Está en la página 1de 22

VALORIZACION DE AVANCE DE OBRA Nº 001

FORMATO : VM - 1
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA EJECUCION PRESUPUESTAL DIRECTA
META : 13 FUENTE DE FINANCIAMIENTO : CANON Y SOBRE CANON
OBRA / PIP : "MEJORAMIENTO, AMPLIACION DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO EN LA COMUNI
MES / AÑO : MAYO - 2,017
MONTO VALOR REFERENCIAL : S/. 1,098,519.37
ASIGNACION PRESUPUESTAL - 2015 : S/. 600,000.00

DESCRIPCION PRESUPUESTO BASE AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %

01 EFICIENTE INFRAESTRUCTURA DEL SISTEMA DE AGUA POTABLE


01.01 OBRAS PROVISIONALES
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.00 X 2.00 M und 1.00 801.21 801.21 0.00 0.00% 1.00 801.21 100.00% 1.00 801.21 100.00% 0.00 0.00 0.00%
01.01.02 ALMACEN DE OBRA EN AREAS URBANAS mes 6.00 235.00 1,410.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 6.00 1,410.00 100.00%
01.01.03 CAMPAMENTO DE ROLLIZOS CON TECHO CALAMINA m2 135.00 69.94 9,441.90 0.00 0.00% 46.00 3,217.24 34.07% 46.00 3,217.24 34.07% 89.00 6,224.66 65.93%
01.02 CAPTACION DE MANANTE (5.00 UND) - 0.00 0.00
01.02.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 9.33 1.25 11.66 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 9.33 11.66 100.00%
01.02.02 DEMOLICION DE CAPTACION EXISTENTE und 4.00 206.00 824.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.00 824.00 100.00%
01.02.03 ZANJA DE INFILTRACION (TUB. PVC CRIBADA, CAPA ARCILLA) m 35.00 121.18 4,241.30 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 35.00 4,241.30 100.00%
01.02.04 EXCAVACION MANUAL PARA ESTRUCTURAS m3 13.05 14.00 182.70 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 13.05 182.70 100.00%
01.02.05 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 16.31 10.50 171.26 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 16.31 171.26 100.00%
01.02.06 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 7.08 26.24 185.78 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 7.08 185.78 100.00%
01.02.07 ENCOFRADO Y DESENCOFRADO m2 65.90 16.95 1,117.01 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 65.90 1,117.01 100.00%
01.02.08 ACERO DE REFUERZO 3/8" FY=4200 KG/CM2 kg 289.80 5.67 1,643.17 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 289.80 1,643.17 100.00%
01.02.09 CONCRETO CICLOPEO FC=140 KG/CM2 MEZCLA 1:10 m3 0.50 273.86 136.93 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.50 136.93 100.00%
01.02.10 CONCRETO FC=175 KG/CM2 m3 6.78 432.90 2,935.06 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 6.78 2,935.06 100.00%
01.02.11 FILTRO DE GRAVA (MAT. SELECCIONADO) m3 5.00 133.50 667.50 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.00 667.50 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.02.12 m2 13.80 27.79 383.50 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 13.80 383.50 100.00%
MEZCLA 1:2
01.02.13 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 31.15 18.00 560.70 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 31.15 560.70 100.00%
01.02.14 PINTURA EN MUROS m2 20.50 7.65 156.83 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 20.50 156.83 100.00%
01.02.15 ACCESORIOS PARA CAPTACION DE 1" GLB 5.00 485.34 2,426.70 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.00 2,426.70 100.00%
01.02.16 TRABAJOS DE PROTECCION DE CAPTACIONES( 05 UND) - 0.00 0.00
01.02.16.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.90 14.00 12.60 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.90 12.60 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
01.02.16.02 m3 1.17 10.50 12.29 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.17 12.29 100.00%
BUGGIE
01.02.16.03 CONCRETO FC=175 KG/CM2 m3 0.90 432.90 389.61 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.90 389.61 100.00%
01.02.16.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 25.00 55.75 1,393.75 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 25.00 1,393.75 100.00%
MALLA METALICA PROTECTORA CON ALAMBRE N.12 X
01.02.16.05 m 54.00 90.00 4,860.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 54.00 4,860.00 100.00%
COCADAS DE 2" H=2.00M
01.02.16.06 PUERTA METALICA S/DISEÑO und 5.00 200.00 1,000.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.00 1,000.00 100.00%
01.03 LINEA DE CONDUCCION (3,527.00 ML) - 0.00 0.00
TRAZO NIVELACION Y REPLANTEO DURANTE LA
01.03.01.01 m 3,527.00 1.03 3,632.81 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3,527.00 3,632.81 100.00%
CONSTRUCCION
01.03.02.01 EXCAVACION EN TIERRA ZANJA DE 0.50 X 0.70 m 3,527.00 4.20 14,813.40 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3,527.00 14,813.40 100.00%
01.03.02.02 REFINE Y NIVELACION DE ZANJAS m 3,527.00 1.68 5,925.36 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3,527.00 5,925.36 100.00%
01.03.02.03 CAMA DE APOYO PARA TUBERIAS MENORES DE 6" (e=1") m 3,527.00 1.35 4,761.45 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3,527.00 4,761.45 100.00%
01.03.02.04 RELLENO Y COMPACTACION MANUAL DE ZANJAS m 3,527.00 6.56 23,137.12 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3,527.00 23,137.12 100.00%
01.03.03 TUBERIAS - 0.00 0.00
SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 DE 1
01.03.03.01 m 677.00 6.32 4,278.64 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 677.00 4,278.64 100.00%
1/2" NTP ISO 1452:2011(NTP ISO 4422:2007)
01.03.03.02 SUMINISTRO DE ACCESORIOS L.C 1 1/2" GLB 1.00 240.00 240.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 240.00 100.00%
SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 DE 1"
01.03.03.03 m 2,850.00 5.18 14,763.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2,850.00 14,763.00 100.00%
NTP ISO 1452:2011 (NTP ISO 4422:2007)
01.03.03.04 SUMINISTRO DE ACCESORIOS L.C 1" GLB 1.00 350.00 350.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 350.00 100.00%
01.03.03.05 INSTALAC. DE ACCESORIOS PROMEDIO und 110.00 2.63 289.30 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 110.00 289.30 100.00%
01.03.04 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION - 0.00 0.00
PRUEBA HIDRAULICA+DESINFECCION TUB.< 4" A ZANJA
01.03.04.01 m 3,527.00 0.83 2,927.41 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3,527.00 2,927.41 100.00%
TAPADA
DESCRIPCION PRESUPUESTO BASE AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %

01.04 PASE AEREO L=6.00 ML EN LINEA DE CONDUCCION (2.00 UND) - 0.00 0.00
01.04.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 16.00 1.25 20.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 16.00 20.00 100.00%
01.04.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.44 14.00 20.16 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.44 20.16 100.00%
01.04.03 CONCRETO FC=175 KG/CM2 m3 1.44 432.90 623.38 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.44 623.38 100.00%
01.04.04 ENCOFRADO Y DESENCOFRADO m2 9.60 16.95 162.72 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 9.60 162.72 100.00%
01.04.05 SUMINISTRO DE ACCESORIOS SANITARIOS GLB 2.00 149.80 299.60 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.00 299.60 100.00%
01.05 CAMARA DE REUNION ( 2.00 UND) - 0.00 0.00
01.05.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 2.32 1.25 2.90 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.32 2.90 100.00%
01.05.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.94 14.00 13.16 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.94 13.16 100.00%
01.05.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 2.36 10.50 24.78 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.36 24.78 100.00%
01.05.04 ENCOFRADO Y DESENCOFRADO m2 10.08 16.95 170.86 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 10.08 170.86 100.00%
01.05.05 ACERO DE REFUERZO FY=4200 kg 52.82 4.76 251.42 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 52.82 251.42 100.00%
01.05.06 CONCRETO FC=175 KG/CM2 m3 0.77 432.90 333.33 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.77 333.33 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.05.07 m2 5.04 27.79 140.06 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.04 140.06 100.00%
MEZCLA 1:2
01.05.08 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.76 18.00 103.68 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.76 103.68 100.00%
01.05.09 PINTURA EN MUROS m2 6.40 7.65 48.96 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 6.40 48.96 100.00%
01.05.10 SUMINISTRO DE ACCESORIOS CAMARA DE REUNION GLB 2.00 218.45 436.90 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.00 436.90 100.00%
01.05.11 CAJA DE VALVULAS DE CAMARA DE REUNION (2.00 UND) - 0.00 0.00
01.05.11.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.49 14.00 6.86 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.49 6.86 100.00%
01.05.11.02 ENCOFRADO Y DESENCOFRADO m2 2.24 16.95 37.97 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.24 37.97 100.00%
01.05.11.03 ACERO DE REFUERZO FY=4200 kg 4.65 4.76 22.13 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.65 22.13 100.00%
01.05.11.04 CONCRETO FC=175 KG/CM2 m3 0.18 432.90 77.92 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.18 77.92 100.00%
01.05.11.05 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 0.48 18.00 8.64 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.48 8.64 100.00%
01.05.11.06 PINTURA EN MUROS m2 0.48 7.65 3.67 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.48 3.67 100.00%
SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE C.R.
01.05.11.07 GLB 1.00 191.45 191.45 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 191.45 100.00%
(1")
SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE C.R.
01.05.11.08 GLB 1.00 245.45 245.45 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 245.45 100.00%
(11/2")
01.06 CAMARA DE DISTRIBUCION DE CAUDALES (4.00 UND) - 0.00 0.00
01.06.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 7.60 1.25 9.50 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 7.60 9.50 100.00%
01.06.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 4.18 14.00 58.52 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.18 58.52 100.00%
01.06.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 4.18 10.50 43.89 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.18 43.89 100.00%
01.06.04 FILTRO DE GRAVA (MAT. SELECCIONADO) m3 0.06 133.50 8.01 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.06 8.01 100.00%
01.06.05 CONCRETO CICLOPEO FC=140 KG/CM2 MEZCLA 1:10 m3 0.20 273.86 54.77 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.20 54.77 100.00%
01.06.06 CONCRETO FC=175 KG/CM2 m3 0.21 432.90 90.91 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.21 90.91 100.00%
01.06.07 CONCRETO FC=210 KG/CM2 m3 5.29 494.88 2,617.92 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.29 2,617.92 100.00%
01.06.08 ENCOFRADO Y DESENCOFRADO m2 51.78 16.95 877.67 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 51.78 877.67 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.06.09 m2 58.44 27.79 1,624.05 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 58.44 1,624.05 100.00%
MEZCLA 1:2
01.06.10 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 30.92 18.00 556.56 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 30.92 556.56 100.00%
01.06.11 PINTURA EN MUROS m2 30.92 7.65 236.54 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 30.92 236.54 100.00%
01.06.12 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. 01 GLB 1.00 844.00 844.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 844.00 100.00%
01.06.13 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. 02 GLB 1.00 844.00 844.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 844.00 100.00%
01.06.14 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. 03 GLB 1.00 844.00 844.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 844.00 100.00%
01.06.15 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. 04 GLB 1.00 844.00 844.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 844.00 100.00%
01.07 CAMARA DE FILTRO PARA TRATAMIENTO DE AGUA POTABLE (1.00 UND) - 0.00 0.00
01.07.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.26 1.25 1.58 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.26 1.58 100.00%
01.07.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.76 14.00 10.64 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.76 10.64 100.00%
01.07.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 0.95 10.50 9.98 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.95 9.98 100.00%
01.07.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 1.26 26.24 33.06 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.26 33.06 100.00%
01.07.05 ENCOFRADO Y DESENCOFRADO m2 6.00 16.95 101.70 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 6.00 101.70 100.00%
01.07.06 ACERO DE REFUERZO FY=4200 kg 36.68 4.76 174.60 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 36.68 174.60 100.00%
01.07.07 CONCRETO FC=175 KG/CM2 m3 0.43 432.90 186.15 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.43 186.15 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.07.08 m2 2.16 27.79 60.03 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.16 60.03 100.00%
MEZCLA 1:2
01.07.09 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 3.91 18.00 70.38 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3.91 70.38 100.00%
01.07.10 PINTURA EN MUROS m2 3.91 7.65 29.91 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3.91 29.91 100.00%
01.07.11 MATERIAL SELECCIONADO PARA FILTRO m3 0.42 133.50 56.07 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.42 56.07 100.00%
01.07.12 SUMINISTRO DE ACCESORIOS CAMARA DE FILTRO GLB 1.00 503.80 503.80 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 503.80 100.00%
DESCRIPCION PRESUPUESTO BASE AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %

