METRADOS

CONCRETO
ANCHO LARGO ALTO DIM
Z4 1.5 1.5 0.6 1.35
SOLADO 1.5 1.5 0.1 0.23
COLUMNAS 0.6 0.4 11.2 2.688
VIGAS LARGA 0.6 0.4 50.23 12.0552
VIGAS CORTAS 0.6 0.4 20 4.8
VIGA DE CIMENTACION 0.6 0.4 50.23 12.0552
VIGA DE CIMENTACION 0.4 0.3 20 2.4
LOSA 20 50 0.25 250

TOTAL

METRADOS
SOBRECIMIENTO
ANCHO LARGO ALTO DIM
LARGO 0.15 50.23 0.9 6.78
CORTO 0.15 20 0.9 2.70

ACERO
ZAPATA LARGO N° VAR CANT ZAPT PARCIAL
1.38 14 54 1043.28

COLUMNA LARGO N° VAR CANT ZAPT PARCIAL(M)


6.5 6 54 2106

VIGAS LARGO N° VAR CANT VIG PARCIAL(M)


LADO LARGO 52.4 6 2 628.8

VIGAS LARGO N° VAR CANT ZAPT PARCIAL(M)


LADO CORTO 20.89 6 2 250.68

VIGAS CIMENTA LARGO N° VAR CANT VIG PARCIAL(M)


LADO LARGO 52.4 4 2 419.2
VIGAS CIMENTAC LARGO N° VAR CANT ZAPT PARCIAL(M)
LADO CORTO 20.89 4 2 167.12

LOSA LARGO N° VAR CANT ZAPT PARCIAL(M)


LOSA 52.4 50 2 5240

TOTAL

METRADOS
EXCAVACION
ANCHO LARGO ALTO DIM
RASPADO 20 50.23 0.1 100.46
CIMENTACION 1.5 1.5 0.7 1.58

METRADOS
LADRILLOS
ANCHO LARGO ALTO DIM
LARGO 3.3 49 161.70
CORTO 3.3 30 1 99.00

24 LAD/M2

METRADOS
LADRILLOS TECHO
ANCHO LARGO ALTO DIM
LARGO 50 20 1000.00
CORTO 1 0.00
2137.17 1316

85 63

25.1431765 20.8888888888889
CANT PARCIAL
54 72.9
54 12.15
54 145.152
2 24.1104
2 9.6
2 24.1104
2 4.8
1 250

530.6728

535 M3
149,800.00

CANT PARCIAL
2 13.5621
2 5.4
18.9621

20 M3
3,000.00

% DESPERDICIO TOTAL (m) precio /M


1147.608 1150

% DESPERDICIO TOTAL (m) precio /M


2316.6 2400

% DESPERDICIO TOTAL (m) precio /M


691.68 700

% DESPERDICIO TOTAL (m) precio /M


275.748 300

% DESPERDICIO TOTAL (m) precio /M


461.12 470
% DESPERDICIO TOTAL (m) precio /M
183.832 190

% DESPERDICIO TOTAL (m) precio /M


5764 5800

5210 1.55 583.333333 25666.666667


5250 METROS
583.333333333333

CANT PARCIAL (M3)


1 100.46
54 85.05
841
300
90 M3 500
8500

CANT PARCIAL (M2)


2 323.4
1 99
422.4

430 M2

10,320.00 LADRILLOS 13,416.00

CANT PARCIAL (M2)


