FORMATO : VM - 1
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA EJECUCION PRESUPUESTAL DIRECTA
META : 13 FUENTE DE FINANCIAMIENTO : CANON Y SOBRE CANON
OBRA / PIP : "MEJORAMIENTO, AMPLIACION DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO EN LA COMUNI
MES / AÑO : MAYO - 2,017
MONTO VALOR REFERENCIAL : S/. 1,098,519.37
ASIGNACION PRESUPUESTAL - 2015 : S/. 600,000.00
DESCRIPCION PRESUPUESTO BASE AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %
01.04 PASE AEREO L=6.00 ML EN LINEA DE CONDUCCION (2.00 UND) - 0.00 0.00
01.04.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 16.00 1.25 20.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 16.00 20.00 100.00%
01.04.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.44 14.00 20.16 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.44 20.16 100.00%
01.04.03 CONCRETO FC=175 KG/CM2 m3 1.44 432.90 623.38 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.44 623.38 100.00%
01.04.04 ENCOFRADO Y DESENCOFRADO m2 9.60 16.95 162.72 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 9.60 162.72 100.00%
01.04.05 SUMINISTRO DE ACCESORIOS SANITARIOS GLB 2.00 149.80 299.60 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.00 299.60 100.00%
01.05 CAMARA DE REUNION ( 2.00 UND) - 0.00 0.00
01.05.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 2.32 1.25 2.90 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.32 2.90 100.00%
01.05.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.94 14.00 13.16 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.94 13.16 100.00%
01.05.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 2.36 10.50 24.78 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.36 24.78 100.00%
01.05.04 ENCOFRADO Y DESENCOFRADO m2 10.08 16.95 170.86 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 10.08 170.86 100.00%
01.05.05 ACERO DE REFUERZO FY=4200 kg 52.82 4.76 251.42 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 52.82 251.42 100.00%
01.05.06 CONCRETO FC=175 KG/CM2 m3 0.77 432.90 333.33 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.77 333.33 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.05.07 m2 5.04 27.79 140.06 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.04 140.06 100.00%
MEZCLA 1:2
01.05.08 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.76 18.00 103.68 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.76 103.68 100.00%
01.05.09 PINTURA EN MUROS m2 6.40 7.65 48.96 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 6.40 48.96 100.00%
01.05.10 SUMINISTRO DE ACCESORIOS CAMARA DE REUNION GLB 2.00 218.45 436.90 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.00 436.90 100.00%
01.05.11 CAJA DE VALVULAS DE CAMARA DE REUNION (2.00 UND) - 0.00 0.00
01.05.11.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.49 14.00 6.86 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.49 6.86 100.00%
01.05.11.02 ENCOFRADO Y DESENCOFRADO m2 2.24 16.95 37.97 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.24 37.97 100.00%
01.05.11.03 ACERO DE REFUERZO FY=4200 kg 4.65 4.76 22.13 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.65 22.13 100.00%
01.05.11.04 CONCRETO FC=175 KG/CM2 m3 0.18 432.90 77.92 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.18 77.92 100.00%
01.05.11.05 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 0.48 18.00 8.64 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.48 8.64 100.00%
01.05.11.06 PINTURA EN MUROS m2 0.48 7.65 3.67 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.48 3.67 100.00%
SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE C.R.
01.05.11.07 GLB 1.00 191.45 191.45 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 191.45 100.00%
(1")
SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE C.R.