01.08 RESERVORIO DE CONCRETO ARMADO DE V=5.00 M3 (1.00 UND) - 0.00 0.00


01.08.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 7.29 1.25 9.11 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 7.29 9.11 100.00%
01.08.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 5.83 14.00 81.62 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.83 81.62 100.00%
01.08.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 7.58 10.50 79.59 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 7.58 79.59 100.00%
01.08.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 7.29 26.24 191.29 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 7.29 191.29 100.00%
01.08.05 CONCRETO FC=210 KG/CM2 m3 3.99 494.88 1,974.57 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3.99 1,974.57 100.00%
01.08.06 CONFORMACION DE PENDIENTE E= 2" MEZCLA 1:12 C-H m2 4.00 26.24 104.96 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.00 104.96 100.00%
01.08.07 ENCOFRADO Y DESENCOFRADO m2 31.58 16.95 535.28 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 31.58 535.28 100.00%
01.08.08 ACERO DE REFUERZO FY=4200 kg 152.35 4.76 725.19 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 152.35 725.19 100.00%
01.08.09 SUMINISTRO DE ACCESORIOS RESERVORIO V=5.00 M3 GLB 1.00 639.00 639.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 639.00 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.08.10 m2 16.40 27.79 455.76 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 16.40 455.76 100.00%
MEZCLA 1:2
01.08.11 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 20.47 18.00 368.46 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 20.47 368.46 100.00%
01.08.12 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION GLB 1.00 103.05 103.05 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 103.05 100.00%
01.08.13 PINTURA EN MUROS m2 20.47 7.65 156.60 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 20.47 156.60 100.00%
01.08.14 CAJA DE VALVULAS DE RESERORIO DE V=5.00 M3 ( 01 UND) - 0.00 0.00
01.08.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.24 1.25 1.55 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.24 1.55 100.00%
01.08.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.05 14.00 14.70 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.05 14.70 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
01.08.14.03 m3 1.31 10.50 13.76 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.31 13.76 100.00%
BUGGIE
01.08.14.04 ENCOFRADO Y DESENCOFRADO m2 8.90 16.95 150.86 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 8.90 150.86 100.00%
01.08.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 45.85 6.19 283.81 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 45.85 283.81 100.00%
01.08.14.06 CONCRETO FC=175 KG/CM2 m3 0.70 432.90 303.03 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.70 303.03 100.00%
SUMINISTRO DE ACCESORIOS DE ENTRADA RESERVORIO
01.08.14.07 GLB 1.00 321.34 321.34 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 321.34 100.00%
V=5.00 M3
SUMINISTRO DE ACCESORIOS DE SALIDA RESERVORIO V=5
01.08.14.08 GLB 1.00 699.52 699.52 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 699.52 100.00%
M3
SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOSE
01.08.14.09 GLB 1.00 439.34 439.34 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 439.34 100.00%
RESERVORIO V=5.00 M3
01.08.14.10 SUMINISTRO DE TAPA METALICA GLB 1.00 155.45 155.45 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 155.45 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.08.14.11 m2 3.30 27.79 91.71 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3.30 91.71 100.00%
MEZCLA 1:2
01.08.14.12 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.71 18.00 102.78 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.71 102.78 100.00%
01.08.14.13 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.04 38.56 100.00%
TRABAJOS DE PROTECCION DE RESERVORIO V=5.00 M3( 01
01.08.15 - 0.00 0.00
UND)
01.08.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.43 14.00 6.02 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.43 6.02 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
01.08.15.02 m3 0.56 10.50 5.88 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.56 5.88 100.00%
BUGGIE
01.08.15.03 CONCRETO FC=175 KG/CM2 m3 0.43 432.90 186.15 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.43 186.15 100.00%
01.08.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 12.00 55.75 669.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 12.00 669.00 100.00%
MALLA METALICA PROTECTORA CON ALAMBRE N.12 X
01.08.15.05 m 32.40 90.00 2,916.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 32.40 2,916.00 100.00%
COCADAS DE 2" H=2.00M
01.08.15.06 PUERTA METALICA S/DISEÑO und 1.00 200.00 200.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 200.00 100.00%
01.08.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO - 0.00 0.00

EQUIPO DE CLORACION POR GOTEO (INCLUYE CASETA,


01.08.16.01 und 1.00 3,611.24 3,611.24 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 3,611.24 100.00%
TANQUE DE AGUA, SOPORTE Y ACCESORIOS EN SU TOTALIDAD)

01.09 RESERVORIO DE CONCRETO ARMADO DE V=3.00 M3 (1.00 UND) - 0.00 0.00


01.09.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 7.02 1.25 8.78 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 7.02 8.78 100.00%
01.09.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 5.62 14.00 78.68 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.62 78.68 100.00%
01.09.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 7.30 10.50 76.65 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 7.30 76.65 100.00%
01.09.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 7.02 26.24 184.20 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 7.02 184.20 100.00%
01.09.05 CONCRETO FC=210 KG/CM2 m3 3.96 494.88 1,959.72 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3.96 1,959.72 100.00%
01.09.06 CONFORMACION DE PENDIENTE E= 2" MEZCLA 1:12 C-H m2 3.80 26.24 99.71 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3.80 99.71 100.00%
01.09.07 ENCOFRADO Y DESENCOFRADO m2 31.72 16.95 537.65 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 31.72 537.65 100.00%
01.09.08 ACERO DE REFUERZO FY=4200 kg 224.80 4.76 1,070.05 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 224.80 1,070.05 100.00%
01.09.09 SUMINISTRO DE ACCESORIOS RESERVORIO V=3.00 M3 GLB 1.00 639.00 639.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 639.00 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.09.10 m2 15.89 27.79 441.58 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 15.89 441.58 100.00%
MEZCLA 1:2
01.09.11 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 20.85 18.00 375.30 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 20.85 375.30 100.00%
01.09.12 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION GLB 1.00 103.05 103.05 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 103.05 100.00%
DESCRIPCION PRESUPUESTO BASE AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %

01.09.13 PINTURA EN MUROS m2 20.85 7.65 159.50 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 20.85 159.50 100.00%
01.09.14 CAJA DE VALVULAS DE RESERORIO DE V=3.00 M3 ( 01 UND) - 0.00 0.00
01.09.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.24 1.25 1.55 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.24 1.55 100.00%
01.09.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.05 14.00 14.70 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.05 14.70 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
01.09.14.03 m3 1.31 10.50 13.76 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.31 13.76 100.00%
BUGGIE
01.09.14.04 ENCOFRADO Y DESENCOFRADO m2 8.90 16.95 150.86 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 8.90 150.86 100.00%
01.09.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 45.85 6.19 283.81 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 45.85 283.81 100.00%
01.09.14.06 CONCRETO FC=175 KG/CM2 m3 0.70 432.90 303.03 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.70 303.03 100.00%
SUMINISTRO DE ACCESORIOS DE ENTRADA RESERVORIO
01.09.14.07 GLB 1.00 321.34 321.34 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 321.34 100.00%
V=3.00 M3
SUMINISTRO DE ACCESORIOS DE SALIDA RESERVORIO
01.09.14.08 GLB 1.00 576.52 576.52 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 576.52 100.00%
V=3.00 M3
SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOSE
01.09.14.09 GLB 1.00 439.34 439.34 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 439.34 100.00%
RESERVORIO V=3.00 M3
01.09.14.10 SUMINISTRO DE TAPA METALICA GLB 1.00 155.45 155.45 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 155.45 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.09.14.11 m2 3.30 27.79 91.71 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3.30 91.71 100.00%
MEZCLA 1:2
01.09.14.12 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.71 18.00 102.78 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.71 102.78 100.00%
01.09.14.13 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.04 38.56 100.00%
01.09.15 TRABAJOS DE PROTECCION DE RESERVORIO V=5.00 M3( 01 UND) - 0.00 0.00
01.09.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.29 14.00 4.06 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.29 4.06 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
01.09.15.02 m3 0.37 10.50 3.89 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.37 3.89 100.00%
BUGGIE
01.09.15.03 CONCRETO FC=175 KG/CM2 m3 0.29 432.90 125.54 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.29 125.54 100.00%
01.09.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 8.00 55.75 446.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 8.00 446.00 100.00%
MALLA METALICA PROTECTORA CON ALAMBRE N.12 X
01.09.15.05 m 21.60 90.00 1,944.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 21.60 1,944.00 100.00%
COCADAS DE 2" H=2.00M
01.09.15.06 PUERTA METALICA S/DISEÑO und 1.00 200.00 200.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 200.00 100.00%
01.09.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO - 0.00 0.00

EQUIPO DE CLORACION POR GOTEO (INCLUYE CASETA,


01.09.16.01 und 1.00 3,611.24 3,611.24 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 3,611.24 100.00%
TANQUE DE AGUA, SOPORTE Y ACCESORIOS EN SU TOTALIDAD)

