DATOS DE OBRA

- ENTIDAD : PROYECTO ESPECIAL DE INFRAEST. DE TRANSPORTE DESCENTRALIZADO - PROVIAS DESCENTRALIZADO


- MODALIDAD DE CONCURSO : LICITACION PUBLICA INTERNACIONAL
- PROCESO : CONV - PROC- 028-2022 -MTC/21-LPI
- CONTRATO DE OBRA : Nº 166-2022-MTC/21
- MODALIDAD DE EJECUCIÓN : PRECIO UNITARIO
"CONV-PROC-028-2022-MTC/21-LPI: MEJORAMIENTO DEL CAMINO
VECINAL EMP. PE-5NC-VALENCIA – EL PALMITO – GUAYAQUIL – DV.
- OBRA : CAMPO BONITO – DV. CORAZON DE MARIA – DV. LIMON – DV. MONTE
SECO – EL PORVENIR – SECTOR EL ARENAL, DIST. ARAMANGO – PROV.
BAGUA – DPTO. AMAZONAS"
- CONTRATISTA : CONSORCIO VIAL VIRGEN DEL PILAR
- RESIDENTE DE OBRA : ING. WILBERT AGUIRRE GONZALEZ CIP Nº: 54055
- SUPERVISOR DE OBRA : CONSORCIO SUPERVISOR PALMITO RUC N°:
- JEFE DE SUPERVISIÓN : ING. JUAN BAUTISTA ROJAS VILLEGAS CIP Nº: 79085
- PRESUPUESTO CONTRATADO : S/. 15,739,440.40 abril, 2016 Incl. IGV
- VALOR REFERENCIAL : S/. 15,203,480.07 abril, 2016 Incl. IGV
- FACTOR DE RELACIÓN : 1.00000
- COSTO DIRECTO : S/.12,744,486.15
- PLAZO CONTRACTUAL : 180 Días Calendario
- INICIO DE OBRA : 20 de octubre de 2022
- FECHA DE TÉRMINO DE OBRA : 17 de abril de 2023
- ADELANTO DIRECTO : S/. 0.00
- ANTICIPO OTORGADO : S/. 2,360,916.06
VALORIZACIÓN N° 03 : (Del 1 al 31 de DICIEMBRE de 2022) FECHA DE FECHA AL
MES DE VALORIZACION : DICIEMBRE 2022 1 31
- UBICACIÓN

DISTRITO : ARAMANGO ,
PROVINCIA : BAGUA -
DEPARTAMENTO : AMAZONAS
ESPECIAL DE INFRAEST. DE TRANSPORTE DESCENTRALIZADO - PROVIAS DESCENTRALIZADO

7/20/2020
239
3/16/2021
INDICE
"CONV-PROC-028-2022-MTC/21-LPI: MEJORAMIENTO DEL CAMINO VECINAL EMP. PE-5NC-
VALENCIA – EL PALMITO – GUAYAQUIL – DV. CAMPO BONITO – DV. CORAZON DE MARIA – DV.
OBRA:
LIMON – DV. MONTE SECO – EL PORVENIR – SECTOR EL ARENAL, DIST. ARAMANGO – PROV.
BAGUA – DPTO. AMAZONAS"

VALORIZACION N° 02 Folios

DEL CONTRATISTA
01.- Caratula ………………………………………………………………………………………………………

02.- Índice de la Valorización del contrato de obra .…….…….……………………….………...………

03.- Factura ………………………………………………………………………………………………………

04.- Resumen de las valorizaciones …………….…………………………………………………………

05.- Memoria explicativa …………………………………………………………………………………………

06.- Metrados ejecutados …………………………………………………………………………………………

07.- Control de pago de valorizaciones ….……………..……………………………………………………

08.- Valorización mensual según componentes y partidas ………………………………………………

09.- Cuadro comparativo y gráfico de avance de obra programado vs ejecutado ………………

10.- Control de Amortizaciones …………………………………………………………………………………

11.- Copia de contrato de obra y adendas correspondientes …………………………………………

12.- Resoluciones …………………………………………………………………………………………………

13.- Actas realizadas durante la ejecución …………………………………………………………………

14.- Documentos de condiciones de inicio de plazo contractual …………………………………

15.- Cuaderno de obra ………………………………………………………………...……………...………

16.- Copias de cartas fianzas vigentes …………………………………………….…………………………

17.- Protocolos de calidad copia (Entidades reconocidas como: MTC, SENCICO, universidades)

18.- Copia de comprobantes de pago de las obligaciones laborales del contratista…………

19.- Fotografías de partidas ejecutadas a colores, mínimo 20 ………………………………………

20.- Otros documentos: ……………………………………………………………………………………

21.- Otros documentos según Contrato ………………………………………………………………………

22.- Anexo - Planos ………………………………………………………………………………………………

23.- Informe de especialistas ……………………………………………………………………………………

24.- CD con contenido del mes valorizado (vistas fotográficas panoramicas en formato JPG)
HOJA RESUMEN DE PAGO
Mes de DICIEMBRE de 2022
PERIODO: (Del 1 al 31 de DICIEMBRE de 2022)

