Documentos de Académico
Documentos de Profesional
Documentos de Cultura
01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE OBRA DE 8.50 X 3.60 M und
01.02 CASETA PARA ALMACEN y GUARDIANIA m2
01.03 MANTENIENTO DE TRANSITO y SEGURIDAD VIAL glb
01.04 MOVILIZACION, DESMOVILIZACION DE EQUIPOS y MAQUINARIAS vje
02 PAVIMENTOS
02.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA DEL TERRENO MANUAL m2
02.01.02 TRAZO y REPLANTEO DURANTE LA EJECUION DE LA OBRA m2
02.01.03 DEMOLICION DE PAVIMENTO DE CONCRETO e=0.12m. m2
02.02 MOVIMIENTO DE TIERRAS
02.02.01 CORTE A NIVEL DE SUBRASANTE C/EQUIPO m3
02.02.02 CONFORMACION, PERFILADO y COMPACTADO C/EQUIPO m2
02.02.04 ELIMINACION DE MATERIAL EXCEDENTE D=15 Km. m3
02.03 BASE GRANULAR
02.03.01 BASE GRANULAR E=0.15 m. PARA PAVIMENTO DE CONCRETO m2
02.03.02 BASE GRANULAR E=0.15 m. PARA PAVIMENTO CON PIEDRA EMBOQUILLADA m2
02.04 PAVIMENTOS RIGIDO
02.04.01 CONCRETO f'c=175 kg/cm2 PARA PAVIMENTO E=0.15 m Inc. CURADO m3
02.04.02 ACERO DE REFUERZO Kg
02.04.03 ENCOFRADO y DESENCOFRADO EN PAVIMENTOS m2
02.04.04 JUNTAS ASFALTICAS m
02.05 PAVIMENTO CON PIEDRA DE e=0.20M.
02.05.01 CONCRETO f'c=175 kg/cm2 PARA PAVIMENTO CON PIEDRA E=20 cm Inc. Piedra m2
03 VEREDAS DE PIEDRA EMBOQUILLADA
03.01 TRABAJOS PRELIMINARES
03.01.01 LIMPIEZA DEL TERRENO MANUAL m2
03.01.02 TRAZO y REPLANTEO DURANTE LA EJECUCION DE LA OBRA m2
03.01.03 DEMOLICION DE VEREDAS EXISTENTE DE e=0.10m. m2
03.01.04 ELIMINACION DE MATERIAL EXCEDENTE D=15 Km. m3
03.02 MOVIMIENTO DE TIERRAS
03.02.01 CORTE DE MATERIAL (VEREDAS) m2
03.02.02 CONFORMACION DE BASE GRANULAR DE E=0.10 m m2
03.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3
03.03 CONCRETO SIMPLE
03.03.01 CONCRETO VEREDAS f´c= 175kg/cm2, E= 10 CM. Inc. Curado m3
03.03.02 ENCOFRADO y DESENCOFRADO EN VEREDAS m2
CALENDARIO DE AVANCE DE OBRA VALORIZADO
AVANCE ACUMULADO
DE AVANCE DE OBRA VALORIZADO
OCTUBRE, 2018
PERIODO
OCTUBRE NOVIEMBRE DICIEMBRE TOTAL
22 DIAS 30 DIAS 8 DIAS
OCTUBRE, 2018
PERIODO
OCTUBRE NOVIEMBRE DICIEMBRE TOTAL
22 DIAS 30 DIAS 8 DIAS
0.00 431.99 0.00 431.99
0.00
0.00
697.53 0.00 0.00 697.53
421.60 361.15 0.00 782.75
5,587.26 0.00 0.00 5,587.26
2,960.13 0.00 0.00 2,960.13
0.00
1,725.24 0.00 0.00 1,725.24
6,128.14 0.00 0.00 6,128.14
1,791.33 0.00 0.00 1,791.33
0.00
0.00 10,525.55 3,880.75 14,406.30
0.00
0.00
0.00 2,000.00 1,822.28 3,822.28
0.00 2,000.00 1,869.14 3,869.14
0.00
1,581.51 0.00 0.00 1,581.51
0.00
3,948.88 3,751.44 0.00 7,700.32
2,250.99 2,346.78 0.00 4,597.77
734.40 734.40 0.00 1,468.80
0.00
721.08 398.78 0.00 1,119.86
0.00
16,233.50 0.00 0.00 16,233.50
2,500.00 0.00 0.00 2,500.00
4,000.00 2,500.00 1,500.00 8,000.00
4,000.00 2,500.00 1,500.00 8,000.00
171,600.75 107,209.28 10,572.17 289,382.52
22,927.06 14,323.91 1,412.52 38,663.53
17,160.08 10,720.93 1,057.22 28,938.25
211,687.89 132,254.12 13,041.90 356,984.30
38,103.82 23,805.74 2,347.54 64,257.17
249,791.71 156,059.86 15,389.45 421,241.47
59.30% 37.05% 3.65% 100.00%
DE AVANCE DE OBRA VALORIZADO
OCTUBRE, 2018
PERIODO
OCTUBRE NOVIEMBRE DICIEMBRE TOTAL
22 DIAS 30 DIAS 8 DIAS
59.30% 96.35% 100.00% 100.00%
CRONOGRAMA DE DESEMBOLSO
MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR y PEATONAL DE LA LOCALIDAD DE CHUPAMARCA CENTRO POBLADO DE CHUPAMARCA - DISTRITO DE VALOR REFERENCIAL 421,241.27 con IGV
OBRA: CHUPAMARCA - PROVINCIA DE CASTROVIRREYNA - REGION HUANCAVELICA.
VALOR REFERENCIAL 356,984.13 sin IGV
PROPIETARIO MUNICIPALIDAD DISTRITAL DE CHUPAMARCA FECHA: Enero, 2018
LUGAR CHUPAMARCA - CASTROVIRREYNA - HUANCAVELICA
MONTO EN NUEVOS SOLES
DIAS ADELANTOS TOTAL DESEMBOLSOS
CALENDARIOS VALORIZACION PARCIAL (4)
(SIN IGV) PRESUPUESTO PRESUPUESTO
DIRECTO (10%) (1) MATERIALES (20%) (2) TOTAL ADELANTOS (3) I.G.V. (18%)
PARCIAL (4)-(3) TOTAL
SIN IGV CON IGV SIN IGV CON IGV SIN IGV CON IGV
35,698.41 42,124.13 71,396.83 84,248.26 107,095.24 126,372.39 356,984.14 249,888.90 44,980.00 294,868.91
AMORTIZACIONES
MES 01 (30 DIAS) 20,646.26 24,362.60 41,292.53 48,725.19 61,938.79 73,087.78 206,462.65 61,938.79 11,148.98 73,087.77
MES 02 (30 DIAS) 15,052.15 17,761.54 30,104.30 35,523.07 45,156.45 53,284.61 150,521.49 45,156.45 8,128.16 53,284.61
SUB TOTALES 35,698.41 42,124.13 71,396.83 84,248.26 107,095.24 126,372.39 356,984.14 107,095.24 64,257.14 126,372.38