01.10 RESERVORIO DE CONCRETO ARMADO DE V=2.00 M3 (2.00 UND) - 0.00 0.00


01.10.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 10.58 1.25 13.23 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 10.58 13.23 100.00%
01.10.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 8.46 14.00 118.44 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 8.46 118.44 100.00%
01.10.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 11.00 10.50 115.50 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 11.00 115.50 100.00%
01.10.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 10.58 26.24 277.62 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 10.58 277.62 100.00%
01.10.05 CONCRETO FC=210 KG/CM2 m3 6.25 494.88 3,093.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 6.25 3,093.00 100.00%
01.10.06 CONFORMACION DE PENDIENTE E= 2" MEZCLA 1:12 C-H m2 5.12 26.24 134.35 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.12 134.35 100.00%
01.10.07 ENCOFRADO Y DESENCOFRADO m2 51.72 16.95 876.65 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 51.72 876.65 100.00%
01.10.08 ACERO DE REFUERZO FY=4200 kg 366.92 4.76 1,746.54 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 366.92 1,746.54 100.00%
01.10.09 SUMINISTRO DE ACCESORIOS RESERVORIO V=2.00M3 GLB 1.00 592.00 592.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 592.00 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.10.10 m2 24.96 27.79 693.64 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 24.96 693.64 100.00%
MEZCLA 1:2
01.10.11 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 33.90 18.00 610.20 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 33.90 610.20 100.00%
01.10.12 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION GLB 1.00 103.05 103.05 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 103.05 100.00%
01.10.13 PINTURA EN MUROS m2 33.90 7.65 259.34 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 33.90 259.34 100.00%
01.10.14 CAJA DE VALVULAS DE RESERORIO DE V=2.00 M3 ( 2.00 UND) - 0.00 0.00
01.10.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 2.47 1.25 3.09 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.47 3.09 100.00%
01.10.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 2.10 14.00 29.40 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.10 29.40 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
01.10.14.03 m3 2.62 10.50 27.51 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.62 27.51 100.00%
BUGGIE
01.10.14.04 ENCOFRADO Y DESENCOFRADO m2 17.80 16.95 301.71 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 17.80 301.71 100.00%
01.10.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 91.70 6.19 567.62 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 91.70 567.62 100.00%
01.10.14.06 CONCRETO FC=175 KG/CM2 m3 1.40 432.90 606.06 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.40 606.06 100.00%
SUMINISTRO DE ACCESORIOS DE ENTRADA RESERVORIO
01.10.14.07 GLB 2.00 269.17 538.34 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.00 538.34 100.00%
V=2.00 M3
SUMINISTRO DE ACCESORIOS DE SALIDA RESERVORIO
01.10.14.08 GLB 1.00 384.17 384.17 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 384.17 100.00%
V=2.00 M3 (1")
SUMINISTRO DE ACCESORIOS DE SALIDA RESERVORIO
01.10.14.09 GLB 1.00 339.52 339.52 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 339.52 100.00%
V=2.00 M3 (3/4")
DESCRIPCION PRESUPUESTO BASE AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %

SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOSE


01.10.14.10 GLB 2.00 407.00 814.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.00 814.00 100.00%
RESERVORIO V=2.00 M3
01.10.14.11 SUMINISTRO DE TAPA METALICA GLB 2.00 155.45 310.90 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.00 310.90 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.10.14.12 m2 10.60 27.79 294.57 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 10.60 294.57 100.00%
MEZCLA 1:2
01.10.14.13 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 11.41 18.00 205.38 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 11.41 205.38 100.00%
01.10.14.14 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.04 38.56 100.00%
TRABAJOS DE PROTECCION DE RESERVORIO 2.00 m3( 2.00
01.10.15 - 0.00 0.00
UND)
01.10.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.58 14.00 8.12 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.58 8.12 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
01.10.15.02 m3 0.75 10.50 7.88 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.75 7.88 100.00%
BUGGIE
01.10.15.03 CONCRETO FC=175 KG/CM2 m3 0.58 432.90 251.08 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.58 251.08 100.00%
01.10.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 16.00 55.75 892.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 16.00 892.00 100.00%
MALLA METALICA PROTECTORA CON ALAMBRE N.12 X
01.10.15.05 m 43.20 90.00 3,888.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 43.20 3,888.00 100.00%
COCADAS DE 2" H=2.00M
01.10.15.06 PUERTA METALICA S/DISEÑO und 2.00 200.00 400.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.00 400.00 100.00%
01.10.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO - 0.00 0.00

EQUIPO DE CLORACION POR GOTEO (INCLUYE CASETA,


01.10.16.01 und 2.00 3,611.24 7,222.48 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.00 7,222.48 100.00%
TANQUE DE AGUA, SOPORTE Y ACCESORIOS EN SU TOTALIDAD)

01.11 RESERVORIO DE CONCRETO ARMADO DE V=1.00 M3 (1.00 UND) - 0.00 0.00


01.11.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 4.62 1.25 5.78 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.62 5.78 100.00%
01.11.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 3.70 14.00 51.80 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3.70 51.80 100.00%
01.11.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 4.81 10.50 50.51 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.81 50.51 100.00%
01.11.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 4.62 26.24 121.23 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.62 121.23 100.00%
01.11.05 CONCRETO FC=210 KG/CM2 m3 2.65 494.88 1,311.43 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.65 1,311.43 100.00%
01.11.06 CONFORMACION DE PENDIENTE E= 2" MEZCLA 1:12 C-H m2 2.10 26.24 55.10 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.10 55.10 100.00%
01.11.07 ENCOFRADO Y DESENCOFRADO m2 21.50 16.95 364.43 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 21.50 364.43 100.00%
01.11.08 ACERO DE REFUERZO FY=4200 kg 160.62 4.76 764.55 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 160.62 764.55 100.00%
01.11.09 SUMINISTRO DE ACCESORIOS RESERVORIO V=1.00M3 GLB 1.00 592.00 592.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 592.00 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.11.10 m2 10.22 27.79 284.01 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 10.22 284.01 100.00%
MEZCLA 1:2
01.11.11 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 14.30 18.00 257.40 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 14.30 257.40 100.00%
01.11.12 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION GLB 1.00 103.05 103.05 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 103.05 100.00%
01.11.13 PINTURA EN MUROS m2 14.30 7.65 109.40 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 14.30 109.40 100.00%
01.11.14 CAJA DE VALVULAS DE RESERORIO DE V=1.00 M3 ( 1.00 UND) - 0.00 0.00
01.11.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.24 1.25 1.55 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.24 1.55 100.00%
01.11.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.05 14.00 14.70 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.05 14.70 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
01.11.14.03 m3 1.31 10.50 13.76 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.31 13.76 100.00%
BUGGIE
01.11.14.04 ENCOFRADO Y DESENCOFRADO m2 8.90 16.95 150.86 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 8.90 150.86 100.00%
01.11.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 45.85 6.19 283.81 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 45.85 283.81 100.00%
01.11.14.06 CONCRETO FC=175 KG/CM2 m3 0.70 432.90 303.03 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.70 303.03 100.00%
SUMINISTRO DE ACCESORIOS DE ENTRADA RESERVORIO
01.11.14.07 GLB 1.00 269.17 269.17 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 269.17 100.00%
V=1.0M3
SUMINISTRO DE ACCESORIOS DE SALIDA RESERVORIO
01.11.14.08 GLB 1.00 339.52 339.52 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 339.52 100.00%
V=1.0M3
SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOSE
01.11.14.09 GLB 1.00 407.00 407.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 407.00 100.00%
RESERVORIO V=1.00 M3
01.11.14.10 SUMINISTRO DE TAPA METALICA GLB 1.00 155.45 155.45 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 155.45 100.00%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.11.14.11 m2 5.30 27.79 147.29 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.30 147.29 100.00%
MEZCLA 1:2
01.11.14.12 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.71 18.00 102.78 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.71 102.78 100.00%
01.11.14.13 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.04 38.56 100.00%
01.11.15 TRABAJOS DE PROTECCION DE RESERVORIO V=1.00 m3( 01 UND) - 0.00 0.00
01.11.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.29 14.00 4.06 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.29 4.06 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
01.11.15.02 m3 0.37 10.50 3.89 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.37 3.89 100.00%
BUGGIE
01.11.15.03 CONCRETO FC=175 KG/CM2 m3 0.29 432.90 125.54 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.29 125.54 100.00%
01.11.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 8.00 55.75 446.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 8.00 446.00 100.00%
DESCRIPCION PRESUPUESTO BASE AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %

MALLA METALICA PROTECTORA CON ALAMBRE N.12 X


01.11.15.05 m 21.60 90.00 1,944.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 21.60 1,944.00 100.00%
COCADAS DE 2" H=2.00M
01.11.15.06 PUERTA METALICA S/DISEÑO und 1.00 200.00 200.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 200.00 100.00%
01.11.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO - 0.00 0.00
EQUIPO DE CLORACION POR GOTEO (INCLUYE CASETA,
01.11.16.01 und 1.00 1,611.24 1,611.24 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 1,611.24 100.00%
TANQUE Y TODOS LOS ACCSORIOS)
01.12 RED DE DISTRIBUCION (5,952.00 ML) - 0.00 0.00
01.12.01 TRABAJOS PRELIMINARES - 0.00 0.00
TRAZO NIVELACION Y REPLANTEO DURANTE LA
01.12.01.01 m 5,952.00 1.03 6,130.56 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5,952.00 6,130.56 100.00%
CONSTRUCCION
01.12.02 MOVIMIENTO DE TIERRAS - 0.00 0.00
01.12.02.01 EXCAVACION EN TIERRA ZANJA DE 0.50 X 0.70 m 5,952.00 4.20 24,998.40 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5,952.00 24,998.40 100.00%
01.12.02.02 REFINE Y NIVELACION DE ZANJAS m 5,952.00 1.68 9,999.36 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5,952.00 9,999.36 100.00%
01.12.02.03 CAMA DE APOYO PARA TUBERIAS MENORES DE 6" (e=1") m 5,952.00 1.35 8,035.20 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5,952.00 8,035.20 100.00%
01.12.02.04 RELLENO Y COMPACTACION MANUAL DE ZANJAS m 5,952.00 6.56 39,045.12 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5,952.00 39,045.12 100.00%
01.12.03 TUBERIAS - 0.00 0.00
SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 DE 2"
01.12.03.01 m 110.00 8.37 920.70 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 110.00 920.70 100.00%
NTP ISO 1452:2011 (NTP ISO 4422:2007)
SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 DE 1
01.12.03.02 m 283.00 6.32 1,788.56 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 283.00 1,788.56 100.00%
1/2" NTP ISO 1452:2011 (NTP ISO 4422:2007)
SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 DE 1"
01.12.03.03 m 1,170.00 5.18 6,060.60 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1,170.00 6,060.60 100.00%
NTP ISO 1452:2011 (NTP ISO 4422:2007)
SUMINISTRO E INSTALAC.DE TUB. PVC CLASE A-10 DE 3/4"
01.12.03.04 m 1,310.00 4.47 5,855.70 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1,310.00 5,855.70 100.00%
NTP ISO 1452:2011 (NTP ISO 4422:2007)
SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 DE 1/2"
01.12.03.05 m 3,079.00 3.83 11,792.57 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 3,079.00 11,792.57 100.00%
NTP ISO 1452:2011 (NTP ISO 4422:2007)
01.12.04 ACCESORIOS - 0.00 0.00
SUMINISTRO DE ACCESORIOS RED DE DISTRIBUCION
01.12.04.01 GLB 1.00 1,512.70 1,512.70 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 1,512.70 100.00%
GENERAL
01.12.04.02 INSTALAC. DE ACCESORIOS PROMEDIO und 140.00 2.63 368.20 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 140.00 368.20 100.00%
01.12.05 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION - 0.00 0.00
PRUEBA HIDRAULICA+DESINFECCION TUB.< 4" A ZANJA
01.12.05.01 m 5,952.00 0.83 4,940.16 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5,952.00 4,940.16 100.00%
TAPADA
01.13 CAJA DE VALVULAS DE CONTROL +ACCESORIOS (19.00 UND) - 0.00 0.00
01.13.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 2.38 14.00 33.32 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.38 33.32 100.00%
01.13.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 2.85 10.50 29.93 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.85 29.93 100.00%
01.13.03 ENCOFRADO Y DESENCOFRADO m2 42.18 16.95 714.95 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 42.18 714.95 100.00%
01.13.04 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 80.43 6.19 497.86 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 80.43 497.86 100.00%
01.13.05 CONCRETO FC=175 KG/CM2 m3 2.76 432.90 1,194.80 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.76 1,194.80 100.00%
01.13.06 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 22.80 18.00 410.40 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 22.80 410.40 100.00%
01.13.07 PINTURA EN MUROS m2 22.80 7.65 174.42 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 22.80 174.42 100.00%
SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE
01.13.08 GLB 1.00 350.90 350.90 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 350.90 100.00%
CONTROL DE 2"
SUMINISTRO DE ACCESORIOS PARA CAJA DE VALVULAS DE
01.13.09 GLB 2.00 263.90 527.80 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.00 527.80 100.00%
CONTROL DE 1"
SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE
01.13.10 GLB 7.00 212.90 1,490.30 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 7.00 1,490.30 100.00%
CONTROL DE 3/4"
SUMINISTRO DE ACCESORIOS PARA CAJA DE VALVULA DE
01.13.11 und 9.00 200.00 1,800.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 9.00 1,800.00 100.00%
CONTROL DE 1/2"
01.14 CAJA DE VALVULAS DE PURGA +ACCESORIOS (14.00 UND) - 0.00 0.00
01.14.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 2.52 14.00 35.28 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.52 35.28 100.00%
01.14.02 ENCOFRADO Y DESENCOFRADO m2 36.40 16.95 616.98 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 36.40 616.98 100.00%
01.14.03 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 89.25 6.19 552.46 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 89.25 552.46 100.00%
01.14.04 CONCRETO FC=175 KG/CM2 m3 2.28 432.90 987.01 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.28 987.01 100.00%
01.14.05 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 20.16 18.00 362.88 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 20.16 362.88 100.00%
01.14.06 PINTURA EN MUROS m2 20.16 7.65 154.22 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 20.16 154.22 100.00%
SUMINISTRO DE ACCESORIOS PARA VALVULA DE PURGA DE
01.14.07 und 12.00 200.00 2,400.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 12.00 2,400.00 100.00%
1/2"
SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE PURGA
01.14.08 GLB 2.00 218.90 437.80 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 2.00 437.80 100.00%
DE 3/4"
01.15 PASE AEREO L=18.00 ML EN RED DE DISTRIBUCION (1.00 UND) - 0.00 0.00
DESCRIPCION PRESUPUESTO BASE AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %

