 CONCRETO ARMADO
01.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84 811.87
01.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48 797.53
01.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35 296.06
01.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTES
01.02.05.01 m2 5.53 32.48 179.61
M=1:3 e=1.5cm
01.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76 358.61
01.02.06 PINTURA
PINTURA ESMALTE 2 MANOS EN MUROS
01.02.06.01 m2 12.05 13.23 159.42
EXTERIORES
FILTRO DE GRAVA, ARENA Y MATERIAL
01.02.07
IMPERMEABLE
01.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85 265.53
01.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77 25.86
01.02.08 CARPINTERIA METALICA
01.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 179.83 179.83
01.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53 281.53
01.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.02.09.01 CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO und 1.00 501.29 501.29
HIDRAULICO y VENTILACION Ø=2")
01.02.10 CERCO PERIMETRICO EN CAPTACION
01.02.10.01 TRABAJOS PRELIMINARES
01.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84 44.16
01.02.10.02 MOVIMIENTO DE TIERRAS
01.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86 23.52
01.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
01.02.10.03 CONCRETO SIMPLE
01.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98 210.03
01.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
01.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
01.02.10.05 COLOCADO DE ROLLIZOS
01.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
01.02.10.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS
01.02.10.06.01 m 33.80 3.80 128.44
MANOS C/ESMALTE SINTETICO
SUM. E INST. MALLA GANADERA DE 12 HILOS
01.02.10.07
H=1.80m
01.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22 533.28
01.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
01.02.10.08.01 und 1.00 194.10 194.10
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
01.03 LINEA DE CONDUCCION (L=1102.00 m)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,102.00 0.49 539.98
01.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 1,102.00 1.53 1,686.06
TRAZO Y NIVELACION DURANTE LA EJECUCION
01.03.01.03 m 1,102.00 1.53 1,686.06
EN ZANJAS REDES Y LINEAS
01.03.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
01.03.02.01 m3 396.72 49.82 19,764.59
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
01.03.02.02 m3 44.08 55.80 2,459.66
ROCA SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
01.03.02.03 m 1,102.00 1.81 1,994.62
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA
01.03.02.04 m 110.20 6.08 670.02
SUELTA Y FIJA P/TUBERIA
RELLENO Y COMPACTADO DE ZANJAS CON
01.03.02.05 MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, m3 165.30 36.40 6,016.92
H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
01.03.02.06 MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" m3 27.55 65.17 1,795.43
P/TUBERIA, H=0.50 m
01.03.02.07 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 27.55 25.69 707.76
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.03.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SP
01.03.03.01 m 1,102.00 7.19 7,923.38
C-10, Ø=1"
01.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 140.33 140.33
01.03.04 PRUEBA HIDRAULICA
01.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 1,102.00 1.51 1,664.02
01.03.05 CAMARA ROMPE PRESION T-6 (01 UND)
01.03.05.01 OBRAS PRELIMINARES
01.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.44 0.49 0.71
01.03.05.01.02 TRAZO Y REPLANTEO m2 1.44 1.84 2.65
01.03.05.02 MOVIMIENTO DE TIERRAS
01.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.58 39.86 62.98
01.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.98 25.69 50.87
01.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 1.44 7.95 11.45
01.03.05.03 OBRAS DE CONCRETO SIMPLE
01.03.05.03.01 SOLADO E=4" m3 1.21 35.81 43.33
01.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13
01.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
01.03.05.03.04 m2 0.50 121.10 60.55
80% PM
01.03.05.04 OBRAS DE CONCRETO ARMADO
01.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 0.79 546.69 431.89
01.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.10 44.48 360.29
01.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 37.23 4.35 161.95
01.03.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.03.05.05.01 m2 2.52 32.48 81.85
MEZCLA 1:2 E=2 cm H=1.5 Max
01.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.24 29.76 96.42
01.03.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
01.03.05.06.01 m2 3.24 11.18 36.22
ESMALTE-2 MANOS
01.03.05.07 CARPINTERIA METALICA
01.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 1.00 213.73 213.73
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.03.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
01.03.05.08.01 und 1.00 299.60 299.60
EN CRP T6, INGRESO Ø=1" y SALIDA Ø=1"
01.03.06 VALVULA DE PURGA TIPO I (1 UND)
01.03.06.01 OBRAS PRELIMINARES
01.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 0.49 0.49
01.03.06.01.02 TRAZO Y REPLANTEO m2 1.00 1.84 1.84
01.03.06.02 MOVIMIENTO DE TIERRAS
01.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.51 39.86 20.33
RELLENO Y COMPACTADO CON MATERIAL
01.03.06.02.02 m3 0.51 13.11 6.69
PROPIO A MANO
01.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.49 7.95 3.90
01.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 0.64 25.69 16.44
01.03.06.03 OBRAS DE CONCRETO SIMPLE
01.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.02 413.17 8.26
01.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.24 44.48 10.68
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
01.03.06.03.03 m2 0.27 121.10 32.70
80% PM
01.03.06.04 OBRAS DE CONCRETO ARMADO
01.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.35 546.69 191.34
01.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.72 44.48 165.47
01.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 14.94 4.35 64.99
01.03.06.05 REVOQUES Y ENLUCIDOS
01.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 1.44 32.48 46.77
01.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.36 29.76 99.99
01.03.06.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
01.03.06.06.01 m2 2.16 11.18 24.15
ESMALTE-2 MANOS
01.03.06.07 CARPINTERIA METALICA
01.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 1.00 214.83 214.83
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.03.06.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
01.03.06.08.01 und 1.00 153.06 153.06
EN VALVULA DE PURGA TIPO I, Ø=1"
01.04 RESERVORIO (V=8.00 m3, 01 UND)
01.04.01 OBRAS PRELIMINARES
01.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49 17.64
01.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
01.04.02 MOVIMIENTO DE TIERRAS
01.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 51.43 39.86 2,050.00
01.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 11.41 7.95 90.71
01.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 64.29 25.69 1,651.61
01.04.03 CONCRETO SIMPLE
01.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13
01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
01.04.03.03 m2 0.50 121.10 60.55
80% PM
01.04.04 OBRAS DE CONCRETO ARMADO
01.04.04.01 SOLADO PARA LOSA FONDO m2 11.41 40.87 466.33
01.04.04.02 CONCRETO f'c=210 kg/cm2 m3 11.27 546.69 6,161.20
01.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 51.29 44.48 2,281.38
01.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 322.94 4.35 1,404.79
01.04.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.04.05.01 m2 31.32 32.48 1,017.27
MEZCLA 1:2 E=2 cm H=1.5 Max
01.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 40.61 29.76 1,208.55
01.04.06 PINTURA
PINTURA ESMALTE EN MUROS EXTERIORES DE
01.04.06.01 m2 34.92 13.23 461.99
RESERVORIO
01.04.07 CARPINTERIA METALICA
01.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.04.08
ACCESORIOS
SUMINISTRO E INSTALACIONES DE ACCESORIOS
01.04.08.01 und 1.00 1,745.47 1,745.47
EN RESERVORIO (ING. 1 ", SAL.1")
01.04.09 CERCO PERIMETRICO EN RESERVORIO
01.04.09.01 TRABAJOS PRELIMINARES
01.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84 66.24
01.04.09.02 MOVIMIENTO DE TIERRAS
01.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86 27.90
01.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
01.04.09.03 CONCRETO SIMPLE
01.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98 249.19
01.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
01.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
01.04.09.05 COLOCADO DE ROLLIZOS
01.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
01.04.09.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS
01.04.09.06.01 m 66.40 3.80 252.32
MANOS C/ESMALTE SINTETICO
SUM. E INST. MALLA GANADERA DE 12 HILOS
01.04.09.07
H=1.80m
01.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22 515.50
01.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
01.04.09.08.01 und 1.00 194.10 194.10
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
01.04.10 CLORADOR POR GOTEO
01.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
CASETA DE MURO DE LADRILLO -CLORADOR
01.04.10.01.01
POR GOTEO
MURO DE LADRILLO PANDERETA
01.04.10.01.01.01 (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA m2 7.52 54.96 413.30
1.5 cm.
MURO DE LADRILLO PANDERETA
01.04.10.01.01.02 INTERCALADO(0.10x0.12x0.24) AMARRE SOGA m2 4.48 49.36 221.13
MORTERO 1:5 JUNTA 1.5 cm.
01.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
01.04.10.01.02.01 CORREAS DE MADERA DE 2" x 2" m 6.00 29.07 174.42
COBERTURA CON CALAMINA
01.04.10.01.02.02 m2 5.98 34.08 203.80

01.04.10.01.03 REVOQUES Y ENLUCIDOS


TARRAJEO MUROS DE INTERIORES Y
01.04.10.01.03.01 m2 14.98 30.00 449.40
EXTERIORES, CEMENTO : ARENA, 1:5
DERRAME EN PUERTAS h =0.10 m, C:A 1:2,
01.04.10.01.03.02 m 4.00 13.78 55.12
e=2.0 cm
01.04.10.01.04 CARPINTERIA METALICA
SUMINISTRO E INSTALACION DE PUERTA
01.04.10.01.04.01 und 1.00 367.18 367.18
METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO
01.04.10.01.05 PINTURAS
PINTURA ESMALTE EN MUROS INTERIORES Y
01.04.10.01.05.01 m2 14.98 11.18 167.48
EXTERIORES
PINTURA ANTICORROSIVA Y ESMALTE EN
01.04.10.01.05.02 m2 4.00 12.25 49.00
PUERTAS
TANQUE DE AGUA 250 LTRS, INCLUYE ACC.
01.04.10.02
INTERNOS
SUMINISTRO E INSTALACION DE TANQUE DE
01.04.10.02.01 und 1.00 435.06 435.06
POLIETILENO, CAP=250 LTRS.
01.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
SUMINISTRO Y COLOCACION DE TUBERIAS Y
01.04.10.03.01 ACCESORIOS EN SISTEMA DE CLORACION POR GLB 1.00 939.22 939.22
GOTEO
01.05 RED DE ADUCCION Y DISTRIBUCION (L=4,375.00m)
01.05.01 TRABAJOS PRELIMINARES
01.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,187.50 0.49 1,071.88
01.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 4,375.00 1.53 6,693.75
TRAZO Y NIVELACION DURANTE LA EJECUCION
01.05.01.03 m 4,375.00 1.53 6,693.75
EN ZANJAS REDES Y LINEAS
01.05.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
01.05.02.01 m3 525.00 39.86 20,926.50
SUELTO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
01.05.02.02 m3 1,137.50 49.82 56,670.25
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
01.05.02.03 m3 87.50 55.80 4,882.50
ROCA SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
01.05.02.04 m 4,375.00 1.81 7,918.75
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA
01.05.02.05 m 4,375.00 6.08 26,600.00
SUELTA Y FIJA P/TUBERIA
RELLENO Y COMPACTADO DE ZANJAS CON
01.05.02.06 MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, m3 623.44 36.40 22,693.22
H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
01.05.02.07 MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" m3 32.81 65.17 2,138.23
P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
01.05.02.08 m3 1,181.25 25.07 29,613.94
MATERIAL PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON
01.05.02.09 m3 142.19 62.16 8,838.53
MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m
01.05.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 87.50 25.69 2,247.88
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC
01.05.03.01 m 1,820.00 8.05 14,651.00
SAP C-10 DE 1"
SUMINISTRO E INSTALACION DE TUBERIA PVC
01.05.03.02 m 2,555.00 4.84 12,366.20
SAP C-10 DE 3/4"
01.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 137.74 137.74
01.05.04 PRUEBA HIDRAULICA
01.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 4,375.00 1.51 6,606.25
01.05.05 CAMARA ROMPE PRESION T-7 (11 UND)
01.05.05.01 OBRAS PRELIMINARES
01.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 22.77 0.49 11.16
01.05.05.01.02 TRAZO Y REPLANTEO m2 22.77 1.84 41.90
01.05.05.02 MOVIMIENTO DE TIERRAS
01.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 14.32 39.86 570.80
01.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 9.55 40.95 391.07
RELLENO Y COMPACTADO CON MATERIAL
01.05.05.02.03 m3 2.39 13.11 31.33
PROPIO A MANO
01.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 21.62 7.95 171.88
01.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.28 59.44 76.08
01.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 9.84 25.69 252.79
01.05.05.03 OBRAS DE CONCRETO SIMPLE
01.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.13 413.17 53.71
01.05.05.03.02 SOLADO E=4" m3 1.82 35.81 65.17
01.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.20 44.48 97.86
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
01.05.05.03.04 m2 2.97 121.10 359.67
80% PM
01.05.05.04 OBRAS DE CONCRETO ARMADO
01.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 14.96 546.69 8,178.48
01.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 153.14 44.48 6,811.67
01.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,164.62 4.35 9,416.10
01.05.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.05.05.05.01 m2 47.52 32.48 1,543.45
MEZCLA 1:2 E=2 cm H=1.5 Max
01.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 102.98 29.76 3,064.68
01.05.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
01.05.05.06.01 m2 66.00 11.18 737.88
ESMALTE-2 MANOS
01.05.05.07 CARPINTERIA METALICA
01.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 11.00 179.83 1,978.13
01.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 11.00 213.73 2,351.03
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
01.05.05.08.01 und 7.00 384.08 2,688.56
EN CRP T7, INGRESO Y SALIDA Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS
01.05.05.08.02 und 5.00 379.18 1,895.90
EN CRP T7, INGRESO Y SALIDA Ø=3/4"
01.05.06 VALVULA DE CONTROL (05 UND)
01.05.06.01 OBRAS PRELIMINARES
01.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49 2.45
01.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.84 9.20
01.05.06.02 MOVIMIENTO DE TIERRAS
01.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 39.86 199.30
01.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 25.69 160.56
01.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.95 39.75
01.05.06.03 OBRAS DE CONCRETO ARMADO
01.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 546.69 1,350.32
01.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 44.48 947.42
01.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.35 668.94
01.05.06.04 REVOQUES Y ENLUCIDOS
01.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 32.48 233.86
01.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 29.76 321.41
01.05.06.05 PINTURA
PINTURA EN MUROS EXTERIORES CON
01.05.06.05.01 m2 6.48 11.18 72.45
ESMALTE-2 MANOS
01.05.06.06 CARPINTERIA METALICA
01.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 162.88 814.40
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.06.07
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
01.05.06.07.01 und 1.00 90.28 90.28
EN VALVULA DE CONTROL, Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS
01.05.06.07.02 und 4.00 79.02 316.08
EN VALVULA DE CONTROL, Ø=3/4"
01.05.07 VALVULA DE PURGA TIPO II (08 UND)
01.05.07.01 OBRAS PRELIMINARES
01.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.00 0.49 3.92
01.05.07.01.02 TRAZO Y REPLANTEO m2 8.00 1.84 14.72
01.05.07.02 MOVIMIENTO DE TIERRAS
01.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 12.23 39.86 487.49
EXCAVACION MANUAL EN TERRENO ROCA
01.05.07.02.02 m3 4.08 49.82 203.27
SUELTA
RELLENO Y COMPACTADO CON MATERIAL
01.05.07.02.03 m3 4.08 13.11 53.49
PROPIO A MANO
01.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 3.92 7.95 31.16
01.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.92 25.69 100.70
01.05.07.03 OBRAS DE CONCRETO SIMPLE
01.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 2.45 413.17 1,012.27
01.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.92 44.48 85.40
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
01.05.07.03.03 m2 1.02 121.10 123.52
80% PM
01.05.07.04 OBRAS DE CONCRETO ARMADO
01.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 2.80 546.69 1,530.73
01.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 29.76 44.48 1,323.72
01.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 119.53 4.35 519.96
01.05.07.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.05.07.05.01 m2 11.52 32.48 374.17
MEZCLA 1:2 E=2 cm H=1.5 Max
01.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 26.88 29.76 799.95
01.05.07.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
01.05.07.06.01 m2 12.96 11.18 144.89
ESMALTE-2 MANOS
01.05.07.07 CARPINTERIA METALICA
MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN.
01.05.07.07.01 und 8.00 213.73 1,709.84
DE 0.60x0.40m.
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.07.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
01.05.07.08.01 EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA und 1.00 149.25 149.25
Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS
01.05.07.08.02 EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA und 7.00 132.94 930.58
Ø=3/4"
01.05.08 CONEXIONES DOMICILIARIAS (92 UND)
01.05.08.01 OBRAS PRELIMINARES
01.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 824.32 0.49 403.92
01.05.08.01.02 TRAZO Y REPLANTEO m2 1,236.48 1.84 2,275.12
01.05.08.02 MOVIMIENTO DE TIERRAS
EXCAVACION A MANO DE ZANJA MANUAL
01.05.08.02.01 m3 989.18 39.86 39,428.71
TERRENO NORMAL
RELLENO Y COMPACTADO DE ZANJAS CON
01.05.08.02.02 m3 989.18 33.00 32,642.94
MATERIAL PROPIO CLASIFICADO
SUMINISTRO Y COLOCACION DE GRAVA
01.05.08.02.03 m3 103.04 209.11 21,546.69
SELECCIONADA
01.05.08.03 OBRAS DE CONCRETO SIMPLE
01.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 6.82 413.17 2,817.82
01.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 34.04 44.48 1,514.10
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.08.04
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
01.05.08.04.01 und 92.00 80.77 7,430.84
EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND)
TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m
01.05.08.04.02 und 92.00 155.21 14,279.32
CON LLAVE TIPO BUJIA
SUMINISTRO E INSTALACIONES DE ACOMETIDA
01.05.08.04.03 m 736.00 3.50 2,576.00
DOMICILIARIA RANGO 2 - 50 M.
02 LOCALIDAD PUEBLO LIBRE
02.01 CONSTRUCCIONES PROVISIONALES
OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y
02.01.01 m2 100.00 44.55 4,455.00
VESTUARIOS
ALQUILER DE PREDIOS PARA CAMPAMENTOS Y
02.01.02 mes 6.00 500.00 3,000.00
ALMACENES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m
02.01.03 und 1.00 1,539.82 1,539.82
x 7.20 m
02.02 CAPTACION TIPO LADERA (YACUPACCARI)
02.02.01 TRABAJOS PRELIMINARES
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49 24.01
02.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
02.02.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO
02.02.02.01 m3 22.53 39.86 898.05
CONGLOMERADO
RELLENO Y COMPACTADO CON MATERIAL
02.02.02.02 m3 2.55 29.50 75.23
PROPIO A MANO C/PISON
02.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95 214.65
02.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 25.05 25.69 643.53
02.02.03 CONCRETO SIMPLE
02.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17 706.52
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48 117.43
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
02.02.03.03 m2 0.50 121.10 60.55
80% PM
02.02.04 CONCRETO ARMADO
02.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84 811.87
02.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48 797.53
02.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35 296.06
02.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTES
02.02.05.01 m2 5.53 32.48 179.61
M=1:3 e=1.5cm
02.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76 358.61
02.02.06 PINTURA
PINTURA ESMALTE 2 MANOS EN MUROS
02.02.06.01 m2 12.05 13.23 159.42
EXTERIORES
FILTRO DE GRAVA, ARENA Y MATERIAL
02.02.07
IMPERMEABLE
02.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85 265.53
02.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77 25.86
02.02.08 CARPINTERIA METALICA
02.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 180.93 180.93
02.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53 281.53
02.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.02.09.01 CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO und 1.00 501.29 501.29
HIDRAULICO y VENTILACION Ø=2"
02.02.10 CERCO PERIMETRICO EN CAPTACION
02.02.10.01 TRABAJOS PRELIMINARES
02.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84 44.16
02.02.10.02 MOVIMIENTO DE TIERRAS
02.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86 23.52
02.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
02.02.10.03 CONCRETO SIMPLE
02.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98 210.03
02.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
02.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
02.02.10.05 COLOCADO DE ROLLIZOS
02.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
02.02.10.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS
02.02.10.06.01 m 33.80 3.80 128.44
MANOS C/ESMALTE SINTETICO
SUM. E INST. MALLA GANADERA DE 12 HILOS
02.02.10.07
H=1.80m
02.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22 533.28
02.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
02.02.10.08.01 und 1.00 194.10 194.10
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
02.03 CRUCE AEREO DE L=6.00 ML. (01 UNIDAD)
02.03.01 OBRAS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 22.40 0.49 10.98
02.03.01.02 TRAZO Y REPLANTEO m2 22.40 1.84 41.22
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION A MANO TERRENO NORMAL m3 2.57 39.86 102.44
02.03.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.21 25.69 82.46
02.03.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 3.28 7.95 26.08
02.03.03 OBRAS DE CONCRETO SIMPLE
02.03.03.01 CONCRETO F'C=100 KG/CM2.PARA SOLADOS m3 0.13 403.78 52.49
02.03.04 OBRAS DE CONCRETO ARMADO
02.03.04.01 CONCRETO FC=210 KG/CM2 m3 2.72 466.07 1,267.71
02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.50 44.48 111.20
02.03.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 40.12 4.35 174.52
02.03.05 REVOQUES Y ENLUCIDOS
02.03.05.01 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 2.50 29.76 74.40
02.03.06 PINTURA
PINTURA ESMALTE 2 MANOS EN MUROS
02.03.06.01 m2 2.50 19.51 48.78
EXTERIORES
02.03.07 TUBERIA TN ISO 65 SERIE LIVIANA (L)
SUMINISTRO E INSTALACION DE TUBERIA TN ISO
02.03.07.01 m 11.70 312.13 3,651.92
65 Ø 1"
02.03.08 CABLE DE ACERO PRINCIPAL Ø 3/8" TIPO BOA
02.03.08.01 TENDIDO DE CABLE PRINCIPAL TIPO BOA Ø 3/8 m 7.86 37.33 293.41
02.03.09 PENDOLAS
02.03.09.01 PENDOLAS CON F° LISO Ø 1/4" m 14.40 35.37 509.33
02.03.10 ACCESORIOS
ACCESORIOS PARA ACUEDUCTO COLGANTE,
02.03.10.01 und 1.00 934.94 934.94
ARGOLLA Ø 1", L=6.00ml
02.04 LINEA DE CONDUCCION (L=2153.00 m)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,153.00 0.49 1,054.97
02.04.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 2,153.00 1.53 3,294.09
TRAZO Y NIVELACION DURANTE LA EJECUCION
02.04.01.03 m 2,153.00 1.53 3,294.09
EN ZANJAS REDES Y LINEAS
02.04.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
02.04.02.01 m3 86.12 39.86 3,432.74
SUELTO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
02.04.02.02 m3 775.08 49.82 38,614.49
CONGLOMERADO
REFINE Y NIVELACION DE ZANJA EN TERRENO
02.04.02.03 m 2,153.00 1.81 3,896.93
NORMAL P/TUBERIA
02.04.02.04 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 2,153.00 4.28 9,214.84
RELLENO Y COMPACTADO DE ZANJAS CON
02.04.02.05 MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, m3 322.95 36.40 11,755.38
H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
02.04.02.06 m3 538.25 25.07 13,493.93
MATERIAL PROPIO P/TUBERIA, H=0.50 m
02.04.02.07 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 26.91 25.69 691.32
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.04.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC
02.04.03.01 m 2,153.00 5.94 12,788.82
SAP C-10 DE 1"
02.04.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 215.53 215.53
02.04.04 PRUEBA HIDRAULICA
02.04.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 2,153.00 1.51 3,251.03
02.04.05 CAMARA ROMPE PRESION T-6 (06 UND)
02.04.05.01 OBRAS PRELIMINARES
02.04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.64 0.49 4.23
02.04.05.01.02 TRAZO Y REPLANTEO m2 8.64 1.84 15.90
02.04.05.02 MOVIMIENTO DE TIERRAS
02.04.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 9.50 39.86 378.67
02.04.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.88 25.69 305.20
02.04.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 8.64 7.95 68.69
02.04.05.03 OBRAS DE CONCRETO SIMPLE
02.04.05.03.01 SOLADO E=4" m3 7.26 35.81 259.98
02.04.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.07 413.17 28.92
02.04.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 44.48 53.38
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
02.04.05.03.04 m2 3.00 121.10 363.30
80% PM
02.04.05.04 OBRAS DE CONCRETO ARMADO
02.04.05.04.01 CONCRETO f'c=210 kg/cm2 m3 4.74 546.69 2,591.31
02.04.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 48.60 44.48 2,161.73
02.04.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 223.37 4.35 971.66
02.04.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.04.05.05.01 m2 15.12 32.48 491.10
MEZCLA 1:2 E=2 cm H=1.5 Max
02.04.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 19.44 29.76 578.53
02.04.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
02.04.05.06.01 m2 19.44 11.18 217.34
ESMALTE-2 MANOS
02.04.05.07 CARPINTERIA METALICA
02.04.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 6.00 213.73 1,282.38
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.04.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
02.04.05.08.01 und 6.00 299.60 1,797.60
EN CRP T6, INGRESO Ø=1 1/2" y SALIDA Ø=1 1/2"
02.04.06 VALVULA DE PURGA TIPO I (2 UND)
02.04.06.01 OBRAS PRELIMINARES
02.04.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.00 0.49 0.98
02.04.06.01.02 TRAZO Y REPLANTEO m2 2.00 1.84 3.68
02.04.06.02 MOVIMIENTO DE TIERRAS
02.04.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.02 39.86 40.66
RELLENO Y COMPACTADO CON MATERIAL
02.04.06.02.02 m3 1.02 13.11 13.37
PROPIO A MANO
02.04.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.98 7.95 7.79
02.04.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1.27 25.69 32.63
02.04.06.03 OBRAS DE CONCRETO SIMPLE
02.04.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.04 413.17 16.53
02.04.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.48 44.48 21.35
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
02.04.06.03.03 m2 0.54 121.10 65.39
80% PM
02.04.06.04 OBRAS DE CONCRETO ARMADO
02.04.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.70 546.69 382.68
02.04.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.44 44.48 330.93
02.04.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 29.88 4.35 129.98
02.04.06.05 REVOQUES Y ENLUCIDOS
02.04.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 2.88 32.48 93.54
02.04.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.72 29.76 199.99
02.04.06.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
02.04.06.06.01 m2 4.32 11.18 48.30
ESMALTE-2 MANOS
02.04.06.07 CARPINTERIA METALICA
02.04.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 2.00 214.83 429.66
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.04.06.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
02.04.06.08.01 und 2.00 153.06 306.12
EN VALVULA DE PURGA TIPO I, Ø=1 1/2"
02.05 RESERVORIO (V=10.00 m3, 01 UND)
02.05.01 OBRAS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49 17.64
02.05.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 79.30 39.86 3,160.90
02.05.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 11.41 7.95 90.71
02.05.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 99.13 25.69 2,546.65
02.05.03 CONCRETO SIMPLE
02.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13
02.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
02.05.03.03 m2 0.50 121.10 60.55
80% PM
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 SOLADO PARA LOSA FONDO m2 11.41 40.87 466.33
02.05.04.02 CONCRETO f'c=210 kg/cm2 m3 13.50 546.69 7,380.32
02.05.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 57.48 44.48 2,556.71
02.05.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 349.49 4.35 1,520.28
02.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.05.05.01 m2 32.94 32.48 1,069.89
MEZCLA 1:2 E=2 cm H=1.5 Max
02.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 57.14 29.76 1,700.49
02.05.06 PINTURA
PINTURA ESMALTE EN MUROS EXTERIORES DE
02.05.06.01 m2 51.45 13.23 680.68
RESERVORIO
02.05.07 CARPINTERIA METALICA
02.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.05.08
ACCESORIOS
SUMINISTRO E INSTALACIONES DE ACCESORIOS
02.05.08.01 und 1.00 1,745.47 1,745.47
EN RESERVORIO (ING. 1", SAL.1")
02.05.09 CERCO PERIMETRICO EN RESERVORIO
02.05.09.01 TRABAJOS PRELIMINARES
02.05.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84 66.24
02.05.09.02 MOVIMIENTO DE TIERRAS
02.05.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86 27.90
02.05.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
02.05.09.03 CONCRETO SIMPLE
02.05.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98 249.19
02.05.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
02.05.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
02.05.09.05 COLOCADO DE ROLLIZOS
02.05.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
02.05.09.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS
02.05.09.06.01 m 66.40 3.80 252.32
MANOS C/ESMALTE SINTETICO
SUM. E INST. MALLA GANADERA DE 12 HILOS
02.05.09.07
H=1.80m
02.05.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22 515.50
02.05.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
02.05.09.08.01 und 1.00 194.10 194.10
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
02.05.10 CLORADOR POR GOTEO
02.05.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
CASETA DE MURO DE LADRILLO -CLORADOR
02.05.10.01.01
POR GOTEO
MURO DE LADRILLO PANDERETA
02.05.10.01.01.01 (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA m2 7.52 54.96 413.30
1.5 cm.
MURO DE LADRILLO PANDERETA
02.05.10.01.01.02 INTERCALADO(0.10x0.12x0.24) AMARRE SOGA m2 4.48 49.36 221.13
MORTERO 1:5 JUNTA 1.5 cm.
02.05.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
02.05.10.01.02.01 CORREAS DE MADERA DE 2" x 2" m 6.00 29.07 174.42
COBERTURA CON CALAMINA
02.05.10.01.02.02 m2 5.98 34.08 203.80

02.05.10.01.03 REVOQUES Y ENLUCIDOS


TARRAJEO MUROS DE INTERIORES Y
02.05.10.01.03.01 m2 14.98 30.00 449.40
EXTERIORES, CEMENTO : ARENA, 1:5
DERRAME EN PUERTAS h =0.10 m, C:A 1:2,
02.05.10.01.03.02 m 4.00 13.78 55.12
e=2.0 cm
02.05.10.01.04 CARPINTERIA METALICA
SUMINISTRO E INSTALACION DE PUERTA
02.05.10.01.04.01 und 1.00 367.18 367.18
METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO
02.05.10.01.05 PINTURAS
PINTURA ESMALTE EN MUROS INTERIORES Y
02.05.10.01.05.01 m2 14.98 11.18 167.48
EXTERIORES
PINTURA ANTICORROSIVA Y ESMALTE EN
02.05.10.01.05.02 m2 4.00 12.25 49.00
PUERTAS
TANQUE DE AGUA 250 LTRS, INCLUYE ACC.
02.05.10.02
INTERNOS
SUMINISTRO E INSTALACION DE TANQUE DE
02.05.10.02.01 und 1.00 435.06 435.06
POLIETILENO, CAP=250 LTRS.
02.05.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
SUMINISTRO Y COLOCACION DE TUBERIAS Y
02.05.10.03.01 ACCESORIOS EN SISTEMA DE CLORACION POR GLB 1.00 939.22 939.22
GOTEO
02.06 RED DE ADUCCION Y DISTRIBUCION (L=5,678.00 m)
02.06.01 TRABAJOS PRELIMINARES
02.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,839.00 0.49 1,391.11
02.06.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 5,678.00 1.53 8,687.34
TRAZO Y NIVELACION DURANTE LA EJECUCION
02.06.01.03 m 5,678.00 1.53 8,687.34
EN ZANJAS REDES Y LINEAS
02.06.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
02.06.02.01 m3 1,362.72 49.82 67,890.71
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
02.06.02.02 m3 908.48 55.80 50,693.18
ROCA SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
02.06.02.03 m 5,678.00 1.81 10,277.18
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA
02.06.02.04 m 2,271.20 6.08 13,808.90
SUELTA Y FIJA P/TUBERIA
RELLENO Y COMPACTADO DE ZANJAS CON
02.06.02.05 MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, m3 511.02 36.40 18,601.13
H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
02.06.02.06 MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" m3 567.80 65.17 37,003.53
P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
02.06.02.07 m3 1,987.30 25.07 49,821.61
MATERIAL PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON
02.06.02.08 m3 1,135.60 62.16 70,588.90
MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m
02.06.02.09 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 567.80 25.69 14,586.78
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC
02.06.03.01 m 1,146.00 8.05 9,225.30
SAP C-10 DE 1"
SUMINISTRO E INSTALACION DE TUBERIA PVC
02.06.03.02 m 4,533.00 4.84 21,939.72
SAP C-10 DE 3/4"
02.06.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 351.43 351.43
02.06.04 PRUEBA HIDRAULICA
02.06.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 5,678.00 1.51 8,573.78
02.06.05 CAMARA ROMPE PRESION T-7 (16 UND)
02.06.05.01 OBRAS PRELIMINARES
02.06.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 33.12 0.49 16.23
02.06.05.01.02 TRAZO Y REPLANTEO m2 33.12 1.84 60.94
02.06.05.02 MOVIMIENTO DE TIERRAS
02.06.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 22.91 39.86 913.19
02.06.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 15.27 40.95 625.31
RELLENO Y COMPACTADO CON MATERIAL
02.06.05.02.03 m3 3.82 13.11 50.08
PROPIO A MANO
02.06.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 31.44 7.95 249.95
02.06.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.86 59.44 110.56
02.06.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 22.91 25.69 588.56
02.06.05.03 OBRAS DE CONCRETO SIMPLE
02.06.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.19 413.17 78.50
02.06.05.03.02 SOLADO E=4" m3 2.64 35.81 94.54
02.06.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.20 44.48 142.34
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
02.06.05.03.04 m2 4.32 121.10 523.15
80% PM
02.06.05.04 OBRAS DE CONCRETO ARMADO
02.06.05.04.01 CONCRETO f'c=210 kg/cm2 m3 21.74 546.69 11,885.04
02.06.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 222.76 44.48 9,908.36
02.06.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 3,148.54 4.35 13,696.15
02.06.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.06.05.05.01 m2 69.12 32.48 2,245.02
MEZCLA 1:2 E=2 cm H=1.5 Max
02.06.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 149.79 29.76 4,457.75
02.06.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
02.06.05.06.01 m2 96.00 11.18 1,073.28
ESMALTE-2 MANOS
02.06.05.07 CARPINTERIA METALICA
02.06.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 16.00 179.83 2,877.28
02.06.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 16.00 213.73 3,419.68
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
02.06.05.08.01 und 3.00 384.08 1,152.24
EN CRP T7, INGRESO Y SALIDA Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS
02.06.05.08.02 und 13.00 379.18 4,929.34
EN CRP T7, INGRESO Y SALIDA Ø=3/4"
02.06.06 VALVULA DE CONTROL (05 UND)
02.06.06.01 OBRAS PRELIMINARES
02.06.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.00 0.49 2.94
02.06.06.01.02 TRAZO Y REPLANTEO m2 6.00 1.84 11.04
02.06.06.02 MOVIMIENTO DE TIERRAS
02.06.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 6.00 39.86 239.16
02.06.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 7.50 25.69 192.68
02.06.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 6.00 7.95 47.70
02.06.06.03 OBRAS DE CONCRETO ARMADO
02.06.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.96 546.69 1,618.20
02.06.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 25.56 44.48 1,136.91
02.06.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 184.53 4.35 802.71
02.06.06.04 REVOQUES Y ENLUCIDOS
02.06.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 8.64 32.48 280.63
02.06.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 12.96 29.76 385.69
02.06.06.05 PINTURA
PINTURA EN MUROS EXTERIORES CON
02.06.06.05.01 m2 12.96 11.18 144.89
ESMALTE-2 MANOS
02.06.06.06 CARPINTERIA METALICA
02.06.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 6.00 162.88 977.28
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.06.07
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
02.06.06.07.01 und 2.00 90.28 180.56
EN VALVULA DE CONTROL, Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS
02.06.06.07.02 und 4.00 79.02 316.08
EN VALVULA DE CONTROL, Ø=3/4"
02.06.07 VALVULA DE PURGA TIPO II (03 UND)
02.06.07.01 OBRAS PRELIMINARES
02.06.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 3.00 0.49 1.47
02.06.07.01.02 TRAZO Y REPLANTEO m2 3.00 1.84 5.52
02.06.07.02 MOVIMIENTO DE TIERRAS
02.06.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 4.59 39.86 182.96
EXCAVACION MANUAL EN TERRENO ROCA
02.06.07.02.02 m3 1.53 49.82 76.22
SUELTA
RELLENO Y COMPACTADO CON MATERIAL
02.06.07.02.03 m3 1.53 13.11 20.06
PROPIO A MANO
02.06.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 1.47 7.95 11.69
02.06.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.47 25.69 37.76
02.06.07.03 OBRAS DE CONCRETO SIMPLE
02.06.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.92 413.17 380.12
02.06.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.72 44.48 32.03
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
02.06.07.03.03 m2 0.38 121.10 46.02
80% PM
02.06.07.04 OBRAS DE CONCRETO ARMADO
02.06.07.04.01 CONCRETO f'c=210 kg/cm2 m3 1.05 546.69 574.02
02.06.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 11.16 44.48 496.40
02.06.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 44.82 4.35 194.97
02.06.07.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.06.07.05.01 m2 4.32 32.48 140.31
MEZCLA 1:2 E=2 cm H=1.5 Max
02.06.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.08 29.76 299.98
02.06.07.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
02.06.07.06.01 m2 4.84 11.18 54.11
ESMALTE-2 MANOS
02.06.07.07 CARPINTERIA METALICA
MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN.
02.06.07.07.01 und 3.00 213.73 641.19
DE 0.60x0.40m.
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.07.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
02.06.07.08.01 EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA und 3.00 132.94 398.82
Ø=3/4"
02.06.08 CONEXIONES DOMICILIARIAS (125 UND)
02.06.08.01 OBRAS PRELIMINARES
02.06.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,120.00 0.49 548.80
02.06.08.01.02 TRAZO Y REPLANTEO m2 1,680.00 1.84 3,091.20
02.06.08.02 MOVIMIENTO DE TIERRAS
EXCAVACION A MANO DE ZANJA MANUAL
02.06.08.02.01 m3 1,344.00 39.86 53,571.84
TERRENO NORMAL
RELLENO Y COMPACTADO DE ZANJAS CON
02.06.08.02.02 m3 1,344.00 33.00 44,352.00
MATERIAL PROPIO CLASIFICADO
SUMINISTRO Y COLOCACION DE GRAVA
02.06.08.02.03 m3 140.00 209.11 29,275.40
SELECCIONADA
02.06.08.03 OBRAS DE CONCRETO SIMPLE
02.06.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 9.27 413.17 3,830.09
02.06.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 46.25 44.48 2,057.20
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.08.04
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
02.06.08.04.01 und 125.00 80.77 10,096.25
EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND)
TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m
02.06.08.04.02 und 125.00 155.21 19,401.25
CON LLAVE TIPO BUJIA
SUMINISTRO E INSTALACIONES DE ACOMETIDA
02.06.08.04.03 m 1,125.00 3.50 3,937.50
DOMICILIARIA RANGO 2 - 20 M.
03 LOCALIDAD TANCARPATA
03.01 CONSTRUCCIONES PROVISIONALES
OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y
03.01.01 m2 100.00 44.55 4,455.00
VESTUARIOS
ALQUILER DE PREDIOS PARA CAMPAMENTOS Y
03.01.02 mes 6.00 500.00 3,000.00
ALMACENES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m
03.01.03 und 1.00 1,539.82 1,539.82
x 7.20 m
03.02 CAPTACION A TIPO LADERA YACUTOCCYAC (01 UND)
03.02.01 TRABAJOS PRELIMINARES
03.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49 24.01
03.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
03.02.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO
03.02.02.01 m3 15.03 39.86 599.10
CONGLOMERADO
RELLENO Y COMPACTADO CON MATERIAL
03.02.02.02 m3 2.55 29.50 75.23
PROPIO A MANO C/PISON
03.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95 214.65
03.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.60 25.69 400.76
03.02.03 CONCRETO SIMPLE
03.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17 706.52
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48 117.43
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
03.02.03.03 m2 0.50 121.10 60.55
80% PM
03.02.04 CONCRETO ARMADO
03.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84 811.87
03.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48 797.53
03.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35 296.06
03.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTES
03.02.05.01 m2 5.53 32.48 179.61
M=1:3 e=1.5cm
03.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76 358.61
03.02.06 PINTURA
PINTURA ESMALTE 2 MANOS EN MUROS
03.02.06.01 m2 12.05 13.23 159.42
EXTERIORES
FILTRO DE GRAVA, ARENA Y MATERIAL
03.02.07
IMPERMEABLE
03.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85 265.53
03.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77 25.86
03.02.08 CARPINTERIA METALICA
03.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 180.93 180.93
03.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53 281.53
03.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.02.09.01 CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO und 1.00 497.69 497.69
HIDRAULICO y VENTILACION Ø=2")
03.02.10 CERCO PERIMETRICO EN CAPTACION
03.02.10.01 TRABAJOS PRELIMINARES
03.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84 44.16
03.02.10.02 MOVIMIENTO DE TIERRAS
03.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86 23.52
03.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
03.02.10.03 CONCRETO SIMPLE
03.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98 210.03
03.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
03.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
03.02.10.05 COLOCADO DE ROLLIZOS
03.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
03.02.10.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS
03.02.10.06.01 m 33.80 3.80 128.44
MANOS C/ESMALTE SINTETICO
SUM. E INST. MALLA GANADERA DE 12 HILOS
03.02.10.07
H=1.80m
03.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22 533.28
03.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
03.02.10.08.01 und 1.00 194.10 194.10
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
03.03 LINEA DE CONDUCCION (L=196.00 m)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 196.00 0.49 96.04
03.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 196.00 1.53 299.88
TRAZO Y NIVELACION DURANTE LA EJECUCION
03.03.01.03 m 196.00 1.53 299.88
EN ZANJAS REDES Y LINEAS
03.03.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
03.03.02.01 m3 72.13 49.82 3,593.52
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
03.03.02.02 m3 6.27 55.80 349.87
ROCA SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
03.03.02.03 m 196.00 1.81 354.76
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA
03.03.02.04 m 196.00 6.08 1,191.68
SUELTA Y FIJA P/TUBERIA
03.03.02.05 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 196.00 4.28 838.88
RELLENO Y COMPACTADO DE ZANJAS CON
03.03.02.06 MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, m3 27.05 36.40 984.62
H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
03.03.02.07 MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" m3 2.35 65.17 153.15
P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
03.03.02.08 m3 45.05 25.07 1,129.40
MATERIAL PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON
03.03.02.09 m3 3.92 62.16 243.67
MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m
03.03.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.92 25.69 100.70
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.03.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC
03.03.03.01 m 196.00 5.94 1,164.24
SAP C-10 DE 1"
03.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 160.91 160.91
03.03.04 PRUEBA HIDRAULICA
03.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 180.36 1.51 272.34
03.03.05 CAMARA ROMPE PRESION T-6 (01 UND)
03.03.05.01 OBRAS PRELIMINARES
03.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.44 0.49 0.71
03.03.05.01.02 TRAZO Y REPLANTEO m2 1.44 1.84 2.65
03.03.05.02 MOVIMIENTO DE TIERRAS
03.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.58 39.86 62.98
03.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.98 25.69 50.87
03.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 1.44 7.95 11.45
03.03.05.03 OBRAS DE CONCRETO SIMPLE
03.03.05.03.01 SOLADO E=4" m3 1.21 35.81 43.33
03.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13
03.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
03.03.05.03.04 m2 0.50 121.10 60.55
80% PM
03.03.05.04 OBRAS DE CONCRETO ARMADO
03.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 0.79 546.69 431.89
03.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.10 44.48 360.29
03.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 37.23 4.35 161.95
03.03.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.03.05.05.01 m2 2.52 32.48 81.85
MEZCLA 1:2 E=2 cm H=1.5 Max
03.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.24 29.76 96.42
03.03.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
03.03.05.06.01 m2 3.24 11.18 36.22
ESMALTE-2 MANOS
03.03.05.07 CARPINTERIA METALICA
03.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 1.00 213.73 213.73
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.03.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
03.03.05.08.01 und 1.00 299.60 299.60
EN CRP T6, INGRESO Ø=1 y SALIDA Ø=1 "
03.03.06 VALVULA DE PURGA TIPO I (1 UND)
03.03.06.01 OBRAS PRELIMINARES
03.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 0.49 0.49
03.03.06.01.02 TRAZO Y REPLANTEO m2 1.00 1.84 1.84
03.03.06.02 MOVIMIENTO DE TIERRAS
03.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.51 39.86 20.33
RELLENO Y COMPACTADO CON MATERIAL
03.03.06.02.02 m3 0.51 13.11 6.69
PROPIO A MANO
03.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.49 7.95 3.90
03.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 0.64 25.69 16.44
03.03.06.03 OBRAS DE CONCRETO SIMPLE
03.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.20 413.17 82.63
03.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.24 44.48 10.68
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
03.03.06.03.03 m2 0.27 121.10 32.70
80% PM
03.03.06.04 OBRAS DE CONCRETO ARMADO
03.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.35 546.69 191.34
03.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.72 44.48 165.47
03.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 14.94 4.35 64.99
03.03.06.05 REVOQUES Y ENLUCIDOS
03.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 1.44 32.48 46.77
03.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.36 29.76 99.99
03.03.06.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
03.03.06.06.01 m2 2.16 11.18 24.15
ESMALTE-2 MANOS
03.03.06.07 CARPINTERIA METALICA
03.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 1.00 214.83 214.83
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.03.06.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
03.03.06.08.01 und 1.00 153.06 153.06
EN VALVULA DE PURGA TIPO I, Ø=1"
03.04 RESERVORIO (V=5.00 m3, 01 UND)
03.04.01 OBRAS PRELIMINARES
03.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49 17.64
03.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
03.04.02 MOVIMIENTO DE TIERRAS
03.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 60.95 39.86 2,429.47
03.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 8.05 7.95 64.00
03.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 76.19 25.69 1,957.32
03.04.03 CONCRETO SIMPLE
03.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13
03.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
03.04.03.03 m2 0.50 121.10 60.55
80% PM
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 SOLADO PARA LOSA FONDO m2 8.05 40.87 329.00
03.04.04.02 CONCRETO f'c=210 kg/cm2 m3 9.51 546.69 5,199.02
03.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 49.52 44.48 2,202.65
03.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 254.64 4.35 1,107.68
03.04.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.04.05.01 m2 31.00 32.48 1,006.88
MEZCLA 1:2 E=2 cm H=1.5 Max
03.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 35.50 29.76 1,056.48
03.04.06 PINTURA
PINTURA ESMALTE EN MUROS EXTERIORES DE
03.04.06.01 m2 29.15 13.23 385.65
RESERVORIO
03.04.07 CARPINTERIA METALICA
03.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.04.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.04.08.01 RESERVORIO (INGRESO Ø 1"-LIMPIA, REBOSE y SELLO und 1.00 1,618.16 1,618.16
HIDR. Ø 2"-VENTILAC. Ø 3")
03.04.09 CERCO PERIMETRICO EN RESERVORIO
03.04.09.01 TRABAJOS PRELIMINARES
03.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84 66.24
03.04.09.02 MOVIMIENTO DE TIERRAS
03.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86 27.90
03.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
03.04.09.03 CONCRETO SIMPLE
03.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98 249.19
03.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
03.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
03.04.09.05 COLOCADO DE ROLLIZOS
03.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
03.04.09.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS
03.04.09.06.01 m 66.40 3.80 252.32
MANOS C/ESMALTE SINTETICO
SUM. E INST. MALLA GANADERA DE 12 HILOS
03.04.09.07
H=1.80m
03.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22 515.50
03.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
03.04.09.08.01 und 1.00 194.10 194.10
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
03.04.10 CLORADOR POR GOTEO
03.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
CASETA DE MURO DE LADRILLO -CLORADOR
03.04.10.01.01
POR GOTEO
MURO DE LADRILLO PANDERETA
03.04.10.01.01.01 (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA m2 7.52 54.96 413.30
1.5 cm.
MURO DE LADRILLO PANDERETA
03.04.10.01.01.02 INTERCALADO(0.10x0.12x0.24) AMARRE SOGA m2 4.48 49.36 221.13
MORTERO 1:5 JUNTA 1.5 cm.
03.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
03.04.10.01.02.01 CORREAS DE MADERA DE 2" x 2" m 6.00 29.07 174.42
COBERTURA CON CALAMINA
03.04.10.01.02.02 m2 5.98 34.08 203.80

