CRONOGRAMA VALORIZADO DE OBRA

Presupuesto CONSTRUCCION DE CANAL PARA EL REACONDICIONAMIENTO DEL LECHO DE RIO EN LA ZONA DE DESCARGA DEL TUNEL DE TRASVASE HACIA LA PRESA PILLONES

Cliente EMPRESA DE GENERACION ELECTRICA DE AREQUIPA S.A.


Contratista CONSORCIO OBRAS HIDRAULICAS DEL SUR
Lugar AREQUIPA - CAYLLOMA - SAN ANTONIO DE CHUCA

Item Descripción Und. Metrado Precio S/. Parcial S/. Sep-2017 oct-2017 nov-2017 dic-2017 ene-2018

01 OBRAS PROVISIONALES
01.01 HABILITACION DE ACCESO PROVISIONAL EXISTENTE KM 1.07 7,648.99 8,184.42 4,637.84 3,546.58
01.02 CAMPAMENTO PROVISIONAL (Almacen, oficinas, comedor, caseta de guardiania y vestidores) und 1.00 90,433.46 90,433.46 51,245.63 39,187.83

01.03 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 M und 1.00 1,336.17 1,336.17 757.16 579.01
01.04 LIMPIEZA Y EXPLANACION DE AREA PARA CAMPAMENTO m2 900.00 3.51 3,159.00 1,790.10 1,368.90
02 TRABAJOS PRELIMINARES
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 35,198.96 35,198.96 19,946.08 15,252.88
02.02 TRAZO Y CONTROL TOPOGRAFICO DURANTE LA EJECUCION DE OBRA mes 4.00 18,176.92 72,707.68 10,300.25 18,782.82 18,176.92 18,782.82 6,664.87
02.03 DESMONTAJE Y RETIRO DE GAVIONES m3 301.50 63.46 19,133.19 10,842.14 8,291.05
02.04 LIMPIEZA Y REHABILITACION DE ZANJA DE CORONACION m 473.57 18.26 8,647.39 4,900.19 3,747.20
02.05 OBRAS DE DESVIOS Y ENCAUSAMIENTO GLB 1.00 3,400.14 3,400.14 1,926.75 1,473.39
02.06 DESMONTAJE Y RETIRO DE COLCHON RENO m3 43.45 63.46 2,757.34 781.25 1,424.63 551.46
02.07 LIMPIEZA, RETIRO Y ACARREO DE ROCAS EN CAUSE DE CANAL m3 126.00 19.89 2,506.14 1,420.15 1,085.99
02.08 DESQUINCHE DE ROCA EXISTENTE und 1.00 997.93 997.93 565.49 432.44
03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE MATERIAL SUELTO m3 4,590.56 5.94 27,267.93 7,725.91 14,088.43 5,453.59
03.02 CORTE EN ROCA SUELTA m3 3,825.47 12.58 48,124.41 13,635.25 24,864.28 9,624.88
03.03 CORTE EN ROCA FIJA m3 2,513.88 22.94 57,668.41 16,339.38 29,795.35 11,533.68
03.04 PERFILADO Y COMPACTADO EN ZONA DE CORTE m2 1,705.09 5.15 8,781.21 995.20 4,976.02 2,809.99
03.05 PROTECCION DE RELLENO LATERAL CON PIEDRA TIPO RIP RAP m2 740.50 33.38 24,717.89 7,003.40 12,770.91 4,943.58
03.06 RELLENO LATERAL DE CANAL CON MATERIAL PROPIO SELECCIONADO m3 918.35 125.54 115,289.66 13,066.16 65,330.81 36,892.69
03.07 RELLENO COMPACTADO PARA BASE DE CANAL m3 1,243.65 116.86 145,332.94 16,471.07 47,475.43 58,133.18 23,253.26
04 OBRAS DE ARTE Y DRENAJE
04.01 DREN FRANCES PARA DERIVAR AGUA DE MANANTIALES m 157.83 122.41 19,319.97 11,591.98 7,727.99
04.02 RELLENO CON GRAVA SELECCIONADA PARA TUBERIA CRIBADA m3 60.00 373.72 22,423.20 13,453.92 8,969.28
04.03 TUBERIA PVC SAP 8" PARA DRENAJE m 120.00 47.80 5,736.00 3,441.60 2,294.40
05 ENROCADO DE PROTECCION
05.01 CONFORMACION DE COLCHON CON PIEDRA EXISTENTE TM=20" , TRAMO FINAL m3 330.03 42.73 14,102.18 8,461.31 5,640.87
06 CONCRETO SIMPLE
06.01 CONCRETO FC=100 KG/CM2 SOLADOS m3 496.97 399.14 198,360.61 11,240.43 68,103.81 87,278.67 31,737.70
07 CONCRETO ARMADO UÑAS DE SUJECION
CRONOGRAMA VALORIZADO DE OBRA