01.15.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 25.00 1.25 31.25 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 25.00 31.25 100.00%
01.15.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 5.00 14.00 70.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.00 70.00 100.00%
01.15.03 CONCRETO FC=210 KG/CM2 m3 0.35 494.88 173.21 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.35 173.21 100.00%
01.15.04 CONCRETO FC=175 KG/CM2 m3 1.60 432.90 692.64 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.60 692.64 100.00%
01.15.05 ENCOFRADO Y DESENCOFRADO m2 5.60 16.95 94.92 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.60 94.92 100.00%
01.15.06 ACERO DE REFUERZO FY=4200 kg 107.99 4.76 514.03 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 107.99 514.03 100.00%
01.15.07 SUMINISTRO DE CABLE DE 1/4" m 27.05 13.00 351.65 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 27.05 351.65 100.00%
01.15.08 SUMINISTRO DE ACCESORIOS DE CERRAJERIA GLB 1.00 740.40 740.40 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 740.40 100.00%
SUMINISTRO DE ACCESORIOS SANITARIOS PASE AEREO
01.15.09 GLB 1.00 272.00 272.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 272.00 100.00%
L=18.ML
01.16 PASE AEREO L=6.00 ML EN RED DE DISTRIBUCION (1.00 UND) - 0.00 0.00
01.16.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 8.00 1.25 10.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 8.00 10.00 100.00%
01.16.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.72 14.00 10.08 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.72 10.08 100.00%
01.16.03 CONCRETO FC=175 KG/CM2 m3 0.72 432.90 311.69 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 0.72 311.69 100.00%
01.16.04 ENCOFRADO Y DESENCOFRADO m2 4.80 16.95 81.36 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.80 81.36 100.00%
01.16.05 SUMINISTRO DE ACCESORIOS SANITARIOSS GLB 1.00 120.80 120.80 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 120.80 100.00%
01.17 CAJA DE VALVULAS DE PASO DE CONEX. DOMICIL. VALVULA ESFERICA ( 65.00 UND) - 0.00 0.00
01.17.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 6.50 14.00 91.00 0.00 0.00% 1.20 16.80 18.46% 1.20 16.80 18.46% 5.30 74.20 81.54%
01.17.02 ENCOFRADO Y DESENCOFRADO m2 61.10 16.95 1,035.65 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 61.10 1,035.65 100.00%
01.17.03 CONCRETO FC=175 KG/CM2 m3 4.05 432.90 1,753.25 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 4.05 1,753.25 100.00%
01.17.04 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 46.80 18.00 842.40 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 46.80 842.40 100.00%
01.17.05 PINTURA EN MUROS m2 46.80 7.65 358.02 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 46.80 358.02 100.00%
01.17.06 ACCESORIOS PARA CONEXION DOMICILIARIA 1/2" und 65.00 186.30 12,109.50 0.00 0.00% 2.00 372.60 3.08% 2.00 372.60 3.08% 63.00 11,736.90 96.92%
01.18 PILETAS DOMICILIARIAS (65.00 UND) - 0.00 0.00
01.18.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 31.20 1.25 39.00 0.00 0.00% 0.96 1.20 3.08% 0.96 1.20 3.08% 30.24 37.80 96.92%
01.18.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.95 14.00 27.30 0.00 0.00% 0.18 2.52 9.23% 0.18 2.52 9.23% 1.77 24.78 90.77%
01.18.03 SUMINISTRO DE ACCESORIOS DE PILETA GLB 65.00 91.45 5,944.25 0.00 0.00% 2.00 182.90 3.08% 2.00 182.90 3.08% 63.00 5,761.35 96.92%
01.18.04 ENCOFRADO Y DESENCOFRADO m2 215.96 16.95 3,660.52 0.00 0.00% 6.65 112.72 3.08% 6.65 112.72 3.08% 209.31 3,547.80 96.92%
01.18.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 307.13 6.19 1,901.13 0.00 0.00% 85.06 526.52 27.70% 85.06 526.52 27.70% 222.07 1,374.61 72.30%
01.18.06 CONCRETO FC=175 KG/CM2 m3 5.66 432.90 2,450.21 0.00 0.00% 0.18 77.92 3.18% 0.18 77.92 3.18% 5.48 2,372.29 96.82%
01.18.07 CONCRETO CICLOPEO FC=140 KG/CM2 MEZCLA 1:10 m3 35.10 273.86 9,612.49 0.00 0.00% 0.27 73.94 0.77% 0.27 73.94 0.77% 34.83 9,538.55 99.23%
TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM
01.18.08 m2 96.36 27.79 2,677.84 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 96.36 2,677.84 100.00%
MEZCLA 1:2
01.18.09 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 90.35 18.00 1,626.30 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 90.35 1,626.30 100.00%
02 ADECUADA INFRAESTRUCTURA PARA DISPOSICION DE EXCRETAS Y AGUAS SERVIDAS - 0.00 0.00
02.01 LETRINAS DOMICILIARIAS CON BIODIGESTOR (63.00 UND) - 0.00 0.00
02.01.01 TRABAJOS PRELIMINARES - 0.00 0.00
02.01.01.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 606.06 1.25 757.58 0.00 0.00% 519.48 649.35 85.71% 519.48 649.35 85.71% 86.58 108.23 14.29%
02.01.02 MOVIMIENTO DE TIERRAS - 0.00 0.00
02.01.02.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 85.05 14.00 1,190.70 0.00 0.00% 63.45 888.30 74.60% 63.45 888.30 74.60% 21.60 302.40 25.40%
02.01.02.02 EXCAVACION EN TIERRA ZANJA DE 0.50 X 0.70 m 453.60 4.20 1,905.12 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 453.60 1,905.12 100.00%
02.01.02.03 RELLENO Y COMPACTACION MANUAL DE ZANJAS m 453.60 3.44 1,560.38 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 453.60 1,560.38 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
02.01.02.04 m3 567.00 10.50 5,953.50 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 567.00 5,953.50 100.00%
BUGGIE
02.01.03 OBRAS DE CONCRETO SIMPLE - 0.00 0.00
CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON
02.01.03.01 m3 85.05 306.43 26,061.87 0.00 0.00% 40.50 12,410.42 47.62% 40.50 12,410.42 47.62% 44.55 13,651.45 52.38%
30% PIEDRA MEDIANA
02.01.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS m2 247.59 27.38 6,779.01 0.00 0.00% 58.95 1,614.05 23.81% 58.95 1,614.05 23.81% 188.64 5,164.96 76.19%
02.01.03.03 CONCRETO FC=140 KG/CM2 + 30 % PM EN SOBRECIMIENTOS m3 18.43 366.30 6,750.91 0.00 0.00% 4.40 1,611.72 23.87% 4.40 1,611.72 23.87% 14.03 5,139.19 76.13%
02.01.04 OBRAS DE CONCRETO ARMADO - 0.00 0.00
02.01.04.01 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 49.14 27.38 1,345.45 0.00 0.00% 3.12 85.43 6.35% 3.12 85.43 6.35% 46.02 1,260.02 93.65%
02.01.04.02 ACERO DE REFUERZO 3/8" FY=4200 KG/CM2 EN VIGAS kg 190.01 5.67 1,077.36 0.00 0.00% 114.84 651.14 60.44% 114.84 651.14 60.44% 75.17 426.22 39.56%
02.01.04.03 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 126.00 6.19 779.94 0.00 0.00% 57.75 357.47 45.83% 57.75 357.47 45.83% 68.25 422.47 54.17%
02.01.04.04 CONCRETO FC=210 KG/CM2 m3 3.28 494.88 1,623.21 0.00 0.00% 0.47 232.59 14.33% 0.47 232.59 14.33% 2.81 1,390.62 85.67%
02.01.05 ALBAÑILERIA - 0.00 0.00
MURO DE BLOQUE HUECO DE CONCRETO 15 X 20 X 40 CM
02.01.05.01 m2 812.39 55.74 45,282.62 0.00 0.00% 58.05 3,235.71 7.15% 58.05 3,235.71 7.15% 754.34 42,046.91 92.85%
MEZCLA 1:5
02.01.06 PISOS Y PAVIMENTOS - 0.00 0.00
02.01.06.01 BASE DE PIEDRA m2 152.46 19.79 3,017.18 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 152.46 3,017.18 100.00%
DESCRIPCION PRESUPUESTO BASE AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %

