3.0 Valorizacion Mensual
3.0 Valorizacion Mensual
1.01 CAPTACION DE LADERA (02 UNIDADES) 4,582.65 1,023.74 22.34% 1,188.47 25.93%
01.01.01.03 CARTEL DE IDENTIFICACION DE OBRA glb 1 800 800 1 800 100.00% 0 0 0.00% 1
01.01.02.01 EXCAVACION DE ZANJAS m3 11.75 10.31 121.14 0 0 0.00% 5.87 60.57 50.00% 5.87
01.01.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 33.6 29.08 977.09 0 0 0.00% 16.8 488.54 50.00% 16.8
01.01.03.02 CONCRETO fc= 175 kg/cm2 m3 1.91 357.59 683 0 0 0.00% 0.96 342.21 50.10% 0.96
01.01.04.01 TARRAJEO MUROS INTERIORES Y EXTERIORES (MORTERO 1:5) C/ IMPERMEABILIZANTE m2 10.92 20.88 228.01 0 0 0.00% 5.46 114 50.00% 5.46
01.01.05.01 PINTURA EN MUROS EXTERIORES AL LATEX, IMPR, TEMPLE m2 6.64 4.02 26.69 0 0 0.00% 0 0 0.00% 0
01.01.06 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS 298.32 223.74 75.00% 74.58 25.00%
01.01.06.01 SUMINISTRO E INSTALACION ACCESORIOS EN SALIDA u 2 77.08 154.16 1.5 115.62 75.00% 0.5 38.54 25.00% 2
01.01.06.02 SUMINISTRO E INSTALACION DE ACCESORIOS EN LIMPIA Y REBOSE u 2 72.08 144.16 1.5 108.12 75.00% 0.5 36.04 25.00% 2
01.01.07.01 TAPA METALICA DE 0.60 x 0.60M e=1/8" u 2 101.6 203.2 0 0 0.00% 1 101.6 50.00% 1
01.01.08.03 PUERTA DE MADERA CON ALAMBRE DE PUAS N° 16 u 2 49.04 98.08 0 0 0.00% 0 0 0.00% 0
1.02 CAMARA DE DISTRIBUCION (01 UNIDAD) 1,802.56 96.62 5.36% 1,065.53 59.11%
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 1.82 0.14 0.25 0 0 0.00% 1.82 0.25 100.00% 1.82
01.02.01.02 TRAZO Y REPLANTEO INICIAL m2 1.82 0.38 0.69 0 0 0.00% 1.82 0.69 100.00% 1.82
01.02.02.01 EXCAVACION PARA CIMIENTOS PARA MATERIAL SUELTO m3 1.82 8.09 14.72 0 0 0.00% 1.82 14.72 100.00% 1.82
01.02.03.01 CONCRETO fc= 175 kg/cm2 m3 0.6 357.21 214.33 0 0 0.00% 0.6 214.33 100.00% 0.6
01.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 10.72 21.95 235.3 0 0 0.00% 10.72 235.3 100.00% 10.72
01.02.03.03 ACERO fy=4200 kg/cm2 GRADO 60 kg 84.24 3.59 302.42 0 0 0.00% 84.24 302.42 100.00% 84.24
01.02.04.01 TARRAJEO MUROS INTERIORES (MORTERO 1:5) C/ IMPERMEABILIZANTE SIKA I m2 3.68 22.49 82.76 0 0 0.00% 3.68 82.76 100.00% 3.68
01.02.04.02 TARRAJEO EN EXTERIORES (MORTERO 1:5) m2 1.62 9.81 15.89 0 0 0.00% 1.62 15.89 100.00% 1.62
01.02.05.01 SUMINISTRO E INSTALACION EN TUBERIA PVC SAP DE 2" m 3 6.73 20.19 2 13.46 66.67% 1 6.73 33.33% 3
01.02.05.02 SUMINISTRO E INSTAL. DE ACCESORIOS EN CAMARAS u 1 166.31 166.31 0.5 83.16 50.00% 0.5 83.16 50.00% 1