03.04.10.01.03 REVOQUES Y ENLUCIDOS


TARRAJEO MUROS DE INTERIORES Y
03.04.10.01.03.01 m2 14.98 30.00 449.40
EXTERIORES, CEMENTO : ARENA, 1:5
DERRAME EN PUERTAS h =0.10 m, C:A 1:2,
03.04.10.01.03.02 m 4.00 13.78 55.12
e=2.0 cm
03.04.10.01.04 CARPINTERIA METALICA
SUMINISTRO E INSTALACION DE PUERTA
03.04.10.01.04.01 und 1.00 367.18 367.18
METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO
03.04.10.01.05 PINTURAS
PINTURA ESMALTE EN MUROS INTERIORES Y
03.04.10.01.05.01 m2 14.98 11.18 167.48
EXTERIORES
PINTURA ANTICORROSIVA Y ESMALTE EN
03.04.10.01.05.02 m2 4.00 12.25 49.00
PUERTAS
TANQUE DE AGUA 250 LTRS, INCLUYE ACC.
03.04.10.02
INTERNOS
SUMINISTRO E INSTALACION DE TANQUE DE
03.04.10.02.01 und 1.00 435.06 435.06
POLIETILENO, CAP=250 LTRS.
03.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
SUMINISTRO Y COLOCACION DE TUBERIAS Y
03.04.10.03.01 ACCESORIOS EN SISTEMA DE CLORACION POR GLB 1.00 939.22 939.22
GOTEO
03.05 RED DE ADUCCION Y DISTRIBUCION (L=2,740.00 m)
03.05.01 TRABAJOS PRELIMINARES
03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,370.00 0.49 671.30
03.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 2,740.00 1.53 4,192.20
TRAZO Y NIVELACION DURANTE LA EJECUCION
03.05.01.03 m 2,740.00 1.53 4,192.20
EN ZANJAS REDES Y LINEAS
03.05.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
03.05.02.01 m3 1,041.20 49.82 51,872.58
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
03.05.02.02 m3 54.80 55.80 3,057.84
ROCA SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
03.05.02.03 m 2,740.00 1.81 4,959.40
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA
03.05.02.04 m 137.00 6.08 832.96
SUELTA Y FIJA P/TUBERIA
RELLENO Y COMPACTADO DE ZANJAS CON
03.05.02.05 MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, m3 390.45 36.40 14,212.38
H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
03.05.02.06 MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" m3 20.55 65.17 1,339.24
P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
03.05.02.07 m3 719.25 25.07 18,031.60
MATERIAL PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON
03.05.02.08 m3 68.50 62.16 4,257.96
MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m
03.05.02.09 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 34.25 25.69 879.88
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC
03.05.03.01 m 4.00 8.05 32.20
SAP C-10 DE 1"
SUMINISTRO E INSTALACION DE TUBERIA PVC
03.05.03.02 m 2,736.00 4.84 13,242.24
SAP C-10 DE 3/4"
03.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 96.63 96.63
03.05.04 PRUEBA HIDRAULICA
03.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 2,740.00 1.51 4,137.40
03.05.05 CAMARA ROMPE PRESION T-7 (09 UND)
03.05.05.01 OBRAS PRELIMINARES
03.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 18.63 0.49 9.13
03.05.05.01.02 TRAZO Y REPLANTEO m2 18.63 1.84 34.28
03.05.05.02 MOVIMIENTO DE TIERRAS
03.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 14.32 39.86 570.80
03.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 7.16 40.95 293.20
RELLENO Y COMPACTADO CON MATERIAL
03.05.05.02.03 m3 2.39 13.11 31.33
PROPIO A MANO
03.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 17.69 7.95 140.64
03.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.06 59.44 63.01
03.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 8.06 25.69 207.06
03.05.05.03 OBRAS DE CONCRETO SIMPLE
03.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.11 413.17 45.45
03.05.05.03.02 SOLADO E=4" m3 1.49 35.81 53.36
03.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.80 44.48 80.06
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
03.05.05.03.04 m2 2.43 121.10 294.27
80% PM
03.05.05.04 OBRAS DE CONCRETO ARMADO
03.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 12.23 546.69 6,686.02
03.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 125.30 44.48 5,573.34
03.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,771.06 4.35 7,704.11
03.05.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.05.05.05.01 m2 38.88 32.48 1,262.82
MEZCLA 1:2 E=2 cm H=1.5 Max
03.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 84.26 29.76 2,507.58
03.05.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
03.05.05.06.01 m2 54.00 11.18 603.72
ESMALTE-2 MANOS
03.05.05.07 CARPINTERIA METALICA
03.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 9.00 179.83 1,618.47
03.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 9.00 213.73 1,923.57
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
03.05.05.08.01 und 9.00 379.18 3,412.62
EN CRP T7, INGRESO Y SALIDA Ø=3/4"
03.05.06 VALVULA DE CONTROL (05 UND)
03.05.06.01 OBRAS PRELIMINARES
03.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49 2.45
03.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.84 9.20
03.05.06.02 MOVIMIENTO DE TIERRAS
03.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 39.86 199.30
03.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 25.69 160.56
03.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.95 39.75
03.05.06.03 OBRAS DE CONCRETO ARMADO
03.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 546.69 1,350.32
03.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 44.48 947.42
03.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.35 668.94
03.05.06.04 REVOQUES Y ENLUCIDOS
03.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 32.48 233.86
03.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 29.76 321.41
03.05.06.05 PINTURA
PINTURA EN MUROS EXTERIORES CON
03.05.06.05.01 m2 10.80 11.18 120.74
ESMALTE-2 MANOS
03.05.06.06 CARPINTERIA METALICA
03.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 162.88 814.40
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.06.07
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
03.05.06.07.01 und 5.00 79.02 395.10
EN VALVULA DE CONTROL, Ø=3/4"
03.05.07 VALVULA DE PURGA TIPO II (06 UND)
03.05.07.01 OBRAS PRELIMINARES
03.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.00 0.49 2.94
03.05.07.01.02 TRAZO Y REPLANTEO m2 6.00 1.84 11.04
03.05.07.02 MOVIMIENTO DE TIERRAS
03.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 9.17 39.86 365.52
EXCAVACION MANUAL EN TERRENO ROCA
03.05.07.02.02 m3 3.06 49.82 152.45
SUELTA
RELLENO Y COMPACTADO CON MATERIAL
03.05.07.02.03 m3 3.06 13.11 40.12
PROPIO A MANO
03.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 2.94 7.95 23.37
03.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 2.94 25.69 75.53
03.05.07.03 OBRAS DE CONCRETO SIMPLE
03.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 1.84 413.17 760.23
03.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.44 44.48 64.05
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
03.05.07.03.03 m2 0.77 121.10 93.25
80% PM
03.05.07.04 OBRAS DE CONCRETO ARMADO
03.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 2.10 546.69 1,148.05
03.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 23.32 44.48 1,037.27
03.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 86.64 4.35 376.88
03.05.07.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.05.07.05.01 m2 8.64 32.48 280.63
MEZCLA 1:2 E=2 cm H=1.5 Max
03.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 20.16 29.76 599.96
03.05.07.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
03.05.07.06.01 m2 9.72 11.18 108.67
ESMALTE-2 MANOS
03.05.07.07 CARPINTERIA METALICA
MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN.
03.05.07.07.01 und 6.00 213.73 1,282.38
DE 0.60x0.40m.
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.07.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
03.05.07.08.01 EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA und 6.00 132.94 797.64
Ø=3/4"
03.05.08 CONEXIONES DOMICILIARIAS (53 UND)
03.05.08.01 OBRAS PRELIMINARES
03.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 474.88 0.49 232.69
03.05.08.01.02 TRAZO Y REPLANTEO m2 712.32 1.84 1,310.67
03.05.08.02 MOVIMIENTO DE TIERRAS
EXCAVACION A MANO DE ZANJA MANUAL
03.05.08.02.01 m3 569.86 39.86 22,714.62
TERRENO NORMAL
RELLENO Y COMPACTADO DE ZANJAS CON
03.05.08.02.02 m3 569.86 33.00 18,805.38
MATERIAL PROPIO CLASIFICADO
SUMINISTRO Y COLOCACION DE GRAVA
03.05.08.02.03 m3 50.36 209.11 10,530.78
SELECCIONADA
03.05.08.03 OBRAS DE CONCRETO SIMPLE
03.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 3.93 413.17 1,623.76
03.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.61 44.48 872.25
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.08.04
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
03.05.08.04.01 und 53.00 80.77 4,280.81
EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND)
TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m
03.05.08.04.02 und 53.00 155.21 8,226.13
CON LLAVE TIPO BUJIA
SUMINISTRO E INSTALACIONES DE ACOMETIDA
03.05.08.04.03 m 530.00 3.50 1,855.00
DOMICILIARIA RANGO 2 - 20 M.
04 LOCALIDAD TARACA
04.01 CONSTRUCCIONES PROVISIONALES
OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y
04.01.01 m2 100.00 44.55 4,455.00
VESTUARIOS
ALQUILER DE PREDIOS PARA CAMPAMENTOS Y
04.01.02 mes 6.00 500.00 3,000.00
ALMACENES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m
04.01.03 und 1.00 1,539.82 1,539.82
x 7.20 m
04.02 CAPTACION A TIPO LADERA YACUTOCCYAC (01 UND)
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.49 24.01
04.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
04.02.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO
04.02.02.01 m3 17.55 39.86 699.54
CONGLOMERADO
RELLENO Y COMPACTADO CON MATERIAL
04.02.02.02 m3 2.55 29.50 75.23
PROPIO A MANO C/PISON
04.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.95 214.65
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.60 25.69 400.76
04.02.03 CONCRETO SIMPLE
04.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 413.17 706.52
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 44.48 117.43
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
04.02.03.03 m2 0.50 121.10 60.55
80% PM
04.02.04 CONCRETO ARMADO
04.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 513.84 811.87
04.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 44.48 797.53
04.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.35 296.06
04.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTES
04.02.05.01 m2 5.53 32.48 179.61
M=1:3 e=1.5cm
04.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 29.76 358.61
04.02.06 PINTURA
PINTURA ESMALTE 2 MANOS EN MUROS
04.02.06.01 m2 12.05 13.23 159.42
EXTERIORES
FILTRO DE GRAVA, ARENA Y MATERIAL
04.02.07
IMPERMEABLE
04.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 175.85 265.53
04.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 95.77 25.86
04.02.08 CARPINTERIA METALICA
04.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 180.93 180.93
04.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 281.53 281.53
04.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.02.09.01 CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO und 1.00 497.69 497.69
HIDRAULICO y VENTILACION Ø=2")
04.02.10 CERCO PERIMETRICO EN CAPTACION
04.02.10.01 TRABAJOS PRELIMINARES
04.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.84 44.16
04.02.10.02 MOVIMIENTO DE TIERRAS
04.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 39.86 23.52
04.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
04.02.10.03 CONCRETO SIMPLE
04.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 355.98 210.03
04.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
04.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
04.02.10.05 COLOCADO DE ROLLIZOS
04.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
04.02.10.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS
04.02.10.06.01 m 33.80 3.80 128.44
MANOS C/ESMALTE SINTETICO
SUM. E INST. MALLA GANADERA DE 12 HILOS
04.02.10.07
H=1.80m
04.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 22.22 533.28
04.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
04.02.10.08.01 und 1.00 194.10 194.10
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
04.03 LINEA DE CONDUCCION (L=1231.00 m)
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,231.00 0.49 603.19
04.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 1,231.00 1.53 1,883.43
TRAZO Y NIVELACION DURANTE LA EJECUCION
04.03.01.03 m 1,231.00 1.53 1,883.43
EN ZANJAS REDES Y LINEAS
04.03.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
04.03.02.01 m3 392.92 39.86 15,661.79
SUELTO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
04.03.02.02 m3 73.86 49.82 3,679.71
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
04.03.02.03 m3 15.39 55.80 858.76
ROCA SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
04.03.02.04 m 1,231.00 1.81 2,228.11
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA
04.03.02.05 m 61.55 6.08 374.22
SUELTA Y FIJA P/TUBERIA
04.03.02.06 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 1,231.00 4.28 5,268.68
RELLENO Y COMPACTADO DE ZANJAS CON
04.03.02.07 MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, m3 175.42 36.40 6,385.29
H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
04.03.02.08 MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" m3 9.23 65.17 601.52
P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
04.03.02.09 m3 292.36 25.07 7,329.47
MATERIAL PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON
04.03.02.10 m3 6.16 62.16 382.91
MATERIAL DE PRESTAMO P/TUBERIA, H=0.50 m
04.03.02.11 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.39 25.69 395.37
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.03.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC
04.03.03.01 m 1,231.00 5.94 7,312.14
SAP C-10 DE 1"
04.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 157.71 157.71
04.03.04 PRUEBA HIDRAULICA
04.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 1,231.00 1.51 1,858.81
04.03.05 CAMARA ROMPE PRESION T-6 (02 UND)
04.03.05.01 OBRAS PRELIMINARES
04.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.88 0.49 1.41
04.03.05.01.02 TRAZO Y REPLANTEO m2 2.88 1.84 5.30
04.03.05.02 MOVIMIENTO DE TIERRAS
04.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 3.17 39.86 126.36
04.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 7.92 25.69 203.46
04.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 2.88 7.95 22.90
04.03.05.03 OBRAS DE CONCRETO SIMPLE
04.03.05.03.01 SOLADO E=4" m3 2.42 35.81 86.66
04.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.02 413.17 8.26
04.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.40 44.48 17.79
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
04.03.05.03.04 m2 1.00 121.10 121.10
80% PM
04.03.05.04 OBRAS DE CONCRETO ARMADO
04.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 546.69 863.77
04.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 16.20 44.48 720.58
04.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 74.46 4.35 323.90
04.03.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.03.05.05.01 m2 5.04 32.48 163.70
MEZCLA 1:2 E=2 cm H=1.5 Max
04.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.48 29.76 192.84
04.03.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
04.03.05.06.01 m2 6.48 11.18 72.45
ESMALTE-2 MANOS
04.03.05.07 CARPINTERIA METALICA
04.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.03.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
04.03.05.08.01 und 2.00 299.60 599.20
EN CRP T6, INGRESO Ø=1 y SALIDA Ø=1 "
04.03.06 VALVULA DE PURGA TIPO I (1 UND)
04.03.06.01 OBRAS PRELIMINARES
04.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.00 0.49 0.98
04.03.06.01.02 TRAZO Y REPLANTEO m2 2.00 1.84 3.68
04.03.06.02 MOVIMIENTO DE TIERRAS
04.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.02 39.86 40.66
RELLENO Y COMPACTADO CON MATERIAL
04.03.06.02.02 m3 1.02 13.11 13.37
PROPIO A MANO
04.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.98 7.95 7.79
04.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1.27 25.69 32.63
04.03.06.03 OBRAS DE CONCRETO SIMPLE
04.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.04 413.17 16.53
04.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.48 44.48 21.35
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
04.03.06.03.03 m2 0.54 121.10 65.39
80% PM
04.03.06.04 OBRAS DE CONCRETO ARMADO
04.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.70 546.69 382.68
04.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.44 44.48 330.93
04.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 29.88 4.35 129.98
04.03.06.05 REVOQUES Y ENLUCIDOS
04.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 2.88 32.48 93.54
04.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.72 29.76 199.99
04.03.06.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
04.03.06.06.01 m2 4.32 11.18 48.30
ESMALTE-2 MANOS
04.03.06.07 CARPINTERIA METALICA
04.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 2.00 214.83 429.66
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.03.06.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
04.03.06.08.01 und 2.00 153.06 306.12
EN VALVULA DE PURGA TIPO I, Ø=1"
04.04 RESERVORIO (V=5.00 m3, 01 UND)
04.04.01 OBRAS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.49 17.64
04.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.84 66.24
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 36.02 39.86 1,435.76
04.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 8.05 7.95 64.00
04.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 45.02 25.69 1,156.56
04.04.03 CONCRETO SIMPLE
04.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 413.17 4.13
04.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 44.48 8.90
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
04.04.03.03 m2 0.50 121.10 60.55
80% PM
04.04.04 OBRAS DE CONCRETO ARMADO
04.04.04.01 SOLADO PARA LOSA FONDO m2 8.05 40.87 329.00
04.04.04.02 CONCRETO f'c=210 kg/cm2 m3 9.51 546.69 5,199.02
04.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 49.52 44.48 2,202.65
04.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 254.64 4.35 1,107.68
04.04.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.04.05.01 m2 31.00 32.48 1,006.88
MEZCLA 1:2 E=2 cm H=1.5 Max
04.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 35.50 29.76 1,056.48
04.04.06 PINTURA
PINTURA ESMALTE EN MUROS EXTERIORES DE
04.04.06.01 m2 29.15 13.23 385.65
RESERVORIO
04.04.07 CARPINTERIA METALICA
04.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 213.73 427.46
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.04.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.04.08.01 RESERVORIO (INGRESO Ø 1"-LIMPIA, REBOSE y SELLO und 1.00 1,618.16 1,618.16
HIDR. Ø 2"-VENTILAC. Ø 3")
04.04.09 CERCO PERIMETRICO EN RESERVORIO
04.04.09.01 TRABAJOS PRELIMINARES
04.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.84 66.24
04.04.09.02 MOVIMIENTO DE TIERRAS
04.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 39.86 27.90
04.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 25.69 18.75
04.04.09.03 CONCRETO SIMPLE
04.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 355.98 249.19
04.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
04.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 44.48 69.39
04.04.09.05 COLOCADO DE ROLLIZOS
04.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 42.83 556.79
04.04.09.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS
04.04.09.06.01 m 66.40 3.80 252.32
MANOS C/ESMALTE SINTETICO
SUM. E INST. MALLA GANADERA DE 12 HILOS
04.04.09.07
H=1.80m
04.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 22.22 515.50
04.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
04.04.09.08.01 und 1.00 194.10 194.10
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
04.04.10 CLORADOR POR GOTEO
04.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
CASETA DE MURO DE LADRILLO -CLORADOR
04.04.10.01.01
POR GOTEO
MURO DE LADRILLO PANDERETA
04.04.10.01.01.01 (0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 JUNTA m2 7.52 54.96 413.30
1.5 cm.
MURO DE LADRILLO PANDERETA
04.04.10.01.01.02 INTERCALADO(0.10x0.12x0.24) AMARRE SOGA m2 4.48 49.36 221.13
MORTERO 1:5 JUNTA 1.5 cm.
04.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
04.04.10.01.02.01 CORREAS DE MADERA DE 2" x 2" m 6.00 29.07 174.42
COBERTURA CON CALAMINA
04.04.10.01.02.02 m2 5.98 34.08 203.80

04.04.10.01.03 REVOQUES Y ENLUCIDOS


TARRAJEO MUROS DE INTERIORES Y
04.04.10.01.03.01 m2 14.98 30.00 449.40
EXTERIORES, CEMENTO : ARENA, 1:5
DERRAME EN PUERTAS h =0.10 m, C:A 1:2,
04.04.10.01.03.02 m 4.00 13.78 55.12
e=2.0 cm
04.04.10.01.04 CARPINTERIA METALICA
SUMINISTRO E INSTALACION DE PUERTA
04.04.10.01.04.01 und 1.00 367.18 367.18
METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO
04.04.10.01.05 PINTURAS
PINTURA ESMALTE EN MUROS INTERIORES Y
04.04.10.01.05.01 m2 14.98 11.18 167.48
EXTERIORES
PINTURA ANTICORROSIVA Y ESMALTE EN
04.04.10.01.05.02 m2 4.00 12.25 49.00
PUERTAS
TANQUE DE AGUA 250 LTRS, INCLUYE ACC.
04.04.10.02
INTERNOS
SUMINISTRO E INSTALACION DE TANQUE DE
04.04.10.02.01 und 1.00 435.06 435.06
POLIETILENO, CAP=250 LTRS.
04.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
SUMINISTRO Y COLOCACION DE TUBERIAS Y
04.04.10.03.01 ACCESORIOS EN SISTEMA DE CLORACION POR GLB 1.00 939.22 939.22
GOTEO
04.05 RED DE ADUCCION Y DISTRIBUCION (L=3,674.00 m)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,837.00 0.49 900.13
04.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 3,674.00 1.53 5,621.22
TRAZO Y NIVELACION DURANTE LA EJECUCION
04.05.01.03 m 3,674.00 1.53 5,621.22
EN ZANJAS REDES Y LINEAS
04.05.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
04.05.02.01 m3 73.48 39.86 2,928.91
SUELTO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
04.05.02.02 m3 1,352.03 49.82 67,358.13
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
04.05.02.03 m3 44.09 55.80 2,460.22
ROCA SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
04.05.02.04 m 3,674.00 1.81 6,649.94
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA
04.05.02.05 m 110.22 6.08 670.14
SUELTA Y FIJA P/TUBERIA
RELLENO Y COMPACTADO DE ZANJAS CON
04.05.02.06 MATERIAL PROPIO SELECCIONADO DE 3/8" P/TUBERIA, m3 534.57 36.40 19,458.35
H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
04.05.02.07 MATERIAL DE PRESTAMO SELECCIONADO DE 3/8" m3 16.53 65.17 1,077.26
P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON
04.05.02.08 m3 946.06 25.07 23,717.72
MATERIAL PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON
04.05.02.09 m3 55.11 62.16 3,425.64
MATERIAL DE PRESTAMO P/TUBERIA, H=0.20 m
04.05.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 27.56 25.69 708.02
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC
04.05.03.01 m 104.00 8.05 837.20
SAP C-10 DE 1"
SUMINISTRO E INSTALACION DE TUBERIA PVC
04.05.03.02 m 3,570.00 4.84 17,278.80
SAP C-10 DE 3/4"
04.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 87.97 87.97
04.05.04 PRUEBA HIDRAULICA
04.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 3,674.00 1.51 5,547.74
04.05.05 CAMARA ROMPE PRESION T-7 (12 UND)
04.05.05.01 OBRAS PRELIMINARES
04.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 24.84 0.49 12.17
04.05.05.01.02 TRAZO Y REPLANTEO m2 24.84 1.84 45.71
04.05.05.02 MOVIMIENTO DE TIERRAS
04.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 16.71 39.86 666.06
04.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 9.55 40.95 391.07
RELLENO Y COMPACTADO CON MATERIAL
04.05.05.02.03 m3 2.39 13.11 31.33
PROPIO A MANO
04.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 23.58 7.95 187.46
04.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.39 59.44 82.62
04.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 12.53 25.69 321.90
04.05.05.03 OBRAS DE CONCRETO SIMPLE
04.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.14 413.17 57.84
04.05.05.03.02 SOLADO E=4" m3 1.98 35.81 70.90
04.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.40 44.48 106.75
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
04.05.05.03.04 m2 3.24 121.10 392.36
80% PM
04.05.05.04 OBRAS DE CONCRETO ARMADO
04.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 16.30 546.69 8,911.05
04.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 167.06 44.48 7,430.83
04.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,361.41 4.35 10,272.13
04.05.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.05.05.05.01 m2 51.84 32.48 1,683.76
MEZCLA 1:2 E=2 cm H=1.5 Max
04.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 112.34 29.76 3,343.24
04.05.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
04.05.05.06.01 m2 72.00 11.18 804.96
ESMALTE-2 MANOS
04.05.05.07 CARPINTERIA METALICA
04.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 12.00 179.83 2,157.96
04.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 12.00 213.73 2,564.76
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
04.05.05.08.01 und 12.00 379.18 4,550.16
EN CRP T7, INGRESO Y SALIDA Ø=3/4"
04.05.06 VALVULA DE CONTROL (05 UND)
04.05.06.01 OBRAS PRELIMINARES
04.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49 2.45
04.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.84 9.20
04.05.06.02 MOVIMIENTO DE TIERRAS
04.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 39.86 199.30
04.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 25.69 160.56
04.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.95 39.75
04.05.06.03 OBRAS DE CONCRETO ARMADO
04.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 546.69 1,350.32
04.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 44.48 947.42
04.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.35 668.94
04.05.06.04 REVOQUES Y ENLUCIDOS
04.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 32.48 233.86
04.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 29.76 321.41
04.05.06.05 PINTURA
PINTURA EN MUROS EXTERIORES CON
04.05.06.05.01 m2 10.80 11.18 120.74
ESMALTE-2 MANOS
04.05.06.06 CARPINTERIA METALICA
04.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 162.88 814.40
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.06.07
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
04.05.06.07.01 und 5.00 79.02 395.10
EN VALVULA DE CONTROL, Ø=3/4"
04.05.07 VALVULA DE PURGA TIPO II (05 UND)
04.05.07.01 OBRAS PRELIMINARES
04.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.49 2.45
04.05.07.01.02 TRAZO Y REPLANTEO m2 5.00 1.84 9.20
04.05.07.02 MOVIMIENTO DE TIERRAS
04.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 7.64 39.86 304.53
EXCAVACION MANUAL EN TERRENO ROCA
04.05.07.02.02 m3 2.55 49.82 127.04
SUELTA
RELLENO Y COMPACTADO CON MATERIAL
04.05.07.02.03 m3 2.55 13.11 33.43
PROPIO A MANO
04.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 2.45 7.95 19.48
04.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 2.45 25.69 62.94
04.05.07.03 OBRAS DE CONCRETO SIMPLE
04.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 1.53 413.17 632.15
04.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 44.48 53.38
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA +
04.05.07.03.03 m2 0.64 121.10 77.50
80% PM
04.05.07.04 OBRAS DE CONCRETO ARMADO
04.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 1.75 546.69 956.71
04.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 18.60 44.48 827.33
04.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 74.70 4.35 324.95
04.05.07.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.05.07.05.01 m2 7.20 32.48 233.86
MEZCLA 1:2 E=2 cm H=1.5 Max
04.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 16.80 29.76 499.97
04.05.07.06 PINTURA
PINTURA EN MUROS EXTERIORES CON
04.05.07.06.01 m2 8.10 11.18 90.56
ESMALTE-2 MANOS
04.05.07.07 CARPINTERIA METALICA
MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN.
04.05.07.07.01 und 5.00 213.73 1,068.65
DE 0.60x0.40m.
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.07.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
04.05.07.08.01 EN VALVULA DE PURGA TIPO II, INGRESO Y SALIDA und 5.00 132.94 664.70
Ø=3/4"
04.05.08 CONEXIONES DOMICILIARIAS (53 UND)
04.05.08.01 OBRAS PRELIMINARES
04.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 474.88 0.49 232.69
04.05.08.01.02 TRAZO Y REPLANTEO m2 712.32 1.84 1,310.67
04.05.08.02 MOVIMIENTO DE TIERRAS
EXCAVACION A MANO DE ZANJA TERRENO
04.05.08.02.01 m3 596.86 40.95 24,441.42
NORMAL
RELLENO Y COMPACTADO DE ZANJAS CON
04.05.08.02.02 m3 569.86 33.00 18,805.38
MATERIAL PROPIO CLASIFICADO
SUMINISTRO Y COLOCACION DE GRAVA
04.05.08.02.03 m3 59.36 209.11 12,412.77
SELECCIONADA
04.05.08.03 OBRAS DE CONCRETO SIMPLE
04.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 3.93 413.17 1,623.76
04.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.61 44.48 872.25
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.08.04
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS
04.05.08.04.01 und 53.00 80.77 4,280.81
EN CONEXIONES DOMICILIARIAS DE AGUA (53 UND)
TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m
04.05.08.04.02 und 53.00 155.21 8,226.13
CON LLAVE TIPO BUJIA
SUMINISTRO E INSTALACIONES DE ACOMETIDA
04.05.08.04.03 m 636.00 3.50 2,226.00
DOMICILIARIA RANGO 2 - 20 M.

01 LOCALIDAD SANTA LUCIA


01.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
01.01.01 TRABAJOS PRELIMINARES
01.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 465.00 0.49 227.85
01.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 465.00 1.84 855.60
01.01.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO
01.01.02.01 m3 231.57 39.86 9,230.38
CONGLOMERADO
01.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 40.92 29.66 1,213.69
01.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 238.08 25.69 6,116.28
01.01.03 CONCRETO SIMPLE
01.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 279.00 373.75 104,276.25
01.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 40.92 398.69 16,314.39
01.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 678.90 44.48 30,197.47
01.01.03.04 CONCRETO f'c=175 kg/cm2 m3 28.83 448.85 12,940.35
01.01.04 MURO DE LADRILLO
MURO DE LADRILLO KK CARAVISTA DE 18
01.01.04.01 m2 1,354.08 58.10 78,672.05
HUECOS DE SOGA C/M 1:4 x 1.5cm
EMPEDRADO DE PROTECCION CON PIEDRA
01.01.04.02 m2 26.04 70.33 1,831.39
TAMAÑO 4"-6"
01.01.05 REVOQUES Y ENLUCIDOS
TARRAJEO DE MUROS Y PISOS
01.01.05.01 C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre m2 1,272.24 16.34 20,788.40
hidraulico)
01.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 20.46 36.55 747.81
01.01.06 PINTURA
PINTURA EN MUROS INTERIORES C/LATEX
01.01.06.01 m2 767.25 11.53 8,846.39
LAVABLE COLOR MARFIL
01.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO
01.01.07.01 ETERNIT(1,14x0.72x0.005m) m2 605.43 66.22 40,091.57

01.01.08 CARPINTERIA METALICA


SUMINISTRO E INSTALACION DE PUERTA
01.01.08.01 und 93.00 363.74 33,827.82
METALICA 1.80x0.70m, INCL. MARCO Y PINTADO
01.01.09 CARPINTERIA DE MADERA
VENTANA DE MADERA TORNILLO INC. MALLA
01.01.09.01 m2 16.74 75.90 1,270.57
MOSQUITERA
01.01.09.02 COBERTURA DE MADERA PARA TECHO und 93.00 97.95 9,109.35
01.01.10 SISTEMA DE AGUA FRIA
01.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 880.71 3.65 3,214.59
01.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
01.01.11.01 TEE PVC-SAP 1/2" pza 186.00 20.85 3,878.10
01.01.11.02 CODO PVC SAP 1/2" pza 558.00 15.59 8,699.22
01.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 186.00 51.25 9,532.50
SUMINISTRO E INSTALACION DE DUCHA
01.01.11.04 und 93.00 33.08 3,076.44
INCLUIDO ACCESORIOS
01.01.12 SISTEMA DE DESAGUE
01.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 897.45 4.02 3,607.75
01.01.12.02 TUBERIA Ø=4" PVC SAL m 339.45 3.65 1,238.99
01.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
01.01.13.01 CODO PVC SAL 2"X90° pza 651.00 11.77 7,662.27
01.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 93.00 15.53 1,444.29
01.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 279.00 16.11 4,494.69
01.01.14 ADITAMIENTOS VARIOS
01.01.14.01 SUMIDEROS DE BRONCE 2" und 93.00 12.25 1,139.25
01.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 186.00 11.09 2,062.74
INODORO DE LOZA VITRIFICADA COLOR BLANCO
01.01.14.03 und 93.00 147.40 13,708.20
INCLUYE TANQUE
01.01.14.04 ACCESORIOS DE LOZA und 93.00 64.86 6,031.98
SUMINISTRO E INSTALACION DE TUBERIA DE
01.01.14.05 VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y GLB 93.00 29.15 2,710.95
ACCESORIOS
SUMINISTRO E INSTALACION DE LAVATORIO DE
01.01.14.06 und 93.00 124.59 11,586.87
LOZA COLOR BLANCO INCLUIDO ACCESORIOS
SUMINISTRO E INSTALACION DE CAJA DE
01.01.14.07 und 186.00 129.89 24,159.54
REGISTRO DE 12"x24"
01.01.15 INSTALACIONES ELECTRICAS
01.01.15.01 SALIDA DE CENTRO DE LUZ pto 93.00 49.14 4,570.02
01.01.15.02 TUBERIA PVC SEL 5/8" m 213.90 4.15 887.69
01.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 520.80 2.28 1,187.42
01.01.15.04 TABLEROS DISTRIBUCION pza 93.00 89.04 8,280.72
01.01.16 CONSTRUCCION POZO PERCOLADOR
01.01.16.01 TRABAJOS PRELIMINARES
01.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 292.02 0.49 143.09
01.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 292.02 1.84 537.32
01.01.16.02 MOVIMIENTO DE TIERRAS
01.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 150.66 39.86 6,005.31
RELLENO CON MATERIAL PROPIO
01.01.16.02.02 m3 22.32 29.66 662.01
SELECCIONADO
01.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 80.91 89.30 7,225.26
01.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 188.79 25.69 4,850.02
01.01.16.03 TAPA DE CONCRETO
01.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 18.81 448.85 8,442.87
01.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 196.26 44.48 8,729.64
01.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,957.65 4.35 8,515.78
01.01.16.04 ANILLO DE CONCRETO
01.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 6.51 355.98 2,317.43
01.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 111.60 44.48 4,963.97
01.01.16.05 MURO DE LADRILLO
MURO DE LADRILLO ARTESANAL AMARRE DE
01.01.16.05.01 m2 388.74 48.94 19,024.94
SOGA, JUNTA 1.5 CM MORTERO 1:1:5
01.01.16.06 SISTEMA DE DESAGUE LLEGADA
01.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 181.35 4.02 729.03
01.01.16.06.02 CODO PVC SAL 2"X90° pza 93.00 11.77 1,094.61
01.01.17 INSTALACION DEL BIODIGESTOR
01.01.17.01 TRABAJOS PRELIMINARES
01.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 351.54 0.49 172.25
01.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 351.54 1.84 646.83
01.01.17.02 MOVIMIENTO DE TIERRAS
01.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 281.20 39.86 11,208.63
RELLENO CON MATERIAL PROPIO
01.01.17.02.02 m3 211.97 29.66 6,287.03
SELECCIONADO
01.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 351.50 25.69 9,030.04
01.01.17.03 CONCRETO SIMPLE
01.01.17.03.01 SOLADO E=4" m2 60.45 39.68 2,398.66
01.01.17.04 CONCRETO ARMADO
01.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 66.96 448.85 30,055.00
01.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 420.36 44.48 18,697.61
01.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 518.01 4.35 2,253.34
01.01.17.05 BIODIGESTOR
SUMINISTRO E INSTALACION DE BIODIGESTOR
01.01.17.05.01 und 91.00 779.59 70,942.69
AUTOLIMPIABLE DE PVC DE 600 LTS
SUMINISTRO E INSTALACION DE BIODIGESTOR
01.01.17.05.02 und 2.00 1,320.79 2,641.58
AUTOLIMPIABLE DE PVC DE 1300 LTS
01.01.17.06 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.01.17.06.01 m2 332.01 32.48 10,783.68
MEZCLA 1:2 E=2 cm H=1.5 Max
01.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
01.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 93.00 4.02 373.86
SUMINISTRO E INSTALACION DE VALVULA DE
01.01.17.07.02 und 93.00 29.86 2,776.98
PVC DE 2"
01.02 LAVADERO INTRADOMICILIARIO (91 UND)
01.02.01 OBRAS PRELIMINARES
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 460.46 0.49 225.63
01.02.01.02 TRAZO Y REPLANTEO m2 460.46 1.84 847.25
01.02.02 MOVIMIENTO DE TIERRAS
01.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 103.03 37.48 3,861.56
RELLENO Y COMPACTADO DE ZANJA CON
01.02.02.02 m3 84.63 13.11 1,109.50
MATERIAL PROPIO CLASIFICADO
01.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 21.16 25.69 543.60
01.02.03 OBRAS DE CONCRETO ARMADO
01.02.03.01 CONCRETO f'c=175 kg/cm2 m3 9.57 448.85 4,295.49
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 304.63 44.48 13,549.94
01.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 359.91 4.35 1,565.61
01.02.04 MURO DE LADRILLO
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
01.02.04.01 m2 60.17 47.74 2,872.52
Lavaderos)
01.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.02.05.01 m2 107.29 32.48 3,484.78
MEZCLA 1:2 E=2 cm H=1.5 Max
01.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 205.30 29.76 6,109.73
01.02.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE LAVADERO
01.02.06.01 und 91.00 136.31 12,404.21
INTRADOMICILIARIA
01.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
01.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 455.00 3.35 1,524.25
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01
01.03
UND)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55
TRAZO, NIVELACION Y REPLANTEO EN
01.03.01.02 m2 11.32 1.84 20.83
ESTRUCTURAS
01.03.02 MOVIMIENTO DE TIERRAS
01.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48 102.70
REFINE, NIVELACION Y COMPACTADO EN
01.03.02.02 m2 11.32 1.02 11.55
TERRENO NORMAL
01.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
01.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69 34.42
01.03.03 OBRAS DE CONCRETO SIMPLE
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
01.03.03.01 m2 2.20 48.96 107.71
FROTACHADO C/MEZCLADORA
01.03.04 OBRAS DE CONCRETO ARMADO
01.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35 36.32
ENCOFRADO Y DESENCOFRADO PARA
01.03.04.02 m2 4.09 44.01 180.00
ESTRUCTURAS
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA
01.03.04.03 m3 0.21 448.85 94.26
PARA LAVADEROS
01.03.05 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA
01.03.05.01 m2 2.49 32.96 82.07
1:2 E=2 cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5
01.03.05.02 m2 2.11 23.98 50.60
cm, H=1.5 MAX
01.03.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.03.06.01 und 1.00 176.99 176.99
LAVADERO I.E. INICIAL
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
01.03.06.02 und 2.00 142.50 285.00
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO
01.03.06.03 und 1.00 57.77 57.77
0.30x0.30x0.30m (INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO
01.03.06.04 und 1.00 48.19 48.19
0.30x0.30x0.25m (INTERIORES), E=0.05
01.03.07 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002:2009
01.03.07.01 m 12.00 6.35 76.20
C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP
01.03.07.02 m 10.00 6.65 66.50
399.003:2007 PARA DESAGUE Ø=2"x3 M
02 LOCALIDAD PUEBLO LIBRE (130 UND)
02.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 650.00 0.49 318.50
02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 650.00 1.84 1,196.00
02.01.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO
02.01.02.01 m3 323.70 39.86 12,902.68
CONGLOMERADO
02.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 57.20 29.66 1,696.55
02.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 332.80 25.69 8,549.63
02.01.03 CONCRETO SIMPLE
02.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 390.00 373.75 145,762.50
02.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 57.20 398.69 22,805.07
02.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 949.00 44.48 42,211.52
02.01.03.04 CONCRETO f'c=175 kg/cm2 m3 40.30 448.85 18,088.66
02.01.04 MURO DE LADRILLO
MURO DE LADRILLO KK CARAVISTA DE 18
02.01.04.01 m2 1,892.80 58.10 109,971.68
HUECOS DE SOGA C/M 1:4 x 1.5cm
EMPEDRADO DE PROTECCION CON PIEDRA
02.01.04.02 m2 36.40 70.33 2,560.01
TAMAÑO 4"-6"
02.01.05 REVOQUES Y ENLUCIDOS
TARRAJEO DE MUROS Y PISOS
02.01.05.01 C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre m2 1,778.40 16.34 29,059.06
hidraulico)
02.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 28.60 36.55 1,045.33
02.01.06 PINTURA
PINTURA EN MUROS INTERIORES C/LATEX
02.01.06.01 m2 1,072.50 11.53 12,365.93
LAVABLE COLOR MARFIL
02.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO
02.01.07.01 ETERNIT(1,14x0.72x0.005m) m2 846.60 66.22 56,061.85

02.01.08 CARPINTERIA METALICA


SUMINISTRO E INSTALACION DE PUERTA
02.01.08.01 und 130.00 363.74 47,286.20
METALICA 1.80x0.70m, INCL. MARCO Y PINTADO
02.01.09 CARPINTERIA DE MADERA
VENTANA DE MADERA TORNILLO INC. MALLA
02.01.09.01 m2 23.40 75.90 1,776.06
MOSQUITERA
02.01.09.02 COBERTURA DE MADERA PARA TECHO und 130.00 97.95 12,733.50
02.01.10 SISTEMA DE AGUA FRIA
02.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 1,231.00 3.65 4,493.15
02.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
02.01.11.01 TEE PVC-SAP 1/2" pza 260.00 20.85 5,421.00
02.01.11.02 CODO PVC SAP 1/2" pza 780.00 15.59 12,160.20
02.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 260.00 51.25 13,325.00
SUMINISTRO E INSTALACION DE DUCHA
02.01.11.04 und 130.00 33.08 4,300.40
INCLUIDO ACCESORIOS
02.01.12 SISTEMA DE DESAGUE
02.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 1,254.50 4.02 5,043.09
02.01.12.02 TUBERIA Ø=4" PVC SAL m 474.50 3.65 1,731.93
02.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
02.01.13.01 CODO PVC SAL 2"X90° pza 910.00 11.77 10,710.70
02.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 130.00 15.53 2,018.90
02.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 390.00 16.11 6,282.90
02.01.14 ADITAMIENTOS VARIOS
02.01.14.01 SUMIDEROS DE BRONCE 2" und 130.00 12.25 1,592.50
02.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 260.00 11.09 2,883.40
INODORO DE LOZA VITRIFICADA COLOR BLANCO
02.01.14.03 und 130.00 147.40 19,162.00
INCLUYE TANQUE
02.01.14.04 ACCESORIOS DE LOZA und 130.00 64.86 8,431.80
SUMINISTRO E INSTALACION DE TUBERIA DE
02.01.14.05 VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y GLB 130.00 29.15 3,789.50
ACCESORIOS
SUMINISTRO E INSTALACION DE LAVATORIO DE
02.01.14.06 und 130.00 124.59 16,196.70
LOZA COLOR BLANCO INCLUIDO ACCESORIOS
SUMINISTRO E INSTALACION DE CAJA DE
02.01.14.07 und 260.00 129.89 33,771.40
REGISTRO DE 12"x24"
02.01.15 INSTALACIONES ELECTRICAS
02.01.15.01 SALIDA DE CENTRO DE LUZ pto 130.00 49.14 6,388.20
02.01.15.02 TUBERIA PVC SEL 5/8" m 299.00 4.15 1,240.85
02.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 728.00 2.28 1,659.84
02.01.15.04 TABLEROS DISTRIBUCION pza 130.00 89.04 11,575.20
02.01.16 CONSTRUCCION POZO PERCOLADOR
02.01.16.01 TRABAJOS PRELIMINARES
02.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 408.20 0.49 200.02
02.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 408.20 1.84 751.09
02.01.16.02 MOVIMIENTO DE TIERRAS
02.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 210.60 39.86 8,394.52
RELLENO CON MATERIAL PROPIO
02.01.16.02.02 m3 31.20 29.66 925.39
SELECCIONADO
02.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 113.10 89.30 10,099.83
02.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 163.90 25.69 4,210.59
02.01.16.03 TAPA DE CONCRETO
02.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 22.10 448.85 9,919.59
02.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 236.60 44.48 10,523.97
02.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,736.50 4.35 11,903.78
02.01.16.04 ANILLO DE CONCRETO
02.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 9.10 355.98 3,239.42
02.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 156.00 44.48 6,938.88
02.01.16.05 MURO DE LADRILLO
MURO DE LADRILLO ARTESANAL AMARRE DE
02.01.16.05.01 m2 543.40 48.94 26,594.00
SOGA, JUNTA 1.5 CM MORTERO 1:1:5
02.01.16.06 SISTEMA DE DESAGUE LLEGADA
02.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 253.50 4.02 1,019.07
02.01.16.06.02 CODO PVC SAL 2"X90° pza 130.00 11.77 1,530.10
02.01.17 INSTALACION DEL BIODIGESTOR
02.01.17.01 TRABAJOS PRELIMINARES
02.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 491.40 0.49 240.79
02.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 491.40 1.84 904.18
02.01.17.02 MOVIMIENTO DE TIERRAS
02.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 396.70 39.86 15,812.46
RELLENO CON MATERIAL PROPIO
02.01.17.02.02 m3 299.24 29.66 8,875.46
SELECCIONADO
02.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 504.11 25.69 12,950.59
02.01.17.03 CONCRETO SIMPLE
02.01.17.03.01 SOLADO E=4" m2 84.50 39.68 3,352.96
02.01.17.04 CONCRETO ARMADO
02.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 93.60 448.85 42,012.36
02.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 587.60 44.48 26,136.45
02.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 724.10 4.35 3,149.84
02.01.17.05 BIODIGESTOR
SUMINISTRO E INSTALACION DE BIODIGESTOR
02.01.17.05.01 und 121.00 779.59 94,330.39
AUTOLIMPIABLE DE PVC DE 600 LTS
SUMINISTRO E INSTALACION DE BIODIGESTOR
02.01.17.05.02 und 9.00 1,320.79 11,887.11
AUTOLIMPIABLE DE PVC DE 1300 LTS
02.01.17.06 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.01.17.06.01 m2 464.10 32.48 15,073.97
MEZCLA 1:2 E=2 cm H=1.5 Max
02.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
02.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 130.00 4.02 522.60
SUMINISTRO E INSTALACION DE VALVULA DE
02.01.17.07.02 und 130.00 29.86 3,881.80
PVC DE 2"
02.02 LAVADERO INTRADOMICILIARIO (121 UND)
02.02.01 OBRAS PRELIMINARES
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 612.26 0.49 300.01
02.02.01.02 TRAZO Y REPLANTEO m2 612.26 1.84 1,126.56
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 137.00 37.48 5,134.76
RELLENO Y COMPACTADO DE ZANJA CON
02.02.02.02 m3 112.53 13.11 1,475.27
MATERIAL PROPIO CLASIFICADO
02.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 28.14 25.69 722.92
02.02.03 OBRAS DE CONCRETO ARMADO
02.02.03.01 CONCRETO f'c=175 kg/cm2 m3 12.72 448.85 5,709.37
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 405.06 44.48 18,017.07
02.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 478.56 4.35 2,081.74
02.02.04 MURO DE LADRILLO
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
02.02.04.01 m2 80.01 47.74 3,819.68
Lavaderos)
02.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.02.05.01 m2 142.66 32.48 4,633.60
MEZCLA 1:2 E=2 cm H=1.5 Max
02.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 272.98 29.76 8,123.88
02.02.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE LAVADERO
02.02.06.01 und 121.00 136.31 16,493.51
INTRADOMICILIARIA
02.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
02.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 605.00 3.35 2,026.75
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01
02.03
UND)
02.03.01 TRABAJOS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55
TRAZO, NIVELACION Y REPLANTEO EN
02.03.01.02 m2 11.32 1.84 20.83
ESTRUCTURAS
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48 102.70
REFINE, NIVELACION Y COMPACTADO EN
02.03.02.02 m2 11.32 1.02 11.55
TERRENO NORMAL
02.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
02.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69 34.42
02.03.03 OBRAS DE CONCRETO SIMPLE
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
02.03.03.01 m2 2.20 48.96 107.71
FROTACHADO C/MEZCLADORA
02.03.04 OBRAS DE CONCRETO ARMADO
02.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35 36.32
ENCOFRADO Y DESENCOFRADO PARA
02.03.04.02 m2 4.09 44.01 180.00
ESTRUCTURAS
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA
02.03.04.03 m3 0.21 448.85 94.26
PARA LAVADEROS
02.03.05 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA
02.03.05.01 m2 2.49 32.96 82.07
1:2 E=2 cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5
02.03.05.02 m2 2.11 23.98 50.60
cm, H=1.5 MAX
02.03.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.03.06.01 und 1.00 176.99 176.99
LAVADERO I.E. INICIAL
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
02.03.06.02 und 2.00 142.50 285.00
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO
02.03.06.03 und 1.00 57.77 57.77
0.30x0.30x0.30m (INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO
02.03.06.04 und 1.00 48.19 48.19
0.30x0.30x0.25m (INTERIORES), E=0.05
02.03.07 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002:2009
02.03.07.01 m 12.00 6.35 76.20
C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP
02.03.07.02 m 10.00 6.65 66.50
399.003:2007 PARA DESAGUE Ø=2"x3 M
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA
02.04
(01 UND)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.49 5.87
TRAZO, NIVELACION Y REPLANTEO EN
02.04.01.02 m2 11.98 1.84 22.04
ESTRUCTURAS
02.04.02 MOVIMIENTO DE TIERRAS
02.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 37.48 104.94
REFINE, NIVELACION Y COMPACTADO EN
02.04.02.02 m2 11.98 1.02 12.22
TERRENO NORMAL
02.04.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
02.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 25.69 36.22
02.04.03 OBRAS DE CONCRETO SIMPLE
CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M.
02.04.03.01 m3 0.06 339.60 20.38
(TMN6") EN LAVADERO C/MEZCLADORA
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
02.04.03.02 m2 2.86 48.96 140.03
FROTACHADO C/MEZCLADORA
02.04.04 OBRAS DE CONCRETO ARMADO
02.04.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.35 49.98
ENCOFRADO Y DESENCOFRADO PARA
02.04.04.02 m2 4.33 44.01 190.56
ESTRUCTURAS
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA
02.04.04.03 m3 0.31 448.85 139.14
PARA LAVADEROS
02.04.05 ALBAÑILERIA
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
02.04.05.01 m2 0.36 58.08 20.91
Lavaderos)
02.04.06 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA
02.04.06.01 m2 3.51 32.96 115.69
1:2 E=2 cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5
02.04.06.02 m2 3.29 23.98 78.89
cm, H=1.5 MAX
02.04.07 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.04.07.01 und 1.00 176.99 176.99
LAVADERO TIPO I.E. PRIMARIA
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
02.04.07.02 und 2.00 142.50 285.00
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO
02.04.07.03 und 1.00 57.77 57.77
0.30x0.30x0.30m (INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO
02.04.07.04 und 1.00 48.19 48.19
0.30x0.30x0.25m (INTERIORES), E=0.05
02.04.08 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002 PARA
02.04.08.01 m 12.00 6.35 76.20
AGUA CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP
02.04.08.02 m 10.00 6.65 66.50
399.003:2007 PARA DESAGUE Ø=2"x3 M
02.05 LAVADERO I.E. SECUNDARIA (01 UND)
02.05.01 TRABAJOS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55
TRAZO, NIVELACION Y REPLANTEO EN
02.05.01.02 m2 11.32 1.84 20.83
ESTRUCTURAS
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 3.70 37.48 138.68
REFINE, NIVELACION Y COMPACTADO EN
02.05.02.02 m2 11.32 1.02 11.55
TERRENO NORMAL
02.05.02.03 RELLENO CON MATERIAL PROPIO m3 2.64 29.50 77.88
02.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.27 25.69 32.63
02.05.03 OBRAS DE CONCRETO SIMPLE
CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M.
02.05.03.01 m3 0.08 339.60 27.17
(TMN6") EN LAVADERO C/MEZCLADORA
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
02.05.03.02 m2 0.22 48.96 10.77
FROTACHADO C/MEZCLADORA
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 0.26 4.35 1.13
ENCOFRADO Y DESENCOFRADO PARA
02.05.04.02 m2 5.20 44.01 228.85
ESTRUCTURAS
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA
02.05.04.03 m3 12.73 448.85 5,713.86
PARA LAVADEROS
02.05.05 ALBAÑILERIA
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
02.05.05.01 m2 1.04 58.08 60.40
Lavaderos)
02.05.06 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA
02.05.06.01 m2 3.13 32.96 103.16
1:2 E=2 cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5
02.05.06.02 m2 4.41 23.98 105.75
cm, H=1.5 MAX
02.05.07 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.05.07.01 und 1.00 176.99 176.99
LAVADERO TIPO I.E. PRIMARIA
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
02.05.07.02 und 2.00 142.50 285.00
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO
02.05.07.03 und 1.00 57.77 57.77
0.30x0.30x0.30m (INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO
02.05.07.04 und 1.00 48.19 48.19
0.30x0.30x0.25m (INTERIORES), E=0.05
02.05.08 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002 PARA
02.05.08.01 m 12.00 6.35 76.20
AGUA CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP
02.05.08.02 m 10.00 6.65 66.50
399.003:2007 PARA DESAGUE Ø=2"x3 M
03 LOCALIDAD TANCARPATA (55 UND)
03.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
03.01.01 TRABAJOS PRELIMINARES
03.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 275.00 0.49 134.75
03.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 275.00 1.84 506.00
03.01.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO
03.01.02.01 m3 136.95 39.86 5,458.83
CONGLOMERADO
03.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 24.20 29.66 717.77
03.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 140.80 25.69 3,617.15
03.01.03 CONCRETO SIMPLE
03.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 165.00 373.75 61,668.75
03.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 24.20 398.69 9,648.30
03.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 401.50 44.48 17,858.72
03.01.03.04 CONCRETO f'c=175 kg/cm2 m3 17.05 448.85 7,652.89
03.01.04 MURO DE LADRILLO
MURO DE LADRILLO KK CARAVISTA DE 18
03.01.04.01 m2 800.80 58.10 46,526.48
HUECOS DE SOGA C/M 1:4 x 1.5cm
EMPEDRADO DE PROTECCION CON PIEDRA
03.01.04.02 m2 15.40 70.33 1,083.08
TAMAÑO 4"-6"
03.01.05 REVOQUES Y ENLUCIDOS
TARRAJEO DE MUROS Y PISOS
03.01.05.01 C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre m2 752.40 16.34 12,294.22
hidraulico)
03.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 12.10 36.55 442.26
03.01.06 PINTURA
PINTURA EN MUROS INTERIORES C/LATEX
03.01.06.01 m2 453.75 11.53 5,231.74
LAVABLE COLOR MARFIL
03.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO
03.01.07.01 ETERNIT(1,14x0.72x0.005m) m2 358.05 66.22 23,710.07

