Contenido

19. PASE AEREO ............................................................................................................ 2


1 MEMORIA DESCRIPTIVA ..................................................................................... 2
1.1. JUSTIFICACION .................................................................................................................... 2
1.2. ALCANCES ............................................................................................................................ 2
2 MEMORIA DE CÁLCULO ESTRUCTURAL .......................................................... 3
2.1. GENERALIDADES ................................................................................................................. 3
2.2. PROCEDIMIENTO DE DISEÑO Y EVALUACIÓN ................................................................ 3
2.3. CARACTERISTICAS DE LA ESTRUCTURA ........................................................................ 6
19. PASE AEREO

1 MEMORIA DESCRIPTIVA

1.1. JUSTIFICACION

El presente informe técnico, tiene por objeto elaborar el expediente técnico de adicional
de obra N° 1 para la construcción de 02 pases aéreos para la línea de emisión de
alcantarillado de las localidades de Santa ana y Union Palaycca respectivamente.

Estructuras que no estuvieron contempladas en el expediente técnico contractual y que


por ser una infraestructura necesaria para cumplir con la operatividad de servicio, es
presentado para su justificación.

1.2. ALCANCES

Para el caso que se presenta, los Pases aéreos constarán de 02 columnas dobles
sostenidas en zapatas, será de concreto armado de f’c=210 kg/cm2.

En los extremos del pase aéreo iran ubicadas cámaras de anclaje de concreto f´c=175
kg/cm2 para lograr el equilibrio de dicho pase. La tubería que pasa será soportada con
un cable principal de acero serie 6x19 tipo Boa alma de acero y pendolas con sus
respectivos accesorios según planos de detalles.
2 MEMORIA DE CÁLCULO ESTRUCTURAL

2.1. GENERALIDADES

A continuación describiremos las características de las estructuras consideradas para


los pases aéreos de las tuberías y los criterios que se usaron para poder diseñarlas.

2.1.1. Proyecto

Todos los componentes del sistema de agua potable, serán justificados mediante un
cálculo estructural, de manera que se determine los refuerzos objetivamente.
Los cálculos estructurales serán firmados por un ingeniero civil, colegiado y
habilitado.

2.1.2. Descripción de la Estructura

Los pases aéreos son estructuras compuestas por 02 columnas de concreto armado
en cada extremo, cada una de las cuales presentan una zapata aislada como
cimentación. Entre los extremos pasa un cable principal el cual tiene como objetivo
sostener la tubería mediante péndolas distribuidas equidistantemente a lo largo de
toda la longitud del vano, el cable principal se encuentra apoyado sobre las columnas
y sostenido por anclajes de concreto. Las estructuras a evaluar y diseñar presentan
un sistema estructural conformado por el cable principal, las péndolas, el dado de
anclaje y las columnas con sus respectivas zapatas ubicadas en los extremos, los
cuales soportan los esfuerzos que transmiten los cables.

2.1.3. Normas vigentes

Reglamento Nacional de edificaciones y sus actualizaciones.


(E.020 Norma de Cargas).
(E.030 Norma de Diseño Sismo Resistente).
(E.050 Norma Suelos y Cimentación).
(E.060 Norma de Concreto Armado).
Norma de referencia ACI 350 y ACI 318.

2.2. PROCEDIMIENTO DE DISEÑO Y EVALUACIÓN

Para el diseño se consideró:

Localidad Union Palaycca

- Zona sísmica 4, terreno blando (capacidad portante de 1.0 kg/cm²) y velocidad


máxima de vientos 80km/h, como asunción general se tomó las condiciones más
desfavorables para el diseño.

Localidad de Santa Ana

- Zona sísmica 4, terreno blando (capacidad portante de 0.4 kg/cm²) y velocidad


máxima de vientos 60 km/h, como asunción general se tomó las condiciones
más desfavorables para el diseño.
Análisis Estático:

Se verificó el comportamiento estático de las columnas frente a fuerzas de flexo-


compresión trasmitidas por el cable, para luego trasmitir estas fuerzas a la zapatas y
esta al terreno, mediante un análisis indicado en la Norma Peruana E.060. Para el
diseño del cable se tuvo en cuenta el esfuerzo de fluencia del cable, calculando el
esfuerzo de tensión se servicio, ocasionado por fuerzas de gravedad y de viento. Con
ese propósito se construyó un modelo matemático para el análisis respectivo. Para
el cálculo de esfuerzos y diseño se usó el Excel.

Ilustración 1: Parámetros de la fuerza sísmica - Normativa de diseño sismo resistente

Elaboración: Programa Nacional de Saneamiento Rural

De acuerdo a la figura:

Zona Más Crítica : Zona 4


Factor de Zona : Z=0.45g

Tabla 1: Factores de Zona


FACTORES DE ZONA
ZONA Z
4 0.45
3 0.35
2 0.25
1 0.1
Factor de Suelo.-
Perfil tipo : S3
Factor de Suelo : S=1.10
Periodo del Suelo : Tp=1.0

Tabla 2: Factor "S" y Período "Tp" y "Tl"


Factor "S"
So S1 S2 S3
Z4 0.80 1.00 1.05 1.10
Z3 0.80 1.00 1.15 1.20
Z2 0.80 1.00 1.20 1.40
Z1 0.80 1.00 1.60 2.00

Período "Tp" y "Tl"


Perfil de suelo
So S1 S2 S3
Tp(s) 0.3 0.4 0.6 1.0
Tl (s) 3 2.5 2 1.6
Elaboración: Programa Nacional de Saneamiento Rural

Factor de Importancia.-
Para las estructuras de este proyecto, por ser fundamentales ante cualquier sismo,
usaremos el valor más alto de 1.5.

Tabla 3: Categoría de las Edificaciones


CATEGORIA DE LAS EDIFICACIONES
CATEGORIA DESCRIPCION FACTOR U
A1: Establecimientos de salud como hospitales, institutos o
similares, según clasificación del ministerio de Salud, ubicados en
las zonas sísmicas 4 y 3 que alojen cualquiera de los servicios
indicados.
A2: Edificaciones esenciales cuya función no debería interrumpirse
después de que ocurra un sismo severo como:
- Hospitales no comprendidos en la categoría A1, clínicas, postas
médicas, excepto edificios administrativos o de consulta externa.
A
- Puertos, aeropuertos, centrales de comunicaciones. Estaciones de
Edificaciones
bomberos, cuarteles de las fuerzas armadas y policía.
Esenciales
- Instalaciones de generación y transformación de electricidad,
1.5
reservorios y plantas de tratamiento de agua.
Todas aquellas edificaciones que pueden servir de refugio después
de un desastre, tales como colegios, institutos superiores
tecnológicos y universidades.
Se incluyen edificaciones cuyo colapso puede representar un riesgo
adicional, tales como como grandes hornos, fábricas y depósitos de
materiales inflamables o tóxicos.
Elaboración: Programa Nacional de Saneamiento Rural

Factor de Reducción Sísmica.-


Para el sistema estructural utilizado el valor correspondiente es de 8.

Tabla 4: Sistemas Estructurales


Sistemas Estructurales
Coeficiente Básico
Sistemas Estructural
de Reducción Ro
Acero:
Pórticos dúctiles con uniones 8
resistentes a momentos.
Otras Estructuras de acero:
7
Arriostres Excéntricos
Arriostres Concéntricos 6
Elaboración: Programa Nacional de Saneamiento Rural
Factor de Amplificación Sísmica, C.-
𝑇
𝐶 = 2,5 ; 𝐶 ≤ 2,5
𝑇

Se considerará el valor más crítico el cual corresponde a 2.5.

2.2.1. Verificación de esfuerzos:

Entre los parámetros que intervienen en la VERIFICACIÓN ESTRUCTURAL se


encuentran la resistencia al corte para las zapatas, análisis de estabilidad, resistencia
al corte y flexión para las columnas, resistencia al deslizamiento y estabilidad para
los dados de anclaje.

2.2.2. Criterio de la Evaluación Estructural

La consideración que se hace para las estructuras propuestas, las columnas de los
extremos funcionara como elementos de apoyo para el cable principal, el cual estará
empotrado al terreno a través de dados de anclaje de concreto.

2.3. CARACTERISTICAS DE LA ESTRUCTURA

2.3.1. Características de los materiales:


Se muestra a continuación los materiales y las especificaciones que conforman la
estructura del mismo:

Concreto:
- Resistencia del concreto – Elementos Estructurales f’c =210 Kg/cm2.
- Resistencia del concreto – Dado de Anclaje f’c =175 Kg/cm2.

Acero de Refuerzo:
Resistencia a la fluencia del acero grado 60, f’y = 4200 Kg/cm2

Cables de Acero:
Cable de Acero Tipo BOA (6x19) para péndolas y cable principal

Tabla 5: Diámetro de acero


TIPO BOA (6x19)
DIAMETROS
Peso (Kg/m) Rotura (Tn)
1/4 '' 0.17 2.67
3/8 '' 0.37 6.7
1/2 '' 0.69 12.6
5/8 '' 1.05 19
3/4 '' 1.48 26.8
1 '' 2.78 50.3
1 1/8 '' 3.46 62.5
1 1/4 '' 4.21 76.1
1 3/8 '' 5.04 91.1
1 1/2 '' 5.97 107.3
1 5/8 '' 7.26 104
1 3/4 '' 8.32 149.4
2 '' 11.06 189.6
Elaboración: Programa Nacional de Saneamiento Rural
Pases Aereos: Union Palaycca – Santa Ana

ESPECIFICACIONES TECNICAS

02.01.01.01 TRABAJOS PRELIMINARES


02.01.01.01.01 LIMPIEZA DE TERRENO MANUAL (M2)

Descripción
Consiste en limpiar el área designada para el proyecto, de todos los árboles, arbustos, y
demás vegetación, obstáculos, basura e inclusive desarraigamiento de muñones y retiro
de todos los materiales inservibles que resulten de la limpieza y deforestación.
La limpieza de terreno se realizará con la finalidad de garantizar el adecuado inicio de los
trabajos de trazo, replanteo y la ejecución de la obra; se utilizarán herramientas manuales
como machete, serruchos, pico, pala, barretas, así como otras herramientas para tal fin.
Medición
La unidad de medida será el metro cuadrado de limpieza de terreno.
Forma de Pago.
Se realizará de acuerdo al avance realmente ejecutado.

02.01.01.01.02 TRAZO Y REPLANTEO PRELIMINAR (M2)


Consideraciones
Consiste en el trabajo de topografía que debe realizar el contratista/residente para
determinar la localización planimétrica y altimétrica de todas las obras del contrato, a partir
de los puntos y ejes topográficos dados como referencia, de acuerdo con las libretas de
topografía, los planos del proyecto o las instrucciones del Supervisor.
El Residente de Obra se obliga a suministrar y mantener durante la ejecución del contrato
comisiones de topografía con personal idóneo y dotado del equipo de precisión adecuado,
previamente autorizado por la Supervisión, las cuales deben realizar todos los trabajos de
localización, replanteo y altimetría necesarios, para la correcta ejecución y control de la
obra, bajo la responsabilidad total del Residente de Obra, de acuerdo con las órdenes e
instrucciones impartidas por el Supervisor.
Antes de iniciar las obras, el Residente de Obra someterá a la verificación y aprobación de
la Supervisión la localización general del proyecto y sus niveles.
Durante la construcción el Residente de Obra deberá verificar periódicamente las medidas
y cotas, cuantas veces sea necesario, para ajustarse al proyecto.
Antes de iniciar cualquier trabajo, el Residente de Obra debe hacer el levantamiento
planimétrico y altimétrico del área del proyecto, elaborando el plano respectivo y
sometiéndolo a aprobación de la Supervisión.
El Residente de Obra debe ejecutar la localización objeto de las actividades del proyecto,
así como el de las respectivas construcciones de redes y edificaciones, trazar y verificar
los ejes de cimientos, muros y demás estructuras mostradas en los planos y el replanteo
general del proyecto utilizando todos los instrumentos de precisión que sean necesarios
para la ubicación exacta de las obras.
El Residente de Obra debe tomar las medidas necesarias para asegurar que sus trabajos
de localización sean exactos y es responsable por la corrección o demolición de obras que
resulten defectuosas por errores en la localización.
Será obligación del Residente de Obra poner a disposición de la Supervisión la comisión
de topografía, cuando ésta lo requiera para efectuar trabajos de verificación y control de
las obras en construcción o para la ejecución de trabajos de planimetría o altimetría que se
requieran para definir aspectos relativos a las obras objeto del Contrato.

Especificaciones Tecnicas 1
Pases Aereos: Union Palaycca – Santa Ana

Al finalizar la obra, el Residente de Obra debe hacer el levantamiento altimétrico y


planimétrico del proyecto tal como quedó construido y someter a aprobación del Supervisor
los planos definitivos de construcción, antes de entregar el original respectivo.
Igualmente deberá dejar referenciados físicamente en dos puntos del proyecto,
previamente definidos por el Supervisor.
Trazo y replanteo inicial del proyecto, para líneas-redes con estación total
Descripción
Esta partida considera el trazo inicial de las líneas y redes de agua potable, la ubicación de
interferencias que serán tratadas con las administradoras de los servicios y la propia
población, la preparación de los planos de obra y/o la modificación de los diseños para
reflejar los cambios luego de confrontar el terreno con el diseño.
El Contratista/residente debe proceder al replanteo del eje de la zanja con alineaciones
rectas, destacando la ubicación de accesorios con testigos debidamente marcados con
pintura esmalte y sus signos representativos, corriendo por su cuenta la reposición de
cualquier estaca. Antes del inicio de las excavaciones, el Contratista/residente someterá a
la aprobación del Supervisor los planos de replanteo de las líneas de agua y alcantarillado,
esquemas, planos de detalle y de fábrica de las partes de las obras donde sea necesario.
Replanteo final de la obra, para líneas redes con estación total
El equipo de topografía bajo la dirección del residente de la obra, realizará los trabajos de
replanteo topográfico finales una vez concluida la obra, este consistirá en el registro de la
longitud de tramos, accesorios y válvulas, etc.
Esta información posteriormente deberá ser procesada en gabinete y ser entregada a
través de planos a la entidad contratante a fin de formar parte de su catastro técnico, todo
esto previa conformidad técnica del Ing. Supervisor. Todos los planos y diseños serán
entregados en archivos digital en formato cad (*.dwg) en la última versión de la licencia
adoptada por la entidad contratante y juegos impresos en la cantidad indicada en los Datos
del Contrato.

Medición
La unidad de medida será el metro cuadrado de trazo y replanteo.

Forma de Pago
El pago de esta partida se efectuará de acuerdo al avance aprobado y con el precio
estipulado en el contrato e incluye todos los materiales, mano de obra, equipo, etc.
Requeridos.

Especificaciones Tecnicas 2
Pases Aereos: Union Palaycca – Santa Ana

02.01.01.02 MOVIMIENTO DE TIERRAS


02.01.01.02.01 EXCAVACION MANUAL PARA ESTRUCTURAS EN T.N. (M3)
Descripción
Este trabajo consiste en toda la excavación necesaria para alcanzar los niveles adecuados
dados por los planos. La ampliación de las explanaciones incluirá la conformación, perfilado
y conservación de taludes, bermas y cunetas, de acuerdo a los planos de secciones
transversales del proyecto.

Método de Construcción
Este trabajo consiste en toda la excavación necesaria para la ampliación de las
explanaciones en corte de material no rocoso. La ampliación de las explanaciones incluirá
la conformación, perfilado y conservación de taludes, bermas y cunetas, de acuerdo a los
planos de secciones transversales del proyecto.
El material producto de estas excavaciones se empleará en la construcción o ampliación
de terraplenes y el excedente deberá ser depositado en botaderos donde indique el
Supervisor.
Se entiende como material suelto, aquel que para su remoción no necesita el uso de
explosivos, ni de martillos neumáticos, pudiendo ser excavado mediante el empleo de
tractores, excavadoras o cargadores frontales, y desmenuzado mediante el escarificador
de un tractor sobre orugas.

Corte
Este tipo de actividad está referida a aquellos cortes efectuados a mano o máquina, con
anchos y profundidades necesarias para la construcción de infraestructuras hidráulicas; de
acuerdo a los planos replanteados en obra y/o a las presentes especificaciones en las
medidas indicadas. Se debe señalar que esta actividad se realizará luego de haber
efectuado el trazo y replanteo correspondiente el mismo que debe ser aprobado por la
supervisión.

Para la ejecución de la mencionada actividad el Contratista/Residente debe tener en cuenta


las diferentes eventualidades que se puedan presentar en obras, para ello debe considerar
lo siguiente:
- Establecer las medidas de seguridad y protección tanto del personal de la
construcción, así como del público en general.
- Establecer las posibles perturbaciones que puedan presentarse en las
construcciones colindantes, tales como desplomes, asentamiento o derrumbes.
- Evitar la destrucción de instalaciones, de servicios subterráneos que pudieran
existir en el área.

Calidad de los Materiales


Se muestran en forma general, los distintos aspectos que deberán tener en cuenta el
Contratista/Residente y el supervisor para realizar el control de calidad para la ejecución
del presente trabajo.

- Sistema de control de calidad


- Revisión material
- Revisión de trabajos de construcción
- Revisión en laboratorio
- Revisión de campo
- Revisión de dimensiones
- Revisión por medición directa

Especificaciones Tecnicas 3
Pases Aereos: Union Palaycca – Santa Ana

- Revisión por fotografías


- Revisión de la calidad de la partida ejecutada
- Revisión de dimensiones
- Revisión de la calidad final
- Pruebas de revisión de la operación

El Contratista/Residente hará efectivo el auto-control en la ejecución de la presente partida


y la supervisión efectuara los controles a que hubiere lugar para el aseguramiento de la
calidad.

Sistema De Control De Calidad


Se muestran en forma general, los distintos aspectos que deberán tener en cuenta el
Contratista/Residente y el supervisor para realizar el control de calidad para la ejecución
del presente trabajo.
Sistema de control de calidad
Revisión material
Revisión de trabajos de construcción
Revisión en laboratorio
Revisión de campo
Revisión de dimensiones
Revisión por medición directa
Revisión por fotografías
Revisión de la calidad de la partida ejecutada
Revisión de dimensiones
Revisión de la calidad final
Pruebas de revisión de la operación
El Contratista/Residente hará efectivo el auto-control en la ejecución de la presente partida
y la supervisión efectuara los controles a que hubiere lugar para el aseguramiento de la
calidad.

Medición
Se medirá por metro cúbico de corte en terreno de material suelto de la obra a ejecutar.

Forma de Pago
Se pagará por la cantidad de metros cúbicos por corte en terreno de material suelto,
tomando en cuenta la Norma de Medición y la Unidad de Medida correspondiente.

02.01.01.02.02 REFINE Y COMPACTACION MANUAL EN T.N. PARA ESTRUCTURAS


(M2)

Descripción
Se efectuará después de concluida la excavación.
El refine consiste en perfilar las paredes como del fondo, teniendo especial cuidado que no
quede protuberancias rocosas que hagan contacto con el cuerpo de las tuberías, las que
pueden causar diversas averías a las instalaciones de las mismas.
La nivelación se efectuará en el fondo del terreno, con el tipo de tierra clasificada y
aprobada por la Supervisión. Tanto la clase de material de relleno, como la compactación
deben controlarse continuamente durante la ejecución de la obra.

Especificaciones Tecnicas 4
Pases Aereos: Union Palaycca – Santa Ana

El relleno superior, se realiza con material propio seleccionado procedente de las


excavaciones de las zanjas, en capas de 10 a 15 cm. compactando con pisón de mano,
hasta el nivel superior de la zanja. El material de relleno debe quedar como un lomo a lo
largo de la zanja, para que en el proceso de consolidación, que ocurre con el tiempo, baje
a su nivel.

- El relleno debe hacerse con materiales de buena calidad, libre de desperdicios,


materia orgánica u otros materiales inadecuados.
- Los materiales utilizados para el relleno, deberán estar conformes con los
requerimientos especificados. Seguir los requerimientos normales para relleno
común cuando no se especifique el uso de material de relleno clasificado.
- Los materiales para los diversos rellenos deberán obtenerse de las excavaciones
propias, que serán aprobadas por la Supervisión.
- Si el material procedente de las excavaciones o canteras, no cumplen con las
condiciones granulométricas requeridas, se procederá al zarandeo y/u otros medios
para separar el material incompetente.
- El contenido de materia orgánica no podrá ser superior al 5% y el material que pasa
la malla Nº 40, tendrá un límite líquido máximo de 35% y un índice de plasticidad
máximo de 20%.
- La adaptabilidad de los materiales y su ubicación en los rellenos estarán sujetos a
la aprobación de la SUPERVISION.
El trabajo a realizar bajo estas Partidas del Contrato comprende el suministro de toda la
mano de obra, herramientas, materiales, equipos y servicios necesarios para el refine y
nivelación de zanja, en los diferentes diámetros y alturas que se indica en los planos y que
cumplan con las Especificaciones Técnicas aplicables.
Medición
La unidad de medida será el metro cuadrado de refine y compactación de material.
Forma de Pago
El pago se efectuará de acuerdo al avance ejecutado, constituyendo dicho precio y pago,
compensación plena por mano de obra, equipos fletes, etc. y todos los imprevistos
necesarios para completar la partida.

02.01.01.02.03 RELLENO CON MATERIAL PROPIO SELECCIONADO (M3)

Descripción
El relleno consiste en cubrir los espacios que quedan posteriores al vaciado de las
estructuras de concreto cimentadas, estos rellenos deberán de alcanzar los niveles que
especifican los planos.