Presupuesto CONSTRUCCION DE CANAL PARA EL REACONDICIONAMIENTO DEL LECHO DE RIO EN LA ZONA DE DESCARGA DEL TUNEL DE TRASVASE HACIA LA PRESA PILLONES

Cliente EMPRESA DE GENERACION ELECTRICA DE AREQUIPA S.A.


Contratista CONSORCIO OBRAS HIDRAULICAS DEL SUR
Lugar AREQUIPA - CAYLLOMA - SAN ANTONIO DE CHUCA

Item Descripción Und. Metrado Precio S/. Parcial S/. Sep-2017 oct-2017 nov-2017 dic-2017 ene-2018
07.01 ACERO DE REFUERZO FY= 4200 KG/CM2 kg 6,850.74 4.79 32,815.04 19,689.02 13,126.02
07.02 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m2 11.04 61.74 681.61 408.97 272.64
07.03 CONCRETO FC=280 KG/CM2 m3 58.39 591.83 34,556.95 20,734.17 13,822.78
08 CONCRETO ARMADO CANAL TECHADO
08.01 BASE Y MUROS
08.01.01 ACERO DE REFUERZO FY= 4200 KG/CM2 kg 11,952.12 4.79 57,250.65 34,350.39 22,900.26
08.01.02 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m2 315.00 61.74 19,448.10 11,668.86 7,779.24
08.01.03 CONCRETO FC=280 KG/CM2 m3 115.50 591.83 68,356.37 41,013.82 27,342.55
08.02 TECHADO DE CANAL TIPO BOVEDA
08.02.01 ACERO DE REFUERZO FY= 4200 KG/CM2 kg 4,892.90 4.79 23,436.99 14,062.19 9,374.80
08.02.02 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m2 209.74 82.33 17,267.89 10,360.73 6,907.16
08.02.03 CONCRETO FC=280 KG/CM2 m3 35.37 591.83 20,933.03 12,559.82 8,373.21
09 CONCRETO ARMADO RAPIDAS
09.01 ACERO DE REFUERZO FY= 4200 KG/CM2 kg 45,572.14 4.79 218,290.55 52,389.73 87,316.22 62,576.62 16,007.98
09.02 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m2 750.63 61.74 46,343.90 11,122.54 18,537.56 13,285.25 3,398.55
09.03 CONCRETO FC=280 KG/CM2 m3 465.92 591.83 275,745.43 66,178.90 110,298.17 79,047.02 20,221.34
10 CONCRETO ARMADO CANAL DE TRANSICION
10.01 ACERO DE REFUERZO FY= 4200 KG/CM2 kg 48,145.48 4.79 230,616.85 27,674.02 101,471.41 84,559.51 16,911.91
10.02 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m2 810.93 61.74 50,066.82 6,008.02 22,029.40 18,357.83 3,671.57
10.03 CONCRETO FC=280 KG/CM2 m3 554.54 591.83 328,193.41 39,383.21 144,405.10 120,337.58 24,067.52
11 CONCRETO ARMADO CANAL DE ENTREGA
11.01 ACERO DE REFUERZO FY= 4200 KG/CM2 kg 16,488.71 4.79 78,980.92 9,477.71 46,335.47 23,167.74
11.02 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m2 204.00 61.74 12,594.96 1,511.40 7,389.04 3,694.52
11.03 CONCRETO FC=210KG/CM2 m3 179.38 522.31 93,691.97 11,243.04 54,965.96 27,482.97
12 TRANSPORTE
12.01 ACARREO DE MATERIAL EXCEDENTE A BOTADEROS M3K 12,514.44 6.03 75,462.07 8,552.37 29,178.67 24,147.86 10,816.23 2,766.94
13 SEGURIDAD Y SALUD OCUPACIONAL
13.01 ELABORACION E IMPLEMENTACION DEL PLAN DE SEGURIDAD GLB 1.00 5,000.00 5,000.00 2,833.33 2,166.67
13.02 EQUIPOS DE PROTECCION INDIVIDUAL GLB 1.00 29,307.41 29,307.41 16,607.53 12,699.88
13.03 EQUIPO DE PROTECCION COLECTIVA GLB 1.00 1,064.07 1,064.07 602.97 461.10
13.04 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 1,253.63 1,253.63 177.60 323.85 313.41 323.85 114.92
13.05 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD GLB 1.00 1,483.72 1,483.72 210.19 383.29 370.93 383.29 136.02
CRONOGRAMA VALORIZADO DE OBRA

