TALLER

0 A 2 1 3 C 6 6 E 9 9 G 12
6 2 8 9 3 12 12 3 15 15 3 18

1
1 B 5 5 D 10 10 F 12
7 4 11 11 5 16 16 2 18

PLAZO TOTAL 18

A.- Genere la curva de avance acumulado de la Obra si el presupuesto es:


Act Millones $
A 450
B 600
C 300
D 600
E 300
F 450
G 300
3000

B.- Genere la curva de Contratación si el proyecto son 12000 m2 y los indices de HD son

Act HD
A 2 Considere 20 días por mes
B 3
C 1
D 4
E 2
F 3
G 1

mes A
1 1
2 3
3 4
4 4
5 4
6 4
7 3
0 1 2 3 4 5 6 7 8 8 1
24
1 3 4 4 4 4 3 1 24

mes C
4 1
5 3
6 5
7 6
8 6
9 6
10 5
3 4 5 6 7 8 9 10 11 12 11 3
12 1
1 3 5 6 6 6 5 3 1 36 36
mes E
7 1
8 3
9 5
10 6
11 6
12 6
13 5
6 7 8 9 10 11 12 13 14 15 14 3
15 1
1 3 5 6 6 6 5 3 1 36 36

mes G
10 1
11 3
12 5
13 6
14 6
15 6
16 5
9 10 11 12 13 14 15 16 17 18 17 3
18 1
1 3 5 6 6 6 5 3 1 36 36

mes B
2 1
3 3
4 5
5 7
6 8
7 8
8 7
1 2 3 4 5 6 7 8 9 10 9 5
10 3
1 3 5 7 8 8 7 5 3 1 48 11 1
48
mes D
6 1
7 3
8 5
9 7
10 9
11 10
12 9
5 6 7 8 9 10 11 12 13 14 15 16 13 7
14 5
1 3 5 7 9 10 9 7 5 3 1 60 15 3
16 1
60

mes F
11 1
12 3
13 4
14 4
15 4
16 4
17 3
10 11 12 13 14 15 16 17 18 18 1
24
1 3 4 4 4 4 3 1 24
0.15 0.2 0.1 0.2 0.1 0.15 0.1 PROYECTO
mes A B C D E F G PAR ACUM
1 4.2% 0.6% 0.6%
2 12.5% 2.1% 2.3% 2.9%
3 16.7% 6.3% 3.8% 6.7%
4 16.7% 10.4% 2.8% 4.9% 11.5%
5 16.7% 14.6% 8.3% 6.3% 17.8%
6 16.7% 16.7% 13.9% 1.7% 7.6% 25.3%
7 12.5% 16.7% 16.7% 5.0% 2.8% 8.2% 33.5%
8 4.2% 14.6% 16.7% 8.3% 8.3% 7.7% 41.2%
9 10.4% 16.7% 11.7% 13.9% 7.5% 48.7%
10 6.3% 13.9% 15.0% 16.7% 2.8% 7.6% 56.3%
11 2.1% 8.3% 16.7% 16.7% 4.2% 8.3% 7.7% 64.0%
12 2.8% 15.0% 16.7% 12.5% 13.9% 8.2% 72.2%
13 11.7% 13.9% 16.7% 16.7% 7.9% 80.1%
14 8.3% 8.3% 16.7% 16.7% 6.7% 86.7%
15 5.0% 2.8% 16.7% 16.7% 5.4% 92.2%
16 1.7% 16.7% 13.9% 4.2% 96.4%
17 12.5% 8.3% 2.7% 99.1%
18 4.2% 2.8% 0.9% 100%

AVANCE PROGRAMADO/AVANCE ACUMULADO

100.0%

90.0%
A.P.A
80.0%

70.0%

60.0%

50.0%

40.0%

30.0%
A.R.A
º A.R.A
20.0%

10.0% A.R.A
0.0%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
mes A B C D E F G
1 50 50
2 150 38 188
3 200 113 313
4 200 188 17 405
5 200 263 50 513
6 200 300 84 40 624
7 150 300 100 120 34 704
8 50 263 100 200 100 713
9 188 100 280 167 735
10 113 84 360 200 17 774
11 38 50 400 200 75 50 813
12 17 360 200 225 84 886
13 280 167 300 100 847
14 200 100 300 100 700
15 120 34 300 100 554
16 40 300 84 424
17 225 50 275
18 75 17 92

contratación

800

700

600

500

400

300

200

100

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18