01.05.11.08 GLB 1.00 245.45 245.45 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 245.45 100.00%
(11/2")
01.06 CAMARA DE DISTRIBUCION DE CAUDALES (4.00 UND) - 0.00 0.00
01.06.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 7.60 1.25 9.50 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 7.60 9.50 100.00%
01.06.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 4.18 14.00 58.52 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.18 58.52 100.00%
01.06.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 4.18 10.50 43.89 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.18 43.89 100.00%
01.06.04 FILTRO DE GRAVA (MAT. SELECCIONADO) m3 0.06 133.50 8.01 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.06 8.01 100.00%
01.06.05 CONCRETO CICLOPEO FC=140 KG/CM2 MEZCLA 1:10 m3 0.20 273.86 54.77 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.20 54.77 100.00%
01.06.06 CONCRETO FC=175 KG/CM2 m3 0.21 432.90 90.91 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.21 90.91 100.00%
01.06.07 CONCRETO FC=210 KG/CM2 m3 5.29 494.88 2,617.92 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.29 2,617.92 100.00%
01.06.08 ENCOFRADO Y DESENCOFRADO m2 51.78 16.95 877.67 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 51.78 877.67 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.06.09 m2 58.44 27.79 1,624.05 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 58.44 1,624.05 100.00%
MEZCLA 1:2
01.06.10 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 30.92 18.00 556.56 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 30.92 556.56 100.00%
01.06.11 PINTURA EN MUROS m2 30.92 7.65 236.54 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 30.92 236.54 100.00%
01.06.12 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. 01 GLB 1.00 844.00 844.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 844.00 100.00%
01.06.13 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. 02 GLB 1.00 844.00 844.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 844.00 100.00%
01.06.14 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. 03 GLB 1.00 844.00 844.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 844.00 100.00%
01.06.15 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. 04 GLB 1.00 844.00 844.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 844.00 100.00%
01.07 CAMARA DE FILTRO PARA TRATAMIENTO DE AGUA POTABLE (1.00 UND) - 0.00 0.00
01.07.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.26 1.25 1.58 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.26 1.58 100.00%
01.07.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.76 14.00 10.64 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.76 10.64 100.00%
01.07.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 0.95 10.50 9.98 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.95 9.98 100.00%
01.07.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 1.26 26.24 33.06 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.26 33.06 100.00%
01.07.05 ENCOFRADO Y DESENCOFRADO m2 6.00 16.95 101.70 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 6.00 101.70 100.00%
01.07.06 ACERO DE REFUERZO FY=4200 kg 36.68 4.76 174.60 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 36.68 174.60 100.00%
01.07.07 CONCRETO FC=175 KG/CM2 m3 0.43 432.90 186.15 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.43 186.15 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.07.08 m2 2.16 27.79 60.03 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.16 60.03 100.00%
MEZCLA 1:2
01.07.09 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 3.91 18.00 70.38 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3.91 70.38 100.00%
