CONSORCIO BICENTENARIO

OBRA “RECUPERACION DE LA INSTITUCION EDUCATIVA PRIMARIA N°10320 SAN LUIS DE QUIPAYUC, DISTRITO DE QUEROCOTILLO, PROVINCIA DE CUTERVO - CAJAMARCA”

ENTIDAD MUNICIPALIDAD DISTRITAL DE QUEROCOTILLO


CONTRATISTA CONSORCIO BICENTENARIO
RESIDENTE Ing. CESAR J. MORANTE PASTOR
SUPERVISOR ING BAUTISTA ESPINOZA SANTOS

CURVA DE AVANCE DE OBRA

RESUME DE VALORIZACION N°18


GRAFICA DE AVANCE DE OBRA
% S/. 100.0% 100.00%
99.94% 100.00%
97.93%
97.93% 97.93%
97.93%
% ACUM. PROG. 99.94% 4,788,998.79
90.0% 91.91%
91.91%
80% ACUM. PROG. 79.95% 3,831,199.04
80.0% 79.51%
79.51%

PORCENTAJE DE AVANCE
% ACUM. EJEC. 100.00% 4,792,102.74 70.0% 69.65%
69.64%
65.35%
65.35%
60.0% 58.12%
58.12%
50.0% 43.28% 49.46%
49.46%
40.84% 47.28%
47.28%
43.28%
SITUACIÓN ACTUAL DE LA OBRA CON RESPECTO AL 40.0% 40.84% Series2 Series1
33.71%
ACUMUL. PROGR. 27.95% 33.72%
30.0%
ADELANTADA 21.01% 27.95%
14.67% 21.01%
EN 0.06% 20.0%
4.54% 14.67%
10.0% 2.64%
0.00%
2.64% 4.54%
0.0% 0.00%
% ACUM. EJEC. > 80% ACUM. PROG. INICIO sep.-21 oct.-21 dic.-21 feb.-22 mar.-22 abr.-22 may.-22 jun.-22 jul.-22 ago.-22 may.-23 jun.-23 jul.-23 ago.-23 sep.-23 oct.-23 nov.-23 feb.-24 mar.-24
29/09/21
AVANCE ACEPTABLE MESES

INICIO
MESES sep.-21 oct.-21 dic.-21 feb.-22 mar.-22 abr.-22 may.-22 jun.-22 jul.-22 ago.-22 may.-23 jun.-23 jul.-23 ago.-23 sep.-23 oct.-23 nov.-23 feb.-24 mar.-24
29/09/21
PROG 0.00% 2.64% 4.54% 14.67% 21.01% 27.95% 33.71% 40.84% 43.28% 47.28% 49.46% 58.12% 65.35% 69.65% 79.51% 91.91% 97.93% 97.93% 99.94% 100.00%
% ACUMULADO
REAL 0.00% 2.64% 4.54% 14.67% 21.01% 27.95% 33.72% 40.84% 43.28% 47.28% 49.46% 58.12% 65.35% 69.64% 79.51% 91.91% 97.93% 97.93% 100.00%