Método De Construcción:
Relleno Estructural
Colocación de Relleno para Estructuras:
- Antes de comenzar el relleno, todo material extraño, incluyendo agua debe ser
removido del espacio a ser rellenado y el área a ser rellenada deberá ser
inspeccionada y aprobada por el Supervisor. Los lados inclinados del espacio
excavado deben ser escalonados con el fin de prevenir la acción de apretar el relleno
contra la estructura. No se debe colocar ningún relleno alrededor o en cualquier
estructura hasta que se pruebe que el concreto haya alcanzado la resistencia
suficiente y que la estructura en conjunto es adecuada para recibir el relleno. La
resistencia a la compresión del concreto deberá ser determinada por pruebas en

Especificaciones Tecnicas 5
Pases Aereos: Union Palaycca – Santa Ana

muestras representativas curadas bajo condiciones similares a aquéllas


prevalecientes en la zona.
- El relleno debe ser colocado en capas uniformes en lados opuestos de estructuras y
paredes antes de la compactación. El Contratista/Residente debe informar al
Supervisor de la secuencia del relleno a ser seguida alrededor de cada estructura y
esta secuencia deberá ser aprobada por el Supervisor antes que cualquier relleno sea
colocado.

Compactación del Relleno para Estructura:


- El relleno para estructuras deberá ser colocado en capas horizontales de
profundidades compatibles al tipo de equipo de compactación a ser usado, pero en
ningún caso deben estas capas exceder de 200 mm. Cada capa debe ser esparcida,
el contenido de humedad convertido a condiciones óptimas y luego compactada a una
densidad que no sea menor a 95 por ciento de la densidad máxima en una humedad
óptima.
- El relleno debe ser mecánicamente compactada por un equipo de tamaño y tipo
aprobado por el Supervisor. El permiso para usar equipo de compactación
especificado no debe interpretarse como garantizando o implicando que el uso de
dicho equipo no dañará suelos adyacentes, instalaciones existentes o estructuras
instaladas bajo el Contrato.
- Inundación, chorros de agua o charcas no será permitido para la compactación de
cualquier estructura de relleno.

Relleno Controlado

Compactación: A menos que sea especificado de otra manera, el material de relleno debe
ser compactado por el Contratista/Residente mientras que el contenido de humedad esté
cerca del contenido óptimo de humedad y a una densidad que no sea menor al 90 por
ciento de la máxima densidad a una humedad óptima.

Preparación de Áreas a ser Rellenadas.

- Toda materia vegetal, orgánica y plástica y otros materiales inconvenientes deberá


ser removido por el Contratista/Residente desde la superficie en la cual el relleno
será colocado y cualquier suelo suelto poroso debe ser removido o compactado a
una profundidad como se muestra en los Planos. La superficie luego debe ser
arado o escarificado a una profundidad mínima de 150 mm hasta que la superficie
esté libre de perfiles irregulares que podrían impedir la compactación uniforme por
el equipo a ser usado.
- Donde los rellenos sean construidos en laderas o colocados en pendientes de
terrenos original, deberá colocarse escalonados por el Contratista/Residente como
se muestran en los planos. Los escalones deben extenderse completamente a
través del manto del suelo y en los materiales de formación base.
- Después que la base para el relleno ha sido limpiado, arado o escarificado, deberá
ser arado o cortado por el Contratista/Residente hasta tener forma uniforme y libre
de terrones que será compactado con el apropiado contenido de humedad, tal como
está especificado.

Colocación, Extendido y Compactación del Material de Relleno:


- El material de relleno deberá ser colocado por el Contratista/Residente en capas
delgadas y cuando sean compactadas no deben excederse de 200 mm. Cada capa
debe de extenderse uniformemente y mezclarse durante su extendido para obtener
uniformidad de material en cada capa.

Especificaciones Tecnicas 6
Pases Aereos: Union Palaycca – Santa Ana

- Cuando el contenido de humedad del material de relleno está debajo de lo


especificado por el Supervisor, el Contratista/Residente deberá adicionar agua
hasta que el contenido de humedad sea como lo especificado.
- Cuando el contenido de humedad del material de relleno está por arriba de lo
especificado por el Supervisor, el material de relleno debe ser aireado por el
Contratista/Residente mediante paleo, mezcla u otros métodos satisfactorios hasta
que el contenido de humedad sea de acuerdo a lo especificado.
- Después que cada capa ha sido colocada, mezclada y extendida, deberá ser
totalmente compactada por el Contratista/Residente a una densidad especificada.
La Compactación debe ser efectuada por equipos de compactación aceptables. El
equipo debe ser de tal diseño que sea capaz de compactar el relleno a la densidad
especificada. La compactación debe ser continua sobre el área total y el equipo
debe hacer pases suficientes sobre el material para asegurar que la densidad
deseada ha sido obtenida.
- Las superficie inclinadas de relleno deben ser compactadas, con el fin de que los
taludes sean estables y no debe haber pérdida excesiva de suelo en los taludes.
- El Contratista/Residente deberá suministrar y mantener instalaciones de control de
erosión adecuada durante la construcción de áreas de relleno. Las instalaciones
de control de erosión deben de mantenerse en óptima condición hasta que el
sistema de drenaje permanente y vegetación se complete. Las instalaciones deben
de ser inspeccionadas siguiendo el exceso de inundación de agua en el sitio, las
reparaciones hechas y el exceso de sedimento removido. Será responsabilidad del
Contratista/Residente prevenir la descarga del sedimento fuera del sitio o en cursos
de agua

Sistema De Control De Calidad:


La supervisión verificara la correcta ejecución del relleno compactado del terreno.
Tomar en cuenta las siguientes pautas para un mejor control de obra:
Revisión material
Revisión de trabajos de construcción
Revisión de campo
Revisión de la calidad de la partida ejecutada.
Pruebas de revisión de la operación.

Medición
La unidad de medida será el metro cúbico.
Forma de Pago

Para el pago se determinarán en obras directamente las cantidades, de acuerdo a lo


indicado en el proyecto y las órdenes del Ingeniero Supervisor.

02.01.01.02.04 ELIMINACIÓN DE MATERIAL EXCEDENTE A MANO (D=30 m) (M3)


Descripción
El Residente/Contratista, una vez terminada la obra deberá dejar el terreno completamente
limpio de desmonte.

Consiste en el retiro de todo el material proveniente de la demolición y de la excavación


que fuera excedente y de todo material inservible. Incluye el material proveniente de
reparaciones, limpieza final de la zona de trabajo y toda eliminación que sea necesario
efectuarse prestará particular atención al hecho que, tratándose de trabajos a realizarse en
zona urbana, no deberá apilarse los excedentes interrumpiendo el tránsito peatonal o

Especificaciones Tecnicas 7
Pases Aereos: Union Palaycca – Santa Ana

vehicular así como molestias con el polvo que generan las tareas de apilamiento, carguío
y transporte que forman parte de la partida.

La eliminación de desmonte deberá ser periódica, no permitiendo que permanezca en la


obra más de un mes, salvo lo que se va a usar en los rellenos.

Medición
La unidad de medida será según el metro cúbico de material excedente eliminado.

Forma de Pago
El pago por esta partida será en por metro cúbico (m3), una vez que sea verificado por el
supervisor la culminación de la misma.

02.01.01.03.01 CONCRETO f'c=100 kg/cm PARA SOLADO


02.01.01.03.02 CONCRETO f 'c=210 kg/cm2 EN ZAPATAS
02.01.01.03.03 CONCRETO f 'c=210 kg/cm2 EN COLUMNAS
02.01.02.02.03 CONCRETO f'c=175 kg/cm2

Descripción
Concreto f’c=100 kg/cm2 en Solados
Se refieren al colocado de un solado de concreto simple sobre el terreno apisonado como
una primera capa de concreto que sirve de protección y para el posterior trazo de la
armadura de la estructura, cuyo espesor es de 10 cms. La resistencia mínima de la matriz
de concreto será de 100 kg/cm2 y no será necesario el uso de ningún tipo de aditivo para
este tipo de concreto.
Se limpiará la zona a llenar de solado de concreto simple, este deberá estar nivelado y
apisonado.
Deberá colocarse puntos para mantener el nivel. Luego se vaciará el concreto simple sobre
la superficie compactado, posteriormente se debe mantener el nivel requerido por tratarse
de estructuras importantes.
Concreto Armado f’c=210 a 280 kg/cm2
El concreto será fabricado con una mezcla de cemento- piedra chancada, que den como
resultado una resistencia a la compresión equivalente mayor a 210 kg/cm2 según lo
indicado, como mínimo, a los 28 días de fragua. La mezcla será preparada
mecánicamente, será vaciada sin excesivo manipuleo y se utilizará el tipo de aditivo
indicado en el análisis de precios unitarios para este tipo de concreto.

Medición
La unidad de medida será el metro cúbico de concreto

Forma de Pago
Se pagará por el total del concreto vaciado y en buen estado.

Especificaciones Tecnicas 8
Pases Aereos: Union Palaycca – Santa Ana

02.01.01.03.04 ACERO DE REFUERZO fy=4,200 kg/cm2 EN ZAPATAS (KG)

Descripción
El acero de construcción, también se denomina acero al carbono, constituye el principal
producto de los aceros que se producen, El aumento del contenido de carbono en el acero
eleva su resistencia a la tracción y corte, incrementa el índice de fragilidad en frío y hace
que disminuya la tenacidad y la ductilidad.
Son barras de acero corrugado colocadas para absorber en el concreto los esfuerzos de
tracción y corte así como para permitir que la estructura mantenga su resistencia y
durabilidad durante su vida útil.

Características Técnicas
El acero de construcción es corrugado, lo cual le permite una alta adherencia con el concreto.
Antes de ser habilitadas en su posición final las barras de acero deberá estar libre de
impurezas, escamas y óxidos suelto y de cualquier suciedad que los recubra caso contrario
se deberá limpiar usando escobilla de acero (no tendrá más oxidación que aquella que pueda
haber acumulado durante el transporte a obra), para evitar destruir o reducir la adherencia
con el concreto.
El suministro de estos debe estar libres de defectos, dobleces y curvas; se aceptan aquellas
que puedan ser rápidas y completamente enderezadas en el campo.
Las barras serán colocadas en posición exacta y espaciamiento que indiquen los planos y
serán sujetos firmemente para impedir desplazamiento, durante el vibrado del concreto;
para este fin se podrá utilizar como separadores dados de concreto, preparados
especialmente con este fin.
El acero está especificado en los planos de acuerdo a su carga de fluencia pero deberá
además ceñirse a las siguientes condiciones:
- Carga de Fluencia en 4200 kg/cm2.
- Carga de rotura en 5000-6000 kg/cm2.
- Deformación mínima a la rotura 10%
- Corrugaciones: ITINTEC o ASTM 305-66 T.

El acero se fabrica en varillas de 9 m en los siguientes diámetros: 6 mm, 8 mm, 3/8”, 12 mm,
½”, 5/8”, ¾”, 1”.
Las dimensiones y pesos nominales del acero de construcción se indican en la tabla
siguiente:

Especificaciones Tecnicas 9
Pases Aereos: Union Palaycca – Santa Ana

Tabla 1: Diámetro de Acero


DIAMETRO DE BARRA SECCION PERIMETRO PESO ALTURA DE LOS
Pulg. mm (mm²) (mm) (kg/m) RESALTES (mm - mín)
- 6 28 18.8 0.222 0.24
- 8 50 25.1 0.395 0.32
3/8” 8.5 71 29.9 0.560 0.38
- 12 113 37.7 0.888 0.48
½” 12.7 129 39.9 0.994 0.51
5/8” 15.9 199 49.9 1.552 0.71
¾” 19.1 284 59.8 2.235 0.97
1” 25.4 510 79.8 3.973 1.27
1 3/8” 35.8 1006 112.5 7.907 1.80
Elaboración: Programa Nacional de Saneamiento Rural

Los diámetros de doblado especificados por las Normas Técnicas para la prueba de doblado
son:

Tabla 2: Diámetros de acero especificados por las Normas


DIAMETRO 6 mm 8 mm 3/8” 12 mm ½” 5/8” ¾” 1” 1 3/8”
DIAMETRO 3.5d 3.5d 3.5d 3.5d 3.5d 3.5d 5d 5d 7d
DOBLADO
mm 21.0 28.0 33.3 42.0 44.5 55.6 95.5 127.0 250.6
Elaboración: Programa Nacional de Saneamiento Rural

Los aceros serán doblados por única vez, no pudiendo ser enderezados para luego corregir
el doblado anterior.
Las barras son identificadas por marcas de laminación en alto relieve que indican el
fabricante, el diámetro y el grado del acero.

Transporte a Obra
- Se recomienda evitar el doblado de las varillas de acero para el transporte dentro
de la obra, en todo caso se recomienda habilitarlos en el almacén principal de tal
forma que el traslado se realice con facilidad (por las dimensiones menores que
tienen las varillas listas para instalación en las estructuras específicas).

- Si se almacenan por tiempos prolongados, se almacenara, en depósitos bajo techo,


para evitar que estas se oxiden provocados por la humedad o el agua.

Medición
Se medirá por kilogramo (Kg) de acero habilitado e instalado.

Forma de Pago
Se realizará de acuerdo al presupuesto por kilogramo (Kg).

02.01.01.03.06 ENCOFRADO Y DESENCOFRADO EN ZAPATAS (M2)


02.01.01.03.07 ENCOFRADO Y DESENCOFRADO EN COLUMNAS (M2)
02.01.02.03.01 ENCOFRADO Y DESENCOFRADO (M2)
Descripción
Son estructuras temporales, construidas generalmente de madera, diseñadas para recibir el
concreto no endurecido y obtener las formas y dimensiones especificadas en los planos.
Especificaciones Tecnicas
10
Pases Aereos: Union Palaycca – Santa Ana

Método de Ejecución
Los encofrados deberán ser ejecutados por operarios calificados; su estructura debe ser
tal que resista las cargas de la mezcla fresca y las cargas vivas producto del trabajo, así
también las formas deberán tener la suficiente estanqueidad para impedir la pérdida de la
lechada de cemento y no perjudicar la resistencia de diseño del concreto.
Los encofrados deberán poseer un adecuado sistema de arriostre para mantener su
posición y forma durante el vaciado y endurecimiento del concreto. Serán de madera
tornillo o similar de no menos de 5/8” de espesor, no se permitirán el uso de tirantes de
alambre, ni se colocarán dentro de las formas tacos, conos, arandelas u otros elementos
extraños. Todas las superficies interiores deberán estar libres de materiales adheridos,
después de cada uso se pasará escobilla metálica y se recubrirán con aceite para su uso
posterior. Antes de proceder con el vaciado deberán ser supervisados y aprobados. En
general, el encofrado será removido cuando el concreto haya endurecido suficientemente
para soportar su peso propio y cualquier otra carga de diseño.
Medición
Será por metro cuadrado (m2).
Forma de Pago
Se realizará de acuerdo al presupuesto por metro cuadrado (m2).

02.01.01.04 ACABADOS
02.01.02.01 TARRAJEO DE EXTERIORES C:A 1:4 e=2.00 cm. (M2)

Descripción
Comprende el tarrajeo de superficies exteriores de las estructuras. Se ha considerado
partes por debajo del nivel del terreno con la finalidad de proteger la estructura.
Se deberá tener en cuenta lo siguiente:
- Se empleará mortero cemento, arena de proporción 1:4, la arena será uniforme,
libre de arcilla, materia orgánica y salitre.
- Se limpiarán y se humedecerán las superficies, según el caso, antes de proceder al
tarrajeo.
- La superficie deberá tener suficiente aspereza para que exista buena adherencia.
- El acabado del tarrajeo será un plano vertical u horizontal según sea el caso, para
ello se trabajará con cintas de preferencia de mortero pobre (1:7), corridas
verticalmente a lo largo del muro.
- Las cintas convenientemente aplomadas sobresaldrán el espesor exacto del
tarrajeo, tendrán el espaciamiento máximo de 1.00 m. lineal, arrancando lo más
cerca posible de la esquina del paramento, una vez terminado un paño, se picarán
las cintas, rellenando el espacio con mezcla algo más rica que la usada en el resto
del tarrajeo.
- La entidad ejecutora cuidará y será responsable de todo maltrato o daño que ocurra
en el acabado de los revoques. Correrá por su cuenta hacer los resanes hasta
entregar la obra.
- El alineamiento de las aristas de todos los derrames será perfectamente recto, tanto
horizontal como vertical.
- Las aristas de los derrames expuestos impactos serán convenientemente
achatadas de acuerdo a las indicaciones del supervisor.

Especificaciones Tecnicas
11
Pases Aereos: Union Palaycca – Santa Ana

Medición
El trabajo ejecutado se medirá en metros cuadrados (M2) de superficie tarrajeada.

Forma de Pago
El pago se efectuará de acuerdo al avance de la partida realmente ejecutado, aprobadas
por el Supervisor, entendiéndose que dicho precio y pago constituirá compensación
completa para toda la mano de obra, materiales, equipo, herramientas y demás conceptos
que completan esta partida.

02.01.01.04.02 PINTURA LATEX EN ESTRUCTURA, 2 MANOS (M2)

Descripción
Comprende todas las actividades necesarias para el pintado de superficies que han sido
previamente tarrajeadas, a fin de mejorar su acabado.

Para su aplicación es necesario los siguientes pasos:


- Ejecutado el revoque y estando completamente seco, se lijan los muros exteriores, con
la finalidad de pulir la superficie y eliminar posibles grumos que siempre se presentan
en el revoque.
- Finalmente se aplica la primera mano de pintura esmalte que puede ser con brocha
o equipo de fumigación, cuidando desde un principio que no se presente superficies
disparejas, secada la primera mano se aplica la segunda, tratando de uniformizar el
color y presentar finalmente la obra de arte terminada.

Medición
La medición de estos trabajos se hará por Metro Cuadrado (M2), de área pintada.

Forma de Pago
El pago se efectuará de acuerdo al área total de la partida realmente ejecutado, aprobadas
por el Supervisor, entendiéndose que dicho precio y pago constituirá compensación
completa para toda la mano de obra, materiales, equipo, herramientas y demás conceptos
que completan esta partida.

02.01.01.04.03 PINTURA BITUMINOSA (M2)

Descripción
Todas las paredes externas de la estructura en contacto con el terreno.
Se empleará una pintura bituminosa que tenga garantizada su utilidad, y que obtenga la
aprobación previa del Supervisor,
Limpiar con cepillo u otras herramientas adicionales la superficie a proteger de modo de
obtener una superficie limpia de grasas, polvo u otros materiales extraños dejándola limpia
y seca.
La pintura se aplicará con brocha o rodillo, en dos capas de no menos de cuatro décimas
de milímetro de espesor (0,4 mm), cada una. Se evitará su aplicación cuando la
temperatura ambiente sea inferior a cinco (5) grados centígrados. El intervalo entre la

Especificaciones Tecnicas
12
Pases Aereos: Union Palaycca – Santa Ana

aplicación de cada capa dependerá de la temperatura ambiente, con un mínimo de dos


días.
Deberá utilizarse protección contra la lluvia durante las cuarenta y ocho (48) horas
siguientes al extendido final.

Medición
La medida para el pago será la cantidad de metros cuadrados (m2) correspondientes al
área de la superficie debidamente pintada y aceptada por el Ingeniero Supervisor.

Forma de Pago
El pago se efectuará de acuerdo a la cantidad de metros cuadrados pintados de la partida
realmente ejecutado, aprobadas por el Supervisor, entendiéndose que dicho precio y pago
constituirá compensación completa para toda la mano de obra, materiales, equipo,
herramientas y demás conceptos que completan esta partida.

02.01.03 ELEMENTOS METÁLICOS DE SOPORTE


02.01.03.01 ACCESORIOS METALICOS DE ANCLAJE Y SOPORTE DE CABLE
(UND)
02.01.03.02 CABLE TIPO BOA 6x19 DE 1/2" (M)
02.01.03.03 CABLE TIPO BOA 6x19 DE 1/4" (M)
02.01.03.04 ABRAZADERA DE PLATINA DE 3/16" + PERNO DE 1/4" (UND)

Generalidades:
Todas estas partidas tienen que ver con la instalación del soporte de la tubería de agua
para el pase aéreo. En lo que respecta al cable de soporte de la tubería el cual será Acerado
Tipo Boa de Ø ½”, 3/8” o ¼”, según sea el diseño y su función será soportar el peso de la
tubería la cual será transmitida a través de las péndolas que estarán distribuidas a lo largo
de toda su dimensión, las péndolas estarán constituidas por cable de Acero Tipo Boa de Ø
indicado en plano y en cada extremo llevaran para su sujeción al cable tensor grapas
Crosby para cable de diámetro indicado en planos.
El cable principal estará soportado por dos torres de concreto armado ubicadas en cada
extremo del lecho de quebrada, y estará anclado a una cámara de anclaje ubicado detrás
de cada columna, las dimensiones y detalles de los accesorios figuran en los respectivos
planos.

Método de Medición:
El suministro e instalación de cables y accesorios para pase aéreo estarán medidos y
computados en Ml y Und, cabe indicar que la medidas de los cables se computara toda la
luz de la quebrada más la longitud de anclaje del cable; en los accesorios se computara
todas las unidades que intervengan en la instalación.

Bases de Pago:
El pago se efectuará por Ml para cables y Und para accesorios del pase aéreo.