01.07.10 PINTURA EN MUROS m2 3.91 7.65 29.91 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3.91 29.91 100.00%
01.07.11 MATERIAL SELECCIONADO PARA FILTRO m3 0.42 133.50 56.07 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.42 56.07 100.00%
01.07.12 SUMINISTRO DE ACCESORIOS CAMARA DE FILTRO GLB 1.00 503.80 503.80 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 503.80 100.00%
DESCRIPCION PRESUPUESTO BASE AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %
01.09.13 PINTURA EN MUROS m2 20.85 7.65 159.50 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 20.85 159.50 100.00%
01.09.14 CAJA DE VALVULAS DE RESERORIO DE V=3.00 M3 ( 01 UND) - 0.00 0.00
01.09.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.24 1.25 1.55 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.24 1.55 100.00%
01.09.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.05 14.00 14.70 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.05 14.70 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
01.09.14.03 m3 1.31 10.50 13.76 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.31 13.76 100.00%
BUGGIE
01.09.14.04 ENCOFRADO Y DESENCOFRADO m2 8.90 16.95 150.86 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 8.90 150.86 100.00%
01.09.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 45.85 6.19 283.81 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 45.85 283.81 100.00%
01.09.14.06 CONCRETO FC=175 KG/CM2 m3 0.70 432.90 303.03 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.70 303.03 100.00%
SUMINISTRO DE ACCESORIOS DE ENTRADA RESERVORIO
01.09.14.07 GLB 1.00 321.34 321.34 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 321.34 100.00%
V=3.00 M3
SUMINISTRO DE ACCESORIOS DE SALIDA RESERVORIO
01.09.14.08 GLB 1.00 576.52 576.52 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 576.52 100.00%
V=3.00 M3
SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOSE
01.09.14.09 GLB 1.00 439.34 439.34 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 439.34 100.00%
RESERVORIO V=3.00 M3
01.09.14.10 SUMINISTRO DE TAPA METALICA GLB 1.00 155.45 155.45 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 155.45 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.09.14.11 m2 3.30 27.79 91.71 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3.30 91.71 100.00%
MEZCLA 1:2
01.09.14.12 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.71 18.00 102.78 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.71 102.78 100.00%
01.09.14.13 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.04 38.56 100.00%
01.09.15 TRABAJOS DE PROTECCION DE RESERVORIO V=5.00 M3( 01 UND) - 0.00 0.00
01.09.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.29 14.00 4.06 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.29 4.06 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
01.09.15.02 m3 0.37 10.50 3.89 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.37 3.89 100.00%
BUGGIE
01.09.15.03 CONCRETO FC=175 KG/CM2 m3 0.29 432.90 125.54 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.29 125.54 100.00%
01.09.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 8.00 55.75 446.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 8.00 446.00 100.00%
MALLA METALICA PROTECTORA CON ALAMBRE N.12 X
01.09.15.05 m 21.60 90.00 1,944.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 21.60 1,944.00 100.00%
COCADAS DE 2" H=2.00M
01.09.15.06 PUERTA METALICA S/DISEÑO und 1.00 200.00 200.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 200.00 100.00%
01.09.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO - 0.00 0.00
01.15.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 25.00 1.25 31.25 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 25.00 31.25 100.00%
