Está en la página 1de 9

NUMEROS GENERADORES

OBRA: PLANTA DE BOMBEO PLANO:


CARCAMO DE BOMBEO 1 FFCHA:
UBICACIN: NOGALES, EDO. DE SONORA CALCULO:

CLAVE CONCEPTO LOCALIZARON


EJE TRAMO TIPO LARGO ANCHO ALTO PZAS RESULTADO OBSERVACIONES
1005 01 LIMPIEZA Y TRAZO EN EL AREA DE TRABAJO.
A- B 1-2 18.82 16.35 307.71 M2
TOTAL: 307.71 M2

A110A EXCAVACION CON MAQUINA PARA ZANJAS, EN V = h (A1 + A2)/2 A1 = 129.53 A2 = 68.45 7.07 699.86 M3
MATERIAL "B", EN SECO, CON AFLOJE Y
EXTRACCION DEL MATERIAL, AMACICE Y
LIMPIEZA DE PLANTILLA Y TALUDES,
REMOCIN, CARGA A CAMION O A UN LADO DE
LA ZANJA, INCLUYENDO ACARREO A 10 M. DEL
EJE DE LA MISMA Y CONSERVACIN

TOTAL: 699.86 M3

S/C RELLENO EN ESTRUCTURAS

S/C COMPACTADO AL 90% PROCTOR, CON


MATERIAL PRODUCTO DE EXCAVACION
(vol. Excavado) V = h (A1 + A2)/2 A1 = 129.53 A2 = 68.45 7.07 699.86 M3
(vol. plantilla de crcamo de bombeo) 7.60 5.13 0.05 -1.95 M3
(vol. de estructura) 7.60 5.13 5.76 -224.57 M3
473.34 M3

4030 00 FABRICACION Y COLADO DE CONCRETO


VIBRADO Y CURADO.

4030 01 PLANTILLA DE CONCRETO F'C=100 KG/CM2


VIBRADO Y CURADO, AGREGADO MXIMO DE
3/4" DE 5 CM DE ESPESOR
7.87 5.13 0.05 2.02 M3
TOTAL: 2.02 M3

4030 05 FABRICACION Y COLADO DE CONCRETO


F'C=250 KG/CM2 VIBRADO Y CURADO,
AGREGADO MX. DE 3/4"

a) EN CIMENTACIONES.
A 1-2 7.87 5.13 0.30 12.11 M3
A 1-2 5.00 5.13 0.30 3.85 M3
b) EN TRABES.
N2 5.13 0.25 0.75 0.96 M3
N1 2.50 0.20 0.23 0.12 M3
N1 2.50 0.20 0.23 0.12 M3

Pgina 1 de 9
NUMEROS GENERADORES

OBRA: PLANTA DE BOMBEO PLANO:


CARCAMO DE BOMBEO 1 FFCHA:
UBICACIN: NOGALES, EDO. DE SONORA CALCULO:

CLAVE CONCEPTO LOCALIZARON


EJE TRAMO TIPO LARGO ANCHO ALTO PZAS RESULTADO OBSERVACIONES
N1 2.50 0.20 0.23 0.12 M3
N1 2.50 0.20 0.23 0.12 M3
N1 2.50 0.20 0.23 0.12 M3
Lim. De Agua 5.13 0.15 3.42 2.63 M3
Huecos para llenar carcamo 0.85 0.30 0.15 -0.04 M3
c) EN LOSAS.
4 Complementos de las rejillas 0.90 0.66 0.15 4.00 0.36 M3
Losa completa de 20 cm. 4.34 4.53 0.20 3.93 M3
(registro hombre) 0.85 0.85 0.20 -0.14 M3
d) EN MUROS.
A 1-2 6.52 5.13 0.30 10.03 M3
B 1-2 6.52 5.13 0.30 10.03 M3
1 A- B 6.52 7.60 0.30 14.87 M3
2 A- B 6.52 7.60 0.30 14.87 M3
TOTAL: 74.06 M3

4080 00 CIMBRA DE MADERA PARA ACABADOS NO


APARENTES EN.

