METRADOS DE CARGAS

1er Nivel
Muros en X
1x
2x
3x
4x
5x
6x
7x
Alfeizer Eje 1
Alfeizer Eje 2
Alfeizer Eje 6
Alfeizer Eje 7
T1X
T2X
T3X

L (m)
1.45
2.65
2.45
3.80
2.45
1.45
1.55
1.95
2.10
2.00
2.20
2.65
0.85
0.85

Ancho (m)
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.15
0.15
0.15

Altura (m)
2.40
2.40
2.40
2.40
2.40
2.40
2.40
1.00
1.00
1.00
1.00
2.40
2.40
2.40

PP Alb (kg/m3)
1800
1800
1800
1800
1800
1800
1800
1800
1800
1800
1800
1800
1800
1800

Peso (kg)
1566.00
2862.00
2646.00
4104.00
2646.00
1566.00
1674.00
877.50
945.00
900.00
990.00
1717.20
550.80
550.80
23595.30

Muros en Y
1y
2y
3y
4y
T1Y
T2Y

L (m)
11.55
5.00
5.00
11.50
0.90
1.00

Ancho (m)
0.15
0.15
0.15
0.15
0.15
0.15

Altura (m)
2.40
2.40
2.40
2.40
2.40
2.40

PP Alb (kg/m3)
1800
1800
1800
1800
1800
1800

Peso (kg)
7484.40
3240.00
3240.00
7452.00
583.20
648.00
22647.60

Losa
PT

300.00
100.00

88.16
88.16

---------

--------CM

26448.00
8816.00
81506.90

S/C

250.00

88.16

-----

----CV

22040.00
22040.00

Ancho (m)
0.25
0.25
0.25
0.25
0.25
0.25
0.25

Altura (m)
2.40
2.40
2.40
2.40
2.40
2.40
2.40

PP Alb (kg/m3)
1800
1800
1800
1800
1800
1800
1800

Peso (kg)
1566.00
2862.00
2646.00
4104.00
2646.00
1566.00
1674.00
17064.00

2er Nivel
Muros en X
1x
2x
3x
4x
5x
6x
7x

L (m)
1.45
2.65
2.45
3.80
2.45
1.45
1.55

Muros en Y
1y
2y
3y
4y

L (m)
11.55
5.00
5.00
11.50

Ancho (m)
0.15
0.15
0.15
0.15

Altura (m)
2.40
2.40
2.40
2.40

PP Alb (kg/m3)
1800
1800
1800
1800

Peso (kg)
7484.40
3240.00
3240.00
7452.00
21416.40

Losa
PT

300
100.00

88.16
88.16

---------

--------CM

26448
8816
73744.40

S/C

150.00

88.16

-----

----CV

13224
13224.00

Pcm+Pcv (Kg)
103546.90
86968.40
190515.30

Pcm+25%Pcv (Kg)
87016.90
77050.40
164067.30

Pcm+25%Pcv (Tn)
87.02
77.05
164.07

RESUMEN DE CARGAS
Entonces :
Nivel
1er Nivel
2do Nivel

Pcm (Kg)
Pcv (Kg)
81506.90
22040.00
73744.40
13224.00
Peso total de la estructura

CALCULO DE LAS CARGAS Pg Y Pm PARA CADA MURO


1er Nivel
Direccin X
Nivel
1er Nivel

Pcm (Tn)
81.51

Pcv (Tn)
22.04

Pm (Tn)
103.55

Pg (m2)
87.02

Area (m2)
88.16

Pm (Tn/m2)
1.17

Muro
1X
2X
3X
4X
5X
6X
7X

L (m)
1.45
2.65
2.45
3.80
2.45
1.45
1.55

t (m)
0.24
0.24
0.24
0.24
0.24
0.24
0.24

Area Tributaria (m2)


2.20
5.11
4.93
5.11
4.93
2.28
2.20

Pm (Tn)
4.75
11.04
10.65
11.04
10.65
4.93
4.75

Pg(Tn)
4.09
9.51
9.18
9.51
9.18
4.24
4.09

m (kg/cm2)
1.36
1.74
1.81
1.21
1.81
1.42
1.28

L (m)
11.55
5.00
5.00
11.50

t (m)
0.14
0.14
0.14
0.14

Area Tributaria (m2)


