CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

OBRA
“MEJORAMIENTO DE LA VIA VEHICULAR Y PEATONAL EN LA CALLE LOS ULCUMANOS, CALLE LOS CAUCHOS, CALLE LAS PALMERAS, CALLE
LOS ROBLES Y PASAJE ACHAHUASCA, URB. CAPELO - LA MERCED, PROVINCIA DE CHANCHAMAYO – JUNIN” – TERCERA ETAPA – (META: JR.
LOS CAUCHOS DESDE EL JR. LOS ROBLES L=0+135.29 KMS)

UBICACIÓN MUNICIPALIDAD PROVINCIAL DE CHANCHAMAYO


FECHA MARZO 2017
PLAZ. EJEC. 60 DIAS CALENDARIOS COSTO DE OBRA S/. 332,853.47 Inc. I.G.V.

PLAZO DE EJECUCION
CODIGO DESCRIPCION TOTAL
COSTO 1ra QUINCENA 2da QUINCENA 3ra QUINCENA 4ta QUINCENA (15
PRESUPUESTO (15 Dias) (15 Dias) (15 Dias) Dias)
01 OBRAS PROVISIONALES 6,626.42 6,626.42 6,626.42
02 PAVIMENTO
02.01 TRABAJOS PRELIMINARES 1,699.10 339.82 509.73 509.73 339.82 1,699.10
02.02 MOVIMIENTO DE TIERRAS 8,596.54 2,578.96 2,578.96 2,578.96 859.65 8,596.54
02.03 PAVIMENTO RIGIDO F'C=210KG/CM2 103,517.52 20,703.50 31,055.26 31,055.26 20,703.50 103,517.52
02.04 VARIOS 1,668.98 1,668.98 1,668.98
03. DRENAJE PLUVIAL SUPERFICIAL
03.01 CUNETAS LATERALES 42,732.52 4,273.25 12,819.76 12,819.76 12,819.76 42,732.52
03.02 CUNETAS DE CRUCE DE VIAS 1,373.20 137.32 411.96 411.96 411.96 1,373.20
04 VEREDAS RAMPAS Y MARTILLOS
04.01 TRABAJOS PRELIMINARES 918.41 91.84 367.36 459.21 918.41
04.02 MOVIMIENTO DE TIERRAS 9,242.54 1,848.51 3,697.02 3,697.02 9,242.54
04.03 RAMPA 182.54 182.54 182.54
04.04 VEREDAS Y MARTILLOS 35,247.67 14,099.07 14,099.07 7,049.53 35,247.67
04.05 VARIOS 840.00 840.00 840.00
05 CONSTRUCCION DE SARDINEL
05.01 TRABAJOS PRELIMINARES 92.50 92.50 92.50
05.02 MOVIMIENTO DE TIERRAS 1,364.73 272.95 1,091.78 1,364.73
05.03 CONCRETO ENSARDINEL 15,283.88 7,641.94 7,641.94 15,283.88
06 AREAS VERDES 617.43 617.43 617.43
07 SENALIZACION 8,179.88 8,179.88 8,179.88
07 VARIOS 866.32 346.53 519.79 866.32

TOTAL COSTO DIRECTO 239,050.18 34,659.28 65,084.06 73,893.03 65,413.82 239,050.18

G.G 10.00% 23,905.02 3,465.93 6,508.41 7,389.30 6,541.38 23,905.02


UTILIDAD 8.00% 19,124.01 2,772.74 5,206.72 5,911.44 5,233.11 19,124.01
SUB TOTAL 282,079.21 40,897.95 76,799.19 87,193.77 77,188.31 282,079.21
CRONOGRAMA VALORIZADO DE AVANCE DE OBRA
OBRA
“MEJORAMIENTO DE LA VIA VEHICULAR Y PEATONAL EN LA CALLE LOS ULCUMANOS, CALLE LOS CAUCHOS, CALLE LAS PALMERAS, CALLE
LOS ROBLES Y PASAJE ACHAHUASCA, URB. CAPELO - LA MERCED, PROVINCIA DE CHANCHAMAYO – JUNIN” – TERCERA ETAPA – (META: JR.
LOS CAUCHOS DESDE EL JR. LOS ROBLES L=0+135.29 KMS)

UBICACIÓN MUNICIPALIDAD PROVINCIAL DE CHANCHAMAYO


FECHA MARZO 2017
PLAZ. EJEC. 60 DIAS CALENDARIOS COSTO DE OBRA S/. 332,853.47 Inc. I.G.V.

