CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

PROYECTO : ALCANTARILLADO SAN FRANCISCO ZONA I


REGION : MOQUEGUA
PROVINCIA : MARISCAL NIETO
FECHA : NOVIEMBRE 2008

MES 1 MES 2 MES 3 MES 4 MES 5


ITEM DESCRIPCION PARTIDA UND METRADO PRECIO PARCIAL TOTAL % TOTAL % TOTAL % TOTAL % TOTAL %
S/. AVANCE S/. AVANCE S/. AVANCE S/. AVANCE S/. AVANCE

01 OBRAS PROVISIONALES

01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m u 1.00 758.32 758.32 758.32 100%

01.02 ALMACEN, OFICINA Y CASETA DE GUARDIANIA m2 45.00 45.68 2,055.60 2055.6 100%

01.03 CERCO DE ESTERAS m 50.00 17.90 895.00 895 100%

01.04 CINTA PLASTICA SEÑALIZADORA PARA LIMITE DE SEGURIDAD m 1,000.00 1.60 1,600.00 1600 100%

01.05 CERCO DE MALLA ANARANJADA DE 1 m ALTURA PARA LIMITE DE SEGURIDAD DE OBRA m 1,000.00 7.78 7,780.00 7780 100%

01.06 CONO FIBRA DE VIDRIO FOSFORESCENTE P/DESVIO DE TRANSITO S/D u 10.00 58.82 588.20 588.2 100%

01.07 PUENTE DE MADERA PARA PASE PEATONAL SOBRE ZANJA S/D u 20.00 126.05 2,521.00 2521 100%

02 OBRAS PRELIMINARES

02.01 TRAZO Y REPLANTEO C/EQUIPO m 12,481.82 0.74 9,236.55 9236.55 100%

02.02 TRAZO Y REPLANTEO C/EQUIPO DURANTE LA EJECUCION DE LA OBRA m 12,481.82 0.74 9,236.55 9236.55 100%

02.03 DEMOLICION Y CORTE DE PAVIMENTO FLEXIBLE m2 5,009.59 4.64 23,244.50 9297.8 40% 6973.35 30% 6973.35 30%

02.04 PRUEBA COMPACTACION SUELOS (PROCTOR MODIFICADO DENSIDAD DE CAMPO) u 200.00 126.05 25,210.00 12605 50% 12605.00 50%

02.05 TRANSPORTE DE EQUIPOS Y HERRAMIENTAS glb 1.00 840.34 840.34 840.34 100%

03 REDES DE ALCANTARILLADO

03.01 MOVIMIENTO DE TIERRAS

03.01.01 EXCAV. A MANO T. N. HASTA 1.00 P/TUB. D = 4 - 6" m 1,398.73 13.45 18,812.92 5643.876 30% 5643.88 30% 7525.17 40%

03.01.02 EXCAV. A MANO T. N. HASTA 1.50 P/TUB. D = 4 - 6" m 337.18 23.55 7,940.59 2382.177 30% 2382.18 30% 3176.24 40%

03.01.03 EXCAV. C/I A MAQ. T.N. HASTA 1.5 P/TUB. D = 4"-6" m 637.37 3.99 2,543.11 2543.11 100%

03.01.04 EXCAV. C/I A MAQ. T.N. HASTA 2.0 P/TUB. D = 4"-6" m 388.98 5.29 2,057.70 2057.7 100%
03.01.05 EXCAV. C/I A MAQ. T.N. HASTA 1.5 P/TUB. D = 8"-10" m 1,538.21 8.48 13,044.02 7826.412 60% 5217.61 40%

03.01.06 EXCAV. C/I A MAQ. T.N. HASTA 2.0 P/TUB. D = 8"-10" m 5,991.16 6.01 36,006.87 32406.183 90% 3600.69 10%

03.01.07 EXCAV. C/I A MAQ. T.N. HASTA 2.5 P/TUB. D = 8"-10" m 2,190.19 8.22 18,003.36 18003.36 100%

03.01.08 REFINE Y NIV. DE ZANJAS T. NORMAL P/TUB. D = 4"-6" m 2,762.26 1.35 3,729.05 2610.335 70% 1118.72 30%

03.01.09 REFINE Y NIV. DE ZANJAS T. NORMAL P/TUB. D = 8"-10" m 9,719.56 2.54 24,687.68 9875.072 40% 9875.07 40% 4937.54 20%

