Está en la página 1de 14

LIQUIDACION DE VALORIZACION DE OBRA Nº 03

CORRESPONDIENTE AL MES DE AGOSTO DEL 2017


OBRA CONSTRUCCION DE PISTAS Y VEREDAS DEL TRAMO PLAZA PRINCIAL- PARQUE BOLIVAR DEL, DISTRITO DE RICRAN - JAUJA - JUNI

EJECUTA CONSORCIO BOLIVAR Residente de Obra Ing. Walter Gomez Ramos


SUPERVISA MUNICIPALIDAD DISTRITAL DE RICRAN Inspector de Obra Ing. Alipio Astete Orellana
CLIENTE MUNICIPALIDAD DISTRITAL DE RICRAN
PRESUP. REFERENC. 1,720,751.47 1,458,263.96 Sin/IGV
MONTO DE CONT. 1,720,000.00 1,457,627.12 Sin/IGV
FACT. DE RELAC. 0.99956
ADEL. DIRECTO. 0.00 0.00 Sin/IGV
ADEL. MATERIALES 0.00 0.00 Sin/IGV
UBICACIÓN : DISTRITO DE RICRAN - JAUJA - JAUJA
PLAZO EJEC. : 120 DIAS CALENDARIOS
INCIO DE OBRA : 08 DE JUNIO DEL 2017

Monto Valorización
Descripción
Contratado Anterior Actual

A. VALORIZACIÓN CONTRACTUAL
MONTO DE CONTRATO 1,457,627.12 800,151.45 403,211.25
AVANCE FISICO DE OBRA 100.00% 54.89% 27.66%
AVANCE PROGRAMADO 50.83% 32.16%

REAJUSTES POR FORMULA POLINOMICA ( R ) 0.00 -

B. AMORTIZACIONES
DEL ADELANTO DIRECTO (20%) 0.00 0.00 0.00
ADELANTO DE MATERIALES (40%) 0.00 0.00 0.00
TOTAL (B) : 0.00 0.00

VALORIZACION NETA (VN=A+R-B) : 800,151.45 403,211.25

C. DEDUCCION POR REINTEGROS


REINTEGRO POR ADELANTO DIRECTO 0.00 0.00
REINTEGRO POR ADELANTO DE MATERIALES 0.00 0.00
TOTAL (C) : 0.00 0.00

D. MONTO A PAGAR AL CONTRATISTA


EN EFECTIVO (VN-C) : 800,151.45 403,211.25
IGV (18% VN) : 144,027.26 72,578.03
TOTAL (D) : 944,178.71 475,789.28

E. TOTAL COMPROMISO A SOLICITAR OBRA "A" (S/.) 475,789.28


Nº 03
2017
ITO DE RICRAN - JAUJA - JUNIN

Walter Gomez Ramos


lipio Astete Orellana

orización Saldo por


Acumulado Valorizar

1,203,362.70 254,264.42
82.56% 17.44%
82.99%

0.00 0.00
0.00 0.00
0.00

1,203,362.70

0.00
0.00
0.00

1,203,362.70
216,605.29
1,419,967.99
VALO
AL M
OBRA CONSTRUCCION DE PISTAS Y VEREDAS DEL TRAMO PLAZA PRINCIAL- PARQUE BOLIVAR DEL, DISTRITO DE RICRAN - JAUJA - JUN
EJECUTA CONSORCIO BOLIVAR Residente de Obra
SUPERVISA MUNICIPALIDAD DISTRITAL DE RICRAN Inspector de Obra

PRESUP. REFERENC. 1720751.47


MONTO DE CONT. 1720000.00
FACT. DE RELAC. 0.99956
ADEL. DIRECTO. 0.00
ADEL. MATERIALES 0.00
UBICACIÓN : DISTRITO DE RICRAN - JAUJA - JAUJA
PLAZO EJEC.: 120 DIAS CALENDARIOS
INCIO DE OB : 08 DE JUNIO DEL 2017

Partida Descripción Und Metrado C.U.


(S/.)

