COLOCACION DE
COLOCACION DE
CONTRATISTA MANZANA LOTE TIPOLOGIA NIVELES CIMENTACION SOBERCIMIENTO ALBAÑILERIA COLUMNAS ALIGERADO TARRAJEO INST. SANITARIAS INST. ELECTRICAS PISO CABLEADO
MAYOLICA
APARATOS VEREDAS ESCALERA PINTADO % AVANCE POR % AVANCE
SANITARIOS LOTE TOTAL
1 29/02/2024 7/03/2024 12/03/2024 13/03/2024 16/03/2024
1B TIPO 5 33.33%
2 21/03/2024 26/03/2024 28/03/2024
1 29/02/2024 7/03/2024 12/03/2024 13/03/2024 16/03/2024
2A TIPO 5 33.33%
2 23/03/2024 26/03/2024 28/03/2024
4A TIPO 5
1 15/03/2024 21/03/2024
8.33%
2
4B TIPO 5
1 15/03/2024 21/03/2024 8.33%
2
A 5A TIPO 5
1
2
1
16/02/2024
15/03/2024
23/02/2024
19/03/2024
27/02/2024
26/03/2024
28/02/2024 19/03/2024
20.83%
7A TIPO 5 12.50%
2
A
8A TIPO 5 12.50%
2
C
1 8/03/2024
AL
1 8/03/2024
O
2
PE
1
1A TIPO 2 VIVIENDA INTERVENIDA POR (GILDO ASTOQUILCA) 0.00%
B 4A TIPO 2
2
1
2
VIVIENDA INTERVENIDA POR (GILDO ASTOQUILCA) 0.00%
1 16/02/2024 20/02/2024 24/02/2024 27/02/2024 15/03/2024
3A TIPO 2 33.33%
2 12/03/2024 14/03/2024 20/03/2024
1 15/02/2024 20/02/2024 23/02/2024 24/02/2024 1/03/2024
4A TIPO 2 33.33%
I 4B TIPO 2
2
1
2
15/02/2024 20/02/2024
6/03/2024
23/02/2024
6/03/2024
12/03/2024
23/02/2024
12/03/2024
14/03/2024
1/03/2024
14/03/2024
33.33%
1 15/02/2024 20/02/2024 21/02/2024 22/02/2024 1/03/2024 27/03/2024 26/03/2024 29/03/2024
5B TIPO 2 54.17%
2 12/03/2024 20/02/2024 19/03/2024 27/03/2024 26/03/2024
N° LOTES 11 AVANCE ACTUALIZADO % 86.67% 73.33% 50.00% 43.33% 43.33% 6.67% 6.67% 3.33% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
FECHA INICIO 13‐Feb 19‐Feb 2‐Mar 6‐Mar 9‐Mar 23‐Mar 29‐Mar 30‐Mar 1‐Abr 5‐Abr 12‐Abr 15‐Abr 15‐Abr 14‐Mar 4‐Abr
AVANCE FECHA FIN 7‐Mar 9‐Mar 12‐Mar 16‐Mar 30‐Mar 6‐Abr 8‐Abr 8‐Abr 10‐Abr 13‐Abr 22‐Abr 23‐Abr 25‐Abr 24‐Mar 16‐Abr
PROGRAMADO % AVANCE
PROYECTADO 100.00% 100.00% 100.00% 100.00% 100.00% 71.49% 42.94% 37.24% 17.24% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00%
COLOCACION DE
COLOCACION DE
CONTRATISTA MANZANA LOTE TIPOLOGIA NIVELES CIMENTACION SOBERCIMIENTO ALBAÑILERIA COLUMNAS ALIGERADO TARRAJEO INST. SANITARIAS INST. ELECTRICAS PISO CABLEADO
MAYOLICA
APARATOS VEREDAS ESCALERA PINTADO % AVANCE POR % AVANCE
SANITARIOS LOTE TOTAL
C 2A TIPO 4 1 VIVIENDA INTERVENIDA (AGUSTIN GUTIERREZ) 0.00%
