CRONOGRAMA VALORIZADO DE OBRA

PROYECTO : "REHABILITACIÓN DE LAS PISTAS Y VEREDAS DESDE EL TRAMO 1-1946 HASTA 1-1953 DE LA
LOCALIDAD DE HUACLLAN, DISTRITO DE HUACLLÁN, PROVINCIA DE AIJA - ANCASH"
DISTRITO: HUACLLÁN PROVINCIA: AIJA DEPARTAMENTO: ANCASH

MES 1 MES 2 MES 3


Items Descripción Und Metrado P.Unitario S/. Parcial S/.
Parcial % Parcial % Parcial %
01 SISTEMA COLECTORA DE DESAGÜE 101,170.41 20,777.40 20.54% 75,717.25 74.84% 4,675.76 4.62%
01.01 OBRAS PRELIMINARES 3,422.34 3,422.34 100.00% 0.00% 0.00%
01.01.01 TRAZO, NIVELACION Y REPLANTEO INICIAL m 914.08 2.41 2,202.93 2,202.93 100.00% 0.00% 0.00%
01.01.02 DESVIO DE AGUAS RESIDUALES DURANTE LA CONSTRUCCION m 182.82 6.67 1,219.41 1,219.41 100.00% 0.00% 0.00%
01.02 MOVIMIENTO DE TIERRAS 74,073.40 17,355.06 23.43% 53,893.95 72.76% 2,824.39 3.81%
01.02.01 EXCAVACION MANUAL EN TERRENO CONGLOMERADO m3 1,006.52 37.27 37,513.00 14,946.59 39.84% 22,566.41 60.16% 0.00%
01.02.02 REFINE, NIVELACION Y COMPACTADO m2 731.26 35.93 26,274.17 2,408.47 9.17% 23,865.70 90.83% 0.00%
01.02.03 PREPARACION Y EXTENDIDO CAMA DE APOYO C/MAT. PRESTAMm 914.08 5.91 5,402.21 0.00% 5,402.21 100.00% 0.00%
01.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO m3 915.01 4.41 4,035.19 0.00% 2,059.63 51.04% 1,975.56 48.96%
01.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 109.81 7.73 848.83 0.00% 0.00% 848.83 100.00%
01.03 SUMINISTRO E INSTALACION DE TUBERIAS 22,312.69 0.00% 21,823.30 97.81% 489.39 2.19%
01.03.01 SUMINISTRO E INSTALACION TUBERIA PVC S-25, D=160mm. m 914.08 24.41 22,312.69 0.00% 21,823.30 97.81% 489.39 2.19%
01.04 PRUEBA HIDRAULICA 1,361.98 0.00% 0.00% 1,361.98 100.00%
01.04.01 PRUEBA HIDRAULICA DE TUBERIA PVC-UF A ZANJA ABIERTA m 914.08 1.49 1,361.98 0.00% 0.00% 1,361.98 100.00%
02 BUZONES DE INSPECCION 17,706.89 2,111.24 11.92% 11,250.24 63.54% 4,345.41 24.54%
02.01 OBRAS PRELIMINARES 92.03 92.03 100.00% 0.00% 0.00%
02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 20.36 0.16 3.26 3.26 100.00% 0.00% 0.00%
02.01.02 TRAZO, NIVELACION Y REPLANTEO INICIAL m2 20.36 4.36 88.77 88.77 100.00% 0.00% 0.00%
02.02 MOVIMIENTO DE TIERRAS 1,785.36 1,295.83 72.58% 357.57 20.03% 131.96 7.39%
02.02.01 EXCAVACION A MANO EN TERRENO NORMAL m3 23.41 37.27 872.49 804.33 92.19% 68.16 7.81% 0.00%
02.02.02 REFINE, NIVELACION Y COMPACTADO m2 20.36 35.93 731.53 491.50 67.19% 240.03 32.81% 0.00%
02.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADm3 7.15 4.27 30.53 0.00% 30.53 100.00% 0.00%
02.02.04 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 19.51 7.73 150.81 0.00% 18.85 12.50% 131.96 87.50%
02.03 OBRAS DE CONCRETO SIMPLE 1,559.56 723.38 46.38% 836.18 53.62% 0.00%
02.03.01 SOLADO DE CONCRETO C:H (1:10) E=4" m2 20.36 44.46 905.21 723.38 79.91% 181.83 20.09% 0.00%
02.03.02 CONCRETO f'c=140kg/cm2 MEDIA CAÑA m3 1.36 481.14 654.35 0.00% 654.35 100.00% 0.00%
02.04 OBRAS DE CONCRETO ARMADO 9,243.92 0.00% 9,243.92 100.00% 0.00%
