SERVICIO DE INSPECCION Y CAMBIO DE BUSHING ANTAPACCAY

ID Task TaskName Duratio Start Finish


Mode 6:00a.m 7:00a.m 8:00a.m 9:00a.m 10:00a.m11:00a.m12:00p.m1:00p.m 2:00p.m 3:00p.m 4:00p.m 5:00p.m 6:00p.m 7:00p.m 8:00p.m 9:00p.m 10:00p.m11:00p.m12:00a.m1:00a.m 2:00a.m 3:00a.m 4:00a.m 5:00a.m 6:00a.m
1 SERVICIODEINSPECCIONCOMPONENTESCHP 22hrs Wed24/05/17 Thu25/05/17

2 DESMONTAJEDECUPULAYSPIDER 4hrs Wed24/05/17 Wed24/05/17

3 Bloqueodelequipo 0.5hrs Wed24/05/17 Wed24/05/17 4


4 SoldeodeOrejasparacolocarlineasdeVida 1hr Wed24/05/17 Wed24/05/17

5 ColocaciondePlataformasdeAceso 1hr Wed24/05/17 Wed24/05/17

6 DesmontajedeSiperCap 0.5hrs Wed24/05/17 Wed24/05/17

7 RetirodePernosdelSuperbolt 1hr Wed24/05/17 Wed24/05/17

8 DesmontajedeSpider 1hr Wed24/05/17 Wed24/05/17

9 MetrologiadelSpiderBushing 1hr Wed24/05/17 Wed24/05/17

10 DESMONTAJEDEMAINSHAFT 2hrs Wed24/05/17 Wed24/05/17

11 Colocaciondelaplataformaparainstalaciondemaniobra 0.5hrs Wed24/05/17 Wed24/05/17

12 Colocaciondelosaparejosdeizaje 0.25hrs Wed24/05/17 Wed24/05/17

13 DesmontajedeMainShaft 1hr Wed24/05/17 Wed24/05/17

14 Instalaciondeescalerayplataformadetrabajo 0.25hrs Wed24/05/17 Wed24/05/17

15 InspeccindelMuninferiordelMainshaft 1.5hrs Wed24/05/17 Wed24/05/17

16 CAMBIODEINNERBUSHING 4hrs Wed24/05/17 Wed24/05/17

17 Limpiezadelaceitedelinteriordelinnerbushing 0.5hrs Wed24/05/17 Wed24/05/17

18 Retirodelcenterwearingringybottonpistonwearingring 1hr Wed24/05/17 Wed24/05/17

19 InspeccinymedicindePistonWearingRing,CenterWearing 1hr Wed24/05/17 Wed24/05/17


RingyMainshaftWearingRing.

20 Controldimensionaleinspecciondelinnerbushing_Antiguo 0.5hrs Wed24/05/17 Wed24/05/17

21 CortedeInnerBushing 1hr Wed24/05/17 Wed24/05/17

22 PreparaciondelInnerBushing(ColocaciondeBocinaentinacon 3.5hrs Wed24/05/17 Wed24/05/17


nitrogeno)/Simultaneo

23 ControldimensionaleinspeccionNDTdelinnerbushing_Nuevo 1hr Wed24/05/17 Wed24/05/17

24 MontajedeInnerBushing,einstalacindePistonWearingRing, 1hr Wed24/05/17 Wed24/05/17


CenterWearingRingyMainshaftWearingRing.

25 PERFORACIONDEAGUJEROSPARAINSTALACIONDEDOWELPIN 2hrs Wed24/05/17 Wed24/05/17

26 TrazodeperforaciondeAgujeros 0.5hrs Wed24/05/17 Wed24/05/17

27 PerforaciondeagujerosconTaladromagntico 1.5hrs Wed24/05/17 Wed24/05/17

28 MONTAJEDEMAINSHAFT60X113" 4hrs Wed24/05/17 Thu25/05/17

29 Maniobrasdemontajedemainshaft 2hrs Wed24/05/17 Wed24/05/17

30 Fijaciondeposteyretirodeplataforma 1hr Wed24/05/17 Wed24/05/17

31 Montajedemediaslunasdeltopshell 1hr Wed24/05/17 Thu25/05/17

32 MONTAJEDECUPULAYSPIDER 5hrs Thu25/05/17 Thu25/05/17

33 MontajedelSpider 2hrs Thu25/05/17 Thu25/05/17

34 Instalacionyfijaciondedepernosdelsuperbolt 1hr Thu25/05/17 Thu25/05/17

35 Adiciondegrasaacabezadelposte 1hr Thu25/05/17 Thu25/05/17

36 Retirodeplataformadetrabajo 0.5hrs Thu25/05/17 Thu25/05/17

37 Montajedecupula 0.5hrs Thu25/05/17 Thu25/05/17

38 RETIRODEEQUIPOSYDESBLOQUEO 1hr Thu25/05/17 Thu25/05/17

39 Retirodemateriales,limpiezadelareadetrabajoyretirode 0.5hrs Thu25/05/17 Thu25/05/17


escaleradeingreso

40 Desbloqueodelequipo 0.5hrs Thu25/05/17 Thu25/05/17

41 FINDEACTIVIDADES 0days Thu25/05/17 Thu25/05/17 25/05