PRESUPUESTO INSTALACIONES SANITARIAS

ITEM DESCRIPCION UND METRADO PU PARCIAL

A SISTEMA DE DESAGUE
1.00 TRABAJOS PRELIMINARES
1.01 TRAZO Y REPLANTEO gbl 1.00 S/. 4,247.93 S/. 4,247.93
1.02 EXCAVACION DE ZANJAS m 180.00 S/. 35.77 S/. 6,438.97
1.03 RELLENO CON MATERIAL PROPIO Y COMP m 180.00 S/. 29.87 S/. 5,376.54
1.04 ACARREO DE DESMONTE A LUGAR DE ACO m3 160.00 S/. 27.95 S/. 4,471.51
3.00 REDES COLECTORAS ENTERRADAS
3.01 TUBERIA DE PVC Ø4" m 190.00 S/. 50.62 S/. 9,617.32
3.02 TUBERIA DE PVC P Ø2" m 30.00 S/. 14.00 S/. 419.87
3.03 TUBERIA DE PVC P Ø6" m 34.00 S/. 59.62 S/. 2,026.96
4.00 REDES COLECTORAS COLGADAS
4.01 TUBERIA COLGADA DE PVC P Ø2" m 62.00 S/. 19.59 S/. 1,214.28
4.02 TUBERIA COLGADA DE PVC P Ø3" m 150.00 S/. 26.83 S/. 4,024.36
4.03 TUBERIA COLGADA DE PVC P Ø4" m 310.00 S/. 38.02 S/. 11,785.88
4.04 TUBERIA COLGADA DE PVC P Ø6" m 44.00 S/. 62.65 S/. 2,756.42
4.05 TUBERIA DE PVC C-10 Ø3" IMPULSIÓN D m 48.00 S/. 51.42 S/. 2,468.27
5.00 REDES COLECTORAS EMPOTRADAS EN LOSA
5.01 TUBERIA EMPOTRADADE EN LOSA PVC P Ø m 3,234.40 S/. 16.77 S/. 54,234.90
5.02 TUBERIA EMPOTRADA EN LOSA DE PVC P Ø m 195.23 S/. 25.71 S/. 5,019.59
5.03 TUBERIA EMPOTRADA EN LOSA DE PVC P Ø m 951.60 S/. 35.77 S/. 34,040.68
6.00 CAJAS DE REGISTRO
6.01 CAJA DE REGISTRO DE DESAGÜE 12"x24"D und 8.00 S/. 402.44 S/. 3,219.48
6.02 CAJA DE REGISTRO DE DESAGÜE 18"x24"D und 2.00 S/. 626.01 S/. 1,252.02