OBRA : "CONV-PROC-028-2022-MTC/21-LPI: MEJORAMIENTO DEL CAMINO VECINAL EMP. PE-5NC-VALENCIA –


EL PALMITO – GUAYAQUIL – DV. CAMPO BONITO – DV. CORAZON DE MARIA – DV. LIMON – DV.
MONTE SECO – EL PORVENIR – SECTOR EL ARENAL, DIST. ARAMANGO – PROV. BAGUA – DPTO.
AMAZONAS"

ENTIDAD : PROYECTO ESPECIAL DE INFRAEST. DE TRANSPORTE DESCENTRALIZADO - PROVIAS DESCENTRALIZADO

UBICACIÓN : DISTRITO: ARAMANGO, PROVINCIA: BAGUA - AMAZONAS

CONTRATISTA : CONSORCIO VIAL VIRGEN DEL PILAR F


RESIDENCIA : ING WILBERT AGUIRRE GONZALEZ F
SUPERVISIÓN : CONSORCIO SUPERVISOR PALMITO

CONCEPTO S/.
A. MONTOS VALORIZADOS EN EL PRESENTE MES 65,163.98
VALORIZACIÓN N° 03: (Del 1 al 31 de DICIEMBRE de 2022) 65,163.98

B. MONTOS POR REAJUSTE EN EL PRESENTE MES 0.00


REAJUSTE VALORIZACIÓN N° 03: (Del 1 al 31 de DICIEMBRE de 2022) 0.00

C. AMORTIZACIÓN DEL ADELANTO DE ANTICIPO EN EL PRESENTE MES 9,774.60


DEL ADELANTO DE ANTICIPO 15.00% 9,774.60
DEDUCTIVO DEL REAJUSTE DEL ADELANTO DIRECTO 0.00

D. AMORTIZACIÓN DEL ADELANTO DE MATERIALES EN EL PRESENTE MES 0.00


POR ADELANTO 0.00
REAJUSTE QUE NO CORRESPONDE - ADELANTO DE MATERIALES 0.00

E. OTROS 0.00
PENALIDAD 0.00

I. MONTO FACTURABLE (SIN I.G.V.) 55,389.38

F. MONTO RETENIDO POR FONDO DE GARANTÍA 0.00


FONDO DE GARANTÍA (10%) SIN IGV. 0.00
FONDO DE GARANTÍA REAJUSTE 0.00
FONDO DE GARANTÍA REGULARIZ. REAJUSTE 0.00

II. TOTAL RETENCIÓN 10% de garantia de carta fianza. 0.00

III. MONTO LÍQUIDO A PAGAR (I - II) 55,389.38

IV. I.G.V. 0.00% 0.00

V. MONTO A FACTURAR (III + IV) S/. 55,389.38

SON: #VALUE!
CUADRO DE RESUMEN DE VALORIZACION Nº 03 - DICIEMBRE 2022

"CONV-PROC-028-2022-MTC/21-LPI: MEJORAMIENTO DEL CAMINO VECINAL EMP. PE-5NC-VALENCIA – EL


OBRA : PALMITO – GUAYAQUIL – DV. CAMPO BONITO – DV. CORAZON DE MARIA – DV. LIMON – DV. MONTE
SECO – EL PORVENIR – SECTOR EL ARENAL, DIST. ARAMANGO – PROV. BAGUA – DPTO. AMAZONAS"

CONTRATISTA : CONSORCIO VIAL VIRGEN DEL PILAR


SUPERVISOR : ING. WILBERT AGUIRRE GONZALEZ
RESIDENTE : CONSORCIO SUPERVISOR PALMITO
PERIODO : (Del 1 al 31 de DICIEMBRE de 2022)

MONTO VALORIZACION
DESCRIPCION CONTRACTUAL
(S/IGV)
ANTERIOR ACTUAL ACUMULADO ACTUAL

A: VALORIZACION CONTRACTUAL
01 TRABAJOS PRELIMINARES 126769.09 7,659.28 10,670.35 18,329.63 23,829.01
02 MOVIMIENTO DE TIERRAS 2269464.37 14,596.00 7,122.85 21,718.85 760.65
03 PAVIMENTOS 4705432.66 0.00 0.00 0.00 0.00
04 OBRAS DE ARTE Y DRENAJE 2276527.6 5,597.76 0.00 5,597.76 0.00
05 TRANSPORTE DE MATERIAL 1993020.68 0.00 0.00 0.00 0.00
06 SEÑALIZACION 964001.37 0.00 0.00 0.00
07 PLAN DE MANEJO AMBIENTAL 92192.75 0.00 3,263.40 3,263.40 0.00
08 PLAN COVID 317077.63 31,707.76 31,707.76 63,415.53 0.00
COSTO DIRECTO 12,744,486.15 59,560.80 52,764.36 112,325.17 24,589.65
GASTOS GENERALES (12.00 % C.D.) 1,529,338.34 7,147.30 6,331.72 13,479.02 2,950.76
UTILIDAD (5.00% C.D.) 1,465,615.91 6,849.49 6,067.90 12,917.39 1,229.48
SUB TOTAL (A) 15,739,440.40 73,557.59 65,163.98 138,721.58 29,261.68