03.01.10 RELLENO COMPAC. ZANJA T.N. P/TUB. HASTA 1.5 D = 4"-6" INC. C/ARENA m 2,373.28 27.06 64,220.96 64220.96 100%

03.01.11 RELLENO COMPAC. ZANJA T.N. P/TUB. HASTA 2.0 D = 4"-6" INC. C/ARENA m 388.98 40.59 15,788.70 15788.70 100%

03.01.12 RELLENO COMPAC. ZANJA T.N. P/TUB. HASTA 1.5 D = 8"-10" INC. C/ARENA m 1,538.21 28.27 43,485.20 43485.20 100%

03.01.13 RELLENO COMPAC. ZANJA T.N. P/TUB. HASTA 2.0 D = 8"-10" INC. C/ARENA m 5,991.16 43.36 259,776.70 129888.35 50% 129888.35 50%

03.01.14 RELLENO COMPAC. ZANJA T.N. P/TUB. HASTA 2.5 D = 8"-10" INC. C/ARENA m 2,190.19 67.29 147,377.89 147377.89 100%

03.01.15 ELIMINACION MATERIAL EXCEDENTE (ACARREO) m3 9,347.98 9.60 89,740.61 89740.61 100%

03.01.16 ELIMINACION DE MATERIAL EXCEDENTE (CARGUIO) m3 9,347.98 1.71 15,985.05 15985.05 100%

03.01.17 ELIMINACION (TRANSPORTE) VOLQUETE DE 10 m3 D=2 km m3 9,347.98 4.35 40,663.71 40663.71 100%

03.02 SUMINISTRO E INSTALACION DE TUBERIA

03.02.01 SUMINISTRO E INSTALACION DE TUBERIA PROVISIONAL EN SISTEMA DE ALCANTARILL m 1,500.00 118.27 177,405.00 177405 100%

03.02.02 SUMINISTRO E INSTALACION DE TUBERIA PVC-ISO 160 MM S-25 U.F. m 2,373.28 19.44 46,136.56 46136.56 100%

03.02.03 SUMINISTRO E INSTALACION DE TUBERIA PVC-ISO 160 MM S-20 U.F. m 388.98 23.71 9,222.72 9222.72 100%

03.02.04 SUMINISTRO E INSTALACION DE TUBERIA PVC-ISO 200 MM S-25 U.F. m 1,538.21 29.24 44,977.26 44977.26 100%

03.02.05 SUMINISTRO E INSTALACION DE TUBERIA PVC-ISO 200 MM S-20 U.F. m 5,991.16 35.90 215,082.64 215082.64 100%

03.02.06 SUMINISTRO E INSTALACION DE TUBERIA PVC-ISO 250 MM S-25 U.F. m 2,190.19 44.97 98,492.84 98492.84 100%

03.02.07 SUMINISTRO E INSTALACION DE TUBERIA PVC-ISO 250 MM S-20 U.F. m 334.33 55.69 18,618.84 18618.84 100%

03.02.08 PRUEBA HIDRAULICA EN TUBERIA PVC DE ALCANTARILLADO m 12,481.82 1.55 19,346.82 19346.82 100%

03.03 BUZONES

03.03.01 DEMOLICION DE BUZONES C/EQUIPO m3 290.11 170.06 49,336.11 9867.222 20% 34535.28 70% 4933.61 10%
03.03.02 BUZONETAS DE CONCRETO HASTA 1.00 m u 79.00 957.49 75,641.71 75641.71 100%