12.93
16.08
11.88
13.15

Pm (Tn)
27.95
34.75
25.67
28.42

Pg(Tn)
23.91
29.73
21.97
24.32

m (kg/cm2)
1.73
4.96
3.67
1.77

Nivel
2do Nivel

Pcm (Tn)
73.74

Pcv (Tn)
13.22

Pm (Tn)
86.97

Pg (m2)
77.05

Area (m2)
88.16

Pm (Tn/m2)
0.99

Muro
1X
2X
3X
4X
5X
6X
7X

L (m)
1.45
2.65
2.45
3.80
2.45
1.45
1.55

t (cm)
0.24
0.24
0.24
0.24
0.24
0.24
0.24

Area Tributaria (m2)


2.20
5.11
4.93
5.11
4.93
2.28
2.20

Pm (Tn)
2.17
5.04
4.86
5.04
4.86
2.25
2.17

Pg(Tn)
1.92
4.47
4.31
4.47
4.31
1.99
1.92

m (kg/cm2)
0.62
0.79
0.83
0.55
0.83
0.65
0.58

L (m)
11.55
5.00
5.00
11.50

t (cm)
0.14
0.14
0.14
0.14

Area Tributaria (m2)


12.93
16.08
11.88
13.15

Pm (Tn)
12.76
15.86
11.72
12.97

Pg(Tn)
11.15
13.86
10.24
11.34

m (kg/cm2)
0.79
2.27
1.67
0.81

Pg (Tn/m2)
0.99

Direccin Y
Muro
1Y
2Y
3Y
4Y
2do Nivel
Direccin X
Pg (Tn/m2)
0.87

Direccin Y
Muro
1Y
2Y
3Y
4Y

ESFUERZO AXIAL MAXIMO


Como observamos, para realizar el diseo de los muros del primer nivel recurriremos al acpite 8.6.3 de la norma.
Para el diseo de los muros de pisos superiores recurriremos al acpite 8.6.4 debido a que no se agrietan en los niveles superiores.
Adems de esto debemos chequear la siguiente igualdad, que solo la haremos para el primer nivel, por ser el ms crticosuperiores
y si pasa para este primer nivel, pasara para los otros niveles

h 2
Pm
m
0.2 f m 1
0.15 f m
Lt
35t

f'm=

650

MURO 2Y (MAS CRITICO) :

Muro

Pm (Tn)

L*t (m2)

m (Tn/m2)

2Y

34.75

0.70

49.64

h
0.2 f m 1

35t

98.81

0.15 f m
97.50

Como vemos el muro ms crticocumple con las dos desigualdades, lo cual nos indica que podemos continuar con el diseo

Tn/m2

ANALISIS SISMICO
Calculo del Cortante Basal :
* Factor Zona
* Factor de Uso
* Factor de Suelo
* Coeficiente Ssmico

Z=
U=
S=

0.4
1
1.2

C=
C=
Ts=

11.494
2.5
0.4

T=
hn=
Ct=
h=

0.087
5.2
60
2.6

Altura de la Edificacion
Estructuras de Mamposteria
Altura Cada Nivel

R=
R=
C/R=

3
6
0.417

Sismo Severo
Sismo Moderado
OK

* Periodo del Suelo


* Periodo Fundamental Para Cada Direccion

* Factor de Ductibilidad
Verificar:

C/R>=0.125

T
C 2.5 P
T
Corregir Valor

C 2.5

Corregido

hn
CT

Z U C S
P
R
V=
0.2
*P

* Cortante Basal

* Peso de la Estructura P :
P=

164.07

Tn

V=

32.81

Tn

Distribucin del Cortante Basal :

Nivel
2do piso
1er piso

h (m)
5.20
2.60

P (Tn)
77.05
87.02

Ph
400.66
226.24
626.9

21.00

(%)
0.64
0.36
1

Sismo Moderado
F (Tn)
V (Tn)
21.00
21.00
11.81
32.81
32.81

Sismo Severo
F (Tn)
V (Tn)
42.00
42.00
23.62
65.62

42.00
21.00

11.81

32.81

SISMO MODERADO

42.00

23.62

65.62

SISMO SEVERO