01 OBRAS PROVISIONALES
01.01 CARTEL DE OBRA 3.60 X 8.50 und 1.00 1300.00
01.02 OFICINAS Y ALMACENES mes 4.00 750.00
02 TRABAJOS PRELIMINARES
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00 34987.50
02.02 TRANSPORTE DE MATERIALES glb 1.00 41961.54
02.03 DESVIO DE TRANSITO mes 4.00 2314.52
02.04 DEMOLICIONES m3 27.84 54.54
02.05 ELIMINACION DE DEMOLICIONES m3 33.40 7.67
02.06 TRAZO, NIVELES Y REPLANTEO m2 7669.67 1.09
03 MOVIMIENTO DE TIERRAS
03.01 CORTE A NIVEL DE SUBRASANTE m3 2065.01 4.55
03.02 CORTE A NIVEL DE SUBRASANTE EN TERRENO ROCOSO m3 667.41 203.16
03.03 RELLENO CON MATERIAL DE PRESTAMO m3 428.21 15.07
03.04 ELIMINACION DE MATERIAL EXCEDENTE m3 2765.05 7.36
04 PAVIMENTOS
04.01 PAVIMENTO RIGIDO
04.01.01 PERFILADO Y COMPACTADO DE LA SUBRASANTE DE PAVIMENTO RIGI m2 4136.21 2.77
04.01.02 CONFORMACION Y COMPACTACION DE BASE GRANULAR e=0.20m m2 4136.21 16.88
04.01.03 ENCOFRADO Y DESENCOFRADO DE PAVIMENTO RIGIDO m2 664.63 38.17
04.01.04 CONCRETO f´c = 210 kg/cm2 EN PAVIMENTOS RIGIDOS, e=0.20m m2 4116.79 77.41
04.01.05 CONCRETO f'c=175 kg/cm2 EN BERMAS m2 71.87 70.00
04.01.06 CURADO DEL CONCRETO EN PAVIMENTO RIGIDO m2 4116.79 2.27
04.01.07 JUNTAS ASFALTICAS DE CONSTRUCCION Y DILATACION (d) m 3389.05 6.27
04.01.08 JUNTAS DE CONTRACCION (d) m 1132.50 5.23
04.01.09 ACERO LISO PARA PASADORES LONGITUDINALES Y TRANSVERSALES kg 988.28 5.15
05 VEREDAS DE CONCRETO
05.01 PERFILADO Y COMPACTADO DE LA SUBRASANTE PARA VEREDAS m2 1354.51 4.89
05.02 CONFORMACION Y COMPACTACION DE BASE GRANULAR EN VEREDAS em2 1354.51 14.98
05.03 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 195.69 25.97
05.04 ENCOFRADO Y DESENCOFRADO DE MARTILLOS m2 29.85 50.23
05.05 CONCRETO f'c=175 kg/cm2 EN VEREDAS, e=0.10m m2 1206.87 49.46
05.06 CONCRETO f'c=175 kg/cm2 EN MARTILLOS, e=0.10m m2 147.64 49.46
05.07 CURADO DEL CONCRETO EN VEREDAS, MARTILLOS Y RAMPAS m2 1354.51 2.67
05.08 BRUÑADO EN VEREDAS DE CONCRETO m 1452.15 2.69
05.09 ACABADO SUPERFICIAL Y LATERAL DE VEREDA m2 1354.51 6.66
05.10 JUNTAS ASFALTICAS EN VEREDAS e=1" m 504.74 6.08
06 SARDINELES DE CONCRETO
06.01 SARDINELES PERALTADOS
06.01.01 ENCOFRADO Y DESENCOFRADO PARA SARDINELES PERALTADOS m2 1000.39 26.56
06.01.02 CONCRETO f'c=175 kg/cm2 EN SARDINEL PERALTADO m3 150.06 369.32
06.01.03 CURADO DEL CONCRETO EN SARDINEL PERALTADO m2 1000.39 2.67
06.01.04 ACABADO EN SARDINEL PERALTADO m2 1000.39 4.45
06.01.05 JUNTAS ASFALTICAS EN SARDINELESPERALTADOS e=1" m 167.40 5.67