01.02.06.01 PINTURA EN MUROS EXTERIORES AL LATEX, IMPR, TEMPLE m2 5.06 4.21 21.3 0 0 0.00% 0 0 0.00% 0
01.02.07.01 TAPA METALICA DE 0.60 x 0.60M e=1/16" u 1 109.28 109.28 0 0 0.00% 1 109.28 100.00% 1
01.02.08.03 PUERTA DE MADERA CON ALAMBRE DE PUAS N° 16 u 1 49.04 49.04 0 0 0.00% 0 0 0.00% 0
01.03.01.01 TRAZO, NIVELACION Y REPLANTEO DE ZANJAS m 1,468.67 0.25 367.17 1,468.67 367.17 100.00% 0 0 0.00% 1,468.67
01.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL HASTA=0.70M m 1,100.00 3.61 3,971.00 1,100.00 3,971.00 100.00% 0 0 0.00% 1,100.00
01.03.02.02 EXCAVACION DE ZANJAS 0.40 x 0.70 M, ROCA SUELTA m 282.32 4.6 1,298.67 282.32 1,298.67 100.00% 0 0 0.00% 282.32
01.03.02.03 REFINE Y NIVELACION DE FONDO DE ZANJA m 1,468.67 0.19 279.05 1,468.67 279.05 100.00% 0 0 0.00% 1,468.67
01.03.02.04 CAMA DE APOYO (MATERIAL PROPIO SARANDEADO) m 1,468.67 0.92 1,351.18 1,468.67 1,351.18 100.00% 0 0 0.00% 1,468.67
01.03.02.05 RELLENO COMPACTADO DE ZANJAS, H < 0.70 M m 1,468.67 1.21 1,777.09 1,468.67 1,777.09 100.00% 0 0 0.00% 1,468.67
01.03.03.01 TUBERIA PVC SAP CLASE 10, 1 1/2" m 1,468.67 5.33 7,828.01 1,468.67 7,828.01 100.00% 0 0 0.00% 1,468.67
01.03.03.02 PRUEBA HIDRAULICA Y DESINFECCION EN REDES DE TUBERIA DE AGUA m 1,468.67 0.49 719.65 1,314.00 643.86 89.47% 0 0 0.00% 1,314.00
01.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 20.25 0.29 5.87 20.25 5.87 100.00% 0 0 0.00% 20.25
01.04.01.02 TRAZO Y REPLANTEO INICIAL m2 20.25 0.29 5.87 0 0 0.00% 20.25 5.87 100.00% 20.25
E JIPATA DISTRITO MOHO-PUNOPROVINCIA MOHO
SALDO
ACUMULADO
VALORIZADO % METRADO VALORIZADO %
249,732.34 77.09%
2,212.21 48.27%
806.96 100.00%
60.57 50.00%
830.76 50.04%
114 50.00%
0 0.00%
298.32 100.00%
101.6 50.00%
0 0.00%
1,162.14 64.47%
14.72 100.00%
752.05 100.00%
98.65 100.00%
186.5 100.00%
0 0.00%
109.28 100.00%
0 0.00%
17,516.03 99.57%
367.17 100.00%
8,676.99 100.00%
8,471.87 99.11%
9,029.69 64.78%
14.98 100.00%
01.04.01.03 TRAZO Y REPLANTEO DURANTE LA EJECUCION m2 20.25 0.16 3.24 20.25 3.24 100.00% 0 0 0.00% 20.25
01.04.02.01 EXCAVACION MANUAL EN ROCA SUELTA m3 11.56 18.4 212.7 11.56 212.7 100.00% 0 0 0.00% 11.56
01.04.02.02 EXCAVACION MANUAL EN TERRENO SUELTO PARA CIMIENTOS PARA CERCO m3 1.36 10.51 14.29 1.36 14.29 100.00% 0 0 0.00% 1.36
01.04.02.03 REFINE, NIVELACION Y COMPACTACION m2 19.26 1.63 31.39 19.26 31.39 100.00% 0 0 0.00% 19.26
01.04.02.04 ACARREO DE MATERIAL EXCEDENTE HASTA D PROM = 30 M m3 13.87 6.02 83.5 13.87 83.5 100.00% 0 0 0.00% 13.87