PISO DE 2" CONCRETO F'C 140 KG/CM2 X 4 CM.+ PULIDO 1:2 X


02.01.06.02 m2 152.46 28.40 4,329.86 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 152.46 4,329.86 100.00%
1CM
02.01.07 REVESTIMIENTOS - 0.00 0.00
02.01.07.01 TARRAJEO INTERIOR Y EXTERIOR CON CEMENTO-ARENA 1:5 m2 1,676.56 22.23 37,269.93 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1,676.56 37,269.93 100.00%
02.01.07.02 CIELORRASOS CON YESO CON CINTA L=1 CM. m2 328.86 14.96 4,919.75 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 328.86 4,919.75 100.00%
02.01.08 COBERTURAS - 0.00 0.00
02.01.08.01 COBERTURA CON TEJA ANDINA m2 388.08 56.56 21,949.80 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 388.08 21,949.80 100.00%
02.01.08.02 CORREAS DE MADERA DE 2"X2" p2 771.75 3.28 2,531.34 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 771.75 2,531.34 100.00%
02.01.08.03 VIGUETAS DE MADERA DE 2"X3" p2 909.72 3.30 3,002.08 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 909.72 3,002.08 100.00%
02.01.09 PINTURA - 0.00 0.00
02.01.09.01 PINTURA EN EXTERIORES E INTERIORES m2 1,676.56 6.60 11,065.30 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1,676.56 11,065.30 100.00%
02.01.10 CARPINTERIA DE MADERA - 0.00 0.00
02.01.10.01 PUERTA DE MADERA CORRIENTE P/ LETRINA und 63.00 231.50 14,584.50 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 63.00 14,584.50 100.00%
02.01.10.02 VENTANA DE MADERA AGUANO 0.50 X 0.60M und 126.00 61.30 7,723.80 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 126.00 7,723.80 100.00%
02.01.11 VEREDAS DE CONCRETO - 0.00 0.00
02.01.11.01 ENCOFRADO Y DESENCOFRADO m2 97.02 19.54 1,895.77 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 97.02 1,895.77 100.00%
02.01.11.02 BASE DE PIEDRA m2 245.70 19.79 4,862.40 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 245.70 4,862.40 100.00%
02.01.11.03 CONCRETO FC=175 KG/CM2 m3 245.70 442.49 108,719.79 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 245.70 108,719.79 100.00%
02.01.12 INSTALACIONES SANITARIAS - 0.00 0.00
02.01.12.01 ACCESORIOS PARA LETRINAS GLB 63.00 499.10 31,443.30 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 63.00 31,443.30 100.00%
02.01.13 INSTALACIONES ELECTRICAS - 0.00 0.00
02.01.13.01 INSTALACIONES ELECTRICAS EN LETRINA GLB 63.00 90.50 5,701.50 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 63.00 5,701.50 100.00%
02.01.14 BIODIGESTOR PARA LETRINAS - 0.00 0.00
02.01.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 189.00 1.25 236.25 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 189.00 236.25 100.00%
02.01.14.02 EXCAVACION DE ZANJAS MANUAL m3 195.30 13.73 2,681.47 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 195.30 2,681.47 100.00%
ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN
02.01.14.03 m3 244.13 10.50 2,563.37 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 244.13 2,563.37 100.00%
BUGGIE
RELLENO DE POZO DE ABSORCION CON MATERIAL
02.01.14.04 m3 63.00 96.60 6,085.80 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 63.00 6,085.80 100.00%
SELECCIONADO
02.01.14.05 BIODIGESTOR DE 600 LT PARA LETRINA und 63.00 1,387.25 87,396.75 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 63.00 87,396.75 100.00%
02.01.14.06 CAJA DE VALVULAS PARA EXTRACCION DE LODOS und 63.00 212.49 13,386.87 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 63.00 13,386.87 100.00%
02.02 MITIGACION DE IMPACTO AMBIENTAL - 0.00 0.00
02.02.01 LIMPIEZA FINAL DE OBRA GLB 1.00 1,503.80 1,503.80 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 1,503.80 100.00%
02.03 FLETES - 0.00 0.00
02.03.01 FLETE TERRESTRE GLB 1.00 10,000.00 10,000.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 10,000.00 100.00%
02.03.02 FLETE RURAL GLB 1.00 10,000.00 10,000.00 0.00 0.00% 0.10 1,000.00 10.00% 0.10 1,000.00 10.00% 0.90 9,000.00 90.00%
02.03.03 ACARREO DE MATERIALES A ZONAS SIN ACCESO VEHICULAR GLB 1.00 6,120.00 6,120.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 6,120.00 100.00%
02.04 PRUEBAS DE LABOTARIO - 0.00 0.00
02.04.01 DISEÑO DE MEZCLA DE CONCRETOS und 5.00 360.00 1,800.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 5.00 1,800.00 100.00%
PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA
02.04.02 und 20.00 40.00 800.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 20.00 800.00 100.00%
COMPRESION)
02.05 PLACA RECORDATORIA - 0.00 0.00
02.05.01 PLACA RECORDATORIA DE ALUMINIO DE 0.40 X 0.60M und 1.00 600.00 600.00 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 600.00 100.00%
MEJOR ORGANIZACION PARA OPERACION, MANTENIMIENTO Y GESTION DE LOS
03 - 0.00 0.00
SERVICIOS
ELABORACION DEL PLAN DE CAPACITACION Y PROGRAMA DE
03.01 CAPACITACION GLB 1.00 20,999.10 20,999.10 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 20,999.10 100.00%
EN GESTION DEL SERVICIO A LA JASS
04 MEJOR EDUCACION SANITARIA DE LA POBLACION - 0.00 0.00
04.01 CAMPAÑA DE EDUCACION SANITARIA LOCAL GLB 1.00 4,489.08 4,489.08 0.00 0.00% - 0.00 0.00% 0.00 0.00 0.00% 1.00 4,489.08 100.00%

1 COSTO DIRECTO 905,284.70 - 28,121.75 28,121.75 877,162.95


PORCENTAJE DE AVANCE ( % ) 0.00% 3.11% 3.11% 96.89%
2 GASTOS GENERALES (14.48 %) 103,903.20 - 0.00% 4,212.08 4.05% 4,212.08 4.05% 99,691.12 95.95%
3 GASTOS DE INSPECCION ( 6.03 % ) 54,557.22 - 0.00% 1,423.71 2.61% 1,423.71 2.61% 53,133.51 97.39%
4 GASTOS DE EXPEDIENTE TECNICO ( 2.43 % ) 22,000.00 - 0.00% 22,000.00 100.00% 22,000.00 100.00% - 0.00%
5 GASTOS DE LIQUIDACION ( 1.41 % ) 12,774.25 - 0.00% - 0.00% - 0.00% 12,774.25 100.00%
DESCRIPCION PRESUPUESTO BASE AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %

6 TOTAL VALORIZACION (1)+(2)+(3)+(4)+(5)+(6) 1,098,519.37 - 0.00% 55,757.54 5.08% 55,757.54 5.08% 1,042,761.83 94.92%
VALORIZACION ADICIONAL POR MAYORES METRADOS Nº 002
FORMATO : VM - 1
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA EJECUCION PRESUPUESTAL DIRECTA
META : 105 FUENTE DE FINANCIAMIENTO : CANON Y SOBRE CANON
OBRA / PIP : "MEJORAMIENTO, AMPLIACION DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO EN LA COMUN
MES / AÑO : JULIO - 2,015
MONTO VALOR REFERENCIAL :
ASIGNACION PRESUPUESTAL : S/. 0.00

PRESUPUESTO ADICIONAL POR MAYORES


DESCRIPCION AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM METRADOS
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %

02 MOVIMIENTO DE TIERRAS
02.03 RELLENO CON MATERIAL DE PRESTAMO LATERAL M3 365.96 0.00 0.00 0.00 0.00 -
08 CANTERAS

08.02 EXCAVACION DE MATERIAL DE DESCARGUE m3 1,100.00 0.00 0.00 0.00 0.00

1 COSTO DIRECTO - - - - -
PORCENTAJE DE AVANCE ( % ) 0.00% 0.00% 0.00% 0.00%
2 GASTOS GENERALES ( 14.99 % ) - - 0.00% - 0.00% - 0.00% - 0.00%
3 GASTOS DE INSPECCION ( 5.06 % ) - - 0.00% - 0.00% - 0.00% - 0.00%
4 GASTOS DE EXPEDIENTE TECNICO - - 0.00% - 0.00% - 0.00% - 0.00%
5 GASTOS DE EVALUACION DEL EXPEDIENTE TECNICO - - Err:509 - 0.00% - 0.00% - 0.00%
6 GASTOS DE LIQUIDACION - - 0.00% - Err:509 - Err:509 - Err:509
7 TOTAL VALORIZACION (1)+(2)+(3)+(4)+(5)+(6) - - 0.00% - 0.00% - 0.00% - 0.00%
VALORIZACION ADICIONAL POR PARTIDA NUEVA Nº 004
FORMATO : VM - 1
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA EJECUCION PRESUPUESTAL DIRECTA
META : 105 FUENTE DE FINANCIAMIENTO : CANON Y SOBRE CANON
OBRA / PIP : "MEJORAMIENTO, AMPLIACION DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO EN LA COMU
MES / AÑO : JULIO - 2,015
MONTO VALOR REFERENCIAL :
ASIGNACION PRESUPUESTAL : S/. 0.00

PRESUPUESTO ADICIONAL POR PARTIDA


DESCRIPCION AVANCE ACUMULADO ANTERIOR AVANCE MES ACTUAL AVANCE ACUMULADO ACTUAL SALDOS
ITEM NUEVA
DE LA PARTIDA UND METRADO PRECIO SUB-TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %

01. OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES -


01.06 ROCE Y LIMPIEZA CON MAQUINARIA HA - 0.00 0.00 0.00 0.00 0.00 - #DIV/0!
01.07 ELIMINACION DE MATERIAL ORGANICO EN ZONAS DE RELLENO M3 - 0.00 0.00 0.00 0.00 0.00 - #DIV/0!
01.09 HABILITACION DE DESVIOS EN PUENTES Y ALCANTARILLAS KM - 0.00 0.00 0.00 0.00 0.00 - #DIV/0!
02 MOVIMIENTO DE TIERRAS
02 MOVIMIENTO DE TIERRAS -
02.06 REPOSICION DE MATERIAL ORGANICO EN ZONAS DE RELLENO M3 - 0.00 0.00 0.00 0.00 0.00 - #DIV/0!
02.09 ELIMINACION Y REPOSICION DE MATERIAL TURBA SATURADO M3 - 0.00 0.00 0.00 0.00 0.00 - #DIV/0!
07 VARIOS -
07.03 CERCOS DE ALAMBRE DE PUAS M - 0.00 0.00 0.00 0.00 - #DIV/0!