01.15.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 5.00 14.00 70.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.00 70.00 100.00%
01.15.03 CONCRETO FC=210 KG/CM2 m3 0.35 494.88 173.21 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.35 173.21 100.00%
01.15.04 CONCRETO FC=175 KG/CM2 m3 1.60 432.90 692.64 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.60 692.64 100.00%
01.15.05 ENCOFRADO Y DESENCOFRADO m2 5.60 16.95 94.92 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.60 94.92 100.00%
01.15.06 ACERO DE REFUERZO FY=4200 kg 107.99 4.76 514.03 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 107.99 514.03 100.00%
01.15.07 SUMINISTRO DE CABLE DE 1/4" m 27.05 13.00 351.65 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 27.05 351.65 100.00%
01.15.08 SUMINISTRO DE ACCESORIOS DE CERRAJERIA GLB 1.00 740.40 740.40 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 740.40 100.00%
SUMINISTRO DE ACCESORIOS SANITARIOS PASE AEREO
01.15.09 GLB 1.00 272.00 272.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 272.00 100.00%
L=18.ML
01.16 PASE AEREO L=6.00 ML EN RED DE DISTRIBUCION (1.00 UND) - 0.00 0.00
01.16.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 8.00 1.25 10.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 8.00 10.00 100.00%
01.16.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.72 14.00 10.08 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.72 10.08 100.00%
01.16.03 CONCRETO FC=175 KG/CM2 m3 0.72 432.90 311.69 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.72 311.69 100.00%
01.16.04 ENCOFRADO Y DESENCOFRADO m2 4.80 16.95 81.36 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.80 81.36 100.00%
01.16.05 SUMINISTRO DE ACCESORIOS SANITARIOSS GLB 1.00 120.80 120.80 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 120.80 100.00%
01.17 CAJA DE VALVULAS DE PASO DE CONEX. DOMICIL. VALVULA ESFERICA ( 65.00 UND) - 0.00 0.00
01.17.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 6.50 14.00 91.00 0.00 0.00% 1.20 16.80 18.46% 1.20 16.80 18.46% 5.30 74.20 81.54%
01.17.02 ENCOFRADO Y DESENCOFRADO m2 61.10 16.95 1,035.65 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 61.10 1,035.65 100.00%
01.17.03 CONCRETO FC=175 KG/CM2 m3 4.05 432.90 1,753.25 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.05 1,753.25 100.00%
01.17.04 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 46.80 18.00 842.40 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 46.80 842.40 100.00%
01.17.05 PINTURA EN MUROS m2 46.80 7.65 358.02 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 46.80 358.02 100.00%
01.17.06 ACCESORIOS PARA CONEXION DOMICILIARIA 1/2" und 65.00 186.30 12,109.50 0.00 0.00% 2.00 372.60 3.08% 2.00 372.60 3.08% 63.00 11,736.90 96.92%
01.18 PILETAS DOMICILIARIAS (65.00 UND) - 0.00 0.00
01.18.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 31.20 1.25 39.00 0.00 0.00% 0.96 1.20 3.08% 0.96 1.20 3.08% 30.24 37.80 96.92%
01.18.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.95 14.00 27.30 0.00 0.00% 0.18 2.52 9.23% 0.18 2.52 9.23% 1.77 24.78 90.77%
01.18.03 SUMINISTRO DE ACCESORIOS DE PILETA GLB 65.00 91.45 5,944.25 0.00 0.00% 2.00 182.90 3.08% 2.00 182.90 3.08% 63.00 5,761.35 96.92%
01.18.04 ENCOFRADO Y DESENCOFRADO m2 215.96 16.95 3,660.52 0.00 0.00% 6.65 112.72 3.08% 6.65 112.72 3.08% 209.31 3,547.80 96.92%
01.18.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 307.13 6.19 1,901.13 0.00 0.00% 85.06 526.52 27.70% 85.06 526.52 27.70% 222.07 1,374.61 72.30%
01.18.06 CONCRETO FC=175 KG/CM2 m3 5.66 432.90 2,450.21 0.00 0.00% 0.18 77.92 3.18% 0.18 77.92 3.18% 5.48 2,372.29 96.82%