Especificaciones Tecnicas
13
Pases Aereos: Union Palaycca – Santa Ana

02.01.04 TUBERIAS
02.01.04.01 SUMINISTRO E INSTALACIÓN DE TUBERIA PVC LISA NTP-ISO 4427
(M)

Generalidades
El material presentado bajo esta Especificación Técnica, deberá cumplir con la Norma Técnica
Peruana NTP ISO 4427:2008 PE100 SDR11 PN 10

MANEJO
El manejo de las tuberías polietileno de agua potable se puede realizar de dos maneras:
manual o con equipos. Se debe manipular el producto de tal manera que no sea golpeado
con ningún elemento.
En tuberías de PVC a pesar de ser un material flexible y resistente debe evitarse arrastrar
los rollos sobre el suelo áspero.
Al mover los rollos para el almacenaje, pueden hacerse rodar sobre sí mismos, procurando
que en su camino no pisen objetos punzantes o con aristas que puedan dañar la superficie
del tubo.
Si es necesario desatar un rollo para cortar un trozo de tubo, es conveniente atarlo de
nuevo sin apretar excesivamente las ataduras, a fin de no segarlo.
Para cortar el tubo, utilice una sierra, un cuchillo o un cortador especial, nunca herramienta
que al cortar pueda producir aplastamiento del mismo.
Si debido al manejo o almacenaje defectuoso, una tubería resulta dañada o con dobleces,
la porción afectada debe ser suprimida completamente.
- En caso de ser necesario la tubería debe desenrollarse de forma tangencial rodándolo
sobre sí mismo, evitando hacerlo en forma de espiral para evitar estrangulamiento y
daños en la tubería.
- Antes de hacer cualquier tipo de manipulación de producto se hará una verificación en
su interior, el cual debe estar completamente vacío.
- En ningún caso se permite descargar tuberías mediante caídas no controladas, por lo
cual debe asegurarse la estabilidad en todo momento.

Especificaciones Tecnicas
14
Pases Aereos: Union Palaycca – Santa Ana

ALMACENAMIENTO:
La tubería en tramos se almacena en posición horizontal, debidamente soportada sobre
toda su extensión. La superficie de apoyo debe estar libre de incrustaciones y elementos
que puedan llegar a rayar o fracturar la tubería.
La tubería en rollos se debe almacenar parada y recostada sobre una superficie rígida.
- No se deben colocar cargas sobre las tuberías.
- La tubería en rollos debe almacenarse zunchada y permanecer así hasta su
utilización.
- La altura de apilamiento para tramos, a fin de evitar esfuerzos importantes en las
capas inferiores, no sobrepasará de 2 metros en tubos de PVC . En zonas cálidas
o con temperaturas superiores a 50° C, estas alturas se reducirán a 1.5 metros.
- Las tuberías de polietileno PVC pueden ser almacenadas bajo techo o al
descubierto solo si son negras, ya que están protegidas de la acción solar por la
adición en su masa de negro de carbono.
- Las tuberías de polietileno pigmentadas en azul o amarillo precisan de una atención
especial respecto a los rayos solares, por lo que se recomienda una exposición
limitada a los seis meses para los azules y un año para los amarillos.
- Los rollos de tubería de PVC deberán ser almacenados también sobre superficies
planas y limpias.
- No obstante si no existe otra solución se almacenaran verticalmente pero en una
sola altura.
Se evitará que los tubos almacenados, en rollos o por tramos, estén en contacto con
combustibles, disolventes, adhesivos, pinturas agresivas ni con conducciones de vapor o
agua caliente. Debe asegurarse que la temperatura de la superficie externa no alcance los
45° C, por lo que es conveniente una buena aireación de los tubos para evitar la
deformación debida a la acumulación de calor.
La tubería se debe acomodar levantando los tubos o deslizándolos en forma lenta para
evitar el maltrato del producto.

Instalación
Recomendaciones básicas de uso
Las tuberías de polietileno agua potable están diseñadas para soportar la presión nominal
a una temperatura máxima de 23° C. Valores por encima de los indicados no garantizan la
durabilidad y el buen funcionamiento de la tubería.
Evite realizar operaciones tales como el cierre rápido de una válvula, ya que esto produce
un fenómeno de sobre presión llamado “Golpe de Ariete”.
La resistencia a la presión hidrostática de la tubería está directamente relacionada con el
espesor de pared y el tipo de material, por tal motivo, la indebida manipulación de tuberías
y accesorios tales como golpes, rayones o fisuras afectan dicha condición.
No se debe permitir el tránsito por encima de los tubos una vez sean hechas las uniones a
los accesorios y/o otros tramos de la tubería.
Si los trabajos se suspenden, deben taponarse los extremos de la tubería para prevenir la
flotación en caso de que la zanja se inunde.
Debe colocarse, a una distancia entre 0.20 m y 0.30 m por encima de la superficie superior
de la tubería, una cinta de 10 cm. de ancho, que indique la presencia de la tubería y el
fluido que conduce.
La tubería de polietileno, permite cierto radio de curvatura sin necesidad de utilizar
accesorios para sobrepasar obstáculos o generar desviaciones, sin embargo dicho valor
depende del diámetro de la misma.
El tendido de la instalación debe realizarse de forma que se reduzcan parcialmente las
tensiones producidas por las variaciones térmicas.

Especificaciones Tecnicas
15
Pases Aereos: Union Palaycca – Santa Ana

Las tuberías de polietileno de agua potable son aptas para ser instaladas tanto en zanja
como en superficie. Lógicamente, la vida de una instalación en zanja será mucho más
prolongada que aquella que se encuentra en la superficie, al quedar perfectamente
protegida.
Cuando las tuberías de polietileno se instalan en bosques o en terrenos rocosos, no es
necesario eliminar los obstáculos ya que dada su flexibilidad relativamente elevada,
pueden ser salvados la mayoría de ellos.
No obstante debe tenerse en cuenta su rigidez, para evitar que se deformen, al faltarles el
apoyo de las tierras laterales que le ayuden a mantener su estabilidad dimensional.
Para el transporte en el sitio de la obra, es imperativo cargar los rollos y evitar rodarlos por
el piso ya que se pueden generar fisuras o perforaciones a la superficie.
El tendido de las tuberías, en el caso de existir pendientes fuertes en el trazado, se realiza
preferentemente en el sitio ascendente, previendo puntos de anclaje para la tubería.

Sistema de Instalación con Apertura de Zanja (Tradicional)


Inicialmente se debe realizar la apertura de la zanja, teniendo en cuenta las siguientes
características:
- El fondo de la zanja debe ser continuo, liso libre de filos y uniforme.
- El ancho de la zanja debe permitir colocar el tubo, unir el tubo dentro de ellas (si es
absolutamente necesario) y compactar los lados del tubo.
- Entibar el terreno en suelos con posible desprendimiento de material.
- Siempre que se realice el montaje en el fondo de la zanja, el ancho de la misma vendrá
determinada por la fórmula B = Dn + 300mm, donde Dn es el diámetro nominal, con
un mínimo de 600mm. En caso de zanjas de poca profundidad y tubos de diámetro
inferiores a 110mm la anchura mínima podrá ser de 400mm.
- Después de realizada la zanja se procede a unir tanto de los tramos de la tubería como
los diferentes accesorios necesarios, de acuerdo al diseño hidráulico y a los sistemas
de unión.

Medición
La unidad de medida será el metro lineal

Forma de Pago
La presente partida estará pagada por metro lineal (m) de tubería tendida conforme lo
especifican los planos y en las condiciones antes señaladas, según el avance real de los
trabajos, previa verificación del Ingeniero Supervisor.

02.01.04.02 SUMINISTRO E INSTALACION DE TUBERIA PVC NTP 339.002 (M)

Generalidades
El material presentado bajo esta Especificación Técnica, deberá cumplir con la Norma
Técnica Peruana NTP 399.002-2009 para tuberías menores a 63mm (2”).
La instalación de la tubería de PVC es a simple presión (SP)

Método constructivo:

Especificaciones Tecnicas
16
Pases Aereos: Union Palaycca – Santa Ana

Todas las tuberías para pases aéreos de agua potable que considera el proyecto, deberán
ser instaladas con los diámetros y presiones de trabajo especificadas en los planos, como
en los trazos, profundidades y otros detalles que se consideran en los documentos del
proyecto.

Transporte y almacenamiento:
En todas las fases del transporte, inclusive su manipuleo, carga, descarga y apilamiento,
se deberá tomar medidas para evitar choques que altere la hermeticidad del sistema.
Si una tubería es dañada accidentalmente, márquela claramente, separándola a fin de
efectuar posteriormente su reparación.
Para almacenamiento en obra, el apilamiento se hará en forma piramidal, nivelando el
terreno y colocando vigas transversales.

Montaje de los tubos de espiga y campana con pegamento:


Para efectuar un correcto montajes de los tubos y accesorios de PVC por el sistema simple
pegar, se debe seguir las siguientes recomendaciones a fin economizar tiempo y asegurar
instalaciones de calidad.
- Limpiar cuidadosamente el extremo del tubo y el interior de la campana donde
insertará, limpiarlos del polvo y grasa con un trapo húmedo.
- Pulir con una lija fina el interior de la campana y el exterior de la espiga a insertar.
En caso sea necesario cortar el tubo, utilizar el arco de sierra cuidando efectuar el corte a
escuadra y luego proceder hacer un chaflán o bisel en el tubo con ayuda de una escofina
de grano fino.
Es de suma importancia obtener el chaflán indicado, para distribuir mejor el pegamento
dentro de la campana al momento del ensamblaje.
Aplicar el pegamento, tanto en la espiga del tubo como en el interior de la campana, sin
exceso y con ayuda de una brocha pequeña.
Después de la aplicación del pegamento introducir el tubo en la campana con un
movimiento rectilíneo, asegurando que la inserción de la espiga sea igual al largo de la
campana.
No girar el tubo introducido, pues podría romperse la continuidad de la película del
pegamento aplicado previamente.
Es muy importante efectuar el empalme rápidamente debido a que el solvente del
pegamento se volatiza con mucha rapidez por lo cual toda la operación desde la aplicación
del pegamento hasta el término de la inserción debe demorar alrededor de un minuto.
No quitar el exceso de pegamento de la unión efectuada. En un empalme bien hecho debe
aparecer un cordón de pegamento entre la campana y el tubo insertado.
Si este exceso de pegamento no sale en el momento que se hace el empalme, significa
que no se ha utilizado la cantidad necesaria de pegamento y por consiguiente esa unión
podría tener fugas.
Dejar secar el pegamento de 10 a 15 minutos antes de acomodar la tubería en su posición
final dentro de la zanja.
Efectos de la temperatura:
Dilatación de la tubería PVC
La fórmula para calcular la expansión de las tuberías de PVC es la siguiente:
DL =K (T2-T1) L
Dónde:
DL= dilatación en cm.
K= Coeficiente de dilatación 0.8 mm/ m 10°
T2= Temperatura máxima
T1= Temperatura mínima
L= Longitud de la tubería en m.
Especificaciones Tecnicas
17
Pases Aereos: Union Palaycca – Santa Ana

Cuando la tubería está expuesta a temperaturas más bajas que la temperatura de la


instalación se debe permitir contracciones.
En general cuando la diferencia total de temperatura es menor de 15 °C no es necesario
considerar juntas de dilatación sobre todo cuando la línea tiene varios cambios de dirección
y por lo tanto proporcionan su propia flexibilidad.
Cuando hay conexiones roscadas es necesario considerar junta de dilatación.
Cuando existen cambios de temperatura considerable hay varios métodos para neutralizar
la expansión térmica, siendo el más común él a base de codos cementados.

Calidad de los materiales:


Las tuberías deberán ser revisados cuidadosamente antes de instalarlas, a fin de descubrir
defectos tales como: roturas, rajaduras, porosidad, fallas de alineamiento, etc. y se
verificará que estén libres de cuerpos extraños u otros. Se empleará tuberías PVC para
fluidos a presión con empalme espiga campana o simple presión (SP) NTP 399.002.

Sistema de control de calidad:


Durante la ejecución de los trabajos, el supervisor efectuara los siguientes controles
principales:
- Verificar que las tuberías cumplan con la norma técnica peruana NTP 399.002
tuberías pvc para fluidos a presión con simple presión (SP).
- Verificar que las tuberías se encuentren instaladas de acuerdo a los planos.
- Supervisar la correcta aplicación de los métodos de trabajo aceptados.
- Vigilar el cumplimiento de los programas de trabajo.

Medición
La unidad de medida será el metro lineal.

Bases de Pago:
La forma de pago se efectuará por metro lineal (ml), entendiéndose que dicho precio y pago
constituirá la compensación total por la mano de obra, materiales, equipo, herramientas,
accesorios e imprevistos necesarios para la ejecución de la partida.

02.01.04.03 EMPALME DE TUBERIA PVC A TUBERIA PVC Ø 6" (UND)


Descripción
Comprende el suministro e instalación de los accesorios de PVC SP
Todos los materiales serán de la mejor calidad y de primer uso, por lo que no deberán
presentar ningún tipo de falla o abolladura o defectos tales como roturas, rajaduras,
porosidades, etc. en cada elemento.
Así mismo el residente deberá presentar el certificado de control de calidad de los
materiales expedido por el fabricante, el cual será verificado por el supervisor.
Todos los Accesorios serán revisados cuidadosamente antes de ser instalados a fin de
verificarán que esté libre de cuerpos extraños, tierra, etc.

Sistema de control de calidad:

Especificaciones Tecnicas
18
Pases Aereos: Union Palaycca – Santa Ana

Los Accesorios de PVC, Serán cloruro de polivinilo PVC, Clase 10, del tipo inyectado que
se utilizarán en el sistema de agua potable. Tendrá similares características que las
tuberías de PVC NTP Nº 399.002:2009 para agua potable.
Deberán soportar una presión de trabajo de hasta 150 lb/pulg2.
Serán fabricados de acuerdo a norma técnica peruana NTP Nº 399.002:2009

Método constructivo:
Los accesorios de PVC serán instalados de acuerdo a lo especificado en los planos y
contando con la aprobación de la supervisión.
Los accesorios de PVC en todo cambio brusco de dirección, se anclarán en dados de
concreto.

Medición
La unidad de medida será la unidad.

Forma de Pago
El pago se efectuará por unidad de cada tipo de accesorio instalado, entendiéndose que
dicho precio y pago constituirá una compensación total por materiales, mano de obra,
equipos y herramientas e imprevistos necesarios para la realización de esta partida.

Especificaciones Tecnicas
19
Pases Aereos: Union Palaycca – Santa Ana

MANUAL DE OPERACIÓN Y MANTENIMIENTO


1.1. CONCEPTO

El pase aéreo es una estructura que se usa en las líneas de conducción, aducción y
redes de distribución para salvar los obstáculos de los ríos y quebradas encontrados en
el trazo.

1.2. OPERACIÓN

Por el tipo de estructura no requiere operación.

1.3. MANTENIMIENTO

Todos los meses al recorrer y revisar la infraestructura del sistema de agua, también se
debe inspeccionar y verificar el estado del pase aéreo.

Infraestructura civil

- Revisar periódicamente que la torre no presenta inclinación o deslizamiento de su


posición original o socavamiento en la aparte de su fundación.
- Limpiar externamente las torres y dados de anclaje, es decir sus alrededores
retirando malezas, piedras y otros materiales extraños.
- En caso de grietas o rajaduras en las estructuras resanar en partes iguales de
cemento y arena fina.
- Pintado de la parte expuesta de la infraestructura (solo concreto)

Cables, péndolas y estructuras metálicas

- Revisar periódicamente que las partes metálicas y los cables no se estén oxidando.
- Pintar las partes metálicas para que no se oxiden (péndolas de acero liso).
- Para evitar la corrosión de los cable de acero se debe realizar un engrasado o
lubricación periódica, así se evita en parte la oxidación (preferentemente cables
que no son galvanizados).
- Antes de la aplicación de lubricante hay que eliminar al máximo el polvo y material
abrasivo sobre la superficie del cable, inmediatamente después de la limpieza hay
que aplicar el lubricante.
- Verificar que el carro de dilatación este en su posición de diseño, en caso este
desalineado su posición se debe corregir.
- Engrasar la base del carro de dilatación para que se deslice libremente el rodillo.
- Se debe evitar que el cable de acero sufra de rozamiento alguno que afecte su
estructura o diámetro.

Especificaciones Tecnicas
20
Memoria de Calculos
Memoria de Calculo
“MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA Y SANTA ISABEL
Proyecto
DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578
Localidad Union Palaycca
Distrito San Pedro
Provincia Lucanas
Tema Pase Aereo N°2 - L=50.00m
Elaborado por
Fecha 23/07/2021

DISEÑO DE PASE AEREO A DESNIVEL L=50 m

DATOS A INGRESAR PARA EL DISEÑO DATOS


Longitud del Pase Aereo LP 50 m f'c 210 kg/cm2
Desnivel 2 m F'y 4200 kg/cm2
Diametro de la tuberia de agua Dtub 6 " Rec. col. 3 cm
Material de la tuberia de agua HDPE Rec. Zap 7 cm
Separacion entre pendolas Sp 1 m Cap. Port. St 2 kg/cm2
Velocidad del viento Vi 60 Km/h γs Suelo 1700 kg/m3
Factor de Zona sismica Z 0.45 Zona 4 γC° Concreto Armado 2400 kg/m3
γC° Concreto Simple 2300 kg/m3
Ø 18 °

FLECHA DEL CABLE (Fc) ALTURA DE LA TORRRE DE SUSPENSION


Tramo 1 = 38.0 m. Altura debajo de la Tuberia 0.1 m.
Tramo 2 = 12.0 m. Altura Minima de la Tuberia a la Pendula 1.0 m.
Fc 1 = 2.5 m. Altura de Profundización Para Cimentación Torre 1 1.0 m.
Fc 2 = 1.2 m. Altura de Profundización Para Cimentación Torre 2 1.8 m.
Altura de Columna N° 01 3.1 m.
Altura de Columna N° 02 4.8 m.

3.1 m
Fc 1 = 2.52m

1.20

Fc 2 = 1.2m

1.0 m
4.8 m

38.0 m 12.0 m

LP = 50 m

A.- DISEÑO DE PENDOLAS Y CABLE PRINCIPAL


CALCULOS DESCRIPCION

Carga Muerta (WD)


Peso de tuberia 4.58 kg/m
Peso del agua 18.2 kg/m
Peso accesorios (grapas, otros) 5.0 kg/m
WD = 27.8 kg/m
Carga Viva (WL)
Peso de una persona por tuberia kg/m
WL = 15.0 kg/m
Carga de Viento (WV))
Velocidad del viento a 20 m de altura 65.6 kg/m
Presion del viento 25.82 kg/m
WV = 3.93 kg/m

Carga Ultima (WU)


WU = 54.00 kg/m Carga Ultima (Wu)= 0.75*(1.4wd+1.7wl+1.7wv)
Factores de Seguridad
Factor de seguridad para el diseño de Péndolas 5
factor de seguridad para el diseño del cable principal 5

1/12
Memoria de Calculo
“MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA Y SANTA ISABEL
Proyecto
DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578
Localidad Union Palaycca
Distrito San Pedro
Provincia Lucanas
Tema Pase Aereo N°2 - L=50.00m
Elaborado por
Fecha 23/07/2021

A.1.- DISEÑO DE PENDOLAS


CALCULOS DESCRIPCION
Peso total de la pendola 54.0 Kg
Factor de seguridad a la tension (3 - 5) 5.0
Tension de la pendola 0.27 Ton
Se adopta Cable de 1/4 Tipo Boa ( 6x19 ) para pendolas OK!
Tension a la rotura 2.67 Ton
Cantidad de pendolas 49 Und.
Determinacion de Longitud de Pendolas

Ecuacion de la parabola y = 4f . x²/l²

Distancia al Longitud de Longitud de la


Parabola 1 Parabola 2
N° Pendolas Centro de la la pendola pendola (Y2)
Pendola N° Pendola N°
Pendola "S" (Y1) m m

Centro 0.00 1.00 1.00


Parabola 1 37 1 1 1.00 0.96 1.05
Parabola 2 12 2 2 2.00 0.93 1.11
3 3 3.00 0.90 1.20
4 4 4.00 0.87 1.29
5 5 5.00 0.84 1.41
6 6 6.00 0.82 1.54
7 7 7.00 0.81 1.69
8 8 8.00 0.79 1.85
9 9 9.00 0.78 2.04
10 10 10.00 0.77 2.23
11 11 11.00 0.77 3.29
12 12 12.00 0.77 3.68
13 13.00 0.77
14 14.00 0.78
15 15.00 0.79
16 16.00 0.81
17 17.00 0.82
18 18.00 0.85
19 19.00 0.87
20 20.00 0.90
21 21.00 0.93
22 22.00 0.96
23 23.00 1.00
24 24.00 1.05
25 25.00 1.09
26 26.00 1.14
27 27.00 1.19
28 28.00 1.25
29 29.00 1.31
30 30.00 1.37
31 31.00 1.44
32 32.00 1.51
33 33.00 1.58
34 34.00 1.66
35 35.00 1.74
36 36.00 1.82
37 37.00 1.91
38
39

