ENTIDAD TECNICA COAR NORTH SAC

CRONOGRAMA VALORIZADO DE OBRA


MODULOS : 15 CSP
PLAZO : 90 DIAS CALENDARIOS
FECHA : jun-19
PRESUPUESTO AVANCE DE OBRA
ITEM DESCRIPCION TOTAL
REFERENCIAL 1° MES 2° MES 3° MES
ESTRUCTURAS
01.02 OBRAS PROVIS. Y TRAB. PRELIMINARES 6,151.74 6,151.74 6,151.74
01.03 MOVIMIENTO DE TIERRAS 9,227.61 9,227.61 9,227.61
01.04 CONCRETO SIMPLE 30,758.72 15,379.36 15,379.36 30,758.72
01.05 CONCRETO ARMADO 123,034.87 36,910.46 36,910.46 49,213.95 123,034.87
ARQUITECTURA
02.01 ALBAÑILERIA 7,997.27 2,399.18 3,198.91 2,399.18 7,997.27
02.02 MAMPOSTERIA 38,755.98 11,626.79 15,502.39 11,626.79 38,755.98
02.03 REVOQUES, ENLUCIDOS (REVESTIMIENTO) 18,455.23 9,227.61 9,227.61 18,455.23
02.04 PISOS 7,074.50 3,537.25 3,537.25 7,074.50
02.05 ZOCALOS 5,536.57 2,768.28 2,768.28 5,536.57
02.06 PUERTAS Y VENTANAS 20,300.75 6,090.23 8,120.30 6,090.23 20,300.75
02.07 CERRAJERIA 2,153.11 1,076.56 1,076.56 2,153.11
02.08 VIDRIOS, CRISTALES Y SIMILARES 5,228.98 2,614.49 2,614.49 5,228.98
02.09 APARATOS Y ACCESORIOS SANITARIOS 11,073.14 5,536.57 5,536.57 11,073.14
02.10 PINTURA 2,460.70 2,460.70 2,460.70
INSTALACIONES ELECTRICAS
03.00 INSTALACIONES ELECTRICAS 7,997.27 2,399.18 3,198.91 2,399.18 7,997.27
INSTALACIONES SANITARIAS
04.00 SISTEMA DE AGUA 4,613.81 1,384.14 1,845.52 1,384.14 4,613.81
SISTEMA DE DESAGUE
05.00 SISTEMA DE DESAGUE 6,766.92 2,030.08 2,706.77 2,030.08 6,766.92
COSTO DIRECTO S/. 307,587.16 93,598.77 111,623.38 102,365.01 307,587.16
Gastos Generales 10.00% 30,758.72 9,359.88 11,162.34 10,236.50 30,758.72
Gastos Financieros 1.5% del Total al 110% 6,605.78 6,605.78 6,605.78
Gastos de Supervision 3.01% 9,260.27 2,817.90 3,360.55 3,081.82 9,260.27
Utilidad+Impuesto Renta 15.00% 46,138.07 14,039.82 16,743.51 15,354.75 46,138.07
TOTAL S/. 400,350.00 126,422.14 142,889.78 131,038.08 400,350.00
Porcentaje de Avance de Obra 31.58% 35.69% 32.73% 100.00%