07 SISTEMA DE EVACUACION DE AGUAS PLUVIALES
07.01 CUNETAS DE CONCRETO Y REJILLAS
07.01.01 ENCOFRADO Y DESENCOFRADO EN CUNETAS m2 66.39 30.15
07.01.02 CONCRETO f'c=175 kg/cm2 EN CUNETAS m3 21.51 369.32
07.01.03 CURADO DEL CONCRETO EN CUNETAS m2 66.39 2.67
07.01.04 ACABADO EN CUNETAS m2 66.39 3.58
07.01.05 JUNTAS ASFALTICAS EN CUNETAS e=1" m 23.43 5.67
08 REHABILITACION DE CANAL EXISTENTE
08.01 EXCAVACION MANUAL EN TERRENO NORMAL PARA CANAL m3 168.31 12.76
08.02 REFINE, NIVELACION Y COMPACTADO CON EQUIPO m2 168.31 3.84
08.03 ENCOFRADO Y DESENCOFRADO EN BASE Y PAREDES m2 336.62 42.76
08.04 ENCOFRADO Y DESENCOFRADO DE TAPAS m2 304.20 42.76
08.05 CONCRETO f'c=210 kg/cm2 EN BASE Y PAREDES m3 58.91 422.58
08.06 CONCRETO f'c=210 KG/CM2 PARA TAPAS DE CANAL m3 33.80 422.58
08.07 ACERO DE REFUERZO fy=4200 kg/cm2 EN BASE Y PAREDES kg 5900.80 6.37
08.08 ACERO CORRUGADO FY= 4200 kg/cm2 EN TAPAS DE CANAL kg 2587.73 6.37
09 BADENES
09.01 CONCRETO f'c=210 KG/CM2 m3 3.30 422.58
09.02 ENCOFRADO Y DESENCOFRADO m2 10.00 43.26
10 MUROS DE CONTENCION
10.01 MUROS DE CONTENCION DE CONCRETO ARMADO
10.01.01 REFINE, NIVELACION Y COMPACTADO CON EQUIPO m2 149.43 3.84
10.01.02 ENCOFRADO Y DESENCOFRADO DE MUROS DE CONTENCION m2 188.55 62.42
10.01.03 SOLADO EN MURO DE CONTENCION m2 149.43 24.78
10.01.04 CONCRETO f'c=210 kg/cm2 PARA MURO DE C° A° m3 121.75 422.58
10.01.05 ACERO DE REFUERZO fy=4200 kg/cm2 EN MURO DE CONTENCION kg 4205.16 6.37
10.01.06 DRENAJE EN MURO DE CONTENCION CON TUBERIA PVC DE AGUA 3" m 32.40 28.34
11 SEÑALIZACION
11.01 SEÑALIZACION HORIZONTAL
11.01.01 PINTURA INTERM. DISCONT. CENTRO DE VIA m 3061.98 4.68
11.01.02 PINTURA EN CRUCE PEATONAL m2 693.00 5.66
12 VARIOS
12.01 REPOSICION DE CAJAS DOMICILIARIAS DE AGUA Y DESAGUE und 116.00 43.96
12.02 ELEVACION DE TECHO DE BUZONES A NIVEL DE RASANTE und 16.00 164.50
12.03 REUBICACION DE POSTES DE BAJA TENSION und 13.00 1562.88
12.04 SEMBRADO DE GRASS m2 4.28 22.98
12.05 PLANTADO DE ARBOLES und 2.00 16.89
12.06 LIMPIEZA FINAL DE OBRA m2 7669.67 0.18
12.07 MITIGACION DEL IMPACTO AMBIENTAL glb 1.00 12000.00
12.08 SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 22714.92
COSTO DIRECTO
GASTOS GENERALES 8.000%
UTILIDAD 7.000%
SUB TOTAL
FACTOR DE RELACION 0.99956
I.G.V. 18.00%
TOTAL (INC. IGV)
VALORIZACION DE OBRA Nº 03
AL MES DE AGOSTO DEL 2017
DISTRITO DE RICRAN - JAUJA - JUNIN
Ing. Walter Gomez Ramos
Ing. Alipio Astete Orellana