Longitud Total de Péndolas 40.55 22.38 62.93

Esquema de Pase Aéreo a Desnivel


4.0

3.5

3.0

2.5

2.0 Parabola 1
1.5 Parabola 2

1.0 Lineal (Tubería)

0.5

0.0
-10.0 0.0 10.0 20.0 30.0 40.0 50.0
-0.5

-1.0

NOTA: SE DEBE EVALUAR QUE LA TUBERÍA NO QUEDE POR DEBAJO DE LA CATENARIA DEL CABLE PRINCIPAL
A.2.- DISEÑO DE CABLES PRINCIPALES
CALCULOS DESCRIPCION

Asumimos diametro 5/8 ''


Carga Muerta (WD)
Carga Muerta de la pendola (WDp) 27.8
Peso de cable pendola 0.2 kg/m
Peso de cable Principal 1.1 kg/m
WD = 29.0 kg/m
Carga Viva (WL)
Peso de una persona por tuberia kg/m

2/12
Memoria de Calculo
“MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA Y SANTA ISABEL
Proyecto
DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578
Localidad Union Palaycca
Distrito San Pedro
Provincia Lucanas
Tema Pase Aereo N°2 - L=50.00m
Elaborado por
Fecha 23/07/2021

WL = 15.0 kg/m
Carga de Viento (WV))
WV = 3.93 kg/m

Carga Ultima (WU)


WU = 55.00 kg/m
Tensiones

Tensión en Extremo Superior


Tension Horizontal (TH) 15,757.94
Tension Maxima Servico (T max.ser) 15,895.93
Tension Vertical (TV) 22,382.88

Tensión en Extremo Inferior


Tension Horizontal (TH) 3,300.00
Tension Maxima Servico (T max.ser) 3,735.65
Tension Vertical (TV) 4,984.48

Diseño de Cable
Factor de seguridad a la tension (2 -5) 1.0
Tmax.rotr = Tmax.ser x Fs 15.9 Tn > 19 OK!
Se adopta Cable de 5/8 '' Cable tipo Boa ( 6x19 )

B.- DISEÑO DE LA CAMARA DE ANCLAJE

CALCULOS DESCRIPCION

Capacidad portante admisible del terreno 2.0 kg/cm2 (verificar in situ)


Peso unitario del terreno Pu= 1700.0 kg/m3
1.20
Calidad del concreto (camara de anclaje) f´c= 175.0 kg/cm2 3.00
Angulo de friccion interna " Ø "= 18.0 °
Angulo de salida del cable principal " 0 "= 45.0 °

Et (Empuje del estrato de tierra) 2.10


Et= P.u*H^2*prof**(Tan(45-Ø/2))^2 / 2
Et = 1.9
X1 = 0.3
Tmax.ser*SEN(o) = 11.24 Ton-m
Tmax.ser*COS(o) = 11.24 Ton-m Tmax.ser*SEN(o) Tmax.ser

Wp (peso propio de la camara de anclaje)


Wp = P.u concreto*H*b*prof
Wp = 17.4 ton
b/2= d + e
0
e=b/2-d < b/3 Tmax.ser*COS(o)
d=( suma de momentos)/(suma de fuerzas verticales) 0.3 = Y1
d=Wp*b/2-Tmax,serSEN(o)*X1-Tmax,serCOS(o)*Y1 q2 W
Wp-Tmax.ser*SEN(o) q1

d= 1.873
d= 1.9 m
b =2.1

e d

b/2
e (excentricidad de la resultante de fuerzas)
e= -0.823 < b/3 = 0.7 OK !
q ( presion con que actua la estructura sobre el terreno)
q =(suma Fzas. verticales/ Area)*(1 ± 6* e/ b)

q1=[(Wp-Tmax.ser*SEN(o) )/(b*prof)]*(1+6* e/ b)
q1= -0.1318 < 2.0 kg/cm2 OK!
q2=[(Wp-Tmax.ser*SEN(o) )/(b*prof)]*(1-6* e/ b)
q2= 0.3270 < 2.0 kg/cm2 OK!

3/12
Memoria de Calculo
“MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA Y SANTA ISABEL
Proyecto
DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578
Localidad Union Palaycca
Distrito San Pedro
Provincia Lucanas
Tema Pase Aereo N°2 - L=50.00m
Elaborado por
Fecha 23/07/2021

ANALISIS DE LOS FACTORES DE SEGURIDAD

F.S.D (Factor de seguridad al deslizamiento)


F.S.D=(Fzas. estabilizadoras/ Fzas.desestabilizadoras)
F.S.D=[ (Wp -Tmax.ser*SEN(o))*U ] / [ Tmax.ser*COS(o) ] F.S.D = 0.4 < 1.75 NO CUMPLE

F.S.V (Factor de seguridad al volteo)


F.S.V=(Momentos estabilizadores/ Momentos desestabilizadores)
F.S.V= (Wp *b/2 )/ ( Tmax.ser*SEN(o)*X1+Tmax.ser*COS(o)*Y1) F.S.V = 2.7 > 1.75 OK!

C.- CIMENTACIÓN

DIMENSIONAMIENTO
TORRE N° 01
CALCULOS DESCRIPCION
Sobre carga piso 150.00 kg/m2
Profundiadad de desplante (Df) 1.00 m.
Diametro de Acero Columna 1/2 "
Calculo del peralte (ld) Ld=0.08xdbxfy/√/f´c 11.59 cm.
Altura de Zapata teorica 19.09 cm
Altura de Zapata Asumida (hc) 0.60 m
ht 0.40 m
Calculo de Presion de suelo (qm) qm = qa - gtxht - gcxhc - s/c 1.97 kg/cm2 ht = 0.40
Tension Vertical = TH*Sen (0) 15757.94 Kg Df = 1.00
Peso de la Columna 1171.8 Kg Lv
Peso sobre la columna (Ps) 16929.74 kg
Calculo de Area de Zapata
A'z = Ps A'z = 8593.77 cm2 hc = 0.60
qm T = 98.00 cm
T = Az^.5 + ( t - b ) B = 88.00 cm T = 2.00
2 B = 1.50
B = Az^.5 - ( t - b )
2 b = 0.35
Dimensiones a Usar
T = 200.00 cm
B = 150.00 cm t = 0.45
VERIFICACION POR CORTE ( Ø = 0.85 )
CALCULOS DESCRIPCION

Verificacion de la reaccion amplificada (qmu)


qmu = Pu/Az 0.79 kg/cm2 0.1
POR FLEXION T = 2.00
Diametro de Acero Zapata 5/8 "
Peralte de la zapata (dz) 51.41 cm
Lv = ( T - t ) / 2 77.50 cm B=
Vu = qmu * B * ( Lv - dz ) 78.11 1.50 n = b + dz = 86.41
Vc = 0.53 x√f 'cxBxdz 59.23
Vu ≤ Øvc Aumentar Espesor de Zapata
m = t + dz = 96.41
POR PUNSONAMIENTO
Vu = Pu - qmu * m * n 17,119.49 kg
bo = 2 xm + 2 xdz 365.65 cm
bc=t/b bc = 1.29
Vc = 0.27 x(2 + 4/bc )x √f 'c xboxdz
vc = 375,943.89 kg
Ø vc = 319,552.31 kg
Vc = 1.1 x√f 'cxboxdz vc = 299,665.42 kg
Ø vc = 254,715.61 kg
Vu ≤ Øvc OK

CALCULO DEL REFUERZO ( Ø = 0.90 )


DIRECCION LONGITUDINAL
CALCULOS DESCRIPCION
Lv = ( T - t ) / 2 77.50 cm T = 2.00
Mu = qmu x B x Lv²/2 355,894.80 kg-cm

As = Mu / ( Ø x fy x (dz - a/2 )) B= 150.00 cm


a = As x fy / ( 0.85 x f 'c x B ) d= 51.41 cm B = 1.50
a= 0.23 cm OK
As = 1.84 cm2
a= 0.23 cm
As = 1.84 cm
As mín = 0.0018 x B x d As min = 13.88 cm2 As min > As USAR As min
Diámetro Ø Separacion Area Total As
Area as cm2 Numero de varillas
As Longitudinal = 13.88 cm2 Pulg (cm) cm2
5/8 1.98 8 15 15.84 Ok

4/12
Memoria de Calculo
“MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA Y SANTA ISABEL
Proyecto
DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578
Localidad Union Palaycca
Distrito San Pedro
Provincia Lucanas
Tema Pase Aereo N°2 - L=50.00m
Elaborado por
Fecha 23/07/2021

DIRECCION TRANSVERSAL
CALCULOS DESCRIPCION
Lv = ( B - b ) / 2 57.50 cm T = 2.00
Mu = qmu x T x Lv²/2 261,211.73 kg-cm

As = Mu / ( Ø x fy x (dz - a/2 )) T= 200.00 cm


a = As x fy / ( 0.85 x f 'c x T ) d= 51.41 cm B = 1.50
a= 0.12 cm OK
As = 1.35 cm2
a= 0.12 cm
As = 1.35 cm
As mín = 0.0018 x T x d As min = 18.51 cm2 As min > As USAR As min
Diámetro Ø Separacion Area Total As
Area as cm2 Numero de varillas
As Transversal = 18.51 cm2 Pulg (cm) cm2
5/8 1.98 10 20 19.8 Ok

VERIFICACION DE LA CONEXIÓN COLUMNA - ZAPATA ( Ø = 0.70 )


CALCULOS DESCRIPCION

Resistencia al Aplastamiento Sobre la Columna


Pu = (1.4*PD+1.7PL) Pu = 23,701.63 kg
Pn = Pu/Ø Pn = 33,859.47 kg
Ac = t x b Ac = 1,575.00 cm2
Pnb = 0.85 x f 'c x Ac Pnb= 281,137.50 kg Pn < Pnb CONFORME

Resistencia en el Concreto de la Cimentación


Pu = 23,701.63 kg
Pn = Pu/Ø Pn = 33,859.47 kg
A2=T^2 x b/t A2 = 31,500,000.00 cm2
Ao = √(A2/Ac) x Ac Ao = 141.42 x Ac Usar Ao = 2 x Ac
Ao <= 2 x Aco Ao = 2.00 Ac
Pnb = 0.85 x f 'c x Ao Pnb= 562,275.00 kg Pn < Pnb CONFORME

Refuerzo Adicional Minimo


As = (Pu-ØPn)/Øfy As = 0.00 cm2
As min = 0.005 * Ac As min = 7.88 cm2
Asc = area de acero de la columna
Asc = 4Ø 1/2" Asc = 5.16 cm2 usar As min

No existe problemas de aplastamiento en la union columna - zapata y no requiere refuerzo adicional para la transmisión de cargas de un elemento a otro

TORRE N° 02
CALCULOS DESCRIPCION
Sobre carga piso 150.00 kg/m2
Profundiadad de desplante (Df) 1.80 m.
Diametro de Acero Columna 1/2 "
Calculo del peralte (ld) Ld=0.08xdbxfy/√/f´c 11.59 cm.
Altura de Zapata teorica 12.09 cm
Altura de Zapata Asumida (hc) 0.60 m
ht 1.20 m
Calculo de Presion de suelo (qm) qm = qa - gtxht - gcxhc - s/c 1.97 kg/cm2 ht = 1.20
Tension Vertical = TH*Sen (0) 3300.00 Kg Df = 1.80
Peso de la Columna 1806.84 Kg Lv
Peso sobre la columna (Ps) 5106.84 kg
Calculo de Area de Zapata
A'z = Ps A'z = 2592.30 cm2 hc = 0.60
qm T = 56.00 cm
T = Az^.5 + ( t - b ) B = 46.00 cm T = 2.20
2 B = 1.50
B = Az^.5 - ( t - b )
2 b = 0.45
Dimensiones a Usar
T = 220.00 cm
B = 150.00 cm t = 0.35
VERIFICACION POR CORTE ( Ø = 0.85 )
CALCULOS DESCRIPCION

Verificacion de la reaccion amplificada (qmu)


qmu = Pu/Az 0.22 kg/cm2 0.1
POR FLEXION T = 2.20
Diametro de Acero Zapata 5/8 "
Peralte de la zapata (dz) 58.41 cm
Lv = ( T - t ) / 2 92.50 cm B=
Vu = qmu * B * ( Lv - dz ) 26.29 1.50 n = b + dz = 103.41
Vc = 0.53 x√f 'cxBxdz 67.29
Vu ≤ Øvc OK
m = t + dz = 93.41
POR PUNSONAMIENTO
Vu = Pu - qmu * m * n 5,056.70 kg
bo = 2 xm + 2 xdz 393.65 cm
bc=t/b bc = 0.78
Vc = 0.27 x(2 + 4/bc )x √f 'c xboxdz
vc = 642,630.64 kg
Ø vc = 546,236.04 kg
Vc = 1.1 x√f 'cxboxdz vc = 366,537.47 kg
Ø vc = 311,556.85 kg
Vu ≤ Øvc OK

5/12
Memoria de Calculo
“MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA Y SANTA ISABEL
Proyecto
DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578
Localidad Union Palaycca
Distrito San Pedro
Provincia Lucanas
Tema Pase Aereo N°2 - L=50.00m
Elaborado por
Fecha 23/07/2021

CALCULO DEL REFUERZO ( Ø = 0.90 )


DIRECCION LONGITUDINAL
CALCULOS DESCRIPCION
Lv = ( T - t ) / 2 92.50 cm T = 2.00
Mu = qmu x B x Lv²/2 139,030.82 kg-cm

As = Mu / ( Ø x fy x (dz - a/2 )) B= 150.00 cm


a = As x fy / ( 0.85 x f 'c x B ) d= 58.41 cm B = 1.50
a= 0.17 cm OK
As = 0.63 cm2
a= 0.17 cm
As = 0.63 cm
As mín = 0.0018 x B x d As min = 15.77 cm2 As min > As USAR As min
Diámetro Ø Numero de varillas Separacion Area Total As
Area as cm2
As Longitudinal = 15.77 cm2 Pulg Min. (cm) cm2
5/8 1.98 8 20 15.84 Ok

DIRECCION TRANSVERSAL
CALCULOS DESCRIPCION
Lv = ( B - b ) / 2 52.50 cm T = 2.00
Mu = qmu x T x Lv²/2 65,686.73 kg-cm

As = Mu / ( Ø x fy x (dz - a/2 )) T= 220.00 cm


a = As x fy / ( 0.85 x f 'c x T ) d= 58.41 cm B = 1.50
a= 0.03 cm OK
As = 0.34 cm2
a= 0.03 cm
As = 0.30 cm
As mín = 0.0018 x T x d As min = 23.13 cm2 As min > As USAR As min
Diámetro Ø Numero de varillas Separacion Area Total As
Area as cm2
As Transversal = 23.13 cm2 Pulg Min. (cm) cm2
5/8 1.98 12 15 23.76 Ok

VERIFICACION DE LA CONEXIÓN COLUMNA - ZAPATA ( Ø = 0.70 )


CALCULOS DESCRIPCION

Resistencia al Aplastamiento Sobre la Columna


Pu = (1.4*PD+1.7PL) Pu = 7,149.58 kg
Pn = Pu/Ø Pn = 10,213.68 kg
Ac = t x b Ac = 1,575.00 cm2
Pnb = 0.85 x f 'c x Ac Pnb= 281,137.50 kg Pn < Pnb CONFORME

Resistencia en el Concreto de la Cimentación


Pu = 7,149.58 kg
Pn = Pu/Ø Pn = 10,213.68 kg
A2=T^2 x b/t A2 = 25,714.29 cm2
Ao = √(A2/Ac) x Ac Ao = 4.04 x Ac Usar Ao = 2 x Ac
Ao <= 2 x Aco Ao = 2.00 Ac
Pnb = 0.85 x f 'c x Ao Pnb= 562,275.00 kg Pn < Pnb CONFORME

Refuerzo Adicional Minimo


As = (Pu-ØPn)/Øfy As = 0.00 cm2
As min = 0.005 * Ac As min = 7.88 cm2
Asc = area de acero de la columna
Asc = 4Ø 1/2" Asc = 5.16 cm2 usar As min

No existe problemas de aplastamiento en la union columna - zapata y no requiere refuerzo adicional para la transmisión de cargas de un elemento a otro

D.- DISEÑO DE LA TORRE DE SUSPENSION

D1.- DISEÑO DE LA TORRE DE SUSPENSION N° 01 - LADO IZQUIERDO

CALCULO DE LAS FUERZAS SISMICAS POR REGLAMENTO

Factor de importancia U 1.50


Factor de suelo S 1.10 45° o o2 25°
Coeficiente sismico C 2.50
Factor de ductilidad Rd 8.00
Factor de Zona Z 0.45
Angulo de salida del cable
Torre-camara o 45.0 °
Angulo de salida del cable (valor de comparacion =arctan(2*Fc/LP)
Torre-Puente o2 25.0 ° 7.59 °

6/12
Memoria de Calculo
“MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA Y SANTA ISABEL
Proyecto
DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578
Localidad Union Palaycca
Distrito San Pedro
Provincia Lucanas
Tema Pase Aereo N°2 - L=50.00m
Elaborado por
Fecha 23/07/2021

DIMENSIONAMIENTO DEL TORREON

0.35 Fs3 =0.14


0.45
, Ht/3
Fs2 =0.09
Ht = 3.10
Ht/3 Ht= 3.1

Fs1 =0.05

Ht/3

2.00 0.60 Fs =0.27

1.50

Nivel hi wixhi Fs ( i )
3 3.1 2.42172 0.14 Ton
2 2.1 1.61 0.09 Ton
1 1.0 0.81 0.05 Ton
4.84344
Fs = (S.U.C.Z / Rd )*Peso de toda la estructura Fs (fuerza sismica total en la base)
Fs = 0.27 Ton

ANALISIS DE ESTABILIDAD

Tmax.ser*SEN(o2)= 6.7 Ton-m


Tmax.ser*COS(o2)= 14.4 Ton-m
Tmax.ser*SEN(o)= 11.2 Ton-m
Tmax.ser*COS(o)= 11.2 Ton-m Tmax.ser *COS(o) Tmax.ser *COS(o2)

Wp (peso propio de la torre-zapata)


Wp=P.u concreto*volumen total Tmax.ser*SEN(o) Tmax.ser *SEN(o2)
Wp= 1.2 ton
Wz= 4.3 ton

b/2= d + e
Wp
e=b/2-d < b/3
d=( suma de momentos)/(suma de fuerzas verticales)

d = (Wp*2b/3+Wz*b/2+Tmax.ser*SEN(o2)*2b/3+Tmax.ser*SEN(o)*2b/3-[ Tmax.ser*COS(o2)-
Tmax.ser*COS(o) ]*(H+hz)-Fs3*(H+hz)-Fs2*2*(H+hz)/3-Fs1*(H+hz)/3) /
(Wp+Wz+Tmax.ser*SEN(o)+Tmax.ser*SEN(o2))

q2 q1
d = 0.7 m

e (excentricidad de la resultante de fuerzas)


e = 0.264 < b/3 = 0.7 OK !

b =2
q ( presion con que actua la estructura sobre el terreno) e d
q =(suma Fzas. verticales/ Area)*(1+ 6* e/ b)
q1=[(Wp+Wz+Tmax.ser*SEN(o2)+Tmax.ser*SEN(o) ))/ (b*prof)]*(1+6* e/ b) b/2
q1= 1.40 < 2.0 kg/cm2 OK!
q2=[(Wp+Wz+Tmax.ser*SEN(o2)+Tmax.ser*SEN(o) ))/ (b*prof)]*(1-6* e/ b)
q2= 0.16 < 2.0 kg/cm2 OK!
ANALISIS DE LOS FACTORES DE SEGURIDAD

F.S.D (Factor de seguridad al deslizamiento)


F.S.D=(Fzas. estabilizadoras/ Fzas.desestabilizadoras)
F.S.D= [ (Wp+Wz +Tmax.ser*SEN(o2)+Tmax.ser*SEN(o))*U ]
[Tmax.ser*COS(o2)- Tmax.ser*COS(o) +Fs3+Fs2+Fs1 ]
F.S.D= 3.4 > 1.5 OK!

F.S.V (Factor de seguridad al volteo)


F.S.V=(Momentos estabilizadores/ Momentos desestabilizadores)
F.S.V= Wp*2b/3+Wz*b/2+ Tmax.ser*SEN(o2)*2b/3+Tmax.ser*SEN(o)*2b/3
(Tmax.ser*COS(o2)*(Ht+hz)-Tmax.ser*COS(o)*(Ht+hz)+Fs3*(Ht+hz)+Fs2*(2*Ht/3+hz)+Fs1*(Ht/3+hz))
F.S.V= 2.4 > 1.75 OK!