03.03.03 BUZON TIPO I T.N. HASTA 1.50 m u 110.00 2,415.82 265,740.20 66435.05 25% 66435.05 25% 66435.05 25%

03.03.04 BUZON TIPO I T.N. HASTA 2.00 m u 123.00 2,775.60 341,398.80 85349.70 25% 85349.70 25% 85349.70 25%

03.03.05 BUZON TIPO II T. N. HASTA 5.00 m u 37.00 6,564.67 242,892.79 121446.40 50% 121446.40 50%

03.03.06 PERFORACIÓN DE FUSTE BUZON EXISTENTE PARA EMPALME Y DADO DE ANCLAJE u 8.00 137.97 1,103.76 1103.76 100%

03.03.07 DISPOSITIVO DE CAIDA DENTRO DE BUZON Ø 160.00 MM u 2.00 1,120.33 2,240.66

03.03.08 DISPOSITIVO DE CAIDA DENTRO DE BUZON Ø 200.00 MM u 6.00 1,895.87 11,375.22

03.03.09 DISPOSITIVO DE CAIDA DENTRO DE BUZON Ø 250.00 MM u 1.00 3,788.63 3,788.63

03.04 CONEXIONES DOMICILIARIAS

03.04.01 CONEXION DOMICILIARIA CON SILLA TEE PVC D=160MM X 160MM u 369.00 404.52 149,267.88 37316.97 25% 111950.91 75%

03.04.02 CONEXION DOMICILIARIA CON SILLA TEE PVC D=200MM X 160MM u 931.00 419.77 390,805.87 195402.94 50% 195402.94 50%

03.04.03 CONEXION DOMICILIARIA CON SILLA TEE PVC D=250MM X 160MM u 340.00 420.84 143,085.60 14308.56 10% 128777.04 90%

04 PAVIMENTO ASFALTICO

04.01 BASE GRANULAR E=0.20 M m2 5,009.59 14.33 71,787.42 71787.42 100%

04.02 IMPRIMADO PARA CARPETA ASFALTICA m2 5,009.59 9.09 45,537.17 45537.17 100%

04.03 REPOSICION DE CARPETA ASFALTICA E=2" m2 5,009.59 29.96 150,087.32 150087.32 100%

05 VARIOS

05.01 LIMPIEZA FINAL DE OBRA m 12,481.82 1.18 14,728.55 7364.28 50%

COSTO DIRECTO 3,475,930.55 328,034.81 217,320.71 1,356,062.25 ### 507,166.58


MES 6
TOTAL
TOTAL %
S/. AVANCE S/. % Materiales

###

###

758.32 100% ###

2,055.60 100% ###

895.00 100% ###

###

1,600.00 100%

###

7,780.00 100%

###

588.20 100% ###

2,521.00 100% ###

###

###

9,236.55 100% ###

###

9,236.55 100% ###

###

23,244.50 100% ###

###

25,210.00 100% ###

###

840.34 100%

###

###

###

18,812.92 100%

###

7,940.59 100%

2,543.11 100%

2,057.70 100%
13,044.02 100%

36,006.87 100%

18,003.36 100%

3,729.05 100%

24,687.68 100%

64,220.96 100%

15,788.70 100%

43,485.20 100%

259,776.70 100%

147,377.89 100%

89,740.61 100%

15,985.05 100%

40,663.71 100%

177,405.00 100%

46,136.56 100%

9,222.72 100%

44,977.26 100%

215,082.64 100%

98,492.84 100%

18,618.84 100%

19,346.82 100%

49,336.11 100%
75,641.71 100%

66435.05 25% 265,740.20 100%

85349.70 25% 341,398.80 100%

242,892.79 100%

1,103.76 100%

2240.66 100% 2,240.66 100%

11375.22 100% 11,375.22 100%

3788.63 100% 3,788.63 100%

149,267.88 100%

390,805.87 100%

143,085.60 100%

71,787.42 100%

45,537.17 100%

150,087.32 100%

7364.28 50% 14,728.55 100%

176,553.54 3,475,930.55
CRONOGRAMA DE ADQUISICIONES DE OBRA
PROYECT : ALCANTARILLADO SAN FRANCISCO ZONA I
REGION : MOQUEGUA
PROVINC : MARISCAL NIETO
FECHA : NOVIEMBRE 2008

MANO DE OBRA
MES 1 MES 2 MES 3
Código Insumo Unidad Cantidad Precio Presupuestado
% S/. % S/. % S/.

