Cronograma PS Shirambari
Cronograma PS Shirambari
100% 100%
01.05 ESTRUCTURA DE TECHO 3,885.09
01.05.01 TIJERAL DE MADERA (INC. CARTELA) 3,885.09 0.00 0.00 3,885.09 0.00 0.00 0.00
100% 80% 20%
01.06 COBERTURAS 5,868.37
01.06.01 COBERTURA DE CALAMINA 11 CANALES (I/CUMBRERA + CORREAS) 5,868.37 0.00 0.00 4,694.70 1,173.67 0.00 0.00
100% 100%
01.07 CIELORRASOS 10,235.74
01.07.01 CIELORASO DE MADERA MACHIHEMBRADA (INC/ENTRAMADO) 9,410.97
01.07.02 FRISO DE MADERA DE 1/2" x 0.25 M. 350.19
01.07.03 RODON DE MADERA E=3/4" 474.58 0.00 0.00 0.00 10,235.74 0.00 0.00
100% 30% 70%
01.08 MUROS Y TABIQUES DE ALBAÑILERIA 7,597.50
01.08.01 MURO DE LADRILLO TUBULAR DE 12X15X24 CM. ASENTADO DE CANTO ( 7,597.50 0.00 2,279.25 5,318.25 0.00 0.00 0.00
100% 100%
01.09 REVOQUES ENLUCIDOS Y MOLDURAS 11,003.41
01.09.01 TARRAJEO PRIMARIO O RAYADO 461.79
01.09.02 TARRAJEO MESADA 95.93
01.09.03 TARRAJEO EN MUROS INTERIORES Y EXTERIORES 6,138.32
01.09.04 TARRAJEO DE COLUMNAS Y VIGAS 1,636.24
01.09.05 TARRAJEO EN VESTIDURA DE DERRAMES 2,671.13 0.00 0.00 0.00 11,003.41 0.00 0.00
100% 50% 50%
01.10 PISOS Y PAVIMENTOS 10,085.13
01.10.01 FALSO PISO 446.63
01.10.02 CONTRAPISO DE CEMENTO BRUÑADO E=1 1/2" 299.05
01.10.03 PISO CERAMICO DE COLOR CLARO DE 30 X 30 CM. 1,034.12
01.10.04 PISO DE CEMENTO SEMIPULIDO Y BRUÑADO E=5" 6,137.23
01.10.05 VEREDA DE CONCRETO F'=140 KG/CM2 BRUÑADO 2,168.10 0.00 0.00 0.00 5,042.57 5,042.57 0.00
100% 100%
01.11 ZOCALOS Y CONTRAZOCALOS 4,346.88
01.11.01 CONTRAZOCALO CERAMICO 0.30 X 0.30 M. 2,893.15
01.11.02 MESADA CON CERAMICO 0.30 X 0.30 M. 601.00
01.11.03 BRUÑA EN MUROS DE 1/2" 75.22
01.11.04 CONTRAZOCALO CEMENTO SEMIPULIDO SIN COLOREAR H = 20 CM (EXT 279.56
01.11.05 CONTRAZOCALO CEMENTO SEMI PULIDO SIN COLOREAR H = 10 CM (IN 497.95 0.00 0.00 0.00 0.00 4,346.88 0.00
100% 100%
01.12 CARPINTERIA DE MADERA 5,376.78
01.12.01 PUERTA DE MADERA CAOBA APANELADA 1.20 X 2.10 M. (INC. MARCO) 900.00
01.12.02 PUERTA CONTRAPLACADA DE 45 mm TRIPLAY (INC. MARCO) 1,673.94
01.12.03 VENTANA DE MADERA CON FIERROS PASANTES D=1/2" 2,802.84 0.00 0.00 0.00 0.00 5,376.78 0.00
CRONOGRAMA DE AVANCE DE OBRA
Proyecto: MEJORAMIENTO DE LA CAPACIDAD OPERATIVA Y RESOLUTIVA DEL PUESTO DE SALUD SHIRAMBARI
META: CONSTRUCCION DE PUESTO DE SALUD, TANQUE ELEVADO, POZO TUBULAR
