CALENDARIO VALORIZADO DE AVANCE DE OBRA

“MEJORAMIENTO DEL SERVICIO DE LA TRANSITABILIDAD EN LAS CALLES Y JIRONES DEL AAHH EL HUERTO Y CASCO
PROYECTO
URBANO DE LA CIUDAD DEL DISTRITO DE TAMBOGRANDE- PIURA- PIURA”

LUGAR AA.HH. EL HUERTO Y CASCO URBANO DE LA CIUDAD DEL DISTRITO DE TAMBOGRANDE


PLAZO DE EJEC 04 MESES

ITEM DESCRIPCION UNID METRADO Precio Parcial 1 Mes 2 Mes 3 Mes 4 Mes

01 OBRAS PROVISIONALES 85,943.66


01.01 CARTEL DE OBRA DE 3.60 m x 7.20 m und 1.00 1,395.20 1,395.20 1,395.20 0.00 0.00 0.00 1,395.20 0.00
01.02 ALQUILER DE LOCAL PARA (TALLERES, INSTALACIONES Y PATIOS DE MAQUINAS) mes 4.00 450.00 1,800.00 450.00 450.00 450.00 450.00 1,800.00 0.00
01.03 TRANQUERA MÓVIL, DE MADERA, P/DESVIO DE TRANSITO VEHICULAR und 50.00 222.54 11,127.00 2,781.75 2,781.75 2,781.75 2,781.75 11,127.00 0.00
01.04 AGUA PARA LA CONSTRUCCION GLB 1.00 1,500.00 1,500.00 375.00 375.00 375.00 375.00 1,500.00 0.00
01.05 DEPOSITO PARA ALMACENAR AGUA GLB 1.00 257.90 257.90 64.48 64.48 64.48 64.48 257.90 0.00
01.06 ALQUILER DE BAÑOS QUIMICOS mes 2.00 1,046.00 2,092.00 523.00 523.00 523.00 523.00 2,092.00 0.00
01.07 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS GLB 1.00 4,354.23 4,354.23 4,354.23 0.00 0.00 0.00 4,354.23 0.00
01.08 FLETE TERRESTRE GLB 1.00 63,417.33 63,417.33 63,417.33 0.00 0.00 0.00 63,417.33 0.00
02 TRABAJOS PRELIMINARES 200,171.85
02.01 TRAZO, NIVELACION Y REPLANTEO C/EQUIPO P/PAVIMENTACION m2 23,510.43 2.39 56,189.93 56,189.93 0.00 0.00 0.00 56,189.93 0.00
02.02 SEÑALIZACIÓN EN OBRA DURANTE EJECUCIÓN ML 835.42 1.66 1,386.80 1,386.80 0.00 0.00 0.00 1,386.80 0.00
02.03 DEMOLICION DE SARDINEL DE CONCRETO SUMERGIDOS/PERALTADOS m3 28.15 42.84 1,205.95 1,205.95 0.00 0.00 0.00 1,205.95 0.00
02.04 DEMOLICION DE BASE DE LOSA DE CONCRETO EXISTENTE m2 804.26 64.11 51,561.11 51,561.11 0.00 0.00 0.00 51,561.11 0.00
02.05 DEMOLICION DE VEREDEAS H=0.10 m m2 2,215.60 19.90 44,090.44 44,090.44 0.00 0.00 0.00 44,090.44 0.00
02.06 ELIMINACION DE MATERIAL DE DEMOLICIONES EXCEDENTE CON VOLQUETE DE 10 m3 677.74 13.71 9,291.82 9,291.82 0.00 0.00 0.00 9,291.82 0.00
02.07 REUBICACION DE POSTES DE LUZ und 40.00 505.59 20,223.60 20,223.60 0.00 0.00 0.00 20,223.60 0.00
02.08 LIMPIEZA DE TERRENO MANUAL m2 23,510.43 0.69 16,222.20 14,599.98 1,622.22 0.00 0.00 16,222.20 0.00
03 PAVIMENTACIÓN 3,826,244.20 0.00 3,826,244.20
03.01 MOVIMIENTO DE TIERRAS 1,730,232.23 0.00 1,730,232.23
03.01.01 CORTE DE TERRENO HASTA NIVEL DE SUB-RASANTE C/EQUIPO (RETROEXCAVA m3 7,445.53 151.65 1,129,114.62 564,557.31 564,557.31 0.00 0.00 1,129,114.62 0.00
03.01.02 CORTE DE TERRENO HASTA NIVEL DE SUB-RASANTE C/EQUIPO (RETROEXCAVA m3 2,653.33 58.55 155,352.47 77,676.24 77,676.24 0.00 0.00 155,352.47 0.00
03.01.03 EXCAVACION MANUAL DE ZANJAS PARA SARDINELES DE BORDE m3 68.07 30.36 2,066.61 1,033.31 1,033.31 0.00 0.00 2,066.61 0.00
