Precios Mayo 2019

Cantidad Unidad Precio I.V.A.


Cemento 1.00 Ton $3,100.00 $496.00
Arena 1.00 M3 $340.00 $54.40
Grava 1.00 M3 $320.00 $51.20
Agua 1.00 M3 $28.61 $4.58

Peoó n 1.00 JOR $459.00


Oficial Albanñ íól 1.00 JOR $767.00
Cabo de Oficios 1.00 JOR $831.00
Cantidad Unidad Costo Unitario Costo I.V.A.

Materiales
Cemento 0.26 TON $3,596.00 $934.96 $149.59
Arena 0.55 M3 $394.40 $216.92 $34.71
Grava 0.65 M3 $371.20 $241.28 $38.60
Agua 0.25 M3 $33.19 $8.30 $1.33
Total Materiales $1,401.46 $224.23
Mano de Obra
Peoó n 5.00 JOR $459.00 $2,295.00
Oficial Albanñ il 1.00 JOR $767.00 $767.00
Cabo de Oficios 0.50 JOR $831.00 $415.50
CUADRILLA (1A+5P) 0.08 JOR $3,477.50 $289.79

Equipo y Herramienta 0.03 % $289.79 $8.69


Total

Costo por M3 de Concreto F'C=100kg/cm2 $1,924.18


Cantidad a Elaborar 5.00

Volumen Requerido Unidad Costo I.V.A.


1.3 TON $23,374.00 $3,739.84
2.75 M3 $5,423.00 $867.68
3.25 M3 $6,032.00 $965.12
1.25 M3 $207.42 $33.19
$35,036.42 $5,605.83

$1,448.96

$43.47

$42,134.68
Cantidad Unidad Costo Unitario Costo I.V.A.

Materiales
Cemento 0.31 TON $3,596.00 $1,114.76 $178.36
Arena 0.54 M3 $394.40 $212.98 $34.08
Grava 0.64 M3 $371.20 $237.57 $38.01
Agua 0.25 M3 $33.19 $8.30 $1.33
Total Materiales $1,573.60 $251.78
Mano de Obra
Peoó n 5.00 JOR $459.00 $2,295.00
Oficial Albanñ il 1.00 JOR $767.00 $767.00
Cabo de Oficios 0.50 JOR $831.00 $415.50
CUADRILLA (1A+5P) 0.08 JOR $3,477.50 $289.79

Equipo y Herramienta 0.03 % $289.79 $8.69


Total

Costo por M3 de Concreto F'C=150kg/cm2 $2,123.86


Cantidad a Elaborar 5.00

Volumen Requerido Unidad Costo I.V.A.


1.55 TON $27,869.00 $4,459.04
2.7 M3 $5,324.40 $851.90
3.2 M3 $5,939.20 $950.27
1.25 M3 $207.42 $33.19
$39,340.02 $6,294.40

$1,448.96

$43.47

$47,126.85
Cantidad Unidad Costo Unitario Costo I.V.A.

Materiales
Cemento 0.35 TON $3,596.00 $1,258.60 $201.38
Arena 0.53 M3 $394.40 $209.03 $33.45
Grava 0.64 M3 $371.20 $237.57 $38.01
Agua 0.24 M3 $33.19 $7.80 $1.25
Total Materiales $1,713.00 $274.08
Mano de Obra
Peoó n 5.00 JOR $459.00 $2,295.00
Oficial Albanñ il 1.00 JOR $767.00 $767.00
Cabo de Oficios 0.50 JOR $831.00 $415.50
CUADRILLA (1A+5P) 0.08 JOR $3,477.50 $289.79

Equipo y Herramienta 0.03 % $289.79 $8.69


Total

Costo por M3 de Concreto F'C=200kg/cm2 $2,285.56


Cantidad a Elaborar 5.00

Volumen Requerido Unidad Costo I.V.A.


1.75 TON $31,465.00 $5,034.40
2.65 M3 $5,225.80 $836.13
3.2 M3 $5,939.20 $950.27
1.175 M3 $194.98 $31.20
$42,824.98 $6,852.00

$1,448.96

$43.47

$51,169.40
Cantidad Unidad Costo Unitario Costo I.V.A.

Materiales
Cemento 0.39 TON $3,596.00 $1,402.44 $224.39
Arena 0.53 M3 $394.40 $209.03 $33.45
Grava 0.63 M3 $371.20 $233.86 $37.42
Agua 0.23 M3 $33.19 $7.63 $1.22
Total Materiales $1,852.96 $296.47
Mano de Obra
Peoó n 5.00 JOR $459.00 $2,295.00
Oficial Albanñ il 1.00 JOR $767.00 $767.00
Cabo de Oficios 0.50 JOR $831.00 $415.50
CUADRILLA (1A+5P) 0.08 JOR $3,477.50 $289.79

Equipo y Herramienta 0.03 % $289.79 $8.69


Total

Costo por M3 de Concreto F'C=150kg/cm2 $2,447.92


Cantidad a Elaborar 5.00

Volumen Requerido Unidad Costo I.V.A.


1.95 TON $35,061.00 $5,609.76
2.65 M3 $5,225.80 $836.13
3.15 M3 $5,846.40 $935.42
1.15 M3 $190.83 $30.53
$46,324.03 $7,411.84

$1,448.96

$43.47

$55,228.30