Lugar: YARINACOCHA PPTO S/. 186,954.01
1 MES 2 MES 3 MES
ITEM DESCRIPCIÓN PARCIAL 15 DÍAS 30 DIAS 45 DÍAS 60 DÍAS 75 DÍAS 90 DÍAS
100% 100%
01.13 CERRAJERIA 1,410.26
01.13.01 CERRADURA DOS GOLPES (INC. JALADOR) 207.99
01.13.02 CERRADURA PARA BAÑO TIPO PERILLA 589.60
01.13.03 BISAGRA ALUMINIZADAS DE 4" 605.88
01.13.04 PICAPORTE DE ALUMINIO 2" 6.79 0.00 0.00 0.00 0.00 1,410.26 0.00
100% 100%
01.14 PINTURA 5,975.22
01.14.01 PINTURA LATEX EN CIELORRASOS 1,621.56
01.14.02 PINTURA LATEX EN MUROS INTERIORES 1,305.46
01.14.03 PINTURA ESMALTE EN MUROS EXTERIORES (INTERIOR DERRAMES) 1,545.24
01.14.04 PINTURA ESMALTE EN COLUMNAS Y VIGAS 694.16
01.14.05 PINTURA BARNIZ MARINO EN CARPINTERIA DE MADERA 308.80
01.14.06 PINTURA ANTICORROSIVA Y ESMALTE EN Fº PASANTE 342.69
01.14.07 PINTURA ESMALTE EN CONTRAZOCALOS 157.31 0.00 0.00 0.00 0.00 0.00 5,975.22
100% 40% 40% 20%
01.15 INSTALACIONES ELECTRICAS 6,299.70
01.15.01 SALIDA DE CENTRO DE LUZ 870.00
01.15.02 SALIDA PARA TOMACORRIENTES BIPOLARES DOBLES CON PUESTA A TI 1,726.18
01.15.03 INTERRUPTORES SIMPLES 201.72
01.15.04 INTERRUPTORES DOBLES 59.43
01.15.05 TABLERO GENERAL (INC. CAJA METALICA) 578.86
01.15.06 POZO A TIERRA 568.71
01.15.07 ARTEFACTO FLUORESCENTE DE 1 X 40 W. 420.75
01.15.08 ARTEFACTO FLUORESCENTE DE 3 X 40 W. 640.71
01.15.09 SPOT LIGHT (INC. FOCO AHORRADOR) 558.88
01.15.10 ACOMETIDA 188.25
01.15.11 ALIMENTACIÓN ELECTRICA AL TANQUE ELEVADO 372.40
01.15.12 PRUEBAS ELECTRICAS 113.81 0.00 0.00 0.00 2,519.88 2,519.88 1,259.94
100% 80% 20%
01.16 SISTEMA DE AGUA DE LLUVIA 1,816.58
01.16.01 CANALETA DE ZINC D=6" 1,136.57
01.16.02 BAJADA DE DRENAJE PLUVIAL Ø 4" 268.60
01.16.03 MURO PROTECTOR D/TUBO, BAJADA DE DRENAJE PLUVIAL 298.88
01.16.04 CUNETAS A TAJO ABIERTO 112.53 0.00 0.00 0.00 0.00 1,453.26 363.32
100% 50% 50%
01.17 INSTALACIONES SANITARIAS 4,976.55
01.17.01 APARATOS SANITARIOS Y ACCESORIOS 2,187.77
01.17.01.01 LAVATORIO DE PARED BLANCO 1 LLAVE (INC. GRIFERIA, ACCESORIOS 595.02
01.17.01.02 INODORO TANQUE BAJO BLANCO (I/COLOCACION) 662.79
CRONOGRAMA DE AVANCE DE OBRA
Proyecto: MEJORAMIENTO DE LA CAPACIDAD OPERATIVA Y RESOLUTIVA DEL PUESTO DE SALUD SHIRAMBARI
META: CONSTRUCCION DE PUESTO DE SALUD, TANQUE ELEVADO, POZO TUBULAR
Lugar: YARINACOCHA PPTO S/. 186,954.01
1 MES 2 MES 3 MES