01.18.07 CONCRETO CICLOPEO FC=140 KG/CM2 MEZCLA 1:10 m3 35.10 273.86 9,612.49 0.00 0.00% 0.27 73.94 0.77% 0.27 73.94 0.77% 34.83 9,538.55 99.23%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.18.08 m2 96.36 27.79 2,677.84 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 96.36 2,677.84 100.00%
MEZCLA 1:2
01.18.09 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 90.35 18.00 1,626.30 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 90.35 1,626.30 100.00%
02 ADECUADA INFRAESTRUCTURA PARA DISPOSICION DE EXCRETAS Y AGUAS SERVIDAS - 0.00 0.00
02.01 LETRINAS DOMICILIARIAS CON BIODIGESTOR (63.00 UND) - 0.00 0.00
02.01.01 TRABAJOS PRELIMINARES - 0.00 0.00
02.01.01.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 606.06 1.25 757.58 0.00 0.00% 519.48 649.35 85.71% 519.48 649.35 85.71% 86.58 108.23 14.29%
02.01.02 MOVIMIENTO DE TIERRAS - 0.00 0.00
02.01.02.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 85.05 14.00 1,190.70 0.00 0.00% 63.45 888.30 74.60% 63.45 888.30 74.60% 21.60 302.40 25.40%
02.01.02.02 EXCAVACION EN TIERRA ZANJA DE 0.50 X 0.70 m 453.60 4.20 1,905.12 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 453.60 1,905.12 100.00%
02.01.02.03 RELLENO Y COMPACTACION MANUAL DE ZANJAS m 453.60 3.44 1,560.38 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 453.60 1,560.38 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
02.01.02.04 m3 567.00 10.50 5,953.50 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 567.00 5,953.50 100.00%
BUGGIE
02.01.03 OBRAS DE CONCRETO SIMPLE - 0.00 0.00
CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON
02.01.03.01 m3 85.05 306.43 26,061.87 0.00 0.00% 40.50 12,410.42 47.62% 40.50 12,410.42 47.62% 44.55 13,651.45 52.38%
30% PIEDRA MEDIANA
02.01.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS m2 247.59 27.38 6,779.01 0.00 0.00% 58.95 1,614.05 23.81% 58.95 1,614.05 23.81% 188.64 5,164.96 76.19%
02.01.03.03 CONCRETO FC=140 KG/CM2 + 30 % PM EN SOBRECIMIENTOS m3 18.43 366.30 6,750.91 0.00 0.00% 4.40 1,611.72 23.87% 4.40 1,611.72 23.87% 14.03 5,139.19 76.13%
02.01.04 OBRAS DE CONCRETO ARMADO - 0.00 0.00
02.01.04.01 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 49.14 27.38 1,345.45 0.00 0.00% 3.12 85.43 6.35% 3.12 85.43 6.35% 46.02 1,260.02 93.65%
02.01.04.02 ACERO DE REFUERZO 3/8" FY=4200 KG/CM2 EN VIGAS kg 190.01 5.67 1,077.36 0.00 0.00% 114.84 651.14 60.44% 114.84 651.14 60.44% 75.17 426.22 39.56%
02.01.04.03 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 126.00 6.19 779.94 0.00 0.00% 57.75 357.47 45.83% 57.75 357.47 45.83% 68.25 422.47 54.17%
02.01.04.04 CONCRETO FC=210 KG/CM2 m3 3.28 494.88 1,623.21 0.00 0.00% 0.47 232.59 14.33% 0.47 232.59 14.33% 2.81 1,390.62 85.67%
02.01.05 ALBAÑILERIA - 0.00 0.00
MURO DE BLOQUE HUECO DE CONCRETO 15 X 20 X 40 CM
02.01.05.01 m2 812.39 55.74 45,282.62 0.00 0.00% 58.05 3,235.71 7.15% 58.05 3,235.71 7.15% 754.34 42,046.91 92.85%
MEZCLA 1:5
02.01.06 PISOS Y PAVIMENTOS - 0.00 0.00
02.01.06.01 BASE DE PIEDRA m2 152.46 19.79 3,017.18 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 152.46 3,017.18 100.00%
DESCRIPCION PRESUPUESTO BASE AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %
6 TOTAL VALORIZACION (1)+(2)+(3)+(4)+(5)+(6) 1,098,519.37 - 0.00% 55,757.54 5.08% 55,757.54 5.08% 1,042,761.83 94.92%
VALORIZACION ADICIONAL POR MAYORES METRADOS Nº 002
FORMATO : VM - 1
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA EJECUCION PRESUPUESTAL DIRECTA
META : 105 FUENTE DE FINANCIAMIENTO : CANON Y SOBRE CANON
OBRA / PIP : "MEJORAMIENTO, AMPLIACION DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO EN LA COMUN
MES / AÑO : JULIO - 2,015
MONTO VALOR REFERENCIAL :
ASIGNACION PRESUPUESTAL : S/. 0.00
02 MOVIMIENTO DE TIERRAS
