MUNICIPALIDAD DISTRITAL DE TANTAMAYO

PROGRAMACIÓN DE OBRA
PROYECTO : "CREACION DE PISTAS, VEREDAS Y CUNETAS EN EL JR. SAN PEDRO DE PARIARCA DE LA COMUNIDAD CAMPESINA DE SAN PEDRO DE PARIARCA, EN EL DISTRITO DE TANTAMAYO -
HUAMALIES - HUANUCO"
ETAPA 2.0 : PISTAS Y VEREDAS
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE TANTAMAYO
UBICACION : DPTO:HUANUCO PROV:HUAMALIES DIST:TANTAMAYO LOC:SAN PEDRO DE PARIARCA
FECHA PROYECTO : 12/06/2015
01/09/2015 06/09/2015 13/09/2015 20/09/2015 27/09/2015 04/10/2015 11/10/2015 18/10/2015 25/10/2015 01/11/2015 08/11/2015 15/11/2015 22/11/2015 29/11/2015 06/12/2015 13/12/2015 20/12/2015 27/12/2015 03/01/2016 10/01/2016 17/01/2016 24/01/2016 31
Item Descripción Duracion Inicio Fin
M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D

2.0 PISTAS Y VEREDAS 131 días 01/09/2015 30/01/2016

2.1 PISTAS Y VEREDAS 131 días 01/09/2015 30/01/2016

2.1.1 PISTAS 131 días 01/09/2015 30/01/2016

2.1.1.1 TRABAJOS PRELIMINARES 27 días 01/09/2015 01/10/2015

5 días
2.1.1.1.1 LIMPIEZA DE TERRENO MANUAL 5 días 01/09/2015 05/09/2015

10 días
2.1.1.1.2 DEMOLICION DE VEREDA EXISTENTES 10 días 07/09/2015 17/09/2015

9 días
2.1.1.1.3 DEMOLICION DE CUNETAS EXISTENTES 9 días 12/09/2015 22/09/2015

ELIMINACION DE DESMONTE PROVENIENTE DE LA DEMOLICION 10 días


2.1.1.1.4 10 días 16/09/2015 26/09/2015
DE VEREDAS
12 días
2.1.1.1.5 TRAZO NIVELES Y REPLANTEO 12 días 18/09/2015 01/10/2015

2.1.1.2 MOVIMIENTO DE TIERRAS 35 días 28/09/2015 06/11/2015

10 días
2.1.1.2.1 CORTE EN TERRENO NORMAL CON MAQUINARIA 10 días 28/09/2015 08/10/2015

6 días
2.1.1.2.2 RELLENO CON MATERIAL PROPIO 6 días 05/10/2015 10/10/2015

15 días
2.1.1.2.3 PERFILADO Y COMPACTADO DE SUB RASANTE 15 días 05/10/2015 21/10/2015

15 días
2.1.1.2.4 CONFORMACION DE BASE GRANULAR E=20 CM 15 días 21/10/2015 06/11/2015

12 días
2.1.1.2.5 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA 12 días 12/10/2015 24/10/2015

2.1.1.3 OBRAS DE CONCRETO 66 días 02/11/2015 16/01/2016

66 días
2.1.1.3.1 PISTA DE CONCRETO HIDRÁULICO E=20 CM, FC=210 KG/CM2 66 días 02/11/2015 16/01/2016

24 días
2.1.1.3.2 ENCOFRADO Y DESENCOFRADO DE PAVIMENTO 24 días 09/11/2015 05/12/2015

18 días
2.1.1.3.3 ACERO EN JUNTAS LONGITUDINALES F'Y=4200 KG/CM2 18 días 16/11/2015 05/12/2015

2.1.1.4 JUNTAS ASFALTICAS 61 días 21/11/2015 30/01/2016

36 días
2.1.1.4.1 JUNTAS ASFALTICAS DE CONTRACION (E=1/2", H=2") 36 días 21/12/2015 30/01/2016

36 días
2.1.1.4.2 JUNTAS ASFALTICAS DE DILATACION (E=3/4", H=20 CM) 36 días 21/12/2015 30/01/2016

JUNTAS ASFALTICAS LONGITUDINALES (E=3/4", H=20CM) 36 días


2.1.1.4.3 36 días 21/12/2015 30/01/2016

43 días
2.1.1.4.4 TEKNOPORT EN JUNTAS DE E=1/2" (H=2") 43 días 21/11/2015 09/01/2016