03.01.08 CARPINTERIA METALICA


SUMINISTRO E INSTALACION DE PUERTA
03.01.08.01 und 55.00 363.74 20,005.70
METALICA 1.80x0.70m, INCL. MARCO Y PINTADO
03.01.09 CARPINTERIA DE MADERA
VENTANA DE MADERA TORNILLO INC. MALLA
03.01.09.01 m2 9.90 75.90 751.41
MOSQUITERA
03.01.09.02 COBERTURA DE MADERA PARA TECHO und 55.00 97.95 5,387.25
03.01.10 SISTEMA DE AGUA FRIA
03.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 520.85 3.65 1,901.10
03.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
03.01.11.01 TEE PVC-SAP 1/2" pza 110.00 20.85 2,293.50
03.01.11.02 CODO PVC SAP 1/2" pza 330.00 15.59 5,144.70
03.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 110.00 51.25 5,637.50
SUMINISTRO E INSTALACION DE DUCHA
03.01.11.04 und 55.00 33.08 1,819.40
INCLUIDO ACCESORIOS
03.01.12 SISTEMA DE DESAGUE
03.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 530.75 4.02 2,133.62
03.01.12.02 TUBERIA Ø=4" PVC SAL m 200.75 3.65 732.74
03.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
03.01.13.01 CODO PVC SAL 2"X90° pza 385.00 11.77 4,531.45
03.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 55.00 15.53 854.15
03.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 165.00 16.11 2,658.15
03.01.14 ADITAMIENTOS VARIOS
03.01.14.01 SUMIDEROS DE BRONCE 2" und 55.00 12.25 673.75
03.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 110.00 11.09 1,219.90
INODORO DE LOZA VITRIFICADA COLOR BLANCO
03.01.14.03 und 55.00 147.40 8,107.00
INCLUYE TANQUE
03.01.14.04 ACCESORIOS DE LOZA und 55.00 64.86 3,567.30
SUMINISTRO E INSTALACION DE TUBERIA DE
03.01.14.05 VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y GLB 55.00 29.15 1,603.25
ACCESORIOS
SUMINISTRO E INSTALACION DE LAVATORIO DE
03.01.14.06 und 55.00 124.59 6,852.45
LOZA COLOR BLANCO INCLUIDO ACCESORIOS
SUMINISTRO E INSTALACION DE CAJA DE
03.01.14.07 und 110.00 129.89 14,287.90
REGISTRO DE 12"x24"
03.01.15 INSTALACIONES ELECTRICAS
03.01.15.01 SALIDA DE CENTRO DE LUZ pto 55.00 49.14 2,702.70
03.01.15.02 TUBERIA PVC SEL 5/8" m 126.50 4.15 524.98
03.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 308.00 2.28 702.24
03.01.15.04 TABLEROS DISTRIBUCION pza 55.00 89.04 4,897.20
03.01.16 CONSTRUCCION POZO PERCOLADOR
03.01.16.01 TRABAJOS PRELIMINARES
03.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 172.70 0.49 84.62
03.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 172.20 1.84 316.85
03.01.16.02 MOVIMIENTO DE TIERRAS
03.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 89.10 39.86 3,551.53
RELLENO CON MATERIAL PROPIO
03.01.16.02.02 m3 13.20 29.66 391.51
SELECCIONADO
03.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 47.85 89.30 4,273.01
03.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 111.65 25.69 2,868.29
03.01.16.03 TAPA DE CONCRETO
03.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 9.35 448.85 4,196.75
03.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 100.10 44.48 4,452.45
03.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,157.75 4.35 5,036.21
03.01.16.04 ANILLO DE CONCRETO
03.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 3.85 355.98 1,370.52
03.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.00 44.48 2,935.68
03.01.16.05 MURO DE LADRILLO
MURO DE LADRILLO ARTESANAL AMARRE DE
03.01.16.05.01 m2 229.90 48.94 11,251.31
SOGA, JUNTA 1.5 CM MORTERO 1:1:5
03.01.16.06 SISTEMA DE DESAGUE LLEGADA
03.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 107.25 4.02 431.15
03.01.16.06.02 CODO PVC SAL 2"X90° pza 55.00 11.77 647.35
03.01.17 INSTALACION DEL BIODIGESTOR
03.01.17.01 TRABAJOS PRELIMINARES
03.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 207.90 0.49 101.87
03.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 207.90 1.84 382.54
03.01.17.02 MOVIMIENTO DE TIERRAS
03.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 170.94 39.86 6,813.67
RELLENO CON MATERIAL PROPIO
03.01.17.02.02 m3 129.10 29.66 3,829.11
SELECCIONADO
03.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 213.67 25.69 5,489.18
03.01.17.03 CONCRETO SIMPLE
03.01.17.03.01 SOLADO E=4" m2 35.75 39.68 1,418.56
03.01.17.04 CONCRETO ARMADO
03.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 39.60 448.85 17,774.46
03.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.60 44.48 11,057.73
03.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 306.35 4.35 1,332.62
03.01.17.05 BIODIGESTOR
SUMINISTRO E INSTALACION DE BIODIGESTOR
03.01.17.05.01 und 51.00 779.59 39,759.09
AUTOLIMPIABLE DE PVC DE 600 LTS
SUMINISTRO E INSTALACION DE BIODIGESTOR
03.01.17.05.02 und 4.00 1,320.79 5,283.16
AUTOLIMPIABLE DE PVC DE 1300 LTS
03.01.17.06 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.01.17.06.01 m2 196.35 32.48 6,377.45
MEZCLA 1:2 E=2 cm H=1.5 Max
03.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
03.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 55.00 4.02 221.10
SUMINISTRO E INSTALACION DE VALVULA DE
03.01.17.07.02 und 55.00 29.86 1,642.30
PVC DE 2"
03.02 LAVADERO INTRADOMICILIARIO (51 UND)
03.02.01 OBRAS PRELIMINARES
03.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 258.06 0.49 126.45
03.02.01.02 TRAZO Y REPLANTEO m2 258.06 1.84 474.83
03.02.02 MOVIMIENTO DE TIERRAS
03.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 57.74 37.48 2,164.10
RELLENO Y COMPACTADO DE ZANJA CON
03.02.02.02 m3 47.43 13.11 621.81
MATERIAL PROPIO CLASIFICADO
03.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.86 25.69 304.68
03.02.03 OBRAS DE CONCRETO ARMADO
03.02.03.01 CONCRETO f'c=175 kg/cm2 m3 5.36 448.85 2,405.84
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 170.73 44.48 7,594.07
03.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 201.71 4.35 877.44
03.02.04 MURO DE LADRILLO
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
03.02.04.01 m2 33.72 47.74 1,609.79
Lavaderos)
03.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.02.05.01 m2 60.13 32.48 1,953.02
MEZCLA 1:2 E=2 cm H=1.5 Max
03.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 115.06 29.76 3,424.19
03.02.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE LAVADERO
03.02.06.01 und 51.00 136.31 6,951.81
INTRADOMICILIARIA
03.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
03.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 255.00 3.35 854.25
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01
03.03
UND)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55
TRAZO, NIVELACION Y REPLANTEO EN
03.03.01.02 m2 11.32 1.84 20.83
ESTRUCTURAS
03.03.02 MOVIMIENTO DE TIERRAS
03.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48 102.70
REFINE, NIVELACION Y COMPACTADO EN
03.03.02.02 m2 11.32 1.02 11.55
TERRENO NORMAL
03.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
03.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69 34.42
03.03.03 OBRAS DE CONCRETO SIMPLE
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
03.03.03.01 m2 2.20 48.96 107.71
FROTACHADO C/MEZCLADORA
03.03.04 OBRAS DE CONCRETO ARMADO
03.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35 36.32
ENCOFRADO Y DESENCOFRADO PARA
03.03.04.02 m2 4.09 44.01 180.00
ESTRUCTURAS
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA
03.03.04.03 m3 0.21 448.85 94.26
PARA LAVADEROS
03.03.05 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA
03.03.05.01 m2 2.49 32.96 82.07
1:2 E=2 cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5
03.03.05.02 m2 2.11 23.98 50.60
cm, H=1.5 MAX
03.03.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.03.06.01 und 1.00 176.99 176.99
LAVADERO I.E. INICIAL
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
03.03.06.02 und 2.00 142.50 285.00
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO
03.03.06.03 und 1.00 57.77 57.77
0.30x0.30x0.30m (INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO
03.03.06.04 und 1.00 48.19 48.19
0.30x0.30x0.25m (INTERIORES), E=0.05
03.03.07 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002:2009
03.03.07.01 m 12.00 6.35 76.20
C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP
03.03.07.02 m 10.00 6.65 66.50
399.003:2007 PARA DESAGUE Ø=2"x3 M
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA
03.04
(01 UND)
03.04.01 TRABAJOS PRELIMINARES
03.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.49 5.87
TRAZO, NIVELACION Y REPLANTEO EN
03.04.01.02 m2 11.98 1.84 22.04
ESTRUCTURAS
03.04.02 MOVIMIENTO DE TIERRAS
03.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 37.48 104.94
REFINE, NIVELACION Y COMPACTADO EN
03.04.02.02 m2 11.98 1.02 12.22
TERRENO NORMAL
03.04.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
03.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 25.69 36.22
03.04.03 OBRAS DE CONCRETO SIMPLE
CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M.
03.04.03.01 m3 0.06 339.60 20.38
(TMN6") EN LAVADERO C/MEZCLADORA
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
03.04.03.02 m2 2.86 48.96 140.03
FROTACHADO C/MEZCLADORA
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.35 49.98
ENCOFRADO Y DESENCOFRADO PARA
03.04.04.02 m2 4.33 44.01 190.56
ESTRUCTURAS
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA
03.04.04.03 m3 0.31 448.85 139.14
PARA LAVADEROS
03.04.05 ALBAÑILERIA
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
03.04.05.01 m2 0.36 58.08 20.91
Lavaderos)
03.04.06 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA
03.04.06.01 m2 3.51 32.96 115.69
1:2 E=2 cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5
03.04.06.02 m2 3.29 23.98 78.89
cm, H=1.5 MAX
03.04.07 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.04.07.01 und 1.00 176.99 176.99
LAVADERO TIPO I.E. PRIMARIA
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
03.04.07.02 und 2.00 142.50 285.00
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO
03.04.07.03 und 1.00 57.77 57.77
0.30x0.30x0.30m (INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO
03.04.07.04 und 1.00 48.19 48.19
0.30x0.30x0.25m (INTERIORES), E=0.05
03.04.08 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002 PARA
03.04.08.01 m 12.00 6.35 76.20
AGUA CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP
03.04.08.02 m 10.00 6.65 66.50
399.003:2007 PARA DESAGUE Ø=2"x3 M
04 LOCALIDAD TARACA (55 UND)
04.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
04.01.01 TRABAJOS PRELIMINARES
04.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 275.00 0.49 134.75
04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 275.00 1.84 506.00
04.01.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO
04.01.02.01 m3 136.95 39.86 5,458.83
CONGLOMERADO
04.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 24.20 29.66 717.77
04.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 140.80 25.69 3,617.15
04.01.03 CONCRETO SIMPLE
04.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 165.00 373.75 61,668.75
04.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 24.20 398.69 9,648.30
04.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 401.50 44.48 17,858.72
04.01.03.04 CONCRETO f'c=175 kg/cm2 m3 17.05 448.85 7,652.89
04.01.04 MURO DE LADRILLO
MURO DE LADRILLO KK CARAVISTA DE 18
04.01.04.01 m2 800.80 58.10 46,526.48
HUECOS DE SOGA C/M 1:4 x 1.5cm
EMPEDRADO DE PROTECCION CON PIEDRA
04.01.04.02 m2 15.40 70.33 1,083.08
TAMAÑO 4"-6"
04.01.05 REVOQUES Y ENLUCIDOS
TARRAJEO DE MUROS Y PISOS
04.01.05.01 C/IMPERMEBILIZANTE P/CAMARA (UBS arrastre m2 752.40 16.34 12,294.22
hidraulico)
04.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 12.10 36.55 442.26
04.01.06 PINTURA
PINTURA EN MUROS INTERIORES C/LATEX
04.01.06.01 m2 453.75 11.53 5,231.74
LAVABLE COLOR MARFIL
04.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO
04.01.07.01 ETERNIT(1,14x0.72x0.005m) m2 358.05 66.22 23,710.07

04.01.08 CARPINTERIA METALICA


SUMINISTRO E INSTALACION DE PUERTA
04.01.08.01 und 55.00 363.74 20,005.70
METALICA 1.80x0.70m, INCL. MARCO Y PINTADO
04.01.09 CARPINTERIA DE MADERA
VENTANA DE MADERA TORNILLO INC. MALLA
04.01.09.01 m2 9.90 75.90 751.41
MOSQUITERA
04.01.09.02 COBERTURA DE MADERA PARA TECHO und 55.00 97.95 5,387.25
04.01.10 SISTEMA DE AGUA FRIA
04.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 520.85 3.65 1,901.10
04.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
04.01.11.01 TEE PVC-SAP 1/2" pza 110.00 20.85 2,293.50
04.01.11.02 CODO PVC SAP 1/2" pza 330.00 15.59 5,144.70
04.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 110.00 51.25 5,637.50
SUMINISTRO E INSTALACION DE DUCHA
04.01.11.04 und 55.00 33.08 1,819.40
INCLUIDO ACCESORIOS
04.01.12 SISTEMA DE DESAGUE
04.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 530.75 4.02 2,133.62
04.01.12.02 TUBERIA Ø=4" PVC SAL m 200.75 3.65 732.74
04.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
04.01.13.01 CODO PVC SAL 2"X90° pza 385.00 11.77 4,531.45
04.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 55.00 15.53 854.15
04.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 165.00 16.11 2,658.15
04.01.14 ADITAMIENTOS VARIOS
04.01.14.01 SUMIDEROS DE BRONCE 2" und 55.00 12.25 673.75
04.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 110.00 11.09 1,219.90
INODORO DE LOZA VITRIFICADA COLOR BLANCO
04.01.14.03 und 55.00 147.40 8,107.00
INCLUYE TANQUE
04.01.14.04 ACCESORIOS DE LOZA und 55.00 64.86 3,567.30
SUMINISTRO E INSTALACION DE TUBERIA DE
04.01.14.05 VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y GLB 55.00 29.15 1,603.25
ACCESORIOS
SUMINISTRO E INSTALACION DE LAVATORIO DE
04.01.14.06 und 55.00 124.59 6,852.45
LOZA COLOR BLANCO INCLUIDO ACCESORIOS
SUMINISTRO E INSTALACION DE CAJA DE
04.01.14.07 und 110.00 129.89 14,287.90
REGISTRO DE 12"x24"
04.01.15 INSTALACIONES ELECTRICAS
04.01.15.01 SALIDA DE CENTRO DE LUZ pto 55.00 49.14 2,702.70
04.01.15.02 TUBERIA PVC SEL 5/8" m 126.50 4.15 524.98
04.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 308.00 2.28 702.24
04.01.15.04 TABLEROS DISTRIBUCION pza 55.00 89.04 4,897.20
04.02 CONSTRUCCION POZO PERCOLADOR
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 172.70 0.49 84.62
04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 172.20 1.84 316.85
04.02.02 MOVIMIENTO DE TIERRAS
04.02.02.01 EXCAVACION A MANO TERRENO NORMAL m3 89.10 39.86 3,551.53
04.02.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 13.20 29.66 391.51
04.02.02.03 FILTRO DE GRAVA CLASIFICADA m3 47.85 89.30 4,273.01
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 111.65 25.69 2,868.29
04.02.03 TAPA DE CONCRETO
04.02.03.01 CONCRETO f'c=175 kg/cm2 m3 9.35 448.85 4,196.75
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 100.10 44.48 4,452.45
04.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,157.75 4.35 5,036.21
04.02.04 ANILLO DE CONCRETO
04.02.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 3.85 355.98 1,370.52
04.02.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.00 44.48 2,935.68
04.02.05 MURO DE LADRILLO
MURO DE LADRILLO ARTESANAL AMARRE DE
04.02.05.01 m2 229.90 48.94 11,251.31
SOGA, JUNTA 1.5 CM MORTERO 1:1:5
04.02.06 SISTEMA DE DESAGUE LLEGADA
04.02.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 107.25 4.02 431.15
04.02.06.02 CODO PVC SAL 2"X90° pza 55.00 11.77 647.35
04.03 INSTALACION DEL BIODIGESTOR
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 207.90 0.49 101.87
04.03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 207.90 1.84 382.54
04.03.02 MOVIMIENTO DE TIERRAS
04.03.02.01 EXCAVACION A MANO TERRENO NORMAL m3 170.94 39.86 6,813.67
04.03.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 129.10 29.66 3,829.11
04.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 213.67 25.69 5,489.18
04.03.03 CONCRETO SIMPLE
04.03.03.01 SOLADO E=4" m2 35.75 39.68 1,418.56
04.03.04 CONCRETO ARMADO
04.03.04.01 CONCRETO f'c=175 kg/cm2 m3 39.60 448.85 17,774.46
04.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.60 44.48 11,057.73
04.03.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 306.35 4.35 1,332.62
04.03.05 BIODIGESTOR
SUMINISTRO E INSTALACION DE BIODIGESTOR
04.03.05.01 und 51.00 779.59 39,759.09
AUTOLIMPIABLE DE PVC DE 600 LTS
SUMINISTRO E INSTALACION DE BIODIGESTOR
04.03.05.02 und 4.00 1,320.79 5,283.16
AUTOLIMPIABLE DE PVC DE 1300 LTS
04.03.06 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.03.06.01 m2 196.35 32.48 6,377.45
MEZCLA 1:2 E=2 cm H=1.5 Max
04.03.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
04.03.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 55.00 4.02 221.10
SUMINISTRO E INSTALACION DE VALVULA DE PVC
04.03.07.02 und 55.00 29.86 1,642.30
DE 2"
04.04 LAVADERO INTRADOMICILIARIO (51 UND)
04.04.01 OBRAS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 258.06 0.49 126.45
04.04.01.02 TRAZO Y REPLANTEO m2 258.06 1.84 474.83
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 57.74 37.48 2,164.10
RELLENO Y COMPACTADO DE ZANJA CON
04.04.02.02 m3 47.43 13.11 621.81
MATERIAL PROPIO CLASIFICADO
04.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.86 25.69 304.68
04.04.03 OBRAS DE CONCRETO ARMADO
04.04.03.01 CONCRETO f'c=175 kg/cm2 m3 5.36 448.85 2,405.84
04.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 170.73 44.48 7,594.07
04.04.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 201.71 4.35 877.44
04.04.04 MURO DE LADRILLO
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
04.04.04.01 m2 33.72 47.74 1,609.79
Lavaderos)
04.04.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.04.05.01 m2 60.13 32.48 1,953.02
MEZCLA 1:2 E=2 cm H=1.5 Max
04.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 115.06 29.76 3,424.19
04.04.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE LAVADERO
04.04.06.01 und 51.00 136.31 6,951.81
INTRADOMICILIARIA
04.04.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
04.04.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 255.00 3.35 854.25
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01
04.05
UND)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.49 5.55
TRAZO, NIVELACION Y REPLANTEO EN
04.05.01.02 m2 11.32 1.84 20.83
ESTRUCTURAS
04.05.02 MOVIMIENTO DE TIERRAS
04.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 37.48 102.70
REFINE, NIVELACION Y COMPACTADO EN
04.05.02.02 m2 11.32 1.02 11.55
TERRENO NORMAL
04.05.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
04.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 25.69 34.42
04.05.03 OBRAS DE CONCRETO SIMPLE
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
04.05.03.01 m2 2.20 48.96 107.71
FROTACHADO C/MEZCLADORA
04.05.04 OBRAS DE CONCRETO ARMADO
04.05.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.35 36.32
ENCOFRADO Y DESENCOFRADO PARA
04.05.04.02 m2 4.09 44.01 180.00
ESTRUCTURAS
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA
04.05.04.03 m3 0.21 448.85 94.26
PARA LAVADEROS
04.05.05 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA
04.05.05.01 m2 2.49 32.96 82.07
1:2 E=2 cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5
04.05.05.02 m2 2.11 23.98 50.60
cm, H=1.5 MAX
04.05.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.05.06.01 und 1.00 176.99 176.99
LAVADERO I.E. INICIAL
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
04.05.06.02 und 2.00 142.50 285.00
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO
04.05.06.03 und 1.00 57.77 57.77
0.30x0.30x0.30m (INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO
04.05.06.04 und 1.00 48.19 48.19
0.30x0.30x0.25m (INTERIORES), E=0.05
04.05.07 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002:2009
04.05.07.01 m 12.00 6.35 76.20
C-10, P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP
04.05.07.02 m 10.00 6.65 66.50
399.003:2007 PARA DESAGUE Ø=2"x3 M
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA
04.06
(01 UND)
04.06.01 TRABAJOS PRELIMINARES
04.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.49 5.87
TRAZO, NIVELACION Y REPLANTEO EN
04.06.01.02 m2 11.98 1.84 22.04
ESTRUCTURAS
04.06.02 MOVIMIENTO DE TIERRAS
04.06.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 37.48 104.94
REFINE, NIVELACION Y COMPACTADO EN
04.06.02.02 m2 11.98 1.02 12.22
TERRENO NORMAL
04.06.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 29.50 47.79
04.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 25.69 36.22
04.06.03 OBRAS DE CONCRETO SIMPLE
CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M.
04.06.03.01 m3 0.06 339.60 20.38
(TMN6") EN LAVADERO C/MEZCLADORA
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
04.06.03.02 m2 2.86 48.96 140.03
FROTACHADO C/MEZCLADORA
04.06.04 OBRAS DE CONCRETO ARMADO
04.06.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.35 49.98
ENCOFRADO Y DESENCOFRADO PARA
04.06.04.02 m2 4.33 44.01 190.56
ESTRUCTURAS
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA
04.06.04.03 m3 0.31 448.85 139.14
PARA LAVADEROS
04.06.05 ALBAÑILERIA
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
04.06.05.01 m2 0.36 58.08 20.91
Lavaderos)
04.06.06 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA
04.06.06.01 m2 3.51 32.96 115.69
1:2 E=2 cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5
04.06.06.02 m2 3.29 23.98 78.89
cm, H=1.5 MAX
04.06.07 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.06.07.01 und 1.00 176.99 176.99
LAVADERO TIPO I.E. PRIMARIA
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
04.06.07.02 und 2.00 142.50 285.00
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO
04.06.07.03 und 1.00 57.77 57.77
0.30x0.30x0.30m (INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO
04.06.07.04 und 1.00 48.19 48.19
0.30x0.30x0.25m (INTERIORES), E=0.05
04.06.08 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002 PARA
04.06.08.01 m 12.00 6.35 76.20
AGUA CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP
04.06.08.02 m 10.00 6.65 66.50
399.003:2007 PARA DESAGUE Ø=2"x3 M

01 LOCALIDAD SANTA LUCIA


CAPACITACION EN EDUCACION SANITARIA,
01.01
PROMOCION DE LA SALUD Y AOM
01.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
TALLER IMPORTANCIA DE LA ORGANIZACION Y
01.01.01.01 Tall 1.00 940.60 940.60
PARTICIPACION CIUDADANA
01.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60 940.60
EDUCACION SANITARIA (EDUCACION PARA LA
01.01.02
HIGIENE Y SALUD)
TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y
01.01.02.01 Tall 1.00 940.61 940.61
SALUD (Valoracion del agua)
TALLER DE IMPORTANCIA DE LA DECUADA
01.01.02.02 Tall 1.00 940.61 940.61
ELIMINACION DE EXCRETAS
TALLER DE PREVENCION DE ENFERMEDADES
01.01.02.03 LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE Tall 1.00 940.61 940.61
PERSONAL DEL HOGAR Y COMUNAL
CONSTITUCION DEL COMITE DE HIGIENE DEL
01.01.02.04 HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE Tall 1.00 940.61 940.61
EN LA II.EE.
DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA
01.01.02.05 Men 2.00 84.74 169.48
Y SANEAMIENTO (SPOT PUBLICITARIO)
01.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
TALLER DE ADMINIST., CONTABILIDAD Y
01.01.03.01 FORMULACION DE PLAN OPERATIVO ANUAL DE LA Tall 1.00 940.61 940.61
JASS
TALLER RECONOCIMIENTO DE LOS
01.01.03.02 COMPONENTES DEL SISTEMA Y OPERACION Y Tall 1.00 940.61 940.61
MANTENEMIENTO SIST. AGUA POTABLE
01.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61 940.61
TALLER DE CLORACION Y DESINFECCION DE
01.01.03.04 Tall 1.00 1,110.11 1,110.11
AGUA PARA CONSUMO HUMANO
01.02 FLETE
01.02.01 FLETE RURAL
01.02.01.01 FLETE RURAL GLB 1.00 25,395.57 25,395.57
01.02.02 FLETE TERRESTRE
01.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00 4,725.00
01.02.02.02 FLETE TERRESTRE GLB 1.00 10,576.27 10,576.27
01.03 MITIGACION AMBIENTAL
01.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00 2,840.00
PROGRAMA DE CONSERVACION, RESTAURACION Y
01.03.02 COMPESACION DE COBERTURA VEGETAL GLB 1.00 1,712.00 1,712.00
(REFORESTACION)
01.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00 3,400.00
01.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00 1,000.00
PROGRAMA DE CAPACITACION Y EDUCACION
01.03.05 GLB 1.00 500.00 500.00
AMBIENTAL
01.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00 3,600.00
01.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00 600.00
01.04 CONTROL Y SEGURIDAD EN OBRA
01.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 6,959.68 6,959.68
02 LOCALIDAD PUEBLO LIBRE
CAPACITACION EN EDUCACION SANITARIA,
02.01
PROMOCION DE LA SALUD Y AOM
02.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
TALLER IMPORTANCIA DE LA ORGANIZACION Y
02.01.01.01 Tall 1.00 940.60 940.60
PARTICIPACION CIUDADANA
02.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60 940.60
EDUCACION SANITARIA (EDUCACION PARA LA
02.01.02
HIGIENE Y SALUD)
TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y
02.01.02.01 Tall 1.00 940.61 940.61
SALUD (Valoracion del agua)
TALLER DE IMPORTANCIA DE LA DECUADA
02.01.02.02 Tall 1.00 940.61 940.61
ELIMINACION DE EXCRETAS
TALLER DE PREVENCION DE ENFERMEDADES
02.01.02.03 LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE Tall 1.00 940.61 940.61
PERSONAL DEL HOGAR Y COMUNAL
CONSTITUCION DEL COMITE DE HIGIENE DEL
02.01.02.04 HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE Tall 1.00 940.61 940.61
EN LA II.EE.
DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA
02.01.02.05 Men 2.00 84.74 169.48
Y SANEAMIENTO (SPOT PUBLICITARIO)
02.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
TALLER DE ADMINIST., CONTABILIDAD Y
02.01.03.01 FORMULACION DE PLAN OPERATIVO ANUAL DE LA Tall 1.00 940.61 940.61
JASS
TALLER RECONOCIMIENTO DE LOS
02.01.03.02 COMPONENTES DEL SISTEMA Y OPERACION Y Tall 1.00 940.61 940.61
MANTENEMIENTO SIST. AGUA POTABLE
02.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61 940.61
TALLER DE CLORACION Y DESINFECCION DE
02.01.03.04 Tall 1.00 1,110.11 1,110.11
AGUA PARA CONSUMO HUMANO
02.02 FLETE
02.02.01 FLETE RURAL
02.02.01.01 FLETE RURAL GLB 1.00 34,884.02 34,884.02
02.02.02 FLETE TERRESTRE
02.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00 4,725.00
02.02.02.02 FLETE TERRESTRE GLB 1.00 17,338.98 17,338.98
02.02.03 MITIGACION AMBIENTAL
02.02.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00 2,840.00
PROGRAMA DE CONSERVACION, RESTAURACION
02.02.03.02 Y COMPESACION DE COBERTURA VEGETAL GLB 1.00 1,712.00 1,712.00
(REFORESTACION)
02.02.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00 3,400.00
02.02.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00 1,000.00
PROGRAMA DE CAPACITACION Y EDUCACION
02.02.03.05 GLB 1.00 500.00 500.00
AMBIENTAL
02.02.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00 3,600.00
02.02.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00 600.00
02.02.04 CONTROL Y SEGURIDAD EN OBRA
02.02.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 9,221.36 9,221.36
03 LOCALIDAD TANCARPATA
CAPACITACION EN EDUCACION SANITARIA,
03.01
PROMOCION DE LA SALUD Y AOM
03.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
TALLER IMPORTANCIA DE LA ORGANIZACION Y
03.01.01.01 Tall 1.00 940.60 940.60
PARTICIPACION CIUDADANA
03.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60 940.60
EDUCACION SANITARIA (EDUCACION PARA LA
03.01.02
HIGIENE Y SALUD)
TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y
03.01.02.01 Tall 1.00 940.61 940.61
SALUD (Valoracion del agua)
TALLER DE IMPORTANCIA DE LA DECUADA
03.01.02.02 Tall 1.00 940.61 940.61
ELIMINACION DE EXCRETAS
TALLER DE PREVENCION DE ENFERMEDADES
03.01.02.03 LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE Tall 1.00 940.61 940.61
PERSONAL DEL HOGAR Y COMUNAL
CONSTITUCION DEL COMITE DE HIGIENE DEL
03.01.02.04 HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE Tall 1.00 940.61 940.61
EN LA II.EE.
DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA
03.01.02.05 Men 2.00 84.74 169.48
Y SANEAMIENTO (SPOT PUBLICITARIO)
03.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
TALLER DE ADMINIST., CONTABILIDAD Y
03.01.03.01 FORMULACION DE PLAN OPERATIVO ANUAL DE LA Tall 1.00 940.61 940.61
JASS
TALLER RECONOCIMIENTO DE LOS
03.01.03.02 COMPONENTES DEL SISTEMA Y OPERACION Y Tall 1.00 940.61 940.61
MANTENEMIENTO SIST. AGUA POTABLE
03.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61 940.61
TALLER DE CLORACION Y DESINFECCION DE
03.01.03.04 Tall 1.00 1,110.11 1,110.11
AGUA PARA CONSUMO HUMANO
03.02 FLETE
03.02.01 FLETE RURAL
03.02.01.01 FLETE RURAL GLB 1.00 15,348.97 15,348.97
03.02.02 FLETE TERRESTRE
03.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00 4,725.00
03.02.02.02 FLETE TERRESTRE GLB 1.00 6,864.41 6,864.41
03.03 MITIGACION AMBIENTAL
03.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00 2,840.00
PROGRAMA DE CONSERVACION, RESTAURACION Y
03.03.02 COMPESACION DE COBERTURA VEGETAL GLB 1.00 1,712.00 1,712.00
(REFORESTACION)
03.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00 3,400.00
03.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00 1,000.00
PROGRAMA DE CAPACITACION Y EDUCACION
03.03.05 GLB 1.00 500.00 500.00
AMBIENTAL
03.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00 3,600.00
03.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00 600.00
03.04 CONTROL Y SEGURIDAD EN OBRA
03.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 4,564.96 4,564.96
04 LOCALIDAD TARACA
CAPACITACION EN EDUCACION SANITARIA,
04.01
PROMOCION DE LA SALUD Y AOM
04.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
TALLER IMPORTANCIA DE LA ORGANIZACION Y
04.01.01.01 Tall 1.00 940.60 940.60
PARTICIPACION CIUDADANA
04.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 940.60 940.60
EDUCACION SANITARIA (EDUCACION PARA LA
04.01.02
HIGIENE Y SALUD)
TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y
04.01.02.01 Tall 1.00 940.61 940.61
SALUD (Valoracion del agua)
TALLER DE IMPORTANCIA DE LA DECUADA
04.01.02.02 Tall 1.00 940.61 940.61
ELIMINACION DE EXCRETAS
TALLER DE PREVENCION DE ENFERMEDADES
04.01.02.03 LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE Tall 1.00 940.61 940.61
PERSONAL DEL HOGAR Y COMUNAL
CONSTITUCION DEL COMITE DE HIGIENE DEL
04.01.02.04 HOGAR Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE Tall 1.00 940.61 940.61
EN LA II.EE.
DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA
04.01.02.05 Men 2.00 84.74 169.48
Y SANEAMIENTO (SPOT PUBLICITARIO)
04.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
TALLER DE ADMINIST., CONTABILIDAD Y
04.01.03.01 FORMULACION DE PLAN OPERATIVO ANUAL DE LA Tall 1.00 940.61 940.61
JASS
TALLER RECONOCIMIENTO DE LOS
04.01.03.02 COMPONENTES DEL SISTEMA Y OPERACION Y Tall 1.00 940.61 940.61
MANTENEMIENTO SIST. AGUA POTABLE
04.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 940.61 940.61
TALLER DE CLORACION Y DESINFECCION DE
04.01.03.04 Tall 1.00 1,110.11 1,110.11
AGUA PARA CONSUMO HUMANO
04.02 FLETE
04.02.01 FLETE RURAL
04.02.01.01 FLETE RURAL GLB 1.00 15,348.97 15,348.97
04.02.02 FLETE TERRESTRE
04.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,725.00 4,725.00
04.02.02.02 FLETE TERRESTRE GLB 1.00 7,372.78 7,372.78
04.03 MITIGACION AMBIENTAL
04.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,840.00 2,840.00
PROGRAMA DE CONSERVACION, RESTAURACION Y
04.03.02 COMPESACION DE COBERTURA VEGETAL GLB 1.00 1,712.00 1,712.00
(REFORESTACION)
04.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,400.00 3,400.00
04.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 1,000.00 1,000.00
PROGRAMA DE CAPACITACION Y EDUCACION
04.03.05 GLB 1.00 500.00 500.00
AMBIENTAL
04.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,600.00 3,600.00
04.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 600.00 600.00
04.04 CONTROL Y SEGURIDAD EN OBRA
04.04.01 IMPLEMENTOS DE SEGURIDAD PUEBLO LIBRE GLB 1.00 4,564.96 4,564.96

COSTO DIRECTO 5,121,687.49

GASTOS GENERALES (8%) 408,710.66

UTILIDAD (7%) 358,518.12

==================

SUB TOTAL 5,888,916.27

IGV (18%) 1,060,004.93

==================

PRESUPUESTO DE OBRA 6,948,921.20

0.90
AL 97%

ITEM DESCRIPCIÓN UNIDAD METRADO PU SUB TOTAL

01 LOCALIDAD SANTA LUCIA


01.01 CONSTRUCCIONES PROVISIONALES
OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y
01.01.01 m2 100.00 43.21 4,321.35
VESTUARIOS
ALQUILER DE PREDIOS PARA CAMPAMENTOS Y
01.01.02 mes 6.00 485.00 2,910.00
ALMACENES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x
01.01.03 und 1.00 1,493.63 1,493.63
7.20 m
01.02 CAPTACION TIPO LADERA (ROBLEMONTE)
01.02.01 TRABAJOS PRELIMINARES
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.48 23.29
01.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.78 64.25
01.02.02 MOVIMIENTO DE TIERRAS

01.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 16.23 38.66 627.52

RELLENO Y COMPACTADO CON MATERIAL PROPIO A


01.02.02.02 m3 2.55 28.62 72.97
MANO C/PISON
01.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.71 208.21
01.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 17.10 24.92 426.12
01.02.03 CONCRETO SIMPLE
01.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 400.77 685.32
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 43.15 113.91
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
01.02.03.03 m2 0.50 117.47 58.73
PM
01.02.04 CONCRETO ARMADO
01.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 498.42 787.51
01.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 43.15 773.60
01.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.22 287.18
01.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTES
01.02.05.01 m2 5.53 31.51 174.22
M=1:3 e=1.5cm
01.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 28.87 347.85
01.02.06 PINTURA

01.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 12.83 154.64

01.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE

01.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 170.57 257.56


01.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 92.90 25.08
01.02.08 CARPINTERIA METALICA
01.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 174.44 174.44
01.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 273.08 273.08
01.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.02.09.01 CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO und 1.00 486.25 486.25
HIDRAULICO y VENTILACION Ø=2")
01.02.10 CERCO PERIMETRICO EN CAPTACION
01.02.10.01 TRABAJOS PRELIMINARES
01.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.78 42.84
01.02.10.02 MOVIMIENTO DE TIERRAS
01.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 38.66 22.81
01.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 24.92 18.19
01.02.10.03 CONCRETO SIMPLE
01.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 345.30 203.73
01.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
01.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 43.15 67.31
01.02.10.05 COLOCADO DE ROLLIZOS
01.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 41.55 540.09
01.02.10.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
01.02.10.06.01 m 33.80 3.69 124.59
C/ESMALTE SINTETICO
01.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
01.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 21.55 517.28
01.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
01.02.10.08.01 und 1.00 188.28 188.28
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
01.03 LINEA DE CONDUCCION (L=1102.00 m)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,102.00 0.48 523.78
01.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 1,102.00 1.48 1,635.48
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
01.03.01.03 m 1,102.00 1.48 1,635.48
ZANJAS REDES Y LINEAS
01.03.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
01.03.02.01 m3 396.72 48.33 19,171.65
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
01.03.02.02 m3 44.08 54.13 2,385.87
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
01.03.02.03 m 1,102.00 1.76 1,934.78
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA
01.03.02.04 m 110.20 5.90 649.92
Y FIJA P/TUBERIA

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


01.03.02.05 m3 165.30 35.31 5,836.41
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


01.03.02.06 DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.50 m3 27.55 63.21 1,741.57
m
01.03.02.07 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 27.55 24.92 686.53
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.03.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SP C-
01.03.03.01 m 1,102.00 6.97 7,685.68
10, Ø=1"
01.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 136.12 136.12
01.03.04 PRUEBA HIDRAULICA
01.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 1,102.00 1.46 1,614.10
01.03.05 CAMARA ROMPE PRESION T-6 (01 UND)
01.03.05.01 OBRAS PRELIMINARES
01.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.44 0.48 0.69
01.03.05.01.02 TRAZO Y REPLANTEO m2 1.44 1.78 2.57
01.03.05.02 MOVIMIENTO DE TIERRAS
01.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.58 38.66 61.09
01.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.98 24.92 49.34
01.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 1.44 7.71 11.11
01.03.05.03 OBRAS DE CONCRETO SIMPLE
01.03.05.03.01 SOLADO E=4" m3 1.21 34.74 42.03
01.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.01 400.77 4.01
01.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 43.15 8.63
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
01.03.05.03.04 m2 0.50 117.47 58.73
PM
01.03.05.04 OBRAS DE CONCRETO ARMADO
01.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 0.79 530.29 418.93
01.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.10 43.15 349.48
01.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 37.23 4.22 157.09
01.03.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.03.05.05.01 m2 2.52 31.51 79.39
MEZCLA 1:2 E=2 cm H=1.5 Max
01.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.24 28.87 93.53
01.03.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
01.03.05.06.01 m2 3.24 10.84 35.13
MANOS
01.03.05.07 CARPINTERIA METALICA
01.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 1.00 207.32 207.32
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.03.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.03.05.08.01 und 1.00 290.61 290.61
CRP T6, INGRESO Ø=1" y SALIDA Ø=1"
01.03.06 VALVULA DE PURGA TIPO I (1 UND)
01.03.06.01 OBRAS PRELIMINARES
01.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 0.48 0.48
01.03.06.01.02 TRAZO Y REPLANTEO m2 1.00 1.78 1.78
01.03.06.02 MOVIMIENTO DE TIERRAS
01.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.51 38.66 19.72
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
01.03.06.02.02 m3 0.51 12.72 6.49
MANO
01.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.49 7.71 3.78
01.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 0.64 24.92 15.95
01.03.06.03 OBRAS DE CONCRETO SIMPLE
01.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.02 400.77 8.01
01.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.24 43.15 10.36
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
01.03.06.03.03 m2 0.27 117.47 31.72
PM
01.03.06.04 OBRAS DE CONCRETO ARMADO
01.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.35 530.29 185.60
01.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.72 43.15 160.51
01.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 14.94 4.22 63.04
01.03.06.05 REVOQUES Y ENLUCIDOS
01.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 1.44 31.51 45.37
01.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.36 28.87 96.99
01.03.06.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
01.03.06.06.01 m2 2.16 10.84 23.43
MANOS
01.03.06.07 CARPINTERIA METALICA
01.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 1.00 208.39 208.39
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.03.06.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.03.06.08.01 und 1.00 148.47 148.47
VALVULA DE PURGA TIPO I, Ø=1"
01.04 RESERVORIO (V=8.00 m3, 01 UND)
01.04.01 OBRAS PRELIMINARES
01.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.48 17.11
01.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.78 64.25
01.04.02 MOVIMIENTO DE TIERRAS
01.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 51.43 38.66 1,988.50
01.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 11.41 7.71 87.99
01.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 64.29 24.92 1,602.06
01.04.03 CONCRETO SIMPLE
01.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 400.77 4.01
01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 43.15 8.63
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
01.04.03.03 m2 0.50 117.47 58.73
PM
01.04.04 OBRAS DE CONCRETO ARMADO
01.04.04.01 SOLADO PARA LOSA FONDO m2 11.41 39.64 452.34
01.04.04.02 CONCRETO f'c=210 kg/cm2 m3 11.27 530.29 5,976.36
01.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 51.29 43.15 2,212.94
01.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 322.94 4.22 1,362.65
01.04.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.04.05.01 m2 31.32 31.51 986.75
MEZCLA 1:2 E=2 cm H=1.5 Max
01.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 40.61 28.87 1,172.29
01.04.06 PINTURA
PINTURA ESMALTE EN MUROS EXTERIORES DE
01.04.06.01 m2 34.92 12.83 448.13
RESERVORIO
01.04.07 CARPINTERIA METALICA
01.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 207.32 414.64
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.04.08
ACCESORIOS
SUMINISTRO E INSTALACIONES DE ACCESORIOS EN
01.04.08.01 und 1.00 1,693.11 1,693.11
RESERVORIO (ING. 1 ", SAL.1")
01.04.09 CERCO PERIMETRICO EN RESERVORIO
01.04.09.01 TRABAJOS PRELIMINARES
01.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.78 64.25
01.04.09.02 MOVIMIENTO DE TIERRAS 0.00
01.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 38.66 27.06
01.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 24.92 18.19
01.04.09.03 CONCRETO SIMPLE 0.00
01.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 345.30 241.71
01.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL 0.00
01.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 43.15 67.31
01.04.09.05 COLOCADO DE ROLLIZOS
01.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 41.55 540.09
01.04.09.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
01.04.09.06.01 m 66.40 3.69 244.75
C/ESMALTE SINTETICO
01.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
01.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 21.55 500.04
01.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
01.04.09.08.01 und 1.00 188.28 188.28
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
01.04.10 CLORADOR POR GOTEO
01.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
CASETA DE MURO DE LADRILLO -CLORADOR POR
01.04.10.01.01
GOTEO
01.04.10.01.01.0 MURO DE LADRILLO PANDERETA (0.10x0.12x0.24)
m2 7.52 53.31 400.90
1 AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm.
MURO DE LADRILLO PANDERETA
01.04.10.01.01.0
INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 m2 4.48 47.88 214.50
2
JUNTA 1.5 cm.
01.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA 0.00
01.04.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 28.20 169.19
1
01.04.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 33.06 197.69
2
01.04.10.01.03 REVOQUES Y ENLUCIDOS
01.04.10.01.03.0 TARRAJEO MUROS DE INTERIORES Y
m2 14.98 29.10 435.92
1 EXTERIORES, CEMENTO : ARENA, 1:5
01.04.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.37 53.47
2
01.04.10.01.04 CARPINTERIA METALICA
01.04.10.01.04.0 SUMINISTRO E INSTALACION DE PUERTA
und 1.00 356.16 356.16
1 METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO
01.04.10.01.05 PINTURAS
01.04.10.01.05.0 PINTURA ESMALTE EN MUROS INTERIORES Y
m2 14.98 10.84 162.46
1 EXTERIORES
01.04.10.01.05.0 PINTURA ANTICORROSIVA Y ESMALTE EN
m2 4.00 11.88 47.53
2 PUERTAS
01.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
SUMINISTRO E INSTALACION DE TANQUE DE
01.04.10.02.01 und 1.00 422.01 422.01
POLIETILENO, CAP=250 LTRS.
01.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
SUMINISTRO Y COLOCACION DE TUBERIAS Y
01.04.10.03.01 GLB 1.00 911.04 911.04
ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO
01.05 RED DE ADUCCION Y DISTRIBUCION (L=4,375.00m)
01.05.01 TRABAJOS PRELIMINARES
01.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,187.50 0.48 1,039.72
01.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 4,375.00 1.48 6,492.94
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
01.05.01.03 m 4,375.00 1.48 6,492.94
ZANJAS REDES Y LINEAS
01.05.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
01.05.02.01 m3 525.00 38.66 20,298.71
SUELTO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
01.05.02.02 m3 1,137.50 48.33 54,970.14
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
01.05.02.03 m3 87.50 54.13 4,736.03
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
01.05.02.04 m 4,375.00 1.76 7,681.19
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA
01.05.02.05 m 4,375.00 5.90 25,802.00
Y FIJA P/TUBERIA

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


01.05.02.06 m3 623.44 35.31 22,012.42
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