1 COSTO DIRECTO - - - - -
PORCENTAJE DE AVANCE ( % ) 0.00% 0.01% 0.00% 0.00%
2 GASTOS GENERALES ( 14.99 % ) - - 0.00% - 0.01% - 0.00% - 0.00%
3 GASTOS DE INSPECCION ( 5.06 % ) - - 0.00% - 0.01% - 0.00% - 0.00%
4 GASTOS DE EXPEDIENTE TECNICO - - 0.00% - 0.01% - 0.00% - 0.00%
5 GASTOS DE EVALUACION DEL EXPEDIENTE TECNICO - - Err:509 - Err:509 - Err:509 - 0.00%
6 GASTOS DE LIQUIDACION - - 0.00% - 0.01% - 0.00% -
7 TOTAL VALORIZACION (1)+(2)+(3)+(4)+(5)+(6) - - 0.00% - 0.01% - 0.00% -
RESUMEN DE VALORIZACION DE AVANCE DE OBRA Nº 004
FORMATO : VM - 1
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA EJECUCION PRESUPUESTARIA DIRECTA

META : 105 FUENTE DE FINANCIAMIENTO : CANON Y SOBRE CANON

"MEJORAMIENTO, AMPLIACION DEL SISTEMA DE AGUA POTABLE Y


OBRA / PIP : SANEAMIENTO EN LA COMUNIDAD CAMPESINA DE CUYUNI, DISTRITO DE MES / AÑO : JULIO - 2,015
CCATCA - QUISPICANCHI - CUSCO"
MONTO VALOR REFERENCIAL : S/. 1,098,519.37

ASIGNACION PRESUPUESTAL - 2,015 : S/. 600,000.00

ANTERIOR ACTUAL ACUMULADO SALDO


PRESUPUESTO
ITEM DESCRIPCION DEL PRESUPUESTO VALORIZADO VALORIZADO VALORIZADO VALORIZADO
BASE S/.
S/. % S/. % S/. % S/. %

1.00 VALORIZACION CONTRACTUAL

CONTRACTUAL 1,098,519.37 - 0.00% 55,757.54 5.08% 55,757.54 5.08% 1,042,761.83 94.92%

2.00 VALORIZACION DE ADICIONALES POR MAYORES METRADOS

MAYORES METRADOS - 0.00% - 0.00% - 0.00%

2.00 VALORIZACION DE ADICIONALES POR PARTIDAS NUEVAS

1.00 PARTIDAS NUEVAS - 0.00% - 0.00% - 0.00%

TOTAL VALORIZACION 1,098,519.37 - 0.00% 55,757.54 5.08% 55,757.54 5.08% 1,042,761.83 94.92%
CALENDARIO DE AVANCE DE OBRA REPROGRAMADO Y EJECUTADO
FORMATO: Nº 07 - LT
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA INICIO DE OBRA : 08/12/ 2,014 AMPLIACION DE PLAZO : 16 DIAS CALENDARIOS
OBRA / PIP : "MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA" PLAZO PROGRAMADO : 120 DIAS CALENDARIOS PLAZO REPROGRAMADO : 136 DIAS CALENDARIOS
META : 105 TERMINO DE OBRA REPROGRAMADO : 06/04/ 2,015 FECHA REAL DE TERMINO DE OBRA : 19/09/ 2,015
MONTO VALOR REFERENCIAL : S/. 448,698.85

CODIGO
PRESUPUESTO BASE PROGRAMACION MENSUAL
PARTIDA DESCRIPCION DE LA PARTIDA P/E
UND. METRADO PRECIO S/. PARCIAL S/. DICIEMBRE - 2,014 ENERO - 2,015 JUNIO - 2,015 JULIO - 2,015 AGOSTO - 2,015 SETIEMBRE - 2,015
L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 08/12/2,014 INICIO DE OBRA 09/01/2,015 FIN DE OBRA 1º ETAPA 09/06/2,015 REINICIO DE OBRA
01.01 CARTEL DE OBRA m2 17.28 149.20 2,578.18 FIN DE OBRA 19/09/2,015
P 2,578.18 100.00%

E 2,578.18 100.00%
01.02 MOVILIZACION Y DESMOVILIZACION GLB 1.00 7,756.64 7,756.64
P 775.66 10.00% 775.66 10.00% 2,326.99 30.00% 387.83 5.00% 387.84 5.00% 3,102.66 40.00%

E 853.23 11.00% 775.66 10.00% 2,249.43 29.00% 387.83 5.00% 232.70 3.00% 3,257.79 42.00%
01.03 CAMPAMENTO DE OBRA m2 120.00 138.05 16,566.00
P 10,767.90 65.00% 2,153.58 13.00% 3,644.52 22.00%

E 11,044.00 66.67% 2,208.80 13.33% 3,313.20 20.00% - 0.00%


01.04 TRAZO Y REPLANTEO KM 8.82 917.51 8,092.44
P 3,236.98 40.00% - 2,427.73 30.00% 809.24 10.00% 1,618.49 20.00% -

E 3,303.04 40.82% - 2,064.40 25.51% 229.38 2.83% 2,495.63 30.84% -


01.05 ROCE Y LIMPIEZA DE LATERALES MANUAL HA 7.00 966.71 6,766.97
P 1,691.74 25.00% 338.35 5.00% 2,706.79 40.00% 2,030.09 30.00%

E 1,972.09 29.14% 135.34 2.00% 1,082.71 16.00% -


02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACION DE MATERIAL SUELTO m3 7,124.00 4.01 28,567.24
P 1,428.36 5.00% - - 18,568.71 65.00% 5,713.45 20.00% 2,856.72 10.00%

E 192.48 0.67% - - 18,095.93 63.35% 5,301.98 18.56% 4,976.85 17.42%


02.02 RELLENO CON MATERIAL DE PRESTAMO DE CORTE M3 2,109.00 8.35 17,610.15
P - - - 10,566.09 60.00% 7,044.06 40.00%

E - - - - 521.88 2.96% 3,364.21 19.10%


02.03 RELLENO CON MATERIAL DE PRESTAMO LATERAL M3 5,506.96 11.00 60,576.56
P - 27,259.45 45.00% 33,317.11 55.00% -

E - - 28,477.79 47.01% 32,098.77 52.99% - -


02.04 PERFILADO Y COMPACTADO DE SUB-RASANATE EN ZONA DE CO M2 20,960.00 0.98 20,540.80
P - - 3,081.12 15.00% 10,270.40 50.00% 7,189.28 35.00%

E### - - 2,534.46 12.34% 10,925.89 53.19% 2,292.46 11.16%


02.05 ELIMINACION DE MATERIAL EXCEDDENTE DE CORTE M3 5,015.00 4.81 24,122.15
P - - 20,503.83 85.00% 3,618.32 15.00% -

E - - 21,936.97 90.94% 2,185.18 9.06%


02.07 MEJORAMIENTO DE SUB-RASANTE M3 528.00 12.45 6,573.60
P - - 5,258.88 80.00% 1,314.72 20.00% -

E - 5,079.60 77.27% 1,494.00 22.73% -


02.08 REMOSION DE DERRUMBES M3 100.00 3.84 384.00
P - - 384.00 100.00%

E - -
03 PAVIMEN TOS
03.01 SUB-BASE GRANULAR (E = 0.075 M, DM = 3.60 KM) M2 34,756.00 1.67 58,042.52
P - - - 14,510.63 25.00% 43,531.89 75.00%

E - - 15,478.01 26.67% 42,564.51 73.33%


04 OBRAS DE ARTE Y DRENAJE
04.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 188.00 27.97 5,258.36
P - - 262.92 5.00% 788.75 15.00% 525.84 10.00% 3,680.85 70.00%

E - 91.46 1.74% 850.01 16.16% 396.89 7.55% 1,740.01 33.09%


04.07 RELLENO DE FUNDACIONES CON MATERIAL SELECCIONADO m3 144.00 63.74 9,178.56
P### 1,835.71 20.00% 3,671.42 40.00% 1,376.79 15.00% 2,294.64 25.00%

E### 2,107.88 22.97% 3,674.61 40.03% 1,566.73 17.07% 1,829.34 19.93%


04.08 ALCANTARILLA TMC D = 36" ML 32.40 652.30 21,134.52
P### 10,567.26 50.00% 10,567.26 50.00% - -

E 10,567.26 50.00% 10,567.26 50.00% -


04.09 ALCANTARILLA TMC D = 24" ML 48.60 240.03 11,665.46
P 5,249.46 45.00% - 583.27 5.00% 5,832.73 50.00% -

E 5,712.71 48.97% 120.02 1.03% 5,832.73 50.00% -


04.11 EXTRACCION DE TRONCOS P/PTES ML 112.00 41.36 4,632.32
P - - - - 4,632.32 100.00%

E - - - - 4,632.32 100.00% -
CALENDARIO DE AVANCE DE OBRA REPROGRAMADO Y EJECUTADO
FORMATO: Nº 07 - LT
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA INICIO DE OBRA : 08/12/ 2,014 AMPLIACION DE PLAZO : 16 DIAS CALENDARIOS
OBRA / PIP : "MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA" PLAZO PROGRAMADO : 120 DIAS CALENDARIOS PLAZO REPROGRAMADO : 136 DIAS CALENDARIOS
META : 105 TERMINO DE OBRA REPROGRAMADO : 06/04/ 2,015 FECHA REAL DE TERMINO DE OBRA : 19/09/ 2,015
MONTO VALOR REFERENCIAL : S/. 448,698.85

CODIGO
PRESUPUESTO BASE PROGRAMACION MENSUAL
PARTIDA DESCRIPCION DE LA PARTIDA P/E
UND. METRADO PRECIO S/. PARCIAL S/. DICIEMBRE - 2,014 ENERO - 2,015 JUNIO - 2,015 JULIO - 2,015 AGOSTO - 2,015 SETIEMBRE - 2,015
L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

VIENEN…
04.12 COLOCACION Y ACONDICIONAMIENTO DE MUERTOS Y VIGAS ML 112.00 24.10 2,699.20
P - - - - 2,699.20 100.00%

E - - - - 2,699.20 100.00% -
04.13 ENTABLADO CON MADERA ASERRADA ADQ. M2 54.60 110.30 6,022.38
P - - - - 6,022.38 100.00%

E - - - - 6,022.38 100.00% -
04.14 CONFORMACION DE CUNETAS KM 10.00 401.30 4,013.00
P### - - 601.95 15.00% 2,608.45 65.00% 802.60 20.00%

E - - 642.08 16.00% 2,648.58 66.00% 722.34 18.00%

06 SEÑALIZACION Y SEGURIDAD VIAL


06.01 POSTES KILOMETRICOS und 9.00 38.05 342.45
P### - - - - 342.45 100.00%

E - - 342.45 100.00%
06.02 SEÑALES INFORMATIVAS und 14.00 256.75 3,594.50
P### - - - - 3,594.50 100.00%
###
E### - - -
07 VARIOS
07.02 REACONDICIONAMIENTO DE TALUDES M2 240.00 2.92 700.80
P### - - - 700.80 100.00%

E - - 700.80 100.00%
08 CANTERAS
08.01 ROCE Y LIMPIEZA HA 2.30 1,505.68 3,463.06
P### - 692.61 20.00% 1,038.92 30.00% 692.61 20.00% 1,038.92 30.00%

E 662.50 19.13% 1,084.09 31.30% 873.29 25.22% 843.18 24.35%


08.02 EXCAVACION DE MAATERIAL DE DESCARGUE m3 1,540.00 4.01 6,175.40
P### - 6,175.40 100.00% - -

E 6,175.40 100.00% - - -
08.03 CAMINOS DE ACCESO A CANTERA KM 1.00 8,863.10 8,863.10
P### - 886.31 10.00% - 7,976.79 90.00%

E 531.79 6.00% - 8,331.31 94.00% -


08.04 LASTRADO E CAMINOS DE ACCESO A CANTERA KM 1.00 7,418.51 7,418.51
P### - - - - 7,418.51 100.00%

E - - 2,596.48 35.00%
09 MITIGACION DE IMPACTO AMBIENTAL
09.01 REFORESTACION M2. 1,540.00 2.19 3,372.60
P### - - - 3,372.60 100.00%