ITEM DESCRIPCIÓN PARCIAL 15 DÍAS 30 DIAS 45 DÍAS 60 DÍAS 75 DÍAS 90 DÍAS
02.05.06 TARRAJEO CON IMPERMEABILIZANTE EN CUBA 414.72 0.00 0.00 0.00 0.00 593.86 890.79
CRONOGRAMA DE AVANCE DE OBRA
Proyecto: MEJORAMIENTO DE LA CAPACIDAD OPERATIVA Y RESOLUTIVA DEL PUESTO DE SALUD SHIRAMBARI
META: CONSTRUCCION DE PUESTO DE SALUD, TANQUE ELEVADO, POZO TUBULAR
Lugar: YARINACOCHA PPTO S/. 186,954.01
1 MES 2 MES 3 MES
ITEM DESCRIPCIÓN PARCIAL 15 DÍAS 30 DIAS 45 DÍAS 60 DÍAS 75 DÍAS 90 DÍAS
100% 100%
02.06 PISOS Y PAVIMENTOS 427.78
02.06.01 PISO DE CEMENTO PULIDO E=4" 96.21
02.06.02 VEREDA DE CONCRETO E=4" 287.35
02.06.03 ENCOFRADO Y DESENCOFRADO EN VEREDAS 44.22 0.00 0.00 0.00 0.00 0.00 427.78
100% 100%
02.07 ZOCALOS Y CONTRAZOCALOS 49.28
02.07.01 CONTRAZOCALO CEMENTO SEMIPULIDO SIN COLOREAR H = 20 CM 49.28 0.00 0.00 0.00 0.00 0.00 49.28
100% 60% 40%
02.08 CARPINTERIA DE MADERA 61.92
02.08.01 VENTANA DE MADERA CON FIERROS PASANTES D=1/2" 61.92 0.00 0.00 0.00 0.00 37.15 24.77
100% 100%
02.09 CARPINTERIA METALICA 199.17
02.09.01 PUERTA METALICA 199.17 0.00 0.00 0.00 0.00 0.00 199.17
100% 100%
02.10 CERRAJERIA 220.36
02.10.01 BISAGRA ALUMINIZADAS DE 4" 12.37
02.10.02 CERRADURA DOS GOLPES (INC. JALADOR) 207.99 0.00 0.00 0.00 0.00 0.00 220.36
100% 100%
02.11 PINTURA 403.54
02.11.01 PINTURA LATEX EN MUROS INTERIORES 340.94
02.11.02 PINTURA LATEX EN CIELORRASOS 25.19
02.11.03 PINTURA BARNIZ MARINO EN MARCO DE VENTANA 14.85
02.11.04 PINTURA ANTICORROSIVA Y ESMALTE EN Fº PASANTE 12.62
02.11.05 PINTURA ESMALTE EN CONTRAZOCALOS 9.94 0.00 0.00 0.00 0.00 0.00 403.54
100% 40% 60%
02.12 INSTALACIONES SANITARIAS 1,245.04
02.12.01 IMPULSION 458.53
02.12.01.01 TUBERIA DE FIERRO GALVANIZADO 1" 112.50
02.12.01.02 VALVULA COMPUERTA DE BRONCE DE 1" 39.43
02.12.01.03 ABRAZADERAS DE SUJECION (INC. INSTALACION) 306.60
02.12.02 DISTRIBUCION 286.65
02.12.02.01 TUBERIA DE FIERRO GALVANIZADO 1" 180.00
02.12.02.02 TUBERIA DE FIERRO GALVANIZADO 3/4" 59.05
02.12.02.03 REDUCCION DE FIERRO GALVANIZADO 1" A 3/4" 8.17
02.12.02.04 VALVULA COMPUERTA DE BRONCE DE 1" 39.43
02.12.03 DESAGUE Y VENTILACION 499.86
02.12.03.01 TUBO DE FIERRO GALVANIZADO 2" 401.92
02.12.03.02 VALVULA COMPUERTA DE BRONCE DE 2" 87.92
02.12.03.03 SOMBRERO VENTILACION PVC DE 2" 10.02 0.00 0.00 0.00 0.00 498.02 747.02