TOPOGRAFO hh 249.64 12.32 3,075.56 100% 3075.56

CAPATAZ hh 3,114.75 14.78 46,036.01 17% 7672.67 17% 7672.67 17% 7672.67

OPERARIO hh 6,222.19 12.32 76,657.38 17% 12776.23 17% 12776.23 17% 12776.23

OFICIAL hh 6,526.93 11.01 71,861.50 17% 11976.92 17% 11976.92 17% 11976.92

PEON hh 58,607.46 9.95 583,144.23 17% 97190.70 17% 97190.70 17% 97190.70

CONTROLADOR OFICIAL hh 136.48 11.01 1,502.64

PEON ZARANDEADOR/ACOMODADOR hh 41,330.70 9.95 411,240.47 20% 82248.09 40% 164496.19


SUB-TOTAL 1,193,517.79 132692.08 211864.61 294112.70

MATERIALES
MES 1 MES 2 MES 3
Código Insumo Unidad Cantidad Precio Presupuestado
% S/. % S/. % S/.

ALAMBRE NEGRO RECOCIDO # 16 kg 628.03 3.78 2,373.95 100% 2,373.95

ALAMBRE NEGRO RECOCIDO # 8 kg 422.52 3.78 1,597.09 100% 1,597.09

CLAVOS C/CABEZA P/CONSTRUCCION D. PROMEDIO kg 495.37 3.78 1,872.50 100% 1,872.50

CLAVOS PARA CALAMINA kg 0.34 3.78 1.29 100% 1.29

ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 13,099.10 5.04 66,019.46 100% 66,019.46