E### - - 3,372.60 100.00%

COSTO DIRECTO S/. 356,711.47 P 25,728.28 7.21% 13,496.50 3.78% 57,000.52 15.98% 93,860.49 26.31% 77,241.11 21.65% 89,384.57 25.06%
E 25,655.73 7.19% 13,551.72 3.80% 56,496.47 15.84% 92,446.46 25.92% 66,888.68 18.75% 68,603.02 19.23%

GASTOS GENERALES (15.00 %) S/. 53,428.27 P 3,853.58 7.21% 2,021.51 3.78% 8,537.54 15.98% 14,058.43 26.31% 11,569.18 21.65% 13,388.03 25.06%
E 3,842.72 7.19% 2,029.78 3.80% 8,462.05 15.84% 13,846.64 25.92% 10,018.59 18.75% 10,275.36 19.23%

GASTOS DE INSPECCION (5.07 %) S/. 18,059.11 P 1,302.54 7.21% 683.28 3.78% 2,885.75 15.98% 4,751.84 26.31% 3,910.46 21.65% 4,525.24 25.06%
E 1,298.86 7.19% 686.08 3.80% 2,860.23 15.84% 4,680.26 25.92% 3,386.35 18.75% 3,473.14 19.23%

GASTOS DE EXPEDIENTE TECNICO S/. 12,000.00 P 865.52 7.21% 454.03 3.78% 1,917.53 15.98% 3,157.53 26.31% 2,598.44 21.65% 3,006.95 25.06%
E 863.08 7.19% 455.89 3.80% 1,900.58 15.84% 3,109.96 25.92% 2,250.18 18.75% 2,307.85 19.23%

GASTOS DE EVALUACION DEL EXPEDIENTE TECNICO S/. 3,500.00 P 252.44 7.21% 132.43 3.78% 559.28 15.98% 920.94 26.31% 757.88 21.65% 877.03 25.06%
E 251.73 7.19% 132.97 3.80% 554.33 15.84% 907.07 25.92% 656.30 18.75% 673.12 19.23%

GASTOS DE LIQUIDACION S/. 5,000.00 P 360.63 7.21% 189.18 3.78% 798.97 15.98% 1,315.64 26.31% 1,082.68 21.65% 1,252.90 25.06%
E 359.61 7.19% 189.95 3.80% 791.91 15.84% 1,295.82 25.92% 937.57 18.75% 961.60 19.23%

PRESUPUESTO REFERENCIAL S/. 448,698.85 P 32,362.99 7.21% 16,976.93 3.78% 71,699.59 15.98% 118,064.87 26.31% 97,159.75 21.65% 112,434.72 25.06%
E 32,271.73 7.19% 17,046.39 3.80% 71,065.57 15.84% 116,286.21 25.92% 84,137.67 18.75% 86,294.09 19.23%

PRESUPUESTO DE OBRA PROGRAMADO 32,362.99 7.21% 16,976.93 3.78% 71,699.59 15.98% 118,064.87 26.31% 97,159.75 21.65% 112,434.72 25.06%
PRESUPUESTO DE OBRA PROGRAMADO ACUMULADO 32,362.99 7.21% 49,339.92 11.00% 121,039.51 26.98% 239,104.38 53.29% 336,264.13 74.94% 448,698.85 100.00%

PRESUPUESTO DE OBRA EJECUTADO 32,271.73 7.19% 17,046.39 3.80% 71,065.57 15.84% 116,286.21 25.92% 84,137.67 18.75% 86,294.09 19.23%
PRESUPUESTO DE OBRA EJECUTADO ACUMULADO 32,271.73 7.19% 49,318.12 10.99% 120,383.69 26.83% 236,669.90 52.75% 320,807.57 71.50% 407,101.66 90.73%
CALENDARIO DE AVANCE DE OBRA REPROGRAMADO DEL ADICIONAL POR MAYORES METRADOS
FORMATO: Nº 07 - LT
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA INICIO DE OBRA : 08/12/ 2,014 AMPLIACION DE PLAZO : 16 DIAS CALENDARIOS
OBRA / PIP : "MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA" PLAZO PROGRAMADO : 120 DIAS CALENDARIOS PLAZO REPROGRAMADO : 136 DIAS CALENDARIOS
META : 105 TERMINO DE OBRA REPROGRAMADO : 06/04/ 2,015 FECHA REAL DE TERMINO DE OBRA : 19/09/ 2,015
MONTO VALOR REFERENCIAL : S/. 10,612.14

CODIGO
PRESUPUESTO BASE
PARTIDA DESCRIPCION DE LA PARTIDA P/E
UNIDAD METRADO PRECIO S/. PARCIAL S/. JUNIO - 2,015 JULIO - 2,015 AGOSTO - 2,015 SETIEMBRE - 2,015
L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

02 MOVIMIENTO DE TIERRAS 09/06/2,015 REINICIO DE OBRA FIN DE OBRA 19/09/2,015


02.03 RELLENO CON MATERIAL DE PRESTAMO LATERAL M3 365.96 11.00 4,025.56
P - 4,025.56 100.00% - -

08 CANTERAS
08.02 EXCAVACION DE MATERIAL DE DESCARGUE m3 1,100.00 4.01 4,411.00
P 882.20 20.00% 3,528.80 80.00% - -

COSTO DIRECTO S/. 8,436.56 P 882.20 0.25% 7,554.36 2.12% - -

GASTOS GENERALES (15.00 %) S/. 1,263.63 P 132.14 0.25% 1,131.49 2.12% - -

GASTOS DE INSPECCION (5.07 %) S/. 427.11 P 44.66 0.25% 382.45 2.12% - -

GASTOS DE EXPEDIENTE TECNICO S/. 283.81 P 29.68 0.25% 254.13 2.12% - -

GASTOS DE EVALUACION DEL EXPEDIENTE TECNICO S/. 82.78 P 8.66 0.25% 74.12 2.12% - -

GASTOS DE LIQUIDACION S/. 118.25 P 12.36 0.25% 105.89 2.12% - -

PRESUPUESTO REFERENCIAL S/. 10,612.14 P 1,109.70 0.25% 9,502.44 2.12% - 0.00% - 0.00%

PRESUPUESTO DE OBRA PROGRAMADO 1,109.70 0.25% 9,502.44 2.12% - 0.00% - 0.00%


PRESUPUESTO DE OBRA PROGRAMADO ACUMULADO 1,109.70 0.25% 10,612.14 2.37% 10,612.14 2.37% 10,612.14 2.37%
CALENDARIO DE AVANCE DE OBRA REPROGRAMADO DEL ADICIONAL POR PARTIDA NUEVA
FORMATO: Nº 07 - LT
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA INICIO DE OBRA : 08/12/ 2,014 AMPLIACION DE PLAZO : 16 DIAS CALENDARIOS
OBRA / PIP : "MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA" PLAZO PROGRAMADO : 120 DIAS CALENDARIOS PLAZO REPROGRAMADO : 136 DIAS CALENDARIOS
META : 105 TERMINO DE OBRA REPROGRAMADO : 06/04/ 2,015 FECHA REAL DE TERMINO DE OBRA : 19/09/ 2,015
MONTO VALOR REFERENCIAL : S/. 52,857.45

CODIGO
PRESUPUESTO BASE PROGRAMACION MENSUAL
PARTIDA DESCRIPCION DE LA PARTIDA P/E
UND METRADO PRECIO S/. PARCIAL S/. DICIEMBRE - 2,014 ENERO - 2,015 JUNIO - 2,015 JULIO - 2,015 AGOSTO - 2,015 SETIEMBRE - 2,015
L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 08/12/2,014 INICIO DE OBRA 09/06/2,013 REINICIO DE OBRA
01.06 ROCE Y LIMPIEZA CON MAQUINARIA HA 2.00 1,481.68 2,963.36 FIN DE OBRA 19/09/2,015
P 2,607.76 88.00% 355.60 12.00% - -

01.07 ELIMINACION DE MATERIAL ORGANICO EN ZONAS DE RELLENO M3 1,090.04 6.69 7,292.37


P 3,616.28 49.59% - - 3,676.09 50.41% - -
-
01.09 HABILITACION DE DESVIOS EN PUENTES Y ALCANTARILLAS KM 0.20 19,638.92 3,927.78
P - - 785.55 20.00% 3,142.23 80.00% - -

02 MOVIMIENTO DE TIERRAS
02.06 REPOSICION DE MATERIAL ORGANICO EN ZONAS DE RELLENO M3 1,090.04 7.72 8,415.11
P 4,173.05 49.59% - - 4,242.06 50.41% - -
-
02.09 ELIMINACION Y REPOSICION DE MATERIAL TURBA SATURADO M3 948.32 17.11 16,225.76
P - 12,935.16 79.72% 3,290.60 20.28% - -
- - -
07 VARIOS
07.03 CERCOS DEALAMBRE DE PUAS M 240.00 13.32 3,196.80
P ### - 3,196.80 100.00% - -
-

COSTO DIRECTO S/. 42,021.18 P 10,397.09 2.91% - 13,720.71 3.85% 17,903.38 5.02% - -

GASTOS GENERALES (15.00 %) S/. 6,293.94 P 1,557.28 2.91% - 2,055.09 3.85% 2,681.57 5.02% - -

GASTOS DE INSPECCION (5.07 %) S/. 2,127.39 P 526.37 2.91% - 694.63 3.85% 906.39 5.02% - -

GASTOS DE EXPEDIENTE TECNICO S/. 1,413.62 P 349.77 2.91% - 461.57 3.85% 602.28 5.02% - -

GASTOS DE EVALUACION DEL EXPEDIENTE TECNICO S/. 412.31 P 102.01 2.91% - 134.63 3.85% 175.67 5.02% - -

GASTOS DE LIQUIDACION S/. 589.01 P 145.74 2.91% - 192.32 3.85% 250.95 5.02% - -

PRESUPUESTO REFERENCIAL S/. 52,857.45 P 13,078.26 2.91% - 17,258.95 3.85% 22,520.24 5.02% - 0.00% - 0.00%

PRESUPUESTO DE OBRA PROGRAMADO 13,078.26 2.91% - 17,258.95 3.85% 22,520.24 5.02% - 0.00% - 0.00%
PRESUPUESTO DE OBRA PROGRAMADO ACUMULADO 13,078.26 2.91% 13,078.26 2.91% 30,337.21 6.76% 52,857.45 11.78% 52,857.45 11.78% 52,857.45 11.78%
RELACIÓN DE PERSONAL OBRERO MENSUAL Y TOTAL ACUMULADO POR CATEGORÍAS
FORMATO EAP - 11
ENTIDAD : MUNICIPALIDAD DISTRITAL DE CCATCCA
META : 105
OBRA : CONSTRUCCION Y MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA"
MES/AÑO : JULIO - 2015

DIAS HORAS HOMBRE


Nº APELLIDOS Y NOMBRES CARGOS M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V ACUMULADO ACUMULADO
MES
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 ANTERIOR ACTUAL