2A TIPO 2 1 17/02/2024 21/02/2024 23/02/2024 28/02/2024 7/03/2024 23/03/2024 26/03/2024 27/03/2024 53.33%
2B TIPO 2 1 16/02/2024 21/02/2024 24/02/2024 29/02/2024 7/03/2024 23/03/2024 26/03/2024 27/03/2024 53.33%
G 6A TIPO 2 1 16/02/2024 22/02/2024 28/02/2024 1/03/2024 7/03/2024 27/03/2024 27/03/2024 28/03/2024 53.33%
A
IÑ
7B TIPO 2 1 17/02/2024 21/02/2024 29/02/2024 5/03/2024 7/03/2024 26/03/2024 27/03/2024 27/03/2024 53.33%
CR
9A TIPO 2 1 21/02/2024 23/02/2024 5/03/2024 6/03/2024 19/03/2024 26/03/2024 30/03/2024 30/03/2024 53.33%
AL
42.00%
2B TIPO 6 1 8/03/2024 11/03/2024 15/03/2024 19/03/2024 19/03/2024 30/03/2024 40.00%
AJ
AVANCE FECHA FIN 7‐Mar 9‐Mar 12‐Mar 16‐Mar 30‐Mar 6‐Abr 8‐Abr 8‐Abr 10‐Abr 13‐Abr 22‐Abr 23‐Abr 25‐Abr 24‐Mar 16‐Abr
PROGRAMADO % AVANCE
PROYECTADO 100.00% 100.00% 100.00% 100.00% 100.00% 71.49% 42.94% 37.24% 17.24% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00%
COLOCACION DE
COLOCACION DE
CONTRATISTA MANZANA LOTE TIPOLOGIA NIVELES CIMENTACION SOBERCIMIENTO ALBAÑILERIA COLUMNAS ALIGERADO TARRAJEO INST. SANITARIAS INST. ELECTRICAS PISO CABLEADO
MAYOLICA
APARATOS VEREDAS ESCALERA PINTADO % AVANCE POR % AVANCE
SANITARIOS LOTE TOTAL
1 20/02/2024 22/02/2024 29/02/2024 6/03/2024 12/03/2024
2A TIPO 5 29.17%
I 2B TIPO 5
2
1
2
20/02/2024 22/02/2024
26/02/2024
29/02/2024
22/03/2024
30/03/2024
6/03/2024
28/03/2024
8/03/2024
30/03/2024
33.33%
1B TIPO 5 1 20/02/2024 9/03/2024 11/03/2024 13/03/2024 14/03/2024 27/03/2024 28/03/2024 20/03/2024 53.33%
3B TIPO 5 1 23/02/2024 6/03/2024 20/03/2024 21/03/2024 25/03/2024 30/03/2024 40.00%
A
5A TIPO 5 1 6.67%
J VIVIENDA INTERVENIDA (JOEL TACAS)
R
K 5B
6A
6B
TIPO 2
TIPO 2
TIPO 2
1
1
1
24/02/2024
24/02/2024
5/03/2024
4/03/2024
6/03/2024
7/03/2024
13/03/2024
18/03/2024
16/03/2024
21/03/2024
VIVIENDA INTERVENIDA (JOEL TACAS)
29/03/2024
33.33%
0.00%
40.00%
N° LOTES 11 AVANCE ACTUALIZADO % 100.00% 100.00% 100.00% 100.00% 92.31% 30.77% 7.69% 46.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
FECHA INICIO 13‐Feb 19‐Feb 2‐Mar 6‐Mar 9‐Mar 23‐Mar 29‐Mar 30‐Mar 1‐Abr 5‐Abr 12‐Abr 15‐Abr 15‐Abr 14‐Mar 4‐Abr
AVANCE FECHA FIN 7‐Mar 9‐Mar 12‐Mar 16‐Mar 30‐Mar 6‐Abr 8‐Abr 8‐Abr 10‐Abr 13‐Abr 22‐Abr 23‐Abr 25‐Abr 24‐Mar 16‐Abr
