COMPUTOS MÉTRICOS
Itém Descripción Unid Cant P.U.
MODULO 1: TRABAJOS COMPLEMENTARIOS
1 INSTALACION DE FAENAS GLB 1 1,500.00
2 REPLANTEO Y TRAZADO GLB 1 1,500.00
3 LIMPIEZA GENERAL DE OBRAS GLB 1 1,500.00
MODULO 2: OBRA GRUESA
4 HORMIGON SIMPLE f'c=210 Kg/cm2 M3 25.13 1400
5 ACERO ESTRUCTURAL fy=4200 Kg/cm2 KG 14.00
6 HORMIGON CICLOPEO 50%P.D. f'c=180Kg/cm2 M3 9.93 643.00
7 LOSA NERVADA EN UNA DIRECCIÓN E=25CM M2 148.27
8 SOLADURA DE PIEDRA M2 80.85 40.00
9 CONTRAPISO 5cm M2 189.33 103.00
10 EXCAVACION SUELO SEMIDURO 0-1.75m M3 31.51 55.00
11 RELLENO Y COMPACTADO M3 126.87 100.00
12 CUBIERTA METALICA M2 95.78 455.00
MODULO 3: OBRA FINA
13 SOBRECIMIENTO DE H°C° 50% P.D. fc'=180kg/cm2 M3 1.34 800.00
14 IMPERMEABILIZACION DE SOBRECIMIENTO ML 44.62 30.00
15 MURO DE LADRILLO 6H, E=10cm M2 286.62 140.00
16 REVOQUE INTERIOR DE YESO M2 299.05 60.00
17 PUERTA INTERIOR PLACA 0,90X2,10 m PZA 3.00 1,260.00
18 PUERTA INTERIOR PLACA DE 4mm 0,80X2,10 m PZA 5.00 1,260.00
19 PUERTA EXT. PRINCIPAL MADERA MACIZA 1 x2,10 m PZA 1.00 1,800.00
20 PUERTA EXT. EN COCINA Y COMEDOR DE ALUMINIO M2 14.00 478.00
21 PUERTA EXT. EN BALCONES DE ALUMINIO M2 13.44 478.00
22 REVESTIMIENTO CERAMICA PREMIUM COCINA M2 4.716 173.00
23 REVESTIMIENTO CERAMICA PREMIUM BAÑOS M2 70.34 173.00
24 PISO FLOTANTE M2 108.05 173.00
25 PISO PORCELANATO COCINA M2 9.72 173.00
26 PISO CERAMICA BAÑOS, BALCONES Y DESPENSA M2 24.45 173.00
27 MESON DE COCINA DE CUARZO SINTETICO M2 3.15 1,000.00
28 REVOQUE EXTERIOR DE CEMENTO M2 122.13 118.00
29 PINTURA EN INTERIORES LATEX O SIMILARES (DOS MANOS) M2 299.05 32.00
30 PINTURA EN EXTERIORES LATEX O SIMILAR (DOS MANOS) M2 122.13 38.00
31 PROV Y COLOC CHAPA PUERTA PRINCIPAL PZA 1.00
32 PROV Y COLOC CHAPA PUERTAS INTERIORES PZA 4.00
33 PROV Y COLOC CHAPA BAÑOS PZA 4.00
34 ZOCALOS DE CERAMICA ML 128.96 42.00
35 CIELO RASO ENLUCIDO DE YESO M2 116.64 76.00
36 CIELO FALSO DRYWALL COCINA M2 9.72 243.00
37 CIELO FALSO PVC M2 59.21 243.00
38 VENTANA DE ALUMINIO M2 22.00 478.00
39 PROV. Y COLOCADO ROPEROS MELAMINA 18MM ML 16.34
40 PROV. Y COLOCADO CAJONERIA BAJA COCINA ML 3.38
41 PROV. Y COLOCADO CAJONERIA ALTA COCINA ML 1.99
42 BARANDA TUBO REDONDO D =50MM Y D=45MM M2 3.83 360.00
43 RELLENO Y COMPACTADO CON MATERIAL RIPIO E=10CM M3 6.08 150.00
44 ADOQUINES DE HORMIGON M2 60.75 150.00
MODULO 4: INSTALACION HIDROSANITARIA
45 EXCAVACION DE 0 A 1 M TERRENO SEMIDURO M3 11.25 55.00
46 CAMA DE MATERIAL CERNIDO E=5cm M3 0.84 150.00