01.04.02.05 ELIMINACION DE MATERIAL EXCEDENTE MANUAL d=30mts m3 13.87 14.72 204.17 13.87 204.17 100.00% 0 0 0.00% 13.87
01.04.03.01 SOLADO BASE RESERVORIO, E = 4" m2 19.26 22.03 424.3 19.26 424.3 100.00% 0 0 0.00% 19.26
01.04.04.01 CONCRETO f 'c=210 kg/cm2 m3 7.65 369.06 2,823.31 7.65 2,823.31 100.00% 0 0 0.00% 7.65
01.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 72.35 21.95 1,588.08 72.35 1,588.08 100.00% 0 0 0.00% 72.35
01.04.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 518.68 3.55 1,841.31 518.68 1,841.31 100.00% 0 0 0.00% 518.68
01.04.05.01 TARRAJEO MUROS INTERIORES (MORTERO 1:5) C/ IMPERMEABILIZANTE SIKA I m2 29.4 13.91 408.95 0 0 0.00% 29.4 408.95 100.00% 29.4
01.04.05.02 TARRAJEO EN EXTERIORES (MORTERO 1:5) m2 65.81 11.12 731.81 0 0 0.00% 65.81 731.81 100.00% 65.81
01.04.06.01 PINTURA EN MUROS EXTERIORES AL LATEX, IMPR, TEMPLE m2 43.99 4.21 185.2 0 0 0.00% 0 0 0.00% 0
01.04.07.01 SUMINISTRO E INSTALACION ACCESORIOS EN ENTRADA u 1 158.08 158.08 0.8 126.46 80.00% 0.2 31.62 20.00% 1
01.04.07.02 SUMINISTRO E INSTALACION ACCESORIOS EN SALIDA u 1 155.08 155.08 0.8 124.06 80.00% 0.2 31.02 20.00% 1
01.04.07.03 SUMINISTRO E INSTALACION EN LIMPIA Y REBOSE u 1 169.9 169.9 0.8 135.92 80.00% 0.2 33.98 20.00% 1
01.04.08.03 PUERTA DE MADERA CON ALAMBRE DE PUAS N° 16 u 1 49.79 49.79 0 0 0.00% 0 0 0.00% 0
01.04.09.01 ESCALERA FIERRO GALVANIZADO 3/4" (NO EMPOTRADO) u 1 63.78 63.78 0 0 0.00% 0 0 0.00% 0
01.04.09.02 TAPA INSPECCION 0.60x0.60 E=1/8" u 1 123.2 123.2 0 0 0.00% 1 123.2 100.00% 1
01.04.09.03 TUBERIA DE VENTILACION FIERRO GALVANIZADO 3" u 1 44.64 44.64 0 0 0.00% 1 44.64 100.00% 1
01.04.09.05 SUMINISTRO E INSTALACION DE CLORACION POR GOTEO u 1 3,500.00 3,500.00 0 0 0.00% 0 0 0.00% 0
1.05 RED DE DISTRIBUCION (550.00 ml) 7,306.09 3,402.77 46.57% 290.12 3.97%
01.05.01.01 TRAZO, NIVELACION Y REPLANTEO DE ZANJAS m 550 0.3 165 550 165 100.00% 0 0 0.00% 550
01.05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL HASTA=0.70M m 440 3.61 1,588.40 250 902.5 56.82% 0 0 0.00% 250
01.05.02.02 EXCAVACION MANUAL EN ROCA SUELTA HASTA=0.70M m 110 4.51 496.1 0 0 0.00% 0 0 0.00% 0
01.05.02.03 REFINE Y NIVELACION DE FONDO DE ZANJA m 550 0.29 159.5 0 0 0.00% 0 0 0.00% 0
01.05.02.04 CAMA DE APOYO (MATERIAL PROPIO SARANDEADO) m 550 0.56 308 0 0 0.00% 0 0 0.00% 0
01.05.02.05 RELLENO COMPACTADO DE ZANJAS, H < 0.80 m m 550 1.21 665.5 0 0 0.00% 0 0 0.00% 0