7.00 TUBERIAS PVC MONTANTES


7.01 TUBERIA DE PVC P Ø2" EMPOTRADA m 250.00 S/. 19.59 S/. 4,896.30
7.02 TUBERIA DE PVC P Ø2" MONTANTE ADOSA m 420.00 S/. 19.59 S/. 8,225.78
7.03 TUBERIA DE PVC P Ø3" MONTANTE ADOSAD m 3,384.00 S/. 24.59 S/. 83,223.67
7.04 TUBERIA DE PVC P Ø4" MONTANTE ADOSAD m 1,944.00 S/. 38.02 S/. 73,908.90
7.05 TUBERIA DE PVC C-10 Ø2" IMPULSIÓN D m 24.00 S/. 38.01 S/. 912.19
7.06 SOPORTERÍA PARA MONTANTE glb 1.00 S/. 7,266.20 S/. 7,266.20
8.00 SALIDAS DE DESAGÜE
8.01 SALIDA DE DESAGÜE PVC P Ø2" pto 800.00 S/. 41.46 S/. 33,169.63
8.02 SALIDA DE DESAGÜE PVC P Ø4" pto 308.00 S/. 71.06 S/. 21,887.53
8.03 SALIDA PARA SUMIDERO DE PVC P 2" pto 677.00 S/. 41.46 S/. 28,069.80
8.04 SALIDA PARA SUMIDERO DE PVC P 6" pto 2.00 S/. 249.98 S/. 499.96
8.05 SALIDA DE VENTILACIÓN PVC P Ø2" pto 300.00 S/. 36.06 S/. 10,818.81
8.06 TRAMPA EN U 2" PVC pto 557.00 S/. 20.12 S/. 11,207.83
9.00 ACCESORIOS
9.01 SUMIDERO DE BRONCE 2" und 677.00 S/. 20.12 S/. 13,622.44
9.02 SUMIDERO DE BRONCE 6" und 2.00 S/. 80.49 S/. 160.97
9.03 REGISTRO DE BRONCE CROMADO Ø2" und 740.00 S/. 24.59 S/. 18,199.03
9.04 REGISTRO DE BRONCE CROMADO Ø3" und 48.00 S/. 29.06 S/. 1,395.11
9.05 REGISTRO DE BRONCE CROMADO Ø4" und 18.00 S/. 38.01 S/. 684.14
9.06 REGISTRO DE DADO DE BRONCE Ø6" und 3.00 S/. 229.16 S/. 687.49
9.07 REGISTRO DE DADO DE BRONCE Ø4" und 48.00 S/. 106.20 S/. 5,097.52
9.08 REGISTRO DE DADO DE BRONCE Ø3" und 27.00 S/. 74.90 S/. 2,022.24
9.09 REGISTRO DE DADO DE BRONCE Ø2" und 19.00 S/. 59.25 S/. 1,125.70
9.10 SOMBRERO DE VENTILACION DE Ø3" und 67.00 S/. 20.12 S/. 1,348.16
9.11 SOMBRERO VENTILACION PVC Ø2" und 14.00 S/. 15.65 S/. 219.10
9.12 SOMBRERO VENTILACION PVC Ø4" und 33.00 S/. 30.18 S/. 996.03
9.13 VALVULA ANTERETORNO DE 6" DESAGUE und 2.00 S/. 2,012.18 S/. 4,024.36
10.00 PRUEBASDE ESTANCAMIENTO
10.01 PRUEBAS DE ESTANCAMIENTO ml 9,271.23 S/. 2.01 S/. 18,655.36
10.02 EMPALME A LA RED DE DESAGUE gbl 1.00 S/. 2,012.18 S/. 2,012.18
11.00 VARIOS
11.01 PINTADO DE TUBERÍA A LA VISTA gbl 1.00 S/. 5,142.23 S/. 5,142.23
11.02 PASES EN VIGA GBL 1.00 S/. 3,577.20 S/. 3,577.20
B SISTEMA DE AGUA FRIA
12.00 SALIDA DE AGUA FRÍA
12.01 SALIDA DE AGUA FRIA PPR PN-10 DE 1/2" pto 1,460.00 S/. 31.30 S/. 45,698.79
12.02 SALIDA DE AGUA FRIA PPR PN-10 DE 3/4" pto 165.00 S/. 38.01 S/. 6,271.29
13.00 REDES DE DISTRIBUCIÓN
13.01 TUBERIA PPR PN-10 DE 1/2" m 2,119.00 S/. 11.18 S/. 23,687.80
13.02 TUBERIA PPR PN-10 DE 3/4" m 2,281.50 S/. 15.65 S/. 35,706.09
13.03 TUBERIA PPR PN-10 DE 1" m 1,547.00 S/. 19.00 S/. 29,399.03
13.04 TUBERIA PPR PN-10 DE 1 1/4" m 4,326.40 S/. 22.36 S/. 96,727.62
13.05 TUBERIA PPR PN-10 DE 2" COLGADA m 58.50 S/. 65.95 S/. 3,858.35
13.06 TUBERIA PPR PN-10 DE 1 1/2" COLGADA m 24.00 S/. 26.83 S/. 643.90
13.07 TUBERIA PPR PN-10 DE 1" COLGADA m 78.00 S/. 24.59 S/. 1,918.28
13.08 TUBERIA PPR PN-10 DE 3/4" COLGADA m 48.00 S/. 17.89 S/. 858.53
13.09 TUBERIA PPR PN-10 DE 1/2" COLGADA m 35.00 S/. 13.41 S/. 469.51
14.00 MONTANTES DE A.F.
14.01 TUBERIA PPR PN-10 DE 4" ADOSADA m 120.00 S/. 99.49 S/. 11,938.92
14.02 TUBERIA PPR PN-10 DE 2" ADOSADA m 37.00 S/. 41.36 S/. 1,530.37
14.03 TUBERIA PPR PN-10 DE 2 1/2" ADOSADA m 34.00 S/. 53.66 S/. 1,824.37
14.04 TUBERIA PPR PN-10 DE 3" ADOSADA m 48.00 S/. 81.60 S/. 3,917.04
15.00 VÁLVULAS
15.01 VALVULA ESFÉRICA DE 1/2" CON ADAPTAD und 862.00 S/. 58.13 S/. 50,107.70
15.02 VALVULA ESFÉRICA DE 3/4" CON ADAPTAD und 165.00 S/. 67.07 S/. 11,066.98
15.03 VALVULA ESFÉRICA DE 1 1/4" CON ADAPTA und 165.00 S/. 176.62 S/. 29,143.04
15.04 VALVULA ESFERICA DE 2" GENERAL DEL ED und 1.00 S/. 648.37 S/. 648.37
15.05 GRIFO DE RIEGO DE 1/2" und 15.00 S/. 50.30 S/. 754.57
15.06 Válvula REDUCTORA de presion4" und 1.00 S/. 9,812.77 S/. 9,812.77
15.07 Válvula REDUCTORA de presión 2 1/2" und 1.00 S/. 1,387.94 S/. 1,387.94
16.00 MEDIDORES DE AGUA
16.01 MEDIDOR DE AGUA Ø1 1/4" VANSA/NWM DP und 173.00 S/. 548.49 S/. 94,888.10
16.02 BATERIA PARA MEDIDOR und 173.00 S/. 89.43 S/. 15,471.41
17.00 PRUEBAS HIDRAULICAS
17.01 PRUEBA DE TUBERÍA DE AGUA ml 6,756.40 S/. 2.01 S/. 13,595.08
18.00 ROMPEAGUA Y OTROS
18.01 ROMPEAGUA DE 2" LLENADO und 3.00 S/. 313.01 S/. 939.02
18.02 ROMPEAGUA DE 3" SUCCIÓN A.D. und 1.00 S/. 510.87 S/. 510.87
18.03 ROMPEAGUA DE 6" SUCCIÓN ACI und 1.00 S/. 894.30 S/. 894.30
18.04 ROMPEAGUA DE 6" RETORNO, ALIVIO Y P und 5.00 S/. 894.30 S/. 4,471.51
18.05 LINIA DE REBOSE DE 6 " gbl 1.00 S/. 726.62 S/. 726.62
18.06 DESINFECCION DE CISTERNA CON CERTI GBL 1.00 S/. 1,850.00 S/. 1,850.00
18.07 EMPALME LA RED PUBLICA gbl 1.00 S/. 1,341.45 S/. 1,341.45
C SISTEMA DE AGUA CALIENTE
19.00 SALIDA DE AGUA CALIENTE
19.01 SALIDA DE AGUA CALIENTE PPR PN-16 DE 1 pto 810.00 S/. 38.01 S/. 30,786.32
19.02 SALIDA DE AGUA CALIENTE PPR PN-16 DE 3 pto 165.00 S/. 42.48 S/. 7,009.09
19.03
20.00 VÁLVULAS
20.01 VALVULA ESFÉRICA DE 1/2" CON ADAPTAD und 680.00 S/. 58.13 S/. 39,528.11
20.02 VALVULA ESFÉRICA DE 3/4" CON ADAPTAD und 165.00 S/. 67.07 S/. 11,066.98