PROGRAMADO % AVANCE
PROYECTADO 100.00% 100.00% 100.00% 100.00% 100.00% 71.49% 42.94% 37.24% 17.24% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00%
COLOCACION DE
COLOCACION DE
CONTRATISTA MANZANA LOTE TIPOLOGIA NIVELES CIMENTACION SOBERCIMIENTO ALBAÑILERIA COLUMNAS ALIGERADO TARRAJEO INST. SANITARIAS INST. ELECTRICAS PISO CABLEADO
MAYOLICA
APARATOS VEREDAS ESCALERA PINTADO % AVANCE POR % AVANCE
SANITARIOS LOTE TOTAL
36B TIPO 5 1 20/02/2024 28/02/2024 4/03/2024 6/03/2024 8/03/2024 29/03/2024 40.00%
37A TIPO 5 1 24/02/2024 27/02/2024 6/03/2024 20/03/2024 22/03/2024 29/03/2024 40.00%
37B TIPO 5 1 22/02/2024 16/03/2024 18/03/2024 21/03/2024 22/03/2024 29/03/2024 40.00%
38A TIPO 5 1 20/02/2024 9/03/2024 12/03/2024 15/03/2024 16/03/2024 29/03/2024 40.00%
O
CN
38B TIPO 5 1 22/02/2024 6/03/2024 6/03/2024 19/03/2024 21/03/2024 29/03/2024 29/03/2024 46.67%
G
TU
39A TIPO 5 1 17/02/2024 22/02/2024 28/02/2024 12/03/2024 13/03/2024 29/03/2024 40.00% 40.61%
24/02/2024 4/03/2024 7/03/2024 13/03/2024 16/03/2024
R
AVANCE FECHA FIN 7‐Mar 9‐Mar 12‐Mar 16‐Mar 30‐Mar 6‐Abr 8‐Abr 8‐Abr 10‐Abr 13‐Abr 22‐Abr 23‐Abr 25‐Abr 24‐Mar 16‐Abr
PROGRAMADO % AVANCE
PROYECTADO 100.00% 100.00% 100.00% 100.00% 100.00% 71.49% 42.94% 37.24% 17.24% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00%
COLOCACION DE
COLOCACION DE
CONTRATISTA MANZANA LOTE TIPOLOGIA NIVELES CIMENTACION SOBERCIMIENTO ALBAÑILERIA COLUMNAS ALIGERADO TARRAJEO INST. SANITARIAS INST. ELECTRICAS PISO CABLEADO
MAYOLICA
APARATOS VEREDAS ESCALERA PINTADO % AVANCE POR % AVANCE
SANITARIOS LOTE TOTAL
5A TIPO 5 1 29/02/2024 11/03/2024 13/03/2024 19/03/2024 21/03/2024 27/03/2024 28/03/2024 46.67%
S
J
CA
30.00%
29/02/2024 8/03/2024 11/03/2024 14/03/2024 16/03/2024
K 5A TIPO 2 1 27/03/2024 28/03/2024 26.67%
EL
JO
COLOCACION DE
COLOCACION DE
CONTRATISTA MANZANA LOTE TIPOLOGIA NIVELES CIMENTACION SOBERCIMIENTO ALBAÑILERIA COLUMNAS ALIGERADO TARRAJEO INST. SANITARIAS INST. ELECTRICAS PISO CABLEADO
MAYOLICA
APARATOS VEREDAS ESCALERA PINTADO % AVANCE POR % AVANCE
SANITARIOS LOTE TOTAL
1 8/03/2024 26/03/2024 27/03/2024 29/03/2024
A
10A TIPO 5 16.67%
E T
2
VA O
E
16.67%
RR
NA IM
2
N° LOTES 2 AVANCE ACTUALIZADO % 50.00% 50.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