01.05.02.07 DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m3 32.81 63.21 2,074.08
m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
01.05.02.08 m3 1,181.25 24.32 28,725.52
PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
01.05.02.09 m3 142.19 60.30 8,573.37
DE PRESTAMO P/TUBERIA, H=0.50 m
01.05.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 87.50 24.92 2,180.44
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-
01.05.03.01 m 1,820.00 7.81 14,211.47
10 DE 1"
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-
01.05.03.02 m 2,555.00 4.69 11,995.21
10 DE 3/4"
01.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 133.61 133.61
01.05.04 PRUEBA HIDRAULICA
01.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 4,375.00 1.46 6,408.06
01.05.05 CAMARA ROMPE PRESION T-7 (11 UND)
01.05.05.01 OBRAS PRELIMINARES
01.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 22.77 0.48 10.83
01.05.05.01.02 TRAZO Y REPLANTEO m2 22.77 1.78 40.64
01.05.05.02 MOVIMIENTO DE TIERRAS
01.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 14.32 38.66 553.68
01.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 9.55 39.72 379.34
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
01.05.05.02.03 m3 2.39 12.72 30.39
MANO
01.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 21.62 7.71 166.72
01.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.28 57.66 73.80
01.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 9.84 24.92 245.21
01.05.05.03 OBRAS DE CONCRETO SIMPLE
01.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.13 400.77 52.10
01.05.05.03.02 SOLADO E=4" m3 1.82 34.74 63.21
01.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.20 43.15 94.92
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
01.05.05.03.04 m2 2.97 117.47 348.88
PM
01.05.05.04 OBRAS DE CONCRETO ARMADO
01.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 14.96 530.29 7,933.13
01.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 153.14 43.15 6,607.32
01.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,164.62 4.22 9,133.62
01.05.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.05.05.05.01 m2 47.52 31.51 1,497.15
MEZCLA 1:2 E=2 cm H=1.5 Max
01.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 102.98 28.87 2,972.74
01.05.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
01.05.05.06.01 m2 66.00 10.84 715.74
MANOS
01.05.05.07 CARPINTERIA METALICA
01.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 11.00 174.44 1,918.79
01.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 11.00 207.32 2,280.50
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.05.05.08.01 und 7.00 372.56 2,607.90
CRP T7, INGRESO Y SALIDA Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.05.05.08.02 und 5.00 367.80 1,839.02
CRP T7, INGRESO Y SALIDA Ø=3/4"
01.05.06 VALVULA DE CONTROL (05 UND)
01.05.06.01 OBRAS PRELIMINARES
01.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.48 2.38
01.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.78 8.92
01.05.06.02 MOVIMIENTO DE TIERRAS
01.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 38.66 193.32
01.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 24.92 155.74
01.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.71 38.56
01.05.06.03 OBRAS DE CONCRETO ARMADO
01.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 530.29 1,309.81
01.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 43.15 919.00
01.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.22 648.87
01.05.06.04 REVOQUES Y ENLUCIDOS
01.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 31.51 226.84
01.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 28.87 311.77
01.05.06.05 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
01.05.06.05.01 m2 6.48 10.84 70.28
MANOS
01.05.06.06 CARPINTERIA METALICA
01.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 157.99 789.97
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.06.07
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.05.06.07.01 und 1.00 87.57 87.57
VALVULA DE CONTROL, Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.05.06.07.02 und 4.00 76.65 306.60
VALVULA DE CONTROL, Ø=3/4"
01.05.07 VALVULA DE PURGA TIPO II (08 UND)
01.05.07.01 OBRAS PRELIMINARES
01.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.00 0.48 3.80
01.05.07.01.02 TRAZO Y REPLANTEO m2 8.00 1.78 14.28
01.05.07.02 MOVIMIENTO DE TIERRAS
01.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 12.23 38.66 472.87
01.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 4.08 48.33 197.17
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
01.05.07.02.03 m3 4.08 12.72 51.89
MANO
01.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 3.92 7.71 30.23
01.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.92 24.92 97.68
01.05.07.03 OBRAS DE CONCRETO SIMPLE
01.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 2.45 400.77 981.90
01.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.92 43.15 82.84
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
01.05.07.03.03 m2 1.02 117.47 119.81
PM
01.05.07.04 OBRAS DE CONCRETO ARMADO
01.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 2.80 530.29 1,484.81
01.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 29.76 43.15 1,284.01
01.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 119.53 4.22 504.36
01.05.07.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.05.07.05.01 m2 11.52 31.51 362.94
MEZCLA 1:2 E=2 cm H=1.5 Max
01.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 26.88 28.87 775.95
01.05.07.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
01.05.07.06.01 m2 12.96 10.84 140.54
MANOS
01.05.07.07 CARPINTERIA METALICA
MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE
01.05.07.07.01 und 8.00 207.32 1,658.54
0.60x0.40m.
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.07.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.05.07.08.01 und 1.00 144.77 144.77
VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.05.07.08.02 und 7.00 128.95 902.66
VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4"
01.05.08 CONEXIONES DOMICILIARIAS (92 UND)
01.05.08.01 OBRAS PRELIMINARES
01.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 824.32 0.48 391.80
01.05.08.01.02 TRAZO Y REPLANTEO m2 1,236.48 1.78 2,206.87
01.05.08.02 MOVIMIENTO DE TIERRAS
EXCAVACION A MANO DE ZANJA MANUAL TERRENO
01.05.08.02.01 m3 989.18 38.66 38,245.85
NORMAL
RELLENO Y COMPACTADO DE ZANJAS CON
01.05.08.02.02 m3 989.18 32.01 31,663.65
MATERIAL PROPIO CLASIFICADO
SUMINISTRO Y COLOCACION DE GRAVA
01.05.08.02.03 m3 103.04 202.84 20,900.29
SELECCIONADA
01.05.08.03 OBRAS DE CONCRETO SIMPLE
01.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 6.82 400.77 2,733.29
01.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 34.04 43.15 1,468.68
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.08.04
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.05.08.04.01 und 92.00 78.35 7,207.91
CONEXIONES DOMICILIARIAS DE AGUA (53 UND)
TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON
01.05.08.04.02 und 92.00 150.55 13,850.94
LLAVE TIPO BUJIA
SUMINISTRO E INSTALACIONES DE ACOMETIDA
01.05.08.04.03 m 736.00 3.40 2,498.72
DOMICILIARIA RANGO 2 - 50 M.
02 LOCALIDAD PUEBLO LIBRE
02.01 CONSTRUCCIONES PROVISIONALES
OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y
02.01.01 m2 100.00 43.21 4,321.35
VESTUARIOS
ALQUILER DE PREDIOS PARA CAMPAMENTOS Y
02.01.02 mes 6.00 485.00 2,910.00
ALMACENES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x
02.01.03 und 1.00 1,493.63 1,493.63
7.20 m
02.02 CAPTACION TIPO LADERA (YACUPACCARI)
02.02.01 TRABAJOS PRELIMINARES
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.48 23.29
02.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.78 64.25
02.02.02 MOVIMIENTO DE TIERRAS

02.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 22.53 38.66 871.11

RELLENO Y COMPACTADO CON MATERIAL PROPIO A


02.02.02.02 m3 2.55 28.62 72.97
MANO C/PISON
02.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.71 208.21
02.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 25.05 24.92 624.22
02.02.03 CONCRETO SIMPLE
02.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 400.77 685.32
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 43.15 113.91
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
02.02.03.03 m2 0.50 117.47 58.73
PM
02.02.04 CONCRETO ARMADO
02.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 498.42 787.51
02.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 43.15 773.60
02.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.22 287.18
02.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTES
02.02.05.01 m2 5.53 31.51 174.22
M=1:3 e=1.5cm
02.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 28.87 347.85
02.02.06 PINTURA

02.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 12.83 154.64

02.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE

02.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 170.57 257.56


02.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 92.90 25.08
02.02.08 CARPINTERIA METALICA
02.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 175.50 175.50
02.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 273.08 273.08
02.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.02.09.01 CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO und 1.00 486.25 486.25
HIDRAULICO y VENTILACION Ø=2"
02.02.10 CERCO PERIMETRICO EN CAPTACION
02.02.10.01 TRABAJOS PRELIMINARES
02.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.78 42.84
02.02.10.02 MOVIMIENTO DE TIERRAS
02.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 38.66 22.81
02.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 24.92 18.19
02.02.10.03 CONCRETO SIMPLE
02.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 345.30 203.73
02.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
02.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 43.15 67.31
02.02.10.05 COLOCADO DE ROLLIZOS
02.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 41.55 540.09
02.02.10.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
02.02.10.06.01 m 33.80 3.69 124.59
C/ESMALTE SINTETICO
02.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
02.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 21.55 517.28
02.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
02.02.10.08.01 und 1.00 188.28 188.28
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
02.03 CRUCE AEREO DE L=6.00 ML. (01 UNIDAD)
02.03.01 OBRAS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 22.40 0.48 10.65
02.03.01.02 TRAZO Y REPLANTEO m2 22.40 1.78 39.98
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION A MANO TERRENO NORMAL m3 2.57 38.66 99.37
02.03.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.21 24.92 79.99
02.03.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 3.28 7.71 25.30
02.03.03 OBRAS DE CONCRETO SIMPLE
02.03.03.01 CONCRETO F'C=100 KG/CM2.PARA SOLADOS m3 0.13 391.67 50.92
02.03.04 OBRAS DE CONCRETO ARMADO
02.03.04.01 CONCRETO FC=210 KG/CM2 m3 2.72 452.09 1,229.68
02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.50 43.15 107.86
02.03.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 40.12 4.22 169.28
02.03.05 REVOQUES Y ENLUCIDOS
02.03.05.01 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 2.50 28.87 72.17
02.03.06 PINTURA

02.03.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 2.50 18.92 47.32

02.03.07 TUBERIA TN ISO 65 SERIE LIVIANA (L)


SUMINISTRO E INSTALACION DE TUBERIA TN ISO 65 Ø
02.03.07.01 m 11.70 302.77 3,542.36
1"
02.03.08 CABLE DE ACERO PRINCIPAL Ø 3/8" TIPO BOA
02.03.08.01 TENDIDO DE CABLE PRINCIPAL TIPO BOA Ø 3/8 m 7.86 36.21 284.61
02.03.09 PENDOLAS
02.03.09.01 PENDOLAS CON F° LISO Ø 1/4" m 14.40 34.31 494.05
02.03.10 ACCESORIOS
ACCESORIOS PARA ACUEDUCTO COLGANTE,
02.03.10.01 und 1.00 906.89 906.89
ARGOLLA Ø 1", L=6.00ml
02.04 LINEA DE CONDUCCION (L=2153.00 m)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,153.00 0.48 1,023.32
02.04.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 2,153.00 1.48 3,195.27
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
02.04.01.03 m 2,153.00 1.48 3,195.27
ZANJAS REDES Y LINEAS
02.04.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
02.04.02.01 m3 86.12 38.66 3,329.76
SUELTO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
02.04.02.02 m3 775.08 48.33 37,456.06
CONGLOMERADO
REFINE Y NIVELACION DE ZANJA EN TERRENO
02.04.02.03 m 2,153.00 1.76 3,780.02
NORMAL P/TUBERIA
02.04.02.04 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 2,153.00 4.15 8,938.39

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


02.04.02.05 m3 322.95 35.31 11,402.72
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


02.04.02.06 m3 538.25 24.32 13,089.11
PROPIO P/TUBERIA, H=0.50 m
02.04.02.07 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 26.91 24.92 670.58
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.04.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-
02.04.03.01 m 2,153.00 5.76 12,405.16
10 DE 1"
02.04.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 209.06 209.06
02.04.04 PRUEBA HIDRAULICA
02.04.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 2,153.00 1.46 3,153.50
02.04.05 CAMARA ROMPE PRESION T-6 (06 UND)
02.04.05.01 OBRAS PRELIMINARES
02.04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.64 0.48 4.10
02.04.05.01.02 TRAZO Y REPLANTEO m2 8.64 1.78 15.42
02.04.05.02 MOVIMIENTO DE TIERRAS
02.04.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 9.50 38.66 367.31
02.04.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.88 24.92 296.04
02.04.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 8.64 7.71 66.63
02.04.05.03 OBRAS DE CONCRETO SIMPLE
02.04.05.03.01 SOLADO E=4" m3 7.26 34.74 252.18
02.04.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.07 400.77 28.05
02.04.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 43.15 51.78
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
02.04.05.03.04 m2 3.00 117.47 352.40
PM
02.04.05.04 OBRAS DE CONCRETO ARMADO
02.04.05.04.01 CONCRETO f'c=210 kg/cm2 m3 4.74 530.29 2,513.57
02.04.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 48.60 43.15 2,096.88
02.04.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 223.37 4.22 942.51
02.04.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.04.05.05.01 m2 15.12 31.51 476.37
MEZCLA 1:2 E=2 cm H=1.5 Max
02.04.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 19.44 28.87 561.17
02.04.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
02.04.05.06.01 m2 19.44 10.84 210.82
MANOS
02.04.05.07 CARPINTERIA METALICA
02.04.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 6.00 207.32 1,243.91
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.04.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.04.05.08.01 und 6.00 290.61 1,743.67
CRP T6, INGRESO Ø=1 1/2" y SALIDA Ø=1 1/2"
02.04.06 VALVULA DE PURGA TIPO I (2 UND)
02.04.06.01 OBRAS PRELIMINARES
02.04.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.00 0.48 0.95
02.04.06.01.02 TRAZO Y REPLANTEO m2 2.00 1.78 3.57
02.04.06.02 MOVIMIENTO DE TIERRAS
02.04.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.02 38.66 39.44
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
02.04.06.02.02 m3 1.02 12.72 12.97
MANO
02.04.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.98 7.71 7.56
02.04.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1.27 24.92 31.65
02.04.06.03 OBRAS DE CONCRETO SIMPLE
02.04.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.04 400.77 16.03
02.04.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.48 43.15 20.71
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
02.04.06.03.03 m2 0.54 117.47 63.43
PM
02.04.06.04 OBRAS DE CONCRETO ARMADO
02.04.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.70 530.29 371.20
02.04.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.44 43.15 321.00
02.04.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 29.88 4.22 126.08
02.04.06.05 REVOQUES Y ENLUCIDOS
02.04.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 2.88 31.51 90.73
02.04.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.72 28.87 193.99
02.04.06.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
02.04.06.06.01 m2 4.32 10.84 46.85
MANOS
02.04.06.07 CARPINTERIA METALICA
02.04.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 2.00 208.39 416.77
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.04.06.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.04.06.08.01 und 2.00 148.47 296.94
VALVULA DE PURGA TIPO I, Ø=1 1/2"
02.05 RESERVORIO (V=10.00 m3, 01 UND)
02.05.01 OBRAS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.48 17.11
02.05.01.02 TRAZO Y REPLANTEO m2 36.00 1.78 64.25
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 79.30 38.66 3,066.07
02.05.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 11.41 7.71 87.99
02.05.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 99.13 24.92 2,470.25
02.05.03 CONCRETO SIMPLE
02.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 400.77 4.01
02.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 43.15 8.63
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
02.05.03.03 m2 0.50 117.47 58.73
PM
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 SOLADO PARA LOSA FONDO m2 11.41 39.64 452.34
02.05.04.02 CONCRETO f'c=210 kg/cm2 m3 13.50 530.29 7,158.91
02.05.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 57.48 43.15 2,480.01
02.05.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 349.49 4.22 1,474.67
02.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.05.05.01 m2 32.94 31.51 1,037.79
MEZCLA 1:2 E=2 cm H=1.5 Max
02.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 57.14 28.87 1,649.48
02.05.06 PINTURA
PINTURA ESMALTE EN MUROS EXTERIORES DE
02.05.06.01 m2 51.45 12.83 660.26
RESERVORIO
02.05.07 CARPINTERIA METALICA
02.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 207.32 414.64
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.05.08
ACCESORIOS
SUMINISTRO E INSTALACIONES DE ACCESORIOS EN
02.05.08.01 und 1.00 1,693.11 1,693.11
RESERVORIO (ING. 1", SAL.1")
02.05.09 CERCO PERIMETRICO EN RESERVORIO
02.05.09.01 TRABAJOS PRELIMINARES
02.05.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.78 64.25
02.05.09.02 MOVIMIENTO DE TIERRAS
02.05.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 38.66 27.06
02.05.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 24.92 18.19
02.05.09.03 CONCRETO SIMPLE
02.05.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 345.30 241.71
02.05.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
02.05.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 43.15 67.31
02.05.09.05 COLOCADO DE ROLLIZOS
02.05.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 41.55 540.09
02.05.09.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
02.05.09.06.01 m 66.40 3.69 244.75
C/ESMALTE SINTETICO
02.05.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
02.05.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 21.55 500.04
02.05.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
02.05.09.08.01 und 1.00 188.28 188.28
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
02.05.10 CLORADOR POR GOTEO
02.05.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
CASETA DE MURO DE LADRILLO -CLORADOR POR
02.05.10.01.01
GOTEO
02.05.10.01.01.0 MURO DE LADRILLO PANDERETA (0.10x0.12x0.24)
m2 7.52 53.31 400.90
1 AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm.
MURO DE LADRILLO PANDERETA
02.05.10.01.01.0
INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 m2 4.48 47.88 214.50
2
JUNTA 1.5 cm.
02.05.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
02.05.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 28.20 169.19
1
02.05.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 33.06 197.69
2
02.05.10.01.03 REVOQUES Y ENLUCIDOS
02.05.10.01.03.0 TARRAJEO MUROS DE INTERIORES Y
m2 14.98 29.10 435.92
1 EXTERIORES, CEMENTO : ARENA, 1:5
02.05.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.37 53.47
2
02.05.10.01.04 CARPINTERIA METALICA
02.05.10.01.04.0 SUMINISTRO E INSTALACION DE PUERTA
und 1.00 356.16 356.16
1 METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO
02.05.10.01.05 PINTURAS
02.05.10.01.05.0 PINTURA ESMALTE EN MUROS INTERIORES Y
m2 14.98 10.84 162.46
1 EXTERIORES
02.05.10.01.05.0 PINTURA ANTICORROSIVA Y ESMALTE EN
m2 4.00 11.88 47.53
2 PUERTAS
02.05.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
SUMINISTRO E INSTALACION DE TANQUE DE
02.05.10.02.01 und 1.00 422.01 422.01
POLIETILENO, CAP=250 LTRS.
02.05.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
SUMINISTRO Y COLOCACION DE TUBERIAS Y
02.05.10.03.01 GLB 1.00 911.04 911.04
ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO
02.06 RED DE ADUCCION Y DISTRIBUCION (L=5,678.00 m)
02.06.01 TRABAJOS PRELIMINARES
02.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,839.00 0.48 1,349.38
02.06.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 5,678.00 1.48 8,426.72
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
02.06.01.03 m 5,678.00 1.48 8,426.72
ZANJAS REDES Y LINEAS
02.06.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
02.06.02.01 m3 1,362.72 48.33 65,853.99
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
02.06.02.02 m3 908.48 54.13 49,172.38
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
02.06.02.03 m 5,678.00 1.76 9,968.86
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA
02.06.02.04 m 2,271.20 5.90 13,394.63
Y FIJA P/TUBERIA

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


02.06.02.05 m3 511.02 35.31 18,043.10
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


02.06.02.06 DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m3 567.80 63.21 35,893.42
m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
02.06.02.07 m3 1,987.30 24.32 48,326.96
PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
02.06.02.08 m3 1,135.60 60.30 68,471.23
DE PRESTAMO P/TUBERIA, H=0.50 m
02.06.02.09 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 567.80 24.92 14,149.18
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-
02.06.03.01 m 1,146.00 7.81 8,948.54
10 DE 1"
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-
02.06.03.02 m 4,533.00 4.69 21,281.53
10 DE 3/4"
02.06.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 340.89 340.89
02.06.04 PRUEBA HIDRAULICA
02.06.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 5,678.00 1.46 8,316.57
02.06.05 CAMARA ROMPE PRESION T-7 (16 UND)
02.06.05.01 OBRAS PRELIMINARES
02.06.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 33.12 0.48 15.74
02.06.05.01.02 TRAZO Y REPLANTEO m2 33.12 1.78 59.11
02.06.05.02 MOVIMIENTO DE TIERRAS
02.06.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 22.91 38.66 885.79
02.06.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 15.27 39.72 606.55
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
02.06.05.02.03 m3 3.82 12.72 48.58
MANO
02.06.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 31.44 7.71 242.45
02.06.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.86 57.66 107.24
02.06.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 22.91 24.92 570.90
02.06.05.03 OBRAS DE CONCRETO SIMPLE
02.06.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.19 400.77 76.15
02.06.05.03.02 SOLADO E=4" m3 2.64 34.74 91.70
02.06.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.20 43.15 138.07
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
02.06.05.03.04 m2 4.32 117.47 507.46
PM
02.06.05.04 OBRAS DE CONCRETO ARMADO
02.06.05.04.01 CONCRETO f'c=210 kg/cm2 m3 21.74 530.29 11,528.49
02.06.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 222.76 43.15 9,611.11
02.06.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 3,148.54 4.22 13,285.27
02.06.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.06.05.05.01 m2 69.12 31.51 2,177.67
MEZCLA 1:2 E=2 cm H=1.5 Max
02.06.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 149.79 28.87 4,324.02
02.06.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
02.06.05.06.01 m2 96.00 10.84 1,041.08
MANOS
02.06.05.07 CARPINTERIA METALICA
02.06.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 16.00 174.44 2,790.96
02.06.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 16.00 207.32 3,317.09
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.06.05.08.01 und 3.00 372.56 1,117.67
CRP T7, INGRESO Y SALIDA Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.06.05.08.02 und 13.00 367.80 4,781.46
CRP T7, INGRESO Y SALIDA Ø=3/4"
02.06.06 VALVULA DE CONTROL (05 UND)
02.06.06.01 OBRAS PRELIMINARES
02.06.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.00 0.48 2.85
02.06.06.01.02 TRAZO Y REPLANTEO m2 6.00 1.78 10.71
02.06.06.02 MOVIMIENTO DE TIERRAS
02.06.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 6.00 38.66 231.99
02.06.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 7.50 24.92 186.90
02.06.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 6.00 7.71 46.27
02.06.06.03 OBRAS DE CONCRETO ARMADO
02.06.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.96 530.29 1,569.65
02.06.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 25.56 43.15 1,102.80
02.06.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 184.53 4.22 778.63
02.06.06.04 REVOQUES Y ENLUCIDOS
02.06.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 8.64 31.51 272.21
02.06.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 12.96 28.87 374.12
02.06.06.05 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
02.06.06.05.01 m2 12.96 10.84 140.54
MANOS
02.06.06.06 CARPINTERIA METALICA
02.06.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 6.00 157.99 947.96
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.06.07
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.06.06.07.01 und 2.00 87.57 175.14
VALVULA DE CONTROL, Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.06.06.07.02 und 4.00 76.65 306.60
VALVULA DE CONTROL, Ø=3/4"
02.06.07 VALVULA DE PURGA TIPO II (03 UND)
02.06.07.01 OBRAS PRELIMINARES
02.06.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 3.00 0.48 1.43
02.06.07.01.02 TRAZO Y REPLANTEO m2 3.00 1.78 5.35
02.06.07.02 MOVIMIENTO DE TIERRAS
02.06.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 4.59 38.66 177.47
02.06.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 1.53 48.33 73.93
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
02.06.07.02.03 m3 1.53 12.72 19.46
MANO
02.06.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 1.47 7.71 11.34
02.06.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.47 24.92 36.63
02.06.07.03 OBRAS DE CONCRETO SIMPLE
02.06.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.92 400.77 368.72
02.06.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.72 43.15 31.07
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
02.06.07.03.03 m2 0.38 117.47 44.64
PM
02.06.07.04 OBRAS DE CONCRETO ARMADO
02.06.07.04.01 CONCRETO f'c=210 kg/cm2 m3 1.05 530.29 556.80
02.06.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 11.16 43.15 481.51
02.06.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 44.82 4.22 189.12
02.06.07.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.06.07.05.01 m2 4.32 31.51 136.10
MEZCLA 1:2 E=2 cm H=1.5 Max
02.06.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.08 28.87 290.98
02.06.07.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
02.06.07.06.01 m2 4.84 10.84 52.49
MANOS
02.06.07.07 CARPINTERIA METALICA 0.00
MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE
02.06.07.07.01 und 3.00 207.32 621.95
0.60x0.40m.
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.07.08 0.00
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.06.07.08.01 und 3.00 128.95 386.86
VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4"
02.06.08 CONEXIONES DOMICILIARIAS (125 UND)
02.06.08.01 OBRAS PRELIMINARES
02.06.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,120.00 0.48 532.34
02.06.08.01.02 TRAZO Y REPLANTEO m2 1,680.00 1.78 2,998.46
02.06.08.02 MOVIMIENTO DE TIERRAS
EXCAVACION A MANO DE ZANJA MANUAL TERRENO
02.06.08.02.01 m3 1,344.00 38.66 51,964.68
NORMAL
RELLENO Y COMPACTADO DE ZANJAS CON
02.06.08.02.02 m3 1,344.00 32.01 43,021.44
MATERIAL PROPIO CLASIFICADO
SUMINISTRO Y COLOCACION DE GRAVA
02.06.08.02.03 m3 140.00 202.84 28,397.14
SELECCIONADA
02.06.08.03 OBRAS DE CONCRETO SIMPLE
02.06.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 9.27 400.77 3,715.19
02.06.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 46.25 43.15 1,995.48
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.08.04
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.06.08.04.01 und 125.00 78.35 9,793.36
CONEXIONES DOMICILIARIAS DE AGUA (53 UND)
TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON
02.06.08.04.02 und 125.00 150.55 18,819.21
LLAVE TIPO BUJIA
SUMINISTRO E INSTALACIONES DE ACOMETIDA
02.06.08.04.03 m 1,125.00 3.40 3,819.38
DOMICILIARIA RANGO 2 - 20 M.
03 LOCALIDAD TANCARPATA
03.01 CONSTRUCCIONES PROVISIONALES
OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y
03.01.01 m2 100.00 43.21 4,321.35
VESTUARIOS
ALQUILER DE PREDIOS PARA CAMPAMENTOS Y
03.01.02 mes 6.00 485.00 2,910.00
ALMACENES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x
03.01.03 und 1.00 1,493.63 1,493.63
7.20 m
03.02 CAPTACION A TIPO LADERA YACUTOCCYAC (01 UND)
03.02.01 TRABAJOS PRELIMINARES
03.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.48 23.29
03.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.78 64.25
03.02.02 MOVIMIENTO DE TIERRAS
03.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 15.03 38.66 581.13

RELLENO Y COMPACTADO CON MATERIAL PROPIO A


03.02.02.02 m3 2.55 28.62 72.97
MANO C/PISON
03.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.71 208.21
03.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.60 24.92 388.74
03.02.03 CONCRETO SIMPLE
03.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 400.77 685.32
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 43.15 113.91
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
03.02.03.03 m2 0.50 117.47 58.73
PM
03.02.04 CONCRETO ARMADO
03.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 498.42 787.51
03.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 43.15 773.60
03.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.22 287.18
03.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTES
03.02.05.01 m2 5.53 31.51 174.22
M=1:3 e=1.5cm
03.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 28.87 347.85
03.02.06 PINTURA

03.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 12.83 154.64

03.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE

03.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 170.57 257.56


03.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 92.90 25.08
03.02.08 CARPINTERIA METALICA
03.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 175.50 175.50
03.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 273.08 273.08
03.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.02.09.01 CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO und 1.00 482.76 482.76
HIDRAULICO y VENTILACION Ø=2")
03.02.10 CERCO PERIMETRICO EN CAPTACION
03.02.10.01 TRABAJOS PRELIMINARES
03.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.78 42.84
03.02.10.02 MOVIMIENTO DE TIERRAS
03.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 38.66 22.81
03.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 24.92 18.19
03.02.10.03 CONCRETO SIMPLE
03.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 345.30 203.73
03.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
03.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 43.15 67.31
03.02.10.05 COLOCADO DE ROLLIZOS
03.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 41.55 540.09
03.02.10.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
03.02.10.06.01 m 33.80 3.69 124.59
C/ESMALTE SINTETICO
03.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
03.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 21.55 517.28
03.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
03.02.10.08.01 und 1.00 188.28 188.28
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
03.03 LINEA DE CONDUCCION (L=196.00 m)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 196.00 0.48 93.16
03.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 196.00 1.48 290.88
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
03.03.01.03 m 196.00 1.48 290.88
ZANJAS REDES Y LINEAS
03.03.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
03.03.02.01 m3 72.13 48.33 3,485.71
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
03.03.02.02 m3 6.27 54.13 339.37
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
03.03.02.03 m 196.00 1.76 344.12
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA
03.03.02.04 m 196.00 5.90 1,155.93
Y FIJA P/TUBERIA
03.03.02.05 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 196.00 4.15 813.71

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


03.03.02.06 m3 27.05 35.31 955.08
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


03.03.02.07 DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m3 2.35 63.21 148.56
m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.03.02.08 m3 45.05 24.32 1,095.52
PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.03.02.09 m3 3.92 60.30 236.36
DE PRESTAMO P/TUBERIA, H=0.50 m
03.03.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.92 24.92 97.68
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.03.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-
03.03.03.01 m 196.00 5.76 1,129.31
10 DE 1"
03.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 156.08 156.08
03.03.04 PRUEBA HIDRAULICA
03.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 180.36 1.46 264.17
03.03.05 CAMARA ROMPE PRESION T-6 (01 UND)
03.03.05.01 OBRAS PRELIMINARES
03.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.44 0.48 0.69
03.03.05.01.02 TRAZO Y REPLANTEO m2 1.44 1.78 2.57
03.03.05.02 MOVIMIENTO DE TIERRAS
03.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.58 38.66 61.09
03.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.98 24.92 49.34
03.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 1.44 7.71 11.11
03.03.05.03 OBRAS DE CONCRETO SIMPLE
03.03.05.03.01 SOLADO E=4" m3 1.21 34.74 42.03
03.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.01 400.77 4.01
03.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 43.15 8.63
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
03.03.05.03.04 m2 0.50 117.47 58.73
PM
03.03.05.04 OBRAS DE CONCRETO ARMADO 0.00
03.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 0.79 530.29 418.93
03.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.10 43.15 349.48
03.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 37.23 4.22 157.09
03.03.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.03.05.05.01 m2 2.52 31.51 79.39
MEZCLA 1:2 E=2 cm H=1.5 Max
03.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.24 28.87 93.53
03.03.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
03.03.05.06.01 m2 3.24 10.84 35.13
MANOS
03.03.05.07 CARPINTERIA METALICA
03.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 1.00 207.32 207.32
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.03.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.03.05.08.01 und 1.00 290.61 290.61
CRP T6, INGRESO Ø=1 y SALIDA Ø=1 "
03.03.06 VALVULA DE PURGA TIPO I (1 UND)
03.03.06.01 OBRAS PRELIMINARES
03.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 0.48 0.48
03.03.06.01.02 TRAZO Y REPLANTEO m2 1.00 1.78 1.78
03.03.06.02 MOVIMIENTO DE TIERRAS
03.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.51 38.66 19.72
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
03.03.06.02.02 m3 0.51 12.72 6.49
MANO
03.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.49 7.71 3.78
03.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 0.64 24.92 15.95
03.03.06.03 OBRAS DE CONCRETO SIMPLE
03.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.20 400.77 80.15
03.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.24 43.15 10.36
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
03.03.06.03.03 m2 0.27 117.47 31.72
PM
03.03.06.04 OBRAS DE CONCRETO ARMADO
03.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.35 530.29 185.60
03.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.72 43.15 160.51
03.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 14.94 4.22 63.04
03.03.06.05 REVOQUES Y ENLUCIDOS
03.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 1.44 31.51 45.37
03.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.36 28.87 96.99
03.03.06.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
03.03.06.06.01 m2 2.16 10.84 23.43
MANOS
03.03.06.07 CARPINTERIA METALICA
03.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 1.00 208.39 208.39
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.03.06.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.03.06.08.01 und 1.00 148.47 148.47
VALVULA DE PURGA TIPO I, Ø=1"
03.04 RESERVORIO (V=5.00 m3, 01 UND)
03.04.01 OBRAS PRELIMINARES
03.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.48 17.11
03.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.78 64.25
03.04.02 MOVIMIENTO DE TIERRAS
03.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 60.95 38.66 2,356.59
03.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 8.05 7.71 62.08
03.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 76.19 24.92 1,898.60
03.04.03 CONCRETO SIMPLE
03.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 400.77 4.01
03.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 43.15 8.63
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
03.04.03.03 m2 0.50 117.47 58.73
PM
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 SOLADO PARA LOSA FONDO m2 8.05 39.64 319.13
03.04.04.02 CONCRETO f'c=210 kg/cm2 m3 9.51 530.29 5,043.05
03.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 49.52 43.15 2,136.57
03.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 254.64 4.22 1,074.45
03.04.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.04.05.01 m2 31.00 31.51 976.67
MEZCLA 1:2 E=2 cm H=1.5 Max
03.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 35.50 28.87 1,024.79
03.04.06 PINTURA
PINTURA ESMALTE EN MUROS EXTERIORES DE
03.04.06.01 m2 29.15 12.83 374.08
RESERVORIO
03.04.07 CARPINTERIA METALICA
03.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 207.32 414.64
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.04.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.04.08.01 RESERVORIO (INGRESO Ø 1"-LIMPIA, REBOSE y SELLO und 1.00 1,569.62 1,569.62
HIDR. Ø 2"-VENTILAC. Ø 3")
03.04.09 CERCO PERIMETRICO EN RESERVORIO
03.04.09.01 TRABAJOS PRELIMINARES
03.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.78 64.25
03.04.09.02 MOVIMIENTO DE TIERRAS
03.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 38.66 27.06
03.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 24.92 18.19
03.04.09.03 CONCRETO SIMPLE
03.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 345.30 241.71
03.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
03.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 43.15 67.31
03.04.09.05 COLOCADO DE ROLLIZOS
03.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 41.55 540.09
03.04.09.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
03.04.09.06.01 m 66.40 3.69 244.75
C/ESMALTE SINTETICO
03.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
03.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 21.55 500.04
03.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
03.04.09.08.01 und 1.00 188.28 188.28
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
03.04.10 CLORADOR POR GOTEO
03.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
CASETA DE MURO DE LADRILLO -CLORADOR POR
03.04.10.01.01
GOTEO
03.04.10.01.01.0 MURO DE LADRILLO PANDERETA (0.10x0.12x0.24)
m2 7.52 53.31 400.90
1 AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm.
MURO DE LADRILLO PANDERETA
03.04.10.01.01.0
INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 m2 4.48 47.88 214.50
2
JUNTA 1.5 cm.
03.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
03.04.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 28.20 169.19
1
03.04.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 33.06 197.69
2
03.04.10.01.03 REVOQUES Y ENLUCIDOS
03.04.10.01.03.0 TARRAJEO MUROS DE INTERIORES Y
m2 14.98 29.10 435.92
1 EXTERIORES, CEMENTO : ARENA, 1:5
03.04.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.37 53.47
2
03.04.10.01.04 CARPINTERIA METALICA
03.04.10.01.04.0 SUMINISTRO E INSTALACION DE PUERTA
und 1.00 356.16 356.16
1 METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO
03.04.10.01.05 PINTURAS
03.04.10.01.05.0 PINTURA ESMALTE EN MUROS INTERIORES Y
m2 14.98 10.84 162.46
1 EXTERIORES
03.04.10.01.05.0 PINTURA ANTICORROSIVA Y ESMALTE EN
m2 4.00 11.88 47.53
2 PUERTAS
03.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
SUMINISTRO E INSTALACION DE TANQUE DE
03.04.10.02.01 und 1.00 422.01 422.01
POLIETILENO, CAP=250 LTRS.
03.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
SUMINISTRO Y COLOCACION DE TUBERIAS Y
03.04.10.03.01 GLB 1.00 911.04 911.04
ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO
03.05 RED DE ADUCCION Y DISTRIBUCION (L=2,740.00 m)
03.05.01 TRABAJOS PRELIMINARES
03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,370.00 0.48 651.16
03.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 2,740.00 1.48 4,066.43
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
03.05.01.03 m 2,740.00 1.48 4,066.43
ZANJAS REDES Y LINEAS
03.05.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
03.05.02.01 m3 1,041.20 48.33 50,316.40
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
03.05.02.02 m3 54.80 54.13 2,966.10
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
03.05.02.03 m 2,740.00 1.76 4,810.62
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA
03.05.02.04 m 137.00 5.90 807.97
Y FIJA P/TUBERIA

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


03.05.02.05 m3 390.45 35.31 13,786.01
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.05.02.06 DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m3 20.55 63.21 1,299.06
m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.05.02.07 m3 719.25 24.32 17,490.65
PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.05.02.08 m3 68.50 60.30 4,130.22
DE PRESTAMO P/TUBERIA, H=0.50 m
03.05.02.09 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 34.25 24.92 853.48
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-
03.05.03.01 m 4.00 7.81 31.23
10 DE 1"
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-
03.05.03.02 m 2,736.00 4.69 12,844.97
10 DE 3/4"
03.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 93.73 93.73
03.05.04 PRUEBA HIDRAULICA
03.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 2,740.00 1.46 4,013.28
03.05.05 CAMARA ROMPE PRESION T-7 (09 UND)
03.05.05.01 OBRAS PRELIMINARES
03.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 18.63 0.48 8.86
03.05.05.01.02 TRAZO Y REPLANTEO m2 18.63 1.78 33.25
03.05.05.02 MOVIMIENTO DE TIERRAS
03.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 14.32 38.66 553.68
03.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 7.16 39.72 284.40
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
03.05.05.02.03 m3 2.39 12.72 30.39
MANO
03.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 17.69 7.71 136.42
03.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.06 57.66 61.12
03.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 8.06 24.92 200.85
03.05.05.03 OBRAS DE CONCRETO SIMPLE
03.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.11 400.77 44.09
03.05.05.03.02 SOLADO E=4" m3 1.49 34.74 51.76
03.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.80 43.15 77.66
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
03.05.05.03.04 m2 2.43 117.47 285.44
PM
03.05.05.04 OBRAS DE CONCRETO ARMADO
03.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 12.23 530.29 6,485.44
03.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 125.30 43.15 5,406.14
03.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,771.06 4.22 7,472.99
03.05.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.05.05.05.01 m2 38.88 31.51 1,224.94
MEZCLA 1:2 E=2 cm H=1.5 Max
03.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 84.26 28.87 2,432.35
03.05.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
03.05.05.06.01 m2 54.00 10.84 585.61
MANOS
03.05.05.07 CARPINTERIA METALICA
03.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 9.00 174.44 1,569.92
03.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 9.00 207.32 1,865.86
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.05.05.08.01 und 9.00 367.80 3,310.24
CRP T7, INGRESO Y SALIDA Ø=3/4"
03.05.06 VALVULA DE CONTROL (05 UND)
03.05.06.01 OBRAS PRELIMINARES
03.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.48 2.38
03.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.78 8.92
03.05.06.02 MOVIMIENTO DE TIERRAS
03.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 38.66 193.32
03.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 24.92 155.74
03.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.71 38.56
03.05.06.03 OBRAS DE CONCRETO ARMADO
03.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 530.29 1,309.81
03.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 43.15 919.00
03.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.22 648.87
03.05.06.04 REVOQUES Y ENLUCIDOS
03.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 31.51 226.84
03.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 28.87 311.77
03.05.06.05 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
03.05.06.05.01 m2 10.80 10.84 117.12
MANOS
03.05.06.06 CARPINTERIA METALICA
03.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 157.99 789.97
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.06.07
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.05.06.07.01 und 5.00 76.65 383.25
VALVULA DE CONTROL, Ø=3/4"
03.05.07 VALVULA DE PURGA TIPO II (06 UND)
03.05.07.01 OBRAS PRELIMINARES
03.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.00 0.48 2.85
03.05.07.01.02 TRAZO Y REPLANTEO m2 6.00 1.78 10.71
03.05.07.02 MOVIMIENTO DE TIERRAS
03.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 9.17 38.66 354.55
03.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 3.06 48.33 147.88
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
03.05.07.02.03 m3 3.06 12.72 38.92
MANO
03.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 2.94 7.71 22.67
03.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 2.94 24.92 73.26
03.05.07.03 OBRAS DE CONCRETO SIMPLE
03.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 1.84 400.77 737.42
03.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.44 43.15 62.13
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
03.05.07.03.03 m2 0.77 117.47 90.45
PM
03.05.07.04 OBRAS DE CONCRETO ARMADO
03.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 2.10 530.29 1,113.61
03.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 23.32 43.15 1,006.15
03.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 86.64 4.22 365.57
03.05.07.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.05.07.05.01 m2 8.64 31.51 272.21
MEZCLA 1:2 E=2 cm H=1.5 Max
03.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 20.16 28.87 581.96
03.05.07.06 PINTURA 0.00
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
03.05.07.06.01 m2 9.72 10.84 105.41
MANOS
03.05.07.07 CARPINTERIA METALICA
MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE
03.05.07.07.01 und 6.00 207.32 1,243.91
0.60x0.40m.
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.07.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.05.07.08.01 und 6.00 128.95 773.71
VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4"
03.05.08 CONEXIONES DOMICILIARIAS (53 UND)
03.05.08.01 OBRAS PRELIMINARES
03.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 474.88 0.48 225.71
03.05.08.01.02 TRAZO Y REPLANTEO m2 712.32 1.78 1,271.35
03.05.08.02 MOVIMIENTO DE TIERRAS
EXCAVACION A MANO DE ZANJA MANUAL TERRENO
03.05.08.02.01 m3 569.86 38.66 22,033.18
NORMAL
RELLENO Y COMPACTADO DE ZANJAS CON
03.05.08.02.02 m3 569.86 32.01 18,241.22
MATERIAL PROPIO CLASIFICADO
SUMINISTRO Y COLOCACION DE GRAVA
03.05.08.02.03 m3 50.36 202.84 10,214.86
SELECCIONADA
03.05.08.03 OBRAS DE CONCRETO SIMPLE
03.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 3.93 400.77 1,575.05
03.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.61 43.15 846.08
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.08.04
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.05.08.04.01 und 53.00 78.35 4,152.39
CONEXIONES DOMICILIARIAS DE AGUA (53 UND)
TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON
03.05.08.04.02 und 53.00 150.55 7,979.35
LLAVE TIPO BUJIA
SUMINISTRO E INSTALACIONES DE ACOMETIDA
03.05.08.04.03 m 530.00 3.40 1,799.35
DOMICILIARIA RANGO 2 - 20 M.
04 LOCALIDAD TARACA
04.01 CONSTRUCCIONES PROVISIONALES
OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y
04.01.01 m2 100.00 43.21 4,321.35
VESTUARIOS
ALQUILER DE PREDIOS PARA CAMPAMENTOS Y
04.01.02 mes 6.00 485.00 2,910.00
ALMACENES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x
04.01.03 und 1.00 1,493.63 1,493.63
7.20 m
04.02 CAPTACION A TIPO LADERA YACUTOCCYAC (01 UND)
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.48 23.29
04.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.78 64.25
04.02.02 MOVIMIENTO DE TIERRAS

04.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 17.55 38.66 678.55

RELLENO Y COMPACTADO CON MATERIAL PROPIO A


04.02.02.02 m3 2.55 28.62 72.97
MANO C/PISON
04.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.71 208.21
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.60 24.92 388.74
04.02.03 CONCRETO SIMPLE
04.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 400.77 685.32
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 43.15 113.91
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
04.02.03.03 m2 0.50 117.47 58.73
PM
04.02.04 CONCRETO ARMADO
04.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 498.42 787.51
04.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 43.15 773.60
04.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 4.22 287.18
04.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTES
04.02.05.01 m2 5.53 31.51 174.22
M=1:3 e=1.5cm
04.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 28.87 347.85
04.02.06 PINTURA 0.00
04.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 12.83 154.64

04.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE

04.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 170.57 257.56


04.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 92.90 25.08
04.02.08 CARPINTERIA METALICA
04.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 175.50 175.50
04.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 273.08 273.08
04.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.02.09.01 CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO und 1.00 482.76 482.76
HIDRAULICO y VENTILACION Ø=2")
04.02.10 CERCO PERIMETRICO EN CAPTACION
04.02.10.01 TRABAJOS PRELIMINARES
04.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.78 42.84
04.02.10.02 MOVIMIENTO DE TIERRAS
04.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 38.66 22.81
04.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 24.92 18.19
04.02.10.03 CONCRETO SIMPLE
04.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 345.30 203.73
04.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
04.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 43.15 67.31
04.02.10.05 COLOCADO DE ROLLIZOS
04.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 41.55 540.09
04.02.10.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
04.02.10.06.01 m 33.80 3.69 124.59
C/ESMALTE SINTETICO
04.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
04.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 21.55 517.28
04.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
04.02.10.08.01 und 1.00 188.28 188.28
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
04.03 LINEA DE CONDUCCION (L=1231.00 m)
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,231.00 0.48 585.09
04.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 1,231.00 1.48 1,826.93
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
04.03.01.03 m 1,231.00 1.48 1,826.93
ZANJAS REDES Y LINEAS
04.03.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
04.03.02.01 m3 392.92 38.66 15,191.94
SUELTO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
04.03.02.02 m3 73.86 48.33 3,569.32
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
04.03.02.03 m3 15.39 54.13 833.00
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
04.03.02.04 m 1,231.00 1.76 2,161.27
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA
04.03.02.05 m 61.55 5.90 362.99
Y FIJA P/TUBERIA
04.03.02.06 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 1,231.00 4.15 5,110.62

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


04.03.02.07 m3 175.42 35.31 6,193.73
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


04.03.02.08 DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m3 9.23 63.21 583.47
m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.03.02.09 m3 292.36 24.32 7,109.59
PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.03.02.10 m3 6.16 60.30 371.42
DE PRESTAMO P/TUBERIA, H=0.50 m
04.03.02.11 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.39 24.92 383.51
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.03.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-
04.03.03.01 m 1,231.00 5.76 7,092.78
10 DE 1"
04.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 152.98 152.98
04.03.04 PRUEBA HIDRAULICA
04.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 1,231.00 1.46 1,803.05
04.03.05 CAMARA ROMPE PRESION T-6 (02 UND)
04.03.05.01 OBRAS PRELIMINARES
04.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.88 0.48 1.37
04.03.05.01.02 TRAZO Y REPLANTEO m2 2.88 1.78 5.14
04.03.05.02 MOVIMIENTO DE TIERRAS
04.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 3.17 38.66 122.57
04.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 7.92 24.92 197.36
04.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 2.88 7.71 22.21
04.03.05.03 OBRAS DE CONCRETO SIMPLE
04.03.05.03.01 SOLADO E=4" m3 2.42 34.74 84.06
04.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.02 400.77 8.01
04.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.40 43.15 17.26
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
04.03.05.03.04 m2 1.00 117.47 117.47
PM
04.03.05.04 OBRAS DE CONCRETO ARMADO
04.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 530.29 837.86
04.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 16.20 43.15 698.96
04.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 74.46 4.22 314.18
04.03.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.03.05.05.01 m2 5.04 31.51 158.79
MEZCLA 1:2 E=2 cm H=1.5 Max
04.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.48 28.87 187.05
04.03.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
04.03.05.06.01 m2 6.48 10.84 70.28
MANOS
04.03.05.07 CARPINTERIA METALICA
04.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 207.32 414.64
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.03.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.03.05.08.01 und 2.00 290.61 581.22
CRP T6, INGRESO Ø=1 y SALIDA Ø=1 "
04.03.06 VALVULA DE PURGA TIPO I (1 UND)
04.03.06.01 OBRAS PRELIMINARES
04.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.00 0.48 0.95
04.03.06.01.02 TRAZO Y REPLANTEO m2 2.00 1.78 3.57
04.03.06.02 MOVIMIENTO DE TIERRAS
04.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.02 38.66 39.44
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
04.03.06.02.02 m3 1.02 12.72 12.97
MANO
04.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.98 7.71 7.56
04.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1.27 24.92 31.65
04.03.06.03 OBRAS DE CONCRETO SIMPLE
04.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.04 400.77 16.03
04.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.48 43.15 20.71
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
04.03.06.03.03 m2 0.54 117.47 63.43
PM
04.03.06.04 OBRAS DE CONCRETO ARMADO
04.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.70 530.29 371.20
04.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.44 43.15 321.00
04.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 29.88 4.22 126.08
04.03.06.05 REVOQUES Y ENLUCIDOS
04.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 2.88 31.51 90.73
04.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.72 28.87 193.99
04.03.06.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
04.03.06.06.01 m2 4.32 10.84 46.85
MANOS
04.03.06.07 CARPINTERIA METALICA
04.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 2.00 208.39 416.77
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.03.06.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.03.06.08.01 und 2.00 148.47 296.94
VALVULA DE PURGA TIPO I, Ø=1"
04.04 RESERVORIO (V=5.00 m3, 01 UND)
04.04.01 OBRAS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.48 17.11
04.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.78 64.25
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 36.02 38.66 1,392.69
04.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 8.05 7.71 62.08
04.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 45.02 24.92 1,121.86
04.04.03 CONCRETO SIMPLE
04.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 400.77 4.01
04.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 43.15 8.63
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
04.04.03.03 m2 0.50 117.47 58.73
PM
04.04.04 OBRAS DE CONCRETO ARMADO
04.04.04.01 SOLADO PARA LOSA FONDO m2 8.05 39.64 319.13
04.04.04.02 CONCRETO f'c=210 kg/cm2 m3 9.51 530.29 5,043.05
04.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 49.52 43.15 2,136.57
04.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 254.64 4.22 1,074.45
04.04.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.04.05.01 m2 31.00 31.51 976.67
MEZCLA 1:2 E=2 cm H=1.5 Max
04.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 35.50 28.87 1,024.79
04.04.06 PINTURA
PINTURA ESMALTE EN MUROS EXTERIORES DE
04.04.06.01 m2 29.15 12.83 374.08
RESERVORIO
04.04.07 CARPINTERIA METALICA
04.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 207.32 414.64
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.04.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.04.08.01 RESERVORIO (INGRESO Ø 1"-LIMPIA, REBOSE y SELLO und 1.00 1,569.62 1,569.62
HIDR. Ø 2"-VENTILAC. Ø 3")
04.04.09 CERCO PERIMETRICO EN RESERVORIO
04.04.09.01 TRABAJOS PRELIMINARES
04.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.78 64.25
04.04.09.02 MOVIMIENTO DE TIERRAS
04.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 38.66 27.06
04.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 24.92 18.19
04.04.09.03 CONCRETO SIMPLE
04.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 345.30 241.71
04.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
04.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 43.15 67.31
04.04.09.05 COLOCADO DE ROLLIZOS
04.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 41.55 540.09
04.04.09.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
04.04.09.06.01 m 66.40 3.69 244.75
C/ESMALTE SINTETICO
04.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
04.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 21.55 500.04
04.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
04.04.09.08.01 und 1.00 188.28 188.28
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
04.04.10 CLORADOR POR GOTEO
04.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
CASETA DE MURO DE LADRILLO -CLORADOR POR
04.04.10.01.01
GOTEO
04.04.10.01.01.0 MURO DE LADRILLO PANDERETA (0.10x0.12x0.24)
m2 7.52 53.31 400.90
1 AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm.
MURO DE LADRILLO PANDERETA
04.04.10.01.01.0
INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 m2 4.48 47.88 214.50
2
JUNTA 1.5 cm.
04.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
04.04.10.01.02.0
CORREAS DE MADERA DE 2" x 2" m 6.00 28.20 169.19
1
04.04.10.01.02.0 COBERTURA CON CALAMINA
m2 5.98 33.06 197.69
2
04.04.10.01.03 REVOQUES Y ENLUCIDOS
04.04.10.01.03.0 TARRAJEO MUROS DE INTERIORES Y
m2 14.98 29.10 435.92
1 EXTERIORES, CEMENTO : ARENA, 1:5
04.04.10.01.03.0
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 13.37 53.47
2
04.04.10.01.04 CARPINTERIA METALICA
04.04.10.01.04.0 SUMINISTRO E INSTALACION DE PUERTA
und 1.00 356.16 356.16
1 METALICA DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO
04.04.10.01.05 PINTURAS
04.04.10.01.05.0 PINTURA ESMALTE EN MUROS INTERIORES Y
m2 14.98 10.84 162.46
1 EXTERIORES
04.04.10.01.05.0 PINTURA ANTICORROSIVA Y ESMALTE EN
m2 4.00 11.88 47.53
2 PUERTAS
04.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
SUMINISTRO E INSTALACION DE TANQUE DE
04.04.10.02.01 und 1.00 422.01 422.01
POLIETILENO, CAP=250 LTRS.
04.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
SUMINISTRO Y COLOCACION DE TUBERIAS Y
04.04.10.03.01 GLB 1.00 911.04 911.04
ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO
04.05 RED DE ADUCCION Y DISTRIBUCION (L=3,674.00 m)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,837.00 0.48 873.13
04.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 3,674.00 1.48 5,452.58
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
04.05.01.03 m 3,674.00 1.48 5,452.58
ZANJAS REDES Y LINEAS
04.05.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
04.05.02.01 m3 73.48 38.66 2,841.04
SUELTO
EXCAVACION MANUAL DE ZANJA EN MATERIAL
04.05.02.02 m3 1,352.03 48.33 65,337.39
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
04.05.02.03 m3 44.09 54.13 2,386.41
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO
04.05.02.04 m 3,674.00 1.76 6,450.44
NORMAL P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA
04.05.02.05 m 110.22 5.90 650.04
Y FIJA P/TUBERIA

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


04.05.02.06 m3 534.57 35.31 18,874.60
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m

RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL


04.05.02.07 DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m3 16.53 63.21 1,044.94
m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.05.02.08 m3 946.06 24.32 23,006.19
PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.05.02.09 m3 55.11 60.30 3,322.87
DE PRESTAMO P/TUBERIA, H=0.20 m
04.05.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 27.56 24.92 686.78
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-
04.05.03.01 m 104.00 7.81 812.08
10 DE 1"
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-
04.05.03.02 m 3,570.00 4.69 16,760.44
10 DE 3/4"
04.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 85.33 85.33
04.05.04 PRUEBA HIDRAULICA
04.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 3,674.00 1.46 5,381.31
04.05.05 CAMARA ROMPE PRESION T-7 (12 UND)
04.05.05.01 OBRAS PRELIMINARES
04.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 24.84 0.48 11.80
04.05.05.01.02 TRAZO Y REPLANTEO m2 24.84 1.78 44.34
04.05.05.02 MOVIMIENTO DE TIERRAS
04.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 16.71 38.66 646.08
04.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 9.55 39.72 379.34
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
04.05.05.02.03 m3 2.39 12.72 30.39
MANO
04.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 23.58 7.71 181.84
04.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.39 57.66 80.14
04.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 12.53 24.92 312.24
04.05.05.03 OBRAS DE CONCRETO SIMPLE
04.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.14 400.77 56.10
04.05.05.03.02 SOLADO E=4" m3 1.98 34.74 68.77
04.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.40 43.15 103.55
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
04.05.05.03.04 m2 3.24 117.47 380.59
PM
04.05.05.04 OBRAS DE CONCRETO ARMADO
04.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 16.30 530.29 8,643.72
04.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 167.06 43.15 7,207.91
04.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,361.41 4.22 9,963.97
04.05.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.05.05.05.01 m2 51.84 31.51 1,633.25
MEZCLA 1:2 E=2 cm H=1.5 Max
04.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 112.34 28.87 3,242.94
04.05.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
04.05.05.06.01 m2 72.00 10.84 780.81
MANOS
04.05.05.07 CARPINTERIA METALICA
04.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 12.00 174.44 2,093.22
04.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 12.00 207.32 2,487.82
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.05.05.08.01 und 12.00 367.80 4,413.66
CRP T7, INGRESO Y SALIDA Ø=3/4"
04.05.06 VALVULA DE CONTROL (05 UND)
04.05.06.01 OBRAS PRELIMINARES
04.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.48 2.38
04.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.78 8.92
04.05.06.02 MOVIMIENTO DE TIERRAS
04.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 38.66 193.32
04.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 24.92 155.74
04.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.71 38.56
04.05.06.03 OBRAS DE CONCRETO ARMADO
04.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 530.29 1,309.81
04.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 43.15 919.00
04.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 4.22 648.87
04.05.06.04 REVOQUES Y ENLUCIDOS
04.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 31.51 226.84
04.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 28.87 311.77
04.05.06.05 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
04.05.06.05.01 m2 10.80 10.84 117.12
MANOS
04.05.06.06 CARPINTERIA METALICA
04.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 157.99 789.97
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.06.07
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.05.06.07.01 und 5.00 76.65 383.25
VALVULA DE CONTROL, Ø=3/4"
04.05.07 VALVULA DE PURGA TIPO II (05 UND)
04.05.07.01 OBRAS PRELIMINARES
04.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.48 2.38
04.05.07.01.02 TRAZO Y REPLANTEO m2 5.00 1.78 8.92
04.05.07.02 MOVIMIENTO DE TIERRAS
04.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 7.64 38.66 295.39
04.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 2.55 48.33 123.23
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
04.05.07.02.03 m3 2.55 12.72 32.43
MANO
04.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 2.45 7.71 18.90
04.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 2.45 24.92 61.05
04.05.07.03 OBRAS DE CONCRETO SIMPLE
04.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 1.53 400.77 613.19
04.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 43.15 51.78
EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80%
04.05.07.03.03 m2 0.64 117.47 75.18
PM
04.05.07.04 OBRAS DE CONCRETO ARMADO
04.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 1.75 530.29 928.01
04.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 18.60 43.15 802.51
04.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 74.70 4.22 315.20
04.05.07.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.05.07.05.01 m2 7.20 31.51 226.84
MEZCLA 1:2 E=2 cm H=1.5 Max
04.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 16.80 28.87 484.97
04.05.07.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
04.05.07.06.01 m2 8.10 10.84 87.84
MANOS
04.05.07.07 CARPINTERIA METALICA
MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE
04.05.07.07.01 und 5.00 207.32 1,036.59
0.60x0.40m.
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.07.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.05.07.08.01 und 5.00 128.95 644.76
VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4"
04.05.08 CONEXIONES DOMICILIARIAS (53 UND)
04.05.08.01 OBRAS PRELIMINARES
04.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 474.88 0.48 225.71
04.05.08.01.02 TRAZO Y REPLANTEO m2 712.32 1.78 1,271.35
04.05.08.02 MOVIMIENTO DE TIERRAS 0.00

04.05.08.02.01 EXCAVACION A MANO DE ZANJA TERRENO NORMAL m3 596.86 39.72 23,708.18

RELLENO Y COMPACTADO DE ZANJAS CON


04.05.08.02.02 m3 569.86 32.01 18,241.22
MATERIAL PROPIO CLASIFICADO
SUMINISTRO Y COLOCACION DE GRAVA
04.05.08.02.03 m3 59.36 202.84 12,040.39
SELECCIONADA
04.05.08.03 OBRAS DE CONCRETO SIMPLE
04.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 3.93 400.77 1,575.05
04.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.61 43.15 846.08
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.08.04
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.05.08.04.01 und 53.00 78.35 4,152.39
CONEXIONES DOMICILIARIAS DE AGUA (53 UND)
TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON
04.05.08.04.02 und 53.00 150.55 7,979.35
LLAVE TIPO BUJIA
SUMINISTRO E INSTALACIONES DE ACOMETIDA
04.05.08.04.03 m 636.00 3.40 2,159.22
DOMICILIARIA RANGO 2 - 20 M.