21.00 REDES DE DISTRIBUCIÓN


21.01 TUBERIA PPR PN-16 DE 1/2" m 3,497.00 S/. 11.18 S/. 39,092.14
21.02 TUBERIA PPR PN-16 DE 3/4" m 1,756.30 S/. 13.41 S/. 23,559.92
22.00 PRUEBAS HIDRAULICAS
22.01 PRUEBA DE TUBERÍA DE AGUA ml 5,253.30 S/. 2.01 S/. 10,570.57
23.00 INATALACIONES DE APARATOS SANITARIOS
23.01 INSTALACION DE INODORO - SOLO MANO D und 328.00 S/. 60.37 S/. 19,799.83
23.02 INSTALACION DE LAVATORIO - SOLO MANO und 328.00 S/. 57.01 S/. 18,699.84
23.03 INSTALACION DE LAVADERO DE LAVANDERIA und 173.00 S/. 57.01 S/. 9,863.02
23.04 INSTALACION DE LAVADERO DE COCINA - S und 173.00 S/. 57.01 S/. 9,863.02
23.05 INSTALACION DE MEZCLADORA DE DUCHA und 328.00 S/. 38.01 S/. 12,466.56
23.06 INSTALACIONES DE GRIFERIAS und 501.00 S/. 38.01 S/. 19,041.91
TOTAL COSTO DIRECTO S/. S/. 1,269,077.75
PRESUPUESTO INSTALACIONES ELECTRICAS