4080 01 a) EN CIMENTACIONES.
1 A- B 7.87 0.35 2.00 5.51 M2
A 1-2 5.13 0.45 2.00 4.62 M2
TOTAL: 10.13 M2

4080 03 b) TRABES
Nervadura 2 5.13 0.25 1.28 M2
Nervadura 2 5.13 0.40 2.05 M2
Nervadura 2 5.13 0.60 3.08 M2
Nervadura 1 2.80 0.25 4.00 2.80 M2
Nervadura 1 2.80 0.13 4.00 1.46 M2
Nervadura 1 2.80 0.05 16.00 2.24 M2
TOTAL: 12.91 M2

4080 04 c) LOSAS CON ALTURA DE OBRA FALSA HASTA


3.60 M.
Losa 7.87 5.13 40.37 M2
Losa Costados 7.87 0.20 2.00 3.15 M2
Losa Costados 5.13 0.20 2.00 2.05 M2
Lim. De Agua 5.13 0.15 0.77 M2
Lim. De Agua 5.13 1.48 7.59 M2

Pgina 2 de 9
NUMEROS GENERADORES

OBRA: PLANTA DE BOMBEO PLANO:


CARCAMO DE BOMBEO 1 FFCHA:
UBICACIN: NOGALES, EDO. DE SONORA CALCULO:

CLAVE CONCEPTO LOCALIZARON


EJE TRAMO TIPO LARGO ANCHO ALTO PZAS RESULTADO OBSERVACIONES
Lim. De Agua 5.13 1.32 6.77 M2
TOTAL: 53.93 M2

4080 05 d) EN MUROS HASTA 3.00 M DE ALTURA.


1,2 A- B Ext. 7.87 6.52 2.00 102.62 M2
1,2 A- B Int. 7.27 5.72 2.00 83.17 M2
A,B 1-2 Ext. 6.52 4.54 2.00 59.20 M2
A,B 1-2 Int. 5.92 4.54 2.00 53.75 M2
Lim. De Agua 5.13 0.15 0.77 M2
Lim. De Agua 5.13 1.97 10.11 M2
Lim. De Agua 5.13 1.82 9.34 M2
TOTAL: 318.96 M2

4080 07 BONIFICACION EN CIMBRA PARA ACABADO


APARENTE.

b) TRABES
Nervadura 2 5.13 0.25 1.28 M2
Nervadura 2 5.13 0.55 2.82 M2
Nervadura 2 5.13 0.60 3.08 M2
Nervadura 1 2.80 0.25 4.00 2.80 M2
Nervadura 1 2.80 0.13 4.00 1.46 M2
Nervadura 1 2.80 0.05 16.00 2.24 M2
c) LOSAS CON ALTURA DE OBRA FALSA HASTA
3.60 M.
Losa 7.87 5.13 40.37 M2
Losa Costados 7.87 0.20 2.00 3.15 M2
Losa Costados 5.13 0.20 2.00 2.05 M2
Lim. De Agua 5.13 0.15 0.77 M2
Lim. De Agua 5.13 1.48 7.59 M2
Lim. De Agua 5.13 1.32 6.77 M2
d) EN MUROS HASTA 3.00 M DE ALTURA.
1,2 A- B Ext. 7.87 6.17 2.00 97.12 M2
1,2 A- B Int. 7.27 5.72 2.00 83.17 M2
A,B 1-2 Ext. 6.52 4.54 2.00 59.20 M2
A,B 1-2 Int. 5.92 4.54 2.00 53.75 M2
Lim. De Agua 5.13 0.15 0.77 M2
Lim. De Agua 5.13 1.97 10.11 M2
Lim. De Agua 5.13 1.82 9.34 M2
TOTAL: 387.84 M2