01.05.03.01 TUBERIA PVC SAP CLASE 10, 1 1/2" m 120 5.12 614.4 50 256 41.67% 0 0 0.00% 50
01.05.03.02 TUBERIA PVC SAP CLASE 10, 1" m 350 3.98 1,393.00 200 796 57.14% 0 0 0.00% 200
01.05.03.03 TUBERIA PVC SAP CLASE 10, 3/4" m 80 3.07 245.6 40 122.8 50.00% 0 0 0.00% 40
01.05.03.04 PRUEBA HIDRAULICA Y DESINFECCION EN REDES DE TUBERIA DE AGUA m 550 0.4 220 0 0 0.00% 0 0 0.00% 0
01.05.04 SUMINISTRO E INSTALACION DE ACCESORIOS EN RED 1,450.59 1,160.47 80.00% 290.12 20.00%
01.05.04.01 SUMINISTRO E INSTALACION DE ACCESORIOS - RED glb 1 1,450.59 1,450.59 0.8 1,160.47 80.00% 0.2 290.12 20.00% 1
01.06.03.01 CONCRETO SIMPLE fc=175 kg/cm2 m3 3.92 357.21 1,400.26 0 0 0.00% 0 0 0.00% 0
01.06.04.01 TARRAJEO EN EXTERIORES E INTERIORES (MORTERO 1:5) m2 33.6 11.63 390.77 0 0 0.00% 0 0 0.00% 0
01.06.05.01 SUMINISTRO Y COLOCACION DE ACCESORIOS 1" u 10 134.55 1,345.50 5 672.75 50.00% 0 0 0.00% 5
01.06.06.01 TAPA METALICA DE 0.50 X 0.50 M, E=1/8" u 10 102.89 1,028.90 0 0 0.00% 0 0 0.00% 0
01.06.06.02 PINTURA EN MUROS EXTERIORES AL LATEX, IMPR, TEMPLE m2 15.6 4.21 65.68 0 0 0.00% 0 0 0.00% 0
1.07 VALVULA DE PURGA (05 UND.) 3,655.82 594.49 16.26% 165.51 4.53%
01.07.01.01 LIMPIEZA DE TERRENO MANUAL m2 4.2 0.14 0.59 0 0 0.00% 0.84 0.12 19.93% 0.84
01.07.01.02 TRAZO Y REPLANTEO INICIAL m2 4.2 0.29 1.22 0 0 0.00% 0.84 0.24 19.97% 0.84
01.07.02.01 EXCAVACION MANUAL m3 3.36 10.31 34.64 0 0 0.00% 0.67 6.91 19.94% 0.67
01.07.02.02 REFINE, NIVELACION Y COMPACTACION m2 4.2 1.63 6.85 0 0 0.00% 0.84 1.37 19.99% 0.84
01.07.03.01 CONCRETO fc= 175 kg/cm2 m3 1.96 357.21 700.13 0 0 0.00% 0.39 139.31 19.90% 0.39
SALDO
ACUMULADO
VALORIZADO % METRADO VALORIZADO %
546.05 100.00%
424.3 100.00%
6,252.71 100.00%
1,140.76 100.00%
0 0.00%
483.06 100.00%
0 0.00%
167.84 4.44%
3,692.89 50.55%
165 100.00%
902.5 28.05%
1,174.80 47.51%
1,450.59 100.00%
672.75 8.28%
0 0.00%
0 0.00%
0 0.00%
0 0.00%
672.75 50.00%
0 0.00%
760 20.79%
0.36 19.96%
8.28 19.95%
139.31 7.74%
01.07.04.01 TARRAJEO EN EXTERIORES E INTERIORES (MORTERO 1:5) m2 20 11.63 232.6 0 0 0.00% 0 0 0.00% 0
01.07.05.01 SUMINISTRO Y COLOCACION DE ACCESORIOS 1 1/2" u 1 87.8 87.8 0.8 70.24 80.00% 0.2 17.56 20.00% 1
01.07.05.02 SUMINISTRO Y COLOCACION DE ACCESORIOS 1" u 5 109.55 547.75 3 328.65 60.00% 0 0 0.00% 3
01.07.05.03 SUMINISTRO Y COLOCACION DE ACCESORIOS 3/4" u 4 97.8 391.2 2 195.6 50.00% 0 0 0.00% 2
01.07.06.01 TAPA METALICA DE 0.50 X 0.50 M, E=1/8" u 5 102.89 514.45 0 0 0.00% 0 0 0.00% 0