ITEM DESCRIPCION UND METRADO PU PARCIAL

1.00 ALIMENTADORES ELECTRICOS


1.01 De Concesionario a banco de medidores
1.01.01 Tubería de 100mmØ PVC-P ml 37.00 S/. 36.68 S/. 1,357.22
1.02 De Medidor a TBCI
1.02.01 Tubería de 100mmØ PVC-P ml 50.00 S/. 36.68 S/. 1,834.09
1.02.02 Cable 3-1x185mm2N2XOH+1x25/Tmm2N2XOH ml 59.00 S/. 250.55 S/. 14,782.48
1.03 De Medidor a TSG
1.03.01 Tubería de 80mmØ PVC-P ml 39.00 S/. 26.50 S/. 1,033.38
1.03.02 Cable 2(3-1x150mm2 THW + 1x25mm2 TW/T) ml 49.00 S/. 413.07 S/. 20,240.29
1.04 De TSG a TS1
1.04.01 Tubería de 35mmØ PVC-P ml 3.00 S/. 10.38 S/. 31.15
1.04.02 Cable 3-1x16mm2 THW+ 1x6mm2 TW/T ml 6.60 S/. 26.97 S/. 177.99
1.05 De TSG a TS2
1.05.01 Tubería de 35mmØ PVC-P ml 7.00 S/. 10.38 S/. 72.68
1.05.02 Cable 3-1x16mm2 THW+ 1x6mm2 TW/T ml 10.60 S/. 26.97 S/. 285.86
1.06 De TSG a TS3
1.06.01 Tubería de 35mmØ PVC-P ml 11.00 S/. 10.38 S/. 114.22
1.06.02 Cable 3-1x16mm2 THW+ 1x6mm2 TW/T ml 14.60 S/. 26.97 S/. 393.73
1.07 De TSG a TS4
1.07.01 Tubería de 35mmØ PVC-P ml 19.90 S/. 10.38 S/. 206.63
1.07.02 Cable 3-1x16mm2 THW+ 1x6mm2 TW/T ml 23.00 S/. 26.97 S/. 620.25
1.08 De TSG a TSA
1.08.01 Tubería de 40mm2 PVC-P ml 29.00 S/. 11.85 S/. 343.57
1.08.02 Cable 3-1x25mm2 THW+ 1x10mm2 TW/T ml 35.00 S/. 42.11 S/. 1,473.81
1.09 De TSG a TF-VVP
1.09.01 Tubería de 40mm2 PVC-P ml 98.00 S/. 11.85 S/. 1,161.04
1.09.02 Cable 3-1x25mm2 THW+ 1x10mm2 TW/T ml 110.00 S/. 42.11 S/. 4,631.96
1.10 De TSG a TF-ASC 1
1.10.01 Tubería de 40mm PVC-P ml 91.00 S/. 11.85 S/. 1,078.11
1.10.02 Cable 3-1x50mm2 THW+ 1x10mm2 TW/T ml 98.00 S/. 70.79 S/. 6,937.54
1.11 De TSG a TF-ASC 2
1.11.01 Tubería de 40mm PVC-P ml 102.00 S/. 11.85 S/. 1,208.43
1.11.02 Cable 3-1x50mm2 THW+ 1x10mm2 TW/T ml 108.00 S/. 70.79 S/. 7,645.45
1.12 De TSG a TF-ASC 3
1.12.01 Tubería de 40mm PVC-P ml 104.00 S/. 11.85 S/. 1,232.12
1.12.02 Cable 3-1x50mm2 THW+ 1x10mm2 TW/T ml 110.00 S/. 70.79 S/. 7,787.03
1.13 DE TSG a TF-BA
1.13.01 Tubería de 50mmØ PVC-P ml 45.00 S/. 14.55 S/. 654.53
1.13.02 Cable 3-1x70mm2 THW + 1x16mm2 TW/T ml 50.00 S/. 108.86 S/. 5,443.18
1.14 DE TSG a TF-MO
1.14.01 Tubería de 50mmØ PVC-P ml 6.90 S/. 14.55 S/. 100.36
1.14.02 Cable 3-1x70mm2 THW + 1x16mm2 TW/T ml 11.90 S/. 108.86 S/. 1,295.48
1.15 DE TSG a TD-AZ
1.15.01 Tubería de 35mmØ PVC-P ml 105.50 S/. 10.38 S/. 1,095.45
1.15.02 Cable 3-1x16mm2 THW+ 1x6mm2 TW/T ml 115.50 S/. 26.97 S/. 3,114.75
1.16 DE TSG a TD-GYM
1.16.01 Tubería de 35mmØ PVC-P ml 109.50 S/. 10.38 S/. 1,136.98
1.16.02 Cable 3-1x16mm2 THW+ 1x6mm2 TW/T ml 119.50 S/. 26.97 S/. 3,222.62