Pgina 3 de 9
NUMEROS GENERADORES

OBRA: PLANTA DE BOMBEO PLANO:


CARCAMO DE BOMBEO 1 FFCHA:
UBICACIN: NOGALES, EDO. DE SONORA CALCULO:

CLAVE CONCEPTO LOCALIZARON


EJE TRAMO TIPO LARGO ANCHO ALTO PZAS RESULTADO OBSERVACIONES

4090 01 SUMINISTRO Y COLOCACION DE ACERO DE


REFUERZO

1). TRABE DE 25x60 cm DE CONCRETO 159.95 KG


REFORZADO f'c=250 kg/cm2, ARMADA CON 6 var.
No. 5 Y ESTRIBOS No.3 A CADA 20 cm.

a). Acero fy=4,200 kg/cm2 3/8"


No. Estr. = 1.00 m / 0.20 m/est = 6.00 estribos
=Long. x No. Estr. x 0.557 kg/m = 6.02 kg/m
r = 62.61 kg

b). Acero fy=4,200 kg/cm2 5/8"


No. Vars. x 1.560 kg/m = 9.36 kg/m
r = 97.34 kg

2). LOSA DE CIMENTACION DE 45 cm PROMEDIO 2,162.04 KG


DE CONCRETO REFORZADO f'c=250 kg/cm2,
ARMADA CON var. No. 5 @ 15 Y var. No. 6 @ 15.

a). Acero fy=4,200 kg/cm2 5/8"


No. vars. = 1.00 m / 0.15 m = 8.00 vars
=Long. x No. vars. x 1.560 kg/m = 12.48 kg/m
r = 885.24 kg

b). Acero fy=4,200 kg/cm2 3/4"


No. vars. = 1.00 m / 0.15 m = 8.00 vars
=Long. x No. vars. x 2.250 kg/m = 18.00 kg/m
r = 1,276.80 kg

3). LOSA SUPERIOR DE 15 cm DE CONCRETO 229.06 KG


REFORZADO f'c=250 kg/cm2, ARMADO CON var.
No. 4 @ 20.

a). Acero fy=4,200 kg/cm2 1/2"


No. vars. = 1.00 m / 0.20 m = 6.00 vars
=Long. x No. vars. x 0.996 kg/m = 5.98 kg/m
r = 119.20 kg

Pgina 4 de 9
NUMEROS GENERADORES

OBRA: PLANTA DE BOMBEO PLANO:


CARCAMO DE BOMBEO 1 FFCHA:
UBICACIN: NOGALES, EDO. DE SONORA CALCULO:

CLAVE CONCEPTO LOCALIZARON


EJE TRAMO TIPO LARGO ANCHO ALTO PZAS RESULTADO OBSERVACIONES
b). Acero fy=4,200 kg/cm2 1/2"
No. vars. = 8.20 m / 0.30 m = 22.00 vars
=Long. x No. vars. x 0.996 kg/m = 31.77 kg/m
r = 63.54 kg

c). Acero fy=4,200 kg/cm2 1/2"


No. vars. = 5.73 m / 0.40 m = 15.00 vars
=Long. x No. vars. x 0.996 kg/m = 23.16 kg/m
r = 46.32 kg

4). LOSA DE 15 cm DE CONCRETO REFORZADO 158.87 KG


f'c=200 kg/cm2, ARMADO CON var. No. 4 @ 15

a). Acero fy=4,200 kg/cm2 1/2"


No. vars. = 1.00 m / 0.15 m = 8.00 vars
=Long. x No. vars. x 0.996 kg/m = 7.97 kg/m
r = 158.87 kg

5). MURO DE 30 cm PROMEDIO DE CONCRETO 6,505.68 KG


REFORZADO f'c=250 kg/cm2, ARMADO CON var.
No. 5 @ 15, No. 6 @ 15 Y 8 @ 15.

a). Acero fy=4,200 kg/cm2 5/8"