01.07.06.02 PINTURA EN MUROS EXTERIORES AL LATEX, IMPR, TEMPLE m2 9 4.21 37.89 0 0 0.00% 0 0 0.00% 0
01.08.01.01 TRAZO Y REPLANTEO INICIAL m2 198 0.79 156.42 198 156.42 100.00% 0 0 0.00% 198
01.08.02.01 EXCAVACION DE ZANJAS PARA CIMIENTOS m3 5.94 10.31 61.24 5.94 61.24 100.00% 0 0 0.00% 5.94
01.08.02.02 EXCAVACION MANUAL DE ZANJA h=0.60m m3 1,320.00 9.2 12,144.00 1,320.00 12,144.00 100.00% 0 0 0.00% 1,320.00
01.08.02.03 REFINE, NIVELACION Y FONDOS PARA TUBERIA AGUA m 4,400.00 1.37 6,028.00 4,400.00 6,028.00 100.00% 0 0 0.00% 4,400.00
01.08.02.04 CAMA DE APOYO (MATERIAL PROPIO SARANDEADO) m 4,400.00 0.56 2,464.00 4,400.00 2,464.00 100.00% 0 0 0.00% 4,400.00
01.08.02.05 RELLENO COMPACTADO DE ZANJAS, H < 0.70 M m 4,400.00 1.21 5,324.00 4,400.00 5,324.00 100.00% 0 0 0.00% 4,400.00
01.08.03.01 CONCRETO SIMPLE fc=175 kg/cm2 m3 41.58 357.21 14,852.79 41.58 14,852.08 100.00% 0 0 0.00% 41.58
01.08.04.01 CONCRETO fc= 175 kg/cm2 m3 47.84 357.59 17,107.11 47.84 17,107.23 100.00% 0 0 0.00% 47.84
01.08.04.02 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 2,944.85 3.55 10,454.22 2,944.85 10,454.22 100.00% 0 0 0.00% 2,944.85
01.08.04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1,397.62 21.95 30,677.76 1,397.62 30,677.67 100.00% 0 0 0.00% 1,397.62
01.08.05.01 TARRAJEO EN EXTERIORES E INTERIORES (MORTERO 1:5) m2 1,677.98 15.04 25,236.82 1,677.98 25,236.88 100.00% 0 0 0.00% 1,677.98
01.08.06.01 TUBERIA PVC SAP CLASE 10, 1/2" m 5,975.00 2.78 16,610.50 5,975.00 16,610.50 100.00% 0 0 0.00% 5,975.00
01.08.07.01 SUMINISTRO Y COLOCACION DE ACCESORIOS 1/2" u 220 111.74 24,582.80 220 24,582.80 100.00% 0 0 0.00% 220
01.08.07.02 SUMINISTRO Y COLOCACION DE ACCESORIOS PVC SAL 2" u 220 36.09 7,939.80 220 7,939.80 100.00% 0 0 0.00% 220
01.08.07.03 CAJA PARA VALVULA Y TAPA METALICA u 220 55.51 12,212.20 220 12,212.20 100.00% 0 0 0.00% 220
01.08.08.01 PINTURA EN MUROS EXTERIORES AL LATEX, IMPR, TEMPLE m2 123.2 3.29 405.33 0 0 0.00% 0 0 0.00% 0
01.09.01 FLETE TERRESTRE JULIACA - MOHO glb 1 24,410.91 24,410.91 1 24,410.91 100.00% 0 0 0.00% 1
01.09.02 FLETE DE TRANSPORTE LOCAL glb 1 4,424.69 4,424.69 1 4,424.69 100.00% 0 0 0.00% 1
2.01 UBS - BANOS ECOLOGICOS DOMICILIARIOS (220 UND) 555,169.57 528,545.52 80.76% 8,291.76 1.49%
02.01.01.01 LIMPIEZA DE TERRENO MANUAL 1,289.75 0.29 374.03 1,289.75 374.03 100.00% 0 0 0.00% 1,289.75
02.01.01.02 TRAZO Y REPLANTEO INICIAL m2 1,289.75 0.79 1,018.90 1,289.75 1,018.91 100.00% 0 0 0.00% 1,289.75