47 PROVISION Y TENDIDO TUBERIA PVC SDR 41 D=6" ML 10 75.00
48 PROVISION Y TENDIDO TUBERIA PVC D=2" ML 22 41.00
49 PROVISION Y TENDIDO TUBERIA PVC D=1 1/2" ML 4.37 0.00
50 PROV. E INST. TUBERIA DE PVC D= 4" bajantes ML 43 48.00
51 RELLENO Y APISONADO MANUAL TIERRA CERNIDA M3 3.36 60.00
52 RELLENO Y COMPACTADO CON TIERRA COMUN M3 9.40 40.00
53 CAMARA DE INSPECCION HºCº 50% P.D. PZA 4 685.00
54 PROV. E INST. REJILLA P/ PISO 15 X 15 CM PZA 4 117.00
55 PROVISION Y COLOCACION REGISTRO DE PVC 6"X4" PZA 10 281.00
56 PROV. E INST. INODORO TANQUE BAJO PZA. 8 789.00
57 PROV. E INST. DE LAVAMANOS C/GRIFO Y ACCES. PZA 8 1,500.00
58 PROV. E INST. DE LAVAPLATOS DOBLE C/GRIFO + ACC PZA 2 800.00
59 PROV. E INST. DUCHA C/ BASE PZA 4 500.00
60 Inst. tendido cañeria de 1" o 32 mm pvc/fusion ml. 42.42 0.00
61 Inst. tendido cañeria de 3/4 o 25 mm pvc/fusion F/C. ml 21.42 0.00
62 Inst. tendido cañeria de 1/2 o 20 mm pvc/fusion (agua caliente). ml. 42.69 0.00
63 LLAVE DE PASO CORTINA COBRE 1/2" agua caliente PZA 10 197.00
64 LLAVE DE PASO CORTINA COBRE 3/4" agua fria PZA 12 0.00
65 LLAVE DE PASO CORTINA COBRE 1" agua PZA 1 0.00
66 PROVISION Y TENDIDO TUBERIA PVC SDR 41 D=6" DESAGUE PLUVIAL ML 20.15 0.00
MODULO 5: INSTALACION ELECTRICA
61 CAJA DE DERIVACION CIRCULAR PVC. PZA 12.00 13.00
62 PUNTO DE ILUMINACION PTO 61.00 150.00
63 LUMINARIA LED PZA 34.00 150.00
64 LUMINARIA SPOT LED PZA 15.00 100.00
65 LUMINARIA DE EXTERIOR PZA 27.00 150.00
66 INTERRUPTOR SIMPLE PZA 0.00 42.00
67 INTERRUPTOR DOBLE PZA 19.00 49.00
68 INTERRUPTOR CONMUTADOR SIMPLE PZA 5.00 45.00
69 INTERRUPTOR CONMUTADOR DOBLE PZA 4.00 55.00
70 CABLEADO ALAMBRE Nº12 AWG TW INC/DUCTEADO ML 3.00 15.00
71 CABLEADO ALAMBRE Nº 10 AWG TW INC/DUCTEADO ML 183.00 17.00
72 PUNTO DE TV CABLE PTO 234.00 100.00
73 PUNTO DE TELEFONO PTO 5.00 100.00
74 PUNTO DE DATOS PTO 2.00 100.00
75 TABLERO DE DISTRIBUCION DE CIRCUITOS ESPECIALES PZA 4.00 800.00
76 TABLERO DE DISTRIBUCION P/5 TERMICOS BIPOLAR PZA 1.00 900.00
77 INTERRUPTOR MAGNETOTERMICO BIPOLAR 32A PZA 1.00 62.00
78 INTERRUPTOR MAGNETOTERMICO BIPOLAR 25A PZA 1.00 84.00
79 INTERRUPTOR MAGNETOTERMICO BIPOLAR 16A PZA 3.00 88.00
80 TOMACORRIENTE SIMPLE TIPO SCHUKO PZA 2.00 38.00
81 TOMACORRIENTE DOBLE ESTILO EUROAMERICANO PZA 4.00 49.00
82 INSTALACION DE TIMBRE PTO 35.00 800.00
83 ACOMETIDA ELECTRICA INC/PUESTA TIERRA GLB 1.00 800.00
84 EXTRACTOR DE AIRE PARA BAÑOS PZA 4.00
MODULO 6: INSTALACION DE GAS
85 GAS DOMICILIARIO ML 37.10
TOTAL
VERIFICAR PRECIOS UNITARIOS
TOTAL