AVANCE FISICO DE OBRA 0.06% 0.41% 0.47% 0.28%


AVANCE PROGRAMADO DE OBRA 0.06% 0.52% 0.58% 1.41%

B: REAJUSTES 0.00 0.00 0.00 0.00 0.00


TOTAL (B) 0.00 0.00 0.00 0.00 0.00

VALORIZACION BRUTA (VB=A+B) 15,739,440.40 73,557.59 65,163.98 138,721.58 29,261.68

C: AMORTIZACIONES
AMORTIZACION DE ANTICIPO 2,360,916.06 11,033.64 9,774.60 20,808.24 0.00
AMORTIZACION DE ADELANTO DE MATERIALES 0.00 0.00 0.00 0.00 0.00
TOTAL (C) 2,360,916.06 11,033.64 9,774.60 20,808.24 0.00

VALORIZACION NETA (VN=VB-C) 62,523.95 55,389.38 117,913.34 29,261.68

D: MONTO TOTAL
EN EFECTIVO (VN) 15,739,440.40 62,523.95 55,389.38 117,913.33 29,261.68
EN I.G.V. (0.0% VN) 0.00 0.00 0.00 0.00 5,267.10
TOTAL (D) 15,739,440.40 62,523.95 55,389.38 117,913.33 34,528.78

E. FACTOR DE RELACION 1.00000

F. MONTO TOTAL FACTORIZADO


TOTAL (F) 15,739,440.40 62,523.95 55,389.38 117,913.33 117,913.33 0.00 34,528.78
G. RETENCIONES
GARANTIA POR FIEL CUMPLIMIENTO (10% M.C.) 0.00

TOTAL COMPROMISO DE PAGO (F-G)>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>> S/. 55,389.38 S/. 34,528.78

AVANCES DE OBRA: MONTO CONTRATADO 766764.13


PROGRAMADO
ACTUAL 0.52%
ACUMULADO 0.58%
EJECUTADO
AVANCE ANTERIOR 0.06%
AVANCE MENSUAL 0.41%
AVANCE ACUMULADO 0.47%
CUMPLIMIENTO DEL % PROGRAMADO 81.03%
CONTROL DE PAGOS

"CONV-PROC-028-2022-MTC/21-LPI: MEJORAMIENTO DEL CAMINO VECINAL EMP. PE-5NC-VALENCIA – EL PALMITO – GUAYAQUIL – DV. CAMPO BONITO – DV. CORAZON DE MARIA – DV. LIMON – DV. MONTE SECO – EL
OBRA :
PORVENIR – SECTOR EL ARENAL, DIST. ARAMANGO – PROV. BAGUA – DPTO. AMAZONAS"
ENTIDAD : PROYECTO ESPECIAL DE INFRAEST. DE TRANSPORTE DESCENTRALIZADO - PROVIAS DESCENTRALIZADO
UBICACIÓN : DISTRITO: ARAMANGO, PROVINCIA: BAGUA - AMAZONAS
CONTRATISTA : CONSORCIO VIAL VIRGEN DEL PILAR PRECIO REFERENCIAL S/. 15,203,480.07
RESIDENCIA : ING. WILBERT AGUIRRE GONZALEZ PREC. CONTRATADO S/. 15,739,440.40
SUPERVISIÓN : CONSORCIO SUPERVISOR PALMITO ANTICIPO OTORGADO S/. 2,360,916.06

Deducciones del
Valorización Amortizacion de Anticipo VALORIZAC. Reajustes adelanto MONTO A PAGADO COMPROBANTE DE PAGO
OBSERVACIONES
S/. Anticipo Materiales NETA ( VN ) Anticipo Materiales Sub total (VE) IGV FACTURADO DETRACCION RETENCION LIQUIDO A Fecha de
Descripción Factura N°
A B C VN = A - B - C D F G VE=(VN+D)-F-G VE*18% VE+IGV 4% 5% PAGAR Cobranza
Val. N° 01 - Octubre 2020 9,373.55 1,406.03 - 7,967.52 - - - 7,967.52 - 7,967.52 318.70 398.38 7,250.44 EN TRAMITE
Val. N° 02 - Noviembre 2022 64,184.04 9,627.61 - 54,556.43 - - - 54,556.43 - 54,556.43 2,182.26 2,727.82 49,646.35 EN TRAMITE
Val. N° 03 - Diciembre 2022 64,184.04 9,774.60 - 54,409.44 - - - 54,409.44 - 54,409.44 2,176.38 2,720.47 49,512.59 EN TRAMITE

137,741.63 20,808.24 - 116,933.39 - - - 116,933.39 - 116,933.39 4,677.34 5,846.67 106,409.38

24589.66
2950.76
491.79
1229.48
29261.69
29261.69
29261.69
5267.1
34528.79
RESUMEN GENERAL DE VALORIZACIONES
"CONV-PROC-028-2022-MTC/21-LPI: MEJORAMIENTO DEL CAMINO VECINAL EMP. PE-5NC-VALENCIA – EL PALMITO – GUAYAQUIL – DV. CAMPO BONITO – DV.
OBRA : PRECIO REFER. S/. 15,203,480.07
CORAZON DE MARIA – DV. LIMON – DV. MONTE SECO – EL PORVENIR – SECTOR EL ARENAL, DIST. ARAMANGO – PROV. BAGUA – DPTO. AMAZONAS"