No. vars. = 7.11 m / 0.30 m = 25.00 vars
=Long. x No. vars. x 1.560 kg/m = 1072.50 kg/m
r = 1,072.50 kg

b). Acero fy=4,200 kg/cm2 5/8"


No. vars. = 7.11 m / 0.30 m = 25.00 vars
=Long. x No. vars. x 1.560 kg/m = 1008.54 kg/m
r = 1,008.54 kg

c). Acero fy=4,200 kg/cm2 5/8"


No. vars. = 2.70 m / 0.30 m = 10.00 vars
=Long. x No. vars. x 1.560 kg/m = 56.94 kg/m
r = 227.76 kg

d). Acero fy=4,200 kg/cm2 5/8"


No. vars. = 2.70 m / 0.30 m = 10.00 vars
=Long. x No. vars. x 1.560 kg/m = 50.70 kg/m

Pgina 5 de 9
NUMEROS GENERADORES

OBRA: PLANTA DE BOMBEO PLANO:


CARCAMO DE BOMBEO 1 FFCHA:
UBICACIN: NOGALES, EDO. DE SONORA CALCULO:

CLAVE CONCEPTO LOCALIZARON


EJE TRAMO TIPO LARGO ANCHO ALTO PZAS RESULTADO OBSERVACIONES
r = 202.80 kg

e). Acero fy=4,200 kg/cm2 3/4"


No. vars. = 8.20 m / 0.30 m = 28.00 vars
=Long. x No. vars. x 2.250 kg/m = 472.50 kg/m
r = 1,890.00 kg

f). Acero fy=4,200 kg/cm2 5/8"


No. vars. = 5.73 m / 0.30 m = 20.00 vars
=Long. x No. vars. x 1.560 kg/m = 234.00 kg/m
r = 936.00 kg

g). Acero fy=4,200 kg/cm2 3/4"


No. vars. = 8.20 m / 0.30 m = 28.00 vars
=Long. x No. vars. x 2.250 kg/m = 195.30 kg/m
r = 781.20 kg

h). Acero fy=4,200 kg/cm2 5/8"


No. vars. = 5.73 m / 0.30 m = 20.00 vars
=Long. x No. vars. x 1.560 kg/m = 96.72 kg/m
r = 386.88 kg

6). MURO DE 15 cm DE CONCRETO REFORZADO 139.74 KG


f'c=200 kg/cm2, ARMADO CON var. No. 4 @ 15

a). Acero fy=4,200 kg/cm2 1/2"


No. vars. = 1.00 m / 0.15 m = 8.00 vars
=Long. x No. vars. x 0.996 kg/m = 7.97 kg/m
= 139.74 kg

TOTAL: 9,355.34 KG

4140 01 SUMINISTRO Y COLOCACION DE


IMPERMEABILIZANTE INTEGRAL.
1,383.00 KG
concreto f'c = 250 kg/cm2 = 74.06 m3
Cemento : 0.467 ton. = 34,586.02 kg = 691.72 bultos de 50 kg
2 kg por cada bulto de cemento = 1,383.00 kg

Pgina 6 de 9
NUMEROS GENERADORES

OBRA: PLANTA DE BOMBEO PLANO:


CARCAMO DE BOMBEO 1 FFCHA:
UBICACIN: NOGALES, EDO. DE SONORA CALCULO:

CLAVE CONCEPTO LOCALIZARON


EJE TRAMO TIPO LARGO ANCHO ALTO PZAS RESULTADO OBSERVACIONES
TOTAL: 1,383.00 KG

4140 06 SUMINISTRO Y COLOCACION DE BANDA DE


P.V.C., SIN OJILLOS DE 9".
24.80 3.00 74.40 M
TOTAL: 74.40 M

Pgina 7 de 9
Proyecto Ejecutivo del Crcamo de Bombeo
No. de contrato: CONTA08-019
y Emisor de Aguas Residuales
Tarea II
para Nogales, Sonora.