02.04.01 CONCRETO f'c=210kg/cm2 PARA BUZONES m3 8.21 529.67 4,348.59 0.00% 4,348.59 100.00% 0.00%
02.04.02 ENCOFRADO METALICO PARA BUZONES m2 50.48 41.25 2,082.30 0.00% 2,082.30 100.00% 0.00%
02.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 414.29 6.79 2,813.03 0.00% 2,813.03 100.00% 0.00%
02.05 REVOQUES Y ENLUCIDOS 1,110.42 0.00% 812.57 73.18% 297.85 26.82%
02.05.01 TERRAJEO CON IMPERMEABILIZANTE EN INTERIOR, 1:2 m2 29.81 37.25 1,110.42 0.00% 812.57 73.18% 297.85 26.82%
02.06 TAPA DE BUZON 3,915.60 0.00% 0.00% 3,915.60 100.00%
02.06.01 MARCO DE F°F° D=0.60M Y TAPA DE CONCRETO ARMADO und 8.00 489.45 3,915.60 0.00% 0.00% 3,915.60 100.00%
03 CONEXIONES DOMICILIARIAS DE DESAGUE 40,994.39 8,913.60 21.74% 31,885.42 77.78% 195.37 0.48%
03.01 OBRAS PRELIMINARES 1,786.76 1,786.76 100.00% 0.00% 0.00%
03.01.01 TRAZO, NIVELACION Y REPLANTEO INICIAL m2 218.58 4.36 953.01 953.01 100.00% 0.00% 0.00%
03.01.02 DESVIO DE AGUAS RESIDUALES DURANTE LA CONSTRUCCION m 125.00 6.67 833.75 833.75 100.00% 0.00% 0.00%
03.02 MOVIMIENTO DE TIERRAS 14,314.63 7,126.84 49.79% 6,992.42 48.85% 195.37 1.36%
03.02.01 EXCAVACION A MANO EN TERRENO NORMAL m3 100.00 37.27 3,727.00 2,748.66 73.75% 978.34 26.25% 0.00%
03.02.02 REFINE, NIVELACION Y COMPACTADO m2 200.00 35.93 7,186.00 3,143.87 43.75% 4,042.13 56.25% 0.00%
03.02.03 PREPARACION Y EXTENDIDO CAMA DE APOYO C/MAT. PRESTAMm 500.00 5.91 2,955.00 1,234.31 41.77% 1,720.69 58.23% 0.00%
03.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADm3 96.07 4.27 410.22 0.00% 251.26 61.25% 158.96 38.75%
03.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 4.71 7.73 36.41 0.00% 0.00% 36.41 100.00%
03.03 CONEXIONES DOMICILIARIAS 24,893.00 0.00% 24,893.00 100.00% 0.00%
03.03.01 CONEXION DOMICILIARIA DE DESAGUE PVC-UF S-25 DE160MM und 100.00 248.93 24,893.00 0.00% 24,893.00 100.00% 0.00%
04 FLETE 7,738.55 7,738.55 100.00% 0.00 0.00% 0.00 0.00%
04.01 FLETE TERRESTRE glb 1.00 7,738.55 7,738.55 7,738.55 100.00% 0.00 0.00% 0.00 0.00%
Costo Directo S/. 167,610.24 39,540.79 23.59% 118,852.91 70.91% 9,216.54 5.50%
Gastos Generales (8%) 8.00% S/. 13,408.82 3,163.26 23.59% 9,508.23 70.91% 737.32 5.50%
Utilidad (7%) 7.00% S/. 11,732.72 2,767.86 23.59% 8,319.70 70.91% 645.16 5.50%
Sub total S/. 192,751.78 45,471.91 23.59% 136,680.85 70.91% 10,599.02 5.50%
Impuesto General a las Ventas (I.G.V.) 18.00% S/. 34,695.32 8,184.94 23.59% 24,602.55 70.91% 1,907.82 5.50%
PRESUPUESTO DE OBRA S/. 227,447.10 53,656.85 161,283.40 12,506.84
CURVA "S"
VAL. MONTO MES PARCIAL
INICIO 0.00%
VALORIZACION 01 S/53,656.85 MARZO 23.59%
VALORIZACION 02 S/161,283.40 ABRIL 70.91%
VALORIZACION 03 S/12,506.84 MAYO 5.50%
TOTAL S/227,447.10 100.00%

CURVA "S"
100.00%
100.00% 94.50%

90.00%

80.00%

70.00%

60.00%

50.00%

40.00%

30.00% 23.59%
20.00%

10.00%
0.00%
0.00%
0.5 1 1.5 2 2.5 3 3.5 4
ACUMULADO
0.00%
23.59%
94.50%
100.00%

100.00%
50%

3 3.5 4 4.5