ENTIDAD : PROYECTO ESPECIAL DE INFRAEST. DE TRANSPORTE DESCENTRALIZADO - PROVIAS DESCENTRALIZADO PRESUP. CONTRAT. S/. 15,739,440.40

UBICACIÓN : DISTRITO: ARAMANGO, PROVINCIA: BAGUA - AMAZONAS ANTICIPO OTORG. S/. 2,745,453.59

CONTRATISTA : CONSORCIO VIAL VIRGEN DEL PILAR ADEL. EN MAT. S/. 2,360,916.06

RESIDENCIA : ING. WILBERT AGUIRRE GONZALEZ I.G.V. 0.00%

SUPERVISIÓN : CONSORCIO SUPERVISOR PALMITO

AMORTIZ. DELANTO DED. DEL ADELANTO 10% GARANTIA AVANCE AVANCE


MONTO VALORIZ.
PERIODO VALORIZADO REAJUSTES DE FIEL I.G.V. NETO A PAGAR FÍSICO PROGR.
BRUTO NETA
ANTICIPO MAT. ANTICIPO MATERIALES CUMPLIMIENTO ACUMULADO ACUMULADO

VALORIZ. 01 (Del 20 al 31 de Octubre del 2022) 9,373.55 0.00 1,406.03 0.00 0.00 0.00 0.00 7,967.52 0.00 7,967.52 0.06% 0.06%

VALORIZ. 02 (Del 01 al 30 de Noviembre de 2022) 64,184.04 0.00 9,627.61 0.00 0.00 0.00 0.00 54,556.43 0.00 54,556.43 0.41% 0.47%

VALORIZ. 03 (Del 01 al 31 de Diciembre de 2022) 65,163.98 0.00 9,774.60 0.00 0.00 0.00 0.00 55,389.38 0.00 55,389.38 0.41% 0.88%

TOTAL 138,721.57 0.00 20,808.24 0.00 0.00 0.00 0.00 117,913.33 0.00 117,913.33 0.41% 0.47%

NETO A PAGARSE AL CONTRATISTA EN LA PRESENTE VALORIZACION :


SON: #VALUE!