1.17 DE TSG a ECG(CORREDORES 7.5HP(220,3∅,60Hz)
1.17.01 Tubería de 50mmØ PVC-P ml 106.00 S/. 14.55 S/. 1,541.78
1.17.02 Cable 3-1x35mm2 THW+ 1x10mm2 TW/T ml 115.50 S/. 55.64 S/. 6,426.37
1.18 DE TSG a ICG(CORREDORES 10HP(220,3∅,60Hz
1.18.01 Tubería de 40mm2 PVC-P ml 96.30 S/. 11.85 S/. 1,140.90
1.18.02 Cable 3-1x25mm2 THW+ 1x10mm2 TW/T ml 106.30 S/. 42.11 S/. 4,476.16
1.19 DE TF-MO a TCM-1-2-3-4-5
1.19.01 Tubería de 35mmØ PVC-P ml 124.00 S/. 10.38 S/. 1,287.54
1.19.02 Cable 3-1x16mm2 THW+ 1x6mm2 TW/T ml 129.00 S/. 26.97 S/. 3,478.82
1.20 DE TF-MO A EC-CO
1.20.01 Tubería de 50mmØ PVC-P ml 113.50 S/. 14.55 S/. 1,650.87
1.20.02 Cable 3-1x50mm2 THW+ 1x16mm2 TW/T ml 122.50 S/. 70.79 S/. 8,671.92
1.21 DE TCM-1 A ICG
1.21.01 Tubería de 25mmØ PVC-P ml 24.00 S/. 5.30 S/. 127.24
1.21.02 Cable 2-1x4m2 THW+ 1x4mm2 TW/T ml 28.00 S/. 7.72 S/. 216.08
1.22 DE TCM-1 A JET FAN
1.22.01 Tubería de 25mmØ PVC-P ml 157.10 S/. 5.30 S/. 832.87
1.22.02 Cable 3-1x4m2 THW+ 1x4mm2 TW/T ml 178.10 S/. 9.44 S/. 1,681.68
1.23 DE TCM-2 A ICG
1.23.01 Tubería de 25mmØ PVC-P ml 60.00 S/. 5.30 S/. 318.09
1.23.02 Cable 2-1x4m2 THW+ 1x4mm2 TW/T ml 68.00 S/. 7.72 S/. 524.75
1.24 DE TCM-2 A JET FAN
1.24.01 Tubería de 25mmØ PVC-P ml 121.10 S/. 5.30 S/. 642.01
1.24.02 Cable 3-1x4m2 THW+ 1x4mm2 TW/T ml 108.10 S/. 9.44 S/. 1,020.71
1.25 DE TCM-3 A ICG
1.25.01 Tubería de 25mmØ PVC-P ml 58.50 S/. 5.30 S/. 310.14
1.25.02 Cable 2-1x4m2 THW+ 1x4mm2 TW/T ml 66.50 S/. 7.72 S/. 513.18
1.26 DE TCM-3 A JET FAN
1.26.01 Tubería de 25mmØ PVC-P ml 107.00 S/. 5.30 S/. 567.26
1.26.02 Cable 3-1x4m2 THW+ 1x4mm2 TW/T ml 123.00 S/. 9.44 S/. 1,161.40
1.27 DE TCM-4 A ICG
1.27.01 Tubería de 25mmØ PVC-P ml 24.00 S/. 5.30 S/. 127.24
1.27.02 Cable 2-1x4m2 THW+ 1x4mm2 TW/T ml 28.00 S/. 7.72 S/. 216.08
1.28 DE TCM-4 A JET FAN
1.28.01 Tubería de 25mmØ PVC-P ml 19.00 S/. 5.30 S/. 100.73
1.28.02 Cable 3-1x4m2 THW+ 1x4mm2 TW/T ml 23.00 S/. 9.44 S/. 217.17
1.29 DE TF-BA a TC-BS
1.29.01 Tubería de 25mmØ PVC-P ml 4.00 S/. 5.30 S/. 21.21
1.29.02 Cable 3-1x6m2 THW+ 1x4mm2 TW/T ml 7.00 S/. 12.09 S/. 84.61
1.30 DE MEDIDOR a TABLEROS DE DEPARTAMENTO
1.30.01 Tubería de 25mmØ PVC-P ml 2,242.10 S/. 5.30 S/. 11,886.48
1.30.02 Tubería de 35mmØ PVC-P ml 6,386.75 S/. 10.38 S/. 66,316.20
1.30.03 Cable 2-1x10mm2 THW+ 1x6mm2 TW/T ml 4,066.05 S/. 13.45 S/. 54,676.94
1.30.04 Cable 2-1x16mm2 THW+ 1x6mm2 TW/T ml 7,245.35 S/. 21.91 S/. 158,720.82
1.30.05 Cable 2-1x25mm2 THW+ 1x6mm2 TW/T ml 7,483.20 S/. 32.85 S/. 245,857.82
1.30.06 Soportería para tubos y cajas adosadas gbl 1.00 S/. 1,547.58 S/. 1,547.58