7/12
Memoria de Calculo
“MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA Y SANTA ISABEL
Proyecto
DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578
Localidad Union Palaycca
Distrito San Pedro
Provincia Lucanas
Tema Pase Aereo N°2 - L=50.00m
Elaborado por
Fecha 23/07/2021

DISEÑO ESTRUCTURAL DE LA TORRE DE SUSPENSION

Tmax.rot *COS(o) Tmax.rot *COS(o2)

Tmax.rot *SEN(o) Tmax.rot *SEN(o2)

3.1
Wp
A A

0.45
0.35

DISEÑO POR METODO A LA ROTURA


(por columna y en voladizo)

Tmax.rot/columna=1.5*Tmax.ser/columna Tmax.ser = 15.90 Ton-m Tmax.rot = 23.84 Ton-m


Mu=( Tmax.rot*COS(o2)-Tmax.rot*COS(o))*Ht+Fs3*Ht+Fs2*Ht*2/3+Fs1*Ht/3
Mu = 8.03 Ton-m

DISEÑO DE LA COLUMNA A FLEXION

f 'c= 210 kg/cm2


Fy= 4200 kg/cm2
b= 35 cm
Ø Asum.= 1/2 " d = 41.37
rec. Colm.= 3.00 cm
d= 41.37 cm
MU= 8.03 Ton-m
CORTE A-A
w= 0.07 &= 0.004 < 75&b = 0.016 ( FALLA DUCTIL )
As(cm2)= 5.37 cm2
As min= 4.8 cm2
As principal(+) = 5.37 cm2

Diámetro Ø Area Total As


Area as cm2 Cantidad de varillas
Pulg cm2

1/2 1.27 3 3.81 B Cal B asum


1/2 1.27 3 3.81 21.49 35 Ok
TOTAL 7.62 Ok

DISEÑO DE LA COLUMNA A COMPRESION

Pn(max) [carga axial maxima resistente]

Pn(max)=0.80*(0.85*f¨c*(b*h-Ast)+Ast*fy) Pn(max)= 242 Ton


Tmax.rot/columna=1.7*Tmax.ser/columna
Pu [carga axial ultima actuante]
Pu=Wp + Tmax.rot*SEN(o2)+Tmax.rot*SEN(o) Pu= 47 Ton
Pu= 47.0 Ton < Pn(max)= 242.0 Ton OK !
DISEÑO DE LA COLUMNA POR CORTE

Tmax.rot/columna=1.5*Tmax.ser/columna
VU (cortante ultimo)
Vu= Tmax.rot*COS(o2)-Tmax.rot*COS(o)+Fs3+Fs2+Fs1

Vu= 5.0 Ton


Vcon= fi*(0,5*(f´c)^0,5+175*&*Vu*d/Mu
V que absorve el concreto => Vcon= 9 Ton
V que absorve acero = Vace= Vu - Vcon= Vace= -4.5 Ton NO REQUIERE REFUERZO POR CORTE
ADOPTE EL MINIMO
Diametro de Acero para estribo Ø 3/8
S= Av*fy*b/Vace
S= 25 cm

SE ADOPTARA S= 25 cm VAR. 3/8"

D2.- DISEÑO DE LA TORRE DE SUSPENSION N° 02- LADO DERECHO

CALCULO DE LAS FUERZAS SISMICAS POR REGLAMENTO

Factor de importancia U 1.50


Factor de suelo S 1.10 45° o o2 12°
Coeficiente sismico C 2.50
Factor de ductilidad Rd 8.00
Factor de Zona Z 0.45
Angulo de salida del cable
Torre-camara o 45.00 °
Angulo de salida del cable (valor de comparacion =arctan(2*Fc/LP)
Torre-Puente o2 12.0 ° 11.44 °

8/12
Memoria de Calculo
“MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA Y SANTA ISABEL
Proyecto
DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578
Localidad Union Palaycca
Distrito San Pedro
Provincia Lucanas
Tema Pase Aereo N°2 - L=50.00m
Elaborado por
Fecha 23/07/2021

DIMENSIONAMIENTO DEL TORREON

0.35 Fs3 =0.21


0.45
, Ht/3
Fs2 =0.14
Ht = 4.78
Ht/3 Ht= 4.8

Fs1 =0.07

Ht/3

2.20 0.60 Fs =0.42

1.50

Nivel hi wixhi Fs ( i )
3 4.8 5.76 0.21 Ton
2 3.2 3.84 0.14 Ton
1 1.6 1.92 0.07 Ton
11.5155936
Fs = (S.U.C.Z / Rd )*Peso de toda la estructura Fs (fuerza sismica total en la base)
Fs = 0.42 Ton

ANALISIS DE ESTABILIDAD

Tmax.ser*SEN(o2)= 0.8 Ton-m


Tmax.ser*COS(o2)= 3.7 Ton-m
Tmax.ser*SEN(o)= 2.6 Ton-m
Tmax.ser*COS(o)= 2.6 Ton-m Tmax.ser *COS(o) Tmax.ser *COS(o2)

Wp (peso propio de la torre-zapata)


Wp=P.u concreto*volumen total Tmax.ser*SEN(o) Tmax.ser *SEN(o2)
Wp= 1.8 ton
Wz= 4.8 ton

b/2= d + e
e=b/2-d < b/3 Wp
d=( suma de momentos)/(suma de fuerzas verticales)

d = (Wp*2b/3+Wz*b/2+Tmax.ser*SEN(o2)*2b/3+Tmax.ser*SEN(o)*2b/3-[ Tmax.ser*COS(o2)-
Tmax.ser*COS(o) ]*(H+hz)-Fs3*(H+hz)-Fs2*2*(H+hz)/3-Fs1*(H+hz)/3) /
(Wp+Wz+Tmax.ser*SEN(o)+Tmax.ser*SEN(o2))

q2 q1
d = 0.6 m

e (excentricidad de la resultante de fuerzas)


e = 0.536 < b/3 = 0.7 OK !

b =2.2
q ( presion con que actua la estructura sobre el terreno) e d
q =(suma Fzas. verticales/ Area)*(1+ 6* e/ b)
q1=[(Wp+Wz+Tmax.ser*SEN(o2)+Tmax.ser*SEN(o) ))/ (b*prof)]*(1+6* e/ b) b/2
q1= 0.70 < 2.0 kg/cm2 OK!
q2=[(Wp+Wz+Tmax.ser*SEN(o2)+Tmax.ser*SEN(o) ))/ (b*prof)]*(1-6* e/ b)
q2= -0.14 < 2.0 kg/cm2 OK!
ANALISIS DE LOS FACTORES DE SEGURIDAD

F.S.D (Factor de seguridad al deslizamiento)


F.S.D=(Fzas. estabilizadoras/ Fzas.desestabilizadoras)
F.S.D= [ (Wp+Wz +Tmax.ser*SEN(o2)+Tmax.ser*SEN(o))*U ]
[Tmax.ser*COS(o2)- Tmax.ser*COS(o) +Fs3+Fs2+Fs1 ]
F.S.D= 3.5 > 1.5 OK!

F.S.V (Factor de seguridad al volteo)


F.S.V=(Momentos estabilizadores/ Momentos desestabilizadores)
F.S.V= Wp*2b/3+Wz*b/2+ Tmax.ser*SEN(o2)*2b/3+Tmax.ser*SEN(o)*2b/3
(Tmax.ser*COS(o2)*(Ht+hz)-Tmax.ser*COS(o)*(Ht+hz)+Fs3*(Ht+hz)+Fs2*(2*Ht/3+hz)+Fs1*(Ht/3+hz))
F.S.V= 1.8 > 1.75 OK!
DISEÑO ESTRUCTURAL DE LA TORRE DE SUSPENSION

Tmax.rot *COS(o) Tmax.rot *COS(o2)

Tmax.rot *SEN(o) Tmax.rot *SEN(o2)

4.8
Wp
A A

0.45
0.35

9/12
Memoria de Calculo
“MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA Y SANTA ISABEL
Proyecto
DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578
Localidad Union Palaycca
Distrito San Pedro
Provincia Lucanas
Tema Pase Aereo N°2 - L=50.00m
Elaborado por
Fecha 23/07/2021

DISEÑO POR METODO A LA ROTURA


(por columna y en voladizo)

Tmax.rot/columna=1.5*Tmax.ser/columna Tmax.ser = 3.74 Ton-m Tmax.rot = 5.60 Ton-m


Mu=( Tmax.rot*COS(o2)-Tmax.rot*COS(o))*Ht+Fs3*Ht+Fs2*Ht*2/3+Fs1*Ht/3
Mu = 5.19 Ton-m

DISEÑO DE LA COLUMNA A FLEXION

f 'c= 210 kg/cm2


Fy= 4200 kg/cm2
b= 35 cm
Ø Asum.= 1/2 " d = 41.37
rec. Colm.= 3.00 cm
d= 41.37 cm
MU= 5.19 Ton-m
CORTE A-A
w= 0.05 &= 0.002 < 75&b = 0.016 ( FALLA DUCTIL )
As(cm2)= 3.41 cm2
As min= 4.8 cm2
As principal(+) = 4.83 cm2

Diámetro Ø Area Total As


Area as cm2 Cantidad de varillas
Pulg cm2

1/2 1.27 3 3.81 B Cal B asum


1/2 1.27 3 3.81 21.49 35 Ok
TOTAL 7.62 Ok

DISEÑO DE LA COLUMNA A COMPRESION

Pn(max) [carga axial maxima resistente]

Pn(max)=0.80*(0.85*f¨c*(b*h-Ast)+Ast*fy) Pn(max)= 240 Ton


Tmax.rot/columna=1.7*Tmax.ser/columna
Pu [carga axial ultima actuante]
Pu=Wp + Tmax.rot*SEN(o2)+Tmax.rot*SEN(o) Pu= 10.5 Ton
Pu= 10.5 Ton < Pn(max)= 240.0 Ton OK !
DISEÑO DE LA COLUMNA POR CORTE

Tmax.rot/columna=1.5*Tmax.ser/columna
VU (cortante ultimo)
Vu= Tmax.rot*COS(o2)-Tmax.rot*COS(o)+Fs3+Fs2+Fs1

Vu= 1.9 Ton


Vcon= fi*(0,5*(f´c)^0,5+175*&*Vu*d/Mu
V que absorve el concreto => Vcon= 9 Ton
V que absorve acero = Vace= Vu - Vcon= Vace= -7.6 Ton NO REQUIERE REFUERZO POR CORTE
ADOPTE EL MINIMO
Diametro de Acero para estribo Ø 3/8
S= Av*fy*b/Vace
S= 25 cm

SE ADOPTARA S= 25 cm VAR. 3/8"

RESULTADOS DE DISEÑO
DIMENSIONES DE PASE AÉREO

3.1 m
Fc 1 = 2.52m

1.2 m

Fc 2 = 1.2m

1.0 m 4.8 m

38.0 m 12.0 m

LP = 50 m

10/12
Memoria de Calculo
“MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA Y SANTA ISABEL
Proyecto
DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578
Localidad Union Palaycca
Distrito San Pedro
Provincia Lucanas
Tema Pase Aereo N°2 - L=50.00m
Elaborado por
Fecha 23/07/2021

DISEÑO DE PENDOLAS Y CABLE PRINCIPAL


Diseño de Péndolas
Peso Total de la Péndola 54.0 Kg
Cable Adoptado 1/4 '' Tipo Boa ( 6x19 ) para pendolas
Separación de Péndolas 1.00 m
Cantidad de Péndolas 49 Und.
Longitud Total de Péndolas 62.93 m

Diseño de Cables Principales


Tensión Máxima en Cable 15.90 Tn
Cable Adoptado 5/8 '' Cable tipo Boa ( 6x19 )
Tensión Máxima Admisible de Cable 19.00 Tn

DISEÑO DE CÁMARA DE ANCLAJE - PARA AMBOS EXTREMOS


Dimensiones de Cámara

1.20m
3.00m

2.10m

Concreto Hidráulico f'c= 175.0 kg/cm2


Angulo de salida del cable principal 45.0 °
Distancia de Anclaje a la Columna N°01 3.10
Distancia de Anclaje a la Columna N°02 3.58 m
Angulo de salida del cable N°01 25.00 °
Angulo de salida del cable N°02 12.00 °
DISEÑO DE TORRE Y CIMENTACIÓN

TORRE N° 01
Propiedades de los Materiales
Concreto Hidráulico f'c= 210.0 kg/cm2
Acero Grado 60 - f´y= 4200.0 kg/cm2
0.35 m
Dimensiones de Torre 0.45 m
Largo 0.45 m
Ancho 0.35 m
Altura Total de Torre 3.10 m Ht = 3.10 m

Dimensiones de Cimentación
Largo 2.00 m
Ancho 1.50 m
Altura 0.60 m
Profundidad de Desplante 1.00 m

2.00 m 0.60 m
.
1.50 m
Detalle de Armado de Acero

3 Var. ∅ 1/2 '' 3 Var. ∅ 1/2 ''

3 Var. ∅ 1/2 '' VAR. 3/8" : 1 a 5cm, 3 a 15cm, el resto @ 20cm /e


3 Var. ∅ 1/2 ''

2.7 m

3.1 m

Nivel de Terreno

VAR 3/8" @ 20cm


3 Var. ∅ 1/2 ''
3 Var. ∅ 1/2 '' 0.4 m

0.6 m Acero longitudinal en zapata ∅ 5/8 '' @ 15


Acero transversal en zapata ∅ 5/8 '' @ 20

0.775 m 0.45 m 0.775 m

11/12
Memoria de Calculo
“MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA Y SANTA ISABEL
Proyecto
DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578
Localidad Union Palaycca
Distrito San Pedro
Provincia Lucanas
Tema Pase Aereo N°2 - L=50.00m
Elaborado por
Fecha 23/07/2021

TORRE N° 02
Propiedades de los Materiales
Concreto Hidráulico f'c= 210.0 kg/cm2
Acero Grado 60 - f´y= 4200.0 kg/cm2
0.35 m
Dimensiones de Torre 0.45 m
Largo 0.45 m
Ancho 0.35 m
Altura Total de Torre 0.00 m Ht = 4.78 m

Dimensiones de Cimentación
Largo 2.20 m
Ancho 1.50 m
Altura 0.60 m
Profundidad de Desplante 1.80 m

2.20 m 0.60 m
.
1.50 m
Detalle de Armado de Acero

3 Var. ∅ 1/2 '' 3 Var. ∅ 1/2 ''

3 Var. ∅ 1/2 '' VAR. 3/8" : 1 a 5cm, 3 a 15cm, el resto @ 20cm /e


3 Var. ∅ 1/2 ''

3.58 m

4.78 m

Nivel de Terreno

VAR 3/8" @ 20cm


3 Var. ∅ 1/2 ''
3 Var. ∅ 1/2 '' 1.20

0.60 Acero longitudinal en zapata ∅ 5/8 '' @ 20


Acero transversal en zapata ∅ 5/8 '' @ 15

0.875 m 0.45 m 0.875 m

12/12
Resumen del Presupuesto
Resumen del Presupuesto

Proyecto PASES AEREOS: UNION PALAYCCA-SANTA ANA

Cliente MUNICIPALIDAD DISTRITAL DE SAN PEDRO


Departamento AYACUCHO
Provincia LUCANAS
Distrito SAN PEDRO Costo a : Agosto - 2021

Item Descripción Sub presupuesto Costo Directo

01 Obras Civiles 169,832.33

SUB TOTAL COSTO DIRECTO 169,832.33

Mano de Obra 42,920.45


Materiales 111,954.45
Equipo 14,957.43

COSTO DIRECTO 169,832.33


GASTOS GENERALES 8% 13,586.59
UTILIDAD 1.25 % 2,122.90

SUB TOTAL 185,541.82


IGV. 18 % 33,397.53

PRESUPUESTO TOTAL 218,939.35

Son : DOSCIENTOS DIECIOCHO MIL NOVECIENTOS TREINTA Y NUEVE CON 35/100 NUEVOS SOLES

P.2/23
Planilla de Sustento de Metrados
Planilla de Sustento de Metrados
Proyecto PASES AEREOS: UNION PALAYCCA-SANTA ANA
Sub Presupuesto 01 - Obras Civiles
Cliente MUNICIPALIDAD DISTRITAL DE SAN PEDRO
Ubicación SAN PEDRO - LUCANAS - AYACUCHO

Partida 01.01.01 FLETE Total : 1.00 Glb

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Flete 1.00

Partida 01.01.02 ACARREO DE MATERIAL DE CONSTRUCCION Total : 63,200.00 kg

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Acarreo de material de construccion 63,200.00

Partida 01.01.03 LIMPIEZA DE TERRENO MANUAL Total : 70.20 m2

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Limpieza de terreno manual 70.20

Partida 01.01.04 TRAZO, NIVELACION Y REPLANTEO Total : 50.59 m2

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Trazo, nivelacion y replanteo 50.59

Partida 01.02.01 EXCAVACION TERRENO NORMAL Total : 75.46 m3

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Excavacion terreno normal 75.46

Partida 01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO Total : 16.00 m3

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

RELLENO 1 1 16 16.00

Partida 01.03.01 Concreto fc=10 MPa para solados Total : 19.40 m2

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

ZAPATAS 2 2 1.1 2.10 2.10 19.40

Partida 01.03.02 CONCRETO f 'c=140 Kg/cm2 + 30% P.M P/CAMARA DE ANCLAJE Total : 39.69 m3

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

ANCLAJES 1 5 2.10 2.10 1.80 39.69

Partida 01.04.01.01 ACERO EN GENERAL fy = 4200 kg/cm2 Total : 2,402.50 KG

Descripción ø N Estr. N Elem N Var. L Varilla L Total Peso/m Peso

X1 5/8" 40 11 2.45 1,078.00 1.552 1,673.06


X2 5/8" 40 5 2.35 470.00 1.552 729.44

Resumen
ø L Total Peso/m Peso

5/8" 1,548.00 1.552 2,402.50


Partida 01.04.01.02 ENCOFRADO Y DESENCOFRADO PARA ZAPATAS RECTAS Total : 36.04 m2

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

ZAPATAS 2 4 2.80 0.85 19.04


2 4 2.50 0.85 17.00

Partida 01.04.01.03 CONCRETO f'c=210 kg/cm2 PARA ZAPATAS Total : 23.52 m3

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

ZAPATAS 2 2 1.05 2.80 2.50 0.80 23.52

Partida 01.04.02.01 ACERO EN GENERAL fy = 4200 kg/cm2 Total : 3,425.08 KG

Descripción ø N Estr. N Elem N Var. L Varilla L Total Peso/m Peso

VERTICALES 5/8" 8 4 8 6.60 1,689.60 1.552 2,622.26


ESTRIBOS 3/8" 8 4 28 1.60 1,433.60 0.560 802.82

Resumen
ø L Total Peso/m Peso

5/8" 1,689.60 1.552 2,622.26


3/8" 1,433.60 0.560 802.82

Partida 01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS Total : 112.00 m2

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

COLUMNAS 4 4 7.00 0.65 72.80


4 4 7.00 0.35 39.20

Partida 01.04.02.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 Total : 11.83 m3

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

COLUMNAS 2 4 0.65 0.35 6.50 11.83

Partida 01.04.03.01 ACERO EN GENERAL fy = 4200 kg/cm2 Total : 205.21 KG

Descripción ø N Estr. N Elem N Var. L Varilla L Total Peso/m Peso

VERTICALES 5/8" 2 4 8 1.20 76.80 1.552 119.19


ESTRIBOS 3/8" 2 4 12 1.60 153.60 0.560 86.02

Resumen
ø L Total Peso/m Peso

5/8" 76.80 1.552 119.19


3/8" 153.60 0.560 86.02

Partida 01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL Total : 1.84 m2

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Encofrado y desencofrado normal 1.84

Partida 01.04.03.03 CONCRETO f 'c=210 Kg/cm2 Total : 0.08 m3

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Concreto f 'c=210 kg/cm2 0.08

Partida 01.05.01 ACCESORIOS DE ANCLAJE FIJO P/PUENTE COLGANTE Total : 5.00 UND

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial


FIJACION 1 5 5.00

Partida 01.05.02 DISPOSITIVO DE APOYO EN COLUMNA P/PUENTE COLGANTE Total : 4.00 UND

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

APOYO 2 2 4.00

Partida 01.05.03 SUMINISTRO E INSTALACION DE CABLE TIPO BOA 6x19 5/8" Total : 124.00 m

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

CABLE 2 62.00 124.00

Partida 01.05.04 SUMINISTRO E INSTALACION DE CABLE TIPO BOA 1/4" Total : 78.00 m

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

PENDOLAS 2 39.00 78.00

Partida 01.05.05 GRAPAS ANTIDESLIZANTES 5/8" Total : 196.00 Und.

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

ANTIDESLIZANTES 2 49 2 196.00

Partida 01.05.06 ABRAZADERA SUPERIOR PARA CABLE TIPO BOA DE 5/8" Total : 84.00 Und.

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Abrazadera superior para cable tipo boa de 5/8" 84.00

Partida 01.05.07 ABRAZADERA INFERIOR PARA TUBO DE HDPE 6" Total : 96.00 Und.

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Abrazadera inferior para tubo de hdpe 6" 96.00

Partida 01.05.08 PÉNDOLAS DE ACERO 1/4" SERIE 6x19 TIPO BOA P/PUENTE COLGANTE Total : 80.00 m

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Péndolas de acero 1/4" serie 6x19 tipo boa p/puente colgante 80.00

Partida 01.05.09 PUERTA METALICA INC. PINTURA Y CERROJO (02 HOJAS) Total : 4.00 UND

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Puerta metalica inc. pintura y cerrojo (02 hojas) 4.00

Partida 01.06.01 SOLAQUEADO DE COLUMNAS Total : 34.96 m2

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Solaqueado de columnas 34.96

Partida 01.07.01 PINTURA ESMALTE EN METALICOS (INCLUYE BASE ANTICORROSIVA) Total : 30.65 m2

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Pintura esmalte en metalicos (incluye base anticorrosiva) 30.65

Partida 01.08.01 TUBERIA ESTRUCTURADA HDPE SN-2 DN 200MM Total : 108.00 M

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Tuberia estructurada hdpe sn-2 dn 200mm 108.00


Partida 01.08.02 TERMOFUSION PARA TUBERIA ESTRUCTURADA HDPE SN-2 DN 200MM Total : 10.00 Und.