03.01.04 PERFILADO Y COMPACTACION DE SUBRASANTE TRAMOS DE CORTE Y RELLENO m2 17,152.33 2.56 43,909.96 21,954.98 21,954.98 0.00 0.00 43,909.96 0.00
03.01.05 BASE GRANULAR DE MATERIAL AFIRMADO, e=0.15m m2 17,152.33 11.95 204,970.34 102,485.17 102,485.17 0.00 0.00 204,970.34 0.00
03.01.06 CAMA DE ARENA DE E=0.04 M.PARA ASENTADO DE ADOQUINES m2 231.96 10.43 2,419.34 1,209.67 1,209.67 0.00 0.00 2,419.34 0.00
03.01.07 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQUETE DE 15 m3 D<= 5 Km. m3 12,200.31 15.77 192,398.89 96,199.45 96,199.45 0.00 0.00 192,398.89 0.00
03.02 PAVIMENTO RÍGIDO 1,968,950.96 0.00 1,968,950.96
03.02.01 CONCRETO F'C=210 KG/CM2 PARA LOSAS PAVIMENTO m3 2,892.09 417.58 1,207,678.94 120,767.89 241,535.79 362,303.68 483,071.58 1,207,678.94 0.00
03.02.02 ENCOFRADO Y DESENCOF EN LOSA DE CONCRETO m2 3,595.82 51.28 184,393.65 0.00 55,318.10 55,318.10 73,757.46 184,393.65 0.00
03.02.03 JUNTA DE DILATACION ASFALTICA PARA PAVIMENTO, e=1" ML 13,483.83 12.70 171,244.64 0.00 51,373.39 51,373.39 68,497.86 171,244.64 0.00
03.02.04 JUNTA LONGITUDINAL DE ARTICULACION C/CONECTORES DE FIERRO LISO DE 5/ ML 11,236.00 11.84 133,034.24 0.00 39,910.27 39,910.27 53,213.70 133,034.24 0.00
03.02.05 JUNTA TRANSVERSAL DE CONTRACCIÓN C/CONECTORES DE FIERRO LISO DE 5/ ML 14,983.00 14.90 223,246.70 0.00 0.00 111,623.35 111,623.35 223,246.70 0.00
03.02.06 CURADO DE SUPERFICIES DE CONCRETO CON ADITIVO QUIMICO m2 13,484.37 3.66 49,352.79 0.00 0.00 24,676.40 24,676.40 49,352.79 0.00
03.03 PAVIMENTO CON BLOQUETA - ESTACIONAMIENTO 14,652.92 0.00 14,652.92
03.03.01 SUMINISTRO Y COLOCACION DE ADOQUINES DE CONCRETO 10 x 20 x 8 CM m2 231.96 58.37 13,539.51 0.00 0.00 13,539.51 0.00 13,539.51 0.00
03.03.02 COMPACTACIÓN Y SELLADO DE PAVIMENTO m2 231.96 4.80 1,113.41 0.00 0.00 1,113.41 0.00 1,113.41 0.00
03.04 SARDINEL DE CONCRETO PERALTADOS/SUMERGIDOS 64,772.58 0.00 64,772.58
03.04.01 SARDINEL CONCRETO f’c=175 KG/CM2 m3 68.07 393.83 26,808.01 0.00 13,404.01 13,404.01 0.00 26,808.01 0.00
03.04.02 ENCOFRADO Y DESENCOF EN SARDINELES m2 907.56 39.94 36,247.95 0.00 18,123.98 18,123.98 0.00 36,247.95 0.00
03.04.03 JUNTA DE DILATACION ASFALTICA PARA VEREDAS, e=1" ML 38.70 12.17 470.98 0.00 235.49 235.49 0.00 470.98 0.00
03.04.04 CURADO DE SUPERFICIES DE CONCRETO CON ADITIVO QUIMICO m2 340.34 3.66 1,245.64 0.00 0.00 1,245.64 0.00 1,245.64 0.00
03.05 NIVELACION DE BUZONES 47,635.51 0.00 47,635.51
03.05.01 NIVELACION DE BUZONES EN GENERAL und 61.00 780.91 47,635.51 0.00 47,635.51 0.00 0.00 47,635.51 0.00
04 VEREDAS DE CONCRETO 668,880.56 0.00 668,880.56
04.01 TRABAJOS PRELIMINARES 7,284.87 0.00 7,284.87
04.01.01 TRAZO, NIVEL Y REPLANTEO DE VEREDAS m2 5,396.20 1.35 7,284.87 0.00 7,284.87 0.00 0.00 7,284.87 0.00
