ID Task Task Name Duration Start Finish Predecessors

Mode W
0 Como realizar un plan de trabajo 18.68 days? Fri 8/5/20 Wed 3/6/20
1 Fase I: Inicio y Planificacion 4.63 days? Fri 8/5/20 Thu 14/5/20
2 Elaboracion de sow 0.63 days? Fri 8/5/20 Fri 8/5/20
3 Elaboracion de project plan 0.63 days? Fri 8/5/20 Mon 11/5/202
4 Reunion Kick OFF 0.25 days? Mon 11/5/20Mon 11/5/203
5 Entrega de sow 0.13 days? Mon 11/5/20Mon 11/5/204
6 Firma de SOW 1 day? Mon 11/5/20Tue 12/5/20 5
7 Fin fase de inicio 1 day? Tue 12/5/20 Wed 13/5/206
8 Renovacion de Redes de Datos Corporativa & Ciberseguridad. 1 day Wed 13/5/20Thu 14/5/20 7
9 Fase 2: Implementacion de Funcionalidades & Equipos de Next Gen Fortinet 2.34 days Thu 14/5/20 Mon 1
Perimetro/Horas 18/5/20
10 Levantamiento & Analisis de la Seguridad Perimetral Actual 1 day Thu 14/5/20 Fri 15/5/20
11 Instalacion y Preparacion Inicial Equipos Fortigate 600 E (Sede Principal SIB) 1.34 days Fri 15/5/20 Mon 10
18/5/20
12 Instalacion fisica de los equipos 0.5 days Fri 15/5/20 Mon 18/5/20
13 Conectividad Cableado Electrico 0.06 days Mon 18/5/20Mon 18/5/2012
14 Conexion fisica equipo a la Red LAN,WAN, DMZ, VLAN de servicios de 0.03 days Mon Mon 13
seguridad 18/5/20 18/5/20
15 Asignación IP interface Administración 0.03 days Mon 18/5/20Mon 18/5/2014
16 Asignación IP interface WAN 0.03 days Mon 18/5/20Mon 18/5/2015
17 Asignación IP Interface DMZ 0.03 days Mon 18/5/20Mon 18/5/2016
18 Asignacion IP Interface Servicios de Seguridad 0.03 days Mon 18/5/20Mon 18/5/2017
19 Registro de Equipos en el Site de Fortinet 0.13 days Mon 18/5/20Mon 18/5/2018

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors
Mode W
20 Actualización de Firmware a la Version 6.4.0 0.13 days Mon 18/5/20Mon 18/5/2019
21 Configuración basica de red 0.13 days Mon 18/5/20Mon 18/5/2020
22 Configuración HA 0.25 days Mon 18/5/20Mon 18/5/2021
23 Fin de la instalación y Configuración basica de red. 0 days Mon 18/5/20Mon 18/5/2022
24 Fase 2.1 Implementacion de FortiManager 1.16 days Mon 18/5/20Wed 20/5/209
25 Instalacion de OVF FortiManager en el HyperVisor 0.25 days Mon 18/5/20Tue 19/5/20
26 Configuración de Management IP 0.03 days Tue 19/5/20 Tue 19/5/20 25
27 Configuración Basica de la Red 0.13 days Tue 19/5/20 Tue 19/5/20 26
28 Registro del FortiManager en el Site de Fortinet 0.13 days Tue 19/5/20 Tue 19/5/20 27
29 Asignación de licenciamiento 0.06 days Tue 19/5/20 Tue 19/5/20 28
30 Asignacion de DNS 0.06 days Tue 19/5/20 Tue 19/5/20 29
31 Asignacion de NTP 0.13 days Tue 19/5/20 Tue 19/5/20 30
32 Configuracion SMTP (Si aplica) 0.13 days Tue 19/5/20 Tue 19/5/20 31
33 Configuración de Enrutamiento 0.25 days Tue 19/5/20 Wed 20/5/2032
34 Fin de la instalacion y Configuracion inicial del FortiManager 0 days Wed 20/5/20Wed 20/5/2033
35 Fase 2.2-Configuracion Avanzada FortiManager & Fortigate 600E 4.75 days Wed 20/5/20Tue 26/5/20 24
36 Configuracion de ADOMs 0.13 days Wed 20/5/20Wed 20/5/20
37 Agregacion del dispositivo Firewall al ADOMs 0.13 days Wed 20/5/20Wed 20/5/2036
38 Autorizacion del dispositivo 0.13 days Wed 20/5/20Wed 20/5/2037
39 Import politicas al dispositivo 0.13 days Wed 20/5/20Wed 20/5/2038
40 Configuración de explicit web proxy 0.13 days Wed 20/5/20Wed 20/5/2039
41 Configuración de FSSO Collector Agent Domain Controllers 0.25 days Wed 20/5/20Wed 20/5/2040