1 1000
1 0
1000

1000 M2

8000 UND 11200

223,699.33
2302.56 280000

78

29.52
PERSONAL TECNICO
UND MES REMUN PARCIAL
01 RESIDENTE 1 3 2500 7500
01 ASISTENTE 1 3 1500 4500

OPERARIOS 1 3 1800 5400


OFICIALES 2 3 1500 9000
PEONES 3 3 1200 10800
37200

910836073

2250
8075.5 1211.325

2018.875

1.5 301.5
0.8 400

200
85.8
25740
86.58 2000
25974 4000
2800
3000
3600
15400
METRADOS
CONCRETO
ANCHO LARGO ALTO DIM CANT PARCIAL
Z4 1.3 1.3 0.5 0.85 16 13.52
SOLADO 1.3 1.3 0.1 0.17 16 2.704
COLUMNAS 0.4 0.3 11.2 1.344 16 21.504
VIGAS LARGA 0.4 0.3 13.26 1.5912 2 3.1824
VIGAS CORTAS 0.4 0.3 20 2.4 2 4.8
VIGA DE CIMENTACION 0.3 0.3 13.26 1.1934 2 2.3868
VIGA DE CIMENTACION 0.3 0.3 20 1.8 2 3.6
LOSA 6.6 13 0.25 21.45 1 21.45

TOTAL 70.4432

70
14000

METRADOS
SOBRECIMIENTO
ANCHO LARGO ALTO DIM CANT PARCIAL
LARGO 0.15 12.66 0.9 1.71 2 3.4182
CORTO 0.15 6.6 0.9 0.89 2 1.782
5.2002

6
900

ACERO
ZAPATA LARGO N° VAR CANT ZAPT PARCIAL% DESPERDICIO TOTAL (m)
1.22 18 16 351.36 386.496 390

COLUMNA LARGO N° VAR CANT ZAPTPARCIAL(M)


% DESPERDICIO TOTAL (m)
6.5 6 16 624 686.4 670

VIGAS LARGO N° VAR CANT VIG PARCIAL(M)


% DESPERDICIO TOTAL (m)
LADO LARGO 13.66 6 2 163.92 180.312 190

VIGAS LARGO N° VAR CANT ZAPTPARCIAL(M)


% DESPERDICIO TOTAL (m)
LADO CORTO 7.75 6 2 93 102.3 110

VIGAS CIMENTA LARGO N° VAR CANT VIG PARCIAL(M)


% DESPERDICIO TOTAL (m)
LADO LARGO 12.68 4 2 101.44 111.584 115
VIGAS CIMENTAC LARGO N° VAR CANT ZAPTPARCIAL(M)
% DESPERDICIO TOTAL (m)
LADO CORTO 7.75 4 2 62 68.2 70

LOSA LARGO N° VAR CANT ZAPTPARCIAL(M)


% DESPERDICIO TOTAL (m)
LOSA 13.66 30 2 819.6 901.56 950

TOTAL 1545
1600
6222.222222222

METRADOS
EXCAVACION
ANCHO LARGO ALTO DIM CANT PARCIAL (M3)
RASPADO 20 50.23 0.4 401.84 1 401.84
CIMENTACION 2 2 2 8.00 16 128
841

845

METRADOS
LADRILLOS
ANCHO LARGO ALTO DIM CANT PARCIAL (M2)
LARGO 3.3 13 42.90 2 85.8
CORTO 3.3 6.6 1 21.78 1 21.78
107.58

110

24 LAD/M2 2,640.00

METRADOS
LADRILLOS TECHO
ANCHO LARGO ALTO DIM CANT PARCIAL (M2)
LARGO 6.6 13 85.80 1 85.8
CORTO 1 0.00 1 0
85.8

90

720
PERSONAL TECNICO
UND MES REMUN
01 RESIDENTE 1 3 3000
01 ASISTENTE 1 3 2000

OPERARIOS 4 3 1800
OFICIALES 6 3 1500
PEONES 8 3 1200

CEMENTO
ACERO
M3 ENCOFRADO
EXCAVACION
MANO DE OBRA
ESTRIBOS

M3

precio /M
180.6

precio /M

precio /M

precio /M

precio /M
precio /M

precio /M

METROS
177.77778

M3

M2

LADRILLOS 2,640.00

0
200
UND 1008 85.8
25740
53,270.22 86.58 2000
17700 25974 4000
70,970.22 2800
35,000.00 3000
105,970.22 3600
35000 15400
140,970.22
RSONAL TECNICO
PARCIAL
9000
6000

5400
4500
3600
28500