COSTO_MANO_DE_OBRA_y_JORNALES

Costo de Mano de Obra

Operario Oficial Peon


Descripcion S/. S/. S/.

Salario Basico 67.20 53.70 48.10


Bonificacion Unificada 21.50 16.11 14.43
Movilidad 7.20 7.20 7.20
Dominical 11.79 9.42 8.44
Liquidacion y utilidades 10.08 8.06 7.22
Vacaciones 7.75 6.19 5.55
Gratificaciones 14.93 11.93 10.69
Dias Feriados 2.52 2.01 1.80
Asignacion Escolar 16.80 13.43 12.03
Prestaciones de Salud 11.33 8.93 8.00
Accidentes de Trabajo 1.62 1.30 1.16
Overol 0.47 0.47 0.47

Costo Total 173.20 138.75 125.08


Costo por Hora 21.65 17.34 15.64
PLANILLA DE JORNALES Elaborado con base al Acta de Negociacion Colectiva 2018-2019
CONSTRUCCION CIVIL VIGENTE DESDE JUNIO 2018
I II III 1 2 3 4 A B 5 NETO
DESCANSO BONIFICACIONES 1+2+3 (4-3a) Ref(1+2) A+B A
Ocupacion y Equivalente Total de Importe REMUNERADO 3a 3b Importe DESCUENTO TRABAJADOR Total PAGAR
Remuneracion en dias Horas Semanal 2a 2b Movilidad BONIFICACION Semanal S.N.P. CONAFO Descuento 4-5
Basica laborados Laboradas Ordinario Jornal por Jornal por Acumulada UNIFICADA Ordinario .(13%) VICER
descanso feriado no Según RD DE + Ley 2%
Dominical laborado No.777-87 CONSTRUCCION Dominical No.26504 R.S. 001/95
DR-LIM BUC + MTC del
7/8/1987 Bonificacio- 1/5/1995
nes

S 5.5 46.20 7.70 7.20 14.78 75.88 8.93 1.08 10.01 65.88
1D 8.5 71.40 11.90 7.20 22.85 113.35 13.80 1.67 15.47 97.88
1D+S 14.0 117.60 19.60 14.40 37.63 189.23 22.73 2.74 25.47 163.76
OPERARIO 2D 17.0 142.80 23.80 14.40 45.70 226.70 27.60 3.33 30.93 195.77
2D+S 22.5 189.00 31.50 21.60 60.48 302.58 36.53 4.41 40.94 261.64
67.20 3D 25.5 214.20 35.70 21.60 68.54 340.04 41.40 5.00 46.40 293.65
3D+S 31.0 260.40 43.40 28.80 83.33 415.93 50.33 6.08 56.40 359.53
4D 34.0 285.60 47.60 28.80 91.39 453.39 55.20 6.66 61.86 391.53
4D+S 39.5 331.80 55.30 36.00 106.18 529.28 64.13 7.74 71.87 457.41
5D 42.5 357.00 59.50 36.00 114.24 566.74 69.00 8.33 77.33 489.41
6D (S.C.) 48.0 403.20 67.20 43.20 129.02 642.62 77.93 9.41 87.33 555.29
4D+F+S 39.5 331.80 67.20 71.40 36.00 106.18 612.58 74.95 7.98 82.93 529.64
5D+SF 42.5 357.00 67.20 46.20 36.00 114.24 620.64 76.00 8.48 84.49 536.15
S 5.5 36.92 6.15 7.20 11.08 61.35 7.04 0.86 7.90 53.45
1D 8.5 57.06 9.51 7.20 17.12 90.88 10.88 1.33 12.21 78.67
1D+S 14.0 93.98 15.66 14.40 28.19 152.23 17.92 2.19 20.11 132.12
OFICIAL 2D 17.0 114.11 19.02 14.40 34.23 181.77 21.76 2.66 24.42 157.34
2D+S 22.5 151.03 25.17 21.60 45.31 243.11 28.80 3.52 32.32 210.79
53.70 3D 25.5 171.17 28.53 21.60 51.35 272.65 32.64 3.99 36.63 236.02
3D+S 31.0 208.09 34.68 28.80 62.43 334.00 39.68 4.86 44.53 289.46
4D 34.0 228.23 38.04 28.80 68.47 363.53 43.51 5.33 48.84 314.69
4D+S 39.5 265.14 44.19 36.00 79.54 424.88 50.55 6.19 56.74 368.14
5D 42.5 285.28 47.55 36.00 85.58 454.41 54.39 6.66 61.05 393.36
6D (S.C.) 48.0 322.20 53.70 43.20 96.66 515.76 61.43 7.52 68.95 446.81
4D+F+S 39.5 265.14 53.70 57.06 36.00 79.54 491.44 59.21 6.38 65.58 425.86
5D+SF 42.5 285.28 53.70 36.92 36.00 85.58 497.48 59.99 6.78 66.77 430.71
S 5.5 33.07 5.51 7.20 9.92 55.70 6.31 0.77 7.08 48.62
1D 8.5 51.11 8.52 7.20 15.33 82.16 9.74 1.19 10.94 71.22
1D+S 14.0 84.18 14.03 14.40 25.25 137.86 16.05 1.96 18.01 119.84
PEON 2D 17.0 102.21 17.04 14.40 30.66 164.31 19.49 2.38 21.87 142.44
2D+S 22.5 135.28 22.55 21.60 40.58 220.01 25.79 3.16 28.95 191.06
48.10 3D 25.5 153.32 25.55 21.60 46.00 246.47 29.23 3.58 32.81 213.66
3D+S 31.0 186.39 31.06 28.80 55.92 302.17 35.54 4.35 39.89 262.28
4D 34.0 204.43 34.07 28.80 61.33 328.62 38.98 4.77 43.75 284.88
4D+S 39.5 237.49 39.58 36.00 71.25 384.32 45.28 5.54 50.82 333.50
5D 42.5 255.53 42.59 36.00 76.66 410.78 48.72 5.96 54.68 356.10
6D (S.C.) 48.0 288.60 48.10 43.20 86.58 466.48 55.03 6.73 61.76 404.72
4D+F+S 39.5 237.49 48.10 51.11 36.00 71.25 443.95 53.03 5.71 58.75 385.20
5D+SF 42.5 255.53 48.10 33.07 36.00 76.66 449.36 53.74 6.07 59.81 389.55