04.02 MOVIMIENTO DE TIERRAS 161,311.06 0.00 161,311.06
04.02.01 PERFILADO, NIVELACION Y COMPACTACION DE SUBRASANTE EN VEREDAS m2 5,396.20 4.41 23,797.24 0.00 9,518.90 9,518.90 4,759.45 23,797.24 0.00
04.02.02 RELLENO Y COMPACTACION CON AFIRMADO EN VEREDAS, e=0.15m m3 849.90 161.80 137,513.82 0.00 55,005.53 55,005.53 27,502.76 137,513.82 0.00
04.03 VEREDAS, RAMPAS Y MARTILLOS DE CONCRETO 420,852.31 0.00 420,852.31
04.03.01 CONCRETO f'c=175 kg/cm2 PARA GRADAS, VEREDAS Y RAMPAS m3 777.32 389.01 302,385.25 0.00 60,477.05 120,954.10 120,954.10 302,385.25 0.00
04.03.02 ENCOFRADO Y DESENCOFRADO DE GRADAS Y VEREDAS m2 1,834.82 38.34 70,347.00 0.00 14,069.40 28,138.80 28,138.80 70,347.00 0.00
04.03.03 CURADO DE SUPERFICIES DE CONCRETO CON ADITIVO QUIMICO m2 5,666.00 3.66 20,737.56 0.00 0.00 10,368.78 10,368.78 20,737.56 0.00
04.03.04 JUNTA DE DILATACION ASFALTICA PARA VEREDAS, e=1" ML 2,250.00 12.17 27,382.50 0.00 5,476.50 10,953.00 10,953.00 27,382.50 0.00
04.04 VARIOS 79,432.32 0.00 79,432.32
04.04.01 REPOSICION Y NIVELACION DE CAJA DE CONCRETO P/AGUA CONEXIÓN DOMICIL und 352.00 98.75 34,760.00 0.00 13,904.00 13,904.00 6,952.00 34,760.00 0.00
04.04.02 REPOSICION Y NIVELACION DE CAJA DE CONCRETO P/DESAGUE CONEXIÓN DOM und 352.00 126.91 44,672.32 0.00 17,868.93 17,868.93 8,934.46 44,672.32 0.00
05 AREAS VERDES Y JARDINES 51,754.53 0.00 51,754.53
05.01 OBRAS PRELIMINARES 751.49 0.00 751.49
05.01.01 TRAZO Y REPLANTEO EN AREA RECREATIVA m2 429.42 1.75 751.49 0.00 0.00 0.00 751.49 751.49 0.00
05.02 MOVIMIENTO DE TIERRAS 18,510.51 0.00 18,510.51
05.02.01 CORTE DE MATERIAL SEMIROCOSO m3 85.88 111.74 9,596.23 0.00 4,798.12 4,798.12 0.00 9,596.23 0.00
05.02.02 EXCAVACIÓN DE HOYOS PARA SEMBRADO DE PLANTONES Y ARBUSTOS ORNAM m3 4.56 80.97 369.22 0.00 184.61 184.61 0.00 369.22 0.00
05.02.03 SUMINISTRO Y PREPARACIÓN DE TERRENO AGRÍCOLA m2 85.88 74.20 6,372.30 0.00 3,186.15 3,186.15 0.00 6,372.30 0.00
05.02.04 ELIMINACION DE MATERIAL EXCEDENTE EN FORMA MANUAL m3 107.35 20.24 2,172.76 0.00 1,086.38 1,086.38 0.00 2,172.76 0.00
05.03 AREAS VERDES 10,526.53 0.00 10,526.53
05.03.01 SEMBRADO DE GRASS m2 429.43 19.07 8,189.23 0.00 4,094.62 4,094.62 0.00 8,189.23 0.00
05.03.02 SEMBRADO DE ARBUSTOS Y PLANTAS ORNAMENTALES und 45.00 51.94 2,337.30 0.00 1,168.65 1,168.65 0.00 2,337.30 0.00
05.04 TACHOS DE BASURA 21,966.00
05.04.01 TACHOS DE BASURA und 60.00 366.10 21,966.00 0.00 0.00 10,983.00 10,983.00 21,966.00 0.00
06 SEÑALIZACION 140,413.75 0.00 140,413.75
06.01 SEÑAL PREVENTIVA EN OBRA 5,490.00 0.00 5,490.00
06.01.01 CINTA SEÑALIZADORA P/SEGURIDAD m 4,500.00 1.22 5,490.00 1,372.50 1,372.50 1,372.50 1,372.50 5,490.00 0.00
06.02 SEÑALIZACION HORIZONTAL 88,360.48 0.00 88,360.48
06.02.01 SEÑALIZACION HORIZONTAL, PINTURA EN SARDINELES m 5,400.20 12.02 64,910.40 0.00 0.00 32,455.20 32,455.20 64,910.40 0.00
