1.-MATERIALES
Descripción Und. Cantidad Peso Unit (kg) Parcial
TRIPLAY DE 4' X 8' X 6 mm pl 52.5000 27.00 1,417.50
PLANCHAS DE FIBRAFORTE pl 60.0000 30.00 1,800.00
PERNO BROCA 2 1/2"x 6mm, C/CABEZA HEXAGONAL+ CAPUCHON Y 34,599.5200 346.00
u 0.01
ARANDELA PLASTICA TIPO BASE BOYA
ADOQUIN DE COLOR ROJO 0.10x0.20x0.06 u 5,385.5000 2.88 15,510.24
LADRILLO DE ARCILLA PARA TECHO (15X30X30cm) h=15 cm u 5,467.0000 7.60 41,549.20
LADRILLO DE ARCILLA KK 18 HUECOS TIPO IV (9X13X24cm) u 143,009.1400 5.50 786,550.27
LADRILLO QUEMADO DE ARCILLA DE 6 HUECOS (11X14X24) u 2,026.8600 6.00 12,161.16
CEMENTO PORTLAND TIPO ICO (42.5 KG) bls 18,189.6370 42.50 773,059.57
CAL HIDRATADA DE 30 Kg bls 6.9272 30.00 207.82
PEGAMENTO PARA CERAMICOS (BLS 25 Kg) bls 153.0594 25.00 3,826.49
PEGAMENTO PARA PORCELANATO SANSON (BLS 25 Kg) bls 465.2145 25.00 11,630.36
ASFALTO RC-250 gal 22.4846 5.50 123.67
THINNER gal 80.8857 5.50 444.87
AGUARRAS gal 26.4053 5.50 145.23
SELLADOR IGAS NEGRO gal 2.9000 5.50 15.95
FORMADOR DE EMPAQUETADURA gal 0.4700 5.50 2.59
PEGAMENTO PARA PVC gal 240.2793 5.50 1,321.54
SILICATO DE SODIO NEUTRO gal 11.0608 5.50 60.83
PINTURA ESMALTE SINTETICO gal 221.2651 5.50 1,216.96
XILOL gal 24.2110 5.50 133.16
PINTURA ESMALTE gal 0.5000 5.50 2.75
PINTURA LATEX gal 87.4870 5.50 481.18
PINTURA OLEO MATE COLOR BLANCO ARENA gal 213.3890 5.50 1,173.64
PINTURA OLEO MATE COLOR NARANJA gal 121.4803 5.50 668.14
PINTURA ANTICORROSIVA gal 546.7265 5.50 3,007.00
PINTURA IMPRIMANTE gal 617.2352 5.50 3,394.79
PINTURA PARA TRAFICO AMARILLA gal 24.2110 5.50 133.16
ALAMBRE NEGRO RECOCIDO # 16 kg 6,009.4108 1.00 6,009.41
ALAMBRE NEGRO RECOCIDO # 8 kg 2,997.7705 1.00 2,997.77
CLAVOS PARA MADERA CON CABEZA DE 3" kg 2,650.7075 1.00 2,650.71
CLAVOS DE ALAMBRE PARA MADERA C/C DE 1" kg 93.5616 1.00 93.56
CLAVOS DE ACERO CON CABEZA DE 1/2" kg 0.2000 1.00 0.20
CLAVOS DE ACERO CON CABEZA PROMEDIO kg 22.5000 1.00 22.50
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 107,538.3009 1.00 107,538.30
OCRE ROJO kg 77.6360 1.00 77.64
FRAGUA PARA CERAMICOS kg 2,080.6151 1.00 2,080.62
IMPERMEABILIZANTE kg 2.2400 1.00 2.24
SOLDADURA ALEACION DE PLATA (30%), COBRE (30%), ZINC (26%)* kg 4.4765 1.00 4.48
ADITIVO IMPERMEABILIZANTE kg 476.9800 1.00 476.98