COMISIN DE COOPERACIN ECOLGICA FRONTERIZA


ORGANISMO OPERADOR MUNICIPAL DE AGUA POTABLE, ALCANTARILLADO Y SANEAMIENTO

PRESUPUESTO BASE
LOCALIDAD: NOGALES CARCAMO 1 "CAMPO DE BISBOL"
MUNICIPIO: NOGALES (OBRA CIVIL)

CLAVE CONCEPTO UNIDAD CANTIDAD P.U. ($) IMPORTE ($)

1.TERRACERIAS

(NORMA CNA)

1005 01 LIMPIEZA Y TRAZO EN EL AREA DE TRABAJO. M 307.71 $7.16 $2,203.20

TOTAL TERRACERIAS = $2,203.20

2. EXCAVACIONES

A110A EXCAVACION CON MAQUINA PARA ZANJAS, EN MATERIAL "B", EN M 699.86 $21.50 $15,046.99
SECO, CON AFLOJE Y EXTRACCION DEL MATERIAL, AMACICE Y
LIMPIEZA DE PLANTILLA Y TALUDES, REMOCIN, CARGA A
CAMION O A UN LADO DE LA ZANJA, INCLUYENDO ACARREO A 10
M. DEL EJE DE LA MISMA Y CONSERVACIN DE LA EXCAVACION
HASTA LA INSTALACION SATISFACTORIA DE LA TUBERIA.
EXCAVACION DE 0.0 A 8.0 MTS. DE PROFUNDIDAD.

TOTAL EXCAVACIONES = $15,046.99

3. RELLENOS EN ZANJAS

A131D RELLENO APISONADO Y COMPACTADO CON EQUIPO MECNICO M 473.34 $58.70 $27,785.06
CON MATERIAL "A" Y/O "B", EN ZANJAS, CON AGUA EN CAPAS DE
30 CM. DE ESPESOR AL 85% DE LA PRUEBA PROCTOR. INCLUYE,
MANO DE OBRA, EQUIPO, HERRAMIENTA Y TODO LO NECESARIO
PARA SU CORRECTA EJECUCIN.

TOTAL RELLENOS = $27,785.06

27. ALBAILERIA Y ESTRUCTURAS

D030A FABRICACION Y COLADO DE CONCRETO SIMPLE, INCLUYE M 2.02 $1,480.10 $2,989.80


OBTENCION DE ARENAS, GRAVAS, CRIBADO, ACARREO 1ER. KM.
ETC. FABRICACION, ACARREO Y COLOCACION DEL CONCRETO
DE F'c= 100 KG/CM2 T.M.A 3/4", MANO DE OBRA, EQUIPO,
HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA
EJECUCIN.

D030E FABRICACION Y COLADO DE CONCRETO SIMPLE VIBRADO Y M 74.06 $1,919.44 $142,153.73


CURADO CON MEMBRANA, INCLUYE OBTENCION DE ARENAS,
GRAVAS, CRIBADO, ACARREO 1ER. KM. FABRICACION, ACARREO
Y COLOCACION DEL CONCRETO DE F'c= 250 KG/CM2 TM.A. DE
3/4", MANO DE OBRA, EQUIPO, HERRAMIENTA Y TODO LO
NECESARIO PARA SU CORRECTA EJECUCIN.

D0801 CIMBRA DE MADERA PARA ACABADOS NO APARENTES EN M 10.13 $202.55 $2,051.83


CIMENTACIONES, INCLUYE: FLETES Y MANIOBRAS LOCALES DEL
MATERIAL, FABRICACIN, CIMBRADO, DESCIMBRADO,
TERMINADO DEL REA COLADA, MATERIALES, MANO DE OBRA,
EQUIPO, HERRAMIENTA Y TODO LO NECESARIO PARA SU
CORRECTA EJECUCIN.