IGV 18% 18.00% 50,774.26 7,361.63 13,823.85 15,694.88 13,893.89 50,774.26


PRESUPUESTO TOTAL 332,853.47 48,259.58 90,623.04 102,888.65 91,082.20 332,853.47

PORCENTAJE DE AVANCE 14.50% 27.23% 30.91% 27.36% 100.00%


CRONOGRAMA DE DESEMBOLSOS MENSUALES

OBRA “MEJORAMIENTO DE LA VIA VEHICULAR Y PEATONAL EN LA CALLE LOS ULCUMANOS, CALLE LOS CAUCHOS,
CALLE LAS PALMERAS, CALLE LOS ROBLES Y PASAJE ACHAHUASCA, URB. CAPELO - LA MERCED, PROVINCIA DE
CHANCHAMAYO – JUNIN” – TERCERA ETAPA – (META: JR. LOS CAUCHOS DESDE EL JR. LOS ROBLES L=0+135.29
KMS)

UBICACIÓN MUNICIPALIDAD PROVINCIAL DE CHANCHAMAYO


VALOR REFERENCIAL S/. 332,853.47
FECHA MARZO 2017 TIEMP. EJEC: 60 DIAS CALENDARIOS

ADELANTOS AMORTIZACIONES TOTAL A PAGAR


MES VALORIZACION REAJUSTE
DIRECTOS MATERIALES DIRECTOS MATERIALES No Inc. IGV.

33,285.35 66,570.69 -.- -.- -.- -.- 99,856.04


1 -.- -.- 48,259.58 965.19 4,825.96 9,651.92 34,746.90
2 -.- -.- 90,623.04 1,812.46 9,062.30 18,124.61 65,248.59
3 -.- -.- 102,888.65 2,057.77 10,288.86 20,577.73 74,079.83
4 -.- -.- 91,082.20 1,821.64 9,108.22 18,216.44 65,579.18

TOTAL 33,285.35 66,570.69 332,853.47 6,657.07 33,285.35 66,570.69 339,510.53

COSTO DEL PRESUPUESTO BASE Inc. I.G.V. S/ 332,853.47

COSTO DEL REAJUSTE AL CRONOGRAMA Inc. IGV. S/ 339,510.54


CALENDARIO DE ADQUISICION DE MATERIALES
Proyecto

“MEJORAMIENTO DE LA VIA VEHICULAR Y PEATONAL EN LA CALLE LOS ULCUMANOS, CALLE LOS CAUCHOS, CALLE LAS PALMERAS, CALLE LOS ROBLES Y PASAJE ACHAHUASCA, URB. CAPELO - LA MERCED,
PROVINCIA DE CHANCHAMAYO – JUNIN” – TERCERA ETAPA – (META: JR. LOS CAUCHOS DESDE EL JR. LOS ROBLES L=0+135.29 KMS)