ARENA FINA m3 2,857.13 39.50 112,856.64 30% 33,856.99

PIEDRA GRANDE DE 8" m3 0.10 33.61 3.36 100% 3.36

PIEDRA CHANCADA DE 1/2" a 3/4" m3 1,052.09 42.02 44,208.82 10% 4,420.88 60% 26,525.29

AFIRMADO PARA BASE m3 1,302.49 42.00 54,704.58 100% 54,704.58

ARENA GRUESA m3 1,643.03 36.13 59,362.67 10% 5,936.27 80% 47,490.14

ASFALTO EN FRIO m3 375.72 352.94 132,606.62 100% 132,606.62

ASFALTO RC-250 gal 2,254.32 5.88 13,255.40 100% 13,255.40

CEMENTO PORTLAND TIPO I (42.5 kg) bls 10,327.76 23.53 243,012.19 80% 194,409.75

CINTA PLASTICA SEÑALIZADORA m 600.00 1.26 756.00 100% 756.00

YESO kg 499.27 0.63 314.54


YESO EN BOLSAS DE 20 kg u 246.00 12.61 3,102.06 10% 310.21

THINNER gal 0.10 18.07 1.81 100% 1.81

PEGAMENTO PARA PVC gal 103.32 42.02 4,341.51 10% 434.15

ANILLO DE JEBE Ø 160 u 3,280.00 8.40 27,552.00 20% 5,510.40


WINCHA DE 30 M u 2.50 42.02 105.05 100% 105.05

GASOLINA 84 OCTANOS gal 717.51 9.00 6,457.59 5% 322.88 90% 5,811.83

HORMIGON (PUESTO EN OBRA) m3 13.96 29.41 410.56 5% 20.53

LIJA PARA MADERA hja 1.05 1.68 1.76 100% 1.76

AGUA m3 3,152.92 5.04 15,890.72 5% 794.54 80% 12,712.57

ESTERA DE 2.00 X 3.00 m u 17.50 25.21 441.18 100% 441.18

PRUEBAS PROCTOR MODIFICADO DE CAMPO u 200.00 126.05 25,210.00 100% 25,210.00

TRANSPORTE DE EQUIPOS Y HERRAMIENTAS glb 1.00 840.34 840.34 100% 840.34

MADERA TORNILLO p2 14,480.12 3.78 54,734.85 10% 5,473.49 90% 49,261.37

PUENTE DE MADERA PARA PASE PEATONAL SOBRE ZANJA SEGUN DISEÑO u 20.00 126.05 2,521.00 100% 2,521.00

PALO DE EUCALIPTO DE 4"X5.0m pza 2.00 16.81 33.62 100% 33.62

TRIPLAY DE 4' X 8' X 4 mm pl 18.75 26.89 504.19 100% 504.19

MALLA C/NARANJA DE 50 X 1M DE ALTURA P/CERCO m 1,050.00 6.30 6,615.00 100% 6,615.00

TAPA FIERRO FUNDIDO PARA BUZON DE 0.60 m pza 349.00 319.33 111,446.17 100% 111,446.17

ABRAZADERA DE ALUMINIO u 18.00 25.00 450.00


KEROSENE INDUSTRIAL gal 250.48 10.08 2,524.84 100% 2,524.84

PETROLEO DIESSEL # 2 gal 5,367.03 9.24 49,591.36 60% 29,754.81 20% 9,918.27

PINTURA ESMALTE SINTETICO gal 50.38 38.66 1,947.69 100% 1,947.69

SELLADOR O IMPRIMANTE BLANCO gal 0.33 57.14 18.86 100% 18.86

PINTURA ESMALTE PARA TRAFICO gal 1.00 57.14 57.14 100% 57.14

CALAMINA # 30 1.83mX0.83mX3mm pl 30.60 14.29 437.27 100% 437.27

TIRAFONES DE 1/2" X 2" pza 36.00 1.00 36.00


LUBRICANTE PARA PVC gal 96.39 42.02 4,050.31 20% 810.06 20% 810.06 40% 1,620.12

TUBERIA PVC UF C-10 Ø 160.00 MM m 5.00 45.61 228.05


TUBERIA PVC UF C-10 Ø 200.00 MM m 15.00 64.39 965.85
TUBERIA PVC UF C-10 Ø 250.00 MM m 2.50 109.76 274.40
TUBERIA PVC UF C-5 Ø 200.00 MM C/A m 1,530.00 34.59 52,922.70 100% 52,922.70

TUBERIA PVC-ISO 160MM S-25 U.F. m 8,632.96 18.61 160,659.39 20% 32,131.88 80% 128,527.51

TUBERIA ALCANTARILLADO UF S-25 160 MM (6" ) INC. ANILLO m 2,420.75 17.74 42,944.11 100% 42,944.11

TUBERIA ALCANTARILLADO UF S-25 200 MM (8" ) INC. ANILLO m 1,568.97 27.07 42,472.02 100% 42,472.02

TUBERIA ALCANTARILLADO UF S-25 250 MM (10" ) INC. ANILLO m 2,233.99 42.27 94,430.76 100% 94,430.76

TUBERIA ALCANTARILLADO UF S-20 160 MM (6" ) INC. ANILLO m 396.76 21.92 8,696.98 100% 8,696.98

TUBERIA ALCANTARILLADO UF S-20 200 MM (8" ) INC. ANILLO m 6,110.98 33.60 205,328.93 100% 205,328.93

TUBERIA ALCANTARILLADO UF S-20 250 MM (10" ) INC. ANILLO m 341.02 52.78 17,999.04 100% 17,999.04

CODO CACHIMBA 45º PVC D=160 MM U.F. u 1,640.00 38.58 63,271.20 10% 6,327.12

SILLA TEE PVC P/CONEXION DE DESAGUE 200 MM X 160 MM pza 931.00 87.81 81,751.11
SILLA TEE PVC P/CONEXION DE DESAGUE 250 MM X 160 MM pza 340.00 88.88 30,219.20 100% 30,219.20

