"REMODELACION Y AMPLIACION DE REDES PRIMARIAS S.E. YARADA - EL CHASQUI - BOCA DEL RIO, REGION TACNA" J.T.S.

CRONOGRAMA DE EJECUCION DE OBRA


Id EDT Nombre de tarea Costo Duracin Comienzo Fin 2013
jul '13 ago '13 sep '13 oct '13 nov '13
23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10
1 A. "REMODELACION Y AMPLIACION DE REDES PRIMARIAS S.E. YARADA - EL S/. 2,003,916.46 130 das lun 01/07/13 jue 07/11/13
CHASQUI - BOCA DEL RIO, REGION TACNA"
2 B. INICIO S/. 0.00 0 das lun 01/07/13 lun 01/07/13
3 I. SUMINISTRO DE MATERIALES Y EQUIPOS S/. 1,428,025.43 100 das lun 01/07/13 mar 08/10/13
4 01.00 POSTES Y CRUCETAS S/. 324,250.50 75 das lun 01/07/13 vie 13/09/13
5 02.00 CONDUCTORES ELECTRICOS Y ACCESORIOS S/. 481,557.10 75 das lun 01/07/13 vie 13/09/13
6 03.00 EQUIPOS DE TRANSFORMACION, PROTECCION Y MANIOBRA S/. 283,927.00 100 das lun 01/07/13 mar 08/10/13
7 04.00 AISLADORES Y ACCESORIOS S/. 198,090.80 50 das lun 01/07/13 lun 19/08/13
8 05.00 FERRETERIA Y ACCESORIOS S/. 46,903.00 50 das lun 01/07/13 lun 19/08/13
9 06.00 RETENIDAS S/. 29,444.45 50 das lun 01/07/13 lun 19/08/13
10 07.00 PUESTA A TIERRA S/. 63,852.58 50 das lun 01/07/13 lun 19/08/13
11 II. MONTAJE ELECTROMECANICO S/. 430,808.09 130 das lun 01/07/13 jue 07/11/13
12 08.00 OBRAS PRELIMINARES S/. 31,253.52 30 das lun 01/07/13 mar 30/07/13
13 09.00 EXCAVACIONES Y MOVIMIENTO DE TIERRAS S/. 42,013.85 70 das lun 15/07/13 dom 22/09/13
14 10.00 INSTALACION DE POSTES S/. 89,616.22 80 das lun 22/07/13 mi 09/10/13
15 11.00 INSTALACION DE RETENIDAS Y PUESTA A TIERRA S/. 23,554.69 75 das lun 29/07/13 vie 11/10/13
16 12.00 MONTAJE DE ARMADOS S/. 32,110.63 75 das lun 29/07/13 vie 11/10/13
17 13.00 MONTAJE DE CONDUCTORES Y ACCESORIOS S/. 151,339.99 90 das sb 10/08/13 jue 07/11/13
18 1.3.7 INSTALACION DE DUCTOS Y BUZON DE INSPECCION S/. 5,700.04 30 das dom 15/09/13 lun 14/10/13
19 14.00 MONTAJE Y PRUEBAS DE SUBESTACION ELEVADORA Y EQUIPOS DE S/. 30,500.62 30 das vie 04/10/13 sb 02/11/13
PROTECCION Y MANIOBRA
20 15.00 OTROS S/. 24,718.53 20 das sb 19/10/13 jue 07/11/13
21 III. DESMONTAJE ELECTROMECNICO S/. 87,961.92 75 das dom 25/08/13 jue 07/11/13
22 16.00 DESMONTAJE DE MATERIALES Y EQUIPOS S/. 87,961.92 75 das dom 25/08/13 jue 07/11/13
23 IV. TRANSPORTE S/. 57,121.02 130 das lun 01/07/13 jue 07/11/13
24 C. FIN S/. 0.00 0 das jue 07/11/13 jue 07/11/13

Tarea
Tarea crtica
Hito
Resumen
Tarea resumida
Tarea crtica resumida
Hito resumido
Progreso resumido
Divisin
Tareas externas
Resumen del proyecto
Proyecto: ELECTROSUR S.A.
Agrupar por sntTarea
Fecha: 30/04/2013
Tarea inactiva
Hito inactivo
Resumen inactivo
Tarea manual
Slo duracin
Informe de resumen manual
Resumen manual
Slo el comienzo
Slo fin
Progreso
Tarea crtica

Pgina 1

También podría gustarte