02.03 RELLENO CON MATERIAL DE PRESTAMO LATERAL M3 365.96 0.00 0.00 0.00 0.00 -
08 CANTERAS
1 COSTO DIRECTO - - - - -
PORCENTAJE DE AVANCE ( % ) 0.00% 0.00% 0.00% 0.00%
2 GASTOS GENERALES ( 14.99 % ) - - 0.00% - 0.00% - 0.00% - 0.00%
3 GASTOS DE INSPECCION ( 5.06 % ) - - 0.00% - 0.00% - 0.00% - 0.00%
4 GASTOS DE EXPEDIENTE TECNICO - - 0.00% - 0.00% - 0.00% - 0.00%
5 GASTOS DE EVALUACION DEL EXPEDIENTE TECNICO - - Err:509 - 0.00% - 0.00% - 0.00%
6 GASTOS DE LIQUIDACION - - 0.00% - Err:509 - Err:509 - Err:509
7 TOTAL VALORIZACION (1)+(2)+(3)+(4)+(5)+(6) - - 0.00% - 0.00% - 0.00% - 0.00%
VALORIZACION ADICIONAL POR PARTIDA NUEVA Nº 004
FORMATO : VM - 1
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA EJECUCION PRESUPUESTAL DIRECTA
META : 105 FUENTE DE FINANCIAMIENTO : CANON Y SOBRE CANON
OBRA / PIP : "MEJORAMIENTO, AMPLIACION DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO EN LA COMU
MES / AÑO : JULIO - 2,015
MONTO VALOR REFERENCIAL :
ASIGNACION PRESUPUESTAL : S/. 0.00
1 COSTO DIRECTO - - - - -
PORCENTAJE DE AVANCE ( % ) 0.00% 0.01% 0.00% 0.00%
2 GASTOS GENERALES ( 14.99 % ) - - 0.00% - 0.01% - 0.00% - 0.00%
3 GASTOS DE INSPECCION ( 5.06 % ) - - 0.00% - 0.01% - 0.00% - 0.00%
4 GASTOS DE EXPEDIENTE TECNICO - - 0.00% - 0.01% - 0.00% - 0.00%
5 GASTOS DE EVALUACION DEL EXPEDIENTE TECNICO - - Err:509 - Err:509 - Err:509 - 0.00%
6 GASTOS DE LIQUIDACION - - 0.00% - 0.01% - 0.00% -
7 TOTAL VALORIZACION (1)+(2)+(3)+(4)+(5)+(6) - - 0.00% - 0.01% - 0.00% -
RESUMEN DE VALORIZACION DE AVANCE DE OBRA Nº 004
FORMATO : VM - 1
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA EJECUCION PRESUPUESTARIA DIRECTA
TOTAL VALORIZACION 1,098,519.37 - 0.00% 55,757.54 5.08% 55,757.54 5.08% 1,042,761.83 94.92%
CALENDARIO DE AVANCE DE OBRA REPROGRAMADO Y EJECUTADO
FORMATO: Nº 07 - LT
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA INICIO DE OBRA : 08/12/ 2,014 AMPLIACION DE PLAZO : 16 DIAS CALENDARIOS
OBRA / PIP : "MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA" PLAZO PROGRAMADO : 120 DIAS CALENDARIOS PLAZO REPROGRAMADO : 136 DIAS CALENDARIOS
META : 105 TERMINO DE OBRA REPROGRAMADO : 06/04/ 2,015 FECHA REAL DE TERMINO DE OBRA : 19/09/ 2,015
MONTO VALOR REFERENCIAL : S/. 448,698.85
CODIGO
PRESUPUESTO BASE PROGRAMACION MENSUAL
PARTIDA DESCRIPCION DE LA PARTIDA P/E
UND. METRADO PRECIO S/. PARCIAL S/. DICIEMBRE - 2,014 ENERO - 2,015 JUNIO - 2,015 JULIO - 2,015 AGOSTO - 2,015 SETIEMBRE - 2,015
L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 08/12/2,014 INICIO DE OBRA 09/01/2,015 FIN DE OBRA 1º ETAPA 09/06/2,015 REINICIO DE OBRA
01.01 CARTEL DE OBRA m2 17.28 149.20 2,578.18 FIN DE OBRA 19/09/2,015
P 2,578.18 100.00%
E 2,578.18 100.00%
01.02 MOVILIZACION Y DESMOVILIZACION GLB 1.00 7,756.64 7,756.64
P 775.66 10.00% 775.66 10.00% 2,326.99 30.00% 387.83 5.00% 387.84 5.00% 3,102.66 40.00%
E 853.23 11.00% 775.66 10.00% 2,249.43 29.00% 387.83 5.00% 232.70 3.00% 3,257.79 42.00%
01.03 CAMPAMENTO DE OBRA m2 120.00 138.05 16,566.00
P 10,767.90 65.00% 2,153.58 13.00% 3,644.52 22.00%
E - -
03 PAVIMEN TOS
03.01 SUB-BASE GRANULAR (E = 0.075 M, DM = 3.60 KM) M2 34,756.00 1.67 58,042.52
P - - - 14,510.63 25.00% 43,531.89 75.00%
E - - - - 4,632.32 100.00% -
CALENDARIO DE AVANCE DE OBRA REPROGRAMADO Y EJECUTADO
FORMATO: Nº 07 - LT
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA INICIO DE OBRA : 08/12/ 2,014 AMPLIACION DE PLAZO : 16 DIAS CALENDARIOS
OBRA / PIP : "MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA" PLAZO PROGRAMADO : 120 DIAS CALENDARIOS PLAZO REPROGRAMADO : 136 DIAS CALENDARIOS
META : 105 TERMINO DE OBRA REPROGRAMADO : 06/04/ 2,015 FECHA REAL DE TERMINO DE OBRA : 19/09/ 2,015
MONTO VALOR REFERENCIAL : S/. 448,698.85
CODIGO