1458263.96 Sin/IGV
1457627.12 Sin/IGV

0 Sin/IGV
0 Sin/IGV

Parcial VALORIZADO ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULA


(S/.) Metrado Parcial (S/.) % Metrado Parcial (S/.) % Metrado

1300.00 1.00 1300.00 100.00% 0.00 0.00 0.00% 1.00


3000.00 2.00 1500.00 50.00% 1.00 750.00 25.00% 3.00

34987.50 0.50 17493.75 50.00% 0.25 8,746.88 25.00% 0.75


41961.54 0.75 31471.16 75.00% 0.15 6,294.23 15.00% 0.90
9258.08 2.00 4629.04 50.00% 1.00 2,314.52 25.00% 3.00
1518.39 27.84 1518.39 100.00% 0.00 0.00 0.00% 27.84
256.18 33.40 256.18 100.00% 0.00 0.00 0.00% 33.40
8359.94 7669.67 8359.94 100.00% 0.00 0.00 0.00% 7669.67

9395.80 2065.01 9395.80 100.00% 0.00 0.00 0.00% 2065.01


135591.02 667.41 135591.02 100.00% 0.00 0.00 0.00% 667.41
6453.12 428.21 6453.12 100.00% 0.00 0.00 0.00% 428.21
20350.77 2765.05 20350.77 100.00% 0.00 0.00 0.00% 2765.05

11457.30 4136.21 11457.30 100.00% 0.00 0.00 0.00% 4136.21


69819.22 2880.00 48614.40 69.63% 1256.21 21,204.82 30.37% 4136.21
25368.93 254.00 9695.18 38.22% 283.00 10,802.11 42.58% 537.00
318680.71 760.00 58831.60 18.46% 2630.00 203,588.30 63.88% 3390.00
5030.90 0.00 0.00 0.00% 71.87 5,030.90 100.00% 71.87
9345.11 760.00 1725.20 18.46% 2530.00 5,743.10 61.46% 3290.00
21249.34 0.00 0.00 0.00% 2300.00 14,421.00 67.87% 2300.00
5922.98 0.00 0.00 0.00% 877.00 4,586.71 77.44% 877.00
5089.64 150.00 772.50 15.18% 600.00 3,090.00 60.71% 750.00

6623.55 1354.51 6623.55 100.00% 0.00 0.00 0.00% 1354.51


20290.56 1160.00 17376.80 85.64% 0.00 0.00 0.00% 1160.00
5082.07 110.56 2871.24 56.50% 40.00 1,038.80 20.44% 150.56
1499.37 1.97 98.95 6.60% 0.00 0.00 0.00% 1.97
59691.79 760.00 37589.60 62.97% 152.40 7,537.70 12.63% 912.40
7302.27 11.86 586.60 8.03% 0.00 0.00 0.00% 11.86
3616.54 760.00 2029.20 56.11% 280.00 747.60 20.67% 1040.00
3906.28 720.00 1936.80 49.58% 370.00 995.30 25.48% 1090.00
9021.04 610.00 4062.60 45.03% 430.00 2,863.80 31.75% 1040.00
3068.82 0.00 0.00 0.00% 260.00 1,580.80 51.51% 260.00

26570.36 700.00 18592.00 69.97% 0.00 0.00 0.00% 700.00


55420.16 100.00 36932.00 66.64% 0.00 0.00 0.00% 100.00
2671.04 600.00 1602.00 59.98% 0.00 0.00 0.00% 600.00
4451.74 600.00 2670.00 59.98% 0.00 0.00 0.00% 600.00
949.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00

2001.66 0.00 0.00 0.00% 66.39 2,001.66 100.00% 66.39


7944.07 0.00 0.00 0.00% 21.51 7,944.07 100.00% 21.51
177.26 0.00 0.00 0.00% 66.39 177.26 100.00% 66.39
237.68 0.00 0.00 0.00% 66.39 237.68 100.00% 66.39
132.85 0.00 0.00 0.00% 23.43 132.85 100.00% 23.43

2147.64 168.31 2147.64 100.00% 0.00 0.00 0.00% 168.31


646.31 168.31 646.31 100.00% 0.00 0.00 0.00% 168.31
14393.87 336.62 14393.87 100.00% 0.00 0.00 0.00% 336.62
13007.59 304.20 13007.59 100.00% 0.00 0.00 0.00% 304.20
24894.19 58.91 24894.19 100.00% 0.00 0.00 0.00% 58.91
14283.20 33.80 14283.20 100.00% 0.00 0.00 0.00% 33.80
37588.10 5900.80 37588.10 100.00% 0.00 0.00 0.00% 5900.80
16483.84 2587.73 16483.84 100.00% 0.00 0.00 0.00% 2587.73