CIRCUITOS DERIVADOS DEPARTAMENTOS ( accesorios


2.00 en la linea MODUS TICINO)
2.01 Punto para centro luz pto 1,950.00 S/. 87.45 S/. 170,524.66
2.02 Punto para Braquete pto 350.00 S/. 99.25 S/. 34,738.92
2.03 Punto para interruptor unipolar simple pto 526.00 S/. 86.08 S/. 45,277.41
2.04 Punto para interruptor unipolar doble pto 643.00 S/. 93.57 S/. 60,162.72
2.05 Punto para interruptor unipolar triple pto 22.00 S/. 97.25 S/. 2,139.42
2.06 Punto para interruptor conmutado simple pto 57.00 S/. 93.58 S/. 5,333.84
2.07 Punto para interruptor conmutado doble pto 212.00 S/. 127.42 S/. 27,013.92
2.08 Punto para interruptor conmutado triple pto 33.00 S/. 166.41 S/. 5,491.41
2.09 Punto para Tomacorriente doble 2P+T pto 2,868.00 S/. 121.89 S/. 349,587.94
2.10 Punto para Tomacorriente doble 2P+T prueba de agua pto 9.00 S/. 157.62 S/. 1,418.61
2.11 Punto para campana extractora pto 12.00 S/. 91.01 S/. 1,092.17
2.12 Punto para lavadora/secadora pto 9.00 S/. 163.65 S/. 1,472.81
2.13 Llave de 2x30 A para Lavadora/Secadora pto 173.00 S/. 90.48 S/. 15,653.21
2.14 Punto para timbre pto 173.00 S/. 147.50 S/. 25,517.64
2.15 Punto para pulsador pto 173.00 S/. 86.63 S/. 14,987.50
2.16 Punto para extractor de aire en baño pto 314.00 S/. 74.46 S/. 23,380.89
2.17 Punto para Tomacorriente doble 2P+T prueba de agua pto 5.00 S/. 157.62 S/. 788.11

3.00 CIRCUITOS COMUNICACIONES


3.01 Punto para teléfono externo pto 174.00 S/. 101.61 S/. 17,679.58
3.02 Punto para teléfono interno (no incl. Tapa ciega) pto 177.00 S/. 80.56 S/. 14,258.70
3.03 Punto para TV pto 340.00 S/. 94.80 S/. 32,231.84
3.04 Punto para sensor de humo pto 234.00 S/. 77.22 S/. 18,069.95
3.05 Punto para campana gong con luz estroboscópica pto 201.00 S/. 74.02 S/. 14,878.48
3.06 Punto para pulsador manual Aci pto 25.00 S/. 71.81 S/. 1,795.14
3.07 Caja cuadrada de 100x100x50mm (1) pto 158.00 S/. 24.95 S/. 3,942.01

4.00 ÁREA COMUN CIRCUITOS DERIVADOS


4.01 Punto para centro luz pto S/. 92.62 S/. 0.00
4.02 Punto para Spot Light pto 528.00 S/. 101.92 S/. 53,814.01
4.03 Punto para Braquete pto 115.00 S/. 100.70 S/. 11,580.16
4.04 Punto para interruptor unipolar simple pto 12.00 S/. 86.08 S/. 1,032.94
4.05 Punto para interruptor unipolar doble pto 9.00 S/. 93.57 S/. 842.09
4.06 Punto para interruptor unipolar triple pto 3.00 S/. 118.03 S/. 354.10
4.07 Punto para interruptor conmutado triple pto 2.00 S/. 166.41 S/. 332.81
4.08 Punto para Tomacorriente doble 2P+T pto 142.00 S/. 136.53 S/. 19,387.52
4.09 Punto para Tomacorriente doble 2P+T prueba de agua pto 3.00 S/. 157.62 S/. 472.87
4.10 Punto para luz de emergencia pto 213.00 S/. 159.23 S/. 33,916.65
4.11 Punto para extractor de aire en baño pto 3.00 S/. 74.46 S/. 223.38
4.12 Punto para extractor de aire en deposito pto 50.00 S/. 74.46 S/. 3,723.07
4.13 Caja cuadrada de 100x100x50mm (1) pto 208.00 S/. 24.95 S/. 5,189.49
4.14 Caja cuadrada de 150x150x50mm (2) pto 185.00 S/. 35.72 S/. 6,608.15
4.15 Caja cuadrada de 350x350x150mm (6) pto 9.00 S/. 86.82 S/. 781.39
4.16 Caja cuadrada de 450x450x100mm (7) pto 8.00 S/. 139.37 S/. 1,114.92
4.17 Caja cuadrada de 400x700x100mm (7) pto 1.00 S/. 362.17 S/. 362.17
4.18 Caja cuadrada de 400x800x300mm (7) pto 1.00 S/. 372.63 S/. 372.63
4.19 Caja cuadrada de 400x900x400mm (7) pto 1.00 S/. 377.86 S/. 377.86
4.20 Caja cuadrada de 1100x600x200mm (16) pto 1.00 S/. 554.61 S/. 554.61
4.21 Caja cuadrada de 1100x600x300mm (16) pto 1.00 S/. 570.29 S/. 570.29
4.22 Caja cuadrada de 1100x600x400mm (16) pto 1.00 S/. 585.98 S/. 585.98
4.23 Caja Banco de medidores de 710x250x250mm pto 1.00 S/. 734.48 S/. 734.48
4.24 Soporteria glb 1.00 S/. 1,307.08 S/. 1,307.08