SILLA TEE PVC P/CONEXION DE DESAGUE 160 MM X 160 MM pza 369.00 72.56 26,774.64
TEE PVC ISO Ø 160 mm x 160 mm pza 2.00 399.12 798.24
CODO PVC ISO Ø 160 mm x 90º pza 2.00 278.25 556.50
TAPON PVC ISO Ø 160 mm pza 2.00 203.71 407.42
TEE PVC ISO Ø 200 mm x 200 mm pza 6.00 821.55 4,929.30
CODO PVC ISO Ø 200 mm x 90º pza 6.00 545.49 3,272.94
TAPON PVC ISO Ø 200 mm pza 6.00 242.63 1,455.78
TEE PVC ISO Ø 250 mm x 250 mm pza 1.00 1,250.99 1,250.99
CODO PVC ISO Ø 250 mm x 90º pza 1.00 1,114.68 1,114.68
TAPON PVC ISO Ø 250 mm pza 1.00 1,023.34 1,023.34
TEE PVC ISO Ø 160 mm x 200 mm pza 150.00 821.55 123,232.50 100% 123,232.50

CONO FIBRA DE VIDRIO FOSFORESCENTE P/DESVIO DE TRANSITO C/BASE DE FIERRO u 10.00 58.82 588.20 100% 588.20

SUB-TOTAL 2,019,836.23 256,718.72 91,636.71 1,299,566.28

EQUIPO
MES 1 MES 2 MES 3
Código Insumo Unidad Cantidad Precio Presupuestado
% S/. % S/. % S/.

CIZALLA PARA ACERO CONSTRUCCION HASTA 1" u 454.58 42.02 19,100.63 40% 7,640.25

MEZCLADORA DE CONCRETO DE 11p3 18 HP hm 632.79 16.81 10,637.73 40% 4,255.09

MOLDE METALICO PARA BUZON m2 4,774.90 4.20 20,053.84 40% 8,021.54

ANDAMIO METAL TABLAS ALQUILER est 700.34 1.00 700.41 60% 420.25

CAMION VOLQUETE DE 10 m3 hm 373.92 75.63 28,324.38

CORTADORA DE PAVIMENTO CON DISCO DE CORTE hm 801.53 5.88 4,709.01 5% 235.45 30% 1,412.70 30% 1,412.70

COMPRESORA Y PISTOLA hm 5.71 12.61 72.06 100% 72.06

COMPRESORA NEUMATICA 93 HP 335-375 PCM hm 392.14 58.99 23,131.79 20% 4,626.36 50% 11,565.90 20% 4,626.36

COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP hm 2,733.93 15.13 41,361.34 15% 6,204.20 30% 12,408.40

COMPACTADOR VIBRATORIO TIPO PLANCHA 7 HP hm 200.38 15.13 3,055.85 60% 1,833.51

CARGADOR RETROEXCAVADOR 62 HP 1 yd3 hm 546.62 71.43 39,058.72 80% 31,246.98 20% 7,811.74

CARGADOR SOBRE LLANTAS 125 HP 2.5 yd3 hm 86.00 126.05 10,843.66

MARTILLO NEUMATICO 29 kg CON BARRENO Y ACCESORIOS hm 784.30 5.88 4,611.64 20% 922.33 50% 2,305.82 20% 922.33

VIBRADOR DE CONCRETO 4 HP 2.40" hm 579.62 5.88 3,407.74 50% 1,703.87 30% 1,022.32

CAMION IMPRIMIDOR 6 X 2 178 - 210 HP 1,800 gal hm 100.19 126.05 12,624.17 60% 7,574.50

NIVEL TOPOGRAFICO CON TRIPODE he 249.64 5.88 1,497.82 100% 1,497.82

TEODOLITO hm 249.64 5.88 1,497.82 100% 1,497.82

SUB-TOTAL 224,688.61 40,098.81 31,004.23 50,137.25

HERRAMIENTAS
MES 1 MES 2 MES 3
Código Insumo Unidad Cantidad Precio Presupuestado
% S/. % S/. % S/.

HERRAMIENTAS MANUALES %MO 37,887.91 17% 6,314.65 17% 6,314.65 17% 6,314.65

SUB-TOTAL 37,887.91 6,314.65 6,314.65 6,314.65


COSTO DIRECTO 3,475,930.54 435,824.27 340,820.20 1,650,130.89
MES 4 MES 5 MES 6 TOTAL

% S/. % S/. % S/. % S/.