43 días
2.1.1.4.5 TEKNOPORT EN JUNTAS DE E=3/4" (H=0.2 M) 43 días 21/11/2015 09/01/2016

2.1.2 VEREDAS 71 días 07/09/2015 27/11/2015

2.1.2.1 MOVIMIENTO DE TIERRAS 37 días 07/09/2015 19/10/2015

EXCAVACION EN TERRENO NORMAL PARA VEREDAS 20 días


2.1.2.1.1 20 días 07/09/2015 29/09/2015

20 días
2.1.2.1.2 COMPACTADO Y PERFILADO DE SUELOS PARA VEREDAS 20 días 21/09/2015 13/10/2015

15 días
2.1.2.1.3 AFIRMADO DE 4" PARA VEREDAS 15 días 02/10/2015 19/10/2015

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA 8 días


2.1.2.1.4 8 días 10/10/2015 19/10/2015

2.1.2.2 OBRAS DE CONCRETO 24 días 23/10/2015 19/11/2015

CONCRETO F'C=175KG/CM2 PARA VEREDAS 15 días


2.1.2.2.1 15 días 23/10/2015 09/11/2015

CONCRETO EN UÑAS F'C=175KG/CM2 PARA VEREDAS 15 días


2.1.2.2.2 15 días 27/10/2015 12/11/2015

24 días
2.1.2.2.3 ENCOFRADO Y DESENCOFRADO DE VEREDAS 24 días 23/10/2015 19/11/2015

2.1.2.3 JUNTAS ASFALTICAS 30 días 24/10/2015 27/11/2015

17 días
2.1.2.3.1 JUNTAS ASFALTICAS DE DILATACION (E=3/4", H=15 CM) 17 días 09/11/2015 27/11/2015

15 días
2.1.2.3.2 TEKNOPORT EN JUNTAS DE E=3/4" (H=0.15M) 15 días 24/10/2015 10/11/2015

2.1.3 CUNETAS 30 días 23/11/2015 26/12/2015

2.1.3.1 MOVIMIENTO DE TIERRAS 17 días 23/11/2015 11/12/2015

EXCAVACION EN TERRENO NORMAL PARA CUNETAS 12 días


2.1.3.1.1 12 días 23/11/2015 05/12/2015

9 días
2.1.3.1.2 COMPACTADO Y PERFILADO DE SUELOS PARA CUNETAS 9 días 02/12/2015 11/12/2015

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA 7 días


2.1.3.1.3 7 días 02/12/2015 09/12/2015

2.1.3.2 OBRAS DE CONCRETO 13 días 10/12/2015 24/12/2015

10 días
2.1.3.2.1 CONCRETO FC=175 KG/CM2 PARA CUNETAS 10 días 14/12/2015 24/12/2015

ENCOFRADO Y DESENCOFRADO EN CUNETAS 5 días


2.1.3.2.2 5 días 10/12/2015 15/12/2015

2.1.3.3 JUNTAS ASFALTICAS 12 días 14/12/2015 26/12/2015


JUNTAS ASFALTICAS DE DILATACION (E=3/4") 6 días
2.1.3.3.1 6 días 21/12/2015 26/12/2015