CRONOGRAMA DE AVANCE DE OBRA
Proyecto: MEJORAMIENTO DE LA CAPACIDAD OPERATIVA Y RESOLUTIVA DEL PUESTO DE SALUD SHIRAMBARI
META: CONSTRUCCION DE PUESTO DE SALUD, TANQUE ELEVADO, POZO TUBULAR
Lugar: YARINACOCHA PPTO S/. 186,954.01
1 MES 2 MES 3 MES
ITEM DESCRIPCIÓN PARCIAL 15 DÍAS 30 DIAS 45 DÍAS 60 DÍAS 75 DÍAS 90 DÍAS
100% 100%
02.13 INSTALACIONES ELECTRICAS 364.66
02.13.01 CENTRO DE LUZ (I/CABLEADO Y LAMPARA AHORRADORA 25 W.) 60.93
02.13.02 INTERRUPTORES SIMPLES 16.02
02.13.03 TABLERO DE DISTRIBUCION TD-01 287.71 0.00 0.00 0.00 0.00 0.00 364.66
100% 100%
02.14 VARIOS 434.21
02.14.01 ESCALERA DE FIERRO TIPO GATO (EXT. TANQUE) 284.21
02.14.02 LOGOTIPO 150.00 0.00 0.00 0.00 0.00 0.00 434.21
100% 100%
03 POZO TUBULAR 6,301.93
03.01 TRABAJOS PRELIMINARES 161.48
03.01.01 MONTAJE Y DESMONTAJE DE CASTILLO DE PERFORACION 161.48 0.00 0.00 0.00 0.00 161.48 0.00
100% 100%
03.02 MOVIMIENTO DE TIERRAS 1,411.26
03.02.01 EXCAVACION DE ZANJA MANUAL 62.50
03.02.02 PERFORACION POZO CON EQUIPO DE ROTACION BROCA 7" 1,239.00
03.02.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO MEJORADO 43.22
03.02.04 RELLENO CON MATERIAL PROPIO 51.84
03.02.05 ELIMINACION DE MATERIAL EXCEDENTE 14.70 0.00 0.00 0.00 0.00 1,411.26 0.00
100% 100%
03.03 ENTUBADO DEL PERFORADO 1,457.70
03.03.01 TUBO PVC SAP 1" 186.50
03.03.02 ENTUBADO CON TUBO PVC SAP CLASE 10 - 4" 1,011.50
03.03.03 ENTUBADO CON TUBO PVC CLASE 10 - 4" RANURADO 259.70 0.00 0.00 0.00 0.00 1,457.70 0.00
100% 50% 50%
03.04 EQUIPOS ESPECIALES 2,626.27
03.04.01 ELECTROBOMBA SUMERGIBLE 1.0 HP (INC. INSTALACION, AUTOMATICO 2,626.27 0.00 0.00 0.00 0.00 1,313.14 1,313.14
100% 100%
03.05 LIMPIEZA POR BOMBEO 282.10
03.05.01 LIMPIEZA CON ELECTROBOMBA SUMERGIBLE 282.10 0.00 0.00 0.00 0.00 0.00 282.10
100% 100%
03.06 VARIOS 363.12
03.06.01 TAPA PREFABRICADA DE PROTECCION 59.65
03.06.02 CAJA DE CONCRETO F'C= 140 KG/CM2 53.47
03.06.03 PRUEBA DE RENDEMIENTO DE POZO TUBULAR 250.00 0.00 0.00 0.00 0.00 0.00 363.12
CRONOGRAMA DE AVANCE DE OBRA
Proyecto: MEJORAMIENTO DE LA CAPACIDAD OPERATIVA Y RESOLUTIVA DEL PUESTO DE SALUD SHIRAMBARI
META: CONSTRUCCION DE PUESTO DE SALUD, TANQUE ELEVADO, POZO TUBULAR
Lugar: YARINACOCHA PPTO S/. 186,954.01
1 MES 2 MES 3 MES
ITEM DESCRIPCIÓN PARCIAL 15 DÍAS 30 DIAS 45 DÍAS 60 DÍAS 75 DÍAS 90 DÍAS