Descripción N Estr. N Elem Area Largo Ancho Alto Parcial

Termofusion para tuberia estructurada hdpe sn-2 dn 200mm 10.00


Presupuesto
Proyecto PASES AEREOS: UNION PALAYCCA-SANTA ANA
Sub Presupuesto 01 - Obras Civiles
Cliente MUNICIPALIDAD DISTRITAL DE SAN PEDRO
Ubicación SAN PEDRO - LUCANAS - AYACUCHO Costo a : Agosto - 2021

Item Descripción Unidad Metrado Precio Parcial Subtotal Total

01 PASE AEREO L=44 MTS (02 Unidades) 169,832.33


01.01 OBRAS PRELIMINARES 13,845.88
01.01.01 FLETE Glb 1.00 3,600.00 3,600.00
01.01.02 ACARREO DE MATERIAL DE CONSTRUCCION kg 63,200.00 0.16 10,112.00
01.01.03 LIMPIEZA DE TERRENO MANUAL m2 70.20 1.10 77.22
01.01.04 TRAZO, NIVELACION Y REPLANTEO m2 50.59 1.12 56.66
01.02 MOVIMIENTO DE TIERRAS 3,960.81
01.02.01 EXCAVACION TERRENO NORMAL m3 75.46 38.13 2,877.29
01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 16.00 67.72 1,083.52
01.03 OBRAS DE CONCRETO SIMPLE 17,678.19
01.03.01 Concreto fc=10 MPa para solados m2 19.40 75.22 1,459.27
01.03.02 CONCRETO f 'c=140 Kg/cm2 + 30% P.M P/CAMARA DE ANCLAJE
m3 39.69 408.64 16,218.92
01.04 OBRAS DE CONCRETO ARMADO 52,378.45
01.04.01 ZAPATAS 23,115.63
01.04.01.01 ACERO EN GENERAL fy = 4200 kg/cm2 KG 2,402.50 4.96 11,916.40
01.04.01.02 ENCOFRADO Y DESENCOFRADO PARA ZAPATAS RECTAS
m2 36.04 49.61 1,787.94
01.04.01.03 CONCRETO f'c=210 kg/cm2 PARA ZAPATAS m3 23.52 400.14 9,411.29
01.04.02 COLUMNAS 28,111.60
01.04.02.01 ACERO EN GENERAL fy = 4200 kg/cm2 KG 3,425.08 4.96 16,988.40
01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS
m2 112.00 57.04 6,388.48
01.04.02.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 11.83 400.23 4,734.72
01.04.03 VIGAS 1,151.22
01.04.03.01 ACERO EN GENERAL fy = 4200 kg/cm2 KG 205.21 4.96 1,017.84
01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.84 55.08 101.35
01.04.03.03 CONCRETO f 'c=210 Kg/cm2 m3 0.08 400.40 32.03
01.05 CARPINTERIA METALICA 63,431.88
01.05.01 ACCESORIOS DE ANCLAJE FIJO P/PUENTE COLGANTE UND 5.00 1,112.46 5,562.30
01.05.02 DISPOSITIVO DE APOYO EN COLUMNA P/PUENTE COLGANTE
UND 4.00 453.30 1,813.20
01.05.03 SUMINISTRO E INSTALACION DE CABLE TIPO BOA 6x19 5/8" m 124.00 55.80 6,919.20
01.05.04 SUMINISTRO E INSTALACION DE CABLE TIPO BOA 1/4" m 78.00 49.77 3,882.06
01.05.05 GRAPAS ANTIDESLIZANTES 5/8" Und. 196.00 44.40 8,702.40
01.05.06 ABRAZADERA SUPERIOR PARA CABLE TIPO BOA DE 5/8" Und. 84.00 92.94 7,806.96
01.05.07 ABRAZADERA INFERIOR PARA TUBO DE HDPE 6" Und. 96.00 228.87 21,971.52
01.05.08 PÉNDOLAS DE ACERO 1/4" SERIE 6x19 TIPO BOA P/PUENTE COLGANTE
m 80.00 61.71 4,936.80
01.05.09 PUERTA METALICA INC. PINTURA Y CERROJO (02 HOJAS) UND 4.00 459.36 1,837.44
01.06 TARRAJEOS Y ENLUCIDOS 1,014.89
01.06.01 SOLAQUEADO DE COLUMNAS m2 34.96 29.03 1,014.89
01.07 PINTURA 1,101.87
01.07.01 PINTURA ESMALTE EN METALICOS (INCLUYE BASE ANTICORROSIVA)
m2 30.65 35.95 1,101.87
01.08 VARIOS 16,420.36
01.08.01 TUBERIA ESTRUCTURADA HDPE SN-2 DN 200MM M 108.00 123.12 13,296.96
01.08.02 TERMOFUSION PARA TUBERIA ESTRUCTURADA HDPE SN-2Und.
DN 200MM 10.00 312.34 3,123.40

COSTO DIRECTO 169,832.33


GASTOS GENERALES 8% 13,586.59
UTILIDAD 1.25 % 2,122.90

SUB TOTAL 185,541.82


IGV. 18 % 33,397.53

PRESUPUESTO TOTAL 218,939.35

Son : DOSCIENTOS DIECIOCHO MIL NOVECIENTOS TREINTA Y NUEVE CON 35/100 NUEVOS SOLES
Análisis de Costos Unitarios
Proyecto PASES AEREOS: UNION PALAYCCA-SANTA ANA
Sub Presupuesto 01 - Obras Civiles
Cliente MUNICIPALIDAD DISTRITAL DE SAN PEDRO
Ubicación SAN PEDRO - LUCANAS - AYACUCHO Costo a : Agosto - 2021

Partida 01.01.01 FLETE Rend: 1.0000 Glb/DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Materiales
32 02471 FLETE Glb 1.0000 3,600.00 3,600.00
3,600.00
Costo Unitario por Glb : 3,600.00

Partida 01.01.02 ACARREO DE MATERIAL DE CONSTRUCCION Rend: 10,000.0000 kg /DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.0002 23.50 -
47 00009 PEON HH 1.000 0.0008 16.46 0.01
0.01
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 3.0000 0.01 -
48 06866 RETROEXCAVADORA SOBRE LLANTAS 58 HP 1/2 y3 hm 1.000 0.0008 190.00 0.15
0.15
Costo Unitario por kg : 0.16

Partida 01.01.03 LIMPIEZA DE TERRENO MANUAL Rend: 140.0000 m2/DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 00007 OPERARIO HH 0.100 0.0057 22.78 0.13
47 00009 PEON HH 1.000 0.0571 16.46 0.94
1.07
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 3.0000 1.07 0.03
0.03
Costo Unitario por m2 : 1.10

Partida 01.01.04 TRAZO, NIVELACION Y REPLANTEO Rend: 900.0000 m2/DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 00086 TOPOGRAFO HH 1.000 0.0089 27.80 0.25
47 00009 PEON HH 1.000 0.0089 16.46 0.15
0.40
Materiales
30 00266 CORDEL M 0.2500 1.10 0.28
30 07416 YESO EN BOLSAS DE 25 Kg Bol 0.0020 15.20 0.03
44 01387 ESTACA DE MADERA P2 0.0100 5.20 0.05
0.36
Equipo
49 07417 NIVEL TOPOGRÁFICO hm 1.000 0.0089 40.00 0.36
0.36
Costo Unitario por m2 : 1.12

Partida 01.02.01 EXCAVACION TERRENO NORMAL Rend: 48.0000 m3/DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.0333 23.50 0.78
47 00009 PEON HH 2.000 0.3333 16.46 5.49
6.27
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 3.0000 6.27 0.19
48 06866 RETROEXCAVADORA SOBRE LLANTAS 58 HP 1/2 y3 hm 1.000 0.1667 190.00 31.67
31.86
Costo Unitario por m3 : 38.13

Partida 01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO Rend: 10.0000 m3/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.1600 23.50 3.76
47 00007 OPERARIO HH 1.000 0.8000 22.78 18.22
47 00009 PEON HH 3.000 2.4000 16.46 39.50
61.48
Materiales
01 07319 GASOLINA GLN 0.2000 16.00 3.20
3.20
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 3.0000 61.48 1.84
49 06200 COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP UND 0.1000 12.00 1.20
3.04
Costo Unitario por m3 : 67.72

Partida 01.03.01 Concreto fc=10 MPa para solados Rend: 20.0000 m2/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.0800 23.50 1.88
47 00007 OPERARIO HH 2.000 0.8000 22.78 18.22
47 00009 PEON HH 4.000 1.6000 16.46 26.34
46.44
Materiales
05 00002 AGUA m3 0.1200 1.60 0.19
21 06871 CEMENTO PORTLAND TIPO I (42.5 kg) bol 0.4500 22.50 10.13
38 00005 HORMIGON m3 0.1250 125.00 15.63
25.95
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 3.0000 46.44 1.39
48 00430 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 0.500 0.2000 7.20 1.44
2.83
Costo Unitario por m2 : 75.22

Partida 01.03.02 CONCRETO f 'c=140 Kg/cm2 + 30% P.M P/CAMARA DE ANCLAJE Rend: 25.0000 m3/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.100 0.0320 23.50 0.75
47 00007 OPERARIO HH 2.000 0.6400 22.78 14.58
47 00008 OFICIAL HH 1.000 0.3200 18.25 5.84
47 00009 PEON HH 4.000 1.2800 16.46 21.07
42.24
Materiales
05 00002 AGUA m3 0.2200 1.60 0.35
05 01399 PIEDRA MEDIANA DE 4" m3 0.5000 160.00 80.00
21 06871 CEMENTO PORTLAND TIPO I (42.5 kg) bol 6.5000 22.50 146.25
38 00005 HORMIGON m3 1.1000 125.00 137.50
364.10
Equipo
48 00430 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 1.000 0.3200 7.20 2.30
2.30
Costo Unitario por m3 : 408.64

Partida 01.04.01.01 ACERO EN GENERAL fy = 4200 kg/cm2 Rend: 250.0000 KG/DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 00007 OPERARIO HH 1.000 0.0320 22.78 0.73
47 00009 PEON HH 1.000 0.0320 16.46 0.53
1.26
Materiales
02 01401 ACERO DE REFUERZO FY=4200 KG 1.0700 3.15 3.37
02 00123 ALAMBRE NEGRO RECOCIDO # 16 KG 0.0700 4.24 0.30
3.67
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 2.0000 1.26 0.03
0.03
Costo Unitario por KG : 4.96

Partida 01.04.01.02 ENCOFRADO Y DESENCOFRADO PARA ZAPATAS RECTAS Rend: 23.0000 m2/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.100 0.0348 23.50 0.82
47 00007 OPERARIO HH 1.000 0.3478 22.78 7.92
47 00009 PEON HH 1.000 0.3478 16.46 5.72
14.46
Materiales
02 00123 ALAMBRE NEGRO RECOCIDO # 16 KG 0.1000 4.24 0.42
02 00117 ALAMBRE NEGRO RECOCIDO # 8 KG 0.1000 7.50 0.75
02 01485 CLAVOS Fo No C/C 3/4" KG 0.1500 8.60 1.29
43 00342 MADERA NACIONAL P/ENCOFRADO-CARP P2 6.0000 5.40 32.40
34.86
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 2.0000 14.46 0.29
0.29
Costo Unitario por m2 : 49.61

Partida 01.04.01.03 CONCRETO f'c=210 kg/cm2 PARA ZAPATAS Rend: 14.5000 m3/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.100 0.0552 23.50 1.30
47 00007 OPERARIO HH 1.000 0.5517 22.78 12.57
47 00008 OFICIAL HH 1.000 0.5517 18.25 10.07
47 00009 PEON HH 3.000 1.6552 16.46 27.24
51.18
Materiales
01 07319 GASOLINA GLN 0.1000 16.00 1.60
05 00002 AGUA m3 0.1800 1.60 0.29
05 00039 ARENA GRUESA m3 0.4900 145.00 71.05
05 00099 PIEDRA CHANCADA DE 1/2" m3 0.5500 142.10 78.16
21 06871 CEMENTO PORTLAND TIPO I (42.5 kg) bol 8.5000 22.50 191.25
342.35
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 3.0000 51.18 1.54
48 00430 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 1.000 0.5517 7.20 3.97
49 01489 VIBRADOR DE 3/4" - 2" CONCRETO HM 0.500 0.2759 4.00 1.10
6.61
Costo Unitario por m3 : 400.14

Partida 01.04.02.01 ACERO EN GENERAL fy = 4200 kg/cm2 Rend: 250.0000 KG/DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 00007 OPERARIO HH 1.000 0.0320 22.78 0.73
47 00009 PEON HH 1.000 0.0320 16.46 0.53
1.26
Materiales
02 01401 ACERO DE REFUERZO FY=4200 KG 1.0700 3.15 3.37
02 00123 ALAMBRE NEGRO RECOCIDO # 16 KG 0.0700 4.24 0.30
3.67
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 2.0000 1.26 0.03
0.03
Costo Unitario por KG : 4.96

Partida 01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS Rend: 15.5000 m2/DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.100 0.0516 23.50 1.21
47 00007 OPERARIO HH 1.000 0.5161 22.78 11.76
47 00008 OFICIAL HH 1.000 0.5161 18.25 9.42
22.39
Materiales
02 00117 ALAMBRE NEGRO RECOCIDO # 8 KG 0.3000 7.50 2.25
02 00118 CLAVOS PARA MADERA C/C 3" KG 0.1700 4.50 0.77
43 00342 MADERA NACIONAL P/ENCOFRADO-CARP P2 5.1600 5.40 27.86
30.88
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 3.0000 22.39 0.67
48 07431 ANDAMIO METALICO INC. PLATAFORMA hm 1.000 0.5161 6.00 3.10
3.77
Costo Unitario por m2 : 57.04

Partida 01.04.02.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 Rend: 25.0000 m3/DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.100 0.0320 23.50 0.75
47 00007 OPERARIO HH 2.000 0.6400 22.78 14.58
47 00008 OFICIAL HH 1.000 0.3200 18.25 5.84
47 00009 PEON HH 4.500 1.4400 16.46 23.70
44.87
Materiales
01 07319 GASOLINA GLN 0.1000 16.00 1.60
05 00002 AGUA m3 0.1840 1.60 0.29
05 00039 ARENA GRUESA m3 0.6000 145.00 87.00
05 00099 PIEDRA CHANCADA DE 1/2" m3 0.5500 142.10 78.16
21 06871 CEMENTO PORTLAND TIPO I (42.5 kg) bol 8.1500 22.50 183.38
350.43
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 3.0000 44.87 1.35
48 00430 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 1.000 0.3200 7.20 2.30
49 01489 VIBRADOR DE 3/4" - 2" CONCRETO HM 1.000 0.3200 4.00 1.28
4.93
Costo Unitario por m3 : 400.23

Partida 01.04.03.01 ACERO EN GENERAL fy = 4200 kg/cm2 Rend: 250.0000 KG/DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 00007 OPERARIO HH 1.000 0.0320 22.78 0.73
47 00009 PEON HH 1.000 0.0320 16.46 0.53
1.26
Materiales
02 01401 ACERO DE REFUERZO FY=4200 KG 1.0700 3.15 3.37
02 00123 ALAMBRE NEGRO RECOCIDO # 16 KG 0.0700 4.24 0.30
3.67
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 2.0000 1.26 0.03
0.03
Costo Unitario por KG : 4.96

Partida 01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL Rend: 16.0000 m2/DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 00007 OPERARIO HH 1.000 0.5000 22.78 11.39
47 00008 OFICIAL HH 1.000 0.5000 18.25 9.13
47 00009 PEON HH 2.000 1.0000 16.46 16.46
36.98
Materiales
02 00123 ALAMBRE NEGRO RECOCIDO # 16 KG 0.2500 4.24 1.06
02 02069 CLAVOS PARA MADERA C/C 2" KG 0.2500 4.50 1.13
02 00118 CLAVOS PARA MADERA C/C 3" KG 0.1500 4.50 0.68
43 06994 LISTONES DE MADERA 2"x3"x8' u 0.0800 14.20 1.14
43 07053 TABLAS 1"x12"x10' u 0.6800 18.00 12.24
16.25
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 5.0000 36.98 1.85
1.85
Costo Unitario por m2 : 55.08

Partida 01.04.03.03 CONCRETO f 'c=210 Kg/cm2 Rend: 16.0000 m3/DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 00007 OPERARIO HH 1.000 0.5000 22.78 11.39
47 00008 OFICIAL HH 1.000 0.5000 18.25 9.13
47 00009 PEON HH 5.000 2.5000 16.46 41.15
61.67
Materiales
05 00002 AGUA m3 0.1850 1.60 0.30
05 00039 ARENA GRUESA m3 0.5200 145.00 75.40
05 00099 PIEDRA CHANCADA DE 1/2" m3 0.5400 142.10 76.73
21 06871 CEMENTO PORTLAND TIPO I (42.5 kg) bol 8.2000 22.50 184.50
336.93
Equipo
48 00430 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 0.500 0.2500 7.20 1.80
1.80
Costo Unitario por m3 : 400.40

Partida 01.05.01 ACCESORIOS DE ANCLAJE FIJO P/PUENTE COLGANTE Rend: 4.0000 UND/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.100 0.2000 23.50 4.70
47 00007 OPERARIO HH 1.000 2.0000 22.78 45.56
47 00008 OFICIAL HH 1.000 2.0000 18.25 36.50
47 00009 PEON HH 1.000 2.0000 16.46 32.92
119.68
Materiales
02 07486 BARRA DE ACERO TIPO "U" C/SOCKET CONICO DE ANCLAJE
Und. 1.0000 560.00 560.00
02 02368 PERNOS DE 1/2" x 1.80 m UND 4.0000 36.00 144.00
02 04634 RIEL DE FERROCARRIL TIPO T1 M 1.2000 224.00 268.80
02 02369 TUERCAS DE ACERO DE 1/2" UND 4.0000 3.50 14.00
986.80
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 5.0000 119.68 5.98
5.98
Costo Unitario por UND : 1,112.46

Partida 01.05.02 DISPOSITIVO DE APOYO EN COLUMNA P/PUENTE COLGANTE Rend: 2.0000 UND/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.100 0.4000 23.50 9.40
47 00007 OPERARIO HH 1.000 4.0000 22.78 91.12
47 00008 OFICIAL HH 1.000 4.0000 18.25 73.00
47 00009 PEON HH 1.000 4.0000 16.46 65.84
239.36
Materiales
02 02375 PERNO EN "U" DE 5/8" x 0.60 UND 2.0000 16.20 32.40
02 02374 TUERCA DE 5/8" UND 4.0000 3.50 14.00
29 02371 SOLDADURA CELLOCORD P (AWS E6010) 3/16" KG 0.9000 25.30 22.77
51 02376 PLATINA F.N. 1" x 3/8" x 20' PZA 0.1373 16.00 2.20
57 02377 PLANCHA NEGRA LAC DE 1/2" x 4' x 8' UND 0.0416 1,680.00 69.89
57 02372 PLANCHA NEGRA LAC DE 5/8" x 4' x 8' UND 0.0243 2,235.00 54.31
195.57
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 5.0000 239.36 11.97
48 00464 MAQUINA SOLDADORA HM 0.200 0.8000 8.00 6.40
18.37
Costo Unitario por UND : 453.30

Partida 01.05.03 SUMINISTRO E INSTALACION DE CABLE TIPO BOA 6x19 5/8" Rend: 60.0000 m/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.100 0.0133 23.50 0.31
47 00007 OPERARIO HH 2.000 0.2667 22.78 6.08
47 00009 PEON HH 3.000 0.4000 16.46 6.58
12.97
Materiales
30 02380 CABLE DE 5/8", 6x19, CON ALMA DE ACERO GALVANIZADO M 1.0200 39.00 39.78
39.78
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 5.0000 12.97 0.65
48 07469 TIRFOR DE 3 TON HM 1.000 0.1333 18.00 2.40
3.05
Costo Unitario por m : 55.80

Partida 01.05.04 SUMINISTRO E INSTALACION DE CABLE TIPO BOA 1/4" Rend: 44.0000 m/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.100 0.0182 23.50 0.43
47 00007 OPERARIO HH 2.000 0.3636 22.78 8.28
47 00009 PEON HH 3.000 0.5455 16.46 8.98
17.69
Materiales
30 07470 CABLE DE ACERO DE 1/4", TIPO BOA / SERIE 6x19 m 1.0500 26.60 27.93
27.93
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 5.0000 17.69 0.88
48 07469 TIRFOR DE 3 TON HM 1.000 0.1818 18.00 3.27
4.15
Costo Unitario por m : 49.77
Partida 01.05.05 GRAPAS ANTIDESLIZANTES 5/8" Rend: 15.0000 Und./DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.1067 23.50 2.51
47 00007 OPERARIO HH 1.000 0.5333 22.78 12.15
47 00009 PEON HH 0.500 0.2667 16.46 4.39
19.05
Materiales
02 02370 GRAPAS CROSBY DE 5/8" UND 1.0000 12.40 12.40
71 02393 ABRAZADERAS DE Fo.Fo. 6" PZA 1.0000 12.00 12.00
24.40
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 5.0000 19.05 0.95
0.95
Costo Unitario por Und. : 44.40

Partida 01.05.06 ABRAZADERA SUPERIOR PARA CABLE TIPO BOA DE 5/8" Rend: 10.0000 Und./DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.1600 23.50 3.76
47 00007 OPERARIO HH 1.000 0.8000 22.78 18.22
47 00008 OFICIAL HH 2.000 1.6000 18.25 29.20
51.18
Materiales
02 02378 PERNO DE 1/2" x 2' UND 1.0000 8.30 8.30
02 02369 TUERCAS DE ACERO DE 1/2" UND 1.0000 3.50 3.50
29 02371 SOLDADURA CELLOCORD P (AWS E6010) 3/16" KG 0.1500 25.30 3.80
71 07484 ABRAZADERAS C/PLATINA DE 1/4"x6mmx32mm Und. 1.0000 23.60 23.60
39.20
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 5.0000 51.18 2.56
2.56
Costo Unitario por Und. : 92.94