1394.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00


432.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00

573.81 114.00 437.76 76.29% 35.43 136.05 23.71% 149.43


11769.29 110.00 6866.20 58.34% 38.00 2,371.96 20.15% 148.00
3702.88 97.00 2403.66 64.91% 20.60 510.47 13.79% 117.60
51449.12 73.60 31101.89 60.45% 25.00 10,564.50 20.53% 98.60
26786.87 1208.50 7698.15 28.74% 1976.00 12,587.12 46.99% 3184.50
918.22 20.00 566.80 61.73% 8.00 226.72 24.69% 28.00

14330.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00


3922.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00

5099.36 87.00 3824.52 75.00% 12.00 527.52 10.34% 99.00


2632.00 0.00 0.00 0.00% 13.00 2,138.50 81.25% 13.00
20317.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
98.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
33.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
1380.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00
12000.00 0.50 6000.00 50.00% 0.35 4,200.00 35.00% 0.85
22714.92 0.50 11357.46 50.00% 0.25 5,678.73 25.00% 0.75
1,268,055.62 696,087.86 350,771.66
101,444.45 55,687.03 28,061.73
88,763.89 48,726.15 24,554.02
1,458,263.96 800,501.04 403,387.41
1,457,627.12 800,151.45 403,211.25
262,372.88 144,027.26 72,578.03
1,720,000.00 944,178.71 54.89% 475,789.28 27.66%
VALORIZACION ACUMULADA SALDO POR VALORIZAR
Parcial (S/.) % Metrado Parcial (S/.) %

1,300.00 100.00% 0.00 0.00 0.00%


2,250.00 75.00% 1.00 750.00 25.00%

26,240.63 75.00% 0.25 8,746.87 25.00%


37,765.39 90.00% 0.10 4,196.16 10.00%
6,943.56 75.00% 1.00 2,314.52 25.00%
1,518.39 100.00% 0.00 0.00 0.00%
256.18 100.00% 0.00 0.00 0.00%
8,359.94 100.00% 0.00 0.00 0.00%

9,395.80 100.00% 0.00 0.00 0.00%


135,591.02 100.00% 0.00 0.00 0.00%
6,453.12 100.00% 0.00 0.00 0.00%
20,350.77 100.00% 0.00 0.00 0.00%

11,457.30 100.00% 0.00 0.00 0.00%


69,819.22 100.00% 0.00 0.00 0.00%
20,497.29 80.80% 127.63 4,871.64 19.20%
262,419.90 82.35% 726.79 56,260.81 17.65%
5,030.90 100.00% 0.00 0.00 0.00%
7,468.30 79.92% 826.79 1,876.81 20.08%
14,421.00 67.87% 1,089.05 6,828.34 32.13%
4,586.71 77.44% 255.50 1,336.27 22.56%
3,862.50 75.89% 238.28 1,227.14 24.11%

6,623.55 100.00% 0.00 0.00 0.00%


17,376.80 85.64% 194.51 2,913.76 14.36%
3,910.04 76.94% 45.13 1,172.03 23.06%
98.95 6.60% 27.88 1,400.42 93.40%
45,127.30 75.60% 294.47 14,564.49 24.40%
586.60 8.03% 135.78 6,715.67 91.97%
2,776.80 76.78% 314.51 839.74 23.22%
2,932.10 75.06% 362.15 974.18 24.94%
6,926.40 76.78% 314.51 2,094.64 23.22%
1,580.80 51.51% 244.74 1,488.02 48.49%

18,592.00 69.97% 300.39 7,978.36 30.03%


36,932.00 66.64% 50.06 18,488.16 33.36%
1,602.00 59.98% 400.39 1,069.04 40.02%
2,670.00 59.98% 400.39 1,781.74 40.02%
0.00 0.00% 167.40 949.16 100.00%