SESENTA Y NUEVE MIL OCHOCIENTOS QUINCE CON 76/100 SOLES


VALORIZACIÓN DE OBRA N° 03 - DICIEMBRE - 2022
(Del 1 al 31 de DICIEMBRE de 2022)
OBRA : "CONV-PROC-028-2022-MTC/21-LPI: MEJORAMIENTO DEL CAMINO VECINAL EMP. PE-5NC-VALENCIA – EL PALMITO – GUAYAQUIL – DV. CAMPO BONITO – DV. CORAZON DE MARIA – DV. LIMON – DV. MONTE SECO – EL PORVENIR – SECTOR EL ARENAL, DIST. ARAMANGO – PROV. BAGUA – DPTO. AMAZONAS"
ENTIDAD : PROYECTO ESPECIAL DE INFRAEST. DE TRANSPORTE DESCENTRALIZADO - PROVIAS DESCENTRALIZADO PRECIO REFERENCIAL S/. 15,203,480.07 (Sin./IGV)
UBICACIÓN : DISTRITO: ARAMANGO, PROVINCIA: BAGUA - AMAZONAS PREC. CONTRATADO S/. 15,739,440.40 (Sin./IGV)
CONTRATISTA : CONSORCIO VIAL VIRGEN DEL PILAR PLAZO DE EJECUCION: 180 DIAS CALENDARIOS F
SUPERVISOR : CONSORCIO SUPERVISOR PALMITO
PRESUPUESTO BASE (S/.) ACUMULADO ANTERIOR VALORIZACIÓN DEL MES ACUMULADO ACTUAL SALDO POR VALORIZAR
PARTIDA DESCRIPCIÓN UND. METRADO PRECIO PARCIAL SUB TOTAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %
UNITARIO
01 TRABAJOS PRELIMINARES 126,769.09
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 45,000.00 45,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 45,000.00 100.00%
01.02 TOPOGRAFIA Y GEOREFERENCIACION km 18.88 2,447.10 46,201.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.88 46,201.25 100.00%
01.03 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL glb 1.00 10,036.90 10,036.90 0.00 0.00 0.00% 0.30 3,011.07 30.00% 0.30 3,011.07 30.00% 0.70 7,025.83 70.00%
01.04 CAMPAMENTO glb 1.00 25,530.94 25,530.94 0.30 7,659.28 30.00% 0.30 7,659.28 30.00% 0.60 15,318.56 60.00% 0.40 10,212.38 40.00%
02 MOVIMIENTO DE TIERRAS 2,269,464.37
02.01 DESBROCE Y LIMPIEZA EN ZONAS BOSCOSA ha 9.30 2,335.36 21,718.85 6.25 14,596.00 67.20% 3.05 7,122.85 32.80% 9.30 21,718.85 100.00% 0.00 0.00 0.00%
02.02 EXCAVACION EN MATERIAL SUELTO m3 157,986.05 4.17 658,801.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 157,986.05 658,801.83 100.00%
02.03 EXCAVACION EN ROCA FRACTURADA (SUELTA) m3 47,738.18 9.48 452,557.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 47,738.18 452,557.95 100.00%
02.04 EXCAVACION EN ROCA FIJA m3 7,068.59 10.55 74,573.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7,068.59 74,573.62 100.00%
02.05 TERRAPLEN CON MATERIAL PROPIO m3 20,072.23 11.61 233,038.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20,072.23 233,038.59 100.00%
02.06 PERFILADO Y COMPACTACION DE SUBRASANTE m2 95,915.64 3.43 328,990.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 95,915.64 328,990.65 100.00%
02.07 MEJORAMIENTO DE SUB-RASANTE m2 11,113.60 36.61 406,868.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11,113.60 406,868.90 100.00%
02.08 CONFORMACION Y ACOMODO DE DME m3 32,716.19 2.84 92,913.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 32,716.19 92,913.98 100.00%
03 PAVIMENTOS 4,705,432.66
03.01 BASE GRANULAR ESTABILIZADA m3 16,052.97 64.19 1,030,440.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16,052.97 1,030,440.14 100.00%
03.02 IMPRIMACION ASFALTICA m2 99,485.45 6.46 642,676.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 99,485.45 642,676.01 100.00%
03.03 RIEGO DE LIGA m2 99,485.45 4.81 478,525.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 99,485.45 478,525.01 100.00%
03.04 TRATAMIENTO SUPERFICIAL BICAPA CON EMULSION ASFALTICA m2 99,485.45 25.67 2,553,791.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 99,485.45 2,553,791.50 100.00%
04 OBRAS DE ARTE Y DRENAJE 2,276,527.60
04.01 CUNETAS 1,084,906.22
04.01.01 CUNETA REVESTIDA m 13,936.00 77.02 1,073,350.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13,936.00 1,073,350.72 100.00%
04.01.02 CUNETA SIN REVESTIR m 4,202.00 2.75 11,555.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4,202.00 11,555.50 100.00%
04.02 ALCANTARILLAS MCA 867,985.26
04.02.01 TRAZO Y REPLANTEO m2 1,430.45 14.30 20,455.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,430.45 20,455.44 100.00%
04.02.02 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 1,430.45 7.28 10,413.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,430.45 10,413.68 100.00%
04.02.03 RELLENO PARA ESTRUCTUTRAS m3 231.85 26.24 6,083.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 231.85 6,083.74 100.00%
04.02.04 CONCRETO F'C= 210 KG/CM2 m3 561.28 531.82 298,499.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 561.28 298,499.93 100.00%
04.02.05 SOLADO DE CONCRETO f´c= 140 kg/cm2 E=0.10 M m3 63.00 440.05 27,723.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.00 27,723.15 100.00%
04.02.06 ENCOFRADO Y DESENCOFRADO m2 2,959.11 56.70 167,781.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,959.11 167,781.54 100.00%
04.02.07 REVEST. DE PIEDRA EMBOQ. CONCRETO FC= 175 KG/CM2 + 30% P m3 93.58 59.80 5,596.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 93.58 5,596.08 100.00%
04.02.08 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 42,765.38 7.75 331,431.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 42,765.38 331,431.70 100.00%
04.03 BADEN 204,781.68
04.03.01 EXCAVACION PARA ESTRUCTURAS m3 266.20 7.28 1,937.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 266.20 1,937.94 100.00%
04.03.02 RELLENO CON MATERIAL GRANULAR COMPACTADO m3 50.12 49.30 2,470.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 50.12 2,470.92 100.00%
04.03.03 ENCOFRADO Y DESENCOFRADO m2 300.12 56.70 17,016.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 300.12 17,016.80 100.00%
04.03.04 CONCRETO F'C= 210 KG/CM2 m3 137.90 531.82 73,337.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 137.90 73,337.98 100.00%
04.03.05 EMBOQUILLADO DE MAMP. DE PIEDRA f'c=175 kg/cm2 m3 57.75 316.43 18,273.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 57.75 18,273.83 100.00%
04.03.06 JUNTAS ASFALTICAS m 238.00 14.32 3,408.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 238.00 3,408.16 100.00%
04.03.07 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 11,398.20 7.75 88,336.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11,398.20 88,336.05 100.00%
04.04 MURO DE GRAVEDAD 113,045.60
04.04.01 LIMPIEZA DE TERRENO MANUAL m2 154.42 4.01 619.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 154.42 619.22 100.00%
04.04.02 TRAZO Y REPLANTEO m2 154.42 14.30 2,208.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 154.42 2,208.21 100.00%
04.04.03 EXCAVACION DE TERRENO NATURAL m3 226.97 7.28 1,652.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 226.97 1,652.34 100.00%
04.04.04 RELLENO CON MATERIAL GRANULAR DE PRESTAMO m3 65.28 49.30 3,218.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 65.28 3,218.30 100.00%
04.04.05 SOLADO DE CONCRETO f´c= 140 kg/cm2 E=0.10 M m2 69.60 16.58 1,153.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 69.60 1,153.97 100.00%
04.04.06 CONCRETO f'c=175 kg/cm2 + 30% PG m3 157.54 517.20 81,479.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 157.54 81,479.69 100.00%
04.04.07 ENCOFRADO Y DESENCOFRADO m2 341.23 56.70 19,347.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 341.23 19,347.74 100.00%
04.04.08 CURADO DE CONCRETO m2 264.01 12.75 3,366.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 264.01 3,366.13 100.00%
04.05 LIMPIEZA DE PUENTES 5,597.76
04.05.01 LIMPIEZA DE PUENTES m 48.00 116.62 5,597.76 48.00 5,597.76 100.00% 0.00 0.00 0.00% 48.00 5,597.76 100.00% 0.00 0.00 0.00%
04.06 LIMPIEZA DE ALCANTARILLAS 211.08
04.06.01 LIMPIEZA DE ALCANTARILLAS und 3.00 70.36 211.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.00 211.08 100.00%
05 TRANSPORTE DE MATERIAL 1,993,020.68
05.01 TRANSPORTE DE BASE GRANULAR PARA D<=1 KM m3k 15,118.94 4.75 71,814.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15,118.94 71,814.97 100.00%
05.02 TRANSPORTE DE BASE GRANULAR PARA D>1 KM m3k 25,589.26 0.73 18,680.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 25,589.26 18,680.16 100.00%
05.03 TRANSPORTE DE MEZCLA ASFALTICA PARA D<= 1 KM m3k 5,042.07 5.55 27,983.49 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,042.07 27,983.49 100.00%
05.04 TRANSPORTE DE MEZCLA ASFALTICA PARA D> 1 KM m3k 84,432.76 0.73 61,635.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 84,432.76 61,635.91 100.00%
05.05 TRANSPORTE DE MATERIAL EXCEDENTE D< =1 KM m3k 184,877.86 4.84 894,808.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 184,877.86 894,808.84 100.00%
05.06 TRANSPORTE DE MATERIAL EXCEDENTE D> 1 KM m3k 1,208,022.78 0.76 918,097.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,208,022.78 918,097.31 100.00%
06 SEÑALIZACION 964,001.37
06.01 SEÑALES INFORMATIVAS m2 33.35 2,813.50 93,830.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 33.35 93,830.23 100.00%
06.02 SEÑALES PREVENTIVAS und 194.00 2,766.67 536,733.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 194.00 536,733.98 100.00%
06.03 SEÑALES REGLAMENTARIAS und 39.00 2,813.57 109,729.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 39.00 109,729.23 100.00%
06.04 POSTES KILOMETRICOS und 19.00 374.84 7,121.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.00 7,121.96 100.00%
06.05 MARCAS EN EL PAVIMENTO m2 3,810.10 9.34 35,586.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,810.10 35,586.33 100.00%
06.06 REDUCTORES DE VELOCIDAD m 8.00 565.83 4,526.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 4,526.64 100.00%
06.07 TACHAS RETROFLECTIVAS und 3,260.00 15.95 51,997.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,260.00 51,997.00 100.00%
06.08 GUARDAVIAS m 575.00 216.48 124,476.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 575.00 124,476.00 100.00%
07 PLAN DE MANEJO AMBIENTAL 92,192.75
07.01 PROTECCION DE RECURSOS NATURALES glb 1.00 10,878.00 10,878.00 0.00 0.00 0.00% 0.30 3,263.40 30.00% 0.30 3,263.40 30.00% 0.70 7,614.60 70.00%
07.02 PROGRAMA DE CIERRE glb 1.00 81,314.75 81,314.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 81,314.75 100.00%
08 PLAN COVID 317,077.63
08.01 PLAN COVID glb 1.00 317,077.63 317,077.63 0.10 31,707.76 10.00% 0.10 31,707.76 10.00% 0.20 63,415.53 20.00% 0.80 253,662.10 80.00%