06.02.02 PINTURA DE TRAFICO EN SIMBOLOS Y LETRAS m2 138.30 22.52 3,114.52 0.00 0.00 1,557.26 1,557.26 3,114.52 0.00
06.02.03 PINTURA DE TRAFICO EN LINEAS Y PASOS PEATONALES m2 903.00 22.52 20,335.56 0.00 0.00 10,167.78 10,167.78 20,335.56 0.00
06.03 SEÑALIZACION VERTICAL 46,563.27 0.00 46,563.27
06.03.01 SEÑALES PREVENTIVAS DE 0.60x0.60 und 3.00 637.76 1,913.28 0.00 0.00 0.00 1,913.28 1,913.28 0.00
06.03.02 SEÑALES REGLAMENTARIAS DE 0.60x0.60 und 63.00 708.73 44,649.99 0.00 0.00 0.00 44,649.99 44,649.99 0.00
07 MEDIDAS DE MITIGACION Y REDUCCION DE RIESGOS 19,800.00 0.00 19,800.00
07.01 MANTENIMIENTO DE TRANSITO TEMPORAL Y SEGURIDAD VIAL est 1.00 6,800.00 6,800.00 1,700.00 1,700.00 1,700.00 1,700.00 6,800.00 0.00
07.02 HABILITACION DE BOTADERO GLB 1.00 3,500.00 3,500.00 3,500.00 0.00 0.00 0.00 3,500.00 0.00
07.03 EQUIPO DE PROTECCION INDIVIDUAL GLB 1.00 3,000.00 3,000.00 3,000.00 0.00 0.00 0.00 3,000.00 0.00
07.04 RIEGO DE ZONA DE TRABAJO SIN ACCESO VEHIC. P/MITIGAR LA CONTAMINACION- est 1.00 6,500.00 6,500.00 1,625.00 1,625.00 1,625.00 1,625.00 6,500.00 0.00
08 CAPACITACIONES 24,000.00 0.00 24,000.00
08.01 PROGRAMA DE EDUCACION AMBIENTAL GLB 1.00 3,500.00 3,500.00 3,500.00 0.00 0.00 0.00 3,500.00 0.00
08.02 PROGRAMA DE CAPACITACION ANTE DESASTRES NATURALES GLB 1.00 3,500.00 3,500.00 3,500.00 0.00 0.00 0.00 3,500.00 0.00
08.03 PROGRAMA DE SEGUIMIENTO Y VIGILANCIA GLB 1.00 3,500.00 3,500.00 875.00 875.00 875.00 875.00 3,500.00 0.00
08.04 CAPACITACION EN EL MANEJO Y USO DE LOS MATERIALES GLB 1.00 3,500.00 3,500.00 3,500.00 0.00 0.00 0.00 3,500.00 0.00
08.05 CAPACITACION Y MONITOREO EN EL USO DE LOS SS.HH. EN OBRA GLB 1.00 2,000.00 2,000.00 500.00 500.00 500.00 500.00 2,000.00 0.00
08.06 PROGRAMA DE CONTINGENCIAS GLB 1.00 8,000.00 8,000.00 0.00 0.00 0.00 8,000.00 8,000.00 0.00
09 VARIOS 22,341.36 0.00 22,341.36
09.01 REPOSICION DE REDES EXISTENTES DE AGUA Y ALCANTARILLADO GLB 1.00 8,000.00 8,000.00 2,000.00 2,000.00 2,000.00 2,000.00 8,000.00 0.00
09.02 LIMPIEZA FINAL DE OBRA m2 23,510.43 0.61 14,341.36 0.00 0.00 0.00 14,341.36 14,341.36 0.00
COSTO DIRECTO 5,039,549.91 1,282,867.12 1,544,665.28 1,041,527.73 1,170,489.77 5,039,549.91 0.00
GASTOS GENERALES 9.00% 453,559.49 115,458.04 139,019.88 93,737.50 105,344.08 453,559.49 0.00
UTILIDAD 8.00% 403,163.99 102,629.37 123,573.22 83,322.22 93,639.18 403,163.99 0.00
SUB TOTAL 5,896,273.39 1,500,954.54 1,807,258.38 1,218,587.45 1,369,473.04 5,896,273.39 0.00
I.G.V 18.00% 1,061,329.21 270,171.82 325,306.51 219,345.74 246,505.15 1,061,329.21 0.00
TOTAL PRESUPUESTO 6,957,602.60 1,771,126.35 2,132,564.87 1,437,933.19 1,615,978.18 6,957,602.60 0.00

AVANCE PROGRAMADO PARCIAL 25.46% 30.65% 20.67% 23.23%


AVANCE PROGRAMADO ACUMULADO 25.46% 56.11% 76.77% 100.00%