METRADOS

Área del terreno:

7 𝑥 6 = 42𝑚2
Volumen de excavación para cimiento a 0.80 y 0.60:

Eje 1-1 y 2-2:

(7𝑥0.8𝑥0.4)𝑥2 = 4.48𝑚3
(5.12𝑥0.8𝑥0.4)𝑥2 = 1.6384𝑚3

3𝑥0.8𝑥0.4 = 0.96𝑚3

2.87𝑥0.8𝑥0.4 = 0.9184𝑚3

1.7𝑥0.6𝑥0.3 = 0.306𝑚3

2𝑥0.6𝑥0.3 = 0.36𝑚3

2.85𝑥0.6𝑥0.3 = 0.513𝑚3

TOTAL DE VOLUMEN = 9.18𝒎𝟑

Volumen a vaciar para sobrecimiento:

Eje 1-1 y 2-2:

(6.25𝑥0.3𝑥0.25) = 0.47𝑚3

(5.15𝑥0.3𝑥0.25) = 0.39𝑚3

(5.25𝑥0.3𝑥0.25)𝑥2 = 0.40𝑚3

(2.87 + 2.63 + 2 + 0.9 + 2 + 1.7)𝑥0.3𝑥0.25 = 0.908𝑚3

TOTAL DE VOLUMEN = 𝟐. 𝟏𝟕𝒎𝟑

Encofrado y desencofrado de sobrecimiento:

(6.25𝑥0.3) = 1.875𝑚3

(5.15𝑥0.3) = 1.545𝑚3

(5.25𝑥0.3)𝑥2 = 3.15𝑚3

(2.87 + 2.63 + 2 + 0.9 + 2 + 1.7)𝑥0.3 = 3.63𝑚3

TOTAL PARA ENCOFRAR = 𝟏𝟎. 𝟐𝒎𝟐


Falso piso de 2”:

(6.75𝑥5.75) = 38.81𝑚2

(2.87 + 2.63 + 2 + 0.9 + 2 + 1.7)𝑥0.25 = 3.025𝑚2

TOTAL PARA EL FALSO PISO(DIFERENCIA) = 𝟑𝟓. 𝟕𝟖𝟓𝒎𝟐

Solado para zapata de 3”:

(0.8𝑥0.8)𝑥4 = 2.56𝑚2

(1𝑥1) = 1𝑚2

TOTAL DE VOLUMEN PARA SOLADO DE ZAPATAS = 𝟑. 𝟓𝟔𝒎𝟐

Volumen de zapatas:

Zapata esquinera:

(0.8𝑥0.8𝑥0.5)𝑥4 = 1.28𝑚3

Zapata perimetral:

(1𝑥1𝑥0.5) = 0.5𝑚3

TOTAL DE VOLUMEN PARA ZAPATAS = 1.78𝒎𝟑

Metrado de muro de cabeza (altura de muro 2.40m)

(3.55𝑥0.25𝑥2.34) = 2.132𝑚3

(2.70𝑥0.25𝑥1.8) = 1.215𝑚3

(4.25𝑥0.25𝑥2.4) = 2.55𝑚3

(3.55𝑥0.25𝑥2.34) = 2.132𝑚3

(2𝑥0.25𝑥1.8) = 0.9𝑚3

(2.85𝑥0.25𝑥2.4) = 1.71𝑚3

(2.4𝑥0.25𝑥1.8) = 1.08𝑚3

(4.05𝑥0.25𝑥2.4) = 2.43𝑚3

(12.1𝑥0.25𝑥2.4) = 7.26𝑚3
TOTAL DE VOLUMEN PARA ASENTAR MURO DE CABEZA = 𝟏𝟗. 𝟐𝟕𝟓𝑚3

Metrado de columnas(volumen)

(0.25𝑥0.25𝑥2.2)𝑥9 = 1.238𝑚3

TOTAL DE VOLUMEN A VACIAR EN COLUMNAS = 1.238𝒎𝟑

Tarrajeo(exteriores):

(7𝑥0.02𝑥2.4)𝑥2 = 0.672𝑚3

(6𝑥0.02𝑥2.4)𝑥2 = 0.576𝑚3

TOTAL DE VOLUMEN A TARRAJEAR EN EXTERIORES = 1.248𝒎𝟑

Metrado de la losa:

(6𝑥7𝑥0.2) = 8.4𝑚3

(1.4𝑥0.6𝑥0.2) = 0.168𝑚3

RESTO TOTAL DEL VOLUMEN = 8.232𝒎𝟐

(6𝑥7) = 42𝑚2

TRAGALUZ (1.4𝑥0.6) = 0.84𝑚2

RESTO TOTAL DEL AREA = 41.16𝒎𝟐

(41.16𝑥0.05) = 2.058𝑚3
(7/3) = 23.3 = 24 𝐸𝑆𝑃𝐴𝐶𝐼𝑂𝑆
(0.15𝑥0.05𝑥24) = 0.18𝑚3

TOTAL DE VOLUMEN DE CONCRETO = 2.238𝒎𝟑