COSTO DIRECTO 12,744,486.15 12,744,486.15 59,560.80 52,764.36 112,325.17 0.88% 12,632,160.98


GASTOS GENERALES 12.00% C.D. 1,529,338.34 7,147.30 6,331.72 13,479.02 1,515,859.32
UTILIDAD 11.50% C.D. 1,465,615.91 6,849.49 6,067.90 12,917.39 1,452,698.51
SUBTOTAL (VALOR ADJUDICADO) 15,739,440.40 73,557.59 65,163.98 138,721.58 0.88% 15,600,718.81
IGV 0.00% 0.00 0.00 0.00 0.00 0.00
TOTAL PRESUPUESTO 15,739,440.40 73,557.59 65,163.98 138,721.58 15,600,718.81

TOTAL EJECUTADO 15,739,440.40 65,163.98 138,721.58 15,600,718.81

PORCENTAJE DE AVANCE EJECUTADO 100.00% 0.47% 0.41% 0.88% 99.12%

PORCENTAJE DE AVANCE PROGRAMADO 100.00% 0.06% 0.52% 0.58% 99.42%


PORCENTAJE DE ATRASO O ADELANTO RESPECTO AL PROGRAMADO 0.30%
15739440.4

UN MILLON VEINTICUATRO MIL SETENTA CON 40/100 SOLES


45,000.00 -
46,201.25 -
10,036.90 -
25,530.94 -
0.00 -
21,718.85 -
658,801.83 -
452,557.95 -
74,573.62 -
233,038.59 -
328,990.65 -
406,868.90 -
92,913.98 -
0.00 -
1,030,440.14 -
642,676.01 -
478,525.01
2,553,791.50 -
0.00 -
0.00 -
1,073,350.72 -
11,555.50 -
0.00 -
20,455.44 -
10,413.68 -
6,083.74 -
298,499.93 -
27,723.15 -
167,781.54 -
5,596.08 -
331,431.70 -
0.00 -
1,937.94 -
2,470.92 -
17,016.80 -
73,337.98 -
18,273.83 -
3,408.16
88,336.05 -
0.00 -
619.22 -
2,208.21 -
1,652.34 -
3,218.30 -
1,153.97 -
81,479.69 -
19,347.74 -
3,366.13 -
0.00 -
5,597.76 -
0.00 -