5.00 ÁREA COMUN SALIDAS DE FUERZA


5.01 Salida de fuerza para intercomunicador pto 1.00 S/. 253.83 S/. 253.83
5.02 Salida de fuerza para PACI pto 1.00 S/. 328.37 S/. 328.37
5.03 Salida de fuerza para puerta corrediza pto 2.00 S/. 267.92 S/. 535.84
5.04 Salida de fuerza Inyección sótano 1 Jetfan pto 3.00 S/. 343.07 S/. 1,029.21
5.05 Salida de fuerza Inyección sótano 2 Jetfan pto 2.00 S/. 367.03 S/. 734.05
5.06 Salida de fuerza Inyección sótano 3 Jetfan pto 2.00 S/. 390.97 S/. 781.94
5.07 Salida de fuerza Inyección sótano 4 Jetfan pto 3.00 S/. 390.97 S/. 1,172.92
5.08 Salida de fuerza para IA-CB/EC-06 pto 1.00 S/. 232.66 S/. 232.66
5.09 Salida de fuerza para EC-01+IA-SM pto 1.00 S/. 332.45 S/. 332.45
5.10 Salida de fuerza para Bomba ACI (a T-CONTROL y Motor) pto 1.00 S/. 5,341.30 S/. 5,341.30
5.11 Salida de fuerza para Bomba Jockey (a T-CONTROL y pto 1.00 S/. 221.71 S/. 221.71
motor)
5.12 Salida de fuerza para valvula de flujo pto 8.00 S/. 133.57 S/. 1,068.58
5.13 Salida de fuerza para ascensor pto 3.00 S/. 360.26 S/. 1,080.78
5.14 Salida de fuerza para bomba de agua 8.5 Hp pto 6.00 S/. 263.75 S/. 1,582.48
5.15 Salida para control sensor de presión o nivel (solo tubo) pto 2.00 S/. 68.52 S/. 137.04
5.16 Salida de fuerza para bomba de desague 5 Hp pto 1.00 S/. 118.23 S/. 118.23

6.00 ÁREA COMUN CIRCUITOS COMUNICACIONES (solo tubo


y caja)
6.01 Punto para Central de Caci pto 1.00 S/. 78.35 S/. 78.35
6.02 Punto para intercomunicador portero pto 1.00 S/. 80.56 S/. 80.56
6.03 Punto para Cerradura electrica pto 1.00 S/. 80.56 S/. 80.56
6.04 Punto para teléfono interno pto 1.00 S/. 80.56 S/. 80.56
6.05 Punto para sensor de humo pto 64.00 S/. 77.22 S/. 4,942.21
6.06 Punto para campana gong con luz estroboscópica pto 7.00 S/. 74.02 S/. 518.16
6.07 Punto para pulsador manual Aci pto 7.00 S/. 71.81 S/. 502.64
6.08 Punto para sensor de monoxido pto 10.00 S/. 109.55 S/. 1,095.54
6.09 Caja cuadrada de 100x100x50mm (1) pto 366.00 S/. 24.95 S/. 9,131.50
6.10 Caja cuadrada de 150x150x50mm (2) pto 185.00 S/. 35.72 S/. 6,608.15
6.11 Caja cuadrada de 350x350x100mm pto 6.00 S/. 86.82 S/. 520.93
6.12 Caja cuadrada de 450x250x100mm pto 52.00 S/. 139.37 S/. 7,247.01
6.13 Caja cuadrada de 550x550x100mm pto 2.00 S/. 231.18 S/. 462.37
6.14 caja tipo C 350X650X150 mm pto 68.00 S/. 235.79 S/. 16,033.44
6.15 caja tipo E 1100X900X200 mm pto 2.00 S/. 406.32 S/. 812.65
6.16 Tuberia de 80mmØ PVC-P / TELEFONO ml 32.00 S/. 26.50 S/. 847.90
6.17 Tuberia de 50mmØ PVC-P / TELEFONO ml 298.00 S/. 14.55 S/. 4,334.45
6.18 Tuberia de 80mmØ PVC-P / TV ml 32.00 S/. 26.50 S/. 847.90
6.19 Tuberia de 50mmØ PVC-P / TV ml 298.00 S/. 14.55 S/. 4,334.45
6.20 Tuberia de 40mmØ PVC-P / INTERCOMUN ml 33.00 S/. 11.85 S/. 390.96
6.21 Tuberia de 50mmØ PVC-P / INTERCOMUN ml 120.00 S/. 14.55 S/. 1,745.42
6.22 Tuberia de 40mmØ PVC-P / ACI ml 82.00 S/. 11.85 S/. 971.48
6.23 Tuberia de 35mmØ PVC-P / ACI ml 35.00 S/. 10.38 S/. 363.42
6.24 Soportería para tubos y cajas adosadas gbl 1.00 S/. 2,352.74 S/. 2,352.74