1,500.00
1,500.00 .
1,500.00

35182
0
6384.99
0
3234.156
19501.2784
1732.83
12687.07
43579.9

1,071.38
1,338.52
40,126.94
17,942.88
3,780.00
6,300.00
1,800.00
6,692.00
6,424.32
815.87
12,169.34
18,692.30
1,680.87
4,229.50
3,150.00
14,410.87
9,569.54
4,640.79
0.00
0.00
0.00
5,416.26
8,864.83
2,360.89
14,388.32
10,517.37
0.00
0.00
0.00
1,377.00
911.25
9,112.50
618.73
126.02
750.00
902.00

2,064.00
201.64
375.94
2,740.00
468.00
2,810.00
6,312.00
12,000.00
1,600.00
2,000.00
0.00
0.00
0.00
1,970.00
0.00
0.00
0.00

156.00
9,150.00
5,100.00
1,500.00
4,050.00
0.00
931.00
225.00
220.00
45.00
3,111.00
23,400.00
500.00
200.00
3,200.00
900.00
62.00
84.00
264.00
76.00
196.00
28,000.00
800.00
0.00

0.00
451,694.10 SOLO UNA CASA
(CASA TIPO B+ ALTILLO )
4 HORMIGON SIMPLE f'c=210 Kg/cm2 Unid: M3
Vol. Total
Elemento L(m) A(m) H(m) Volumen (m3) Cant. Observación
(m3)
Cimentaciones
Zapata 100x100 1.00 1.00 0.25 0.25 11 2.75
Zapata 140x100 1.40 1.00 0.25 0.35 1 0.35
Zapata 136x100 1.36 1.00 0.25 0.35 1 0.35
Zapata 130x100 1.30 1.00 0.25 0.28 1 0.28
Zapata 91.75x100 0.92 1.00 0.25 0.28 1 0.28
Columnas de arranque
Col. Arranq. 35x25 0.35 0.25 1.70 0.15 11 1.64
Columnas planta baja
Columna 35x25 0.30 0.20 2.63 0.16 9 1.42
Columnas 1er piso
Columna 35x25 0.30 0.20 2.5 0.15 11 1.650
Columnas altillo
Columna 35x25 0.30 0.20 2.4 0.14 6 0.864
Vigas de arriostre (Planta baja)
Pórtico 1 3.44 0.20 0.15 0.10 2 0.21
Pórtico 2 2.86 0.20 0.15 0.09 2 0.17
Pórtico 3 3.30 0.20 0.15 0.10 1 0.10
Pórtico 4 2.65 0.20 0.15 0.08 2 0.16
Pórtico 5 4.92 0.20 0.15 0.15 1 0.15
Pórtico 6 5.11 0.20 0.15 0.15 1 0.15
Pórtico 7 2.45 0.20 0.15 0.07 2 0.15
Pórtico 8 0.76 0.20 0.15 0.02 1 0.02
Pórtico 9 5.09 0.20 0.15 0.15 1 0.15
Pórtico 10 1.64 0.20 0.15 0.05 1 0.05
Vigas (Planta primer piso)
Pórtico 1 2.45 0.20 0.15 0.07 2 0.15
Pórtico 2 3.44 0.20 0.15 0.10 2 0.21
Pórtico 3 2.86 0.20 0.15 0.09 2 0.17
Pórtico 4 2.65 0.20 0.15 0.08 3 0.24
Pórtico 5 3.10 0.20 0.15 0.09 2 0.19
Pórtico 6 3.25 0.20 0.15 0.10 2 0.20
Pórtico 7 3.82 0.20 0.15 0.11 3 0.34
Pórtico 8 4.61 0.20 0.15 0.14 1 0.14
Pórtico 9 1.05 0.20 0.15 0.03 2 0.06
Pórtico 10 3.03 0.20 0.15 0.09 1 0.09
Pórtico 11 1.03 0.20 0.15 0.03 1 0.03
Pórtico 12 0.76 0.20 0.15 0.02 1 0.02
Pórtico 13 0.69 0.20 0.15 0.02 1 0.02
Vigas (Planta altillo)
Pórtico 1 3.44 0.20 0.15 0.10 2 0.21
Pórtico 2 3.82 0.20 0.15 0.11 2 0.23
Pórtico 3 2.65 0.20 0.15 0.08 2 0.16
Pórtico 4 2.90 0.20 0.15 0.09 1 0.09
Pórtico 5 1.64 0.20 0.15 0.05 1 0.05
Gradas - escaleras
Peldaño tramo recto 0.98 0.31 0.17 0.03 14 0.35 Area=(A*H/2), X4
Peldaño tramo descanso 1 1.00 0.17 0.09 2 0.17 Area=(A*H/2), X4
Losa inclinada techo
VL1 3.86 1.16 0.15 0.67 1 0.67
VL2 3.99 1.15 0.15 0.69 2 1.38
VL3 7.32 4.14 0.15 4.55 2 9.09
Losa inclinada techo e= 5 cm
Espesor Área Vol (m3) Cant. Total.
Carpeta 5cm 0.00 2 0.00
Volumen total Hormigòn Simple f'c=210 kg/cm2 (m3)= 25.13
6 HORMIGON CICLOPEO 50%P.D. f'c=180Kg/cm2 Unid: M3
Vol. Total
Elemento L(m) A(m) H(m) Volumen (m3) Cant. Observación
(m3)
Planta baja
M5 13.76 0.50 0.50 3.44 1 3.44
M6 25.96 0.50 0.50 6.49 1 6.49
Area total hormigon ciclopeo (m3)= 9.93