02.01.02.01 EXCAVACION MANUAL PARA CIMIENTO m3 297.44 10.31 3,066.61 297.44 3,066.65 100.00% 0 0.04 0.00% 297.44
02.01.03.01 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS m3 297.44 195.48 58,143.57 297.44 58,143.57 100.00% 0 0 0.00% 297.44
02.01.03.02 CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS m3 118.8 234.58 27,868.10 118.8 27,868.10 100.00% 0 0 0.00% 118.8
02.01.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 1,122.66 21.95 24,642.39 1,122.66 24,642.39 100.00% 0 0 0.00% 1,122.66
02.01.05.01 MURO DE SOGA LADRILLO KK DE 0.24x0.14x0.0.09 m2 2,984.30 71.6 213,675.88 2,984.30 213,676.02 100.00% 0 0 0.00% 2,984.30
02.01.06.01 TARRAJEO MUROS INTERIORES (MORTERO 1:5) C/ IMPERMEABILIZANTE SIKA I m2 3,192.20 25.23 80,539.21 3,192.20 80,539.21 100.00% 0 0 0.00% 3,192.20
02.01.07.01 PISO DE CEMENTO COLOREADO PULIDO m2 678.15 23.49 15,929.74 431.55 10,137.19 63.64% 246.6 5,792.62 36.36% 678.15
02.01.08.01 VIGA DE MADERA 2" x 3" x 1.75m u 880 26.81 23,592.80 880 23,592.80 100.00% 0 0 0.00% 880
02.01.08.02 CORREAS DE MADERA 2" x 2" x 10' m 1,980.00 7.98 15,800.40 1,980.00 15,800.40 100.00% 0 0 0.00% 1,980.00
02.01.09.01 COBERTURA DE TEJA DE ACERO GALVANIZADA Y PINTADA m2 1,168.20 29.29 34,216.58 1,168.20 34,216.58 100.00% 0 0 0.00% 1,168.20
02.01.10.01 PINTURA EN MUROS EXTERIORES AL LATEX, IMPR, TEMPLE m2 3,487.22 3.29 11,472.95 0 0 0.00% 725.5 2,386.90 20.80% 725.5
02.01.11.02 SUMINISTRO Y COLOCACION DE DUCHA u 220 80.82 17,780.40 199 16,083.18 90.45% 0 0 0.00% 199
02.01.11.03 SUMINISTRO Y COLOCACION DE SUMIDERO DE 2" PARA DUCHA u 220 22.44 4,936.80 215 4,824.60 97.73% 5 112.2 2.27% 220
02.01.12.01 TENDIDO DE TUBERIA PVC SAL DE 2" m 1,100.00 4.78 5,258.00 1,100.00 5,258.00 100.00% 0 0 0.00% 1,100.00
02.01.13.01 SALIDA DE TECHO CON CABLE AWG TW 2.5 mm (14) + D PVC SEL 16 mm (5/8) pto 220 48.5 10,670.00 189 9,166.50 85.91% 0 0 0.00% 189
02.01.14.01 TRAZO Y REPLANTEO PRELIMINAR m2 330 0.15 49.5 10 1.5 3.03% 0 0 0.00% 10
02.01.14.03 RELLENO CON MATERIAL GRANULAR m3 429 8.99 3,856.71 10 89.9 2.33% 0 0 0.00% 10
2.02 MODULO SANITARIO PARA INSTITUCIONES EDUCATIVAS (05 MODULOS) 54,641.72 29,515.34 54.02% 10,977.18 20.09%
SALDO
ACUMULADO
VALORIZADO % METRADO VALORIZADO %
0 0.00%
612.05 59.61%
0 0.00%
185,851.03 77.71%
156.42 100.00%
26,021.24 100.00%
14,852.08 100.00%
58,239.11 100.00%
25,236.88 100.00%
16,610.50 100.00%