1 BERROCAL NIETO, Victor Alejandro OPERARIO 234.50 0.00 234.50


2 HUAMAN QUISPE, Vicente OPERARIO 192.00 0.00 192.00
3 RAMIREZ DIAZ, Hermes OPERARIO 118.50 0.00 118.50
4 SENCIA HUARECAYO, Isaias OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 223.00 200.50 423.50
5 VALCARCEL AROSTEGUI, Luis Ricardo OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 370.00 200.50 570.50
6 ALVAN MARIÑO, Julio Royle OFICIAL 234.50 0.00 234.50
7 ISUIZA ALVARADO, Jesús OFICIAL 234.50 0.00 234.50
8 CORAL REATEGUI, Rene Toribio OFICIAL 384.00 0.00 384.00
9 VALENCIA CARBALLO, José Nilton OPERARIO 172.50 0.00 172.50
10 CHAVEZ GUERRA, Edwin OFICIAL 192.00 0.00 192.00
11 OSORIO FLORES, Nestor Alberto OFICIAL 240.00 0.00 240.00
12 CONDORI HUAMAN, Leocadio PEON 254.00 0.00 254.00
13 CHOQUEMAMANI RAMOS, Sabino PEON 161.00 0.00 161.00
14 ACOSTA JIMENEZ, Adán OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 144.00 152.50 296.50
15 ARAOZ BARRIOS, Javier OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 192.00 192.00
16 BUENO QUISPE, Tomas Gabriel OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 144.00 200.50 344.50
17 BERROCAL NIETO, Carlos Augusto OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 144.00 152.50 296.50
18 BRAVO SOLIS, Victor Hugo OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 144.00 152.50 296.50
19 CHAVEZ MASIAS, Jorge RaÚL OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 144.00 152.50 296.50
20 INUMA PAREJA, Marcel Eugenio OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 104.50 152.50 257.00
21 ISUIZA ALVARADO, Flavío OPERARIO 144.00 0.00 144.00
22 PINEDO MORA, Manuel OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 144.00 152.50 296.50
23 SAHUARICO RIOS, Hitler OPERARIO 144.00 0.00 144.00
24 VELASQUEZ PORTOCARRERO, Marcos OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 152.50 152.50 305.00
25 VENEGAS COSI, Hugo OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 144.00 152.50 296.50
26 MELENDEZ CAYMACHI, Julío OPERARIO 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 144.00 152.50 296.50
27 FASABI MORENO, Domingo OPERARIO 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 96.00 96.00
28 HERMOZA SOTO, José Santos OFICIAL 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 144.00 152.50 296.50
29 TORRES MARCHENA, Luís Alberto OFICIAL 25.50 0.00 25.50
30 CAPELETTI JULIO, Miguel Angél OFICIAL 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 144.00 200.50 344.50
31 COLLAZOS APAZA, Walter PEON 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 96.00 152.50 248.50
32 RACUA RAMOS, Wilfredo PEON 96.00 0.00 96.00
33 CORAL FLORES Ronald Segúndo PEON 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 104.50 152.50 257.00
34 CORAL REATEGUI, Raúl Hernan PEON 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 104.50 152.50 257.00
35 DA SILVA RENGIFO, Lazaro PEON 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 135.50 200.50 336.00
36 GONZALES KHAN, Clevert PEON 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 144.00 152.50 296.50
37 GRIFA ESTRADA, Robert Eusebio PEON 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 70.50 152.50 223.00
38 FERNANDEZ SOTO, Daniel PEON 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 96.00 169.50 265.50
39 RACUA REAÑO, Edgardo PEON 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 96.00 161.00 257.00
40 MAMANI COLQUE, Saturnino PEON 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 96.00 178.00 274.00
41 CACERES QUISPE, Fredy Michel PEON 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 39.50 152.50 192.00
42 CHAMBI QUISPE, Julian PEON 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 48.00 200.50 248.50
43 YUCRA YUCRA, Edwin Alvaro PEON 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 87.50 87.50
44 CHAMBI POCCO, Jesús PEON 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 113.00 113.00

SUB TOTAL (1) 6,147.50 4,640.00 10,787.50

LEYENDA: PC = Dia paralizado por Factor Climatologico


CV = Permiso a Cuenta de Vacaciones
PS = Permiso por Salud
DF = Dia Feriado
PP = Permiso Particular
RELACIÓN DE PERSONAL EMPLEADO MENSUAL Y TOTAL ACUMULADO POR CATEGORÍAS
FORMATO EAP - 11
ENTIDAD : MUNICIPALIDAD DISTRITAL DE HUARO
META : 105
OBRA : CONSTRUCCION Y MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA"
MES/AÑO : JULIO - 2015

DIAS HORAS HOMBRE


Nº APELLIDOS Y NOMBRES CARGOS M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V ACUMULADO ACUMULADO
MES
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 ANTERIOR ACTUAL
INDIRECTOS DE OBRA
1 DIAZ MARIÑAS , Carlos Ing. Residente 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 200.50 200.50 401.00
2 TORRES ARENAS, Luís Alberto Asistente Tecnico 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 CV CV CV CV 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 152.50 169.50 322.00
3 DIAZ MUÑOZ, Robert Asistente Administrativo 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 406.50 200.50 607.00
4 CALCINA AMANQUI, Melecio Capataz 313.50 - 313.50
5 IRARICA RIVERA ANA LUZ Almacenero 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 144.00 200.50 344.50
6 PINEDO VIGO, Miguel Angel Mecanico II 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 200.50 200.50
7 SAHUARICO RIOS, Hitler Topografo 8.50 8.50 8.50 5.50 8.50 8.50 PC PC PC PC 8.50 8.50 8.50 8.50 8.50 5.50 8.50 8.50 8.50 8.50 8.50 5.50 8.50 DF DF 8.50 8.50 169.50 169.50
SUB TOTAL (2) 1,217.00 1,141.00 2,358.00
TOTAL : (1) + (2) 7,364.50 5,781.00 13,145.50

LEYENDA: PC = Dia paralizado por Factor Climatologico


CV = Permiso a Cuenta de Vacaciones
PS = Permiso por Salud
DF = Dia Feriado
PP = Permiso Particular
OBRA : "MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA"

CUADRO DE PARALIZACION DE MAQUINARIA PROPIA DEBIDO A FALLAS MECANICAS


MES : JULIO - 2,015

HORAS MAQUINA PARALIZADAS

N° MAQUINA J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S ACUMULADO ACUMULADO


MES
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 ANTERIOR ACTUAL

1 TRACTOR SOBRE ORUGAS CAT D6G - 04 2.33 0.50 - 2.83 2.83

2 TRACTOR SOBRE ORUGAS CAT D6G - 06 - - -

3 TRACTOR SOBRE ORUGAS FIATA ALLIS R10C-01 0.67 1.42 1.17 0.83 0.83 0.67 1.00 0.83 4.50 8.50 8.50 47.63 28.92 76.55

4 TRACTOR SOBRE ORUGAS FIATA ALLIS R14C-03 77.50 - 77.50

5 CARGADOR FRONTAL FIAT ALLIS FR-14 - - -

6 CARGADOR FRONTAL FIAT ALLIS FR-180 - NARANJA 0.50 - 0.50 0.50

7 CARGADOR FRONTAL FIAT ALLIS FR-180 - AMARILLO 1.50 7.80 1.50 9.30

8 RODILLO PATA DE CABRA MULLER VAP-70 3.17 0.33 0.33 - 3.83 3.83

9 RODILLO VIBRATORIO DYNAPAC CA-25 - - -

10 RODILLO VIBRATORIO BITELLI C-100 15.17 - 15.17

11 MOTONIVELADORA FIAT ALLIS FG-70B - - -

12 MOTONIVELADORA KOMATSU GD655 Nº 01 - - -

13 PLATAFORMA CISTERNA VOLVO WV - 1140 - - -

14 VOLQUETE - CISTERNA VOLVO WV - 1141 1.00 - 1.00 1.00

15 VOLQUETE VOLVO WV - 1186 - - -

16 VOLQUETE IVECO XG - 5512 - - -

17 VOLQUETE IVECO XG - 6245 4.50 8.50 5.50 7.83 2.67 - 29.00 29.00

18 VOLQUETE IVECO XG - 7042 - - -

TOTAL 148.10 67.58 215.68


OBRA : "MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA"

CUADRO DE PARALIZACION DE MAQUINARIA PROPIA DEBIDO A LLUVIAS


MES : ENERO - 2,015

HORAS MAQUINA PARALIZADAS

N° MAQUINA J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S ACUMULADO ACUMULADO


MES
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 ANTERIOR ACTUAL

1 TRACTOR SOBRE ORUGAS CAT D6G - 04 8.50 5.50 8.50 4.50 34.75 27.00 61.75

2 TRACTOR SOBRE ORUGAS CAT D6G - 06 - - -

3 TRACTOR SOBRE ORUGAS FIATA ALLIS R10C-01 8.50 5.50 8.50 5.00 8.50 8.50 8.50 14.16 53.00 67.16

4 TRACTOR SOBRE ORUGAS FIATA ALLIS R14C-02 6.50 - 6.50

5 CARGADOR FRONTAL FIAT ALLIS FR-14 - - -

6 CARGADOR FRONTAL FIAT ALLIS FR-180 - NARANJA 8.50 5.50 8.50 6.25 8.50 8.50 8.50 - 54.25 54.25

7 CARGADOR FRONTAL FIAT ALLIS FR-180 - AMARILLO 26.33 - 26.33

8 RODILLO PATA DE CABRA MULLER VAP-70 8.50 5.50 8.50 7.00 8.50 8.50 8.50 19.67 55.00 74.67

9 RODILLO VIBRATORIO DYNAPAC CA-25 - - -

10 RODILLO VIBRATORIO BITELLI C-100 8.50 - 8.50

11 MOTONIVELADORA FIAT ALLIS FG-70B - - -

12 MOTONIVELADORA KOMATSU GD655 Nº 01 8.50 5.50 8.50 6.50 8.50 8.50 8.50 21.33 54.50 75.83

13 PLATAFORMA CISTERNA VOLVO WV - 1140 - - -

14 VOLQUETE - CISTERNA VOLVO WV - 1141 8.50 5.50 8.50 8.50 8.50 8.50 8.50 32.67 56.50 89.17

15 VOLQUETE VOLVO WV - 1186 8.50 5.50 8.50 8.50 8.50 8.50 8.50 33.16 56.50 89.66

16 VOLQUETE IVECO XG - 5512 - - -

17 VOLQUETE IVECO XG - 6245 8.50 5.50 8.50 5.50 8.50 8.50 8.50 28.67 53.50 82.17

18 VOLQUETE IVECO XG - 7042 - - -

TOTAL 225.74 410.25 635.99


OBRA :"MEJORAMIENTO CAMINO VECINAL CCATCCA - YACACHETA - ATAPATA"

CUADRO DE LLUVIAS MAYO - 2,017

DIAS DIAS CALENDARIOS DEL MES ENERO


M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S
HORAS 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 LLUVIA
24 SEVERA /
23 TORRENCIAL
22
H 21 LLUVIA
20 MODERADA
19
18
O 17 LLUVIA
16 LEVE
15
14
R 13
12
11
10 NUBLADO
A 9
8
7
6
S 5
4
3
2
1

También podría gustarte