7 LOSA NERVADA EN UNA DIRECCIÓN E=25CM Unid: M2


Area Total
Elemento L(m) A(m) H(m) Area (m2) Cant. Observación
(m2)
Planta primer piso
Losa 1 0 12.25 1 12.25
Losa 2 0 3.51 1 3.51
Losa 3 0 13.54 1 13.54
Losa 4 0 4.60 1 4.60
Losa 5 0 6.15 1 6.15
Losa 6 0 14.25 1 14.25
Losa 7 0 4.64 1 4.64
Losa 8 0 4.67 1 4.67
Losa 9 0 12.66 1 12.66
Losa 10 0 3.68 1 3.68
Planta altillo
Losa 1 0 4.45 1 4.45
Losa 2 0 15.54 1 15.54
Losa 3 0 4.83 1 4.83
Losa 4 0 4.60 1 4.60
Planta cubierta
Losa 1 0 4.45 1 4.45
Losa 2 0 29.87 1 29.87
Losa 3 0 4.60 1 4.60
Area total losa aligerada armada en una direccion (m2)= 148.27

8 SOLADURA DE PIEDRA Unid: M2


Vol. Total
Elemento L(m) A(m) H(m) Volumen (m2) Cant. Observación
(m2)
Planta baja.
Ingreso 1 7.98 1 7.98
Ingreso 2 8.86 1 8.86
Escaleras 6.15 1 6.15
Living - Comedor 29.89 1 29.89
Cocina 9.74 1 9.74
Despensa 2.34 1 2.34
Baño 2.31 1 2.31
Patio trasero 13.59 1 13.59
Volumen total Soladura de piedra. 1 vivienda (m2)= 80.85
Volumen total Soladura de piedra. 2 vivienda (m2)= 161.71

9 CONTRAPISO 5cm Unid: M2


Vol. Total
Elemento L(m) A(m) H(m) Volumen (m2) Cant. Observación
(m2)
Planta baja.
Ingreso 1 21.27 1 21.27 Una vivienda
Escaleras 6.15 1 6.15 Una vivienda
Living - Comedor 30.50 1 30.50 Una vivienda
Cocina 10.00 1 10.00 Una vivienda
Despensa 2.34 1 2.34 Una vivienda
Baño 2.33 1 2.33 Una vivienda
Patio trasero 13.21 1 13.21 Una vivienda
Planta primer piso.
Balcon 1 3.95 1 3.95 Una vivienda
Dormitorio 1(MASTER SUITE) 12.62 1 12.62 Una vivienda
Vestidor 4.67 1 4.67 Una vivienda
Baño 1 4.64 1 4.64 Una vivienda
Baño 2 4.60 1 4.60 Una vivienda
Estar familiar 14.25 1 14.25 Una vivienda
Dormitorio 2 12.25 1 12.25 Una vivienda
Dormitorio 3 13.65 1 13.65 Una vivienda
Balcon 2 3.33 1 3.33 Una vivienda
Planta altillo.
Hall 2 4.45 1 4.45 Una vivienda
Baño 3 4.83 1 4.83 Una vivienda
Estar familiar 15.70 1 15.70 Una vivienda
hall 3 4.60 1 4.60 Una vivienda
Volumen total Contra piso. 1 vivienda (m2)= 189.33
Volumen total Contra piso. 2 vivienda (m2)= 378.67

10 EXCAVACION SUELO SEMIDURO 0-1.75m Unid: M3


Vol. Total
Elemento L(m) A(m) H(m) Volumen (m3) Cant. Observación
(m3)
Planta baja
M5 13.76 0.50 0.50 3.44 1 3.44
M6 25.96 0.50 0.50 6.49 1 6.49
Zapatas
Zapata 100x100 1.00 1.00 1.35 1.35 11 14.85
Zapata 140x100 1.40 1.00 1.35 1.89 1 1.89
Zapata 136x100 1.36 1.00 1.35 1.84 1 1.84
Zapata 130x100 1.30 1.00 1.35 1.76 1 1.76
Zapata 91.75x100 0.92 1.00 1.35 1.24 1 1.24
Area total excavacion (m3)= 31.51