TEKNOPORT EN JUNTAS DE E=3/4" 10 días


2.1.3.3.2 10 días 14/12/2015 24/12/2015

2.1.4 MURO DE MAMPOSTERIA 35 días 01/09/2015 10/10/2015

2.1.4.1 MOVIMIENTO DE TIERRAS 14 días 01/09/2015 16/09/2015


EXCAVACION EN TERRENO NORMAL PARA MUROS DE 8 días
2.1.4.1.1 MAMPOSTERIA 8 días 01/09/2015 09/09/2015

8 días
2.1.4.1.2 RELLENO CON MATERIAL PROPIO 8 días 08/09/2015 16/09/2015

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA 5 días


2.1.4.1.3 5 días 07/09/2015 11/09/2015

2.1.4.2 OBRAS DE CONCRETO 22 días 08/09/2015 02/10/2015

16 días
2.1.4.2.1 CONCRETO DE MAMPOSTERIA CON MORTERO C:H, 1:8 + 30% PM 16 días 10/09/2015 28/09/2015

ENCOFRADO Y DESENCOFRADO DE MUROS DE MAMPOSTERIA 22 días


2.1.4.2.2 22 días 08/09/2015 02/10/2015

2.1.4.3 JUNTAS ASFALTICAS 20 días 18/09/2015 10/10/2015

7 días
2.1.4.3.1 JUNTAS DE CONSTRUCCION (E=3/4") 7 días 03/10/2015 10/10/2015

TEKNOPORT EN JUNTAS DE E=3/4" 10 días


2.1.4.3.2 10 días 18/09/2015 29/09/2015

2.1.5 SARDINEL 41 días 23/11/2015 08/01/2016

2.1.5.1 MOVIMIENTO DE TIERRAS 17 días 23/11/2015 11/12/2015


MUNICIPALIDAD DISTRITAL DE TANTAMAYO

01/09/2015 06/09/2015 13/09/2015 20/09/2015 27/09/2015 04/10/2015 11/10/2015 18/10/2015 25/10/2015 01/11/2015 08/11/2015 15/11/2015 22/11/2015 29/11/2015 06/12/2015 13/12/2015 20/12/2015 27/12/2015 03/01/2016 10/01/2016 17/01/2016 24/01/2016 31
Item Descripción Duracion Inicio Fin
M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D
15 días
2.1.5.1.1 EXCAVACION EN TERRENO NORMAL PARA SARDINEL 15 días 23/11/2015 09/12/2015

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA 5 días


2.1.5.1.2 5 días 07/12/2015 11/12/2015

2.1.5.2 OBRAS DE CONCRETO 24 días 07/12/2015 02/01/2016

24 días
2.1.5.2.1 CONCRETO FC=175 KG/CM2 PARA SARDINEL 24 días 07/12/2015 02/01/2016

ENCOFRADO Y DESENCOFRADO EN SARDINEL 24 días


2.1.5.2.2 24 días 07/12/2015 02/01/2016

2.1.5.3 JUNTAS ASFALTICAS 29 días 07/12/2015 08/01/2016

7 días
2.1.5.3.1 JUNTAS ASFALTICAS DE DILATACION (E=3/4") 7 días 01/01/2016 08/01/2016

24 días
2.1.5.3.2 TEKNOPORT EN JUNTAS DE E=3/4" 24 días 07/12/2015 02/01/2016

2.1.6 ALCANTARILLA 27 días 14/09/2015 14/10/2015

2.1.6.1 MOVIMIENTO DE TIERRAS 9 días 14/09/2015 23/09/2015

EXCAVACION EN TERRENO NORMAL PARA ALCANTARILLAS 6 días


2.1.6.1.1 6 días 14/09/2015 19/09/2015

3 días
2.1.6.1.2 RELLENO CON MATERIAL PROPIO 3 días 21/09/2015 23/09/2015

ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA 2 días


2.1.6.1.3 2 días 21/09/2015 22/09/2015

2.1.6.2 CONCRETO SIMPLE 8 días 25/09/2015 03/10/2015

CONCRETO F'C= 175 KG/CM2 5 días


2.1.6.2.1 5 días 25/09/2015 30/09/2015

EMBOQUILLADO DE PIEDRA CON MORTERO 3 días


2.1.6.2.2 3 días 01/10/2015 03/10/2015

5 días
2.1.6.2.3 ENCOFRADO Y DESENCOFRADO 5 días 25/09/2015 30/09/2015

2.1.6.3 CONCRETO ARMADO 9 días 05/10/2015 14/10/2015

ONCRETO F'C= 175 KG/CM2 EN ALCANTARILLA 3 días


2.1.6.3.1 3 días 12/10/2015 14/10/2015

6 días
2.1.6.3.2 ENCOFRADO Y DESENCOFRADO EN ALCANTARILLA 6 días 05/10/2015 10/10/2015

6 días
2.1.6.3.3 ACERO FY=4200 KG/CM2 GRADO 60 EN ALCANTARILLA 6 días 05/10/2015 10/10/2015

2.1.7 VARIOS 109 días 25/09/2015 29/01/2016

60 días
2.1.7.1 CURADO DE CONCRETO EN PAVIMENTOS 60 días 21/11/2015 29/01/2016

15 días
2.1.7.2 LIMPIEZA DE LOSA 15 días 16/10/2015 02/11/2015

15 días
2.1.7.3 ENSAYO DE SUELO EN SUBRASANTE 15 días 16/10/2015 02/11/2015

ENSAYO DE DENSIDAD DE CAMPO EN SUB BASE 15 días


2.1.7.4 15 días 16/10/2015 02/11/2015

15 días
2.1.7.5 NIVELACION DE BUZONES EN GENERAL 15 días 16/10/2015 02/11/2015

15 días
2.1.7.6 NIVELACION DE MARCOS Y TAPAS DE AGUA Y DESAGUE 15 días 16/10/2015 02/11/2015

109 días
2.1.7.7 PRUEBA DE RESISTENCIA A LA COMPESION DEL Cº 109 días 25/09/2015 29/01/2016
MUNICIPALIDAD DISTRITAL DE TANTAMAYO