01 LOCALIDAD SANTA LUCIA


01.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
01.01.01 TRABAJOS PRELIMINARES
01.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 465.00 0.48 221.01
01.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 465.00 1.78 829.93
01.01.02 MOVIMIENTO DE TIERRAS

01.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 231.57 38.66 8,953.47

01.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 40.92 28.77 1,177.28


01.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 238.08 24.92 5,932.79
01.01.03 CONCRETO SIMPLE
01.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 279.00 362.54 101,147.96
01.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 40.92 386.73 15,824.96
01.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 678.90 43.15 29,291.55
01.01.03.04 CONCRETO f'c=175 kg/cm2 m3 28.83 435.38 12,552.14
01.01.04 MURO DE LADRILLO
MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE
01.01.04.01 m2 1,354.08 56.36 76,311.89
SOGA C/M 1:4 x 1.5cm
EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO
01.01.04.02 m2 26.04 68.22 1,776.45
4"-6"
01.01.05 REVOQUES Y ENLUCIDOS
TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE
01.01.05.01 m2 1,272.24 15.85 20,164.75
P/CAMARA (UBS arrastre hidraulico)
01.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 20.46 35.45 725.38
01.01.06 PINTURA
PINTURA EN MUROS INTERIORES C/LATEX LAVABLE
01.01.06.01 m2 767.25 11.18 8,581.00
COLOR MARFIL
01.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO
01.01.07.01 ETERNIT(1,14x0.72x0.005m) m2 605.43 64.23 38,888.82

01.01.08 CARPINTERIA METALICA


SUMINISTRO E INSTALACION DE PUERTA METALICA
01.01.08.01 und 93.00 352.83 32,812.99
1.80x0.70m, INCL. MARCO Y PINTADO
01.01.09 CARPINTERIA DE MADERA
VENTANA DE MADERA TORNILLO INC. MALLA
01.01.09.01 m2 16.74 73.62 1,232.45
MOSQUITERA
01.01.09.02 COBERTURA DE MADERA PARA TECHO und 93.00 95.01 8,836.07
01.01.10 SISTEMA DE AGUA FRIA
01.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 880.71 3.54 3,118.15
01.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
01.01.11.01 TEE PVC-SAP 1/2" pza 186.00 20.22 3,761.76
01.01.11.02 CODO PVC SAP 1/2" pza 558.00 15.12 8,438.24
01.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 186.00 49.71 9,246.53
SUMINISTRO E INSTALACION DE DUCHA INCLUIDO
01.01.11.04 und 93.00 32.09 2,984.15
ACCESORIOS
01.01.12 SISTEMA DE DESAGUE
01.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 897.45 3.90 3,499.52
01.01.12.02 TUBERIA Ø=4" PVC SAL m 339.45 3.54 1,201.82
01.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
01.01.13.01 CODO PVC SAL 2"X90° pza 651.00 11.42 7,432.40
01.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 93.00 15.06 1,400.96
01.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 279.00 15.63 4,359.85
01.01.14 ADITAMIENTOS VARIOS
01.01.14.01 SUMIDEROS DE BRONCE 2" und 93.00 11.88 1,105.07
01.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 186.00 10.76 2,000.86
INODORO DE LOZA VITRIFICADA COLOR BLANCO
01.01.14.03 und 93.00 142.98 13,296.95
INCLUYE TANQUE
01.01.14.04 ACCESORIOS DE LOZA und 93.00 62.91 5,851.02
SUMINISTRO E INSTALACION DE TUBERIA DE
01.01.14.05 VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y GLB 93.00 28.28 2,629.62
ACCESORIOS
SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA
01.01.14.06 und 93.00 120.85 11,239.26
COLOR BLANCO INCLUIDO ACCESORIOS
SUMINISTRO E INSTALACION DE CAJA DE REGISTRO
01.01.14.07 und 186.00 125.99 23,434.75
DE 12"x24"
01.01.15 INSTALACIONES ELECTRICAS
01.01.15.01 SALIDA DE CENTRO DE LUZ pto 93.00 47.67 4,432.92
01.01.15.02 TUBERIA PVC SEL 5/8" m 213.90 4.03 861.06
01.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 520.80 2.21 1,151.80
01.01.15.04 TABLEROS DISTRIBUCION pza 93.00 86.37 8,032.30
01.01.16 CONSTRUCCION POZO PERCOLADOR
01.01.16.01 TRABAJOS PRELIMINARES
01.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 292.02 0.48 138.80
01.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 292.02 1.78 521.20
01.01.16.02 MOVIMIENTO DE TIERRAS
01.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 150.66 38.66 5,825.15
01.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 22.32 28.77 642.15
01.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 80.91 86.62 7,008.50
01.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 188.79 24.92 4,704.52
01.01.16.03 TAPA DE CONCRETO
01.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 18.81 435.38 8,189.58
01.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 196.26 43.15 8,467.75
01.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,957.65 4.22 8,260.31
01.01.16.04 ANILLO DE CONCRETO
01.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 6.51 345.30 2,247.91
01.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 111.60 43.15 4,815.05
01.01.16.05 MURO DE LADRILLO
MURO DE LADRILLO ARTESANAL AMARRE DE SOGA,
01.01.16.05.01 m2 388.74 47.47 18,454.19
JUNTA 1.5 CM MORTERO 1:1:5
01.01.16.06 SISTEMA DE DESAGUE LLEGADA
01.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 181.35 3.90 707.16
01.01.16.06.02 CODO PVC SAL 2"X90° pza 93.00 11.42 1,061.77
01.01.17 INSTALACION DEL BIODIGESTOR
01.01.17.01 TRABAJOS PRELIMINARES
01.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 351.54 0.48 167.08
01.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 351.54 1.78 627.43
01.01.17.02 MOVIMIENTO DE TIERRAS
01.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 281.20 38.66 10,872.37
01.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 211.97 28.77 6,098.42
01.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 351.50 24.92 8,759.14
01.01.17.03 CONCRETO SIMPLE
01.01.17.03.01 SOLADO E=4" m2 60.45 38.49 2,326.70
01.01.17.04 CONCRETO ARMADO
01.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 66.96 435.38 29,153.35
01.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 420.36 43.15 18,136.68
01.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 518.01 4.22 2,185.74
01.01.17.05 BIODIGESTOR
SUMINISTRO E INSTALACION DE BIODIGESTOR
01.01.17.05.01 und 91.00 756.20 68,814.41
AUTOLIMPIABLE DE PVC DE 600 LTS
SUMINISTRO E INSTALACION DE BIODIGESTOR
01.01.17.05.02 und 2.00 1,281.17 2,562.33
AUTOLIMPIABLE DE PVC DE 1300 LTS
01.01.17.06 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.01.17.06.01 m2 332.01 31.51 10,460.17
MEZCLA 1:2 E=2 cm H=1.5 Max
01.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
01.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 93.00 3.90 362.64
SUMINISTRO E INSTALACION DE VALVULA DE PVC
01.01.17.07.02 und 93.00 28.96 2,693.67
DE 2"
01.02 LAVADERO INTRADOMICILIARIO (91 UND)
01.02.01 OBRAS PRELIMINARES
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 460.46 0.48 218.86
01.02.01.02 TRAZO Y REPLANTEO m2 460.46 1.78 821.83
01.02.02 MOVIMIENTO DE TIERRAS
01.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 103.03 36.36 3,745.71
RELLENO Y COMPACTADO DE ZANJA CON MATERIAL
01.02.02.02 m3 84.63 12.72 1,076.22
PROPIO CLASIFICADO
01.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 21.16 24.92 527.29
01.02.03 OBRAS DE CONCRETO ARMADO
01.02.03.01 CONCRETO f'c=175 kg/cm2 m3 9.57 435.38 4,166.63
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 304.63 43.15 13,143.44
01.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 359.91 4.22 1,518.64
01.02.04 MURO DE LADRILLO
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
01.02.04.01 m2 60.17 46.31 2,786.34
Lavaderos)
01.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.02.05.01 m2 107.29 31.51 3,380.24
MEZCLA 1:2 E=2 cm H=1.5 Max
01.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 205.30 28.87 5,926.44
01.02.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE LAVADERO
01.02.06.01 und 91.00 132.22 12,032.08
INTRADOMICILIARIA
01.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
01.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 455.00 3.25 1,478.52
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01
01.03
UND)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.48 5.38

01.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.78 20.21

01.03.02 MOVIMIENTO DE TIERRAS


01.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 36.36 99.62
REFINE, NIVELACION Y COMPACTADO EN TERRENO
01.03.02.02 m2 11.32 0.99 11.20
NORMAL
01.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 28.62 46.36
01.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 24.92 33.39
01.03.03 OBRAS DE CONCRETO SIMPLE
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
01.03.03.01 m2 2.20 47.49 104.48
FROTACHADO C/MEZCLADORA
01.03.04 OBRAS DE CONCRETO ARMADO
01.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.22 35.23

01.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 42.69 174.60

CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA


01.03.04.03 m3 0.21 435.38 91.43
LAVADEROS
01.03.05 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
01.03.05.01 m2 2.49 31.97 79.61
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
01.03.05.02 m2 2.11 23.26 49.08
H=1.5 MAX
01.03.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.03.06.01 und 1.00 171.68 171.68
LAVADERO I.E. INICIAL
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
01.03.06.02 und 2.00 138.23 276.45
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
01.03.06.03 und 1.00 56.04 56.04
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
01.03.06.04 und 1.00 46.74 46.74
(INTERIORES), E=0.05
01.03.07 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10,
01.03.07.01 m 12.00 6.16 73.91
P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
01.03.07.02 m 10.00 6.45 64.51
PARA DESAGUE Ø=2"x3 M
02 LOCALIDAD PUEBLO LIBRE (130 UND)
02.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 650.00 0.48 308.95
02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 650.00 1.78 1,160.12
02.01.02 MOVIMIENTO DE TIERRAS

02.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 323.70 38.66 12,515.60

02.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 57.20 28.77 1,645.65


02.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 332.80 24.92 8,293.14
02.01.03 CONCRETO SIMPLE
02.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 390.00 362.54 141,389.63
02.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 57.20 386.73 22,120.92
02.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 949.00 43.15 40,945.17
02.01.03.04 CONCRETO f'c=175 kg/cm2 m3 40.30 435.38 17,546.00
02.01.04 MURO DE LADRILLO
MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE
02.01.04.01 m2 1,892.80 56.36 106,672.53
SOGA C/M 1:4 x 1.5cm
EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO
02.01.04.02 m2 36.40 68.22 2,483.21
4"-6"
02.01.05 REVOQUES Y ENLUCIDOS
TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE
02.01.05.01 m2 1,778.40 15.85 28,187.29
P/CAMARA (UBS arrastre hidraulico)
02.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 28.60 35.45 1,013.97
02.01.06 PINTURA
PINTURA EN MUROS INTERIORES C/LATEX LAVABLE
02.01.06.01 m2 1,072.50 11.18 11,994.95
COLOR MARFIL
02.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO
02.01.07.01 ETERNIT(1,14x0.72x0.005m) m2 846.60 64.23 54,379.99

02.01.08 CARPINTERIA METALICA


SUMINISTRO E INSTALACION DE PUERTA METALICA
02.01.08.01 und 130.00 352.83 45,867.61
1.80x0.70m, INCL. MARCO Y PINTADO
02.01.09 CARPINTERIA DE MADERA
VENTANA DE MADERA TORNILLO INC. MALLA
02.01.09.01 m2 23.40 73.62 1,722.78
MOSQUITERA
02.01.09.02 COBERTURA DE MADERA PARA TECHO und 130.00 95.01 12,351.50
02.01.10 SISTEMA DE AGUA FRIA
02.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 1,231.00 3.54 4,358.36
02.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
02.01.11.01 TEE PVC-SAP 1/2" pza 260.00 20.22 5,258.37
02.01.11.02 CODO PVC SAP 1/2" pza 780.00 15.12 11,795.39
02.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 260.00 49.71 12,925.25
SUMINISTRO E INSTALACION DE DUCHA INCLUIDO
02.01.11.04 und 130.00 32.09 4,171.39
ACCESORIOS
02.01.12 SISTEMA DE DESAGUE
02.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 1,254.50 3.90 4,891.80
02.01.12.02 TUBERIA Ø=4" PVC SAL m 474.50 3.54 1,679.97
02.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
02.01.13.01 CODO PVC SAL 2"X90° pza 910.00 11.42 10,389.38
02.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 130.00 15.06 1,958.33
02.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 390.00 15.63 6,094.41
02.01.14 ADITAMIENTOS VARIOS
02.01.14.01 SUMIDEROS DE BRONCE 2" und 130.00 11.88 1,544.73
02.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 260.00 10.76 2,796.90
INODORO DE LOZA VITRIFICADA COLOR BLANCO
02.01.14.03 und 130.00 142.98 18,587.14
INCLUYE TANQUE
02.01.14.04 ACCESORIOS DE LOZA und 130.00 62.91 8,178.85
SUMINISTRO E INSTALACION DE TUBERIA DE
02.01.14.05 VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y GLB 130.00 28.28 3,675.82
ACCESORIOS
SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA
02.01.14.06 und 130.00 120.85 15,710.80
COLOR BLANCO INCLUIDO ACCESORIOS
SUMINISTRO E INSTALACION DE CAJA DE REGISTRO
02.01.14.07 und 260.00 125.99 32,758.26
DE 12"x24"
02.01.15 INSTALACIONES ELECTRICAS
02.01.15.01 SALIDA DE CENTRO DE LUZ pto 130.00 47.67 6,196.55
02.01.15.02 TUBERIA PVC SEL 5/8" m 299.00 4.03 1,203.62
02.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 728.00 2.21 1,610.04
02.01.15.04 TABLEROS DISTRIBUCION pza 130.00 86.37 11,227.94
02.01.16 CONSTRUCCION POZO PERCOLADOR
02.01.16.01 TRABAJOS PRELIMINARES
02.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 408.20 0.48 194.02
02.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 408.20 1.78 728.56
02.01.16.02 MOVIMIENTO DE TIERRAS
02.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 210.60 38.66 8,142.68
02.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 31.20 28.77 897.63
02.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 113.10 86.62 9,796.84
02.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 163.90 24.92 4,084.27
02.01.16.03 TAPA DE CONCRETO
02.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 22.10 435.38 9,622.00
02.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 236.60 43.15 10,208.25
02.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,736.50 4.22 11,546.67
02.01.16.04 ANILLO DE CONCRETO
02.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 9.10 345.30 3,142.24
02.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 156.00 43.15 6,730.71
02.01.16.05 MURO DE LADRILLO
MURO DE LADRILLO ARTESANAL AMARRE DE SOGA,
02.01.16.05.01 m2 543.40 47.47 25,796.18
JUNTA 1.5 CM MORTERO 1:1:5
02.01.16.06 SISTEMA DE DESAGUE LLEGADA
02.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 253.50 3.90 988.50
02.01.16.06.02 CODO PVC SAL 2"X90° pza 130.00 11.42 1,484.20
02.01.17 INSTALACION DEL BIODIGESTOR
02.01.17.01 TRABAJOS PRELIMINARES
02.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 491.40 0.48 233.57
02.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 491.40 1.78 877.05
02.01.17.02 MOVIMIENTO DE TIERRAS
02.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 396.70 38.66 15,338.09
02.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 299.24 28.77 8,609.20
02.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 504.11 24.92 12,562.07
02.01.17.03 CONCRETO SIMPLE
02.01.17.03.01 SOLADO E=4" m2 84.50 38.49 3,252.37
02.01.17.04 CONCRETO ARMADO
02.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 93.60 435.38 40,751.99
02.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 587.60 43.15 25,352.36
02.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 724.10 4.22 3,055.34
02.01.17.05 BIODIGESTOR
SUMINISTRO E INSTALACION DE BIODIGESTOR
02.01.17.05.01 und 121.00 756.20 91,500.48
AUTOLIMPIABLE DE PVC DE 600 LTS
SUMINISTRO E INSTALACION DE BIODIGESTOR
02.01.17.05.02 und 9.00 1,281.17 11,530.50
AUTOLIMPIABLE DE PVC DE 1300 LTS
02.01.17.06 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.01.17.06.01 m2 464.10 31.51 14,621.75
MEZCLA 1:2 E=2 cm H=1.5 Max
02.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
02.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 130.00 3.90 506.92
SUMINISTRO E INSTALACION DE VALVULA DE PVC
02.01.17.07.02 und 130.00 28.96 3,765.35
DE 2"
02.02 LAVADERO INTRADOMICILIARIO (121 UND)
02.02.01 OBRAS PRELIMINARES
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 612.26 0.48 291.01
02.02.01.02 TRAZO Y REPLANTEO m2 612.26 1.78 1,092.76
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 137.00 36.36 4,980.72
RELLENO Y COMPACTADO DE ZANJA CON MATERIAL
02.02.02.02 m3 112.53 12.72 1,431.01
PROPIO CLASIFICADO
02.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 28.14 24.92 701.23
02.02.03 OBRAS DE CONCRETO ARMADO
02.02.03.01 CONCRETO f'c=175 kg/cm2 m3 12.72 435.38 5,538.09
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 405.06 43.15 17,476.56
02.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 478.56 4.22 2,019.29
02.02.04 MURO DE LADRILLO
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
02.02.04.01 m2 80.01 46.31 3,705.09
Lavaderos)
02.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.02.05.01 m2 142.66 31.51 4,494.59
MEZCLA 1:2 E=2 cm H=1.5 Max
02.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 272.98 28.87 7,880.16
02.02.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE LAVADERO
02.02.06.01 und 121.00 132.22 15,998.70
INTRADOMICILIARIA
02.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
02.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 605.00 3.25 1,965.95
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01
02.03
UND)
02.03.01 TRABAJOS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.48 5.38

02.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.78 20.21

02.03.02 MOVIMIENTO DE TIERRAS


02.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 36.36 99.62
REFINE, NIVELACION Y COMPACTADO EN TERRENO
02.03.02.02 m2 11.32 11.20
NORMAL
02.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 28.62 46.36
02.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 24.92 33.39
02.03.03 OBRAS DE CONCRETO SIMPLE
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
02.03.03.01 m2 2.20 47.49 104.48
FROTACHADO C/MEZCLADORA
02.03.04 OBRAS DE CONCRETO ARMADO
02.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.22 35.23

02.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 42.69 174.60

CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA


02.03.04.03 m3 0.21 435.38 91.43
LAVADEROS
02.03.05 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
02.03.05.01 m2 2.49 31.97 79.61
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
02.03.05.02 m2 2.11 23.26 49.08
H=1.5 MAX
02.03.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.03.06.01 und 1.00 171.68 171.68
LAVADERO I.E. INICIAL
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
02.03.06.02 und 2.00 138.23 276.45
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
02.03.06.03 und 1.00 56.04 56.04
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
02.03.06.04 und 1.00 46.74 46.74
(INTERIORES), E=0.05
02.03.07 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10,
02.03.07.01 m 12.00 6.16 73.91
P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
02.03.07.02 m 10.00 6.45 64.51
PARA DESAGUE Ø=2"x3 M
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01
02.04
UND)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.48 5.69

02.04.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.78 21.38

02.04.02 MOVIMIENTO DE TIERRAS


02.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 36.36 101.79
REFINE, NIVELACION Y COMPACTADO EN TERRENO
02.04.02.02 m2 11.98 0.99 11.85
NORMAL
02.04.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 28.62 46.36
02.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 24.92 35.13
02.04.03 OBRAS DE CONCRETO SIMPLE
CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6")
02.04.03.01 m3 0.06 329.41 19.77
EN LAVADERO C/MEZCLADORA
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
02.04.03.02 m2 2.86 47.49 135.83
FROTACHADO C/MEZCLADORA
02.04.04 OBRAS DE CONCRETO ARMADO 0.00
02.04.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.22 48.48

02.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 42.69 184.84

CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA


02.04.04.03 m3 0.31 435.38 134.97
LAVADEROS
02.04.05 ALBAÑILERIA
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
02.04.05.01 m2 0.36 56.34 20.28
Lavaderos)
02.04.06 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
02.04.06.01 m2 3.51 31.97 112.22
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
02.04.06.02 m2 3.29 23.26 76.52
H=1.5 MAX
02.04.07 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.04.07.01 und 1.00 171.68 171.68
LAVADERO TIPO I.E. PRIMARIA
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
02.04.07.02 und 2.00 138.23 276.45
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
02.04.07.03 und 1.00 56.04 56.04
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
02.04.07.04 und 1.00 46.74 46.74
(INTERIORES), E=0.05
02.04.08 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002 PARA
02.04.08.01 m 12.00 6.16 73.91
AGUA CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
02.04.08.02 m 10.00 6.45 64.51
PARA DESAGUE Ø=2"x3 M
02.05 LAVADERO I.E. SECUNDARIA (01 UND)
02.05.01 TRABAJOS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.48 5.38

02.05.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.78 20.21

02.05.02 MOVIMIENTO DE TIERRAS


02.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 3.70 36.36 134.52
REFINE, NIVELACION Y COMPACTADO EN TERRENO
02.05.02.02 m2 11.32 0.99 11.20
NORMAL
02.05.02.03 RELLENO CON MATERIAL PROPIO m3 2.64 28.62 75.54
02.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.27 24.92 31.65
02.05.03 OBRAS DE CONCRETO SIMPLE 0.00
CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6")
02.05.03.01 m3 0.08 329.41 26.35
EN LAVADERO C/MEZCLADORA
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
02.05.03.02 m2 0.22 47.49 10.45
FROTACHADO C/MEZCLADORA
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 0.26 4.22 1.10

02.05.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 5.20 42.69 221.98

CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA


02.05.04.03 m3 12.73 435.38 5,542.44
LAVADEROS
02.05.05 ALBAÑILERIA
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
02.05.05.01 m2 1.04 56.34 58.59
Lavaderos)
02.05.06 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
02.05.06.01 m2 3.13 31.97 100.07
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
02.05.06.02 m2 4.41 23.26 102.58
H=1.5 MAX
02.05.07 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.05.07.01 und 1.00 171.68 171.68
LAVADERO TIPO I.E. PRIMARIA
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
02.05.07.02 und 2.00 138.23 276.45
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
02.05.07.03 und 1.00 56.04 56.04
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
02.05.07.04 und 1.00 46.74 46.74
(INTERIORES), E=0.05
02.05.08 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002 PARA
02.05.08.01 m 12.00 6.16 73.91
AGUA CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
02.05.08.02 m 10.00 6.45 64.51
PARA DESAGUE Ø=2"x3 M
03 LOCALIDAD TANCARPATA (55 UND)
03.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
03.01.01 TRABAJOS PRELIMINARES
03.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 275.00 0.48 130.71
03.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 275.00 1.78 490.82
03.01.02 MOVIMIENTO DE TIERRAS

03.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 136.95 38.66 5,295.07

03.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 24.20 28.77 696.24


03.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 140.80 24.92 3,508.64
03.01.03 CONCRETO SIMPLE
03.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 165.00 362.54 59,818.69
03.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 24.20 386.73 9,358.85
03.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 401.50 43.15 17,322.96
03.01.03.04 CONCRETO f'c=175 kg/cm2 m3 17.05 435.38 7,423.30
03.01.04 MURO DE LADRILLO
MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE
03.01.04.01 m2 800.80 56.36 45,130.69
SOGA C/M 1:4 x 1.5cm
EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO
03.01.04.02 m2 15.40 68.22 1,050.59
4"-6"
03.01.05 REVOQUES Y ENLUCIDOS
TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE
03.01.05.01 m2 752.40 15.85 11,925.39
P/CAMARA (UBS arrastre hidraulico)
03.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 12.10 35.45 428.99
03.01.06 PINTURA
PINTURA EN MUROS INTERIORES C/LATEX LAVABLE
03.01.06.01 m2 453.75 11.18 5,074.79
COLOR MARFIL
03.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO
03.01.07.01 ETERNIT(1,14x0.72x0.005m) m2 358.05 64.23 22,998.77

03.01.08 CARPINTERIA METALICA


SUMINISTRO E INSTALACION DE PUERTA METALICA
03.01.08.01 und 55.00 352.83 19,405.53
1.80x0.70m, INCL. MARCO Y PINTADO
03.01.09 CARPINTERIA DE MADERA
VENTANA DE MADERA TORNILLO INC. MALLA
03.01.09.01 m2 9.90 73.62 728.87
MOSQUITERA
03.01.09.02 COBERTURA DE MADERA PARA TECHO und 55.00 95.01 5,225.63
03.01.10 SISTEMA DE AGUA FRIA
03.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 520.85 3.54 1,844.07
03.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
03.01.11.01 TEE PVC-SAP 1/2" pza 110.00 20.22 2,224.70
03.01.11.02 CODO PVC SAP 1/2" pza 330.00 15.12 4,990.36
03.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 110.00 49.71 5,468.38
SUMINISTRO E INSTALACION DE DUCHA INCLUIDO
03.01.11.04 und 55.00 32.09 1,764.82
ACCESORIOS
03.01.12 SISTEMA DE DESAGUE
03.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 530.75 3.90 2,069.61
03.01.12.02 TUBERIA Ø=4" PVC SAL m 200.75 3.54 710.76
03.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
03.01.13.01 CODO PVC SAL 2"X90° pza 385.00 11.42 4,395.51
03.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 55.00 15.06 828.53
03.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 165.00 15.63 2,578.41
03.01.14 ADITAMIENTOS VARIOS
03.01.14.01 SUMIDEROS DE BRONCE 2" und 55.00 11.88 653.54
03.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 110.00 10.76 1,183.30
INODORO DE LOZA VITRIFICADA COLOR BLANCO
03.01.14.03 und 55.00 142.98 7,863.79
INCLUYE TANQUE
03.01.14.04 ACCESORIOS DE LOZA und 55.00 62.91 3,460.28
SUMINISTRO E INSTALACION DE TUBERIA DE
03.01.14.05 VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y GLB 55.00 28.28 1,555.15
ACCESORIOS
SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA
03.01.14.06 und 55.00 120.85 6,646.88
COLOR BLANCO INCLUIDO ACCESORIOS
SUMINISTRO E INSTALACION DE CAJA DE REGISTRO
03.01.14.07 und 110.00 125.99 13,859.26
DE 12"x24"
03.01.15 INSTALACIONES ELECTRICAS
03.01.15.01 SALIDA DE CENTRO DE LUZ pto 55.00 47.67 2,621.62
03.01.15.02 TUBERIA PVC SEL 5/8" m 126.50 4.03 509.23
03.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 308.00 2.21 681.17
03.01.15.04 TABLEROS DISTRIBUCION pza 55.00 86.37 4,750.28
03.01.16 CONSTRUCCION POZO PERCOLADOR
03.01.16.01 TRABAJOS PRELIMINARES
03.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 172.70 0.48 82.08
03.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 172.20 1.78 307.34
03.01.16.02 MOVIMIENTO DE TIERRAS
03.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 89.10 38.66 3,444.98
03.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 13.20 28.77 379.76
03.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 47.85 86.62 4,144.82
03.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 111.65 24.92 2,782.24
03.01.16.03 TAPA DE CONCRETO
03.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 9.35 435.38 4,070.85
03.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 100.10 43.15 4,318.88
03.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,157.75 4.22 4,885.12
03.01.16.04 ANILLO DE CONCRETO
03.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 3.85 345.30 1,329.40
03.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.00 43.15 2,847.61
03.01.16.05 MURO DE LADRILLO
MURO DE LADRILLO ARTESANAL AMARRE DE SOGA,
03.01.16.05.01 m2 229.90 47.47 10,913.77
JUNTA 1.5 CM MORTERO 1:1:5
03.01.16.06 SISTEMA DE DESAGUE LLEGADA
03.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 107.25 3.90 418.22
03.01.16.06.02 CODO PVC SAL 2"X90° pza 55.00 11.42 627.93
03.01.17 INSTALACION DEL BIODIGESTOR
03.01.17.01 TRABAJOS PRELIMINARES
03.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 207.90 0.48 98.81
03.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 207.90 1.78 371.06
03.01.17.02 MOVIMIENTO DE TIERRAS
03.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 170.94 38.66 6,609.26
03.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 129.10 28.77 3,714.24
03.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 213.67 24.92 5,324.50
03.01.17.03 CONCRETO SIMPLE
03.01.17.03.01 SOLADO E=4" m2 35.75 38.49 1,376.00
03.01.17.04 CONCRETO ARMADO
03.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 39.60 435.38 17,241.23
03.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.60 43.15 10,726.00
03.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 306.35 4.22 1,292.64
03.01.17.05 BIODIGESTOR
SUMINISTRO E INSTALACION DE BIODIGESTOR
03.01.17.05.01 und 51.00 756.20 38,566.32
AUTOLIMPIABLE DE PVC DE 600 LTS
SUMINISTRO E INSTALACION DE BIODIGESTOR
03.01.17.05.02 und 4.00 1,281.17 5,124.67
AUTOLIMPIABLE DE PVC DE 1300 LTS
03.01.17.06 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.01.17.06.01 m2 196.35 31.51 6,186.13
MEZCLA 1:2 E=2 cm H=1.5 Max
03.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
03.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 55.00 3.90 214.47
SUMINISTRO E INSTALACION DE VALVULA DE PVC
03.01.17.07.02 und 55.00 28.96 1,593.03
DE 2"
03.02 LAVADERO INTRADOMICILIARIO (51 UND)
03.02.01 OBRAS PRELIMINARES
03.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 258.06 0.48 122.66
03.02.01.02 TRAZO Y REPLANTEO m2 258.06 1.78 460.59
03.02.02 MOVIMIENTO DE TIERRAS
03.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 57.74 36.36 2,099.18
RELLENO Y COMPACTADO DE ZANJA CON MATERIAL
03.02.02.02 m3 47.43 12.72 603.16
PROPIO CLASIFICADO
03.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.86 24.92 295.54
03.02.03 OBRAS DE CONCRETO ARMADO
03.02.03.01 CONCRETO f'c=175 kg/cm2 m3 5.36 435.38 2,333.66
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 170.73 43.15 7,366.25
03.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 201.71 4.22 851.12
03.02.04 MURO DE LADRILLO
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
03.02.04.01 m2 33.72 46.31 1,561.50
Lavaderos)
03.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.02.05.01 m2 60.13 31.51 1,894.43
MEZCLA 1:2 E=2 cm H=1.5 Max
03.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 115.06 28.87 3,321.46
03.02.06 ACCESORIOS Y VALVULAS 0.00
SUMINISTRO E INSTALACION DE LAVADERO
03.02.06.01 und 51.00 132.22 6,743.26
INTRADOMICILIARIA
03.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO 0.00
03.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 255.00 3.25 828.62
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01
03.03
UND)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.48 5.38

03.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.78 20.21

03.03.02 MOVIMIENTO DE TIERRAS 0.00


03.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 36.36 99.62
REFINE, NIVELACION Y COMPACTADO EN TERRENO
03.03.02.02 m2 11.32 0.99 11.20
NORMAL
03.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 28.62 46.36
03.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 24.92 33.39
03.03.03 OBRAS DE CONCRETO SIMPLE
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
03.03.03.01 m2 2.20 47.49 104.48
FROTACHADO C/MEZCLADORA
03.03.04 OBRAS DE CONCRETO ARMADO
03.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.22 35.23

03.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 42.69 174.60

CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA


03.03.04.03 m3 0.21 435.38 91.43
LAVADEROS
03.03.05 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
03.03.05.01 m2 2.49 31.97 79.61
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
03.03.05.02 m2 2.11 23.26 49.08
H=1.5 MAX
03.03.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.03.06.01 und 1.00 171.68 171.68
LAVADERO I.E. INICIAL
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
03.03.06.02 und 2.00 138.23 276.45
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
03.03.06.03 und 1.00 56.04 56.04
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
03.03.06.04 und 1.00 46.74 46.74
(INTERIORES), E=0.05
03.03.07 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10,
03.03.07.01 m 12.00 6.16 73.91
P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
03.03.07.02 m 10.00 6.45 64.51
PARA DESAGUE Ø=2"x3 M
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01
03.04
UND)
03.04.01 TRABAJOS PRELIMINARES
03.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.48 5.69

03.04.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.78 21.38

03.04.02 MOVIMIENTO DE TIERRAS


03.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 36.36 101.79
REFINE, NIVELACION Y COMPACTADO EN TERRENO
03.04.02.02 m2 11.98 0.99 11.85
NORMAL
03.04.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 28.62 46.36
03.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 24.92 35.13
03.04.03 OBRAS DE CONCRETO SIMPLE
CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6")
03.04.03.01 m3 0.06 329.41 19.77
EN LAVADERO C/MEZCLADORA
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
03.04.03.02 m2 2.86 47.49 135.83
FROTACHADO C/MEZCLADORA
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.22 48.48

03.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 42.69 184.84

CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA


03.04.04.03 m3 0.31 435.38 134.97
LAVADEROS
03.04.05 ALBAÑILERIA
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
03.04.05.01 m2 0.36 56.34 20.28
Lavaderos)
03.04.06 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
03.04.06.01 m2 3.51 31.97 112.22
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
03.04.06.02 m2 3.29 23.26 76.52
H=1.5 MAX
03.04.07 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.04.07.01 und 1.00 171.68 171.68
LAVADERO TIPO I.E. PRIMARIA
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
03.04.07.02 und 2.00 138.23 276.45
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
03.04.07.03 und 1.00 56.04 56.04
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
03.04.07.04 und 1.00 46.74 46.74
(INTERIORES), E=0.05
03.04.08 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002 PARA
03.04.08.01 m 12.00 6.16 73.91
AGUA CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
03.04.08.02 m 10.00 6.45 64.51
PARA DESAGUE Ø=2"x3 M
04 LOCALIDAD TARACA (55 UND)
04.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
04.01.01 TRABAJOS PRELIMINARES
04.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 275.00 0.48 130.71
04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 275.00 1.78 490.82
04.01.02 MOVIMIENTO DE TIERRAS

04.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 136.95 38.66 5,295.07

04.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 24.20 28.77 696.24


04.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 140.80 24.92 3,508.64
04.01.03 CONCRETO SIMPLE
04.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 165.00 362.54 59,818.69
04.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 24.20 386.73 9,358.85
04.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 401.50 43.15 17,322.96
04.01.03.04 CONCRETO f'c=175 kg/cm2 m3 17.05 435.38 7,423.30
04.01.04 MURO DE LADRILLO
MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE
04.01.04.01 m2 800.80 56.36 45,130.69
SOGA C/M 1:4 x 1.5cm
EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO
04.01.04.02 m2 15.40 68.22 1,050.59
4"-6"
04.01.05 REVOQUES Y ENLUCIDOS
TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE
04.01.05.01 m2 752.40 15.85 11,925.39
P/CAMARA (UBS arrastre hidraulico)
04.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 12.10 35.45 428.99
04.01.06 PINTURA
PINTURA EN MUROS INTERIORES C/LATEX LAVABLE
04.01.06.01 m2 453.75 11.18 5,074.79
COLOR MARFIL
04.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO
04.01.07.01 ETERNIT(1,14x0.72x0.005m) m2 358.05 64.23 22,998.77

04.01.08 CARPINTERIA METALICA


SUMINISTRO E INSTALACION DE PUERTA METALICA
04.01.08.01 und 55.00 352.83 19,405.53
1.80x0.70m, INCL. MARCO Y PINTADO
04.01.09 CARPINTERIA DE MADERA
VENTANA DE MADERA TORNILLO INC. MALLA
04.01.09.01 m2 9.90 73.62 728.87
MOSQUITERA
04.01.09.02 COBERTURA DE MADERA PARA TECHO und 55.00 95.01 5,225.63
04.01.10 SISTEMA DE AGUA FRIA
04.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 520.85 3.54 1,844.07
04.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA 0.00
04.01.11.01 TEE PVC-SAP 1/2" pza 110.00 20.22 2,224.70
04.01.11.02 CODO PVC SAP 1/2" pza 330.00 15.12 4,990.36
04.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 110.00 49.71 5,468.38
SUMINISTRO E INSTALACION DE DUCHA INCLUIDO
04.01.11.04 und 55.00 32.09 1,764.82
ACCESORIOS
04.01.12 SISTEMA DE DESAGUE
04.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 530.75 3.90 2,069.61
04.01.12.02 TUBERIA Ø=4" PVC SAL m 200.75 3.54 710.76
04.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
04.01.13.01 CODO PVC SAL 2"X90° pza 385.00 11.42 4,395.51
04.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 55.00 15.06 828.53
04.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 165.00 15.63 2,578.41
04.01.14 ADITAMIENTOS VARIOS
04.01.14.01 SUMIDEROS DE BRONCE 2" und 55.00 11.88 653.54
04.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 110.00 10.76 1,183.30
INODORO DE LOZA VITRIFICADA COLOR BLANCO
04.01.14.03 und 55.00 142.98 7,863.79
INCLUYE TANQUE
04.01.14.04 ACCESORIOS DE LOZA und 55.00 62.91 3,460.28
SUMINISTRO E INSTALACION DE TUBERIA DE
04.01.14.05 VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y GLB 55.00 28.28 1,555.15
ACCESORIOS
SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA
04.01.14.06 und 55.00 120.85 6,646.88
COLOR BLANCO INCLUIDO ACCESORIOS
SUMINISTRO E INSTALACION DE CAJA DE REGISTRO
04.01.14.07 und 110.00 125.99 13,859.26
DE 12"x24"
04.01.15 INSTALACIONES ELECTRICAS
04.01.15.01 SALIDA DE CENTRO DE LUZ pto 55.00 47.67 2,621.62
04.01.15.02 TUBERIA PVC SEL 5/8" m 126.50 4.03 509.23
04.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 308.00 2.21 681.17
04.01.15.04 TABLEROS DISTRIBUCION pza 55.00 86.37 4,750.28
04.02 CONSTRUCCION POZO PERCOLADOR
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 172.70 0.48 82.08
04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 172.20 1.78 307.34
04.02.02 MOVIMIENTO DE TIERRAS
04.02.02.01 EXCAVACION A MANO TERRENO NORMAL m3 89.10 38.66 3,444.98
04.02.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 13.20 28.77 379.76
04.02.02.03 FILTRO DE GRAVA CLASIFICADA m3 47.85 86.62 4,144.82
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 111.65 24.92 2,782.24
04.02.03 TAPA DE CONCRETO
04.02.03.01 CONCRETO f'c=175 kg/cm2 m3 9.35 435.38 4,070.85
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 100.10 43.15 4,318.88
04.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,157.75 4.22 4,885.12
04.02.04 ANILLO DE CONCRETO
04.02.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 3.85 345.30 1,329.40
04.02.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.00 43.15 2,847.61
04.02.05 MURO DE LADRILLO
MURO DE LADRILLO ARTESANAL AMARRE DE SOGA,
04.02.05.01 m2 229.90 47.47 10,913.77
JUNTA 1.5 CM MORTERO 1:1:5
04.02.06 SISTEMA DE DESAGUE LLEGADA
04.02.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 107.25 3.90 418.22
04.02.06.02 CODO PVC SAL 2"X90° pza 55.00 11.42 627.93
04.03 INSTALACION DEL BIODIGESTOR
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 207.90 0.48 98.81
04.03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 207.90 1.78 371.06
04.03.02 MOVIMIENTO DE TIERRAS
04.03.02.01 EXCAVACION A MANO TERRENO NORMAL m3 170.94 38.66 6,609.26
04.03.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 129.10 28.77 3,714.24
04.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 213.67 24.92 5,324.50
04.03.03 CONCRETO SIMPLE
04.03.03.01 SOLADO E=4" m2 35.75 38.49 1,376.00
04.03.04 CONCRETO ARMADO
04.03.04.01 CONCRETO f'c=175 kg/cm2 m3 39.60 435.38 17,241.23
04.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.60 43.15 10,726.00
04.03.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 306.35 4.22 1,292.64
04.03.05 BIODIGESTOR
SUMINISTRO E INSTALACION DE BIODIGESTOR
04.03.05.01 und 51.00 756.20 38,566.32
AUTOLIMPIABLE DE PVC DE 600 LTS
SUMINISTRO E INSTALACION DE BIODIGESTOR
04.03.05.02 und 4.00 1,281.17 5,124.67
AUTOLIMPIABLE DE PVC DE 1300 LTS
04.03.06 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.03.06.01 m2 196.35 31.51 6,186.13
MEZCLA 1:2 E=2 cm H=1.5 Max
04.03.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
04.03.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 55.00 3.90 214.47
SUMINISTRO E INSTALACION DE VALVULA DE PVC DE
04.03.07.02 und 55.00 28.96 1,593.03
2"
04.04 LAVADERO INTRADOMICILIARIO (51 UND)
04.04.01 OBRAS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 258.06 0.48 122.66
04.04.01.02 TRAZO Y REPLANTEO m2 258.06 1.78 460.59
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 57.74 36.36 2,099.18
RELLENO Y COMPACTADO DE ZANJA CON MATERIAL
04.04.02.02 m3 47.43 12.72 603.16
PROPIO CLASIFICADO
04.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.86 24.92 295.54
04.04.03 OBRAS DE CONCRETO ARMADO
04.04.03.01 CONCRETO f'c=175 kg/cm2 m3 5.36 435.38 2,333.66
04.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 170.73 43.15 7,366.25
04.04.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 201.71 4.22 851.12
04.04.04 MURO DE LADRILLO
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
04.04.04.01 m2 33.72 46.31 1,561.50
Lavaderos)
04.04.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.04.05.01 m2 60.13 31.51 1,894.43
MEZCLA 1:2 E=2 cm H=1.5 Max
04.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 115.06 28.87 3,321.46
04.04.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE LAVADERO
04.04.06.01 und 51.00 132.22 6,743.26
INTRADOMICILIARIA
04.04.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
04.04.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 255.00 3.25 828.62
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01
04.05
UND)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.48 5.38

04.05.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.78 20.21

04.05.02 MOVIMIENTO DE TIERRAS


04.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 36.36 99.62
REFINE, NIVELACION Y COMPACTADO EN TERRENO
04.05.02.02 m2 11.32 0.99 11.20
NORMAL
04.05.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 28.62 46.36
04.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 24.92 33.39
04.05.03 OBRAS DE CONCRETO SIMPLE
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
04.05.03.01 m2 2.20 47.49 104.48
FROTACHADO C/MEZCLADORA
04.05.04 OBRAS DE CONCRETO ARMADO
04.05.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 4.22 35.23

04.05.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 42.69 174.60

CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA


04.05.04.03 m3 0.21 435.38 91.43
LAVADEROS
04.05.05 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
04.05.05.01 m2 2.49 31.97 79.61
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
04.05.05.02 m2 2.11 23.26 49.08
H=1.5 MAX
04.05.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.05.06.01 und 1.00 171.68 171.68
LAVADERO I.E. INICIAL
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
04.05.06.02 und 2.00 138.23 276.45
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
04.05.06.03 und 1.00 56.04 56.04
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
04.05.06.04 und 1.00 46.74 46.74
(INTERIORES), E=0.05
04.05.07 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10,
04.05.07.01 m 12.00 6.16 73.91
P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
04.05.07.02 m 10.00 6.45 64.51
PARA DESAGUE Ø=2"x3 M
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01
04.06
UND)
04.06.01 TRABAJOS PRELIMINARES
04.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.48 5.69