FLEXIBLE, CORREDERAS, SOPORTES Y OTROS, SEGUN ESP.TEC. kg 3,300.0000 1.00 3,300.00
SOLDADURA CELLOCORD P 3/16" kg 835.4070 1.00 835.41
FUNDENTE PARA SOLDAR kg 152.6367 1.00 152.64
SOLDADURA DE ESTAÑO (90%), PLATA (5%), COBRE (5%) kg 58.5766 1.00 58.58
HIPOCLORITO DE CALCIO AL 70% kg 83.0984 1.00 83.10
SAL INDUSTRIAL kg 165.0000 1.00 165.00
TRAPO INDUSTRIAL kg 1,177.6080 1.00 1,177.61
WAYPE kg 12.1055 1.00 12.11
SULFATO DE BARIO ( BARITINA ) kg 29.6582 1.00 29.66
REGLA DE MADERA p2 334.2686 3.55 1,186.65
MADERA PARA ENCOFRADO p2 56,711.7471 3.55 201,326.70
MADERA TORNILLO O SIMILAR p2 675.4120 3.55 2,397.71
AISLAMIENTO LANA FIBRA DE VIDRIO m2 255.6773 10.00 2,556.77
PLANCHA DE ALUMINIO COMPUESTO PVDF E=6MM TEXTURA ACERO 488.9600 9,779.20
m2 20.00
RAYADO
PLANCHA DE ALUMINIO COMPUESTO PVDF E=6MM TEXTURA MADERA 249.4200 4,988.40
m2 20.00
TAUPE OSCURO
PLANCHA DE FIBROCEMENTO 4MM m2 1,438.8290 7.20 10,359.57
PLANCHA TERMO ACUSTICO AZ-200 E=45MM m2 4,324.9400 6.00 25,949.64
PORCELANATO DE ALTO TRANSITO 0.60X0.60 cm m2 2,894.9865 7.00 20,264.91
PANEL DE ALUZINC PREPINTADO LISO E=4MM m2 157.4580 10.00 1,574.58
TABIQUERIA DE ALUMINIO Y VIDRIO TEMPLADO E=10MM m2 76.6000 20.00 1,532.00
CERAMICO DE 0.30x0.30 m m2 27.7200 6.00 166.32
CERAMICO DE 0.45x0.45 m m2 465.0900 6.00 2,790.54
CERAMICO DE 0.40x0.40 m m2 109.7807 6.00 658.68
BALDOSA ACUSTICA m2 514.6100 2.00 1,029.22
PERFIL DE SOPORTE ALUMINIO PRELUDE 15/16" HUNTER DOUGLAS m2 514.6100 3.00 1,543.83
2.-AGREGADOS
ARENA FINA m3 350.6636 1.00 350.66
TIERRA FINA COMUN - SUELTA m3 6.5000 1.00 6.50
PIEDRA CHANCADA DE 1/2" m3 9.0752 1.00 9.08
PIEDRA CHANCADA DE 3/4" m3 1,210.9974 1.00 1,211.00
PIEDRA MEDIANA DE 3" m3 2.9565 1.00 2.96
PIEDRA GRANDE m3 137.1981 1.00 137.20
AFIRMADO m3 946.4091 1.00 946.41
ARENA GRUESA m3 1,003.5151 1.00 1,003.52
MATERIAL DE CANTERA m3 1,482.3920 1.00 1,482.39
HORMIGON (PUESTO EN OBRA) m3 130.9892 1.00 130.99
VOLUMEN TOTAL 5,280.70
3- VOLUMEN
MATERIALES UNIDAD VOLUMEN CANTIDAD
AGREGADOS m3 5,280.70 352.05
TOTAL 352.05
UNIDAD DE TRANSPORTE
COSTO POR VIAJE MATERIALES S/. 312.38
FUSO-CAPAC. 10 TN (KG) 10,000.00
FLETE POR KG (MATERIALES) 0.031
UNIDAD DE TRANSPORTE
COSTO POR VIAJE MATERIALES S/. 367.50
VOLQ-CAPAC. 15 m3 15.00
FLETE POR m3 (AGREGADOS) 24.500