PROGRAMACIÓN DE OBRA
PROYECTO : "CREACION DE PISTAS, VEREDAS Y CUNETAS EN EL JR. SAN PEDRO DE PARIARCA DE LA COMUNIDAD CAMPESINA DE SAN
PEDRO DE PARIARCA, EN EL DISTRITO DE TANTAMAYO - HUAMALIES - HUANUCO"
ETAPA 1.0 : OBRAS PROVISIONALES,SEGURIDAD Y SALUD
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE TANTAMAYO
UBICACION : DPTO:HUANUCO PROV:HUAMALIES DIST:TANTAMAYO LOC:SAN PEDRO DE PARIARCA
FECHA PROYECTO : 12/06/2015
01/09/2015 06/09/2015 13/09/2015 20/09/2015 27/09/2015 04/10/2015 11/10/2015 18/10/2015 25/10/2015 01/11/2015 08/11/2015 15/11/2015 22/11/2015 29/11/2015 06/12/2015 13/12/2015 20/12/2015 27/12/2015 03/01/2016 10/01/2016 17/01/2016 24/01/2016 31
Item Descripción Duracion Inicio Fin
M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D

1.0 OBRAS PROVISIONALES,SEGURIDAD Y SALUD 131 días 01/09/2015 30/01/2016

1.1 OBRAS PROVISIONALES, SEGURIDAD Y SALUD 131 días 01/09/2015 30/01/2016

1.1.1 OBRAS PROVISIONALES 131 días 01/09/2015 30/01/2016

2 días
1.1.1.1 OFICINAS,ALMACEN,COMEDOR Y VESTUARIOS 2 días 01/09/2015 02/09/2015

1 día
1.1.1.2 CARTEL DE OBRA 1 días 04/09/2015 04/09/2015

131 días
1.1.1.3 MOVILIZACION Y DESMOVILIZACION DE EQUIPO PESADO 131 días 01/09/2015 30/01/2016

1.1.2 SEGURIDAD Y SALUD 131 días 01/09/2015 30/01/2016

1 día
1.1.2.1 EQUIPO DE PROTECCION 1 días 01/09/2015 01/09/2015

92 días
1.1.2.2 SEÑALIZACION TEMPORAL 92 días 04/09/2015 19/12/2015

131 días
1.1.2.3 CAPACITACION EN SEGURIDAD Y SALUD 131 días 01/09/2015 30/01/2016

RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN 131 días


1.1.2.4 131 días 01/09/2015 30/01/2016
SEGURIDAD Y SALUD
MUNICIPALIDAD DISTRITAL DE TANTAMAYO

PROGRAMACIÓN DE OBRA
PROYECTO : "CREACION DE PISTAS, VEREDAS Y CUNETAS EN EL JR. SAN PEDRO DE PARIARCA DE LA COMUNIDAD CAMPESINA DE SAN
PEDRO DE PARIARCA, EN EL DISTRITO DE TANTAMAYO - HUAMALIES - HUANUCO"
ETAPA 3.0 : COSTOS AMBIENTALES
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE TANTAMAYO
UBICACION : DPTO:HUANUCO PROV:HUAMALIES DIST:TANTAMAYO LOC:SAN PEDRO DE PARIARCA
FECHA PROYECTO : 12/06/2015
01/09/2015 06/09/2015 13/09/2015 20/09/2015 27/09/2015 04/10/2015 11/10/2015 18/10/2015 25/10/2015 01/11/2015 08/11/2015 15/11/2015 22/11/2015 29/11/2015 06/12/2015 13/12/2015 20/12/2015 27/12/2015 03/01/2016 10/01/2016 17/01/2016 24/01/2016 31
Item Descripción Duracion Inicio Fin
M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D

3.0 COSTOS AMBIENTALES 131 días 01/09/2015 30/01/2016

3.1 COSTOS AMBIENTALES 131 días 01/09/2015 30/01/2016

PROGRAMA DE MONITOREO AMBIENTAL 131 días


3.1.1 131 días 01/09/2015 30/01/2016