04.06.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.78 21.38

04.06.02 MOVIMIENTO DE TIERRAS


04.06.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 36.36 101.79
REFINE, NIVELACION Y COMPACTADO EN TERRENO
04.06.02.02 m2 11.98 0.99 11.85
NORMAL
04.06.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 28.62 46.36
04.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 24.92 35.13
04.06.03 OBRAS DE CONCRETO SIMPLE
CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6")
04.06.03.01 m3 0.06 329.41 19.77
EN LAVADERO C/MEZCLADORA
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
04.06.03.02 m2 2.86 47.49 135.83
FROTACHADO C/MEZCLADORA
04.06.04 OBRAS DE CONCRETO ARMADO
04.06.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 4.22 48.48
04.06.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 42.69 184.84

CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA


04.06.04.03 m3 0.31 435.38 134.97
LAVADEROS
04.06.05 ALBAÑILERIA
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
04.06.05.01 m2 0.36 56.34 20.28
Lavaderos)
04.06.06 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
04.06.06.01 m2 3.51 31.97 112.22
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
04.06.06.02 m2 3.29 23.26 76.52
H=1.5 MAX
04.06.07 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.06.07.01 und 1.00 171.68 171.68
LAVADERO TIPO I.E. PRIMARIA
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
04.06.07.02 und 2.00 138.23 276.45
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
04.06.07.03 und 1.00 56.04 56.04
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
04.06.07.04 und 1.00 46.74 46.74
(INTERIORES), E=0.05
04.06.08 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002 PARA
04.06.08.01 m 12.00 6.16 73.91
AGUA CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
04.06.08.02 m 10.00 6.45 64.51
PARA DESAGUE Ø=2"x3 M

01 LOCALIDAD SANTA LUCIA


CAPACITACION EN EDUCACION SANITARIA, PROMOCION
01.01
DE LA SALUD Y AOM
01.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
TALLER IMPORTANCIA DE LA ORGANIZACION Y
01.01.01.01 Tall 1.00 912.38 912.38
PARTICIPACION CIUDADANA
01.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 912.38 912.38
EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE
01.01.02
Y SALUD)
TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y
01.01.02.01 Tall 1.00 912.39 912.39
SALUD (Valoracion del agua)
TALLER DE IMPORTANCIA DE LA DECUADA
01.01.02.02 Tall 1.00 912.39 912.39
ELIMINACION DE EXCRETAS
TALLER DE PREVENCION DE ENFERMEDADES
01.01.02.03 LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE Tall 1.00 912.39 912.39
PERSONAL DEL HOGAR Y COMUNAL
CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR
01.01.02.04 Tall 1.00 912.39 912.39
Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE.
DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y
01.01.02.05 Men 2.00 82.20 164.40
SANEAMIENTO (SPOT PUBLICITARIO)
01.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
TALLER DE ADMINIST., CONTABILIDAD Y
01.01.03.01 Tall 1.00 912.39 912.39
FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS
TALLER RECONOCIMIENTO DE LOS COMPONENTES
01.01.03.02 DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. Tall 1.00 912.39 912.39
AGUA POTABLE
01.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 912.39 912.39
TALLER DE CLORACION Y DESINFECCION DE AGUA
01.01.03.04 Tall 1.00 1,076.81 1,076.81
PARA CONSUMO HUMANO
01.02 FLETE
01.02.01 FLETE RURAL
01.02.01.01 FLETE RURAL GLB 1.00 24,633.70 24,633.70
01.02.02 FLETE TERRESTRE
01.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,583.25 4,583.25
01.02.02.02 FLETE TERRESTRE GLB 1.00 10,258.98 10,258.98
01.03 MITIGACION AMBIENTAL
01.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,754.80 2,754.80
PROGRAMA DE CONSERVACION, RESTAURACION Y
01.03.02 COMPESACION DE COBERTURA VEGETAL GLB 1.00 1,660.64 1,660.64
(REFORESTACION)
01.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,298.00 3,298.00
01.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 970.00 970.00
PROGRAMA DE CAPACITACION Y EDUCACION
01.03.05 GLB 1.00 485.00 485.00
AMBIENTAL
01.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,492.00 3,492.00
01.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 582.00 582.00
01.04 CONTROL Y SEGURIDAD EN OBRA 0.00
01.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 6,750.89 6,750.89
02 LOCALIDAD PUEBLO LIBRE
CAPACITACION EN EDUCACION SANITARIA, PROMOCION
02.01
DE LA SALUD Y AOM
02.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
TALLER IMPORTANCIA DE LA ORGANIZACION Y
02.01.01.01 Tall 1.00 912.38 912.38
PARTICIPACION CIUDADANA
02.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 912.38 912.38
EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE
02.01.02
Y SALUD)
TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y
02.01.02.01 Tall 1.00 912.39 912.39
SALUD (Valoracion del agua)
TALLER DE IMPORTANCIA DE LA DECUADA
02.01.02.02 Tall 1.00 912.39 912.39
ELIMINACION DE EXCRETAS
TALLER DE PREVENCION DE ENFERMEDADES
02.01.02.03 LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE Tall 1.00 912.39 912.39
PERSONAL DEL HOGAR Y COMUNAL
CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR
02.01.02.04 Tall 1.00 912.39 912.39
Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE.
DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y
02.01.02.05 Men 2.00 82.20 164.40
SANEAMIENTO (SPOT PUBLICITARIO)
02.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
TALLER DE ADMINIST., CONTABILIDAD Y
02.01.03.01 Tall 1.00 912.39 912.39
FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS
TALLER RECONOCIMIENTO DE LOS COMPONENTES
02.01.03.02 DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. Tall 1.00 912.39 912.39
AGUA POTABLE
02.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 912.39 912.39
TALLER DE CLORACION Y DESINFECCION DE AGUA
02.01.03.04 Tall 1.00 1,076.81 1,076.81
PARA CONSUMO HUMANO
02.02 FLETE
02.02.01 FLETE RURAL
02.02.01.01 FLETE RURAL GLB 1.00 33,837.50 33,837.50
02.02.02 FLETE TERRESTRE 0.00
02.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,583.25 4,583.25
02.02.02.02 FLETE TERRESTRE GLB 1.00 16,818.81 16,818.81
02.02.03 MITIGACION AMBIENTAL
02.02.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,754.80 2,754.80
PROGRAMA DE CONSERVACION, RESTAURACION Y
02.02.03.02 COMPESACION DE COBERTURA VEGETAL GLB 1.00 1,660.64 1,660.64
(REFORESTACION)
02.02.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,298.00 3,298.00
02.02.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 970.00 970.00
PROGRAMA DE CAPACITACION Y EDUCACION
02.02.03.05 GLB 1.00 485.00 485.00
AMBIENTAL
02.02.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,492.00 3,492.00
02.02.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 582.00 582.00
02.02.04 CONTROL Y SEGURIDAD EN OBRA
02.02.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 8,944.72 8,944.72
03 LOCALIDAD TANCARPATA
CAPACITACION EN EDUCACION SANITARIA, PROMOCION
03.01
DE LA SALUD Y AOM
03.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
TALLER IMPORTANCIA DE LA ORGANIZACION Y
03.01.01.01 Tall 1.00 912.38 912.38
PARTICIPACION CIUDADANA
03.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 912.38 912.38
EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE
03.01.02
Y SALUD)
TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y
03.01.02.01 Tall 1.00 912.39 912.39
SALUD (Valoracion del agua)
TALLER DE IMPORTANCIA DE LA DECUADA
03.01.02.02 Tall 1.00 912.39 912.39
ELIMINACION DE EXCRETAS
TALLER DE PREVENCION DE ENFERMEDADES
03.01.02.03 LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE Tall 1.00 912.39 912.39
PERSONAL DEL HOGAR Y COMUNAL
CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR
03.01.02.04 Tall 1.00 912.39 912.39
Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE.
DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y
03.01.02.05 Men 2.00 82.20 164.40
SANEAMIENTO (SPOT PUBLICITARIO)
03.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
TALLER DE ADMINIST., CONTABILIDAD Y
03.01.03.01 Tall 1.00 912.39 912.39
FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS
TALLER RECONOCIMIENTO DE LOS COMPONENTES
03.01.03.02 DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. Tall 1.00 912.39 912.39
AGUA POTABLE
03.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 912.39 912.39
TALLER DE CLORACION Y DESINFECCION DE AGUA
03.01.03.04 Tall 1.00 1,076.81 1,076.81
PARA CONSUMO HUMANO
03.02 FLETE
03.02.01 FLETE RURAL
03.02.01.01 FLETE RURAL GLB 1.00 14,888.50 14,888.50
03.02.02 FLETE TERRESTRE
03.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,583.25 4,583.25
03.02.02.02 FLETE TERRESTRE GLB 1.00 6,658.48 6,658.48
03.03 MITIGACION AMBIENTAL
03.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,754.80 2,754.80
PROGRAMA DE CONSERVACION, RESTAURACION Y
03.03.02 COMPESACION DE COBERTURA VEGETAL GLB 1.00 1,660.64 1,660.64
(REFORESTACION)
03.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,298.00 3,298.00
03.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 970.00 970.00
PROGRAMA DE CAPACITACION Y EDUCACION
03.03.05 GLB 1.00 485.00 485.00
AMBIENTAL
03.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,492.00 3,492.00
03.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 582.00 582.00
03.04 CONTROL Y SEGURIDAD EN OBRA
03.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 4,428.01 4,428.01
04 LOCALIDAD TARACA
CAPACITACION EN EDUCACION SANITARIA, PROMOCION
04.01
DE LA SALUD Y AOM
04.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
TALLER IMPORTANCIA DE LA ORGANIZACION Y
04.01.01.01 Tall 1.00 912.38 912.38
PARTICIPACION CIUDADANA
04.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 912.38 912.38
EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE
04.01.02
Y SALUD)
TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y
04.01.02.01 Tall 1.00 912.39 912.39
SALUD (Valoracion del agua)
TALLER DE IMPORTANCIA DE LA DECUADA
04.01.02.02 Tall 1.00 912.39 912.39
ELIMINACION DE EXCRETAS
TALLER DE PREVENCION DE ENFERMEDADES
04.01.02.03 LIGADAS AL SANEAMIENTO Y HABITOS DE HIGIENE Tall 1.00 912.39 912.39
PERSONAL DEL HOGAR Y COMUNAL
CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR
04.01.02.04 Tall 1.00 912.39 912.39
Y COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE.
DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y
04.01.02.05 Men 2.00 82.20 164.40
SANEAMIENTO (SPOT PUBLICITARIO)
04.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
TALLER DE ADMINIST., CONTABILIDAD Y
04.01.03.01 Tall 1.00 912.39 912.39
FORMULACION DE PLAN OPERATIVO ANUAL DE LA JASS
TALLER RECONOCIMIENTO DE LOS COMPONENTES
04.01.03.02 DEL SISTEMA Y OPERACION Y MANTENEMIENTO SIST. Tall 1.00 912.39 912.39
AGUA POTABLE
04.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 912.39 912.39
TALLER DE CLORACION Y DESINFECCION DE AGUA
04.01.03.04 Tall 1.00 1,076.81 1,076.81
PARA CONSUMO HUMANO
04.02 FLETE
04.02.01 FLETE RURAL
04.02.01.01 FLETE RURAL GLB 1.00 14,888.50 14,888.50
04.02.02 FLETE TERRESTRE
04.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,583.25 4,583.25
04.02.02.02 FLETE TERRESTRE GLB 1.00 7,151.60 7,151.60
04.03 MITIGACION AMBIENTAL
04.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,754.80 2,754.80
PROGRAMA DE CONSERVACION, RESTAURACION Y
04.03.02 COMPESACION DE COBERTURA VEGETAL GLB 1.00 1,660.64 1,660.64
(REFORESTACION)
04.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,298.00 3,298.00
04.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 970.00 970.00
PROGRAMA DE CAPACITACION Y EDUCACION
04.03.05 GLB 1.00 485.00 485.00
AMBIENTAL
04.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,492.00 3,492.00
04.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 582.00 582.00
04.04 CONTROL Y SEGURIDAD EN OBRA
04.04.01 IMPLEMENTOS DE SEGURIDAD PUEBLO LIBRE GLB 1.00 4,428.01 4,428.01

COSTO DIRECTO 4,968,036.87


GASTOS GENERALES 396,449.34
UTILIDAD (7%) 347,762.58
==================
SUB TOTAL 5,712,248.79
IGV (18%) 1,028,204.78
==================
PRESUPUESTO DE OBR 6,740,453.57
DESAGREGADO DE LAS PARTIDAS

ITEM DESCRIPCIÓN UNIDAD METRADO PU SUB TOTAL

01 LOCALIDAD SANTA LUCIA


01.01 CONSTRUCCIONES PROVISIONALES
OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y
01.01.01 m2 100.00 40.10 4,009.50
VESTUARIOS
ALQUILER DE PREDIOS PARA CAMPAMENTOS Y
01.01.02 mes 6.00 450.00 2,700.00
ALMACENES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20
01.01.03 und 1.00 1,385.84 1,385.84
m
01.02 CAPTACION TIPO LADERA (ROBLEMONTE)
01.02.01 TRABAJOS PRELIMINARES
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.44 21.61
01.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.66 59.62
01.02.02 MOVIMIENTO DE TIERRAS
01.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 16.23 35.87 582.24
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
01.02.02.02 m3 2.55 26.55 67.71
MANO C/PISON
01.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.16 193.19
01.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 17.10 23.12 395.37
01.02.03 CONCRETO SIMPLE
01.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 371.85 635.87
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 40.03 105.69
01.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 108.99 54.50
01.02.04 CONCRETO ARMADO
01.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 462.46 730.68
01.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 40.03 717.78
01.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 3.92 266.45
01.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3
01.02.05.01 m2 5.53 29.23 161.65
e=1.5cm
01.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 26.78 322.75
01.02.06 PINTURA
01.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 11.91 143.48
01.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
01.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 158.27 238.98
01.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 86.19 23.27
01.02.08 CARPINTERIA METALICA
01.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 161.85 161.85
01.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 253.38 253.38
01.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.02.09.01 CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO und 1.00 451.16 451.16
HIDRAULICO y VENTILACION Ø=2")
01.02.10 CERCO PERIMETRICO EN CAPTACION
01.02.10.01 TRABAJOS PRELIMINARES
01.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.66 39.74
01.02.10.02 MOVIMIENTO DE TIERRAS
01.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 35.87 21.17
01.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 23.12 16.88
01.02.10.03 CONCRETO SIMPLE
01.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 320.38 189.03
01.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
01.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 40.03 62.45
01.02.10.05 COLOCADO DE ROLLIZOS
01.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 38.55 501.11
01.02.10.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
01.02.10.06.01 m 33.80 3.42 115.60
C/ESMALTE SINTETICO
01.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
01.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 20.00 479.95
01.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
01.02.10.08.01 und 1.00 174.69 174.69
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
01.03 LINEA DE CONDUCCION (L=1102.00 m)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,102.00 0.44 485.98
01.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 1,102.00 1.38 1,517.45
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
01.03.01.03 m 1,102.00 1.38 1,517.45
ZANJAS REDES Y LINEAS
01.03.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
01.03.02.01 m3 396.72 44.84 17,788.13
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
01.03.02.02 m3 44.08 50.22 2,213.69
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL
01.03.02.03 m 1,102.00 1.63 1,795.16
P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y
01.03.02.04 m 110.20 5.47 603.02
FIJA P/TUBERIA
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
01.03.02.05 m3 165.30 32.76 5,415.23
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
01.03.02.06 m3 27.55 58.65 1,615.89
DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.50 m
01.03.02.07 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 27.55 23.12 636.98
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.03.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SP C-10,
01.03.03.01 m 1,102.00 6.47 7,131.04
Ø=1"
01.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 126.30 126.30
01.03.04 PRUEBA HIDRAULICA
01.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 1,102.00 1.36 1,497.62
01.03.05 CAMARA ROMPE PRESION T-6 (01 UND)
01.03.05.01 OBRAS PRELIMINARES
01.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.44 0.44 0.64
01.03.05.01.02 TRAZO Y REPLANTEO m2 1.44 1.66 2.39
01.03.05.02 MOVIMIENTO DE TIERRAS
01.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.58 35.87 56.68
01.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.98 23.12 45.78
01.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 1.44 7.16 10.31
01.03.05.03 OBRAS DE CONCRETO SIMPLE
01.03.05.03.01 SOLADO E=4" m3 1.21 32.23 39.00
01.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.01 371.85 3.72
01.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 40.03 8.01

01.03.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 108.99 54.50

01.03.05.04 OBRAS DE CONCRETO ARMADO


01.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 0.79 492.02 388.70
01.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.10 40.03 324.26
01.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 37.23 3.92 145.76
01.03.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.03.05.05.01 m2 2.52 29.23 73.67
MEZCLA 1:2 E=2 cm H=1.5 Max
01.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.24 26.78 86.78
01.03.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
01.03.05.06.01 m2 3.24 10.06 32.60
MANOS
01.03.05.07 CARPINTERIA METALICA
01.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 1.00 192.36 192.36
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.03.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP
01.03.05.08.01 und 1.00 269.64 269.64
T6, INGRESO Ø=1" y SALIDA Ø=1"
01.03.06 VALVULA DE PURGA TIPO I (1 UND)
01.03.06.01 OBRAS PRELIMINARES
01.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 0.44 0.44
01.03.06.01.02 TRAZO Y REPLANTEO m2 1.00 1.66 1.66
01.03.06.02 MOVIMIENTO DE TIERRAS
01.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.51 35.87 18.30
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
01.03.06.02.02 m3 0.51 11.80 6.02
MANO
01.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.49 7.16 3.51
01.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 0.64 23.12 14.80
01.03.06.03 OBRAS DE CONCRETO SIMPLE
01.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.02 371.85 7.43
01.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.24 40.03 9.61

01.03.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.27 108.99 29.43

01.03.06.04 OBRAS DE CONCRETO ARMADO


01.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.35 492.02 172.21
01.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.72 40.03 148.92
01.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 14.94 3.92 58.49
01.03.06.05 REVOQUES Y ENLUCIDOS
01.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 1.44 29.23 42.09
01.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.36 26.78 89.99
01.03.06.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
01.03.06.06.01 m2 2.16 10.06 21.74
MANOS
01.03.06.07 CARPINTERIA METALICA
01.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 1.00 193.35 193.35
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.03.06.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.03.06.08.01 und 1.00 137.75 137.75
VALVULA DE PURGA TIPO I, Ø=1"
01.04 RESERVORIO (V=8.00 m3, 01 UND)
01.04.01 OBRAS PRELIMINARES
01.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.44 15.88
01.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.66 59.62
01.04.02 MOVIMIENTO DE TIERRAS
01.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 51.43 35.87 1,845.00
01.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 11.41 7.16 81.64
01.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 64.29 23.12 1,486.45
01.04.03 CONCRETO SIMPLE
01.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 371.85 3.72
01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 40.03 8.01
01.04.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 108.99 54.50
01.04.04 OBRAS DE CONCRETO ARMADO
01.04.04.01 SOLADO PARA LOSA FONDO m2 11.41 36.78 419.70
01.04.04.02 CONCRETO f'c=210 kg/cm2 m3 11.27 492.02 5,545.08
01.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 51.29 40.03 2,053.24
01.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 322.94 3.92 1,264.31
01.04.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.04.05.01 m2 31.32 29.23 915.54
MEZCLA 1:2 E=2 cm H=1.5 Max
01.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 40.61 26.78 1,087.70
01.04.06 PINTURA
PINTURA ESMALTE EN MUROS EXTERIORES DE
01.04.06.01 m2 34.92 11.91 415.79
RESERVORIO
01.04.07 CARPINTERIA METALICA
01.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 192.36 384.71
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.04.08
ACCESORIOS
SUMINISTRO E INSTALACIONES DE ACCESORIOS EN
01.04.08.01 und 1.00 1,570.92 1,570.92
RESERVORIO (ING. 1 ", SAL.1")
01.04.09 CERCO PERIMETRICO EN RESERVORIO
01.04.09.01 TRABAJOS PRELIMINARES
01.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.66 59.62
01.04.09.02 MOVIMIENTO DE TIERRAS 0.00
01.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 35.87 25.11
01.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 23.12 16.88
01.04.09.03 CONCRETO SIMPLE 0.00
01.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 320.38 224.27
01.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL 0.00
01.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 40.03 62.45
01.04.09.05 COLOCADO DE ROLLIZOS
01.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 38.55 501.11
01.04.09.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
01.04.09.06.01 m 66.40 3.42 227.09
C/ESMALTE SINTETICO
01.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
01.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 20.00 463.95
01.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
01.04.09.08.01 und 1.00 174.69 174.69
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
01.04.10 CLORADOR POR GOTEO
01.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
CASETA DE MURO DE LADRILLO -CLORADOR POR
01.04.10.01.01
GOTEO
01.04.10.01.01. MURO DE LADRILLO PANDERETA (0.10x0.12x0.24)
m2 7.52 49.46 371.97
01 AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm.
MURO DE LADRILLO PANDERETA
01.04.10.01.01.
INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 m2 4.48 44.42 199.02
02
JUNTA 1.5 cm.
01.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA 0.00
01.04.10.01.02.
CORREAS DE MADERA DE 2" x 2" m 6.00 26.16 156.98
01
01.04.10.01.02. COBERTURA CON CALAMINA
m2 5.98 30.67 183.42
02
01.04.10.01.03 REVOQUES Y ENLUCIDOS
01.04.10.01.03. TARRAJEO MUROS DE INTERIORES Y EXTERIORES,
m2 14.98 27.00 404.46
01 CEMENTO : ARENA, 1:5
01.04.10.01.03.
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 12.40 49.61
02
01.04.10.01.04 CARPINTERIA METALICA
01.04.10.01.04. SUMINISTRO E INSTALACION DE PUERTA METALICA
und 1.00 330.46 330.46
01 DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO
01.04.10.01.05 PINTURAS
01.04.10.01.05. PINTURA ESMALTE EN MUROS INTERIORES Y
m2 14.98 10.06 150.73
01 EXTERIORES
01.04.10.01.05.
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 11.03 44.10
02
01.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
SUMINISTRO E INSTALACION DE TANQUE DE
01.04.10.02.01 und 1.00 391.55 391.55
POLIETILENO, CAP=250 LTRS.
01.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
SUMINISTRO Y COLOCACION DE TUBERIAS Y
01.04.10.03.01 GLB 1.00 845.30 845.30
ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO
01.05 RED DE ADUCCION Y DISTRIBUCION (L=4,375.00m)
01.05.01 TRABAJOS PRELIMINARES
01.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,187.50 0.44 964.69
01.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 4,375.00 1.38 6,024.38
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
01.05.01.03 m 4,375.00 1.38 6,024.38
ZANJAS REDES Y LINEAS
01.05.02 MOVIMIENTO DE TIERRAS
01.05.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 525.00 35.87 18,833.85
EXCAVACION MANUAL DE ZANJA EN MATERIAL
01.05.02.02 m3 1,137.50 44.84 51,003.23
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
01.05.02.03 m3 87.50 50.22 4,394.25
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL
01.05.02.04 m 4,375.00 1.63 7,126.88
P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y
01.05.02.05 m 4,375.00 5.47 23,940.00
FIJA P/TUBERIA
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
01.05.02.06 m3 623.44 32.76 20,423.90
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
01.05.02.07 m3 32.81 58.65 1,924.41
DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
01.05.02.08 m3 1,181.25 22.56 26,652.55
PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
01.05.02.09 m3 142.19 55.94 7,954.68
DE PRESTAMO P/TUBERIA, H=0.50 m
01.05.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 87.50 23.12 2,023.09
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10
01.05.03.01 m 1,820.00 7.25 13,185.90
DE 1"
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10
01.05.03.02 m 2,555.00 4.36 11,129.58
DE 3/4"
01.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 123.97 123.97
01.05.04 PRUEBA HIDRAULICA
01.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 4,375.00 1.36 5,945.63
01.05.05 CAMARA ROMPE PRESION T-7 (11 UND)
01.05.05.01 OBRAS PRELIMINARES
01.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 22.77 0.44 10.04
01.05.05.01.02 TRAZO Y REPLANTEO m2 22.77 1.66 37.71
01.05.05.02 MOVIMIENTO DE TIERRAS
01.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 14.32 35.87 513.72
01.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 9.55 36.86 351.96
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
01.05.05.02.03 m3 2.39 11.80 28.20
MANO
01.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 21.62 7.16 154.69
01.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.28 53.50 68.47
01.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 9.84 23.12 227.51
01.05.05.03 OBRAS DE CONCRETO SIMPLE
01.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.13 371.85 48.34
01.05.05.03.02 SOLADO E=4" m3 1.82 32.23 58.65
01.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.20 40.03 88.07

01.05.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 2.97 108.99 323.70

01.05.05.04 OBRAS DE CONCRETO ARMADO


01.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 14.96 492.02 7,360.63
01.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 153.14 40.03 6,130.50
01.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,164.62 3.92 8,474.49
01.05.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.05.05.05.01 m2 47.52 29.23 1,389.11
MEZCLA 1:2 E=2 cm H=1.5 Max
01.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 102.98 26.78 2,758.21
01.05.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
01.05.05.06.01 m2 66.00 10.06 664.09
MANOS
01.05.05.07 CARPINTERIA METALICA
01.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 11.00 161.85 1,780.32
01.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 11.00 192.36 2,115.93
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP
01.05.05.08.01 und 7.00 345.67 2,419.70
T7, INGRESO Y SALIDA Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP
01.05.05.08.02 und 5.00 341.26 1,706.31
T7, INGRESO Y SALIDA Ø=3/4"
01.05.06 VALVULA DE CONTROL (05 UND)
01.05.06.01 OBRAS PRELIMINARES
01.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.44 2.21
01.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.66 8.28
01.05.06.02 MOVIMIENTO DE TIERRAS
01.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 35.87 179.37
01.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 23.12 144.50
01.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.16 35.78
01.05.06.03 OBRAS DE CONCRETO ARMADO
01.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 492.02 1,215.29
01.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 40.03 852.68
01.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 3.92 602.05
01.05.06.04 REVOQUES Y ENLUCIDOS
01.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 29.23 210.47
01.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 26.78 289.27
01.05.06.05 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
01.05.06.05.01 m2 6.48 10.06 65.21
MANOS
01.05.06.06 CARPINTERIA METALICA
01.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 146.59 732.96
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.06.07
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.05.06.07.01 und 1.00 81.25 81.25
VALVULA DE CONTROL, Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.05.06.07.02 und 4.00 71.12 284.47
VALVULA DE CONTROL, Ø=3/4"
01.05.07 VALVULA DE PURGA TIPO II (08 UND)
01.05.07.01 OBRAS PRELIMINARES
01.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.00 0.44 3.53
01.05.07.01.02 TRAZO Y REPLANTEO m2 8.00 1.66 13.25
01.05.07.02 MOVIMIENTO DE TIERRAS
01.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 12.23 35.87 438.74
01.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 4.08 44.84 182.94
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
01.05.07.02.03 m3 4.08 11.80 48.14
MANO
01.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 3.92 7.16 28.04
01.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.92 23.12 90.63
01.05.07.03 OBRAS DE CONCRETO SIMPLE
01.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 2.45 371.85 911.04
01.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.92 40.03 76.86

01.05.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 1.02 108.99 111.17

01.05.07.04 OBRAS DE CONCRETO ARMADO


01.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 2.80 492.02 1,377.66
01.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 29.76 40.03 1,191.35
01.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 119.53 3.92 467.96
01.05.07.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.05.07.05.01 m2 11.52 29.23 336.75
MEZCLA 1:2 E=2 cm H=1.5 Max
01.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 26.88 26.78 719.96
01.05.07.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
01.05.07.06.01 m2 12.96 10.06 130.40
MANOS
01.05.07.07 CARPINTERIA METALICA
MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE
01.05.07.07.01 und 8.00 192.36 1,538.86
0.60x0.40m.
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.07.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.05.07.08.01 und 1.00 134.33 134.33
VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.05.07.08.02 und 7.00 119.65 837.52
VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4"
01.05.08 CONEXIONES DOMICILIARIAS (92 UND)
01.05.08.01 OBRAS PRELIMINARES
01.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 824.32 0.44 363.53
01.05.08.01.02 TRAZO Y REPLANTEO m2 1,236.48 1.66 2,047.61
01.05.08.02 MOVIMIENTO DE TIERRAS
EXCAVACION A MANO DE ZANJA MANUAL TERRENO
01.05.08.02.01 m3 989.18 35.87 35,485.84
NORMAL
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
01.05.08.02.02 m3 989.18 29.70 29,378.65
PROPIO CLASIFICADO
SUMINISTRO Y COLOCACION DE GRAVA
01.05.08.02.03 m3 103.04 188.20 19,392.02
SELECCIONADA
01.05.08.03 OBRAS DE CONCRETO SIMPLE
01.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 6.82 371.85 2,536.04
01.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 34.04 40.03 1,362.69
SUMINISTRO E INSTALACION DE TUBERIAS Y
01.05.08.04
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.05.08.04.01 und 92.00 72.69 6,687.76
CONEXIONES DOMICILIARIAS DE AGUA (53 UND)
TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON
01.05.08.04.02 und 92.00 139.69 12,851.39
LLAVE TIPO BUJIA
SUMINISTRO E INSTALACIONES DE ACOMETIDA
01.05.08.04.03 m 736.00 3.15 2,318.40
DOMICILIARIA RANGO 2 - 50 M.
02 LOCALIDAD PUEBLO LIBRE
02.01 CONSTRUCCIONES PROVISIONALES
OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y
02.01.01 m2 100.00 40.10 4,009.50
VESTUARIOS
ALQUILER DE PREDIOS PARA CAMPAMENTOS Y
02.01.02 mes 6.00 450.00 2,700.00
ALMACENES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20
02.01.03 und 1.00 1,385.84 1,385.84
m
02.02 CAPTACION TIPO LADERA (YACUPACCARI)
02.02.01 TRABAJOS PRELIMINARES
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.44 21.61
02.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.66 59.62
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 22.53 35.87 808.25
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
02.02.02.02 m3 2.55 26.55 67.71
MANO C/PISON
02.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.16 193.19
02.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 25.05 23.12 579.18
02.02.03 CONCRETO SIMPLE
02.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 371.85 635.87
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 40.03 105.69
02.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 108.99 54.50
02.02.04 CONCRETO ARMADO
02.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 462.46 730.68
02.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 40.03 717.78
02.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 3.92 266.45
02.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3
02.02.05.01 m2 5.53 29.23 161.65
e=1.5cm
02.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 26.78 322.75
02.02.06 PINTURA
02.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 11.91 143.48
02.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
02.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 158.27 238.98
02.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 86.19 23.27
02.02.08 CARPINTERIA METALICA
02.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 162.84 162.84
02.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 253.38 253.38
02.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.02.09.01 CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO und 1.00 451.16 451.16
HIDRAULICO y VENTILACION Ø=2"
02.02.10 CERCO PERIMETRICO EN CAPTACION
02.02.10.01 TRABAJOS PRELIMINARES
02.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.66 39.74
02.02.10.02 MOVIMIENTO DE TIERRAS
02.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 35.87 21.17
02.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 23.12 16.88
02.02.10.03 CONCRETO SIMPLE
02.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 320.38 189.03
02.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
02.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 40.03 62.45
02.02.10.05 COLOCADO DE ROLLIZOS
02.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 38.55 501.11
02.02.10.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
02.02.10.06.01 m 33.80 3.42 115.60
C/ESMALTE SINTETICO
02.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
02.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 20.00 479.95
02.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
02.02.10.08.01 und 1.00 174.69 174.69
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
02.03 CRUCE AEREO DE L=6.00 ML. (01 UNIDAD)
02.03.01 OBRAS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 22.40 0.44 9.88
02.03.01.02 TRAZO Y REPLANTEO m2 22.40 1.66 37.10
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION A MANO TERRENO NORMAL m3 2.57 35.87 92.20
02.03.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.21 23.12 74.21
02.03.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 3.28 7.16 23.47
02.03.03 OBRAS DE CONCRETO SIMPLE
02.03.03.01 CONCRETO F'C=100 KG/CM2.PARA SOLADOS m3 0.13 363.40 47.24
02.03.04 OBRAS DE CONCRETO ARMADO
02.03.04.01 CONCRETO FC=210 KG/CM2 m3 2.72 419.46 1,140.94
02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.50 40.03 100.08
02.03.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 40.12 3.92 157.07
02.03.05 REVOQUES Y ENLUCIDOS
02.03.05.01 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 2.50 26.78 66.96
02.03.06 PINTURA
02.03.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 2.50 17.56 43.90
02.03.07 TUBERIA TN ISO 65 SERIE LIVIANA (L)
02.03.07.01 SUMINISTRO E INSTALACION DE TUBERIA TN ISO 65 Ø 1" m 11.70 280.92 3,286.73
02.03.08 CABLE DE ACERO PRINCIPAL Ø 3/8" TIPO BOA
02.03.08.01 TENDIDO DE CABLE PRINCIPAL TIPO BOA Ø 3/8 m 7.86 33.60 264.07
02.03.09 PENDOLAS
02.03.09.01 PENDOLAS CON F° LISO Ø 1/4" m 14.40 31.83 458.40
02.03.10 ACCESORIOS
ACCESORIOS PARA ACUEDUCTO COLGANTE, ARGOLLA
02.03.10.01 und 1.00 841.45 841.45
Ø 1", L=6.00ml
02.04 LINEA DE CONDUCCION (L=2153.00 m)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,153.00 0.44 949.47
02.04.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 2,153.00 1.38 2,964.68
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
02.04.01.03 m 2,153.00 1.38 2,964.68
ZANJAS REDES Y LINEAS
02.04.02 MOVIMIENTO DE TIERRAS
02.04.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 86.12 35.87 3,089.47
EXCAVACION MANUAL DE ZANJA EN MATERIAL
02.04.02.02 m3 775.08 44.84 34,753.04
CONGLOMERADO
REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL
02.04.02.03 m 2,153.00 1.63 3,507.24
P/TUBERIA
02.04.02.04 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 2,153.00 3.85 8,293.36
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
02.04.02.05 m3 322.95 32.76 10,579.84
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
02.04.02.06 m3 538.25 22.56 12,144.54
PROPIO P/TUBERIA, H=0.50 m
02.04.02.07 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 26.91 23.12 622.19
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.04.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10
02.04.03.01 m 2,153.00 5.35 11,509.94
DE 1"
02.04.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 193.98 193.98
02.04.04 PRUEBA HIDRAULICA
02.04.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 2,153.00 1.36 2,925.93
02.04.05 CAMARA ROMPE PRESION T-6 (06 UND)
02.04.05.01 OBRAS PRELIMINARES
02.04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 8.64 0.44 3.81
02.04.05.01.02 TRAZO Y REPLANTEO m2 8.64 1.66 14.31
02.04.05.02 MOVIMIENTO DE TIERRAS
02.04.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 9.50 35.87 340.80
02.04.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.88 23.12 274.68
02.04.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 8.64 7.16 61.82
02.04.05.03 OBRAS DE CONCRETO SIMPLE
02.04.05.03.01 SOLADO E=4" m3 7.26 32.23 233.98
02.04.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.07 371.85 26.03
02.04.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 40.03 48.04

02.04.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 3.00 108.99 326.97

02.04.05.04 OBRAS DE CONCRETO ARMADO


02.04.05.04.01 CONCRETO f'c=210 kg/cm2 m3 4.74 492.02 2,332.18
02.04.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 48.60 40.03 1,945.56
02.04.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 223.37 3.92 874.49
02.04.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.04.05.05.01 m2 15.12 29.23 441.99
MEZCLA 1:2 E=2 cm H=1.5 Max
02.04.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 19.44 26.78 520.68
02.04.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
02.04.05.06.01 m2 19.44 10.06 195.61
MANOS
02.04.05.07 CARPINTERIA METALICA
02.04.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 6.00 192.36 1,154.14
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.04.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP
02.04.05.08.01 und 6.00 269.64 1,617.84
T6, INGRESO Ø=1 1/2" y SALIDA Ø=1 1/2"
02.04.06 VALVULA DE PURGA TIPO I (2 UND)
02.04.06.01 OBRAS PRELIMINARES
02.04.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.00 0.44 0.88
02.04.06.01.02 TRAZO Y REPLANTEO m2 2.00 1.66 3.31
02.04.06.02 MOVIMIENTO DE TIERRAS
02.04.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.02 35.87 36.59
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
02.04.06.02.02 m3 1.02 11.80 12.03
MANO
02.04.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.98 7.16 7.01
02.04.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1.27 23.12 29.37
02.04.06.03 OBRAS DE CONCRETO SIMPLE
02.04.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.04 371.85 14.88
02.04.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.48 40.03 19.22

02.04.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.54 108.99 58.85

02.04.06.04 OBRAS DE CONCRETO ARMADO


02.04.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.70 492.02 344.41
02.04.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.44 40.03 297.84
02.04.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 29.88 3.92 116.98
02.04.06.05 REVOQUES Y ENLUCIDOS
02.04.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 2.88 29.23 84.19
02.04.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.72 26.78 179.99
02.04.06.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
02.04.06.06.01 m2 4.32 10.06 43.47
MANOS
02.04.06.07 CARPINTERIA METALICA
02.04.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 2.00 193.35 386.69
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.04.06.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.04.06.08.01 und 2.00 137.75 275.51
VALVULA DE PURGA TIPO I, Ø=1 1/2"
02.05 RESERVORIO (V=10.00 m3, 01 UND)
02.05.01 OBRAS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.44 15.88
02.05.01.02 TRAZO Y REPLANTEO m2 36.00 1.66 59.62
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 79.30 35.87 2,844.81
02.05.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 11.41 7.16 81.64
02.05.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 99.13 23.12 2,291.99
02.05.03 CONCRETO SIMPLE
02.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 371.85 3.72
02.05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 40.03 8.01
02.05.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 108.99 54.50
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 SOLADO PARA LOSA FONDO m2 11.41 36.78 419.70
02.05.04.02 CONCRETO f'c=210 kg/cm2 m3 13.50 492.02 6,642.29
02.05.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 57.48 40.03 2,301.04
02.05.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 349.49 3.92 1,368.25
02.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.05.05.01 m2 32.94 29.23 962.90
MEZCLA 1:2 E=2 cm H=1.5 Max
02.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 57.14 26.78 1,530.44
02.05.06 PINTURA
PINTURA ESMALTE EN MUROS EXTERIORES DE
02.05.06.01 m2 51.45 11.91 612.61
RESERVORIO
02.05.07 CARPINTERIA METALICA
02.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 192.36 384.71
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.05.08
ACCESORIOS
SUMINISTRO E INSTALACIONES DE ACCESORIOS EN
02.05.08.01 und 1.00 1,570.92 1,570.92
RESERVORIO (ING. 1", SAL.1")
02.05.09 CERCO PERIMETRICO EN RESERVORIO
02.05.09.01 TRABAJOS PRELIMINARES
02.05.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.66 59.62
02.05.09.02 MOVIMIENTO DE TIERRAS
02.05.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 35.87 25.11
02.05.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 23.12 16.88
02.05.09.03 CONCRETO SIMPLE
02.05.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 320.38 224.27
02.05.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
02.05.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 40.03 62.45
02.05.09.05 COLOCADO DE ROLLIZOS
02.05.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 38.55 501.11
02.05.09.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
02.05.09.06.01 m 66.40 3.42 227.09
C/ESMALTE SINTETICO
02.05.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
02.05.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 20.00 463.95
02.05.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
02.05.09.08.01 und 1.00 174.69 174.69
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
02.05.10 CLORADOR POR GOTEO
02.05.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
CASETA DE MURO DE LADRILLO -CLORADOR POR
02.05.10.01.01
GOTEO
02.05.10.01.01. MURO DE LADRILLO PANDERETA (0.10x0.12x0.24)
m2 7.52 49.46 371.97
01 AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm.
MURO DE LADRILLO PANDERETA
02.05.10.01.01.
INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 m2 4.48 44.42 199.02
02
JUNTA 1.5 cm.
02.05.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
02.05.10.01.02.
CORREAS DE MADERA DE 2" x 2" m 6.00 26.16 156.98
01
02.05.10.01.02. COBERTURA CON CALAMINA
m2 5.98 30.67 183.42
02
02.05.10.01.03 REVOQUES Y ENLUCIDOS
02.05.10.01.03. TARRAJEO MUROS DE INTERIORES Y EXTERIORES,
m2 14.98 27.00 404.46
01 CEMENTO : ARENA, 1:5
02.05.10.01.03.
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 12.40 49.61
02
02.05.10.01.04 CARPINTERIA METALICA
02.05.10.01.04. SUMINISTRO E INSTALACION DE PUERTA METALICA
und 1.00 330.46 330.46
01 DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO
02.05.10.01.05 PINTURAS
02.05.10.01.05. PINTURA ESMALTE EN MUROS INTERIORES Y
m2 14.98 10.06 150.73
01 EXTERIORES
02.05.10.01.05.
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 11.03 44.10
02
02.05.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
SUMINISTRO E INSTALACION DE TANQUE DE
02.05.10.02.01 und 1.00 391.55 391.55
POLIETILENO, CAP=250 LTRS.
02.05.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
SUMINISTRO Y COLOCACION DE TUBERIAS Y
02.05.10.03.01 GLB 1.00 845.30 845.30
ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO
02.06 RED DE ADUCCION Y DISTRIBUCION (L=5,678.00 m)
02.06.01 TRABAJOS PRELIMINARES
02.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,839.00 0.44 1,252.00
02.06.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 5,678.00 1.38 7,818.61
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
02.06.01.03 m 5,678.00 1.38 7,818.61
ZANJAS REDES Y LINEAS
02.06.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
02.06.02.01 m3 1,362.72 44.84 61,101.64
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
02.06.02.02 m3 908.48 50.22 45,623.86
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL
02.06.02.03 m 5,678.00 1.63 9,249.46
P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y
02.06.02.04 m 2,271.20 5.47 12,428.01
FIJA P/TUBERIA
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
02.06.02.05 m3 511.02 32.76 16,741.02
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
02.06.02.06 m3 567.80 58.65 33,303.18
DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
02.06.02.07 m3 1,987.30 22.56 44,839.45
PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
02.06.02.08 m3 1,135.60 55.94 63,530.01
DE PRESTAMO P/TUBERIA, H=0.50 m
02.06.02.09 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 567.80 23.12 13,128.10
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10
02.06.03.01 m 1,146.00 7.25 8,302.77
DE 1"
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10
02.06.03.02 m 4,533.00 4.36 19,745.75
DE 3/4"
02.06.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 316.29 316.29
02.06.04 PRUEBA HIDRAULICA
02.06.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 5,678.00 1.36 7,716.40
02.06.05 CAMARA ROMPE PRESION T-7 (16 UND)
02.06.05.01 OBRAS PRELIMINARES
02.06.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 33.12 0.44 14.61
02.06.05.01.02 TRAZO Y REPLANTEO m2 33.12 1.66 54.85
02.06.05.02 MOVIMIENTO DE TIERRAS
02.06.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 22.91 35.87 821.87
02.06.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 15.27 36.86 562.78
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
02.06.05.02.03 m3 3.82 11.80 45.07
MANO
02.06.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 31.44 7.16 224.96
02.06.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.86 53.50 99.50
02.06.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 22.91 23.12 529.70
02.06.05.03 OBRAS DE CONCRETO SIMPLE
02.06.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.19 371.85 70.65
02.06.05.03.02 SOLADO E=4" m3 2.64 32.23 85.09
02.06.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.20 40.03 128.11

02.06.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 4.32 108.99 470.84

02.06.05.04 OBRAS DE CONCRETO ARMADO


02.06.05.04.01 CONCRETO f'c=210 kg/cm2 m3 21.74 492.02 10,696.54
02.06.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 222.76 40.03 8,917.52
02.06.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 3,148.54 3.92 12,326.54
02.06.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.06.05.05.01 m2 69.12 29.23 2,020.52
MEZCLA 1:2 E=2 cm H=1.5 Max
02.06.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 149.79 26.78 4,011.98
02.06.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
02.06.05.06.01 m2 96.00 10.06 965.95
MANOS
02.06.05.07 CARPINTERIA METALICA
02.06.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 16.00 161.85 2,589.55
02.06.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 16.00 192.36 3,077.71
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP
02.06.05.08.01 und 3.00 345.67 1,037.02
T7, INGRESO Y SALIDA Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP
02.06.05.08.02 und 13.00 341.26 4,436.41
T7, INGRESO Y SALIDA Ø=3/4"
02.06.06 VALVULA DE CONTROL (05 UND)
02.06.06.01 OBRAS PRELIMINARES
02.06.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.00 0.44 2.65
02.06.06.01.02 TRAZO Y REPLANTEO m2 6.00 1.66 9.94
02.06.06.02 MOVIMIENTO DE TIERRAS
02.06.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 6.00 35.87 215.24
02.06.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 7.50 23.12 173.41
02.06.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 6.00 7.16 42.93
02.06.06.03 OBRAS DE CONCRETO ARMADO
02.06.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.96 492.02 1,456.38
02.06.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 25.56 40.03 1,023.22
02.06.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 184.53 3.92 722.44
02.06.06.04 REVOQUES Y ENLUCIDOS
02.06.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 8.64 29.23 252.57
02.06.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 12.96 26.78 347.12
02.06.06.05 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
02.06.06.05.01 m2 12.96 10.06 130.40
MANOS
02.06.06.06 CARPINTERIA METALICA
02.06.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 6.00 146.59 879.55
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.06.07
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.06.06.07.01 und 2.00 81.25 162.50
VALVULA DE CONTROL, Ø=1"
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.06.06.07.02 und 4.00 71.12 284.47
VALVULA DE CONTROL, Ø=3/4"
02.06.07 VALVULA DE PURGA TIPO II (03 UND)
02.06.07.01 OBRAS PRELIMINARES
02.06.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 3.00 0.44 1.32
02.06.07.01.02 TRAZO Y REPLANTEO m2 3.00 1.66 4.97
02.06.07.02 MOVIMIENTO DE TIERRAS
02.06.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 4.59 35.87 164.66
02.06.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 1.53 44.84 68.60
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
02.06.07.02.03 m3 1.53 11.80 18.05
MANO
02.06.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 1.47 7.16 10.52
02.06.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.47 23.12 33.98
02.06.07.03 OBRAS DE CONCRETO SIMPLE
02.06.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.92 371.85 342.11
02.06.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.72 40.03 28.83

02.06.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.38 108.99 41.42

02.06.07.04 OBRAS DE CONCRETO ARMADO


02.06.07.04.01 CONCRETO f'c=210 kg/cm2 m3 1.05 492.02 516.62
02.06.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 11.16 40.03 446.76
02.06.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 44.82 3.92 175.47
02.06.07.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.06.07.05.01 m2 4.32 29.23 126.28
MEZCLA 1:2 E=2 cm H=1.5 Max
02.06.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.08 26.78 269.98
02.06.07.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
02.06.07.06.01 m2 4.84 10.06 48.70
MANOS
02.06.07.07 CARPINTERIA METALICA 0.00
MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE
02.06.07.07.01 und 3.00 192.36 577.07
0.60x0.40m.
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.07.08 0.00
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.06.07.08.01 und 3.00 119.65 358.94
VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4"
02.06.08 CONEXIONES DOMICILIARIAS (125 UND)
02.06.08.01 OBRAS PRELIMINARES
02.06.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,120.00 0.44 493.92
02.06.08.01.02 TRAZO Y REPLANTEO m2 1,680.00 1.66 2,782.08
02.06.08.02 MOVIMIENTO DE TIERRAS
EXCAVACION A MANO DE ZANJA MANUAL TERRENO
02.06.08.02.01 m3 1,344.00 35.87 48,214.66
NORMAL
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
02.06.08.02.02 m3 1,344.00 29.70 39,916.80
PROPIO CLASIFICADO
SUMINISTRO Y COLOCACION DE GRAVA
02.06.08.02.03 m3 140.00 188.20 26,347.86
SELECCIONADA
02.06.08.03 OBRAS DE CONCRETO SIMPLE
02.06.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 9.27 371.85 3,447.08
02.06.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 46.25 40.03 1,851.48
SUMINISTRO E INSTALACION DE TUBERIAS Y
02.06.08.04
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.06.08.04.01 und 125.00 72.69 9,086.63
CONEXIONES DOMICILIARIAS DE AGUA (53 UND)
TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON
02.06.08.04.02 und 125.00 139.69 17,461.13
LLAVE TIPO BUJIA
SUMINISTRO E INSTALACIONES DE ACOMETIDA
02.06.08.04.03 m 1,125.00 3.15 3,543.75
DOMICILIARIA RANGO 2 - 20 M.
03 LOCALIDAD TANCARPATA
03.01 CONSTRUCCIONES PROVISIONALES
OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y
03.01.01 m2 100.00 40.10 4,009.50
VESTUARIOS
ALQUILER DE PREDIOS PARA CAMPAMENTOS Y
03.01.02 mes 6.00 450.00 2,700.00
ALMACENES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20
03.01.03 und 1.00 1,385.84 1,385.84
m
03.02 CAPTACION A TIPO LADERA YACUTOCCYAC (01 UND)
03.02.01 TRABAJOS PRELIMINARES
03.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.44 21.61
03.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.66 59.62
03.02.02 MOVIMIENTO DE TIERRAS
03.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 15.03 35.87 539.19
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
03.02.02.02 m3 2.55 26.55 67.71
MANO C/PISON
03.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.16 193.19
03.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.60 23.12 360.68
03.02.03 CONCRETO SIMPLE
03.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 371.85 635.87
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 40.03 105.69
03.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 108.99 54.50
03.02.04 CONCRETO ARMADO
03.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 462.46 730.68
03.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 40.03 717.78
03.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 3.92 266.45
03.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3
03.02.05.01 m2 5.53 29.23 161.65
e=1.5cm
03.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 26.78 322.75
03.02.06 PINTURA
03.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 11.91 143.48
03.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
03.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 158.27 238.98
03.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 86.19 23.27
03.02.08 CARPINTERIA METALICA
03.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 162.84 162.84
03.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 253.38 253.38
03.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.02.09.01 CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO und 1.00 447.92 447.92
HIDRAULICO y VENTILACION Ø=2")
03.02.10 CERCO PERIMETRICO EN CAPTACION
03.02.10.01 TRABAJOS PRELIMINARES
03.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.66 39.74
03.02.10.02 MOVIMIENTO DE TIERRAS
03.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 35.87 21.17
03.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 23.12 16.88
03.02.10.03 CONCRETO SIMPLE
03.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 320.38 189.03
03.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
03.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 40.03 62.45
03.02.10.05 COLOCADO DE ROLLIZOS
03.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 38.55 501.11
03.02.10.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
03.02.10.06.01 m 33.80 3.42 115.60
C/ESMALTE SINTETICO
03.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
03.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 20.00 479.95
03.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
03.02.10.08.01 und 1.00 174.69 174.69
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
03.03 LINEA DE CONDUCCION (L=196.00 m)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 196.00 0.44 86.44
03.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 196.00 1.38 269.89
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
03.03.01.03 m 196.00 1.38 269.89
ZANJAS REDES Y LINEAS
03.03.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
03.03.02.01 m3 72.13 44.84 3,234.17
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
03.03.02.02 m3 6.27 50.22 314.88
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL
03.03.02.03 m 196.00 1.63 319.28
P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y
03.03.02.04 m 196.00 5.47 1,072.51
FIJA P/TUBERIA
03.03.02.05 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 196.00 3.85 754.99
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.03.02.06 m3 27.05 32.76 886.16
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.03.02.07 m3 2.35 58.65 137.84
DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.03.02.08 m3 45.05 22.56 1,016.46
PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.03.02.09 m3 3.92 55.94 219.30
DE PRESTAMO P/TUBERIA, H=0.50 m
03.03.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 3.92 23.12 90.63
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.03.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10
03.03.03.01 m 196.00 5.35 1,047.82
DE 1"
03.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 144.82 144.82
03.03.04 PRUEBA HIDRAULICA
03.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 180.36 1.36 245.11
03.03.05 CAMARA ROMPE PRESION T-6 (01 UND)
03.03.05.01 OBRAS PRELIMINARES
03.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.44 0.44 0.64
03.03.05.01.02 TRAZO Y REPLANTEO m2 1.44 1.66 2.39
03.03.05.02 MOVIMIENTO DE TIERRAS
03.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.58 35.87 56.68
03.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.98 23.12 45.78
03.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 1.44 7.16 10.31
03.03.05.03 OBRAS DE CONCRETO SIMPLE
03.03.05.03.01 SOLADO E=4" m3 1.21 32.23 39.00
03.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.01 371.85 3.72
03.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 40.03 8.01