PRESUPUESTO BASE PROGRAMACION MENSUAL
PARTIDA DESCRIPCION DE LA PARTIDA P/E
UND. METRADO PRECIO S/. PARCIAL S/. DICIEMBRE - 2,014 ENERO - 2,015 JUNIO - 2,015 JULIO - 2,015 AGOSTO - 2,015 SETIEMBRE - 2,015
L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
VIENEN…
04.12 COLOCACION Y ACONDICIONAMIENTO DE MUERTOS Y VIGAS ML 112.00 24.10 2,699.20
P - - - - 2,699.20 100.00%
E - - - - 2,699.20 100.00% -
04.13 ENTABLADO CON MADERA ASERRADA ADQ. M2 54.60 110.30 6,022.38
P - - - - 6,022.38 100.00%
E - - - - 6,022.38 100.00% -
04.14 CONFORMACION DE CUNETAS KM 10.00 401.30 4,013.00
P### - - 601.95 15.00% 2,608.45 65.00% 802.60 20.00%
E - - 342.45 100.00%
06.02 SEÑALES INFORMATIVAS und 14.00 256.75 3,594.50
P### - - - - 3,594.50 100.00%
###
E### - - -
07 VARIOS
07.02 REACONDICIONAMIENTO DE TALUDES M2 240.00 2.92 700.80
P### - - - 700.80 100.00%
E - - 700.80 100.00%
08 CANTERAS
08.01 ROCE Y LIMPIEZA HA 2.30 1,505.68 3,463.06
P### - 692.61 20.00% 1,038.92 30.00% 692.61 20.00% 1,038.92 30.00%
E 6,175.40 100.00% - - -
08.03 CAMINOS DE ACCESO A CANTERA KM 1.00 8,863.10 8,863.10
P### - 886.31 10.00% - 7,976.79 90.00%
E - - 2,596.48 35.00%
09 MITIGACION DE IMPACTO AMBIENTAL
09.01 REFORESTACION M2. 1,540.00 2.19 3,372.60
P### - - - 3,372.60 100.00%
COSTO DIRECTO S/. 356,711.47 P 25,728.28 7.21% 13,496.50 3.78% 57,000.52 15.98% 93,860.49 26.31% 77,241.11 21.65% 89,384.57 25.06%
E 25,655.73 7.19% 13,551.72 3.80% 56,496.47 15.84% 92,446.46 25.92% 66,888.68 18.75% 68,603.02 19.23%
GASTOS GENERALES (15.00 %) S/. 53,428.27 P 3,853.58 7.21% 2,021.51 3.78% 8,537.54 15.98% 14,058.43 26.31% 11,569.18 21.65% 13,388.03 25.06%
E 3,842.72 7.19% 2,029.78 3.80% 8,462.05 15.84% 13,846.64 25.92% 10,018.59 18.75% 10,275.36 19.23%
GASTOS DE INSPECCION (5.07 %) S/. 18,059.11 P 1,302.54 7.21% 683.28 3.78% 2,885.75 15.98% 4,751.84 26.31% 3,910.46 21.65% 4,525.24 25.06%
E 1,298.86 7.19% 686.08 3.80% 2,860.23 15.84% 4,680.26 25.92% 3,386.35 18.75% 3,473.14 19.23%
GASTOS DE EXPEDIENTE TECNICO S/. 12,000.00 P 865.52 7.21% 454.03 3.78% 1,917.53 15.98% 3,157.53 26.31% 2,598.44 21.65% 3,006.95 25.06%
E 863.08 7.19% 455.89 3.80% 1,900.58 15.84% 3,109.96 25.92% 2,250.18 18.75% 2,307.85 19.23%
GASTOS DE EVALUACION DEL EXPEDIENTE TECNICO S/. 3,500.00 P 252.44 7.21% 132.43 3.78% 559.28 15.98% 920.94 26.31% 757.88 21.65% 877.03 25.06%
E 251.73 7.19% 132.97 3.80% 554.33 15.84% 907.07 25.92% 656.30 18.75% 673.12 19.23%
GASTOS DE LIQUIDACION S/. 5,000.00 P 360.63 7.21% 189.18 3.78% 798.97 15.98% 1,315.64 26.31% 1,082.68 21.65% 1,252.90 25.06%
E 359.61 7.19% 189.95 3.80% 791.91 15.84% 1,295.82 25.92% 937.57 18.75% 961.60 19.23%
PRESUPUESTO REFERENCIAL S/. 448,698.85 P 32,362.99 7.21% 16,976.93 3.78% 71,699.59 15.98% 118,064.87 26.31% 97,159.75 21.65% 112,434.72 25.06%
E 32,271.73 7.19% 17,046.39 3.80% 71,065.57 15.84% 116,286.21 25.92% 84,137.67 18.75% 86,294.09 19.23%
PRESUPUESTO DE OBRA PROGRAMADO 32,362.99 7.21% 16,976.93 3.78% 71,699.59 15.98% 118,064.87 26.31% 97,159.75 21.65% 112,434.72 25.06%
PRESUPUESTO DE OBRA PROGRAMADO ACUMULADO 32,362.99 7.21% 49,339.92 11.00% 121,039.51 26.98% 239,104.38 53.29% 336,264.13 74.94% 448,698.85 100.00%
PRESUPUESTO DE OBRA EJECUTADO 32,271.73 7.19% 17,046.39 3.80% 71,065.57 15.84% 116,286.21 25.92% 84,137.67 18.75% 86,294.09 19.23%
PRESUPUESTO DE OBRA EJECUTADO ACUMULADO 32,271.73 7.19% 49,318.12 10.99% 120,383.69 26.83% 236,669.90 52.75% 320,807.57 71.50% 407,101.66 90.73%
CALENDARIO DE AVANCE DE OBRA REPROGRAMADO DEL ADICIONAL POR MAYORES METRADOS
FORMATO: Nº 07 - LT
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA INICIO DE OBRA : 08/12/ 2,014 AMPLIACION DE PLAZO : 16 DIAS CALENDARIOS