Region :JUNIN Provincia : CHANCHAMAYO Distrito : CHANCHAMAYO

DESCRIPCION UNID CANTIDAD PRECIO PARCIAL PAVIMENTO RIGIDO


1ra Quincena 2da Quincena 3ra Quincena 4ta Quincena
MANO DE OBRA
% CANTIDAD MONTO % CANTIDAD MONTO % CANTIDAD MONTO % CANTIDAD MONTO
TOPOGRAFO hh 30.5900 18.36 561.60 14.50% 4.44 81.42 27.23% 8.33 152.90 30.91% 9.46 173.60 27.36% 8.37 153.68
OPERARIO hh 944.2200 18.36 17,335.82 14.50% 136.90 2,513.48 27.23% 257.07 4,719.87 30.91% 291.87 5,358.69 27.36% 258.38 4,743.78
OFICIAL hh 576.3200 15.39 8,869.62 14.50% 83.56 1,285.98 27.23% 156.91 2,414.85 30.91% 178.15 2,741.70 27.36% 157.70 2,427.09
PEON hh 2,870.6000 13.84 39,729.15 14.50% 416.20 5,760.23 27.23% 781.55 10,816.70 30.91% 887.33 12,280.71 27.36% 785.51 10,871.51
SUB TOTAL MANO DE OBRA 66,496.19 9,641.11 18,104.32 20,554.70 18,196.05
MES 01 MES 02 MES 03 MES 04
MATERIALES
% CANTIDAD MONTO % CANTIDAD MONTO % CANTIDAD MONTO % CANTIDAD MONTO
ALAMBRE NEGRO RECOCIDO # 16 kg 8.7000 3.50 30.45 50.00% 4.35 15.23 50.00% 4.35 15.23
CLAVOS PARA MADERA C/C 3" kg 78.0800 3.50 273.29 100.00% 78.08 273.29
ALAMBRE NEGRO N°16 kg 47.6100 3.50 166.63 100.00% 47.61 166.63
REJILLA EN CUNETAS (INCL.INSTALACION) m 136.9000 250.00 34,225.00 40.00% 54.76 13,690.00 30.00% 41.07 10,267.50 30.00% 41.07 10,267.50
FIERRO LISO DE 5/8" m 676.2000 3.50 2,366.70 10.00% 67.62 236.67 30.00% 202.86 710.01 30.00% 202.86 710.01 30.00% 202.86 710.01
CLAVOS 2" A 4" kg 3.7000 3.50 12.95 40.00% 1.48 5.18 60.00% 2.22 7.77
ACERO CORRUGADO 1/2" kg 30.0000 3.50 105.00 20.00% 6.00 21.00 20.00% 6.00 21.00 30.00% 9.00 31.50 30.00% 9.00 31.50
ACERO CORRUGADO 0 3/8" kg 70.0000 3.50 245.00 20.00% 14.00 49.00 20.00% 14.00 49.00 30.00% 21.00 73.50 30.00% 21.00 73.50
PLANTAS HORNAMENTALES und 8.1700 12.00 98.06 100.00% 8.17 98.06
ARENA FINA (PUESTO EN OBRA) m3 12.0300 42.00 505.39 40.00% 4.81 202.16 30.00% 3.61 151.62 30.00% 3.61 151.62
TIERRA DE CHACRA O VEGETAL m3 4.0800 25.00 102.05 100.00% 4.08 102.05
PIEDRA CHANCADA DE 1/2" (PUESTO EN OBRA) m3 192.9000 50.84 9,806.99 20.00% 38.58 1,961.40 20.00% 38.58 1,961.40 30.00% 57.87 2,942.10 30.00% 57.87 2,942.10
ARENA GRUESA (PUESTO EN OBRA) m3 208.8000 40.68 8,494.04 20.00% 41.76 1,698.81 20.00% 41.76 1,698.81 30.00% 62.64 2,548.21 30.00% 62.64 2,548.21
MATERIAL CLASIFICADO PARA BASE (PUESTO EN m3 322.9100 38.00 12,270.75 20.00% 64.58 2,454.15 30.00% 96.87 3,681.23 20.00% 64.58 2,454.15 30.00% 96.87 3,681.23
OBRA)
CEMENTO PORTLAND TIPO I (42.5KG) BOL 3,418.2200 19.06 65,151.25 20.00% 683.64 13,030.25 30.00% 1,025.47 19,545.38 30.00% 1,025.47 19,545.38 20.00% 683.64 13,030.25
TECKNOPORT DE 1" m2 155.3000 4.50 698.83 30.00% 46.59 209.65 30.00% 46.59 209.65 20.00% 31.06 139.77 20.00% 31.06 139.77
MOVILIZACION Y DESMOVILIZACION GLB 1.0000 3,738.00 3,738.00 50.00% 0.50 1,869.00 50.00% 0.50 1,869.00
HORMIGON (PUESTO EN OBRA) m3 0.5100 38.00 19.38 100.00% 0.51 19.38
ALQUILER DE ALMACEN Y OFICINA mes 2.0000 450.00 900.00 25.00% 0.50 225.00 25.00% 0.50 225.00 25.00% 0.50 225.00 25.00% 0.50 225.00
AGUA m3 270.3000 5.00 1,351.50 25.00% 67.58 337.88 25.00% 67.58 337.88 25.00% 67.58 337.88 25.00% 67.58 337.88
CALENDARIO DE ADQUISICION DE MATERIALES
Proyecto

“MEJORAMIENTO DE LA VIA VEHICULAR Y PEATONAL EN LA CALLE LOS ULCUMANOS, CALLE LOS CAUCHOS, CALLE LAS PALMERAS, CALLE LOS ROBLES Y PASAJE ACHAHUASCA, URB. CAPELO - LA MERCED,
PROVINCIA DE CHANCHAMAYO – JUNIN” – TERCERA ETAPA – (META: JR. LOS CAUCHOS DESDE EL JR. LOS ROBLES L=0+135.29 KMS)