11 RELLENO Y COMPACTADO Unid: M3


Vol. Total
Elemento L(m) A(m) H(m) Volumen (m3) Cant. Observación
(m3)
Cimentaciones
Zapata 100x100 1.00 1.00 1.35 1.35 11 14.85
columna 25x35 -0.25 0.35 1.35 -0.12 11 -1.30 descuento
Zapata 140x100 1.40 1.00 1.35 1.89 1 1.89
columna 25x35 -0.25 0.35 1.35 -0.12 1 -0.12 descuento
Zapata 136x100 1.36 1.00 1.35 1.84 1 1.84
columna 25x35 -0.25 0.35 1.35 -0.12 1 -0.12 descuento
Zapata 130x100 1.30 1.00 1.35 1.76 1 1.76
columna 25x35 -0.25 0.35 1.35 -0.12 1 -0.12 descuento
Zapata 91.75x100 0.92 1.00 1.35 1.24 1 1.24
columna 25x35 -0.25 0.35 1.35 -0.12 1 -0.12 descuento
Áreas de ambientes
Ingreso 1 21.27 0.3 6.38 2 42.54 Una vivienda
Escaleras 6.15 0.3 1.84 1 6.15 Una vivienda
Living - Comedor 30.50 0.3 9.15 1 30.50 Una vivienda
Cocina 10.00 0.3 3.00 1 10.00 Una vivienda
Despensa 2.34 0.3 0.70 1 2.34 Una vivienda
Baño 2.33 0.3 0.70 1 2.33 Una vivienda
Patio trasero 13.21 0.3 3.96 1 13.21 Una vivienda
VOOLUMEN TOTAL RELLENO Y COMPACTADO (M3) 126.87

12 CUBIERTA METALICA Unid: M2


Vol. Total
Elemento L(m) A(m) H(m) Volumen (m2) Cant. Observación
(m2)
Cubierta primer piso
C1 12.47 2 24.95
C2 11.47 2 22.94
Cubierta altillo
C5 12.47 2 24.95
C6 11.47 2 22.94
Area total cubierta metalica. (m2)= 95.78
13 SOBRECIMIENTO DE H°C° 50% P.D. fc'=180kg/cm2 Unid:
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Vivienda 1 Tipo
M1 5.11 0.30 0.10 0.15 1 0.15
M2 2.86 0.30 0.10 0.09 2 0.17
M3 3.44 0.30 0.10 0.10 2 0.21
M4 3.82 0.30 0.10 0.11 1 0.11
M5 2.65 0.30 0.10 0.08 3 0.24
M6 2.45 0.30 0.10 0.07 2 0.15
M7 0.76 0.30 0.10 0.02 1 0.02
M8 3.30 0.30 0.10 0.10 1 0.10
M9 3.10 0.30 0.10 0.09 1 0.09
M10 1.59 0.30 0.10 0.05 1 0.05
M11 1.49 0.30 0.10 0.04 1 0.05
Total sobre cimiento, 2 casas (m3)= 1.34

14 IMPREMEABILIZACION SOBRECIMIENTO, CARTON ASFALTICO Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(ml) (ml)
Vivienda 1 Tipo
M1 5.11 1 5.11
M2 2.86 2 5.71
M3 3.44 2 6.89
M4 3.82 1 3.82
M5 2.65 3 7.95
M6 2.45 2 4.90
M7 0.76 1 0.76
M8 3.30 1 3.30
M9 3.10 1 3.10
M10 1.59 1 1.59
M11 1.49 1 1.49
Total impermeabilizacion sobrecimiento 2 casas (ml)= 44.62

15 MURO DE LADRILLO 6H, E=10cm Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Vivienda 1 Tipo (PLANTA BAJA)
M1 5.11 2.60 13.28 1 13.28
P1 -2.59 2.30 -5.95 1 -5.95
M2 2.86 2.60 7.42 2 14.85
M3 3.44 2.60 8.95 2 17.91
M4 3.82 2.60 9.92 1 9.92
P2 -1.00 2.10 -2.10 1 -2.10
V1 -0.83 1.70 -1.41 1 -1.42
M5 2.65 2.60 6.89 3 20.67
V2 -1.55 1.70 -2.64 1 -2.64
P3 0.80 2.10 1.68 1 1.68
P4 -1.90 2.30 -4.37 1 -4.37
M6 2.45 2.60 6.37 2 12.74
M7 0.76 2.66 2.02 1 2.02
M8 3.30 2.60 8.58 1 8.58
M9 3.10 2.60 8.06 1 8.06
P5 -0.80 2.10 -1.68 1 -1.68
M10 1.59 2.60 4.14 1 4.14
M11 1.49 2.60 3.88 1 3.88
Vivienda 1 Tipo (Planta Alta)
M1 6.17 2.50 15.41 1 15.41
P1 -2.59 2.30 -5.95 1 -5.95
M2 2.86 2.50 7.14 2 14.28
M3 3.44 2.50 8.61 2 17.22
M4 2.45 2.50 6.13 4 24.50
M5 3.26 2.50 8.14 2 16.28
V1 -0.80 1.88 -1.50 1 -1.50
M6 2.65 2.50 6.63 3 19.88
P2 -1.15 2.10 -2.42 1 -2.42
M7 3.82 2.50 9.54 2 19.08
P3 -0.90 2.10 -1.89 3 -5.67
M8 3.92 2.50 9.79 1 9.79
P4 -1.83 2.10 -3.85 1 -3.85
V2 -0.73 1.70 -1.23 1 -1.23
M9 3.10 2.50 7.75 1 7.75
M10 3.54 2.50 8.86 1 8.86
P5 -0.80 2.10 -1.68 1 -1.68
V2 -1.90 2.50 -4.75 1 -4.75
M11 0.76 2.50 1.91 1 1.91
M12 0.45 2.50 1.13 1 1.13
M13 0.28 2.50 0.70 1 0.70
M14 4.78 0.53 2.54 1 2.54
M15 5.77 0.53 3.06 1 3.06
Vivienda 1 Tipo PISO ALTILLO
M1 3.44 2.40 8.27 2 16.53
M2 3.82 2.40 9.16 2 18.31
V1 -1.84 1.80 -1.42 1 -1.42
V2 -1.67 0.50 -0.83 1 -0.83
M3 2.65 2.40 6.36 2 12.72
V3 -0.80 0.70 -1.42 1 -1.42
V4 -1.65 1.00 -1.65 1 -1.65
M4 2.90 2.40 6.96 1 6.96
M5 3.54 2.40 8.51 1 8.51
P1 -0.80 2.10 -1.42 1 -1.42
ESCALERAS -1.90 2.40 -4.56 1 -4.56
Vivienda 1 Tipo Cubierta- muros PARAPETO ALTILLO
MPA-1 6.79 0.85 5.77 0.00
MPA-2 2.45 0.85 2.08 0.00
MPA-3 3.45 0.85 2.93 0.00
MPA-4 3.55 0.85 3.02 0.00
MPA-5 3.25 0.85 2.76 0.00
MPA-6 -1.00 2.10 -2.10 0.00
MPA-7 -0.83 1.70 -1.41 0.00
Total Muro ladrillo 6H= 10 cm. - 2 casas (m2)= 286.62