Partida 01.05.07 ABRAZADERA INFERIOR PARA TUBO DE HDPE 6" Rend: 20.0000 Und./DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.0800 23.50 1.88
47 00007 OPERARIO HH 1.000 0.4000 22.78 9.11
47 00008 OFICIAL HH 2.000 0.8000 18.25 14.60
25.59
Materiales
02 02378 PERNO DE 1/2" x 2' UND 2.0000 8.30 16.60
02 02369 TUERCAS DE ACERO DE 1/2" UND 2.0000 3.50 7.00
71 07485 ABRAZADERAS C/PLATINA DE 1/4"x6mmx400mm Und. 2.0000 89.20 178.40
202.00
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 5.0000 25.59 1.28
1.28
Costo Unitario por Und. : 228.87

Partida 01.05.08 PÉNDOLAS DE ACERO 1/4" SERIE 6x19 TIPO BOA P/PUENTE COLGANTE Rend: 20.0000 m/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.0800 23.50 1.88
47 00007 OPERARIO HH 1.000 0.4000 22.78 9.11
47 00008 OFICIAL HH 2.000 0.8000 18.25 14.60
47 00009 PEON HH 1.000 0.4000 16.46 6.58
32.17
Materiales
30 07470 CABLE DE ACERO DE 1/4", TIPO BOA / SERIE 6x19 m 1.0500 26.60 27.93
27.93
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 5.0000 32.17 1.61
1.61
Costo Unitario por m : 61.71

Partida 01.05.09 PUERTA METALICA INC. PINTURA Y CERROJO (02 HOJAS) Rend: 2.0000 UND/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.8000 23.50 18.80
18.80
Materiales
63 07483 PUERTA METALICA INC. PINTURA ESMALTE Und. 1.0000 440.00 440.00
440.00
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 3.0000 18.80 0.56
0.56
Costo Unitario por UND : 459.36

Partida 01.06.01 SOLAQUEADO DE COLUMNAS Rend: 10.0000 m2/DIA


Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.1600 23.50 3.76
47 00007 OPERARIO HH 1.000 0.8000 22.78 18.22
21.98
Materiales
04 00033 ARENA FINA m3 0.0180 190.00 3.42
05 00002 AGUA m3 0.1800 1.60 0.29
21 06871 CEMENTO PORTLAND TIPO I (42.5 kg) bol 0.1190 22.50 2.68
6.39
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 3.0000 21.98 0.66
0.66
Costo Unitario por m2 : 29.03

Partida 01.07.01 PINTURA ESMALTE EN METALICOS (INCLUYE BASE ANTICORROSIVA) Rend: 12.0000 m2/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.1333 23.50 3.13
47 00007 OPERARIO HH 1.000 0.6667 22.78 15.19
47 00008 OFICIAL HH 0.200 0.1333 18.25 2.43
20.75
Materiales
53 00480 THINER GLN 0.0400 29.00 1.16
54 00068 PINTURA ANTICORROSIVA GLN 0.0300 45.00 1.35
54 00606 PINTURA ESMALTE SINTETICO GLN 0.0300 55.00 1.65
4.16
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 5.0000 20.75 1.04
49 03945 COMPRESORA DE AIRE MAS PISTOLA HM 1.000 0.6667 15.00 10.00
11.04
Costo Unitario por m2 : 35.95

Partida 01.08.01 TUBERIA ESTRUCTURADA HDPE SN-2 DN 200MM Rend: 40.0000 M/DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.0400 23.50 0.94
47 00007 OPERARIO HH 2.000 0.4000 22.78 9.11
47 00009 PEON HH 10.000 2.0000 16.46 32.92
42.97
Materiales
72 07478 TUBERIA ESTRUCTURADA HDPE SN-2 DN 200MM m 1.0000 78.00 78.00
78.00
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 5.0000 42.97 2.15
2.15
Costo Unitario por M : 123.12

Partida 01.08.02 TERMOFUSION PARA TUBERIA ESTRUCTURADA HDPE SN-2 DN 200MM Rend: 8.0000 Und./DIA
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio Parcial
Mano de Obra
47 07378 MAESTRO DE OBRA HH 0.200 0.2000 23.50 4.70
47 00007 OPERARIO HH 1.000 1.0000 22.78 22.78
47 00009 PEON HH 10.000 10.0000 16.46 164.60
192.08
Materiales
29 07480 SOLDADURA PARA TERMOFUSION KG 1.3000 65.00 84.50
29 07479 SUMINISTRO DE EQUIPO DE TERMOFUSION HM 1.0000 30.00 30.00
114.50
Equipo
37 00004 HERRAMIENTAS MANUALES %MO 3.0000 192.08 5.76
5.76
Costo Unitario por Und. : 312.34
Listado de Insumos
Listado de Insumos
Proyecto PASES AEREOS: UNION PALAYCCA-SANTA ANA
Sub Presupuesto 01 - Obras Civiles
Cliente MUNICIPALIDAD DISTRITAL DE SAN PEDRO
Ubicación SAN PEDRO - LUCANAS - AYACUCHO Costo a : Agosto - 2021

IU Código Descripción Unidad Cantidad Precio Parcial

MANO DE OBRA
47 07378 MAESTRO DE OBRA HH 93.70 23.50 2,201.95
47 00086 TOPOGRAFO HH 0.45 27.80 12.51
47 00007 OPERARIO HH 770.55 22.78 17,553.13
47 00008 OFICIAL HH 393.51 18.25 7,181.56
47 00009 PEON HH 970.31 16.46 15,971.30
42,920.45
MATERIALES
01 07319 GASOLINA GLN 6.73 16.00 107.68
02 01401 ACERO DE REFUERZO FY=4200 KG 6,457.77 3.15 20,341.98
02 00123 ALAMBRE NEGRO RECOCIDO # 16 KG 428.35 4.24 1,816.20
02 00117 ALAMBRE NEGRO RECOCIDO # 8 KG 37.21 7.50 279.08
02 07486 BARRA DE ACERO TIPO "U" C/SOCKET CONICO DE ANCLAJE Und. 5.00 560.00 2,800.00
02 01485 CLAVOS Fo No C/C 3/4" KG 5.40 8.60 46.44
02 02069 CLAVOS PARA MADERA C/C 2" KG 0.46 4.50 2.07
02 00118 CLAVOS PARA MADERA C/C 3" KG 19.34 4.50 87.03
02 02370 GRAPAS CROSBY DE 5/8" UND 196.01 12.40 2,430.52
02 02378 PERNO DE 1/2" x 2' UND 276.00 8.30 2,290.80
02 02375 PERNO EN "U" DE 5/8" x 0.60 UND 8.00 16.20 129.60
02 02368 PERNOS DE 1/2" x 1.80 m UND 20.00 36.00 720.00
02 04634 RIEL DE FERROCARRIL TIPO T1 M 6.00 224.00 1,344.00
02 02374 TUERCA DE 5/8" UND 16.00 3.50 56.00
02 02369 TUERCAS DE ACERO DE 1/2" UND 295.99 3.50 1,035.97
04 00033 ARENA FINA m3 0.63 190.00 119.70
05 00002 AGUA m3 23.78 1.60 38.05
05 00039 ARENA GRUESA m3 18.66 145.00 2,705.70
05 00099 PIEDRA CHANCADA DE 1/2" m3 19.49 142.10 2,769.53
05 01399 PIEDRA MEDIANA DE 4" m3 19.84 160.00 3,174.40
21 06871 CEMENTO PORTLAND TIPO I (42.5 kg) bol 567.87 22.50 12,777.08
29 02371 SOLDADURA CELLOCORD P (AWS E6010) 3/16" KG 16.20 25.30 409.86
29 07480 SOLDADURA PARA TERMOFUSION KG 13.00 65.00 845.00
29 07479 SUMINISTRO DE EQUIPO DE TERMOFUSION HM 10.00 30.00 300.00
30 02380 CABLE DE 5/8", 6x19, CON ALMA DE ACERO GALVANIZADO M 126.48 39.00 4,932.72
30 07470 CABLE DE ACERO DE 1/4", TIPO BOA / SERIE 6x19 m 165.90 26.60 4,412.94
30 00266 CORDEL M 12.75 1.10 14.03
30 07416 YESO EN BOLSAS DE 25 Kg Bol 0.11 15.20 1.67
32 02471 FLETE Glb 1.00 3,600.00 3,600.00
38 00005 HORMIGON m3 46.08 125.00 5,760.00
43 06994 LISTONES DE MADERA 2"x3"x8' u 0.15 14.20 2.13
43 00342 MADERA NACIONAL P/ENCOFRADO-CARP P2 794.17 5.40 4,288.52
43 07053 TABLAS 1"x12"x10' u 1.25 18.00 22.50
44 01387 ESTACA DE MADERA P2 0.53 5.20 2.76
51 02376 PLATINA F.N. 1" x 3/8" x 20' PZA 0.55 16.00 8.80
53 00480 THINER GLN 1.23 29.00 35.67
54 00068 PINTURA ANTICORROSIVA GLN 0.92 45.00 41.40
54 00606 PINTURA ESMALTE SINTETICO GLN 0.92 55.00 50.60
57 02377 PLANCHA NEGRA LAC DE 1/2" x 4' x 8' UND 0.17 1,680.00 285.60
57 02372 PLANCHA NEGRA LAC DE 5/8" x 4' x 8' UND 0.10 2,235.00 223.50
63 07483 PUERTA METALICA INC. PINTURA ESMALTE Und. 4.00 440.00 1,760.00
71 07484 ABRAZADERAS C/PLATINA DE 1/4"x6mmx32mm Und. 84.00 23.60 1,982.40
71 07485 ABRAZADERAS C/PLATINA DE 1/4"x6mmx400mm Und. 192.00 89.20 17,126.40
71 02393 ABRAZADERAS DE Fo.Fo. 6" PZA 196.01 12.00 2,352.12
72 07478 TUBERIA ESTRUCTURADA HDPE SN-2 DN 200MM m 108.00 78.00 8,424.00
111,954.45
EQUIPO
37 00004 HERRAMIENTAS MANUALES %MO 1,619.57
48 07431 ANDAMIO METALICO INC. PLATAFORMA hm 57.82 6.00 346.92
48 00464 MAQUINA SOLDADORA HM 3.20 8.00 25.60
48 00430 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 33.36 7.20 240.19
48 06866 RETROEXCAVADORA SOBRE LLANTAS 58 HP 1/2 y3 hm 62.04 190.00 11,787.60
48 07469 TIRFOR DE 3 TON HM 30.71 18.00 552.78
49 06200 COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP UND 1.60 12.00 19.20
49 03945 COMPRESORA DE AIRE MAS PISTOLA HM 20.43 15.00 306.45
49 07417 NIVEL TOPOGRÁFICO hm 0.45 40.00 18.00
49 01489 VIBRADOR DE 3/4" - 2" CONCRETO HM 10.28 4.00 41.12
14,957.43

COSTO DIRECTO 169,832.33


GASTOS GENERALES 8% 13,586.59
UTILIDAD 1.25 % 2,122.90

SUB TOTAL 185,541.82


IGV. 18 % 33,397.53

PRESUPUESTO TOTAL 218,939.35

Son : DOSCIENTOS DIECIOCHO MIL NOVECIENTOS TREINTA Y NUEVE CON 35/100 NUEVOS SOLES
Desagregado de Gastos Generales
Desagregado de Gastos Generales
Proyecto PASES AEREOS: UNION PALAYCCA-SANTA ANA
Cliente MUNICIPALIDAD DISTRITAL DE SAN PEDRO
Ubicación SAN PEDRO - LUCANAS - AYACUCHO Costo a : Agosto - 2021

COSTO DIRECTO 169,832.33

GASTOS GENERALES 8% 13,586.59

UTILIDAD 1.25 % 2,122.90

SUB TOTAL 185,541.82

IGV. 18 % 33,397.53

PRESUPUESTO TOTAL 218,939.35

TOTAL COSTO DIRECTO 169,832.33

TOTAL COSTOS INDIRECTOS 49,107.02

MONTO TOTAL PRESUPUESTO 218,939.35


Cronograma
PROGRAMACION DE OBRA - DIAGRAMA GANTT

Obra: PASES AEREOS: UNION PALAYCCA-SANTA ANA


Ubicacion: SAN PEDRO - LUCANAS - AYACUCHO
Id Item Nombre de tarea Duración Duración Comienzo Fin mes 1 mes 2
Calendarios Laborables -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62
1 PASES AEREOS: UNION PALAYCCA-SANTA ANA 58 días 50 días lun 2/08/21 mar 28/09/21 58 días
2 Inicio de Obra 0 días 0 días lun 2/08/21 lun 2/08/21

3 Obras Civiles 58 días 50 días lun 2/08/21 mar 28/09/21 58 días


4 01 PASE AEREO L=44 MTS (02 Unidades) 58 días 50 días lun 2/08/21 mar 28/09/21 58 días
5 01.01 OBRAS PRELIMINARES 3 días 3 días lun 2/08/21 mié 4/08/21 3 días
6 01.01.01 FLETE 1 día 1 día lun 2/08/21 lun 2/08/21 1 día
7 01.01.02 ACARREO DE MATERIAL DE CONSTRUCCION 2 días 2 días lun 2/08/21 mar 3/08/21 2 días
8 01.01.03 LIMPIEZA DE TERRENO MANUAL 1 día 1 día mar 3/08/21 mar 3/08/21 1 día
9 01.01.04 TRAZO, NIVELACION Y REPLANTEO 1 día 1 día mié 4/08/21 mié 4/08/21 1 día
10 01.02 MOVIMIENTO DE TIERRAS 5 días 4 días jue 5/08/21 lun 9/08/21 5 días
11 01.02.01 EXCAVACION TERRENO NORMAL 2 días 2 días jue 5/08/21 vie 6/08/21 2 días
12 01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO 3 días 2 días sáb 7/08/21 lun 9/08/21 3 días
13 01.03 OBRAS DE CONCRETO SIMPLE 2 días 2 días mar 10/08/21 mié 11/08/21 2 días
14 01.03.01 Concreto fc=10 MPa para solados 1 día 1 día mar 10/08/21 mar 10/08/21 1 día
15 01.03.02 CONCRETO f 'c=140 Kg/cm2 + 30% P.M P/CAMARA DE 1 día 1 día mié 11/08/21 mié 11/08/21 1 día
ANCLAJE
16 01.04 OBRAS DE CONCRETO ARMADO 15 días 13 días jue 12/08/21 jue 26/08/21 15 días
17 01.04.01 ZAPATAS 5 días 4 días jue 12/08/21 lun 16/08/21 5 días
18 01.04.01.01 ACERO EN GENERAL fy = 4200 kg/cm2 3 días 3 días jue 12/08/21 sáb 14/08/21 3 días
19 01.04.01.02 ENCOFRADO Y DESENCOFRADO PARA ZAPATAS 2 días 2 días vie 13/08/21 sáb 14/08/21 2 días
RECTAS
20 01.04.01.03 CONCRETO f'c=210 kg/cm2 PARA ZAPATAS 3 días 2 días sáb 14/08/21 lun 16/08/21 3 días
21 01.04.02 COLUMNAS 7 días 6 días mar 17/08/21 lun 23/08/21 7 días
22 01.04.02.01 ACERO EN GENERAL fy = 4200 kg/cm2 4 días 4 días mar 17/08/21 vie 20/08/21 4 días
23 01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN 3 días 3 días jue 19/08/21 sáb 21/08/21 3 días
COLUMNAS
24 01.04.02.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 1 día 1 día lun 23/08/21 lun 23/08/21 1 día
25 01.04.03 VIGAS 3 días 3 días mar 24/08/21 jue 26/08/21 3 días
26 01.04.03.01 ACERO EN GENERAL fy = 4200 kg/cm2 1 día 1 día mar 24/08/21 mar 24/08/21 1 día
27 01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL 1 día 1 día mié 25/08/21 mié 25/08/21 1 día
28 01.04.03.03 CONCRETO f 'c=210 Kg/cm2 1 día 1 día jue 26/08/21 jue 26/08/21 1 día
29 01.05 CARPINTERIA METALICA 21 días 18 días vie 27/08/21 jue 16/09/21 21 días
30 01.05.01 ACCESORIOS DE ANCLAJE FIJO P/PUENTE COLGANTE 1 día 1 día vie 27/08/21 vie 27/08/21 1 día

31 01.05.02 DISPOSITIVO DE APOYO EN COLUMNA P/PUENTE 1 día 1 día sáb 28/08/21 sáb 28/08/21 1 día
COLGANTE
32 01.05.03 SUMINISTRO E INSTALACION DE CABLE TIPO BOA 6x19 5/8" 2 días 2 días lun 30/08/21 mar 31/08/21 2 días

33 01.05.04 SUMINISTRO E INSTALACION DE CABLE TIPO BOA 1/4" 2 días 2 días mié 1/09/21 jue 2/09/21 2 días
34 01.05.05 GRAPAS ANTIDESLIZANTES 5/8" 4 días 3 días vie 3/09/21 lun 6/09/21 4 días
35 01.05.06 ABRAZADERA SUPERIOR PARA CABLE TIPO BOA DE 5/8" 2 días 2 días mar 7/09/21 mié 8/09/21 2 días

36 01.05.07 ABRAZADERA INFERIOR PARA TUBO DE HDPE 6" 3 días 3 días jue 9/09/21 sáb 11/09/21 3 días
37 01.05.08 PÉNDOLAS DE ACERO 1/4" SERIE 6x19 TIPO BOA P/PUENTE 2 días 2 días lun 13/09/21 mar 14/09/21 2 días
COLGANTE
38 01.05.09 PUERTA METALICA INC. PINTURA Y CERROJO (02 HOJAS) 2 días 2 días mié 15/09/21 jue 16/09/21 2 días

39 01.06 TARRAJEOS Y ENLUCIDOS 2 días 2 días vie 17/09/21 sáb 18/09/21 2 días
40 01.06.01 SOLAQUEADO DE COLUMNAS 2 días 2 días vie 17/09/21 sáb 18/09/21 2 días
41 01.07 PINTURA 3 días 3 días lun 20/09/21 mié 22/09/21 3 días
42 01.07.01 PINTURA ESMALTE EN METALICOS (INCLUYE BASE 3 días 3 días lun 20/09/21 mié 22/09/21 3 días
ANTICORROSIVA)
43 01.08 VARIOS 6 días 5 días jue 23/09/21 mar 28/09/21 6 días
44 01.08.01 TUBERIA ESTRUCTURADA HDPE SN-2 DN 200MM 3 días 3 días jue 23/09/21 sáb 25/09/21 3 días
45 01.08.02 TERMOFUSION PARA TUBERIA ESTRUCTURADA HDPE SN-2 2 días 2 días lun 27/09/21 mar 28/09/21 2 días
DN 200MM
46 Termino de Obra 0 días 0 días mar 28/09/21 mar 28/09/21

Tarea Tarea Critica Progreso Hito Resumen


Calendario de Avance Físico de Obra
Calendario de Avance Físico de Obra
Obra : PASES AEREOS: UNION PALAYCCA-SANTA ANA
Ubicacion : SAN PEDRO - LUCANAS - AYACUCHO
Costo A : Ago - 2021 Cliente : MUNICIPALIDAD DISTRITAL DE SAN PEDRO
HORAS HOMBRE
HH Total HH
Item Descripcion Unid Metrado Parcial HH 30 Días 28 Días
Unitario 58 Dias

Obras Civiles
01 PASE AEREO L=44 MTS (02 Unidades)
01.01 OBRAS PRELIMINARES
01.01.01 FLETE Glb 1.00 - - - - -
kg
01.01.02 ACARREO DE MATERIAL DE CONSTRUCCION 63,200.00 0.00 63.20 63.20 - 63.20

01.01.03 LIMPIEZA DE TERRENO MANUAL m2 70.20 0.06 4.41 4.41 - 4.41


01.01.04 TRAZO, NIVELACION Y REPLANTEO m2 50.59 0.02 0.90 0.90 - 0.90
01.02 MOVIMIENTO DE TIERRAS
01.02.01 EXCAVACION TERRENO NORMAL m3 75.46 0.37 27.66 27.66 - 27.66
01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 16.00 3.36 53.76 53.76 - 53.76
01.03 OBRAS DE CONCRETO SIMPLE
01.03.01 Concreto fc=10 MPa para solados m2 19.40 2.48 48.11 48.11 - 48.11
01.03.02 CONCRETO f 'c=140 Kg/cm2 + 30% P.M P/CAMARA DE ANCLAJE
m3 39.69 2.27 90.18 90.18 - 90.18
01.04 OBRAS DE CONCRETO ARMADO
01.04.01 ZAPATAS
01.04.01.01 ACERO EN GENERAL fy = 4200 kg/cm2 KG 2,402.50 0.06 153.76 153.76 - 153.76
01.04.01.02 ENCOFRADO Y DESENCOFRADO PARA ZAPATAS RECTAS
m2 36.04 0.73 26.32 26.32 - 26.32
01.04.01.03 CONCRETO f'c=210 kg/cm2 PARA ZAPATAS m3 23.52 2.81 66.18 66.18 - 66.18
01.04.02 COLUMNAS
01.04.02.01 ACERO EN GENERAL fy = 4200 kg/cm2 KG 3,425.08 0.06 219.21 219.21 - 219.21
01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS
m2 112.00 1.08 121.39 121.39 - 121.39
01.04.02.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 11.83 2.43 28.77 28.77 - 28.77
01.04.03 VIGAS
01.04.03.01 ACERO EN GENERAL fy = 4200 kg/cm2 KG 205.21 0.06 13.13 13.13 - 13.13
01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.84 2.00 3.68 3.68 - 3.68
01.04.03.03 CONCRETO f 'c=210 Kg/cm2 m3 0.08 3.50 0.28 0.28 - 0.28
01.05 CARPINTERIA METALICA
01.05.01 ACCESORIOS DE ANCLAJE FIJO P/PUENTE COLGANTE UND 5.00 6.20 31.00 31.00 - 31.00
01.05.02 DISPOSITIVO DE APOYO EN COLUMNA P/PUENTE COLGANTE
UND 4.00 12.40 49.60 49.60 - 49.60