Region :JUNIN Provincia : CHANCHAMAYO Distrito : CHANCHAMAYO

DESCRIPCION UNID CANTIDAD PRECIO PARCIAL PAVIMENTO RIGIDO


IMPRESION DE BANER m2 36.0000 8.48 305.28 100.00% 36.00 305.28
CARTEL DE SEÑALIZACION (SEGUN DISEÑO) und 3.0000 450.00 1,350.00 100.00% 3.00 1,350.00
MADERA NACIONAL P/ENCOFRADO-CARP p2 39.2000 3.20 125.44 100.00% 39.20 125.44
YESO DE 28 Kg BOL 4.9600 15.00 74.41 50.00% 2.48 37.21 50.00% 2.48 37.21
MADERA TORNILLO p2 122.5000 4.20 514.50 50.00% 61.25 257.25 50.00% 61.25 257.25
MADERA PARA ENCOFRADO p2 600.5200 3.20 1,921.67 30.00% 180.16 576.50 70.00% 420.36 1,345.17
TRIPLAY DE 6 MM m2 8.8100 13.68 120.49 50.00% 4.41 60.25 50.00% 4.41 60.25
GRASA AMARILLA kg 1.4500 10.00 14.49 100.00% 1.45 14.49
PERNO DE 5/8" Y CON TUERCA Y HUACHA DE 5" und 12.0000 2.20 26.40 100.00% 12.00 26.40
ASFALTO RC-250 gln 191.5200 11.50 2,202.47 100.00% 191.52 2,202.47
KEROSENE gln 19.9000 15.00 298.50 100.00% 19.90 298.50
LEÑA kg 79.6000 0.60 47.76 100.00% 79.60 47.76
LIJA PARA MADERA und 3.0000 1.20 3.60 100.00% 3.00 3.60
THINER gln 40.0200 20.00 800.44 100.00% 40.02 800.44
PINTURA ESMALTE PARA TRAFICO gln 0.3200 35.00 11.20 100.00% 0.32 11.20
PINTURA ESMALTE gln 60.0300 35.00 2,101.16 100.00% 60.03 2,101.16
DISOLVENTE XILOL gln 7.4800 35.00 261.80 100.00% 7.48 261.80
PINTURA P/TRANSITO gln 11.2200 55.00 617.10 100.00% 11.22 617.10
TEKNOPORT DE 1" pln 25.8800 29.00 750.59 25.00% 6.47 187.65 25.00% 6.47 187.65 25.00% 6.47 187.65 25.00% 6.47 187.65
GRAS NATURAL m2 33.0000 7.50 247.51 100.00% 33.00 247.51
TACHOS DE BASURA (SEGUN DISEÑO) und 2.0000 420.00 840.00 100.00% 2.00 840.00

TUBERIA PVC SAP CLASE 5 (PARA CONEXION EN


m 676.2000 2.50 1,690.50 25.00% 169.05 422.63 25.00% 169.05 422.63 25.00% 169.05 422.63 25.00% 169.05 422.63
LOSAS}

SUB TOTAL MATERIALES 154,886.57 25,894.70 42,941.77 41,759.74 44,290.36

MES 01 MES 02 MES 03 MES 04


EQUIPOS
% CANTIDAD MONTO % CANTIDAD MONTO % CANTIDAD MONTO % CANTIDAD MONTO
HERRAMIENTAS MANUALES %MO 1,624.89 14.50% 0.00 235.59 27.23% 0.00 442.39 30.91% 0.00 502.27 27.36% 0.00 444.64
CORTADORA DE CONCRETO 23HP hm 2.2500 35.00 78.58 40.00% 0.90 31.43 25.00% 0.56 19.65 40.00% 0.90 31.43
MEZCLADORA hm 55.6300 20.00 1,112.65 25.00% 13.91 278.16 25.00% 13.91 278.16 25.00% 13.91 278.16 25.00% 13.91 278.16
CALENDARIO DE ADQUISICION DE MATERIALES
Proyecto

“MEJORAMIENTO DE LA VIA VEHICULAR Y PEATONAL EN LA CALLE LOS ULCUMANOS, CALLE LOS CAUCHOS, CALLE LAS PALMERAS, CALLE LOS ROBLES Y PASAJE ACHAHUASCA, URB. CAPELO - LA MERCED,
PROVINCIA DE CHANCHAMAYO – JUNIN” – TERCERA ETAPA – (META: JR. LOS CAUCHOS DESDE EL JR. LOS ROBLES L=0+135.29 KMS)