OBRA / PIP : "MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA" PLAZO PROGRAMADO : 120 DIAS CALENDARIOS PLAZO REPROGRAMADO : 136 DIAS CALENDARIOS
META : 105 TERMINO DE OBRA REPROGRAMADO : 06/04/ 2,015 FECHA REAL DE TERMINO DE OBRA : 19/09/ 2,015
MONTO VALOR REFERENCIAL : S/. 10,612.14
CODIGO
PRESUPUESTO BASE
PARTIDA DESCRIPCION DE LA PARTIDA P/E
UNIDAD METRADO PRECIO S/. PARCIAL S/. JUNIO - 2,015 JULIO - 2,015 AGOSTO - 2,015 SETIEMBRE - 2,015
L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
08 CANTERAS
08.02 EXCAVACION DE MATERIAL DE DESCARGUE m3 1,100.00 4.01 4,411.00
P 882.20 20.00% 3,528.80 80.00% - -
GASTOS DE EVALUACION DEL EXPEDIENTE TECNICO S/. 82.78 P 8.66 0.25% 74.12 2.12% - -
PRESUPUESTO REFERENCIAL S/. 10,612.14 P 1,109.70 0.25% 9,502.44 2.12% - 0.00% - 0.00%
CODIGO
PRESUPUESTO BASE PROGRAMACION MENSUAL
PARTIDA DESCRIPCION DE LA PARTIDA P/E
UND METRADO PRECIO S/. PARCIAL S/. DICIEMBRE - 2,014 ENERO - 2,015 JUNIO - 2,015 JULIO - 2,015 AGOSTO - 2,015 SETIEMBRE - 2,015
L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 08/12/2,014 INICIO DE OBRA 09/06/2,013 REINICIO DE OBRA
01.06 ROCE Y LIMPIEZA CON MAQUINARIA HA 2.00 1,481.68 2,963.36 FIN DE OBRA 19/09/2,015
P 2,607.76 88.00% 355.60 12.00% - -
02 MOVIMIENTO DE TIERRAS
02.06 REPOSICION DE MATERIAL ORGANICO EN ZONAS DE RELLENO M3 1,090.04 7.72 8,415.11
P 4,173.05 49.59% - - 4,242.06 50.41% - -
-
02.09 ELIMINACION Y REPOSICION DE MATERIAL TURBA SATURADO M3 948.32 17.11 16,225.76
P - 12,935.16 79.72% 3,290.60 20.28% - -
- - -
07 VARIOS
07.03 CERCOS DEALAMBRE DE PUAS M 240.00 13.32 3,196.80
P ### - 3,196.80 100.00% - -
-
COSTO DIRECTO S/. 42,021.18 P 10,397.09 2.91% - 13,720.71 3.85% 17,903.38 5.02% - -
GASTOS GENERALES (15.00 %) S/. 6,293.94 P 1,557.28 2.91% - 2,055.09 3.85% 2,681.57 5.02% - -
GASTOS DE INSPECCION (5.07 %) S/. 2,127.39 P 526.37 2.91% - 694.63 3.85% 906.39 5.02% - -
GASTOS DE EXPEDIENTE TECNICO S/. 1,413.62 P 349.77 2.91% - 461.57 3.85% 602.28 5.02% - -
GASTOS DE EVALUACION DEL EXPEDIENTE TECNICO S/. 412.31 P 102.01 2.91% - 134.63 3.85% 175.67 5.02% - -
GASTOS DE LIQUIDACION S/. 589.01 P 145.74 2.91% - 192.32 3.85% 250.95 5.02% - -
PRESUPUESTO REFERENCIAL S/. 52,857.45 P 13,078.26 2.91% - 17,258.95 3.85% 22,520.24 5.02% - 0.00% - 0.00%
PRESUPUESTO DE OBRA PROGRAMADO 13,078.26 2.91% - 17,258.95 3.85% 22,520.24 5.02% - 0.00% - 0.00%
PRESUPUESTO DE OBRA PROGRAMADO ACUMULADO 13,078.26 2.91% 13,078.26 2.91% 30,337.21 6.76% 52,857.45 11.78% 52,857.45 11.78% 52,857.45 11.78%
RELACIÓN DE PERSONAL OBRERO MENSUAL Y TOTAL ACUMULADO POR CATEGORÍAS
FORMATO EAP - 11
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA
META : 105
OBRA : CONSTRUCCION Y MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA"
MES/AÑO : JULIO - 2015
3 TRACTOR SOBRE ORUGAS FIATA ALLIS R10C-01 0.67 1.42 1.17 0.83 0.83 0.67 1.00 0.83 4.50 8.50 8.50 47.63 28.92 76.55
7 CARGADOR FRONTAL FIAT ALLIS FR-180 - AMARILLO 1.50 7.80 1.50 9.30
8 RODILLO PATA DE CABRA MULLER VAP-70 3.17 0.33 0.33 - 3.83 3.83
17 VOLQUETE IVECO XG - 6245 4.50 8.50 5.50 7.83 2.67 - 29.00 29.00
1 TRACTOR SOBRE ORUGAS CAT D6G - 04 8.50 5.50 8.50 4.50 34.75 27.00 61.75
3 TRACTOR SOBRE ORUGAS FIATA ALLIS R10C-01 8.50 5.50 8.50 5.00 8.50 8.50 8.50 14.16 53.00 67.16
6 CARGADOR FRONTAL FIAT ALLIS FR-180 - NARANJA 8.50 5.50 8.50 6.25 8.50 8.50 8.50 - 54.25 54.25
8 RODILLO PATA DE CABRA MULLER VAP-70 8.50 5.50 8.50 7.00 8.50 8.50 8.50 19.67 55.00 74.67
12 MOTONIVELADORA KOMATSU GD655 Nº 01 8.50 5.50 8.50 6.50 8.50 8.50 8.50 21.33 54.50 75.83
14 VOLQUETE - CISTERNA VOLVO WV - 1141 8.50 5.50 8.50 8.50 8.50 8.50 8.50 32.67 56.50 89.17
15 VOLQUETE VOLVO WV - 1186 8.50 5.50 8.50 8.50 8.50 8.50 8.50 33.16 56.50 89.66
17 VOLQUETE IVECO XG - 6245 8.50 5.50 8.50 5.50 8.50 8.50 8.50 28.67 53.50 82.17