0.00 -
71,814.97 -
18,680.16 -
27,983.49 -
61,635.91 -
894,808.84 -
918,097.31 -
0.00 -
93,830.23 -
536,733.98 -
109,729.23 -
7,121.96
35,586.33 -
4,526.64 -
51,997.00 -
124,476.00 -
0.00 -
10,878.00 -
81,314.75 -
0.00 -
317,077.63 -

12,744,486.15 -
1,529,338.34 -
1,465,615.90 -0.01
15,739,440.39 -0.01
0.00 -
15,739,440.39 -0.01 12,429,895.02 -3,309,545.37
15,739,440.39

1.00 100.00%

1.00 100.00%
CUADRO DE CONTROL DE AVANCE FISICO AL MES DE DICIEMBRE - 2022

"CONV-PROC-028-2022-MTC/21-LPI: MEJORAMIENTO DEL CAMINO VECINAL EMP. PE-5NC-VALENCIA – EL PALMITO – GUAYAQUIL – DV. CAMPO BONITO – DV. CORAZON DE
OBRA MARIA – DV. LIMON – DV. MONTE SECO – EL PORVENIR – SECTOR EL ARENAL, DIST. ARAMANGO – PROV. BAGUA – DPTO. AMAZONAS"
ENTIDAD PROYECTO ESPECIAL DE INFRAEST. DE TRANSPORTE DESCENTRALIZADO - PROVIAS DESCENTRALIZADO
UBICACIÓN DISTRITO: ARAMANGO, PROVINCIA: BAGUA - AMAZONAS
CONTRATISTA CONSORCIO VIAL VIRGEN DEL PILAR
RESIDENCIA ING. WILBERT AGUIRRE GONZALEZ
SUPERVISIÓN CONSORCIO SUPERVISOR PALMITO

CUADRO DE AVANCE FISICO


AVANCE AVANCE
PROGRAMADO EJECUTADO ESTADO DE LA
N°VAL Valorización OBRA
MONTO S/. MES ACUM. MONTO S/. MES ACUM.
1 VALORIZACION N° 01 8,790.83 0.06% 0.06% 9,373.55 0.06% 0.06% NORMAL
2 VALORIZACION N° 02 81,836.36 0.52% 0.58% 64,184.04 0.41% 0.47% ATRASADA
3 VALORIZACION N° 03 527,949.35 3.35% 3.93% 65,163.98 0.41% 0.88% ATRASADA
4 VALORIZACION N° 04 1,658,369.26 10.54% 14.47%
5 VALORIZACION N° 05 2,578,723.63 16.38% 30.85%
6 VALORIZACION N° 06 5,829,116.12 37.04% 67.89%
7 VALORIZACION N° 07 5,054,654.85 32.11% 100.00% -
15,739,440.40
AMORTIZACION DE ANTICIPO
OBRA "CONV-PROC-028-2022-MTC/21-LPI: MEJORAMIENTO DEL CAMINO VECINAL EMP. PE-5NC-VALENCIA – EL PALMITO – GUAYAQUIL – DV. CAMPO BONITO – DV.
CORAZON DE MARIA – DV. LIMON – DV. MONTE SECO – EL PORVENIR – SECTOR EL ARENAL, DIST. ARAMANGO – PROV. BAGUA – DPTO. AMAZONAS"
UBICACIÓN DISTRITO: ARAMANGO, PROVINCIA: BAGUA - AMAZONAS
MODALIDAD DE EJECUCION PRECIO UNITARIO
PRESUPUESTO GENERAL S/. 15,739,440.40
CONTRATISTA CONSORCIO VIAL VIRGEN DEL PILAR
SUPERVISOR DE OBRA CONSORCIO SUPERVISOR PALMITO
RESIDENTE DE OBRA ING. WILBERT AGUIRRE GONZALEZ

DESCRIPCION SIN I.G.V. CON I.G.V. PORCENTAJE (%) FECHA


Presupuesto de Obra 15,739,440.40
Anticipo otorgado 2,360,916.06 0.00 15.00% 10/7/2022

VALORIACIONES AMORTIZACION
SUB TOTAL
Ítem DESCRIPCION ACTUAL % ACUMULADO % SALDO %
VB
01 VALORIZACION N° 01 Oct-22 9,373.55 1,406.03 0.06% 1,406.03 0.06% 2,359,510.03 99.94%
02 VALORIZACION N° 02 Nov-22 64,184.04 9,627.61 0.41% 11,033.64 0.47% 2,349,882.42 99.53%
03 VALORIZACION N° 03 Dec-22 65,163.98 9,774.60 0.41% 20,808.24 0.88% 2,340,107.82 99.12%