44,734.80 100.00%
0 0.00%
28,835.60 100.00%
606,385.40 82.53%
536,837.28 82.25%
1,392.93 100.00%
3,066.69 100.00%
110,654.06 100.00%
213,676.02 100.00%
80,539.21 100.00%
15,929.82 100.00%
39,393.20 100.00%
34,216.58 100.00%
2,386.90 20.80%
21,019.98 92.53%
5,258.00 100.00%
9,166.50 85.91%
137.4 2.22%
40,492.52 74.11%
ITEM DESCRIPCION U.M. PRESUPUESTO BASE METRADO P. UNIT C. PARC. AVANCE FISICO DE OBRA MES DE JUNIO
ANTERIOR ACTUAL ACUMULADO
02.02.01 OBRAS PRELIMINARES
METRADO VALORIZADO % METRADO VALORIZADO % METRADO
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 m2 62.63 0.29 18.16 62.63 18.16 100.00% 0.00 0.00 0.00% 62.63
62.63 0.79 62.63
02.02.01.02 TRAZO Y REPLANTEO INICIAL 49.48 49.48 100.00% 0.00 0 0.00% 62.63
02.02.02.01 EXCAVACION MANUAL PARA CIMIENTO m3 9.79 10.31 100.93 9.79 100.93 100.00% 0.00 0.00 0.00% 9.79
02.02.03.01 CONCRETO fc= 175 kg/cm2 m3 m2 19.57 357.21 6,990.60 19.57 6,990.60 100.00% 0.00 0.00 0.00% 19.57
25.54 21.95 25.54
02.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL 560.6 560.6 100.00% 0.00 0 0.00% 25.54
02.02.04.01 CONCRETO fc= 175 kg/cm2 LOZA FONDO, DINTEL m3 kg 3.12 346.91 1,082.36 0.00 0 0.00% 3.12 1,082.36 100.00% 3.12
43.20 3.55 0.00
02.02.04.02 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 153.36 0 0.00% 43.20 153.36 100.00% 43.2
02.02.05.01 MURO DE SOGA LADRILLO KK DE 0.24x0.14x0.09 m2 151.8 72.42 10,993.36 151.8 1,099.34 100.00% 0.00 0.00 0.00% 151.8
02.02.06.01 TARRAJEO MUROS INTERIORES (MORTERO 1:5) C/ IMPERMEABILIZANTE SIKA I m2 178.2 25.23 4,495.99 178.2 4,495.99 100.00% 0.00 0.00 0.00% 178.2
02.02.07.01 PISO DE CEMENTO COLOREADO PULIDO m2 11.85 166.49 1,972.91 0 0 0.00% 0.00 0.00 0.00% 0
02.02.08.01 TIJERALES DE MADERA 2" x 3" TIPO 02 um 15.00 98.81 1,482.15 15.00 1,482.15 100.00% 0.00 0.00 0.00% 15
40.00 7.98 40.00
02.02.08.02 CORREAS DE MADERA 2" x 2" x 10' 319.2 319.2 100.00% 0.00 0 0.00% 40
02.02.08.03 SUMINISTRO Y COLOCACION DE PUERTA DE MADERA, TABLERO REBAJADO u 15 326.44 4,896.60 6 1,958.64 40.00% 0.00 0 0.00% 6
02.02.08.04 SUMINISTRO Y COLOCACION DE VENTANA DE MADERA, MARCO DE 2" x 2" u 10 60.48 604.8 6 362.88 60.00% 0.00 0 0.00% 6
02.02.09.01 COBERTURA DE TEJA DE ACERO GALVANIZADA Y PINTADA m2 66.72 29.29 1,954.23 66.72 1,954.23 100.00% 0.00 0.00 0.00% 66.72
02.02.10.01 PINTURA EN MUROS EXTERIORES AL LATEX, IMPR, TEMPLE m2 247.5 3.29 814.28 0 0 0.00% 0.00 0.00 0.00% 0