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors
Mode W
42 Configuración de grupos de Usuarios 0.25 days Thu 21/5/20 Thu 21/5/20 41
43 Migración del tráfico Outbound ( Tráfico de navegación de los usuarios) 1 day Thu 21/5/20 Fri 22/5/20 42
44 Validación del funcionamiento del tráfico Outbound (Tráfico de navegación de 0.5 days Fri 22/5/20 Fri 22/5/20 43
los usuarios)
45 Migración del tráfico Inbound (Publicación de Servicios y/o Reglas NAT) 1 day Fri 22/5/20 Mon 25/5/2044
46 Validación del funcionamiento del tráfico Inbound (Publicacion de Servicios y/o 0.5 days Mon Tue 26/5/20 45
Reglas NAT) 25/5/20
47 Migración del tráfico VPN 0.38 days Tue 26/5/20Tue 26/5/20 46
48 Validación del funcionamiento del tráfico VPN 0.25 days Tue 26/5/20Tue 26/5/20 47
49 Fin de la Migracion Plataforma Check Point hacia Fortigate 600 E 0 days Tue 26/5/20Tue 26/5/20 48
50 Fase 2.4: Instalacion y Preparacion Inicial Equipos Fortigate 600 E (Site Alterno 6.22 days Fri 8/5/20 Mon
SIB) 18/5/20
51 Instalacion fisica de los equipos 0.5 days Fri 8/5/20 Fri 8/5/20
52 Conectividad Cableado Electrico 0.06 days Fri 8/5/20 Fri 8/5/20 51
53 Conexion fisica equipo a la Red LAN,WAN, DMZ, VLAN de servicios de seguridad 0.03 days Fri 8/5/20 Fri 8/5/20 52
54 Asignación IP interface Administración 0.03 days Fri 8/5/20 Fri 8/5/20 53
55 Asignación IP interface WAN 0.03 days Fri 8/5/20 Fri 8/5/20 54
56 Asignación IP Interface DMZ 0.03 days Fri 8/5/20 Fri 8/5/20 55
57 Asignacion IP Interface Servicios de Seguridad 0.03 days Fri 8/5/20 Fri 8/5/20 56
58 Registro de Equipos en el Site de Fortinet 0.13 days Fri 8/5/20 Fri 8/5/20 57
59 Actualización de Firmware a la Version 6.4.0 0.13 days Fri 8/5/20 Fri 8/5/20 58
60 Configuración basica de red 0.13 days Fri 8/5/20 Mon 11/5/2059
61 Configuración HA 0.25 days Mon 11/5/20Mon 11/5/2060