03.03.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 108.99 54.50

03.03.05.04 OBRAS DE CONCRETO ARMADO 0.00


03.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 0.79 492.02 388.70
03.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 8.10 40.03 324.26
03.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 37.23 3.92 145.76
03.03.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.03.05.05.01 m2 2.52 29.23 73.67
MEZCLA 1:2 E=2 cm H=1.5 Max
03.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.24 26.78 86.78
03.03.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
03.03.05.06.01 m2 3.24 10.06 32.60
MANOS
03.03.05.07 CARPINTERIA METALICA
03.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 1.00 192.36 192.36
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.03.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP
03.03.05.08.01 und 1.00 269.64 269.64
T6, INGRESO Ø=1 y SALIDA Ø=1 "
03.03.06 VALVULA DE PURGA TIPO I (1 UND)
03.03.06.01 OBRAS PRELIMINARES
03.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.00 0.44 0.44
03.03.06.01.02 TRAZO Y REPLANTEO m2 1.00 1.66 1.66
03.03.06.02 MOVIMIENTO DE TIERRAS
03.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.51 35.87 18.30
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
03.03.06.02.02 m3 0.51 11.80 6.02
MANO
03.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.49 7.16 3.51
03.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 0.64 23.12 14.80
03.03.06.03 OBRAS DE CONCRETO SIMPLE
03.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.20 371.85 74.37
03.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.24 40.03 9.61

03.03.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.27 108.99 29.43

03.03.06.04 OBRAS DE CONCRETO ARMADO


03.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.35 492.02 172.21
03.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 3.72 40.03 148.92
03.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 14.94 3.92 58.49
03.03.06.05 REVOQUES Y ENLUCIDOS
03.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 1.44 29.23 42.09
03.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 3.36 26.78 89.99
03.03.06.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
03.03.06.06.01 m2 2.16 10.06 21.74
MANOS
03.03.06.07 CARPINTERIA METALICA
03.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 1.00 193.35 193.35
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.03.06.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.03.06.08.01 und 1.00 137.75 137.75
VALVULA DE PURGA TIPO I, Ø=1"
03.04 RESERVORIO (V=5.00 m3, 01 UND)
03.04.01 OBRAS PRELIMINARES
03.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.44 15.88
03.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.66 59.62
03.04.02 MOVIMIENTO DE TIERRAS
03.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 60.95 35.87 2,186.52
03.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 8.05 7.16 57.60
03.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 76.19 23.12 1,761.59
03.04.03 CONCRETO SIMPLE
03.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 371.85 3.72
03.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 40.03 8.01
03.04.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 108.99 54.50
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 SOLADO PARA LOSA FONDO m2 8.05 36.78 296.10
03.04.04.02 CONCRETO f'c=210 kg/cm2 m3 9.51 492.02 4,679.12
03.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 49.52 40.03 1,982.39
03.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 254.64 3.92 996.91
03.04.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.04.05.01 m2 31.00 29.23 906.19
MEZCLA 1:2 E=2 cm H=1.5 Max
03.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 35.50 26.78 950.83
03.04.06 PINTURA
PINTURA ESMALTE EN MUROS EXTERIORES DE
03.04.06.01 m2 29.15 11.91 347.09
RESERVORIO
03.04.07 CARPINTERIA METALICA
03.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 192.36 384.71
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.04.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.04.08.01 RESERVORIO (INGRESO Ø 1"-LIMPIA, REBOSE y SELLO HIDR. und 1.00 1,456.34 1,456.34
Ø 2"-VENTILAC. Ø 3")
03.04.09 CERCO PERIMETRICO EN RESERVORIO
03.04.09.01 TRABAJOS PRELIMINARES
03.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.66 59.62
03.04.09.02 MOVIMIENTO DE TIERRAS
03.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 35.87 25.11
03.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 23.12 16.88
03.04.09.03 CONCRETO SIMPLE
03.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 320.38 224.27
03.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
03.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 40.03 62.45
03.04.09.05 COLOCADO DE ROLLIZOS
03.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 38.55 501.11
03.04.09.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
03.04.09.06.01 m 66.40 3.42 227.09
C/ESMALTE SINTETICO
03.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
03.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 20.00 463.95
03.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
03.04.09.08.01 und 1.00 174.69 174.69
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
03.04.10 CLORADOR POR GOTEO
03.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
CASETA DE MURO DE LADRILLO -CLORADOR POR
03.04.10.01.01
GOTEO
03.04.10.01.01. MURO DE LADRILLO PANDERETA (0.10x0.12x0.24)
m2 7.52 49.46 371.97
01 AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm.
MURO DE LADRILLO PANDERETA
03.04.10.01.01.
INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 m2 4.48 44.42 199.02
02
JUNTA 1.5 cm.
03.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
03.04.10.01.02.
CORREAS DE MADERA DE 2" x 2" m 6.00 26.16 156.98
01
03.04.10.01.02. COBERTURA CON CALAMINA
m2 5.98 30.67 183.42
02
03.04.10.01.03 REVOQUES Y ENLUCIDOS
03.04.10.01.03. TARRAJEO MUROS DE INTERIORES Y EXTERIORES,
m2 14.98 27.00 404.46
01 CEMENTO : ARENA, 1:5
03.04.10.01.03.
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 12.40 49.61
02
03.04.10.01.04 CARPINTERIA METALICA
03.04.10.01.04. SUMINISTRO E INSTALACION DE PUERTA METALICA
und 1.00 330.46 330.46
01 DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO
03.04.10.01.05 PINTURAS
03.04.10.01.05. PINTURA ESMALTE EN MUROS INTERIORES Y
m2 14.98 10.06 150.73
01 EXTERIORES
03.04.10.01.05.
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 11.03 44.10
02
03.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
SUMINISTRO E INSTALACION DE TANQUE DE
03.04.10.02.01 und 1.00 391.55 391.55
POLIETILENO, CAP=250 LTRS.
03.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
SUMINISTRO Y COLOCACION DE TUBERIAS Y
03.04.10.03.01 GLB 1.00 845.30 845.30
ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO
03.05 RED DE ADUCCION Y DISTRIBUCION (L=2,740.00 m)
03.05.01 TRABAJOS PRELIMINARES
03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,370.00 0.44 604.17
03.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 2,740.00 1.38 3,772.98
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
03.05.01.03 m 2,740.00 1.38 3,772.98
ZANJAS REDES Y LINEAS
03.05.02 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL DE ZANJA EN MATERIAL
03.05.02.01 m3 1,041.20 44.84 46,685.32
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
03.05.02.02 m3 54.80 50.22 2,752.06
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL
03.05.02.03 m 2,740.00 1.63 4,463.46
P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y
03.05.02.04 m 137.00 5.47 749.66
FIJA P/TUBERIA
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.05.02.05 m3 390.45 32.76 12,791.14
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.05.02.06 m3 20.55 58.65 1,205.32
DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.05.02.07 m3 719.25 22.56 16,228.44
PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.05.02.08 m3 68.50 55.94 3,832.16
DE PRESTAMO P/TUBERIA, H=0.50 m
03.05.02.09 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 34.25 23.12 791.89
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10
03.05.03.01 m 4.00 7.25 28.98
DE 1"
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10
03.05.03.02 m 2,736.00 4.36 11,918.02
DE 3/4"
03.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 86.97 86.97
03.05.04 PRUEBA HIDRAULICA
03.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 2,740.00 1.36 3,723.66
03.05.05 CAMARA ROMPE PRESION T-7 (09 UND)
03.05.05.01 OBRAS PRELIMINARES
03.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 18.63 0.44 8.22
03.05.05.01.02 TRAZO Y REPLANTEO m2 18.63 1.66 30.85
03.05.05.02 MOVIMIENTO DE TIERRAS
03.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 14.32 35.87 513.72
03.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 7.16 36.86 263.88
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
03.05.05.02.03 m3 2.39 11.80 28.20
MANO
03.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 17.69 7.16 126.58
03.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.06 53.50 56.71
03.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 8.06 23.12 186.35
03.05.05.03 OBRAS DE CONCRETO SIMPLE
03.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.11 371.85 40.91
03.05.05.03.02 SOLADO E=4" m3 1.49 32.23 48.02
03.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.80 40.03 72.05

03.05.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 2.43 108.99 264.84

03.05.05.04 OBRAS DE CONCRETO ARMADO


03.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 12.23 492.02 6,017.42
03.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 125.30 40.03 5,016.01
03.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,771.06 3.92 6,933.70
03.05.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.05.05.05.01 m2 38.88 29.23 1,136.54
MEZCLA 1:2 E=2 cm H=1.5 Max
03.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 84.26 26.78 2,256.82
03.05.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
03.05.05.06.01 m2 54.00 10.06 543.35
MANOS
03.05.05.07 CARPINTERIA METALICA
03.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 9.00 161.85 1,456.62
03.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 9.00 192.36 1,731.21
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP
03.05.05.08.01 und 9.00 341.26 3,071.36
T7, INGRESO Y SALIDA Ø=3/4"
03.05.06 VALVULA DE CONTROL (05 UND)
03.05.06.01 OBRAS PRELIMINARES
03.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.44 2.21
03.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.66 8.28
03.05.06.02 MOVIMIENTO DE TIERRAS
03.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 35.87 179.37
03.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 23.12 144.50
03.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.16 35.78
03.05.06.03 OBRAS DE CONCRETO ARMADO
03.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 492.02 1,215.29
03.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 40.03 852.68
03.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 3.92 602.05
03.05.06.04 REVOQUES Y ENLUCIDOS
03.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 29.23 210.47
03.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 26.78 289.27
03.05.06.05 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
03.05.06.05.01 m2 10.80 10.06 108.67
MANOS
03.05.06.06 CARPINTERIA METALICA
03.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 146.59 732.96
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.06.07
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.05.06.07.01 und 5.00 71.12 355.59
VALVULA DE CONTROL, Ø=3/4"
03.05.07 VALVULA DE PURGA TIPO II (06 UND)
03.05.07.01 OBRAS PRELIMINARES
03.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 6.00 0.44 2.65
03.05.07.01.02 TRAZO Y REPLANTEO m2 6.00 1.66 9.94
03.05.07.02 MOVIMIENTO DE TIERRAS
03.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 9.17 35.87 328.97
03.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 3.06 44.84 137.21
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
03.05.07.02.03 m3 3.06 11.80 36.11
MANO
03.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 2.94 7.16 21.03
03.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 2.94 23.12 67.98
03.05.07.03 OBRAS DE CONCRETO SIMPLE
03.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 1.84 371.85 684.21
03.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.44 40.03 57.65

03.05.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.77 108.99 83.93

03.05.07.04 OBRAS DE CONCRETO ARMADO


03.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 2.10 492.02 1,033.25
03.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 23.32 40.03 933.54
03.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 86.64 3.92 339.19
03.05.07.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.05.07.05.01 m2 8.64 29.23 252.57
MEZCLA 1:2 E=2 cm H=1.5 Max
03.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 20.16 26.78 539.96
03.05.07.06 PINTURA 0.00
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
03.05.07.06.01 m2 9.72 10.06 97.80
MANOS
03.05.07.07 CARPINTERIA METALICA
MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE
03.05.07.07.01 und 6.00 192.36 1,154.14
0.60x0.40m.
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.07.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.05.07.08.01 und 6.00 119.65 717.88
VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4"
03.05.08 CONEXIONES DOMICILIARIAS (53 UND)
03.05.08.01 OBRAS PRELIMINARES
03.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 474.88 0.44 209.42
03.05.08.01.02 TRAZO Y REPLANTEO m2 712.32 1.66 1,179.60
03.05.08.02 MOVIMIENTO DE TIERRAS
EXCAVACION A MANO DE ZANJA MANUAL TERRENO
03.05.08.02.01 m3 569.86 35.87 20,443.16
NORMAL
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
03.05.08.02.02 m3 569.86 29.70 16,924.84
PROPIO CLASIFICADO
SUMINISTRO Y COLOCACION DE GRAVA
03.05.08.02.03 m3 50.36 188.20 9,477.70
SELECCIONADA
03.05.08.03 OBRAS DE CONCRETO SIMPLE
03.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 3.93 371.85 1,461.38
03.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.61 40.03 785.03
SUMINISTRO E INSTALACION DE TUBERIAS Y
03.05.08.04
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.05.08.04.01 und 53.00 72.69 3,852.73
CONEXIONES DOMICILIARIAS DE AGUA (53 UND)
TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON
03.05.08.04.02 und 53.00 139.69 7,403.52
LLAVE TIPO BUJIA
SUMINISTRO E INSTALACIONES DE ACOMETIDA
03.05.08.04.03 m 530.00 3.15 1,669.50
DOMICILIARIA RANGO 2 - 20 M.
04 LOCALIDAD TARACA
04.01 CONSTRUCCIONES PROVISIONALES
OFICINAS, ALMACENES, CASETA DE GUARDIANIA Y
04.01.01 m2 100.00 40.10 4,009.50
VESTUARIOS
ALQUILER DE PREDIOS PARA CAMPAMENTOS Y
04.01.02 mes 6.00 450.00 2,700.00
ALMACENES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 m x 7.20
04.01.03 und 1.00 1,385.84 1,385.84
m
04.02 CAPTACION A TIPO LADERA YACUTOCCYAC (01 UND)
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.00 0.44 21.61
04.02.01.02 TRAZO Y REPLANTEO m2 36.00 1.66 59.62
04.02.02 MOVIMIENTO DE TIERRAS
04.02.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 17.55 35.87 629.59
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
04.02.02.02 m3 2.55 26.55 67.71
MANO C/PISON
04.02.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 27.00 7.16 193.19
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.60 23.12 360.68
04.02.03 CONCRETO SIMPLE
04.02.03.01 CONCRETO f'c=140 kg/cm2 m3 1.71 371.85 635.87
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.64 40.03 105.69
04.02.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 108.99 54.50
04.02.04 CONCRETO ARMADO
04.02.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 462.46 730.68
04.02.04.02 ENCOFRADO Y DESENCOFRADO m2 17.93 40.03 717.78
04.02.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 68.06 3.92 266.45
04.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTES M=1:3
04.02.05.01 m2 5.53 29.23 161.65
e=1.5cm
04.02.05.02 TARRAJEO EXTERIORES EN CAPTACION M=1:5 m2 12.05 26.78 322.75
04.02.06 PINTURA 0.00
04.02.06.01 PINTURA ESMALTE 2 MANOS EN MUROS EXTERIORES m2 12.05 11.91 143.48
04.02.07 FILTRO DE GRAVA, ARENA Y MATERIAL IMPERMEABLE
04.02.07.01 SUMINISTRO DE FILTRO CON GRAVA Y ARENA m3 1.51 158.27 238.98
04.02.07.02 SUMINISTRO DE MATERIAL IMPERMEABLE m3 0.27 86.19 23.27
04.02.08 CARPINTERIA METALICA
04.02.08.01 MARCO Y TAPA METALICA DE 0.45m x 0.45m E=1/8" und 1.00 162.84 162.84
04.02.08.02 MARCO Y TAPA METALICA DE 0.85m x 0.85m E=1/8" und 1.00 253.38 253.38
04.02.09 VALVULAS Y ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.02.09.01 CAPTACION (SALIDA Ø=1"-LIMPIA, REBOSE, SELLO und 1.00 447.92 447.92
HIDRAULICO y VENTILACION Ø=2")
04.02.10 CERCO PERIMETRICO EN CAPTACION
04.02.10.01 TRABAJOS PRELIMINARES
04.02.10.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 24.00 1.66 39.74
04.02.10.02 MOVIMIENTO DE TIERRAS
04.02.10.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.59 35.87 21.17
04.02.10.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 23.12 16.88
04.02.10.03 CONCRETO SIMPLE
04.02.10.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.59 320.38 189.03
04.02.10.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
04.02.10.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 40.03 62.45
04.02.10.05 COLOCADO DE ROLLIZOS
04.02.10.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 38.55 501.11
04.02.10.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
04.02.10.06.01 m 33.80 3.42 115.60
C/ESMALTE SINTETICO
04.02.10.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
04.02.10.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 24.00 20.00 479.95
04.02.10.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
04.02.10.08.01 und 1.00 174.69 174.69
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
04.03 LINEA DE CONDUCCION (L=1231.00 m)
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,231.00 0.44 542.87
04.03.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 1,231.00 1.38 1,695.09
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
04.03.01.03 m 1,231.00 1.38 1,695.09
ZANJAS REDES Y LINEAS
04.03.02 MOVIMIENTO DE TIERRAS
04.03.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 392.92 35.87 14,095.61
EXCAVACION MANUAL DE ZANJA EN MATERIAL
04.03.02.02 m3 73.86 44.84 3,311.74
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
04.03.02.03 m3 15.39 50.22 772.88
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL
04.03.02.04 m 1,231.00 1.63 2,005.30
P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y
04.03.02.05 m 61.55 5.47 336.80
FIJA P/TUBERIA
04.03.02.06 CAMA DE APOYO C/MAT. DE PRESTAMO, e=0.10 m. m 1,231.00 3.85 4,741.81
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.03.02.07 m3 175.42 32.76 5,746.76
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.03.02.08 m3 9.23 58.65 541.37
DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.03.02.09 m3 292.36 22.56 6,596.52
PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.03.02.10 m3 6.16 55.94 344.62
DE PRESTAMO P/TUBERIA, H=0.50 m
04.03.02.11 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 15.39 23.12 355.83
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.03.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10
04.03.03.01 m 1,231.00 5.35 6,580.93
DE 1"
04.03.03.02 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 141.94 141.94
04.03.04 PRUEBA HIDRAULICA
04.03.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 1,231.00 1.36 1,672.93
04.03.05 CAMARA ROMPE PRESION T-6 (02 UND)
04.03.05.01 OBRAS PRELIMINARES
04.03.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.88 0.44 1.27
04.03.05.01.02 TRAZO Y REPLANTEO m2 2.88 1.66 4.77
04.03.05.02 MOVIMIENTO DE TIERRAS
04.03.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 3.17 35.87 113.72
04.03.05.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 7.92 23.12 183.11
04.03.05.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 2.88 7.16 20.61
04.03.05.03 OBRAS DE CONCRETO SIMPLE
04.03.05.03.01 SOLADO E=4" m3 2.42 32.23 77.99
04.03.05.03.02 CONCRETO f'c= 140 kg/cm2 m3 0.02 371.85 7.43
04.03.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.40 40.03 16.01

04.03.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 1.00 108.99 108.99

04.03.05.04 OBRAS DE CONCRETO ARMADO


04.03.05.04.01 CONCRETO f'c=210 kg/cm2 m3 1.58 492.02 777.39
04.03.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 16.20 40.03 648.52
04.03.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 74.46 3.92 291.51
04.03.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.03.05.05.01 m2 5.04 29.23 147.33
MEZCLA 1:2 E=2 cm H=1.5 Max
04.03.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.48 26.78 173.56
04.03.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
04.03.05.06.01 m2 6.48 10.06 65.21
MANOS
04.03.05.07 CARPINTERIA METALICA
04.03.05.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 192.36 384.71
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.03.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP
04.03.05.08.01 und 2.00 269.64 539.28
T6, INGRESO Ø=1 y SALIDA Ø=1 "
04.03.06 VALVULA DE PURGA TIPO I (1 UND)
04.03.06.01 OBRAS PRELIMINARES
04.03.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 2.00 0.44 0.88
04.03.06.01.02 TRAZO Y REPLANTEO m2 2.00 1.66 3.31
04.03.06.02 MOVIMIENTO DE TIERRAS
04.03.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 1.02 35.87 36.59
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
04.03.06.02.02 m3 1.02 11.80 12.03
MANO
04.03.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 0.98 7.16 7.01
04.03.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 1.27 23.12 29.37
04.03.06.03 OBRAS DE CONCRETO SIMPLE
04.03.06.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.04 371.85 14.88
04.03.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.48 40.03 19.22

04.03.06.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.54 108.99 58.85

04.03.06.04 OBRAS DE CONCRETO ARMADO


04.03.06.04.01 CONCRETO f'c=210 kg/cm2 m3 0.70 492.02 344.41
04.03.06.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 7.44 40.03 297.84
04.03.06.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 29.88 3.92 116.98
04.03.06.05 REVOQUES Y ENLUCIDOS
04.03.06.05.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 2.88 29.23 84.19
04.03.06.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 6.72 26.78 179.99
04.03.06.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
04.03.06.06.01 m2 4.32 10.06 43.47
MANOS
04.03.06.07 CARPINTERIA METALICA
04.03.06.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.40m E=1/8" und 2.00 193.35 386.69
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.03.06.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.03.06.08.01 und 2.00 137.75 275.51
VALVULA DE PURGA TIPO I, Ø=1"
04.04 RESERVORIO (V=5.00 m3, 01 UND)
04.04.01 OBRAS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 36.00 0.44 15.88
04.04.01.02 TRAZO Y REPLANTEO m2 36.00 1.66 59.62
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION A MANO TERRENO NORMAL m3 36.02 35.87 1,292.18
04.04.02.02 NIVELACION INTERIOR APISONADO MANUAL m2 8.05 7.16 57.60
04.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 45.02 23.12 1,040.90
04.04.03 CONCRETO SIMPLE
04.04.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.01 371.85 3.72
04.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 0.20 40.03 8.01
04.04.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.50 108.99 54.50
04.04.04 OBRAS DE CONCRETO ARMADO
04.04.04.01 SOLADO PARA LOSA FONDO m2 8.05 36.78 296.10
04.04.04.02 CONCRETO f'c=210 kg/cm2 m3 9.51 492.02 4,679.12
04.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 49.52 40.03 1,982.39
04.04.04.04 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 254.64 3.92 996.91
04.04.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.04.05.01 m2 31.00 29.23 906.19
MEZCLA 1:2 E=2 cm H=1.5 Max
04.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 35.50 26.78 950.83
04.04.06 PINTURA
PINTURA ESMALTE EN MUROS EXTERIORES DE
04.04.06.01 m2 29.15 11.91 347.09
RESERVORIO
04.04.07 CARPINTERIA METALICA
04.04.07.01 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 2.00 192.36 384.71
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.04.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.04.08.01 RESERVORIO (INGRESO Ø 1"-LIMPIA, REBOSE y SELLO HIDR. und 1.00 1,456.34 1,456.34
Ø 2"-VENTILAC. Ø 3")
04.04.09 CERCO PERIMETRICO EN RESERVORIO
04.04.09.01 TRABAJOS PRELIMINARES
04.04.09.01.01 TRAZO Y REPLANTEO EN CERCO PERIMETRICO m 36.00 1.66 59.62
04.04.09.02 MOVIMIENTO DE TIERRAS
04.04.09.02.01 EXCAVACION A MANO TERRENO NORMAL m3 0.70 35.87 25.11
04.04.09.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 0.73 23.12 16.88
04.04.09.03 CONCRETO SIMPLE
04.04.09.03.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 0.70 320.38 224.27
04.04.09.04 ENCOFRADO Y DESENCOFRADO EN PEDESTAL
04.04.09.04.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.56 40.03 62.45
04.04.09.05 COLOCADO DE ROLLIZOS
04.04.09.05.01 ROLLIZO TRATADO CON CBC DE Ø 4", H=2.6 M und 13.00 38.55 501.11
04.04.09.06 PINTURA EN CERCO PERIMETRICO
PINTURA EN ROLLIZOS Y PUERTA A DOS MANOS
04.04.09.06.01 m 66.40 3.42 227.09
C/ESMALTE SINTETICO
04.04.09.07 SUM. E INST. MALLA GANADERA DE 12 HILOS H=1.80m
04.04.09.07.01 MALLA GANADERA 12 HILOS H=1.80 m m 23.20 20.00 463.95
04.04.09.08 SUM. E INST. PUERTA EN CERCO PERIMETRICO
SUM. E INST. PUERTA DE MADERA C/MALLA
04.04.09.08.01 und 1.00 174.69 174.69
GALVANIZADA CUADRADA 3/4" Y LISTONES DE 2"x3"
04.04.10 CLORADOR POR GOTEO
04.04.10.01 CASETA DE SISTEMA DE CLORACION POR GOTEO
CASETA DE MURO DE LADRILLO -CLORADOR POR
04.04.10.01.01
GOTEO
04.04.10.01.01. MURO DE LADRILLO PANDERETA (0.10x0.12x0.24)
m2 7.52 49.46 371.97
01 AMARRE SOGA MORTERO 1:5 JUNTA 1.5 cm.
MURO DE LADRILLO PANDERETA
04.04.10.01.01.
INTERCALADO(0.10x0.12x0.24) AMARRE SOGA MORTERO 1:5 m2 4.48 44.42 199.02
02
JUNTA 1.5 cm.
04.04.10.01.02 ESTRUCTURA DE MADERA Y COBERTURA
04.04.10.01.02.
CORREAS DE MADERA DE 2" x 2" m 6.00 26.16 156.98
01
04.04.10.01.02. COBERTURA CON CALAMINA
m2 5.98 30.67 183.42
02
04.04.10.01.03 REVOQUES Y ENLUCIDOS
04.04.10.01.03. TARRAJEO MUROS DE INTERIORES Y EXTERIORES,
m2 14.98 27.00 404.46
01 CEMENTO : ARENA, 1:5
04.04.10.01.03.
DERRAME EN PUERTAS h =0.10 m, C:A 1:2, e=2.0 cm m 4.00 12.40 49.61
02
04.04.10.01.04 CARPINTERIA METALICA
04.04.10.01.04. SUMINISTRO E INSTALACION DE PUERTA METALICA
und 1.00 330.46 330.46
01 DE 1.80 x 0.60 m. INCL. MARCO Y PINTADO
04.04.10.01.05 PINTURAS
04.04.10.01.05. PINTURA ESMALTE EN MUROS INTERIORES Y
m2 14.98 10.06 150.73
01 EXTERIORES
04.04.10.01.05.
PINTURA ANTICORROSIVA Y ESMALTE EN PUERTAS m2 4.00 11.03 44.10
02
04.04.10.02 TANQUE DE AGUA 250 LTRS, INCLUYE ACC. INTERNOS
SUMINISTRO E INSTALACION DE TANQUE DE
04.04.10.02.01 und 1.00 391.55 391.55
POLIETILENO, CAP=250 LTRS.
04.04.10.03 SUMINISTRO E INSTALACIÓN DE CLORADOR
SUMINISTRO Y COLOCACION DE TUBERIAS Y
04.04.10.03.01 GLB 1.00 845.30 845.30
ACCESORIOS EN SISTEMA DE CLORACION POR GOTEO
04.05 RED DE ADUCCION Y DISTRIBUCION (L=3,674.00 m)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,837.00 0.44 810.12
04.05.01.02 TRAZO Y REPLANTEO EN ZANJAS LINEAS Y REDES m 3,674.00 1.38 5,059.10
TRAZO Y NIVELACION DURANTE LA EJECUCION EN
04.05.01.03 m 3,674.00 1.38 5,059.10
ZANJAS REDES Y LINEAS
04.05.02 MOVIMIENTO DE TIERRAS
04.05.02.01 EXCAVACION MANUAL DE ZANJA EN MATERIAL SUELTO m3 73.48 35.87 2,636.02
EXCAVACION MANUAL DE ZANJA EN MATERIAL
04.05.02.02 m3 1,352.03 44.84 60,622.32
CONGLOMERADO
EXCAVACION MANUAL DE ZANJA EN MATERIAL ROCA
04.05.02.03 m3 44.09 50.22 2,214.20
SUELTA
REFINE Y NIVELACION DE ZANJA EN TERRENO NORMAL
04.05.02.04 m 3,674.00 1.63 5,984.95
P/TUBERIA
PERFILADO DE ZANJA EN TERRENO DE ROCA SUELTA Y
04.05.02.05 m 110.22 5.47 603.13
FIJA P/TUBERIA
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.05.02.06 m3 534.57 32.76 17,512.52
PROPIO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.05.02.07 m3 16.53 58.65 969.53
DE PRESTAMO SELECCIONADO DE 3/8" P/TUBERIA, H=0.30 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.05.02.08 m3 946.06 22.56 21,345.95
PROPIO P/TUBERIA, H=0.50 m
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.05.02.09 m3 55.11 55.94 3,083.08
DE PRESTAMO P/TUBERIA, H=0.20 m
04.05.02.10 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 27.56 23.12 637.22
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.03
ACCESORIOS
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10
04.05.03.01 m 104.00 7.25 753.48
DE 1"
SUMINISTRO E INSTALACION DE TUBERIA PVC SAP C-10
04.05.03.02 m 3,570.00 4.36 15,550.92
DE 3/4"
04.05.03.03 SUMINISTRO E INSTALACION DE ACCESORIOS und 1.00 79.17 79.17
04.05.04 PRUEBA HIDRAULICA
04.05.04.01 PRUEBA HIDRAULICA Y DESINFECCION m 3,674.00 1.36 4,992.97
04.05.05 CAMARA ROMPE PRESION T-7 (12 UND)
04.05.05.01 OBRAS PRELIMINARES
04.05.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 24.84 0.44 10.95
04.05.05.01.02 TRAZO Y REPLANTEO m2 24.84 1.66 41.14
04.05.05.02 MOVIMIENTO DE TIERRAS
04.05.05.02.01 EXCAVACION A MANO TERRENO NORMAL m3 16.71 35.87 599.45
04.05.05.02.02 EXCAVACION A MANO ROCA SUELTA m3 9.55 36.86 351.96
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
04.05.05.02.03 m3 2.39 11.80 28.20
MANO
04.05.05.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 23.58 7.16 168.71
04.05.05.02.05 RELLENO CON MATERIAL DE PRESTAMO m3 1.39 53.50 74.36
04.05.05.02.06 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 12.53 23.12 289.71
04.05.05.03 OBRAS DE CONCRETO SIMPLE
04.05.05.03.01 CONCRETO f'c= 140 kg/cm2 m3 0.14 371.85 52.06
04.05.05.03.02 SOLADO E=4" m3 1.98 32.23 63.81
04.05.05.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.40 40.03 96.08

04.05.05.03.04 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 3.24 108.99 353.12

04.05.05.04 OBRAS DE CONCRETO ARMADO


04.05.05.04.01 CONCRETO f'c=210 kg/cm2 m3 16.30 492.02 8,019.95
04.05.05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 167.06 40.03 6,687.75
04.05.05.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,361.41 3.92 9,244.92
04.05.05.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.05.05.05.01 m2 51.84 29.23 1,515.38
MEZCLA 1:2 E=2 cm H=1.5 Max
04.05.05.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 112.34 26.78 3,008.92
04.05.05.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
04.05.05.06.01 m2 72.00 10.06 724.46
MANOS
04.05.05.07 CARPINTERIA METALICA
04.05.05.07.01 MARCO Y TAPA METALICA DE 0.45m x 0.40m E=1/8" und 12.00 161.85 1,942.16
04.05.05.07.02 MARCO Y TAPA METALICA DE 0.60m x 0.60m E=1/8" und 12.00 192.36 2,308.28
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.05.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN CRP
04.05.05.08.01 und 12.00 341.26 4,095.14
T7, INGRESO Y SALIDA Ø=3/4"
04.05.06 VALVULA DE CONTROL (05 UND)
04.05.06.01 OBRAS PRELIMINARES
04.05.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.44 2.21
04.05.06.01.02 TRAZO Y REPLANTEO m2 5.00 1.66 8.28
04.05.06.02 MOVIMIENTO DE TIERRAS
04.05.06.02.01 EXCAVACION A MANO TERRENO NORMAL m3 5.00 35.87 179.37
04.05.06.02.02 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 6.25 23.12 144.50
04.05.06.02.03 NIVELACION INTERIOR APISONADO MANUAL m2 5.00 7.16 35.78
04.05.06.03 OBRAS DE CONCRETO ARMADO
04.05.06.03.01 CONCRETO f'c=210 kg/cm2 m3 2.47 492.02 1,215.29
04.05.06.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 21.30 40.03 852.68
04.05.06.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 153.78 3.92 602.05
04.05.06.04 REVOQUES Y ENLUCIDOS
04.05.06.04.01 TARRAJEO INTERIOR CON MORTERO 1:3 e=1.5cm m2 7.20 29.23 210.47
04.05.06.04.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 10.80 26.78 289.27
04.05.06.05 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
04.05.06.05.01 m2 10.80 10.06 108.67
MANOS
04.05.06.06 CARPINTERIA METALICA
04.05.06.06.01 MARCO Y TAPA METALICA DE 0.40m x 0.40m E=1/8" und 5.00 146.59 732.96
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.06.07
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.05.06.07.01 und 5.00 71.12 355.59
VALVULA DE CONTROL, Ø=3/4"
04.05.07 VALVULA DE PURGA TIPO II (05 UND)
04.05.07.01 OBRAS PRELIMINARES
04.05.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 5.00 0.44 2.21
04.05.07.01.02 TRAZO Y REPLANTEO m2 5.00 1.66 8.28
04.05.07.02 MOVIMIENTO DE TIERRAS
04.05.07.02.01 EXCAVACION A MANO TERRENO NORMAL m3 7.64 35.87 274.08
04.05.07.02.02 EXCAVACION MANUAL EN TERRENO ROCA SUELTA m3 2.55 44.84 114.34
RELLENO Y COMPACTADO CON MATERIAL PROPIO A
04.05.07.02.03 m3 2.55 11.80 30.09
MANO
04.05.07.02.04 NIVELACION INTERIOR APISONADO MANUAL m2 2.45 7.16 17.53
04.05.07.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 2.45 23.12 56.65
04.05.07.03 OBRAS DE CONCRETO SIMPLE
04.05.07.03.01 CONCRETO f'c= 140 kg/cm2 m3 1.53 371.85 568.94
04.05.07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.20 40.03 48.04

04.05.07.03.03 EMBOQUILLADO C/MAMPOSTERIA DE PIEDRA + 80% PM m2 0.64 108.99 69.75

04.05.07.04 OBRAS DE CONCRETO ARMADO


04.05.07.04.01 CONCRETO f'c=210 kg/cm2 m3 1.75 492.02 861.04
04.05.07.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 18.60 40.03 744.60
04.05.07.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 74.70 3.92 292.46
04.05.07.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.05.07.05.01 m2 7.20 29.23 210.47
MEZCLA 1:2 E=2 cm H=1.5 Max
04.05.07.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 16.80 26.78 449.97
04.05.07.06 PINTURA
PINTURA EN MUROS EXTERIORES CON ESMALTE-2
04.05.07.06.01 m2 8.10 10.06 81.50
MANOS
04.05.07.07 CARPINTERIA METALICA
MARCO Y TAPA METALICA LAC 2.0mm, C/MECAN. DE
04.05.07.07.01 und 5.00 192.36 961.79
0.60x0.40m.
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.07.08
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.05.07.08.01 und 5.00 119.65 598.23
VALVULA DE PURGA TIPO II, INGRESO Y SALIDA Ø=3/4"
04.05.08 CONEXIONES DOMICILIARIAS (53 UND)
04.05.08.01 OBRAS PRELIMINARES
04.05.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 474.88 0.44 209.42
04.05.08.01.02 TRAZO Y REPLANTEO m2 712.32 1.66 1,179.60
04.05.08.02 MOVIMIENTO DE TIERRAS 0.00
04.05.08.02.01 EXCAVACION A MANO DE ZANJA TERRENO NORMAL m3 596.86 36.86 21,997.28
RELLENO Y COMPACTADO DE ZANJAS CON MATERIAL
04.05.08.02.02 m3 569.86 29.70 16,924.84
PROPIO CLASIFICADO
SUMINISTRO Y COLOCACION DE GRAVA
04.05.08.02.03 m3 59.36 188.20 11,171.49
SELECCIONADA
04.05.08.03 OBRAS DE CONCRETO SIMPLE
04.05.08.03.01 CONCRETO f'c= 140 kg/cm2 m3 3.93 371.85 1,461.38
04.05.08.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 19.61 40.03 785.03
SUMINISTRO E INSTALACION DE TUBERIAS Y
04.05.08.04
ACCESORIOS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.05.08.04.01 und 53.00 72.69 3,852.73
CONEXIONES DOMICILIARIAS DE AGUA (53 UND)
TAPA SANITARIA DE ALUMINIO DE 0.40x0.40m CON
04.05.08.04.02 und 53.00 139.69 7,403.52
LLAVE TIPO BUJIA
SUMINISTRO E INSTALACIONES DE ACOMETIDA
04.05.08.04.03 m 636.00 3.15 2,003.40
DOMICILIARIA RANGO 2 - 20 M.

01 LOCALIDAD SANTA LUCIA


01.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
01.01.01 TRABAJOS PRELIMINARES
01.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 465.00 0.44 205.07
01.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 465.00 1.66 770.04
01.01.02 MOVIMIENTO DE TIERRAS
01.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 231.57 35.87 8,307.34
01.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 40.92 26.69 1,092.32
01.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 238.08 23.12 5,504.65
01.01.03 CONCRETO SIMPLE
01.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 279.00 336.38 93,848.63
01.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 40.92 358.82 14,682.95
01.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 678.90 40.03 27,177.72
01.01.03.04 CONCRETO f'c=175 kg/cm2 m3 28.83 403.97 11,646.32
01.01.04 MURO DE LADRILLO
MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE
01.01.04.01 m2 1,354.08 52.29 70,804.85
SOGA C/M 1:4 x 1.5cm
EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-
01.01.04.02 m2 26.04 63.30 1,648.25
6"
01.01.05 REVOQUES Y ENLUCIDOS
TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE
01.01.05.01 m2 1,272.24 14.71 18,709.56
P/CAMARA (UBS arrastre hidraulico)
01.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 20.46 32.90 673.03
01.01.06 PINTURA
PINTURA EN MUROS INTERIORES C/LATEX LAVABLE
01.01.06.01 m2 767.25 10.38 7,961.75
COLOR MARFIL
01.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO
01.01.07.01 ETERNIT(1,14x0.72x0.005m) m2 605.43 59.60 36,082.41

01.01.08 CARPINTERIA METALICA


SUMINISTRO E INSTALACION DE PUERTA METALICA
01.01.08.01 und 93.00 327.37 30,445.04
1.80x0.70m, INCL. MARCO Y PINTADO
01.01.09 CARPINTERIA DE MADERA
VENTANA DE MADERA TORNILLO INC. MALLA
01.01.09.01 m2 16.74 68.31 1,143.51
MOSQUITERA
01.01.09.02 COBERTURA DE MADERA PARA TECHO und 93.00 88.16 8,198.42
01.01.10 SISTEMA DE AGUA FRIA
01.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 880.71 3.29 2,893.13
01.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
01.01.11.01 TEE PVC-SAP 1/2" pza 186.00 18.77 3,490.29
01.01.11.02 CODO PVC SAP 1/2" pza 558.00 14.03 7,829.30
01.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 186.00 46.13 8,579.25
SUMINISTRO E INSTALACION DE DUCHA INCLUIDO
01.01.11.04 und 93.00 29.77 2,768.80
ACCESORIOS
01.01.12 SISTEMA DE DESAGUE
01.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 897.45 3.62 3,246.98
01.01.12.02 TUBERIA Ø=4" PVC SAL m 339.45 3.29 1,115.09
01.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
01.01.13.01 CODO PVC SAL 2"X90° pza 651.00 10.59 6,896.04
01.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 93.00 13.98 1,299.86
01.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 279.00 14.50 4,045.22
01.01.14 ADITAMIENTOS VARIOS
01.01.14.01 SUMIDEROS DE BRONCE 2" und 93.00 11.03 1,025.33
01.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 186.00 9.98 1,856.47
INODORO DE LOZA VITRIFICADA COLOR BLANCO
01.01.14.03 und 93.00 132.66 12,337.38
INCLUYE TANQUE
01.01.14.04 ACCESORIOS DE LOZA und 93.00 58.37 5,428.78
SUMINISTRO E INSTALACION DE TUBERIA DE
01.01.14.05 VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y GLB 93.00 26.24 2,439.86
ACCESORIOS
SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA
01.01.14.06 und 93.00 112.13 10,428.18
COLOR BLANCO INCLUIDO ACCESORIOS
SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE
01.01.14.07 und 186.00 116.90 21,743.59
12"x24"
01.01.15 INSTALACIONES ELECTRICAS
01.01.15.01 SALIDA DE CENTRO DE LUZ pto 93.00 44.23 4,113.02
01.01.15.02 TUBERIA PVC SEL 5/8" m 213.90 3.74 798.92
01.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 520.80 2.05 1,068.68
01.01.15.04 TABLEROS DISTRIBUCION pza 93.00 80.14 7,452.65
01.01.16 CONSTRUCCION POZO PERCOLADOR
01.01.16.01 TRABAJOS PRELIMINARES
01.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 292.02 0.44 128.78
01.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 292.02 1.66 483.59
01.01.16.02 MOVIMIENTO DE TIERRAS
01.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 150.66 35.87 5,404.78
01.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 22.32 26.69 595.81
01.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 80.91 80.37 6,502.73
01.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 188.79 23.12 4,365.02
01.01.16.03 TAPA DE CONCRETO
01.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 18.81 403.97 7,598.58
01.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 196.26 40.03 7,856.68
01.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,957.65 3.92 7,664.20
01.01.16.04 ANILLO DE CONCRETO
01.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 6.51 320.38 2,085.69
01.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 111.60 40.03 4,467.57
01.01.16.05 MURO DE LADRILLO
MURO DE LADRILLO ARTESANAL AMARRE DE SOGA,
01.01.16.05.01 m2 388.74 44.05 17,122.45
JUNTA 1.5 CM MORTERO 1:1:5
01.01.16.06 SISTEMA DE DESAGUE LLEGADA
01.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 181.35 3.62 656.13
01.01.16.06.02 CODO PVC SAL 2"X90° pza 93.00 10.59 985.15
01.01.17 INSTALACION DEL BIODIGESTOR
01.01.17.01 TRABAJOS PRELIMINARES
01.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 351.54 0.44 155.03
01.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 351.54 1.66 582.15
01.01.17.02 MOVIMIENTO DE TIERRAS
01.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 281.20 35.87 10,087.77
01.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 211.97 26.69 5,658.33
01.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 351.50 23.12 8,127.04
01.01.17.03 CONCRETO SIMPLE
01.01.17.03.01 SOLADO E=4" m2 60.45 35.71 2,158.79
01.01.17.04 CONCRETO ARMADO
01.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 66.96 403.97 27,049.50
01.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 420.36 40.03 16,827.85
01.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 518.01 3.92 2,028.01
01.01.17.05 BIODIGESTOR
SUMINISTRO E INSTALACION DE BIODIGESTOR
01.01.17.05.01 und 91.00 701.63 63,848.42
AUTOLIMPIABLE DE PVC DE 600 LTS
SUMINISTRO E INSTALACION DE BIODIGESTOR
01.01.17.05.02 und 2.00 1,188.71 2,377.42
AUTOLIMPIABLE DE PVC DE 1300 LTS
01.01.17.06 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.01.17.06.01 m2 332.01 29.23 9,705.31
MEZCLA 1:2 E=2 cm H=1.5 Max
01.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
01.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 93.00 3.62 336.47
SUMINISTRO E INSTALACION DE VALVULA DE PVC DE
01.01.17.07.02 und 93.00 26.87 2,499.28
2"
01.02 LAVADERO INTRADOMICILIARIO (91 UND)
01.02.01 OBRAS PRELIMINARES
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 460.46 0.44 203.07
01.02.01.02 TRAZO Y REPLANTEO m2 460.46 1.66 762.53
01.02.02 MOVIMIENTO DE TIERRAS
01.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 103.03 33.73 3,475.40
RELLENO Y COMPACTADO DE ZANJA CON MATERIAL
01.02.02.02 m3 84.63 11.80 998.55
PROPIO CLASIFICADO
01.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 21.16 23.12 489.24
01.02.03 OBRAS DE CONCRETO ARMADO
01.02.03.01 CONCRETO f'c=175 kg/cm2 m3 9.57 403.97 3,865.94
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 304.63 40.03 12,194.95
01.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 359.91 3.92 1,409.05
01.02.04 MURO DE LADRILLO
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
01.02.04.01 m2 60.17 42.97 2,585.27
Lavaderos)
01.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
01.02.05.01 m2 107.29 29.23 3,136.30
MEZCLA 1:2 E=2 cm H=1.5 Max
01.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 205.30 26.78 5,498.76
01.02.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE LAVADERO
01.02.06.01 und 91.00 122.68 11,163.79
INTRADOMICILIARIA
01.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
01.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 455.00 3.02 1,371.83
01.03 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.44 5.00
01.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.66 18.75
01.03.02 MOVIMIENTO DE TIERRAS
01.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 33.73 92.43
REFINE, NIVELACION Y COMPACTADO EN TERRENO
01.03.02.02 m2 11.32 0.92 10.40
NORMAL
01.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 26.55 43.01
01.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 23.12 30.98
01.03.03 OBRAS DE CONCRETO SIMPLE
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
01.03.03.01 m2 2.20 44.06 96.94
FROTACHADO C/MEZCLADORA
01.03.04 OBRAS DE CONCRETO ARMADO
01.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 3.92 32.69
01.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 39.61 162.00
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA
01.03.04.03 m3 0.21 403.97 84.83
LAVADEROS
01.03.05 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
01.03.05.01 m2 2.49 29.66 73.86
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
01.03.05.02 m2 2.11 21.58 45.54
H=1.5 MAX
01.03.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
01.03.06.01 und 1.00 159.29 159.29
LAVADERO I.E. INICIAL
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
01.03.06.02 und 2.00 128.25 256.50
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
01.03.06.03 und 1.00 51.99 51.99
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
01.03.06.04 und 1.00 43.37 43.37
(INTERIORES), E=0.05
01.03.07 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10,
01.03.07.01 m 12.00 5.72 68.58
P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
01.03.07.02 m 10.00 5.99 59.85
PARA DESAGUE Ø=2"x3 M
02 LOCALIDAD PUEBLO LIBRE (130 UND)
02.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 650.00 0.44 286.65
02.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 650.00 1.66 1,076.40
02.01.02 MOVIMIENTO DE TIERRAS
02.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 323.70 35.87 11,612.41
02.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 57.20 26.69 1,526.90
02.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 332.80 23.12 7,694.67
02.01.03 CONCRETO SIMPLE
02.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 390.00 336.38 131,186.25
02.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 57.20 358.82 20,524.56
02.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 949.00 40.03 37,990.37
02.01.03.04 CONCRETO f'c=175 kg/cm2 m3 40.30 403.97 16,279.79
02.01.04 MURO DE LADRILLO
MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE
02.01.04.01 m2 1,892.80 52.29 98,974.51
SOGA C/M 1:4 x 1.5cm
EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-
02.01.04.02 m2 36.40 63.30 2,304.01
6"
02.01.05 REVOQUES Y ENLUCIDOS
TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE
02.01.05.01 m2 1,778.40 14.71 26,153.15
P/CAMARA (UBS arrastre hidraulico)
02.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 28.60 32.90 940.80
02.01.06 PINTURA
PINTURA EN MUROS INTERIORES C/LATEX LAVABLE
02.01.06.01 m2 1,072.50 10.38 11,129.34
COLOR MARFIL
02.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO
02.01.07.01 ETERNIT(1,14x0.72x0.005m) m2 846.60 59.60 50,455.67