02.02.11.01 SUMINISTRO Y COLOCACION LOZA TURCA uu 15.00 124.64 1,869.60 0.00 0 0.00% 0.00 0.00 0.00% 0
5.00 80.82 0.00
02.02.11.02 SUMINISTRO Y COLOCACION DE DUCHA 404.1 0 0.00% 0.00 0 0.00% 0
02.02.11.03 SUMINISTRO Y COLOCACION DE SUMIDERO DE 2" PARA DUCHA u 20 22.44 448.8 0 0 0.00% 0.00 0 0.00% 0
02.02.12.01 TENDIDO DE TUBERIA PVC SAL DE 4" mm 100.00 3.79 379 0.00 0 0.00% 100.00 379.00 100.00% 100
50.00 4.78 0.00
02.02.12.02 TENDIDO DE TUBERIA PVC SAL DE 2" 239 0 0.00% 50.00 239 100.00% 50
02.02.13.01 SALIDA DE TECHO CON CABLE AWG TW 2.5 mm (14) + D PVC SEL 16 mm (5/8) pto 5 48.5 242.5 0 0 0.00% 0.00 0.00 0.00% 0
02.02.14.01 TRAZO Y REPLANTEO PRELIMINAR m2 m3 35.00 0.15 5.25 21.00 3.15 60.00% 14.00 2.10 40.00% 35
62.70 4.60 37.62
02.02.14.02 EXCAVACION DE ZANJAS 288.42 173.05 60.00% 25.08 115.37 40.00% 62.7
02.02.14.03 CONCRETO fc= 175 kg/cm2 m3 21.72 366.63 7,963.20 0 0 0.00% 13.02 4,773.52 59.94% 13.02
02.02.14.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 221.7 21.95 4,866.32 0 0 0.00% 133.02 2,919.79 60.00% 133.02
02.02.14.05 ACERO EN LOSA MACIZA, FY=4200 KG/CM2 kg 332.36 3.6 1,196.50 0 0 0.00% 332.36 1,196.50 100.00% 332.36
02.02.15.01 TRAZO Y REPLANTEO PRELIMINAR m2 m3 36.00 0.15 5.4 21.60 3.24 60.00% 14.40 2.16 40.00% 36
18.00 4.60 10.80
02.02.15.02 EXCAVACION DE ZANJAS 82.8 49.68 60.00% 7.20 33.12 40.00% 18
02.02.15.03 RELLENO CON MATERIAL GRANULAR m3 18 8.99 161.82 0 0 0.00% 9.00 80.91 50.00% 9
02.03.01 FLETE TERRESTRE JULIACA - MOHO glb glb 1.00 24,410.91 24,410.91 1.00 24,410.91 100.00% 0.00 0.00 0.00% 1
1.00 4,644.69 1.00
02.03.02 FLETE DE TRANSPORTE LOCAL 4,644.69 4,644.69 100.00% 0.00 0 0.00% 1
3.01 COMPONENTE SOCIAL glb 1 34,387.36 34,387.36 0.71 24,412.64 70.99% 0.07 2,309.72 6.72% 0.78
COSTO DIRECTO 13.98% S/. 945,346.52 857,140.73 90.67% 25,699.37 2.72% 882,840.11 93.39%
6.65% 123,461.22 93.39%
GASTOS GENERALES (10.00%) S/. 132,202.46 119,867.28 90.67% 3,593.94 2.72%
GASTOS DE SUPERVISION (5%) S/. 62,889.30 57,021.40 90.67% 1,709.65 2.72%
GASTOS DE EXP. TECNICO (3%) 2.93% S/. 27,734.43 25,146.66 90.67% 753.96 2.72%
COSTO TOTAL S/. 1,168,172.71 ########## 90.67% 31,756.93 2.72%
BRA MES DE JUNIO SALDO
AL ACUMULADO VALORIZADO %
VALORIZADO % METRADO
67.64 100.00%
100.93 100.00%
7,551.20 100.00%
1,235.72 100.00%
10,993.36 100.00%
4,495.99 100.00%
0 0.00%
4,122.87 56.46%
1,954.23 100.00%
0 0.00%
0 0.00%
618 100.00%
0 0.00%
9,183.48 64.13%
169.11 67.64%
29,055.60 100.00%
26,722.36 77.71%