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Task Name Duration Start Finish Predecessors
Mode W
62 Fin de la instalación y Configuración basica de red. 1 day Mon 11/5/20Tue 12/5/20 61
63 Configuracion Avanzada FortiManager & Fortigate 600E 3.88 days Tue 12/5/20 Mon 18/5/2062
76 Fase 3: Implementacion de Citrix SDWAN SIB/Horas 8.71 days Mon 18/5/20Thu 28/5/20 50
77 Levantamiento, Analisis & Diseno de la Implementacion Citrix SDWAN 1 day Mon 18/5/20Tue 19/5/20
78 Instalacion y Configuración Inicial de SD-WAN MCN 1.85 days Tue 19/5/20 Thu 21/5/20 77
79 Instalacion fisica de los equipos 0.25 days Tue 19/5/20 Tue 19/5/20
80 Management IP interface 0.04 days Tue 19/5/20 Tue 19/5/20 79
81 Instalación de las licencias 0.13 days Tue 19/5/20 Tue 19/5/20 80
82 Upgrade Appliance 0.25 days Tue 19/5/20 Tue 19/5/20 81
83 Configuración basica de red 0.31 days Tue 19/5/20 Wed 20/5/2082
84 Hostname 0.06 days Wed 20/5/20Wed 20/5/2083
85 NTP 0.06 days Wed 20/5/20Wed 20/5/2084
86 DNS Server 0.06 days Wed 20/5/20Wed 20/5/2085
87 Integracion Mail Server 0.69 days Wed 20/5/20Thu 21/5/20 86
88 Configuracion SDWAN MCN 1100-500 1.35 days Thu 21/5/20 Fri 22/5/20 78
89 Configuraciones Global 0.25 days Thu 21/5/20 Thu 21/5/20
90 Creacion de AutoPath para MPLS 0.13 days Thu 21/5/20 Thu 21/5/20 89
91 Creacion de Network Objects (Si Aplica) 0.13 days Thu 21/5/20 Thu 21/5/20 90
92 Configuraciónes de los Sites MCN - Premisa 0.35 days Thu 21/5/20 Thu 21/5/20 91
93 Deifinir interface Groups 1 0.06 days Thu 21/5/20 Thu 21/5/20 92
94 Deifinir interface Groups 2 0.06 days Thu 21/5/20 Fri 22/5/20 93
95 Asignar Dominio de Broadcast a Virtual IP Address 1 0.05 days Fri 22/5/20 Fri 22/5/20 94

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task Task Name Duration Start Finish Predecessors
Mode W
96 Definir Interfaz Identity 0.02 days Fri 22/5/20 Fri 22/5/20 95
97 Asignar Dominio de Broadcast a Virtual IP Address 2 0.03 days Fri 22/5/20 Fri 22/5/20 96
98 Configuración de WAN Links 0.06 days Fri 22/5/20 Fri 22/5/20 97
99 Asignacion de WAN Links en Virtual Path 0.08 days Fri 22/5/20 Fri 22/5/20 98
100 Asignacion de AutoPath de MPLS 0.04 days Fri 22/5/20 Fri 22/5/20 99
101 Configuracion WAN-to-WAN Forwarding para Dynamic Virtual Path 0.08 days Fri 22/5/20 Fri 22/5/20 100
102 Creacion de Site: Sucursal A 0.69 days Fri 22/5/20 Mon 25/5/2088
103 Deifinir interface Groups 1 0.06 days Fri 22/5/20 Fri 22/5/20
104 Deifinir interface Groups 2 0.06 days Fri 22/5/20 Fri 22/5/20 103
105 Asignar Dominio de Broadcast a Virtual IP Address 1 0.06 days Fri 22/5/20 Fri 22/5/20 104
106 Asignar Dominio de Broadcast a Virtual IP Address 2 0.06 days Fri 22/5/20 Fri 22/5/20 105
107 Asignar Dominio de Broadcast LANs en Sucursales 0.09 days Fri 22/5/20 Fri 22/5/20 106
108 Definir Interfaz Identity 0.03 days Fri 22/5/20 Fri 22/5/20 107
109 Configuración de WAN Links 0.08 days Fri 22/5/20 Fri 22/5/20 108
110 Asignacion de WAN Links en Virtual Path 0.1 days Fri 22/5/20 Fri 22/5/20 109
111 Asignacion de AutoPath de MPLS 0.04 days Fri 22/5/20 Mon 25/5/20110
112 Vinculacion WAN Link con SITE MCN 0.08 days Mon 25/5/20Mon 25/5/20111
113 Creacion de Site: Sucursal B 0.69 days Mon 25/5/20Mon 25/5/20102
114 Deifinir interface Groups 1 0.06 days Mon 25/5/20Mon 25/5/20
115 Deifinir interface Groups 2 0.06 days Mon 25/5/20Mon 25/5/20114
116 Asignar Dominio de Broadcast a Virtual IP Address 1 0.06 days Mon 25/5/20Mon 25/5/20115
117 Asignar Dominio de Broadcast a Virtual IP Address 2 0.06 days Mon 25/5/20Mon 25/5/20116