02.01.08 CARPINTERIA METALICA


SUMINISTRO E INSTALACION DE PUERTA METALICA
02.01.08.01 und 130.00 327.37 42,557.58
1.80x0.70m, INCL. MARCO Y PINTADO
02.01.09 CARPINTERIA DE MADERA
VENTANA DE MADERA TORNILLO INC. MALLA
02.01.09.01 m2 23.40 68.31 1,598.45
MOSQUITERA
02.01.09.02 COBERTURA DE MADERA PARA TECHO und 130.00 88.16 11,460.15
02.01.10 SISTEMA DE AGUA FRIA
02.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 1,231.00 3.29 4,043.84
02.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
02.01.11.01 TEE PVC-SAP 1/2" pza 260.00 18.77 4,878.90
02.01.11.02 CODO PVC SAP 1/2" pza 780.00 14.03 10,944.18
02.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 260.00 46.13 11,992.50
SUMINISTRO E INSTALACION DE DUCHA INCLUIDO
02.01.11.04 und 130.00 29.77 3,870.36
ACCESORIOS
02.01.12 SISTEMA DE DESAGUE
02.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 1,254.50 3.62 4,538.78
02.01.12.02 TUBERIA Ø=4" PVC SAL m 474.50 3.29 1,558.74
02.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
02.01.13.01 CODO PVC SAL 2"X90° pza 910.00 10.59 9,639.63
02.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 130.00 13.98 1,817.01
02.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 390.00 14.50 5,654.61
02.01.14 ADITAMIENTOS VARIOS
02.01.14.01 SUMIDEROS DE BRONCE 2" und 130.00 11.03 1,433.25
02.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 260.00 9.98 2,595.06
INODORO DE LOZA VITRIFICADA COLOR BLANCO
02.01.14.03 und 130.00 132.66 17,245.80
INCLUYE TANQUE
02.01.14.04 ACCESORIOS DE LOZA und 130.00 58.37 7,588.62
SUMINISTRO E INSTALACION DE TUBERIA DE
02.01.14.05 VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y GLB 130.00 26.24 3,410.55
ACCESORIOS
SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA
02.01.14.06 und 130.00 112.13 14,577.03
COLOR BLANCO INCLUIDO ACCESORIOS
SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE
02.01.14.07 und 260.00 116.90 30,394.26
12"x24"
02.01.15 INSTALACIONES ELECTRICAS
02.01.15.01 SALIDA DE CENTRO DE LUZ pto 130.00 44.23 5,749.38
02.01.15.02 TUBERIA PVC SEL 5/8" m 299.00 3.74 1,116.77
02.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 728.00 2.05 1,493.86
02.01.15.04 TABLEROS DISTRIBUCION pza 130.00 80.14 10,417.68
02.01.16 CONSTRUCCION POZO PERCOLADOR
02.01.16.01 TRABAJOS PRELIMINARES
02.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 408.20 0.44 180.02
02.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 408.20 1.66 675.98
02.01.16.02 MOVIMIENTO DE TIERRAS
02.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 210.60 35.87 7,555.07
02.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 31.20 26.69 832.85
02.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 113.10 80.37 9,089.85
02.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 163.90 23.12 3,789.53
02.01.16.03 TAPA DE CONCRETO
02.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 22.10 403.97 8,927.63
02.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 236.60 40.03 9,471.57
02.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 2,736.50 3.92 10,713.40
02.01.16.04 ANILLO DE CONCRETO
02.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 9.10 320.38 2,915.48
02.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 156.00 40.03 6,244.99
02.01.16.05 MURO DE LADRILLO
MURO DE LADRILLO ARTESANAL AMARRE DE SOGA,
02.01.16.05.01 m2 543.40 44.05 23,934.60
JUNTA 1.5 CM MORTERO 1:1:5
02.01.16.06 SISTEMA DE DESAGUE LLEGADA
02.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 253.50 3.62 917.16
02.01.16.06.02 CODO PVC SAL 2"X90° pza 130.00 10.59 1,377.09
02.01.17 INSTALACION DEL BIODIGESTOR
02.01.17.01 TRABAJOS PRELIMINARES
02.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 491.40 0.44 216.71
02.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 491.40 1.66 813.76
02.01.17.02 MOVIMIENTO DE TIERRAS
02.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 396.70 35.87 14,231.21
02.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 299.24 26.69 7,987.91
02.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 504.11 23.12 11,655.53
02.01.17.03 CONCRETO SIMPLE
02.01.17.03.01 SOLADO E=4" m2 84.50 35.71 3,017.66
02.01.17.04 CONCRETO ARMADO
02.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 93.60 403.97 37,811.12
02.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 587.60 40.03 23,522.81
02.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 724.10 3.92 2,834.86
02.01.17.05 BIODIGESTOR
SUMINISTRO E INSTALACION DE BIODIGESTOR
02.01.17.05.01 und 121.00 701.63 84,897.35
AUTOLIMPIABLE DE PVC DE 600 LTS
SUMINISTRO E INSTALACION DE BIODIGESTOR
02.01.17.05.02 und 9.00 1,188.71 10,698.40
AUTOLIMPIABLE DE PVC DE 1300 LTS
02.01.17.06 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.01.17.06.01 m2 464.10 29.23 13,566.57
MEZCLA 1:2 E=2 cm H=1.5 Max
02.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
02.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 130.00 3.62 470.34
SUMINISTRO E INSTALACION DE VALVULA DE PVC DE
02.01.17.07.02 und 130.00 26.87 3,493.62
2"
02.02 LAVADERO INTRADOMICILIARIO (121 UND)
02.02.01 OBRAS PRELIMINARES
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 612.26 0.44 270.01
02.02.01.02 TRAZO Y REPLANTEO m2 612.26 1.66 1,013.90
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 137.00 33.73 4,621.28
RELLENO Y COMPACTADO DE ZANJA CON MATERIAL
02.02.02.02 m3 112.53 11.80 1,327.74
PROPIO CLASIFICADO
02.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 28.14 23.12 650.63
02.02.03 OBRAS DE CONCRETO ARMADO
02.02.03.01 CONCRETO f'c=175 kg/cm2 m3 12.72 403.97 5,138.43
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 405.06 40.03 16,215.36
02.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 478.56 3.92 1,873.57
02.02.04 MURO DE LADRILLO
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
02.02.04.01 m2 80.01 42.97 3,437.71
Lavaderos)
02.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
02.02.05.01 m2 142.66 29.23 4,170.24
MEZCLA 1:2 E=2 cm H=1.5 Max
02.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 272.98 26.78 7,311.49
02.02.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE LAVADERO
02.02.06.01 und 121.00 122.68 14,844.16
INTRADOMICILIARIA
02.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
02.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 605.00 3.02 1,824.08
02.03 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
02.03.01 TRABAJOS PRELIMINARES
02.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.44 5.00
02.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.66 18.75
02.03.02 MOVIMIENTO DE TIERRAS
02.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 33.73 92.43
REFINE, NIVELACION Y COMPACTADO EN TERRENO
02.03.02.02 m2 11.32 10.40
NORMAL
02.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 26.55 43.01
02.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 23.12 30.98
02.03.03 OBRAS DE CONCRETO SIMPLE
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
02.03.03.01 m2 2.20 44.06 96.94
FROTACHADO C/MEZCLADORA
02.03.04 OBRAS DE CONCRETO ARMADO
02.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 3.92 32.69
02.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 39.61 162.00
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA
02.03.04.03 m3 0.21 403.97 84.83
LAVADEROS
02.03.05 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
02.03.05.01 m2 2.49 29.66 73.86
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
02.03.05.02 m2 2.11 21.58 45.54
H=1.5 MAX
02.03.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.03.06.01 und 1.00 159.29 159.29
LAVADERO I.E. INICIAL
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
02.03.06.02 und 2.00 128.25 256.50
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
02.03.06.03 und 1.00 51.99 51.99
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
02.03.06.04 und 1.00 43.37 43.37
(INTERIORES), E=0.05
02.03.07 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10,
02.03.07.01 m 12.00 5.72 68.58
P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
02.03.07.02 m 10.00 5.99 59.85
PARA DESAGUE Ø=2"x3 M
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01
02.04
UND)
02.04.01 TRABAJOS PRELIMINARES
02.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.44 5.28
02.04.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.66 19.84
02.04.02 MOVIMIENTO DE TIERRAS
02.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 33.73 94.45
REFINE, NIVELACION Y COMPACTADO EN TERRENO
02.04.02.02 m2 11.98 0.92 11.00
NORMAL
02.04.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 26.55 43.01
02.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 23.12 32.60
02.04.03 OBRAS DE CONCRETO SIMPLE
CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6")
02.04.03.01 m3 0.06 305.64 18.34
EN LAVADERO C/MEZCLADORA
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
02.04.03.02 m2 2.86 44.06 126.03
FROTACHADO C/MEZCLADORA
02.04.04 OBRAS DE CONCRETO ARMADO 0.00
02.04.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 3.92 44.98
02.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 39.61 171.50
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA
02.04.04.03 m3 0.31 403.97 125.23
LAVADEROS
02.04.05 ALBAÑILERIA
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
02.04.05.01 m2 0.36 52.27 18.82
Lavaderos)
02.04.06 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
02.04.06.01 m2 3.51 29.66 104.12
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
02.04.06.02 m2 3.29 21.58 71.00
H=1.5 MAX
02.04.07 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.04.07.01 und 1.00 159.29 159.29
LAVADERO TIPO I.E. PRIMARIA
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
02.04.07.02 und 2.00 128.25 256.50
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
02.04.07.03 und 1.00 51.99 51.99
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
02.04.07.04 und 1.00 43.37 43.37
(INTERIORES), E=0.05
02.04.08 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA
02.04.08.01 m 12.00 5.72 68.58
CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
02.04.08.02 m 10.00 5.99 59.85
PARA DESAGUE Ø=2"x3 M
02.05 LAVADERO I.E. SECUNDARIA (01 UND)
02.05.01 TRABAJOS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.44 5.00
02.05.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.66 18.75
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 3.70 33.73 124.81
REFINE, NIVELACION Y COMPACTADO EN TERRENO
02.05.02.02 m2 11.32 0.92 10.40
NORMAL
02.05.02.03 RELLENO CON MATERIAL PROPIO m3 2.64 26.55 70.09
02.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.27 23.12 29.37
02.05.03 OBRAS DE CONCRETO SIMPLE 0.00
CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6")
02.05.03.01 m3 0.08 305.64 24.45
EN LAVADERO C/MEZCLADORA
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
02.05.03.02 m2 0.22 44.06 9.69
FROTACHADO C/MEZCLADORA
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 0.26 3.92 1.02
02.05.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 5.20 39.61 205.97
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA
02.05.04.03 m3 12.73 403.97 5,142.47
LAVADEROS
02.05.05 ALBAÑILERIA
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
02.05.05.01 m2 1.04 52.27 54.36
Lavaderos)
02.05.06 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
02.05.06.01 m2 3.13 29.66 92.84
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
02.05.06.02 m2 4.41 21.58 95.18
H=1.5 MAX
02.05.07 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
02.05.07.01 und 1.00 159.29 159.29
LAVADERO TIPO I.E. PRIMARIA
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
02.05.07.02 und 2.00 128.25 256.50
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
02.05.07.03 und 1.00 51.99 51.99
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
02.05.07.04 und 1.00 43.37 43.37
(INTERIORES), E=0.05
02.05.08 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA
02.05.08.01 m 12.00 5.72 68.58
CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
02.05.08.02 m 10.00 5.99 59.85
PARA DESAGUE Ø=2"x3 M
03 LOCALIDAD TANCARPATA (55 UND)
03.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
03.01.01 TRABAJOS PRELIMINARES
03.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 275.00 0.44 121.28
03.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 275.00 1.66 455.40
03.01.02 MOVIMIENTO DE TIERRAS
03.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 136.95 35.87 4,912.95
03.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 24.20 26.69 645.99
03.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 140.80 23.12 3,255.44
03.01.03 CONCRETO SIMPLE
03.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 165.00 336.38 55,501.88
03.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 24.20 358.82 8,683.47
03.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 401.50 40.03 16,072.85
03.01.03.04 CONCRETO f'c=175 kg/cm2 m3 17.05 403.97 6,887.60
03.01.04 MURO DE LADRILLO
MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE
03.01.04.01 m2 800.80 52.29 41,873.83
SOGA C/M 1:4 x 1.5cm
EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-
03.01.04.02 m2 15.40 63.30 974.77
6"
03.01.05 REVOQUES Y ENLUCIDOS
TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE
03.01.05.01 m2 752.40 14.71 11,064.80
P/CAMARA (UBS arrastre hidraulico)
03.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 12.10 32.90 398.03
03.01.06 PINTURA
PINTURA EN MUROS INTERIORES C/LATEX LAVABLE
03.01.06.01 m2 453.75 10.38 4,708.57
COLOR MARFIL
03.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO
03.01.07.01 ETERNIT(1,14x0.72x0.005m) m2 358.05 59.60 21,339.06

03.01.08 CARPINTERIA METALICA


SUMINISTRO E INSTALACION DE PUERTA METALICA
03.01.08.01 und 55.00 327.37 18,005.13
1.80x0.70m, INCL. MARCO Y PINTADO
03.01.09 CARPINTERIA DE MADERA
VENTANA DE MADERA TORNILLO INC. MALLA
03.01.09.01 m2 9.90 68.31 676.27
MOSQUITERA
03.01.09.02 COBERTURA DE MADERA PARA TECHO und 55.00 88.16 4,848.53
03.01.10 SISTEMA DE AGUA FRIA
03.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 520.85 3.29 1,710.99
03.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA
03.01.11.01 TEE PVC-SAP 1/2" pza 110.00 18.77 2,064.15
03.01.11.02 CODO PVC SAP 1/2" pza 330.00 14.03 4,630.23
03.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 110.00 46.13 5,073.75
SUMINISTRO E INSTALACION DE DUCHA INCLUIDO
03.01.11.04 und 55.00 29.77 1,637.46
ACCESORIOS
03.01.12 SISTEMA DE DESAGUE
03.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 530.75 3.62 1,920.26
03.01.12.02 TUBERIA Ø=4" PVC SAL m 200.75 3.29 659.47
03.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
03.01.13.01 CODO PVC SAL 2"X90° pza 385.00 10.59 4,078.31
03.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 55.00 13.98 768.74
03.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 165.00 14.50 2,392.34
03.01.14 ADITAMIENTOS VARIOS
03.01.14.01 SUMIDEROS DE BRONCE 2" und 55.00 11.03 606.38
03.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 110.00 9.98 1,097.91
INODORO DE LOZA VITRIFICADA COLOR BLANCO
03.01.14.03 und 55.00 132.66 7,296.30
INCLUYE TANQUE
03.01.14.04 ACCESORIOS DE LOZA und 55.00 58.37 3,210.57
SUMINISTRO E INSTALACION DE TUBERIA DE
03.01.14.05 VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y GLB 55.00 26.24 1,442.93
ACCESORIOS
SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA
03.01.14.06 und 55.00 112.13 6,167.21
COLOR BLANCO INCLUIDO ACCESORIOS
SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE
03.01.14.07 und 110.00 116.90 12,859.11
12"x24"
03.01.15 INSTALACIONES ELECTRICAS
03.01.15.01 SALIDA DE CENTRO DE LUZ pto 55.00 44.23 2,432.43
03.01.15.02 TUBERIA PVC SEL 5/8" m 126.50 3.74 472.48
03.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 308.00 2.05 632.02
03.01.15.04 TABLEROS DISTRIBUCION pza 55.00 80.14 4,407.48
03.01.16 CONSTRUCCION POZO PERCOLADOR
03.01.16.01 TRABAJOS PRELIMINARES
03.01.16.01.01 LIMPIEZA DE TERRENO MANUAL m2 172.70 0.44 76.16
03.01.16.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 172.20 1.66 285.17
03.01.16.02 MOVIMIENTO DE TIERRAS
03.01.16.02.01 EXCAVACION A MANO TERRENO NORMAL m3 89.10 35.87 3,196.38
03.01.16.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 13.20 26.69 352.36
03.01.16.02.03 FILTRO DE GRAVA CLASIFICADA m3 47.85 80.37 3,845.71
03.01.16.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 111.65 23.12 2,581.46
03.01.16.03 TAPA DE CONCRETO
03.01.16.03.01 CONCRETO f'c=175 kg/cm2 m3 9.35 403.97 3,777.08
03.01.16.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 100.10 40.03 4,007.21
03.01.16.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,157.75 3.92 4,532.59
03.01.16.04 ANILLO DE CONCRETO
03.01.16.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 3.85 320.38 1,233.47
03.01.16.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.00 40.03 2,642.11
03.01.16.05 MURO DE LADRILLO
MURO DE LADRILLO ARTESANAL AMARRE DE SOGA,
03.01.16.05.01 m2 229.90 44.05 10,126.18
JUNTA 1.5 CM MORTERO 1:1:5
03.01.16.06 SISTEMA DE DESAGUE LLEGADA
03.01.16.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 107.25 3.62 388.04
03.01.16.06.02 CODO PVC SAL 2"X90° pza 55.00 10.59 582.62
03.01.17 INSTALACION DEL BIODIGESTOR
03.01.17.01 TRABAJOS PRELIMINARES
03.01.17.01.01 LIMPIEZA DE TERRENO MANUAL m2 207.90 0.44 91.68
03.01.17.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 207.90 1.66 344.29
03.01.17.02 MOVIMIENTO DE TIERRAS
03.01.17.02.01 EXCAVACION A MANO TERRENO NORMAL m3 170.94 35.87 6,132.30
03.01.17.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 129.10 26.69 3,446.20
03.01.17.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 213.67 23.12 4,940.26
03.01.17.03 CONCRETO SIMPLE
03.01.17.03.01 SOLADO E=4" m2 35.75 35.71 1,276.70
03.01.17.04 CONCRETO ARMADO
03.01.17.04.01 CONCRETO f'c=175 kg/cm2 m3 39.60 403.97 15,997.01
03.01.17.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.60 40.03 9,951.96
03.01.17.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 306.35 3.92 1,199.36
03.01.17.05 BIODIGESTOR
SUMINISTRO E INSTALACION DE BIODIGESTOR
03.01.17.05.01 und 51.00 701.63 35,783.18
AUTOLIMPIABLE DE PVC DE 600 LTS
SUMINISTRO E INSTALACION DE BIODIGESTOR
03.01.17.05.02 und 4.00 1,188.71 4,754.84
AUTOLIMPIABLE DE PVC DE 1300 LTS
03.01.17.06 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.01.17.06.01 m2 196.35 29.23 5,739.71
MEZCLA 1:2 E=2 cm H=1.5 Max
03.01.17.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
03.01.17.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 55.00 3.62 198.99
SUMINISTRO E INSTALACION DE VALVULA DE PVC DE
03.01.17.07.02 und 55.00 26.87 1,478.07
2"
03.02 LAVADERO INTRADOMICILIARIO (51 UND)
03.02.01 OBRAS PRELIMINARES
03.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 258.06 0.44 113.81
03.02.01.02 TRAZO Y REPLANTEO m2 258.06 1.66 427.35
03.02.02 MOVIMIENTO DE TIERRAS
03.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 57.74 33.73 1,947.69
RELLENO Y COMPACTADO DE ZANJA CON MATERIAL
03.02.02.02 m3 47.43 11.80 559.63
PROPIO CLASIFICADO
03.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.86 23.12 274.21
03.02.03 OBRAS DE CONCRETO ARMADO
03.02.03.01 CONCRETO f'c=175 kg/cm2 m3 5.36 403.97 2,165.26
03.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 170.73 40.03 6,834.66
03.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 201.71 3.92 789.70
03.02.04 MURO DE LADRILLO
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
03.02.04.01 m2 33.72 42.97 1,448.81
Lavaderos)
03.02.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
03.02.05.01 m2 60.13 29.23 1,757.72
MEZCLA 1:2 E=2 cm H=1.5 Max
03.02.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 115.06 26.78 3,081.77
03.02.06 ACCESORIOS Y VALVULAS 0.00
SUMINISTRO E INSTALACION DE LAVADERO
03.02.06.01 und 51.00 122.68 6,256.63
INTRADOMICILIARIA
03.02.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO 0.00
03.02.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 255.00 3.02 768.83
03.03 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
03.03.01 TRABAJOS PRELIMINARES
03.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.44 5.00
03.03.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.66 18.75
03.03.02 MOVIMIENTO DE TIERRAS 0.00
03.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 33.73 92.43
REFINE, NIVELACION Y COMPACTADO EN TERRENO
03.03.02.02 m2 11.32 0.92 10.40
NORMAL
03.03.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 26.55 43.01
03.03.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 23.12 30.98
03.03.03 OBRAS DE CONCRETO SIMPLE
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
03.03.03.01 m2 2.20 44.06 96.94
FROTACHADO C/MEZCLADORA
03.03.04 OBRAS DE CONCRETO ARMADO
03.03.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 3.92 32.69
03.03.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 39.61 162.00
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA
03.03.04.03 m3 0.21 403.97 84.83
LAVADEROS
03.03.05 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
03.03.05.01 m2 2.49 29.66 73.86
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
03.03.05.02 m2 2.11 21.58 45.54
H=1.5 MAX
03.03.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.03.06.01 und 1.00 159.29 159.29
LAVADERO I.E. INICIAL
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
03.03.06.02 und 2.00 128.25 256.50
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
03.03.06.03 und 1.00 51.99 51.99
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
03.03.06.04 und 1.00 43.37 43.37
(INTERIORES), E=0.05
03.03.07 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10,
03.03.07.01 m 12.00 5.72 68.58
P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
03.03.07.02 m 10.00 5.99 59.85
PARA DESAGUE Ø=2"x3 M
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01
03.04
UND)
03.04.01 TRABAJOS PRELIMINARES
03.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.44 5.28
03.04.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.66 19.84
03.04.02 MOVIMIENTO DE TIERRAS
03.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 33.73 94.45
REFINE, NIVELACION Y COMPACTADO EN TERRENO
03.04.02.02 m2 11.98 0.92 11.00
NORMAL
03.04.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 26.55 43.01
03.04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 23.12 32.60
03.04.03 OBRAS DE CONCRETO SIMPLE
CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6")
03.04.03.01 m3 0.06 305.64 18.34
EN LAVADERO C/MEZCLADORA
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
03.04.03.02 m2 2.86 44.06 126.03
FROTACHADO C/MEZCLADORA
03.04.04 OBRAS DE CONCRETO ARMADO
03.04.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 3.92 44.98
03.04.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 39.61 171.50
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA
03.04.04.03 m3 0.31 403.97 125.23
LAVADEROS
03.04.05 ALBAÑILERIA
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
03.04.05.01 m2 0.36 52.27 18.82
Lavaderos)
03.04.06 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
03.04.06.01 m2 3.51 29.66 104.12
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
03.04.06.02 m2 3.29 21.58 71.00
H=1.5 MAX
03.04.07 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
03.04.07.01 und 1.00 159.29 159.29
LAVADERO TIPO I.E. PRIMARIA
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
03.04.07.02 und 2.00 128.25 256.50
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
03.04.07.03 und 1.00 51.99 51.99
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
03.04.07.04 und 1.00 43.37 43.37
(INTERIORES), E=0.05
03.04.08 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA
03.04.08.01 m 12.00 5.72 68.58
CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
03.04.08.02 m 10.00 5.99 59.85
PARA DESAGUE Ø=2"x3 M
04 LOCALIDAD TARACA (55 UND)
04.01 CONSTRUCCION DE CASETA ARRASTRE HIDRAULICO
04.01.01 TRABAJOS PRELIMINARES
04.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 275.00 0.44 121.28
04.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 275.00 1.66 455.40
04.01.02 MOVIMIENTO DE TIERRAS
04.01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 136.95 35.87 4,912.95
04.01.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 24.20 26.69 645.99
04.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 140.80 23.12 3,255.44
04.01.03 CONCRETO SIMPLE
04.01.03.01 CIMIENTO CORRIDO FC=140KG/CM2 + 30‰ P.G.(6") m3 165.00 336.38 55,501.88
04.01.03.02 SOBRECIMIENTO DE 1:8 CEM-HOR 25% P.M.(4") m3 24.20 358.82 8,683.47
04.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 401.50 40.03 16,072.85
04.01.03.04 CONCRETO f'c=175 kg/cm2 m3 17.05 403.97 6,887.60
04.01.04 MURO DE LADRILLO
MURO DE LADRILLO KK CARAVISTA DE 18 HUECOS DE
04.01.04.01 m2 800.80 52.29 41,873.83
SOGA C/M 1:4 x 1.5cm
EMPEDRADO DE PROTECCION CON PIEDRA TAMAÑO 4"-
04.01.04.02 m2 15.40 63.30 974.77
6"
04.01.05 REVOQUES Y ENLUCIDOS
TARRAJEO DE MUROS Y PISOS C/IMPERMEBILIZANTE
04.01.05.01 m2 752.40 14.71 11,064.80
P/CAMARA (UBS arrastre hidraulico)
04.01.05.02 EMBOQUILLADO DE MEZCLA CEMENTO Y ARENA m 12.10 32.90 398.03
04.01.06 PINTURA
PINTURA EN MUROS INTERIORES C/LATEX LAVABLE
04.01.06.01 m2 453.75 10.38 4,708.57
COLOR MARFIL
04.01.07 COBERTURA
COBERTURA CON TEJA ANDINA FIBROCEMENTO
04.01.07.01 ETERNIT(1,14x0.72x0.005m) m2 358.05 59.60 21,339.06

04.01.08 CARPINTERIA METALICA


SUMINISTRO E INSTALACION DE PUERTA METALICA
04.01.08.01 und 55.00 327.37 18,005.13
1.80x0.70m, INCL. MARCO Y PINTADO
04.01.09 CARPINTERIA DE MADERA
VENTANA DE MADERA TORNILLO INC. MALLA
04.01.09.01 m2 9.90 68.31 676.27
MOSQUITERA
04.01.09.02 COBERTURA DE MADERA PARA TECHO und 55.00 88.16 4,848.53
04.01.10 SISTEMA DE AGUA FRIA
04.01.10.01 TUBERIA Ø=1/2" PVC SAP CL-10 m 520.85 3.29 1,710.99
04.01.11 ACCESORIOS PARA SISTEMAS DE AGUA FRIA 0.00
04.01.11.01 TEE PVC-SAP 1/2" pza 110.00 18.77 2,064.15
04.01.11.02 CODO PVC SAP 1/2" pza 330.00 14.03 4,630.23
04.01.11.03 VALVULA DE COMPUERTA DE BRONCE DE 1/2 " pza 110.00 46.13 5,073.75
SUMINISTRO E INSTALACION DE DUCHA INCLUIDO
04.01.11.04 und 55.00 29.77 1,637.46
ACCESORIOS
04.01.12 SISTEMA DE DESAGUE
04.01.12.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 530.75 3.62 1,920.26
04.01.12.02 TUBERIA Ø=4" PVC SAL m 200.75 3.29 659.47
04.01.13 ACCESORIOS PARA SISTEMA DE DESAGUE
04.01.13.01 CODO PVC SAL 2"X90° pza 385.00 10.59 4,078.31
04.01.13.02 CODO 90º REVENTILADO PVC-SAL 2" a 4'' und 55.00 13.98 768.74
04.01.13.03 YEE CON REDUCCION PVC SAL 2" A 4" PVC SAL pza 165.00 14.50 2,392.34
04.01.14 ADITAMIENTOS VARIOS
04.01.14.01 SUMIDEROS DE BRONCE 2" und 55.00 11.03 606.38
04.01.14.02 REGISTRO ROSCADO DE BRONCE DE 2" und 110.00 9.98 1,097.91
INODORO DE LOZA VITRIFICADA COLOR BLANCO
04.01.14.03 und 55.00 132.66 7,296.30
INCLUYE TANQUE
04.01.14.04 ACCESORIOS DE LOZA und 55.00 58.37 3,210.57
SUMINISTRO E INSTALACION DE TUBERIA DE
04.01.14.05 VENTILACION PVC PLATINA DE VENTILACION PVC 2" Y GLB 55.00 26.24 1,442.93
ACCESORIOS
SUMINISTRO E INSTALACION DE LAVATORIO DE LOZA
04.01.14.06 und 55.00 112.13 6,167.21
COLOR BLANCO INCLUIDO ACCESORIOS
SUMINISTRO E INSTALACION DE CAJA DE REGISTRO DE
04.01.14.07 und 110.00 116.90 12,859.11
12"x24"
04.01.15 INSTALACIONES ELECTRICAS
04.01.15.01 SALIDA DE CENTRO DE LUZ pto 55.00 44.23 2,432.43
04.01.15.02 TUBERIA PVC SEL 5/8" m 126.50 3.74 472.48
04.01.15.03 CABLE ELECTRICO TW #14 AWG / 2,5 mm2 m 308.00 2.05 632.02
04.01.15.04 TABLEROS DISTRIBUCION pza 55.00 80.14 4,407.48
04.02 CONSTRUCCION POZO PERCOLADOR
04.02.01 TRABAJOS PRELIMINARES
04.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 172.70 0.44 76.16
04.02.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 172.20 1.66 285.17
04.02.02 MOVIMIENTO DE TIERRAS
04.02.02.01 EXCAVACION A MANO TERRENO NORMAL m3 89.10 35.87 3,196.38
04.02.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 13.20 26.69 352.36
04.02.02.03 FILTRO DE GRAVA CLASIFICADA m3 47.85 80.37 3,845.71
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 111.65 23.12 2,581.46
04.02.03 TAPA DE CONCRETO
04.02.03.01 CONCRETO f'c=175 kg/cm2 m3 9.35 403.97 3,777.08
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 100.10 40.03 4,007.21
04.02.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 1,157.75 3.92 4,532.59
04.02.04 ANILLO DE CONCRETO
04.02.04.01 CONCRETO f'c=140 kg/cm2 +30%PM m3 3.85 320.38 1,233.47
04.02.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 66.00 40.03 2,642.11
04.02.05 MURO DE LADRILLO
MURO DE LADRILLO ARTESANAL AMARRE DE SOGA,
04.02.05.01 m2 229.90 44.05 10,126.18
JUNTA 1.5 CM MORTERO 1:1:5
04.02.06 SISTEMA DE DESAGUE LLEGADA
04.02.06.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 107.25 3.62 388.04
04.02.06.02 CODO PVC SAL 2"X90° pza 55.00 10.59 582.62
04.03 INSTALACION DEL BIODIGESTOR
04.03.01 TRABAJOS PRELIMINARES
04.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 207.90 0.44 91.68
04.03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 207.90 1.66 344.29
04.03.02 MOVIMIENTO DE TIERRAS
04.03.02.01 EXCAVACION A MANO TERRENO NORMAL m3 170.94 35.87 6,132.30
04.03.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO m3 129.10 26.69 3,446.20
04.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 213.67 23.12 4,940.26
04.03.03 CONCRETO SIMPLE
04.03.03.01 SOLADO E=4" m2 35.75 35.71 1,276.70
04.03.04 CONCRETO ARMADO
04.03.04.01 CONCRETO f'c=175 kg/cm2 m3 39.60 403.97 15,997.01
04.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.60 40.03 9,951.96
04.03.04.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 306.35 3.92 1,199.36
04.03.05 BIODIGESTOR
SUMINISTRO E INSTALACION DE BIODIGESTOR
04.03.05.01 und 51.00 701.63 35,783.18
AUTOLIMPIABLE DE PVC DE 600 LTS
SUMINISTRO E INSTALACION DE BIODIGESTOR
04.03.05.02 und 4.00 1,188.71 4,754.84
AUTOLIMPIABLE DE PVC DE 1300 LTS
04.03.06 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.03.06.01 m2 196.35 29.23 5,739.71
MEZCLA 1:2 E=2 cm H=1.5 Max
04.03.07 SUMINISTRO E INSTALACIÓN DE TUBERIA
04.03.07.01 TUBERIA DE PVC SAL PARA DESAGUE Ø=2" m 55.00 3.62 198.99
04.03.07.02 SUMINISTRO E INSTALACION DE VALVULA DE PVC DE 2" und 55.00 26.87 1,478.07
04.04 LAVADERO INTRADOMICILIARIO (51 UND)
04.04.01 OBRAS PRELIMINARES
04.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 258.06 0.44 113.81
04.04.01.02 TRAZO Y REPLANTEO m2 258.06 1.66 427.35
04.04.02 MOVIMIENTO DE TIERRAS
04.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 57.74 33.73 1,947.69
RELLENO Y COMPACTADO DE ZANJA CON MATERIAL
04.04.02.02 m3 47.43 11.80 559.63
PROPIO CLASIFICADO
04.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 11.86 23.12 274.21
04.04.03 OBRAS DE CONCRETO ARMADO
04.04.03.01 CONCRETO f'c=175 kg/cm2 m3 5.36 403.97 2,165.26
04.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 170.73 40.03 6,834.66
04.04.03.03 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 201.71 3.92 789.70
04.04.04 MURO DE LADRILLO
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
04.04.04.01 m2 33.72 42.97 1,448.81
Lavaderos)
04.04.05 REVOQUES Y ENLUCIDOS
TARRAJEO INTERIOR CON IMPERMEABILIZANTE
04.04.05.01 m2 60.13 29.23 1,757.72
MEZCLA 1:2 E=2 cm H=1.5 Max
04.04.05.02 TARRAJEO EXTERIOR CON MEZCLA 1:4 E=1.5 cm m2 115.06 26.78 3,081.77
04.04.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE LAVADERO
04.04.06.01 und 51.00 122.68 6,256.63
INTRADOMICILIARIA
04.04.07 TUBERIA PVC ISO 4422 1/2" - INTRADOMICILIARIO
04.04.07.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 1/2" m 255.00 3.02 768.83
04.05 LAVADERO TIPO I.E. NIÑOS MENORES, I.E. INICIAL (01 UND)
04.05.01 TRABAJOS PRELIMINARES
04.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.32 0.44 5.00
04.05.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.32 1.66 18.75
04.05.02 MOVIMIENTO DE TIERRAS
04.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.74 33.73 92.43
REFINE, NIVELACION Y COMPACTADO EN TERRENO
04.05.02.02 m2 11.32 0.92 10.40
NORMAL
04.05.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 26.55 43.01
04.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.34 23.12 30.98
04.05.03 OBRAS DE CONCRETO SIMPLE
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
04.05.03.01 m2 2.20 44.06 96.94
FROTACHADO C/MEZCLADORA
04.05.04 OBRAS DE CONCRETO ARMADO
04.05.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 8.35 3.92 32.69
04.05.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.09 39.61 162.00
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA
04.05.04.03 m3 0.21 403.97 84.83
LAVADEROS
04.05.05 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
04.05.05.01 m2 2.49 29.66 73.86
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
04.05.05.02 m2 2.11 21.58 45.54
H=1.5 MAX
04.05.06 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.05.06.01 und 1.00 159.29 159.29
LAVADERO I.E. INICIAL
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
04.05.06.02 und 2.00 128.25 256.50
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
04.05.06.03 und 1.00 51.99 51.99
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
04.05.06.04 und 1.00 43.37 43.37
(INTERIORES), E=0.05
04.05.07 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002:2009 C-10,
04.05.07.01 m 12.00 5.72 68.58
P/AGUA POTABLE CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
04.05.07.02 m 10.00 5.99 59.85
PARA DESAGUE Ø=2"x3 M
LAVADERO TIPO I.E. NIÑOS MENORES, I.E. PRIMARIA (01
04.06
UND)
04.06.01 TRABAJOS PRELIMINARES
04.06.01.01 LIMPIEZA DE TERRENO MANUAL m2 11.98 0.44 5.28
04.06.01.02 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS m2 11.98 1.66 19.84
04.06.02 MOVIMIENTO DE TIERRAS
04.06.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.80 33.73 94.45
REFINE, NIVELACION Y COMPACTADO EN TERRENO
04.06.02.02 m2 11.98 0.92 11.00
NORMAL
04.06.02.03 RELLENO CON MATERIAL PROPIO m3 1.62 26.55 43.01
04.06.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dp=30m m3 1.41 23.12 32.60
04.06.03 OBRAS DE CONCRETO SIMPLE
CIMIENTO CORRIDO f'c=140 kg/cm2 + 30% P.M. (TMN6")
04.06.03.01 m3 0.06 305.64 18.34
EN LAVADERO C/MEZCLADORA
VEREDA DE CONCRETO f'c=140 kg/cm2, E=0.10M,
04.06.03.02 m2 2.86 44.06 126.03
FROTACHADO C/MEZCLADORA
04.06.04 OBRAS DE CONCRETO ARMADO
04.06.04.01 ACERO f'y = 4200 kg/cm2, GRADO 60 kg 11.49 3.92 44.98
04.06.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 4.33 39.61 171.50
CONCRETO F'C=175 KG/CM2 C/MEZCLADORA PARA
04.06.04.03 m3 0.31 403.97 125.23
LAVADEROS
04.06.05 ALBAÑILERIA
MURO DE SOGA, JUNTA 1.5 cm MORTERO 1:5 (En
04.06.05.01 m2 0.36 52.27 18.82
Lavaderos)
04.06.06 REVOQUES Y REVESTIMIENTOS
TARRAJEO CON IMPERMEABILIZANTE; MEZCLA 1:2 E=2
04.06.06.01 m2 3.51 29.66 104.12
cm, H=1.5 MAX
TARRAJEO EN EXTERIORES, MEZ. C:A 1:4, E=1.5 cm,
04.06.06.02 m2 3.29 21.58 71.00
H=1.5 MAX
04.06.07 ACCESORIOS Y VALVULAS
SUMINISTRO E INSTALACION DE ACCESORIOS EN
04.06.07.01 und 1.00 159.29 159.29
LAVADERO TIPO I.E. PRIMARIA
TAPA SANITARIA DE ALUMINIO DE 0.30x0.30m CON
04.06.07.02 und 2.00 128.25 256.50
LLAVE TIPO BUJIA
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.30m
04.06.07.03 und 1.00 51.99 51.99
(INTERIORES), E=0.05
CAJA DE CONCRETO PRE FABRICADO 0.30x0.30x0.25m
04.06.07.04 und 1.00 43.37 43.37
(INTERIORES), E=0.05
04.06.08 TUBERIA PVC INTRADOMICILIARIO
INSTALACION DE TUBERIA PVC NTP 399.002 PARA AGUA
04.06.08.01 m 12.00 5.72 68.58
CLASE 10 Ø=1/2", 5.0 M
INSTALACION DE TUBERIA PVC SAL NTP 399.003:2007
04.06.08.02 m 10.00 5.99 59.85
PARA DESAGUE Ø=2"x3 M

01 LOCALIDAD SANTA LUCIA


CAPACITACION EN EDUCACION SANITARIA, PROMOCION
01.01
DE LA SALUD Y AOM
01.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
TALLER IMPORTANCIA DE LA ORGANIZACION Y
01.01.01.01 Tall 1.00 846.54 846.54
PARTICIPACION CIUDADANA
01.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 846.54 846.54
EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y
01.01.02
SALUD)
TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y
01.01.02.01 Tall 1.00 846.55 846.55
SALUD (Valoracion del agua)
TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION
01.01.02.02 Tall 1.00 846.55 846.55
DE EXCRETAS
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS
01.01.02.03 AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL Tall 1.00 846.55 846.55
HOGAR Y COMUNAL
CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y
01.01.02.04 Tall 1.00 846.55 846.55
COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE.
DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y
01.01.02.05 Men 2.00 76.27 152.53
SANEAMIENTO (SPOT PUBLICITARIO)
01.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION
01.01.03.01 Tall 1.00 846.55 846.55
DE PLAN OPERATIVO ANUAL DE LA JASS
TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL
01.01.03.02 SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA Tall 1.00 846.55 846.55
POTABLE
01.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 846.55 846.55
TALLER DE CLORACION Y DESINFECCION DE AGUA
01.01.03.04 Tall 1.00 999.10 999.10
PARA CONSUMO HUMANO
01.02 FLETE
01.02.01 FLETE RURAL
01.02.01.01 FLETE RURAL GLB 1.00 22,856.01 22,856.01
01.02.02 FLETE TERRESTRE
01.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,252.50 4,252.50
01.02.02.02 FLETE TERRESTRE GLB 1.00 9,518.64 9,518.64
01.03 MITIGACION AMBIENTAL
01.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,556.00 2,556.00

PROGRAMA DE CONSERVACION, RESTAURACION Y


01.03.02 GLB 1.00 1,540.80 1,540.80
COMPESACION DE COBERTURA VEGETAL (REFORESTACION)

01.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,060.00 3,060.00


01.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 900.00 900.00

01.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 450.00 450.00

01.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,240.00 3,240.00


01.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 540.00 540.00
01.04 CONTROL Y SEGURIDAD EN OBRA 0.00
01.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 6,263.71 6,263.71
02 LOCALIDAD PUEBLO LIBRE
CAPACITACION EN EDUCACION SANITARIA, PROMOCION
02.01
DE LA SALUD Y AOM
02.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
TALLER IMPORTANCIA DE LA ORGANIZACION Y
02.01.01.01 Tall 1.00 846.54 846.54
PARTICIPACION CIUDADANA
02.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 846.54 846.54
EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y
02.01.02
SALUD)
TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y
02.01.02.01 Tall 1.00 846.55 846.55
SALUD (Valoracion del agua)
TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION
02.01.02.02 Tall 1.00 846.55 846.55
DE EXCRETAS
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS
02.01.02.03 AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL Tall 1.00 846.55 846.55
HOGAR Y COMUNAL
CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y
02.01.02.04 Tall 1.00 846.55 846.55
COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE.
DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y
02.01.02.05 Men 2.00 76.27 152.53
SANEAMIENTO (SPOT PUBLICITARIO)
02.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION
02.01.03.01 Tall 1.00 846.55 846.55
DE PLAN OPERATIVO ANUAL DE LA JASS
TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL
02.01.03.02 SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA Tall 1.00 846.55 846.55
POTABLE
02.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 846.55 846.55
TALLER DE CLORACION Y DESINFECCION DE AGUA
02.01.03.04 Tall 1.00 999.10 999.10
PARA CONSUMO HUMANO
02.02 FLETE
02.02.01 FLETE RURAL
02.02.01.01 FLETE RURAL GLB 1.00 31,395.62 31,395.62
02.02.02 FLETE TERRESTRE 0.00
02.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,252.50 4,252.50
02.02.02.02 FLETE TERRESTRE GLB 1.00 15,605.08 15,605.08
02.02.03 MITIGACION AMBIENTAL
02.02.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,556.00 2,556.00

PROGRAMA DE CONSERVACION, RESTAURACION Y


02.02.03.02 GLB 1.00 1,540.80 1,540.80
COMPESACION DE COBERTURA VEGETAL (REFORESTACION)

02.02.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,060.00 3,060.00


02.02.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 900.00 900.00
PROGRAMA DE CAPACITACION Y EDUCACION
02.02.03.05 GLB 1.00 450.00 450.00
AMBIENTAL
02.02.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,240.00 3,240.00
02.02.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 540.00 540.00
02.02.04 CONTROL Y SEGURIDAD EN OBRA
02.02.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 8,299.22 8,299.22
03 LOCALIDAD TANCARPATA
CAPACITACION EN EDUCACION SANITARIA, PROMOCION
03.01
DE LA SALUD Y AOM
03.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
TALLER IMPORTANCIA DE LA ORGANIZACION Y
03.01.01.01 Tall 1.00 846.54 846.54
PARTICIPACION CIUDADANA
03.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 846.54 846.54
EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y
03.01.02
SALUD)
TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y
03.01.02.01 Tall 1.00 846.55 846.55
SALUD (Valoracion del agua)
TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION
03.01.02.02 Tall 1.00 846.55 846.55
DE EXCRETAS
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS
03.01.02.03 AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL Tall 1.00 846.55 846.55
HOGAR Y COMUNAL
CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y
03.01.02.04 Tall 1.00 846.55 846.55
COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE.
DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y
03.01.02.05 Men 2.00 76.27 152.53
SANEAMIENTO (SPOT PUBLICITARIO)
03.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION
03.01.03.01 Tall 1.00 846.55 846.55
DE PLAN OPERATIVO ANUAL DE LA JASS
TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL
03.01.03.02 SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA Tall 1.00 846.55 846.55
POTABLE
03.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 846.55 846.55
TALLER DE CLORACION Y DESINFECCION DE AGUA
03.01.03.04 Tall 1.00 999.10 999.10
PARA CONSUMO HUMANO
03.02 FLETE
03.02.01 FLETE RURAL
03.02.01.01 FLETE RURAL GLB 1.00 13,814.07 13,814.07
03.02.02 FLETE TERRESTRE
03.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,252.50 4,252.50
03.02.02.02 FLETE TERRESTRE GLB 1.00 6,177.97 6,177.97
03.03 MITIGACION AMBIENTAL
03.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,556.00 2,556.00

PROGRAMA DE CONSERVACION, RESTAURACION Y


03.03.02 GLB 1.00 1,540.80 1,540.80
COMPESACION DE COBERTURA VEGETAL (REFORESTACION)

03.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,060.00 3,060.00


03.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 900.00 900.00

03.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 450.00 450.00

03.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,240.00 3,240.00


03.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 540.00 540.00
03.04 CONTROL Y SEGURIDAD EN OBRA
03.04.01 IMPLEMENTOS DE SEGURIDAD GLB 1.00 4,108.46 4,108.46
04 LOCALIDAD TARACA
CAPACITACION EN EDUCACION SANITARIA, PROMOCION
04.01
DE LA SALUD Y AOM
04.01.01 FORTALECIMIENTO DE LA ORANIZACION COMUNAL
TALLER IMPORTANCIA DE LA ORGANIZACION Y
04.01.01.01 Tall 1.00 846.54 846.54
PARTICIPACION CIUDADANA
04.01.01.02 TALLER DE ESTATUTOS Y REGLAMENTOS Tall 1.00 846.54 846.54
EDUCACION SANITARIA (EDUCACION PARA LA HIGIENE Y
04.01.02
SALUD)
TALLER IMPORTANCIA DEL AGUA PARA LA VIDA Y
04.01.02.01 Tall 1.00 846.55 846.55
SALUD (Valoracion del agua)
TALLER DE IMPORTANCIA DE LA DECUADA ELIMINACION
04.01.02.02 Tall 1.00 846.55 846.55
DE EXCRETAS
TALLER DE PREVENCION DE ENFERMEDADES LIGADAS
04.01.02.03 AL SANEAMIENTO Y HABITOS DE HIGIENE PERSONAL DEL Tall 1.00 846.55 846.55
HOGAR Y COMUNAL
CONSTITUCION DEL COMITE DE HIGIENE DEL HOGAR Y
04.01.02.04 Tall 1.00 846.55 846.55
COMUNAL, CAMPAÑA DE SALUD E HIGIENE EN LA II.EE.
DIFUSION MENSAJES EDUCATIVOS SOBRE AGUA Y
04.01.02.05 Men 2.00 76.27 152.53
SANEAMIENTO (SPOT PUBLICITARIO)
04.01.03 OPERACION Y MANTENIMIENTO DEL SISTEMA
TALLER DE ADMINIST., CONTABILIDAD Y FORMULACION
04.01.03.01 Tall 1.00 846.55 846.55
DE PLAN OPERATIVO ANUAL DE LA JASS
TALLER RECONOCIMIENTO DE LOS COMPONENTES DEL
04.01.03.02 SISTEMA Y OPERACION Y MANTENEMIENTO SIST. AGUA Tall 1.00 846.55 846.55
POTABLE
04.01.03.03 TALLER DE OPERACION MANTENIMIENTO DE UBS Tall 1.00 846.55 846.55
TALLER DE CLORACION Y DESINFECCION DE AGUA
04.01.03.04 Tall 1.00 999.10 999.10
PARA CONSUMO HUMANO
04.02 FLETE
04.02.01 FLETE RURAL
04.02.01.01 FLETE RURAL GLB 1.00 13,814.09 13,814.09
04.02.02 FLETE TERRESTRE
04.02.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 4,252.09 4,252.09
04.02.02.02 FLETE TERRESTRE GLB 1.00 6,635.52 6,635.52
04.03 MITIGACION AMBIENTAL
04.03.01 PLAN DE MANEJO AMBIENTAL GLB 1.00 2,556.00 2,556.00

PROGRAMA DE CONSERVACION, RESTAURACION Y


04.03.02 GLB 1.00 1,540.99 1,540.99
COMPESACION DE COBERTURA VEGETAL (REFORESTACION)

04.03.03 PLAN DE CONTINGENCIAS Y SEGURIDAD GLB 1.00 3,060.00 3,060.00


04.03.04 PROGRAMA DE GESTION SOCIAL GLB 1.00 900.00 900.00

04.03.05 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL GLB 1.00 450.00 450.00

04.03.06 PLAN DE MONITOREO AMBIENTAL GLB 1.00 3,240.00 3,240.00


04.03.07 PROGRAMA DE CIERRE O ABANDONO GLB 1.00 540.00 540.00
04.04 CONTROL Y SEGURIDAD EN OBRA
04.04.01 IMPLEMENTOS DE SEGURIDAD PUEBLO LIBRE GLB 1.00 3,306.99 3,306.99

COSTO DIRECTO 4,608,717.082


GASTOS GENERALES 368,697.37
UTILIDAD (7%) 322,610.20
==================
SUB TOTAL 5,300,024.64
IGV (18%) 954,004.44
==================
PRESUPUESTO DE OB 6,254,029.08