01.05.03 SUMINISTRO E INSTALACION DE CABLE TIPO BOA 6x19 5/8" 124.00 0.68 84.32 84.32 - 84.32
m

01.05.04 SUMINISTRO E INSTALACION DE CABLE TIPO BOA 1/4" 78.00 0.93 72.33 - 72.33 72.33
m
01.05.05 GRAPAS ANTIDESLIZANTES 5/8" Und. 196.00 0.91 177.71 - 177.71 177.71
01.05.06 ABRAZADERA SUPERIOR PARA CABLE TIPO BOA DE 5/8"
Und. 84.00 2.56 215.04 - 215.04 215.04
01.05.07 ABRAZADERA INFERIOR PARA TUBO DE HDPE 6" Und. 96.00 1.28 122.88 - 122.88 122.88

01.05.08 PÉNDOLAS DE ACERO 1/4" SERIE 6x19 TIPO BOA P/PUENTE COLGANTE80.00 1.68 134.40 - 134.40 134.40
m
01.05.09 PUERTA METALICA INC. PINTURA Y CERROJO (02 HOJAS)
UND 4.00 0.80 3.20 - 3.20 3.20
01.06 TARRAJEOS Y ENLUCIDOS
01.06.01 SOLAQUEADO DE COLUMNAS m2 34.96 0.96 33.56 - 33.56 33.56
01.07 PINTURA
01.07.01 PINTURA ESMALTE EN METALICOS (INCLUYE BASE ANTICORROSIVA)
m2 30.65 0.93 28.61 - 28.61 28.61
01.08 VARIOS
01.08.01 TUBERIA ESTRUCTURADA HDPE SN-2 DN 200MM M 108.00 2.44 263.52 - 263.52 263.52
01.08.02 TERMOFUSION PARA TUBERIA ESTRUCTURADA HDPE Und.
SN-2 DN 200MM10.00 11.20 112.00 - 112.00 112.00

TOTAL HORAS HOMBRE 2,249.11 1,085.86 1,163.25 2,249.11


TOTAL ACUMULADO 1,085.86 2,249.11
PORCENTAJE DE AVANCE 48.28% 51.72%
PORCENTAJE ACUMULADO 48.28% 100.00%

Página 2 de 12
Calendario de Utilizacion de Recursos
Calendario de Utilizacion de Recursos
Obra : PASES AEREOS: UNION PALAYCCA-SANTA ANA
Ubicacion : SAN PEDRO - LUCANAS - AYACUCHO
Costo A : Ago - 2021 Cliente : MUNICIPALIDAD DISTRITAL DE SAN PEDRO
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Días 28 Días
58 Dias

MANO DE OBRA
47 07378 MAESTRO DE OBRA HH 93.70 23.50 2,201.95 579.21 1,622.74 2,201.95
47 00086 TOPOGRAFO HH 0.45 27.80 12.51 12.51 - 12.51
47 00007 OPERARIO HH 770.55 22.78 17,553.13 9,076.93 8,476.20 17,553.13
47 00008 OFICIAL HH 393.51 18.25 7,181.56 2,084.69 5,096.87 7,181.56
47 00009 PEON HH 970.31 16.46 15,971.30 8,682.45 7,288.85 15,971.30
MATERIALES
01 07319 GASOLINA GLN 6.73 16.00 107.68 107.68 - 107.68
02 01401 ACERO DE REFUERZO FY=4200 KG 6,457.77 3.15 20,341.98 20,341.98 - 20,341.98
02 00123 ALAMBRE NEGRO RECOCIDO # 16 KG 428.35 4.24 1,816.20 1,816.20 - 1,816.20
02 00117 ALAMBRE NEGRO RECOCIDO # 8 KG 37.21 7.50 279.08 279.08 - 279.08
02 07486 BARRA DE ACERO TIPO "U" C/SOCKET CONICO DE ANCLAJE
Und. 5.00 560.00 2,800.00 2,800.00 - 2,800.00
02 01485 CLAVOS Fo No C/C 3/4" KG 5.40 8.60 46.44 46.44 - 46.44
02 02069 CLAVOS PARA MADERA C/C 2" KG 0.46 4.50 2.07 2.07 - 2.07
02 00118 CLAVOS PARA MADERA C/C 3" KG 19.34 4.50 87.03 87.03 - 87.03
02 02370 GRAPAS CROSBY DE 5/8" UND 196.01 12.40 2,430.52 - 2,430.52 2,430.52
02 02378 PERNO DE 1/2" x 2' UND 276.00 8.30 2,290.80 - 2,290.80 2,290.80
02 02375 PERNO EN "U" DE 5/8" x 0.60 UND 8.00 16.20 129.60 129.60 - 129.60
02 02368 PERNOS DE 1/2" x 1.80 m UND 20.00 36.00 720.00 720.00 - 720.00
02 04634 RIEL DE FERROCARRIL TIPO T1 M 6.00 224.00 1,344.00 1,344.00 - 1,344.00
02 02374 TUERCA DE 5/8" UND 16.00 3.50 56.00 56.00 - 56.00
02 02369 TUERCAS DE ACERO DE 1/2" UND 295.99 3.50 1,035.97 70.00 965.97 1,035.97
04 00033 ARENA FINA m3 0.63 190.00 119.70 - 119.70 119.70
05 00002 AGUA m3 23.78 1.60 38.05 27.98 10.07 38.05
05 00039 ARENA GRUESA m3 18.66 145.00 2,705.70 2,705.70 - 2,705.70
05 00099 PIEDRA CHANCADA DE 1/2" m3 19.49 142.10 2,769.53 2,769.53 - 2,769.53
05 01399 PIEDRA MEDIANA DE 4" m3 19.84 160.00 3,174.40 3,174.40 - 3,174.40
21 06871 CEMENTO PORTLAND TIPO I (42.5 kg) bol 567.87 22.50 12,777.08 12,683.47 93.61 12,777.08
29 02371 SOLDADURA CELLOCORD P (AWS E6010) 3/16" KG 16.20 25.30 409.86 91.08 318.78 409.86
29 07480 SOLDADURA PARA TERMOFUSION KG 13.00 65.00 845.00 - 845.00 845.00
29 07479 SUMINISTRO DE EQUIPO DE TERMOFUSION HM 10.00 30.00 300.00 - 300.00 300.00
30 02380 CABLE DE 5/8", 6x19, CON ALMA DE ACERO GALVANIZADO
M 126.48 39.00 4,932.72 4,932.72 - 4,932.72

30 07470 CABLE DE ACERO DE 1/4", TIPO BOA / SERIE 6x19 165.90 26.60 4,412.94 - 4,412.94 4,412.94
m
30 00266 CORDEL M 12.75 1.10 14.03 14.03 - 14.03
30 07416 YESO EN BOLSAS DE 25 Kg Bol 0.11 15.20 1.67 1.67 - 1.67
32 02471 FLETE Glb 1.00 3,600.00 3,600.00 3,600.00 - 3,600.00
38 00005 HORMIGON m3 46.08 125.00 5,760.00 5,760.00 - 5,760.00
43 06994 LISTONES DE MADERA 2"x3"x8' u 0.15 14.20 2.13 2.13 - 2.13
43 00342 MADERA NACIONAL P/ENCOFRADO-CARP P2 794.17 5.40 4,288.52 4,288.52 - 4,288.52
43 07053 TABLAS 1"x12"x10' u 1.25 18.00 22.50 22.50 - 22.50
44 01387 ESTACA DE MADERA P2 0.53 5.20 2.76 2.76 - 2.76
51 02376 PLATINA F.N. 1" x 3/8" x 20' PZA 0.55 16.00 8.80 8.80 - 8.80
53 00480 THINER GLN 1.23 29.00 35.67 - 35.67 35.67
54 00068 PINTURA ANTICORROSIVA GLN 0.92 45.00 41.40 - 41.40 41.40
54 00606 PINTURA ESMALTE SINTETICO GLN 0.92 55.00 50.60 - 50.60 50.60
57 02377 PLANCHA NEGRA LAC DE 1/2" x 4' x 8' UND 0.17 1,680.00 285.60 285.60 - 285.60
57 02372 PLANCHA NEGRA LAC DE 5/8" x 4' x 8' UND 0.10 2,235.00 223.50 223.50 - 223.50
63 07483 PUERTA METALICA INC. PINTURA ESMALTE Und. 4.00 440.00 1,760.00 - 1,760.00 1,760.00
71 07484 ABRAZADERAS C/PLATINA DE 1/4"x6mmx32mm Und. 84.00 23.60 1,982.40 - 1,982.40 1,982.40
71 07485 ABRAZADERAS C/PLATINA DE 1/4"x6mmx400mm Und. 192.00 89.20 17,126.40 - 17,126.40 17,126.40
71 02393 ABRAZADERAS DE Fo.Fo. 6" PZA 196.01 12.00 2,352.12 - 2,352.12 2,352.12
72 07478 TUBERIA ESTRUCTURADA HDPE SN-2 DN 200MM m 108.00 78.00 8,424.00 - 8,424.00 8,424.00
EQUIPO
37 00004 HERRAMIENTAS MANUALES %MO 1,619.57 558.08 1,061.49 1,619.57
48 07431 ANDAMIO METALICO INC. PLATAFORMA hm 57.82 6.00 346.92 346.92 - 346.92
48 00464 MAQUINA SOLDADORA HM 3.20 8.00 25.60 25.60 - 25.60
48 00430 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 33.36 7.20 240.19 240.19 - 240.19
48 06866 RETROEXCAVADORA SOBRE LLANTAS 58 HP 1/2 y3 hm 62.04 190.00 11,787.60 11,787.60 - 11,787.60
48 07469 TIRFOR DE 3 TON HM 30.71 18.00 552.78 297.53 255.25 552.78
49 06200 COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP UND 1.60 12.00 19.20 19.20 - 19.20
49 03945 COMPRESORA DE AIRE MAS PISTOLA HM 20.43 15.00 306.45 - 306.45 306.45
49 07417 NIVEL TOPOGRÁFICO hm 0.45 40.00 18.00 18.00 - 18.00
49 01489 VIBRADOR DE 3/4" - 2" CONCRETO HM 10.28 4.00 41.12 41.12 - 41.12

COSTO DIRECTO 169,832.33 102,164.50 67,667.83 169,832.33


GASTOS GENERALES 8% 13,586.59 8,173.16 5,413.43 13,586.59
UTILIDAD 1.25 % 2,122.90 1,277.05 845.85 2,122.90
SUB TOTAL 185,541.82 111,614.72 73,927.10 185,541.82
IGV. 18 % 33,397.53 20,090.65 13,306.88 33,397.53
PRESUPUESTO TOTAL 218,939.35 131,705.37 87,233.98 218,939.35
TOTAL ACUMULADO 131,705.37 218,939.35
PORCENTAJE DE AVANCE 60.16% 39.84%
PORCENTAJE ACUMULADO 60.16% 100.00%
Calendario Valorizado de Avance de Obra
Calendario Valorizado de Avance de Obra
Obra : PASES AEREOS: UNION PALAYCCA-SANTA ANA
Ubicacion : SAN PEDRO - LUCANAS - AYACUCHO
Costo A : Ago - 2021 Cliente : MUNICIPALIDAD DISTRITAL DE SAN PEDRO

PLAZO DE
EJECUCION

Precio TOTAL
Item Descripcion Unid Metrado Parcial 30 Días 28 Días
Unitario 58 Dias

Obras Civiles
01 PASE AEREO L=44 MTS (02 Unidades)
01.01 OBRAS PRELIMINARES
01.01.01 FLETE Glb 1.00 3,600.00 3,600.00 3,600.00 - 3,600.00
kg
01.01.02 ACARREO DE MATERIAL DE CONSTRUCCION 63,200.00 0.16 10,112.00 10,112.00 - 10,112.00

01.01.03 LIMPIEZA DE TERRENO MANUAL m2 70.20 1.10 77.22 77.22 - 77.22


01.01.04 TRAZO, NIVELACION Y REPLANTEO m2 50.59 1.12 56.66 56.66 - 56.66
01.02 MOVIMIENTO DE TIERRAS
01.02.01 EXCAVACION TERRENO NORMAL m3 75.46 38.13 2,877.29 2,877.29 - 2,877.29
01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 16.00 67.72 1,083.52 1,083.52 - 1,083.52
01.03 OBRAS DE CONCRETO SIMPLE
01.03.01 Concreto fc=10 MPa para solados m2 19.40 75.22 1,459.27 1,459.27 - 1,459.27
01.03.02 CONCRETO f 'c=140 Kg/cm2 + 30% P.M P/CAMARA DE ANCLAJE
m3 39.69 408.64 16,218.92 16,218.92 - 16,218.92
01.04 OBRAS DE CONCRETO ARMADO
01.04.01 ZAPATAS
01.04.01.01 ACERO EN GENERAL fy = 4200 kg/cm2 KG 2,402.50 4.96 11,916.40 11,916.40 - 11,916.40
01.04.01.02 ENCOFRADO Y DESENCOFRADO PARA ZAPATASm2
RECTAS 36.04 49.61 1,787.94 1,787.94 - 1,787.94
01.04.01.03 CONCRETO f'c=210 kg/cm2 PARA ZAPATAS m3 23.52 400.14 9,411.29 9,411.29 - 9,411.29
01.04.02 COLUMNAS
01.04.02.01 ACERO EN GENERAL fy = 4200 kg/cm2 KG 3,425.08 4.96 16,988.40 16,988.40 - 16,988.40
01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS
m2 112.00 57.04 6,388.48 6,388.48 - 6,388.48
01.04.02.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 11.83 400.23 4,734.72 4,734.72 - 4,734.72
01.04.03 VIGAS
01.04.03.01 ACERO EN GENERAL fy = 4200 kg/cm2 KG 205.21 4.96 1,017.84 1,017.84 - 1,017.84
01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 1.84 55.08 101.35 101.35 - 101.35
01.04.03.03 CONCRETO f 'c=210 Kg/cm2 m3 0.08 400.40 32.03 32.03 - 32.03
01.05 CARPINTERIA METALICA
01.05.01 ACCESORIOS DE ANCLAJE FIJO P/PUENTE COLGANTE
UND 5.00 1,112.46 5,562.30 5,562.30 - 5,562.30
01.05.02 DISPOSITIVO DE APOYO EN COLUMNA P/PUENTE COLGANTE
UND 4.00 453.30 1,813.20 1,813.20 - 1,813.20

01.05.03 SUMINISTRO E INSTALACION DE CABLE TIPO BOA 6x19 5/8" 124.00 55.80 6,919.20 6,919.20 - 6,919.20
m

01.05.04 SUMINISTRO E INSTALACION DE CABLE TIPO BOA 1/4" 78.00 49.77 3,882.06 - 3,882.06 3,882.06
m
01.05.05 GRAPAS ANTIDESLIZANTES 5/8" Und. 196.00 44.40 8,702.40 - 8,702.40 8,702.40
01.05.06 ABRAZADERA SUPERIOR PARA CABLE TIPO BOA DE Und.
5/8" 84.00 92.94 7,806.96 - 7,806.96 7,806.96
01.05.07 ABRAZADERA INFERIOR PARA TUBO DE HDPE 6" Und. 96.00 228.87 21,971.52 - 21,971.52 21,971.52

01.05.08 PÉNDOLAS DE ACERO 1/4" SERIE 6x19 TIPO BOA P/PUENTE COLGANTE
80.00 61.71 4,936.80 - 4,936.80 4,936.80
m
01.05.09 PUERTA METALICA INC. PINTURA Y CERROJO (02 HOJAS)
UND 4.00 459.36 1,837.44 - 1,837.44 1,837.44
01.06 TARRAJEOS Y ENLUCIDOS
01.06.01 SOLAQUEADO DE COLUMNAS m2 34.96 29.03 1,014.89 - 1,014.89 1,014.89
01.07 PINTURA
01.07.01 PINTURA ESMALTE EN METALICOS (INCLUYE BASE ANTICORROSIVA)
m2 30.65 35.95 1,101.87 - 1,101.87 1,101.87
01.08 VARIOS
01.08.01 TUBERIA ESTRUCTURADA HDPE SN-2 DN 200MM M 108.00 123.12 13,296.96 - 13,296.96 13,296.96
01.08.02 TERMOFUSION PARA TUBERIA ESTRUCTURADA HDPE
Und.
SN-2 DN 200MM
10.00 312.34 3,123.40 - 3,123.40 3,123.40

COSTO DIRECTO 169,832.33 102,158.03 67,674.30 169,832.33


GASTOS GENERALES 8% 13,586.59 8,172.64 5,413.95 13,586.59
UTILIDAD 1.25 % 2,122.90 1,276.97 845.93 2,122.90
SUB TOTAL 185,541.82 111,607.65 73,934.17 185,541.82
IGV. 18 % 33,397.53 20,089.38 13,308.15 33,397.53
PRESUPUESTO TOTAL 218,939.35 131,697.03 87,242.32 218,939.35
TOTAL ACUMULADO 131,697.03 ########
PORCENTAJE DE AVANCE 60.15% 39.85%
PORCENTAJE ACUMULADO 60.15% 100.00%
Curva ''S'' - Avance de Obra
Curva ''S'' - Avance de Obra
Proyecto PASES AEREOS: UNION PALAYCCA-SANTA ANA
Cliente MUNICIPALIDAD DISTRITAL DE SAN PEDRO
Ubicación SAN PEDRO - LUCANAS - AYACUCHO Costo a : Agosto - 2021

Avance
N Fecha Corte
Programado

02/Ago 0.00%
1 31/Ago 60.15%
2 28/Set 100.00%
Curva ''S''
- Avance de Obra Físico (Horas Hombre)
Curva ''S'' - Avance de Obra Físico (Horas Hombre)
Proyecto PASES AEREOS: UNION PALAYCCA-SANTA ANA
Cliente MUNICIPALIDAD DISTRITAL DE SAN PEDRO
Ubicación SAN PEDRO - LUCANAS - AYACUCHO Costo a : Agosto - 2021

Avance
N Fecha Corte
Programado HH

02/Ago 0.00%
1 31/Ago 48.28%
2 28/Set 100.00%
Planos
PASE AÉREO TÍPICO - PLANTA (LADO IZQUIERDO)

PASE AÉREO TÍPICO - ELEVACIÓN 50 MTS

TABLA No1

NOTA DISEÑO:

ESPECIFICACIONES TÉCNICAS

NORMAS TÉCNICAS VIGENTES

MUNICIPALIDAD DISTRITAL DE SAN PEDRO

OBRA MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO


INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA
SANTA ISABEL DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578

PASEAEREO

E-01
ESPECIFICACIONES TÉCNICAS

d
D

d
D

L
d

A A

PASE AÉREO TÍPICO - ELEVACIÓN (EXTREMO DERECHO)

ELEVACIÓN TORRE 1, TORRE 2


ELEVACIÓN FRONTAL ELEVACIÓN LATERAL

NOTA DISEÑO:

MUNICIPALIDAD DISTRITAL DE SAN PEDRO

SECCIÓN A-A ZAPATA 01, ZAPATA 02 - OBRA MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO
PLANTA INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA
SANTA ISABEL DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578

PASEAEREO

E-02
4 NOTA DISEÑO:

DETALLE 5

4
DETALLE 1 - SECCIÓN 4-4
A A DETALLE COORECTO DE EMPALME DE TEMPLADOR

DETALLE 1
1 X
1
DETALLE 2 - PLANTA

2 2 TEMPLADOR CON DOS ESPIGAS DE OJAL

1 1

DETALLE 3 - PLANTA
DETALLE "C"
EXTREMO SUFERIOR DE PENDOLA
´

DETALLE GRAPA CROSBY Ó SIMILAR

3 3

DETALLE 3 - SECCIÓN 2-2

3
DETALLE 2 - CORTE A-A

3
2 2
3

4
3
2 2

DETALLE SOCKET CÓNICO DE ANCLAJE


MUNICIPALIDAD DISTRITAL DE SAN PEDRO
4 OBRA MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE SANEAMIENTO BASICO
INTEGRAL DE LAS LOCALIDADES DE PUNCUHUACCA Y UNION PALAYCCA, SANTA ANA
SANTA ISABEL DEL DISTRITO DE SAN PEDRO-LUCANAS-AYACUCHO", SNIP N° 313578

DETALLE 4 PASEAEREO

DETALLE
BARRA DE ACERO TIPO "U" E-02
SECCIÓN 3-3