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
ID Task Task Name Duration Start Finish Predecessors
Mode W
118 Asignar Dominio de Broadcast LANs en Sucursales 0.09 days Mon 25/5/20Mon 25/5/20117
119 Definir Interfaz Identity 0.03 days Mon 25/5/20Mon 25/5/20118
120 Configuración de WAN Links 0.08 days Mon 25/5/20Mon 25/5/20119
121 Asignacion de WAN Links en Virtual Path 0.1 days Mon 25/5/20Mon 25/5/20120
122 Asignacion de AutoPath de MPLS 0.04 days Mon 25/5/20Mon 25/5/20121
123 Vinculacion WAN Link con SITE MCN 0.08 days Mon 25/5/20Mon 25/5/20122
124 Creacion de Site: Sucursal C 0.69 days Mon 25/5/20Tue 26/5/20 113
125 Deifinir interface Groups 1 0.06 days Mon 25/5/20Mon 25/5/20
126 Deifinir interface Groups 2 0.06 days Mon 25/5/20Mon 25/5/20125
127 Asignar Dominio de Broadcast a Virtual IP Address 1 0.06 days Mon 25/5/20Mon 25/5/20126
128 Asignar Dominio de Broadcast a Virtual IP Address 2 0.06 days Mon 25/5/20Tue 26/5/20 127
129 Asignar Dominio de Broadcast LANs en Sucursales 0.09 days Tue 26/5/20 Tue 26/5/20 128
130 Definir Interfaz Identity 0.03 days Tue 26/5/20 Tue 26/5/20 129
131 Configuración de WAN Links 0.08 days Tue 26/5/20 Tue 26/5/20 130
132 Asignacion de WAN Links en Virtual Path 0.1 days Tue 26/5/20 Tue 26/5/20 131
133 Asignacion de AutoPath de MPLS 0.04 days Tue 26/5/20 Tue 26/5/20 132
134 Vinculacion WAN Link con SITE MCN 0.08 days Tue 26/5/20 Tue 26/5/20 133
135 Creacion de Site: Sucursal D 0.69 days Tue 26/5/20 Wed 27/5/20124
136 Deifinir interface Groups 1 0.06 days Tue 26/5/20 Tue 26/5/20
137 Deifinir interface Groups 2 0.06 days Tue 26/5/20 Tue 26/5/20 136
138 Asignar Dominio de Broadcast a Virtual IP Address 1 0.06 days Tue 26/5/20 Tue 26/5/20 137
139 Asignar Dominio de Broadcast a Virtual IP Address 2 0.06 days Tue 26/5/20 Tue 26/5/20 138