7.00 SISTEMA PUESTA A TIERRA BAJA TENSION


7.01 Pozo de Tierra und 3.00 S/. 2,101.64 S/. 6,304.92
7.02 Tubería de 50mm2 PVC-P ml 55.00 S/. 14.55 S/. 799.98
7.03 Cable de 95mm2 TW ml 55.00 S/. 42.31 S/. 2,326.91
7.04 Zanja 0.60x0.40 ML 10.00 S/. 91.01 S/. 910.10
7.05 Relleno y compactacion con tierra tratada e=0.20m m3 10.00 S/. 80.22 S/. 802.19
7.06 Relleno y compactacion con material propio m3 10.00 S/. 100.97 S/. 1,009.67
7.07 Caja Equipotencial und 1.00 S/. 335.05 S/. 335.05

SISTEMA PUESTA A TIERRA ASCENSORES


0.01 Pozo de Tierra und 3.00 S/. 2,101.64 S/. 6,304.92
0.02 Tubería de 50mm2 PVC-P ml 55.00 S/. 14.55 S/. 799.98
0.03 Cable de 95mm2 TW ml 130.00 S/. 42.31 S/. 5,499.96
0.04 Zanja 0.60x0.40 ml 44.00 S/. 91.01 S/. 4,004.46
0.05 Relleno y compactacion con tierra tratada e=0.20m m3 10.56 S/. 80.22 S/. 847.11
0.06 Relleno y compactacion con material propio m3 5.28 S/. 100.97 S/. 533.10
0.07 Caja equipotencial und 1.00 S/. 335.05 S/. 335.05

8.00 INSTALACION DE TABLEROS


8.01 TGS und 1.00 S/. 16,678.28 S/. 16,678.28
8.02 TS-A und 1.00 S/. 17,253.39 S/. 17,253.39
8.03 TS-1 und 1.00 S/. 3,508.19 S/. 3,508.19
8.04 TS-2 und 1.00 S/. 3,278.14 S/. 3,278.14
8.05 TS-3 und 1.00 S/. 3,278.14 S/. 3,278.14
8.06 TS-4 und 1.00 S/. 2,760.54 S/. 2,760.54
8.07 TF-VVP und 1.00 S/. 632.62 S/. 632.62
8.08 T- TTA und 1.00 S/. 9,776.92 S/. 9,776.92
8.09 TF-MO und 1.00 S/. 3,565.70 S/. 3,565.70
8.10 TD-AZ und 1.00 S/. 2,415.47 S/. 2,415.47
8.11 TD-GYM und 1.00 S/. 1,955.38 S/. 1,955.38
8.12 TF-BA (Tablero de control sera Por cuenta de equipador) und 1.00 S/. 1,725.34 S/. 1,725.34
8.13 TBD (Tablero de control sera Por cuenta de equipador) und 1.00 S/. 920.18 S/. 920.18
8.14 TASC-1, TASC-2, TASC-3 und 3.00 S/. 1,955.38 S/. 5,866.15
8.15 TF-BCI (Tablero de control sera Por cuenta de equipador) und 1.00 S/. 9,776.92 S/. 9,776.92
8.16 TD-1 und 20.00 S/. 1,265.25 S/. 25,304.97
8.17 TD-2 und 117.00 S/. 1,380.27 S/. 161,491.73
8.18 TD-3 und 36.00 S/. 1,679.33 S/. 60,455.88

9.00 BANDEJAS
9.01 Bandeja de 800x100mm ml 93.00 S/. 311.08 S/. 28,930.80
9.02 Bandeja de 1100x100mm ml 29.00 S/. 520.22 S/. 15,086.26
9.03 Soporteria glb 1.00 S/. 679.68 S/. 679.68

10.00 INSTALACIÓN DE LUMINARIAS SOLO EN ÁREA COMÚN


(NO INCLUYE SUMINISTRO DE EQUIPOS)
10.01 Instalación de luminarias pto 302.00 S/. 17.78 S/. 5,368.42
10.02 Instalación de luz de emergencia pto 213.00 S/. 17.78 S/. 3,786.33

11.00 PRUEBAS ELÉCTRICAS


11.01 Prueba de megado de tableros. und 173.00 S/. 50.19 S/. 8,683.16
11.02 Prueba de continuidad y encendido. und 173.00 S/. 52.28 S/. 9,044.96
11.03 Prueba de resistencia de pozo a tierra. und 6.00 S/. 261.42 S/. 1,568.49

12.00 OTROS
12.01 Punto para alumbrado en ducto de ascensor 1 y 2Y3 und 42.00 S/. 101.92 S/. 4,280.66
12.02 Punto para interruptor conmutado en ducto de ascensor und 6.00 S/. 93.58 S/. 561.46
1y2
12.03 Punto para tomacorriente en ducto de ascensor 1 y 2 und 6.00 S/. 136.53 S/. 819.19

MONTO DIRECTO S/. 2,218,352.08


2218352.08