Presupuesto CONSTRUCCION DE CANAL PARA EL REACONDICIONAMIENTO DEL LECHO DE RIO EN LA ZONA DE DESCARGA DEL TUNEL DE TRASVASE HACIA LA PRESA PILLONES

Cliente EMPRESA DE GENERACION ELECTRICA DE AREQUIPA S.A.


Contratista CONSORCIO OBRAS HIDRAULICAS DEL SUR
Lugar AREQUIPA - CAYLLOMA - SAN ANTONIO DE CHUCA

Item Descripción Und. Metrado Precio S/. Parcial S/. Sep-2017 oct-2017 nov-2017 dic-2017 ene-2018
13.06 CAPACITACION EN SEGURIDAD Y SALUD GLB 1.00 6,000.00 6,000.00 850.00 1,550.00 1,500.00 1,550.00 550.00
13.07 MITIGACION DEL POLVO EN OBRA GLB 1.00 2,967.81 2,967.81 504.53 920.02 890.34 544.10 108.82
14 PROTECCION AMBIENTAL
14.01 CONFORMACION DE BOTADEROS m3 1,390.64 7.63 10,610.58 3,006.33 5,482.13 2,122.12
14.02 RESTAURACION DE AREAS UTILIZADAS COMO CAMPAMENTO Y PATIO DE MAQUINAS m2 294.00 9.94 2,922.36 1,850.83 1,071.53
14.03 FOLLETOS INFORMACION AMBIENTAL und 200.00 19.52 3,904.00 663.68 1,210.24 1,171.20 715.73 143.15
15 VARIOS
15.01 TRANSPORTE DE MATERIALES DE AQP A OBRA ton 1,016.47 60.00 60,988.20 17,279.99 31,510.57 12,197.64
15.02 JUNTAS CON WATER STOP EN CANALES m 682.58 29.13 19,883.56 4,772.05 10,737.12 4,374.39
15.03 PINTADO DE LINEAS DE CONTROL DE CAUDAL m 5.50 11.01 60.56 38.35 22.21
15.04 PINTADO DE LINEAS DE SEGURIDAD m 104.00 5.33 554.32 351.07 203.25
COSTO DIRECTO 2,766,319.96 246,878.35 844,556.07 926,525.84 593,579.50 154,780.20
GASTOS GENERALES 20.3392% 562,647.35 50,213.08 171,775.95 188,447.94 120,729.32 31,481.05
UTILIDAD 10% 276,632.00 24,687.84 84,455.61 92,652.58 59,357.95 15,478.02

SUB TOTAL 3,605,599.31 321,779.27 1,100,787.63 1,207,626.36 773,666.77 201,739.27


IMPUESTO IGV 18% 649,007.88 57,920.27 198,141.77 217,372.74 139,260.02 36,313.07

TOTAL PRESUPUESTO 4,254,607.19 379,699.54 1,298,929.40 1,424,999.10 912,926.79 238,052.34


%AVANCE PARCIAL 8.92 30.53 33.49 21.46 5.60
%AVANCE ACUMULADO 8.92 39.45 72.95 94.40 100.00