2,001.66 100.00% 0.00 0.00 0.00%


7,944.07 100.00% 0.00 0.00 0.00%
177.26 100.00% 0.00 0.00 0.00%
237.68 100.00% 0.00 0.00 0.00%
132.85 100.00% 0.00 0.00 0.00%

2,147.64 100.00% 0.00 0.00 0.00%


646.31 100.00% 0.00 0.00 0.00%
14,393.87 100.00% 0.00 0.00 0.00%
13,007.59 100.00% 0.00 0.00 0.00%
24,894.19 100.00% 0.00 0.00 0.00%
14,283.20 100.00% 0.00 0.00 0.00%
37,588.10 100.00% 0.00 0.00 0.00%
16,483.84 100.00% 0.00 0.00 0.00%

0.00 0.00% 3.30 1,394.51 100.00%


0.00 0.00% 10.00 432.60 100.00%

573.81 100.00% 0.00 0.00 0.00%


9,238.16 78.49% 40.55 2,531.13 21.51%
2,914.13 78.70% 31.83 788.75 21.30%
41,666.39 80.99% 23.15 9,782.73 19.01%
20,285.27 75.73% 1,020.66 6,501.61 24.27%
793.52 86.42% 4.40 124.70 13.58%

0.00 0.00% 3,061.98 14,330.07 100.00%


0.00 0.00% 693.00 3,922.38 100.00%

4,352.04 85.34% 17.00 747.32 14.66%


2,138.50 81.25% 3.00 493.50 18.75%
0.00 0.00% 13.00 20,317.44 100.00%
0.00 0.00% 4.28 98.35 100.00%
0.00 0.00% 2.00 33.78 100.00%
0.00 0.00% 7,669.67 1,380.54 100.00%
10,200.00 85.00% 0.15 1,800.00 15.00%
17,036.19 75.00% 0.25 5,678.73 25.00%
1,046,859.52 221,196.10
83,748.76 17,695.69
73,280.17 15,483.73
1,203,888.45 254,375.52
1,203,362.70 254,264.43
216,605.29 45,767.60
1,419,967.99 82.56% 300,032.03 17.44%
10
RESUMEN VALORIZACION DE OBRA
CORRESPONDIENTE AL MES DE AGOSTO DEL 2

OBRA CONSTRUCCION DE PISTAS Y VEREDAS DEL TRAMO PLAZA PRINCIAL- PARQUE BOLIVAR DEL, DISTRITO DE RICR
EJECUTA CONSORCIO BOLIVAR Residente de Obra
SUPERVISA MUNICIPALIDAD DISTRITAL DE RICRAN Inspector de Obra
CLIENTE MUNICIPALIDAD DISTRITAL DE RICRAN
PRESUP. REFERENC. 1720751.47 1458263.96 Sin/IGV
MONTO DE CONT. 1720000 1457627.12 Sin/IGV
FACT. DE RELAC. 0.99956
ADEL. DIRECTO. 0 0 Sin/IGV
ADEL. MATERIALES 0 0 Sin/IGV
UBICACIÓN : DISTRITO DE RICRAN - JAUJA - JAUJA
PLAZO EJEC. : 120 DIAS CALENDARIOS
INCIO DE OBRA : 08 DE JUNIO DEL 2017

PRESUPUESTO
ITEM FORMULA BASE
SIN IGV
1.00 CONSTRUCCIÓN DE PISTAS Y VEREDAS RICRAN 1,457,627.12

TOTAL SIN IGV (S/.) 1,457,627.11


N VALORIZACION DE OBRA Nº 03
ESPONDIENTE AL MES DE AGOSTO DEL 2017

RQUE BOLIVAR DEL, DISTRITO DE RICRAN - JAUJA - JUNIN


Ing. Walter Gomez Ramos
Ing. Alipio Astete Orellana

VALORIZACION
PORCENTAJE DE AVANCE (%) MONTO VALORIZADO (S/.)
ANTERIOR ACTUAL ACUMULADO ANTERIOR ACTUAL ACUMULADO SALDO
54.89% 27.66% 82.56% 800,151.45 403,211.25 1,203,362.70 254,264.42

54.89% 27.66% 82.56% 800,151.45 403,211.25 1,203,362.70 254,264.41

También podría gustarte