16 REVOQUE INTERIOR DE YESO Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
Living, comedor, gradas 23.52 2.60 61.15 1 61.15
P1 -2.59 2.30 -5.96 1 -5.96
P2 -1.00 2.10 -2.10 1 -2.10
V1 -0.83 1.70 -1.41 1 -1.41
INGRESO COCINA -3.06 2.60 -7.94 1 -7.94
INGRESO ESCALERAS -1.90 2.60 -4.94 1 -4.94
Cocina 8.16 2.60 21.20 1 21.20
P3 -1.90 2.10 -3.99 1 -3.99
P4 -0.80 2.10 -1.68 1 -1.68
Despensa 5.69 2.60 14.79 1 14.79
P5 -0.80 2.10 -1.68 1 -1.68
Baño 5.89 0.30 1.77 1 1.77
ESCALERAS 8.00 0.30 2.40 1 2.40
V2 -1.55 1.70 -2.64 1 -2.64
Bloque 1 - Vivienda 1 - Planta primer piso.
Dormitorio 1, Vestidor 22.43 2.50 56.08 1 56.08
P1 -0.90 2.10 -1.89 1 -1.89
P2 -0.80 2.10 -1.68 1 -1.68
P3 -0.80 2.10 -1.68 1 -1.68
P4 -1.83 2.10 -3.85 1 -3.85
V1 -0.73 0.90 -0.65 1 -0.65
Dormitorio 2 14.57 2.50 36.44 1 36.44
P5 -0.90 2.10 -1.89 1 -1.89
P6 -2.00 2.10 -4.20 1 -4.20
Dormitorio 3 15.18 2.50 37.94 1 37.94
P7 -1.15 2.10 -2.42 1 -2.42
P8 -0.90 2.10 -1.89 1 -1.89
V2 -0.43 0.90 -0.39 1 -0.39
Baño 1 8.99 0.50 4.49 1 4.49
P9 -0.80 2.10 -1.68 1 -1.68
Baño 2 9.50 0.50 4.75 1 4.75
P10 -0.80 2.10 -1.68 1 -1.68
Gradas-HALL 21.52 2.50 53.79 1 53.79
P11 -0.90 2.10 -1.89 1 -1.89
P12 -0.80 2.10 -1.68 1 -1.68
P13 -0.90 2.10 -1.89 1 -1.89
P14 -0.80 2.10 -1.68 1 -1.68
Bloque 1 - Vivienda 1 - Planta altillo.
Estar familiar-gradas 21.92 2.40 52.60 1 52.60
V4 -1.84 1.80 -3.31 1 -3.32
V6 -1.67 0.50 -0.83 1 -0.83
Baño 3 8.99 2.40 21.57 1 21.57
P14 -0.80 2.10 -1.68 1 -1.68
V7 -0.80 0.90 -0.72 1 -0.72
Total Revoque interior de yeso. - 1 Casa (m2)= 299.05
Total Revoque interior de yeso. - 2 Casa (m2)= 598.10

