CODIGO: OBN-153-2018
OBRA: EMPEDRADO Y OBRAS DE ESTABILIZACION CALLE MANUEL ESCOBAR ZONA VILLA LAZARETO
GM-O-ENS-003 ENSAYO - CORTE DIRECTO PARA SUELOS Ensayo 1.00 568.12 568.12 1.00 568.12 0.00 0.00 1.00 568.12 1.00 568.12
1
EXCAVACION 0 - 1 m S/ AGOTAMIENTO
4 GM-O-EXC-007 m3 65.00 57.26 3,721.90 35.18 2,014.41 0.00 0.00 35.18 2,014.41 35.18 2,014.41
TERRENO SEMIDURO
EXCAVACION 0 - 2 m S/ AGOTAMIENTO
5 GM-O-EXC-008 m3 65.00 68.71 4,466.15 67.39 4,630.37 0.00 0.00 67.39 4,630.37 67.39 4,630.37
TERRENO SEMIDURO
EXCAVACION 2 - 4 m S/ AGOTAMIENTO
6 GM-O-EXC-010 m3 40.00 91.16 3,646.40 77.41 7,056.70 0.00 0.00 77.41 7,056.70 77.41 7,056.70
TERRENO SEMIDURO
8 GM-O-DEM-015 DEMOLICION DE HORMIGON CICLOPEO m3 5.00 260.14 1,300.70 6.12 1,592.06 0.00 0.00 6.12 1,592.06 6.12 1,592.06
9 GM-O-HOR-001 HORMIGON POBRE m3 2.00 631.33 1,262.66 2.60 1,641.46 0.00 0.00 2.60 1,641.46 2.60 1,641.46
10 GM-O-FEE-001 ACERO DE REFUERZO kg 200.00 19.29 3,858.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 GM-O-HOR-067 HORMIGON SIMPLE P/MUROS m3 3.00 1,714.34 5,143.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13 GM-O-REL-008 RELLENO DE MATERIAL DE DRENAJE m3 8.00 227.27 1,818.16 2.39 543.18 0.00 0.00 2.39 543.18 2.39 543.18
15 GM-O-SUM-015 SUMIDERO TIPO R I Pza 2.00 1,206.21 2,412.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Pag 1 de 2
VOLÚMENES AUTORIZADOS MODIFICACION VOLUMEN CERTIFICADO AVANCE
No CODIGO DESCRIPCION UNIDAD CANTIDAD MONTO CANTIDAD MONTO CANTIDAD MONTO CANTIDAD MONTO
CANTIDAD P.U. MONTO
APROBADO APROBADO ANTERIOR ANTERIOR PRESENTE PRESENTE TOTAL TOTAL
19 GM-O-TER-014 SUELO CEMENTO m3 2.00 161.62 323.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
21 GM-O-EMP-001 EMPIEDRE DE CALZADA m2 380.00 52.30 19,874.00 360.98 18,879.25 0.00 0.00 360.98 18,879.25 360.98 18,879.25
22 GM-O-EMP-005 DESEMPIEDRE m2 180.09 6.88 1,239.02 358.75 2,468.20 0.00 0.00 358.75 2,468.20 358.75 2,468.20
23 GM-O-EMP-006 EMPIEDRE DE CALZADA S/ PROV m2 50.00 34.36 1,718.00 135.83 4,667.12 0.00 0.00 135.83 4,667.12 135.83 4,667.12
24 GM-O-NIV-001 NIVELACION TERRENO (MANUAL) m3 30.00 68.71 2,061.30 37.00 2,542.27 0.00 0.00 37.00 2,542.27 37.00 2,542.27
25 GM-O-LIM-012 LIMPIEZA Y RETIRO DE ESCOMBROS m3 123.19 84.89 10,457.60 225.50 19,142.70 0.00 0.00 225.50 19,142.70 225.50 19,142.70
Arq. JERCY ERLAN CHAVEZ ZAMBRANA Ing. ELSA ALEJANDRA CARPIO SANDOVAL
ASOCIACIÓN ACCIDENTAL NEO
Pag 2 de 2