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
ID Task Task Name Duration Start Finish Predecessors
Mode W
140 Asignar Dominio de Broadcast LANs en Sucursales 0.09 days Tue 26/5/20 Tue 26/5/20 139
141 Definir Interfaz Identity 0.03 days Tue 26/5/20 Tue 26/5/20 140
142 Configuración de WAN Links 0.08 days Tue 26/5/20 Tue 26/5/20 141
143 Asignacion de WAN Links en Virtual Path 0.1 days Tue 26/5/20 Wed 27/5/20142
144 Asignacion de AutoPath de MPLS 0.04 days Wed 27/5/20Wed 27/5/20143
145 Vinculacion WAN Link con SITE MCN 0.08 days Wed 27/5/20Wed 27/5/20144
146 Configuracion de Enrutamiento, Manejos de Archivos de Configuracion & 1.75 days Wed Thu 28/5/20 135
Optimizacion 27/5/20
147 Creacion de Enrutamiento entre Sites (Preferiblemente Dinamico) 0.38 days Wed 27/5/20Wed 27/5/20
148 Validacion de Enrutamiento entre Sitios SDWAN y no SDWAN 0.13 days Wed 27/5/20Wed 27/5/20147
149 Definicion de Dynamic Virtual Path SDWAN Clients 0.13 days Wed 27/5/20Wed 27/5/20148
150 Optimizacion de QoS entre SITEs 0.25 days Wed 27/5/20Thu 28/5/20 149
151 Descarga de Archivos de Configuracion del MCN para los SDWAN Clients 0.25 days Thu 28/5/20 Thu 28/5/20 150

152 Carga de Archivo de configuracion en los SDWAN Client 0.25 days Thu 28/5/20 Thu 28/5/20 151
153 Prueba de escritorio antes del primer Despliegue del SDWAN 0.25 days Thu 28/5/20 Thu 28/5/20 152
154 Documentacion Tecnica 0.13 days Thu 28/5/20 Thu 28/5/20 153
155 Fase 3.1: Despliegue de SDWAN Clients en Sucursales. 3.75 days Thu 28/5/20 Wed 3/6/20 76
156 Instalacion & Configuracion en Sucursales - SDWAN Clients Sin definir 0.69 days Thu 28/5/20 Fri 29/5/20

157 Instalacion fisica del equipo 0.25 days Thu 28/5/20 Fri 29/5/20
158 Instalación de las licencias 0.06 days Fri 29/5/20 Fri 29/5/20 157
159 Management IP interface 0.06 days Fri 29/5/20 Fri 29/5/20 158

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
ID Task Task Name Duration Start Finish Predecessors
Mode W
160 Upgrade Appliance 0.13 days Fri 29/5/20 Fri 29/5/20 159
161 Configuración Change management 0.06 days Fri 29/5/20 Fri 29/5/20 160
162 Validacion de la operacion de la Localidad 0.13 days Fri 29/5/20 Fri 29/5/20 161
163 Fin de la Instalacion & Configuracion en Sucursales - SDWAN Clients 0 days Fri 29/5/20 Fri 29/5/20 162
164 Instalacion & Configuracion en Sucursales - SDWAN Clients Sin definir 0.69 days Fri 29/5/20 Mon 1/6/20 156

165 Instalacion fisica del equipo 0.25 days Fri 29/5/20 Fri 29/5/20
166 Instalación de las licencias 0.06 days Fri 29/5/20 Fri 29/5/20 165
167 Management IP interface 0.06 days Fri 29/5/20 Fri 29/5/20 166
168 Upgrade Appliance 0.13 days Fri 29/5/20 Mon 1/6/20 167
169 Configuración Change management 0.06 days Mon 1/6/20 Mon 1/6/20 168
170 Validacion de la operacion de la Localidad 0.13 days Mon 1/6/20 Mon 1/6/20 169
171 Fin de la Instalacion & Configuracion en Sucursales - SDWAN Clients 0 days Mon 1/6/20 Mon 1/6/20 170
172 Instalacion & Configuracion en Sucursales - SDWAN Clients Sin definir 0.69 days Mon 1/6/20 Mon 1/6/20 164

173 Instalacion fisica del equipo 0.25 days Mon 1/6/20 Mon 1/6/20
174 Instalación de las licencias 0.06 days Mon 1/6/20 Mon 1/6/20 173
175 Management IP interface 0.06 days Mon 1/6/20 Mon 1/6/20 174
176 Upgrade Appliance 0.13 days Mon 1/6/20 Mon 1/6/20 175
177 Configuración Change management 0.06 days Mon 1/6/20 Mon 1/6/20 176
178 Validacion de la operacion de la Localidad 0.13 days Mon 1/6/20 Mon 1/6/20 177
179 Fin de la Instalacion & Configuracion en Sucursales - SDWAN Clients 0 days Mon 1/6/20 Mon 1/6/20 178