FECHA INICIO 13‐Feb 19‐Feb 2‐Mar 6‐Mar 9‐Mar 23‐Mar | 30‐Mar 1‐Abr 5‐Abr 12‐Abr 15‐Abr 15‐Abr 14‐Mar 4‐Abr
AVANCE FECHA FIN 7‐Mar 9‐Mar 12‐Mar 16‐Mar 30‐Mar 6‐Abr 8‐Abr 8‐Abr 10‐Abr 13‐Abr 22‐Abr 23‐Abr 25‐Abr 24‐Mar 16‐Abr
PROGRAMADO % AVANCE
PROYECTADO 100.00% 100.00% 100.00% 100.00% 100.00% 71.49% #¡VALOR! 37.24% 17.24% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00%
COLOCACION DE
COLOCACION DE
CONTRATISTA MANZANA LOTE TIPOLOGIA NIVELES CIMENTACION SOBERCIMIENTO ALBAÑILERIA COLUMNAS ALIGERADO TARRAJEO INST. SANITARIAS INST. ELECTRICAS PISO CABLEADO
MAYOLICA
APARATOS VEREDAS ESCALERA PINTADO % AVANCE POR % AVANCE
SANITARIOS LOTE TOTAL
1 26/03/2024 27/03/2024 28/03/2024 29/03/2024
B
1A TIPO 2 16.67%
A
ILC
2
TO O
16.67%
QU
AS ILD
4A TIPO 2 16.67%
2
N° LOTES 2 AVANCE ACTUALIZADO % 50.00% 50.00% 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
FECHA INICIO 13‐Feb 19‐Feb 2‐Mar 6‐Mar 9‐Mar 23‐Mar 29‐Mar 30‐Mar 1‐Abr 5‐Abr 12‐Abr 15‐Abr 15‐Abr 14‐Mar 4‐Abr
AVANCE FECHA FIN 7‐Mar 9‐Mar 12‐Mar 16‐Mar 30‐Mar 6‐Abr 8‐Abr 8‐Abr 10‐Abr 13‐Abr 22‐Abr 23‐Abr 25‐Abr 24‐Mar 16‐Abr
PROGRAMADO % AVANCE
PROYECTADO 100.00% 100.00% 100.00% 100.00% 100.00% 71.49% 42.94% 37.24% 17.24% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00%
COLOCACION DE
COLOCACION DE
CONTRATISTA MANZANA LOTE TIPOLOGIA NIVELES CIMENTACION SOBERCIMIENTO ALBAÑILERIA COLUMNAS ALIGERADO TARRAJEO INST. SANITARIAS INST. ELECTRICAS PISO CABLEADO
MAYOLICA
APARATOS VEREDAS ESCALERA PINTADO % AVANCE POR % AVANCE
SANITARIOS LOTE TOTAL
AGUSTIN GUTIERREZ
C 2A TIPO 4 1 28/03/2024 30/03/2024 13.33%
16.67%
K 8A TIPO 4 1 20/02/2024 22/02/2024 25/03/2024 26/03/2024 28/03/2024 33.33%
N° LOTES 2 AVANCE ACTUALIZADO % 50.00% 50.00% 25.00% 25.00% 25.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
FECHA INICIO 13‐Feb 19‐Feb 2‐Mar 6‐Mar 9‐Mar 23‐Mar 29‐Mar 30‐Mar 1‐Abr 5‐Abr 12‐Abr 15‐Abr 15‐Abr 14‐Mar 4‐Abr
AVANCE FECHA FIN 7‐Mar 9‐Mar 12‐Mar 16‐Mar 30‐Mar 6‐Abr 8‐Abr 8‐Abr 10‐Abr 13‐Abr 22‐Abr 23‐Abr 25‐Abr 24‐Mar 16‐Abr
PROGRAMADO % AVANCE
PROYECTADO 100.00% 100.00% 100.00% 100.00% 100.00% 71.49% 42.94% 37.24% 17.24% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00%
28.50%
RESTRICCIONES (SEMNANA 6 )
‐ Ladrillo de techo.