GRUPO N° 6 LINEA DE CONDUCCIÓN CERRO COLORADO PROJECT MANAGEMENT-TT.

CODIGO WBS /
EDT/WBS Ppto. Base Duración Inicio Fin AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE TOTAL
EDT
LC.IN INICIO DE OBRA 0 0 vie 03/08/07 vie 03/08/07
LC.OP OBRAS PROVICIONALES 23,847.08 38 vie 03/08/07 lun 17/09/07
LP.OP.CS OFINA PARA CONTRATISTA Y SUPERVICIÓN 4,664.10 11 vie 03/08/07 mié 15/08/07 4,664.10 4,664.10
LC.OP.HE ALMACEN PARA HERRAMIENTAS Y EQUIPO 2,063.60 4 mar 14/08/07 vie 17/08/07 2,063.60 2,063.60
LC.OP.TU ALMACEN CON COBERTURA PARA TUBERIA 10,704.00 25 jue 16/08/07 lun 17/09/07 6,811.64 3,892.36 10,704.00
LC.OP.CR CERCO P/ALMACENAJE NO CUBIERTO 4,887.00 3 jue 16/08/07 sáb 18/08/07 4,887.00 4,887.00
LC.OP.CO CARTEL DE LA OBRA 3.60 M X 2.40 M 1,528.38 8 vie 10/08/07 sáb 18/08/07 1,528.38 1,528.38
LC.TP TRABAJOS PRELIMINARES 50,766.08 121 lun 06/08/07 vie 28/12/07
LC.TP.TE TRANSPORTE EQUIPO 1,283.04 1 lun 06/08/07 lun 06/08/07 1,283.04 1,283.04
LC.TP.TR TRAZO NIVELES Y REPLANTEO 33,200.00 26 mié 15/08/07 mar 18/09/07 23,240.00 9,960.00 33,200.00
LC.TP.CT CONTROL TOPOGRAFICO 15,000.00 42 mié 19/09/07 jue 08/11/07 6,785.71 8,214.29 15,000.00
LC.TP.DM DESMOVILIZACION 1,283.04 1 vie 28/12/07 vie 28/12/07 1,283.04 1,283.04
LC.MT MOVIMIENTO DE TIERRAS 502,931.14 109 mar 21/08/07 sáb 29/12/07
LC.MT.EE EXC.ZANJA T.NORMAL C/EQ. 38,640.00 100 mar 21/08/07 mar 18/12/07 3,477.60 9,660.00 10,046.40 9,660.00 5,796.00 38,640.00
LC.MT.EM EXC.ZANJA T.NORMAL MANUAL 68,797.82 100 mié 22/08/07 mié 19/12/07 5,503.83 17,199.46 17,887.43 17,199.46 11,007.65 68,797.83
LC.MT.R1 RELLENO C/MAT.PROPIO MANUAL 1ERA.ETAPA 73,337.00 100 vie 24/08/07 vie 21/12/07 4,400.22 18,334.25 19,067.62 18,334.25 13,200.66 73,337.00
LC.MT.R2 RE. C/MAT.PROPIO MANUAL 2DA. ETAPA 27,547.72 100 mar 28/08/07 mié 26/12/07 826.43 6,886.93 7,162.41 6,886.93 5,785.02 27,547.72
LC.MT.RE RE.C/MAT.PR. C/EQ.LIVIANO 252,869.12 100 mié 29/08/07 jue 27/12/07 5,057.38 63,217.28 65,745.97 63,217.28 55,631.21 252,869.12
LC.MT.EL ELIMINACION C/TRANSPORTE 41,739.48 32 jue 22/11/07 sáb 29/12/07 10,434.87 31,304.61 41,739.48
LC.TU TUBERIA 965,300.00 100 jue 23/08/07 jue 20/12/07
LC.TU.SC SUM. E INSTALACION TUBERIA PVC C/10 10PLG 965,300.00 100 jue 23/08/07 jue 20/12/07 67,571.00 241,325.00 250,978.00 241,325.00 164,101.00 965,300.00
LC.VA VARIOS 50,800.00 104 lun 27/08/07 sáb 29/12/07
LC.VA.P1 PRUEBA HID.ZANJA ABIERTA 25,400.00 100 lun 27/08/07 lun 24/12/07 1,016.00 6,350.00 6,604.00 6,350.00 5,080.00 25,400.00
LC.VA.P2 PRUE.HID. ZANJA TAPADA 25,400.00 100 sáb 01/09/07 sáb 29/12/07 6,350.00 6,604.00 6,350.00 6,096.00 25,400.00
LC.FN FIN DE OBRA 0 0 sáb 29/12/07 sáb 29/12/07
TOTAL S/1,593,644.30 S/132,330.22 S/389,960.99 S/392,310.12 S/379,757.79 S/299,285.19 S/1,593,644.31

TOTAL /MES S/132,330.22 S/389,960.99 S/392,310.12 S/379,757.79 S/299,285.19


TOTAL ACUMULADO S/132,330.22 S/522,291.21 S/914,601.33 S/1,294,359.12 S/1,593,644.31
% ACUMULADO 8.30 32.77 57.39 81.22 100.00

CURVA S
1800000

S/1,593,644.31
1600000

1400000
S/1,294,359.12

1200000
% ACUMULADO

1000000 S/914,601.33

800000

600000 S/522,291.21

400000

200000 S/132,330.22

0
1 2 3 4 5

UNIVERSIDAD CÉSAR VALLEJO Pag. 1 E.P Ing. Civil


GRUPO N° 6 LINEA DE CONDUCCIÓN CERRO COLORADO PROJECT MANAGEMENT-TT.
TIEMPO
Series1 Series2

UNIVERSIDAD CÉSAR VALLEJO Pag. 1 E.P Ing. Civil