100% 3,075.56

17% 7672.67 17% 7672.67 17% 7672.67 100% 46,036.00

17% 12776.23 17% 12776.23 17% 12776.23 100% 76,657.38

17% 11976.92 17% 11976.92 17% 11976.92 100% 71,861.50

17% 97190.70 17% 97190.70 17% 97190.70 100% 583,144.23

100% 1502.64 100% 1,502.64

40% 164496.19 100% 411,240.47

294112.70 131119.16 129616.52 100% 1,193,517.79

MES 4 MES 5 MES 6 TOTAL

% S/. % S/. % S/. % S/.

100% 2,373.95

100% 1,597.09

100% 1,872.50

100% 1.29

100% 66,019.46

70% 78,999.64 100% 112,856.64

100% 3.36

20% 8,841.76 10% 4,420.88 100% 44,208.82

100% 54,704.58

10% 5,936.27 100% 59,362.67

100% 132,606.62

100% 13,255.40

20% 48,602.44 100% 243,012.19

100% 756.00

100% 314.54 100% 314.54

90% 2,791.85 100% 3,102.06

100% 1.81

90% 3,907.36 100% 4,341.51

80% 22,041.60 100% 27,552.00


100% 105.05

5% 322.88 100% 6,457.59

95% 390.04 100% 410.56

100% 1.76

15% 2,383.61 100% 15,890.72

100% 441.18

100% 25,210.00

100% 840.34

100% 54,734.85

100% 2,521.00

100% 33.62

100% 504.19

100% 6,615.00

100% 111,446.17

100% 450.00 100% 450.00

100% 2,524.84

5% 2,479.57 15% 7,438.70 100% 49,591.36

100% 1,947.69

100% 18.86

100% 57.14

100% 437.27

100% 36.00 100% 36.00

20% 810.06 100% 4,050.31

100% 228.05 100% 228.05

100% 965.85 100% 965.85

100% 274.40 100% 274.40

100% 52,922.70

100% 160,659.39

100% 42,944.11

100% 42,472.02

100% 94,430.76

100% 8,696.98

100% 205,328.93

100% 17,999.04

90% 56,944.08 100% 63,271.20

100% 81,751.11 100% 81,751.11

100% 30,219.20

100% 26,774.64 100% 26,774.64

100% 798.24 100% 798.24

100% 556.50 100% 556.50


100% 407.42 100% 407.42

100% 4,929.30 100% 4,929.30

100% 3,272.94 100% 3,272.94

100% 1,455.78 100% 1,455.78

100% 1,250.99 100% 1,250.99

100% 1,114.68 100% 1,114.68

100% 1,023.34 100% 1,023.34

100% 123,232.50

100% 588.20

343,291.45 7,438.70 21,184.37 100% 2,019,836.23

MES 4 MES 5 MES 6 TOTAL

% S/. % S/. % S/. % S/.

40% 7,640.25 10% 1,910.06 10% 1,910.06 100% 19,100.63

40% 4,255.09 10% 1,063.77 10% 1,063.77 100% 10,637.73

40% 8,021.54 10% 2,005.38 10% 2,005.38 100% 20,053.84

40% 280.16 100% 700.41

100% 28,324.38 100% 28,324.38

30% 1,412.70 5% 235.45 100% 4,709.01

100% 72.06

10% 2,313.18 100% 23,131.79

30% 12,408.40 15% 6,204.20 10% 4,136.13 100% 41,361.34

40% 1,222.34 100% 3,055.85

100% 39,058.72

20% 2,168.73 80% 8,674.93 100% 10,843.66

10% 461.16 100% 4,611.64

10% 340.77 10% 340.77 100% 3,407.74

40% 5,049.67 100% 12,624.17

100% 1,497.82

100% 1,497.82

45,574.01 48,758.95 9,115.35 100% 224,688.61

MES 4 MES 5 MES 6 TOTAL

% S/. % S/. % S/. % S/.

17% 6,314.65 17% 6,314.65 17% 6,314.65 100% 37,887.91

6,314.65 6,314.65 6,314.65 100% 37,887.91


689,292.81 193,631.47 166,230.90 3,475,930.54