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
ID Task Task Name Duration Start Finish Predecessors
Mode W
180 Instalacion & Configuracion en Sucursales - SDWAN Clients Sin definir 1.69 days Mon 1/6/20 Wed 3/6/20 172

181 Instalacion fisica del equipo 0.25 days Mon 1/6/20 Tue 2/6/20
182 Instalación de las licencias 0.06 days Tue 2/6/20 Tue 2/6/20 181
183 Management IP interface 0.06 days Tue 2/6/20 Tue 2/6/20 182
184 Upgrade Appliance 0.13 days Tue 2/6/20 Tue 2/6/20 183
185 Configuración Change management 0.06 days Tue 2/6/20 Tue 2/6/20 184
186 Validacion de la operacion de la Localidad 0.13 days Tue 2/6/20 Tue 2/6/20 185
187 Fin de la Instalacion & Configuracion en Sucursales - SDWAN Clients 0 days Tue 2/6/20 Tue 2/6/20 186
188 Validacion de Operaciones de todas las Localidades & Comunicacion Dynamic 1Virtual
day Path Tue 2/6/20 Wed 3/6/20 187
189 Fase 5: Cierre 3.44 days Fri 8/5/20 Wed 13/5/20
190 Aceptacion de entregables 0.5 days Fri 8/5/20 Fri 8/5/20
191 Recopilacion Final de las preDocumentacion Fases 2,3,4 1.25 days Fri 8/5/20 Mon 11/5/20190
192 Elaboracion documentacion tecnica 0.94 days Mon 11/5/20Tue 12/5/20 191
193 Elaboracion informe de cierre 0.63 days Tue 12/5/20 Wed 13/5/20192
194 Entrega Informe de cierre 0.13 days Wed 13/5/20Wed 13/5/20193
195 Cierre 0 days Wed 13/5/20Wed 13/5/20194

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
10 May '20 17 May '20 24 May '20 31 May '20 7 Jun '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Recurso 1
Recurso 1
Recurso 1
Recurso 1

Recurso 2
Recurso 2
Recurso 2

Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
10 May '20 17 May '20 24 May '20 31 May '20 7 Jun '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Recurso 2
Recurso 2
Recurso 2
18/5

Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2
20/5

Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
10 May '20 17 May '20 24 May '20 31 May '20 7 Jun '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Recurso 2
Recurso 2
Recurso 2

Recurso 2
Recurso 2

Recurso 2
Recurso 2
26/5

Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2
Recurso 2

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12
10 May '20 17 May '20 24 May '20 31 May '20 7 Jun '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Recurso 3

Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3

Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 13
10 May '20 17 May '20 24 May '20 31 May '20 7 Jun '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3

Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3

Recurso 3
Recurso 3
Recurso 3
Recurso 3

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 14
10 May '20 17 May '20 24 May '20 31 May '20 7 Jun '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3

Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3

Recurso 3
Recurso 3
Recurso 3
Recurso 3

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 15
10 May '20 17 May '20 24 May '20 31 May '20 7 Jun '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3

Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3

Recurso 3
Recurso 3
Recurso 3

Recurso 3
Recurso 3
Recurso 3

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 16
10 May '20 17 May '20 24 May '20 31 May '20 7 Jun '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Recurso 3
Recurso 3
Recurso 3
29/5

Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
1/6

Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
1/6

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 17
10 May '20 17 May '20 24 May '20 31 May '20 7 Jun '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
Recurso 3
2/6
Recurso 3

Recurso 1
Recurso 2;Recurso 3
Recurso 2;Recurso 3
Recurso 1
Recurso 1
13/5

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Como realizar un plan d
Summary Manual Summary Rollup Progress
Date: Mon 18/5/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only