17 PUERTA INTERIOR PLACA 0,90X2,10 m Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
P 0,90x2,10 0 0.00
Bloque 1 - Vivienda 1 - Planta primer piso.
P 0,90x2,10 3 3.00
Bloque 1 - Vivienda 1 - Planta altillo.
P 0,90x2,10 0 0.00
Total Puerta interior placa 0,9x2,10. - 1 Casa (pza)= 3.00
Total Puerta interior placa 0,9x2,10. -2Casa (pza)= 6.00

18 PUERTA INTERIOR PLACA DE 4mm 0,80X2,10 m Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
P 0,80x2,10 2 2.00
Bloque 1 - Vivienda 1 - Planta primer piso.
P 0,80x2,10 2 2.00
Bloque 1 - Vivienda 1 - Planta altillo.
P 0,80x2,10 1 1.00
Total PUERTA INTERIOR PLACA DE 4mm 0,80X2,20 m. - 1 Casa (pza)= 5.00
Total PUERTA INTERIOR PLACA DE 4mm 0,80X2,20 m. -2Casa (pza)= 10.00

19 PUERTA EXT. PRINCIPAL MADERA MACIZA 1 x2,10 m Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
P 1,00x2,10 1 1.00
Bloque 1 - Vivienda 1 - Planta primer piso.
P 1,00x2,10 0 0.00
Bloque 1 - Vivienda 1 - Planta altillo.
P 1,00x2,10 0 0.00
Total PUERTA EXT. PRINCIPAL MADERA MACIZA 1 x2,20 m. - 1 Casa (pza)= 1.00
Total PUERTA EXT. PRINCIPAL MADERA MACIZA 1 x2,20 m. -2Casa (pza)= 2.00

20 PUERTA EXT. EN COCINA Y COMEDOR DE ALUMINIO Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
P 2,50x2,80 2.50 2.80 7.00 1 7.00
P 2,50x2,80 2.50 2.80 7.00 1 7.00
Total PUERTA EXT. EN COCINA Y COMEDOR DE ALUMINIO. - 1 Casa (m2)= 14.00
Total PUERTA EXT. EN COCINA Y COMEDOR DE ALUMINIO. -2Casa (m2)= 28.00

21 PUERTA EXT. EN BALCONES DE ALUMINIO Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta primer piso.
P 2,40x2,10 2.40 2.10 5.04 1 5.04
P 2x2,10 2.00 2.10 4.20 2 8.40
Total PUERTA EXT. EN BALCONES DE ALUMINIO. - 1 Casa (m2)= 13.44
Total PUERTA EXT. EN BALCONES DE ALUMINIO. - 2 Casa (m2)= 26.88

22 REVESTIMIENTO CERAMICA PREMIUM COCINA Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta primer piso.
Cocina 5.71 0.65 3.71 1 3.71
Total REVESTIMIENTO CERAMICA PREMIUM COCINA. - 1 Casa (m2)= 3.71
Total REVESTIMIENTO CERAMICA PREMIUM COCINA. - 2 Casa (m2)= 7.42
23 REVESTIMIENTO CERAMICA PREMIUM BAÑOS Unid:
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta primer piso.
Baño PB 5.96 2.50 14.91 1 14.91
P1 -0.80 2.10 -1.68 1 -1.68
Bloque 1 - Vivienda 1 - Planta primer piso.
Baño 1 9.53 2.40 22.86 1 22.86
V1 -0.70 1.70 -1.19 1 -1.19
P2 -0.80 2.10 -1.68 1 -1.68
Baño 2 8.96 2.30 20.61 1 20.62
P3 -0.80 2.10 -1.68 1 -1.68
Bloque 1 - Vivienda 1 - Planta altillo.
Baño 3 8.99 2.30 20.67 1 20.67
P4 -0.80 2.10 -1.68 1 -1.68
V2 -1.00 0.80 -0.80 1 -0.80
Total REVESTIMIENTO CERAMICA PREMIUM COCINA - 1 Casa (m2)= 70.34
Total REVESTIMIENTO CERAMICA PREMIUM COCINA - 2 Casa (m2)= 140.69

24 PISO FLOTANTE Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta primer piso.
Living, comedor, escalera 35.99 1 35.99
Bloque 1 - Vivienda 1 - Planta primer piso.
Vestidor 4.55 1 4.55
Hall 14.25 1 14.25
Dormitorio 1 12.49 1 12.49
Dormitorio 2 13.34 1 13.34
Dormitorio 3 12.10 1 12.10
Bloque 1 - Vivienda 1 - Planta altillo.
Estar familiar 15.34 1 15.34
Total PISO FLOTANTE - 1 Casa (m2)= 108.05
Total PISO FLOTANTE - 2 Casa (m2)= 216.10