TOTAL A LA FECHA 138,721.57 20,808.24 11,033.64 0.00


478948.01
GRAFICO COMPARATIVO DE AVANCE MONTO PROGRAMADO VS MONTO EJECUTADO
(CURVA "S")
"CONV-PROC-028-2022-MTC/21-LPI: MEJORAMIENTO DEL CAMINO VECINAL EMP. PE-5NC-VALENCIA – EL PALMITO – GUAYAQUIL – DV. CAMPO BONITO –
OBRA DV. CORAZON DE MARIA – DV. LIMON – DV. MONTE SECO – EL PORVENIR – SECTOR EL ARENAL, DIST. ARAMANGO – PROV. BAGUA – DPTO. AMAZONAS"
UBICACIÓN DISTRITO: ARAMANGO, PROVINCIA: BAGUA - AMAZONAS
MODALIDAD DE EJECUCION PRECIO UNITARIO
PRESUPUESTO GENERAL S/. 15,739,440.40
CONTRATISTA CONSORCIO VIAL VIRGEN DEL PILAR
SUPERVISOR DE OBRA CONSORCIO SUPERVISOR PALMITO
RESIDENTE DE OBRA ING. WILBERT AGUIRRE GONZALEZ
FECHA DE INICIO 20 de octubre de 2022
FECHA PREVISTA DE TERMINACIÓN 17 de abril de 2023
PLAZO DE EJECUCION 180 diás Calendarios
CORRESPONDIENTE AL MES DE DICIEMBRE - 2022

PROGRAMADO EJECUTADO
N° Período mes Monto S/. (S/IGV) % Avance Monto S/. (S/IGV) % Avance
Valoriz.
Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial Acumulado
0 20 de Octubre de 2,022 Inicio 0.00 0.00 0.00% 0.00% - - 0.00% 0.00%
1 31 de octubre de 2022 Oct-22 8,790.83 8,790.83 0.06% 0.06% 9,373.55 9,373.55 0.06% 0.06%
2 30 de noviembre de 2022 Nov-22 81,836.36 90,627.19 0.52% 0.58% 64,184.04 73,557.59 0.41% 0.47%
3 31 de diciembre de 2022 Dec-22 527,949.35 618,576.54 3.35% 3.93% 65,163.98 138,721.57 0.41% 0.88%
4 31 de enero de 2022 Jan-23 1,658,369.26 2,276,945.80 10.54% 14.47% 2000
5 28 de febrero de 2022 Feb-23 2,578,723.63 4,855,669.43 16.38% 30.85% 0.5
6 31 de marzo de 2022 Mar-23 5,829,116.12 10,684,785.55 37.04% 67.89%
7 17 de abril de 2022 Apr-23 5,054,654.85 15,739,440.40 32.11% 100.00%
TOTAL S/. S/. 15,739,440.40 100.00% S/. 138,721.57 0.88%

AVANCE PROGRAMADO VS EJECUTADO


1 CURVA "S"

0.9
% DE AVANCE

0.8

0.7

0.6

0.5

0.4

0.3
43.75
0.2 35.000
34.48
0.1 0.52

0
PERIODO

Estado de avance Atraso en la Ejecución


CONTROL DE CARTAS FIANZAS Y/O POLIZAS
"CONV-PROC-028-2022-MTC/21-LPI: MEJORAMIENTO DEL CAMINO VECINAL EMP. PE-5NC-VALENCIA – EL PALMITO – GUAYAQUIL – DV. CAMPO BONITO – DV. CORAZON DE MARIA – DV.
OBRA LIMON – DV. MONTE SECO – EL PORVENIR – SECTOR EL ARENAL, DIST. ARAMANGO – PROV. BAGUA – DPTO. AMAZONAS"
UBICACIÓN DISTRITO: ARAMANGO, PROVINCIA: BAGUA - AMAZONAS
MODALIDAD DE EJECUCION PRECIO UNITARIO
PRESUPUESTO GENERAL S/. 15,739,440.40
CONTRATISTA CONSORCIO VIAL VIRGEN DEL PILAR
SUPERVISOR DE OBRA CONSORCIO SUPERVISOR PALMITO
RESIDENTE DE OBRA ING. WILBERT AGUIRRE GONZALEZ

ORIGINAL RENOVADA
C/F Nº GARANTE GARANTIZA ESTADO
MONTO FECHA VENC. MONTO FECHA VENC.

E3088-00-2022 SECREX COMPAÑÍA DE SEGUROS DE CREDITO Y GARANTIAS FIEL CUMPLIMIENTO 1,573,944.04 6/10/2023 0.00 SUSTITUIDO
E3486-00-2022 SECREX COMPAÑÍA DE SEGUROS DE CREDITO Y GARANTIAS ANTICIPO 2,360,916.06 1/7/2023 0.00 RENOVAR

.
RESUMEN DE METRADO

PARTIDA DESCRIPCIÓN UND. METRADO

01 TRABAJOS PRELIMINARES
01.03 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL glb 3.00
01.04 CAMPAMENTO glb 0.30
02 MOVIMIENTO DE TIERRAS
02.01 DESBROCE Y LIMPIEZA EN ZONAS BOSCOSA ha 3.05
08 PLAN COVID
08.01 PLAN COVID glb 0.10