Region :JUNIN Provincia : CHANCHAMAYO Distrito : CHANCHAMAYO

DESCRIPCION UNID CANTIDAD PRECIO PARCIAL PAVIMENTO RIGIDO


MEZCLADORA CONCRETO TAMBOR 11 P3-18 HP hm 89.7000 20.00 1,794.08 25.00% 22.43 448.52 25.00% 22.43 448.52 25.00% 22.43 448.52 25.00% 22.43 448.52
CAMION VOLQUETE 12 M3. hm 27.9500 95.00 2,655.66 25.00% 6.99 663.92 25.00% 6.99 663.92 25.00% 6.99 663.92 25.00% 6.99 663.92
CAMION CISTERNA REGADOR hm 5.5100 100.00 551.27 25.00% 1.38 137.82 25.00% 1.38 137.82 25.00% 1.38 137.82 25.00% 1.38 137.82
COMPRESORA NEUMATICA 76 HP 125-175 PCM hm 2.2500 80.00 179.62 25.00% 0.56 44.91 25.00% 0.56 44.91 25.00% 0.56 44.91 25.00% 0.56 44.91
BARRENOS hm 4.4900 12.50 56.13 50.00% 2.25 28.07 25.00% 1.12 14.03 25.00% 1.12 14.03
RODILLO LISO VIBR AUTOP 210HP 19-23T hm 5.5100 135.00 744.21 25.00% 1.38 186.05 25.00% 1.38 186.05 25.00% 1.38 186.05 25.00% 1.38 186.05
CARGADOR S/LLANTAS 125-155 HP 3 YD3. hm 27.9500 144.07 4,027.38 25.00% 6.99 1,006.85 25.00% 6.99 1,006.85 25.00% 6.99 1,006.85 25.00% 6.99 1,006.85
TRACTOR DE ORUGAS DE 335 HP hm 10.4000 186.45 1,938.52 20.00% 25.00% 2.60 484.63 25.00% 2.60 484.63 30.00% 3.12 581.56
COCINA DE ASFALTO 320 GLNS hm 4.8600 48.50 235.50 100.00% 4.86 235.50
MARTILLO NEUMATICO DE 24 Kg. hm 4.4900 4.95 22.23 25.00% 1.12 5.56 25.00% 1.12 5.56 25.00% 1.12 5.56 25.00% 1.12 5.56
VIBRADOR DE CONCRETO 4 HP 1.35" hm 44.8500 10.00 448.52 25.00% 11.21 112.13 25.00% 11.21 112.13 25.00% 11.21 112.13 25.00% 11.21 112.13
MOTONIVELADORA DE 125 HP hm 5.5100 177.97 981.10 25.00% 1.38 245.28 25.00% 1.38 245.28 25.00% 1.38 245.28 25.00% 1.38 245.28
PLANCHA COMPACTADORA DE 4 HP hm 11.6800 16.25 189.75 25.00% 2.92 47.44 25.00% 2.92 47.44 25.00% 2.92 47.44 25.00% 2.92 47.44
VIBRADORA DE CONCRETO hm 27.7900 10.00 277.94 25.00% 6.95 69.49 25.00% 6.95 69.49 25.00% 6.95 69.49 25.00% 6.95 69.49
CALENDARIO DE ADQUISICION DE MATERIALES
Proyecto

“MEJORAMIENTO DE LA VIA VEHICULAR Y PEATONAL EN LA CALLE LOS ULCUMANOS, CALLE LOS CAUCHOS, CALLE LAS PALMERAS, CALLE LOS ROBLES Y PASAJE ACHAHUASCA, URB. CAPELO - LA MERCED,
PROVINCIA DE CHANCHAMAYO – JUNIN” – TERCERA ETAPA – (META: JR. LOS CAUCHOS DESDE EL JR. LOS ROBLES L=0+135.29 KMS)

Region :JUNIN Provincia : CHANCHAMAYO Distrito : CHANCHAMAYO

DESCRIPCION UNID CANTIDAD PRECIO PARCIAL PAVIMENTO RIGIDO


NIVEL TOPOGRAFICO hm 30.5900 9.50 290.57 25.00% 7.65 72.64 25.00% 7.65 72.64 25.00% 7.65 72.64 25.00% 7.65 72.64
STACION TOTAL hm 30.5900 15.00 458.82 25.00% 7.65 114.71 25.00% 7.65 114.71 25.00% 7.65 114.71 25.00% 7.65 114.71
SUB TOTAL EQUIPOS 17,667.42 3,669.04 4,419.97 4,454.03 4,740.61

COSTO DIRECTO S/. 239,050.18 S/. 39,204.85 S/. 65,466.06 S/. 66,768.47 S/. 67,227.02

GASTOS GENERALES 10% 23,905.02 3,136.39 5,237.29 5,341.48 5,378.16

UTILIDAD 8% 19,124.01 1,960.24 3,273.30 3,338.42 3,361.35

SUB TOTAL 282,079.21 44,301.48 73,976.65 75,448.37 75,966.54

IGV 18% 50,774.26 7,974.27 13,315.80 13,580.71 13,673.98

COSTO DE OBRA 332,853.47 52,275.75 87,292.45 89,029.07 89,640.51


100.00% 15.705% 26.225% 26.747% 26.931%