D0803 CIMBRA DE MADERA PARA ACABADOS NO APARENTES EN M 12.91 $224.55 $2,898.94


TRABES Y COLUMNAS, CON ALTURA DE OBRA FALSA DE 3.00
MTS., INCLUYE FLETES Y MANIOBRAS LOCALES DEL MATERIAL,
FABRICACION, CIMBRADO, DESCIMBRADO, TERMINADO DEL
REA COLADA, MATERIALES, MANO DE OBRA, EQUIPO,
HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA
EJECUCIN.

Seccin 13:
8
Presupuesto Base
Proyecto Ejecutivo del Crcamo de Bombeo
No. de contrato: CONTA08-019
y Emisor de Aguas Residuales
Tarea II
para Nogales, Sonora.

COMISIN DE COOPERACIN ECOLGICA FRONTERIZA


ORGANISMO OPERADOR MUNICIPAL DE AGUA POTABLE, ALCANTARILLADO Y SANEAMIENTO

PRESUPUESTO BASE
LOCALIDAD: NOGALES CARCAMO 1 "CAMPO DE BISBOL"
MUNICIPIO: NOGALES (OBRA CIVIL)

CLAVE CONCEPTO UNIDAD CANTIDAD P.U. ($) IMPORTE ($)

D0804 CIMBRA DE MADERA PARA ACABADOS NO APARENTES EN LOSAS, M 53.93 $191.91 $10,349.71
CON ALTURA DE OBRA FALSA DE 3.60 MTS., INCLUYE FLETES Y
MANIOBRAS LOCALES DEL MATERIAL, FABRICACION, CIMBRADO,
DESCIMBRADO, TERMINADO DEL REA COLADA, MATERIALES,
MANO DE OBRA, EQUIPO, HERRAMIENTA Y TODO LO NECESARIO
PARA SU CORRECTA EJECUCIN.

D0805 CIMBRA DE MADERA PARA ACABADOS NO APARENTES EN M 318.96 $205.84 $65,654.73


MUROS, CON ALTURA DE OBRA DE HASTA 3.00 MTS., INCLUYE
FLETES Y MANIOBRAS LOCALES DEL MATERIAL, FABRICACION,
CIMBRADO, DESCIMBRADO, TERMINADO DEL REA COLADA,
MATERIALES, MANO DE OBRA, EQUIPO, HERRAMIENTA Y TODO
LO NECESARIO PARA SU CORRECTA EJECUCIN.

4140 06 SUMINISTRO Y COLOCACIN DE BANDA DE PVC, SIN OJILLOS EN M 74.40 $139.05 $10,345.32
JUNTA DE CONSTRUCCIN DE 9".

D090B SUMINISTRO Y COLOCACIN DE ACERO DE REFUERZO DE F= KG 9299.80 $23.95 $222,730.21


4200 Kg./cm, INCLUYE SUMINISTRO DE BODEGA DE LA
COMPAA, DESPERDICIOS, ALAMBRE DE AMARRE,
HABILITACIN Y COLOCACIN.

ESC01 SUMINISTRO, FABRICACIN E INSTALACIN DE ESCALERA KG 88.50 $55.85 $4,942.73


MARINA DE PERFL TUBULAR DE 2"X2" CAL. 14,CON ESCALONES
A CADA 30 CM INCLUYE, MANO DE OBRA, EQUIPO,
HERRAMIENTA, MATERIALES Y TODO LO NECESARIO PARA SU
CORRECTA Y COMPLETA EJECUCIN.

(NORMA CNA)

4080 07 BONIFICACION EN CIMBRA POR ACABADO M 387.84 49.03 $19,015.80

4140 01 SUM. Y COLOC. DE IMPERMEABILIZANTE INTEGRAL KG 1383.00 $17.03 $23,552.49

TOTAL ALBAILERIA Y ESTRUCTURAS = $506,685.29

SUBTOTAL DE PRESUPUESTO = $551,720.54


IVA = $82,758.08
TOTAL DE PRESUPUESTO = $634,478.62

Seccin 13:
9
Presupuesto Base

También podría gustarte