METRADOS
METRADOS
7 𝑥 6 = 42𝑚2
Volumen de excavación para cimiento a 0.80 y 0.60:
(7𝑥0.8𝑥0.4)𝑥2 = 4.48𝑚3
(5.12𝑥0.8𝑥0.4)𝑥2 = 1.6384𝑚3
3𝑥0.8𝑥0.4 = 0.96𝑚3
2.87𝑥0.8𝑥0.4 = 0.9184𝑚3
1.7𝑥0.6𝑥0.3 = 0.306𝑚3
2𝑥0.6𝑥0.3 = 0.36𝑚3
2.85𝑥0.6𝑥0.3 = 0.513𝑚3
(6.25𝑥0.3𝑥0.25) = 0.47𝑚3
(5.15𝑥0.3𝑥0.25) = 0.39𝑚3
(5.25𝑥0.3𝑥0.25)𝑥2 = 0.40𝑚3
(6.25𝑥0.3) = 1.875𝑚3
(5.15𝑥0.3) = 1.545𝑚3
(5.25𝑥0.3)𝑥2 = 3.15𝑚3
(6.75𝑥5.75) = 38.81𝑚2
(0.8𝑥0.8)𝑥4 = 2.56𝑚2
(1𝑥1) = 1𝑚2
Volumen de zapatas:
Zapata esquinera:
(0.8𝑥0.8𝑥0.5)𝑥4 = 1.28𝑚3
Zapata perimetral:
(1𝑥1𝑥0.5) = 0.5𝑚3
(3.55𝑥0.25𝑥2.34) = 2.132𝑚3
(2.70𝑥0.25𝑥1.8) = 1.215𝑚3
(4.25𝑥0.25𝑥2.4) = 2.55𝑚3
(3.55𝑥0.25𝑥2.34) = 2.132𝑚3
(2𝑥0.25𝑥1.8) = 0.9𝑚3
(2.85𝑥0.25𝑥2.4) = 1.71𝑚3
(2.4𝑥0.25𝑥1.8) = 1.08𝑚3
(4.05𝑥0.25𝑥2.4) = 2.43𝑚3
(12.1𝑥0.25𝑥2.4) = 7.26𝑚3
TOTAL DE VOLUMEN PARA ASENTAR MURO DE CABEZA = 𝟏𝟗. 𝟐𝟕𝟓𝑚3
Metrado de columnas(volumen)
(0.25𝑥0.25𝑥2.2)𝑥9 = 1.238𝑚3
Tarrajeo(exteriores):
(7𝑥0.02𝑥2.4)𝑥2 = 0.672𝑚3
(6𝑥0.02𝑥2.4)𝑥2 = 0.576𝑚3
Metrado de la losa:
(6𝑥7𝑥0.2) = 8.4𝑚3
(1.4𝑥0.6𝑥0.2) = 0.168𝑚3
(6𝑥7) = 42𝑚2
(41.16𝑥0.05) = 2.058𝑚3
(7/3) = 23.3 = 24 𝐸𝑆𝑃𝐴𝐶𝐼𝑂𝑆
(0.15𝑥0.05𝑥24) = 0.18𝑚3