25 PISO PORCELANATO COCINA Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta primer piso.
Cocina 9.72 1 9.72
Total PISO PORCELANATO COCINA - 1 Casa (m2)= 9.72
Total PISO PORCELANATO COCINA - 2 Casa (m2)= 19.43
26 PISO CERAMICA BAÑOS, BALCONES Y DESPENSA Unid:
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta primer piso.
Baño Pb 2.33 1 2.33
Despensa 2.34 1 2.34
Bloque 1 - Vivienda 1 - Planta primer piso.
Baño 1 4.64 1 4.64
Baño 2 4.00 1 4.00
Balcon 1 3.45 1 3.45
Balcon 2 3.50 1 3.51
Bloque 1 - Vivienda 1 - Planta altillo.
Baño 3 4.18 1 4.18

Total PISO CERAMICA BAÑOS, BALCONES Y DESPENSA - 1 Casa (m2)= 24.45


Total PISO CERAMICA BAÑOS, BALCONES Y DESPENSA - 2 Casa (m2)= 48.90

27 MESON DE COCINA DE CUARZO SINTETICO Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta primer piso.
MESON 1 0.60 2.85 1.71 1 1.71
MESON CENTRAL 0.90 1.60 1.44 1 1.44
TotalMESON DE COCINA DE CUARZO SINTETICO - 1 Casa (m2)= 3.15
Total MESON DE COCINA DE CUARZO SINTETICO - 2 Casa (m2)= 6.30

28 REVOQUE EXTERIOR DE CEMENTO Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Planta baja.
Rev 1 6.82 2.6 17.72 1 17.72
V1 0.83 1.7 1.41 1 1.42
P1 -1.00 2.3 -2.30 1 -2.30
Rev 2 4.21 2.6 10.96 1 10.96
P2 -2.59 2.3 -5.95 1 -5.95
Rev 3 3.44 2.6 8.94 1 8.94
Rev 4 0.60 2.6 1.55 1 1.55
Rev 5 2.93 2.6 7.60 1 7.61
P2 -1.90 2.3 -4.37 1 -4.37
Rev 6 2.20 2.6 5.71 1 5.71
Rev 7 1.84 2.6 4.79 1 4.79
Planta Primer Piso
Rev 1 7.16 2.6 18.63 1 18.63
V3 -0.73 1.7 -1.23 1 -1.23
V3 -1.81 2.1 -3.81 1 -3.81
P6 -0.80 1.7 -1.36 1 -1.36
Rev 2 2.94 2.6 7.65 2 15.29
Rev 3 0.92 2.6 2.39 1 2.40
Rev 4 3.03 2.6 7.88 1 7.88
P9 -2.00 2.1 -4.20 1 -4.20
Rev 5 1.20 2.9 3.48 1 3.48
Rev 6 4.13 2.6 10.75 2 21.49
P12 -1.15 2.1 -2.42 1 -2.42
P13 -0.43 1.7 -0.74 1 -0.74
Rev 7 0.75 0.7 0.52 1 0.53
Rev 8 4.23 0.7 2.96 1 2.96
Rev 9 4.13 0.7 2.89 1 2.89
Rev 10 0.62 0.7 0.43 1 0.43
PLANTA ALTILLO
Balcón 13.07 0.70 9.15 1 9.15
Exterior 6.68 0.70 4.68 1 4.68
Total REVOQUE EXTERIOR DE CEMENTO - 1 Casa (m2)= 122.13
Total REVOQUE EXTERIOR DE CEMENTO - 2 Casa (m2)= 244.25

29 PINTURA EN INTERIORES LATEX O SIMILARES (DOS MANOS) Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
Living, comedor, gradas 23.52 2.60 61.15 1 61.15
P1 -2.59 2.30 -5.96 1 -5.96
P2 -1.00 2.10 -2.10 1 -2.10
V1 -0.83 1.70 -1.41 1 -1.41
INGRESO COCINA -3.06 2.60 -7.94 1 -7.94
INGRESO ESCALERAS -1.90 2.60 -4.94 1 -4.94
Cocina 8.16 2.60 21.20 1 21.20
P3 -1.90 2.10 -3.99 1 -3.99
P4 -0.80 2.10 -1.68 1 -1.68
Despensa 5.69 2.60 14.79 1 14.79
P5 -0.80 2.10 -1.68 1 -1.68
Baño 5.89 0.30 1.77 1 1.77
ESCALERAS 8.00 0.30 2.40 1 2.40
V2 -1.55 1.70 -2.64 1 -2.64
Bloque 1 - Vivienda 1 - Planta primer piso.
Dormitorio 1, Vestidor 22.43 2.50 56.08 1 56.08
P1 -0.90 2.10 -1.89 1 -1.89
P2 -0.80 2.10 -1.68 1 -1.68
P3 -0.80 2.10 -1.68 1 -1.68
P4 -1.83 2.10 -3.85 1 -3.85
V1 -0.73 0.90 -0.65 1 -0.65
Dormitorio 2 14.57 2.50 36.44 1 36.44
P5 -0.90 2.10 -1.89 1 -1.89
P6 -2.00 2.10 -4.20 1 -4.20
Dormitorio 3 15.18 2.50 37.94 1 37.94
P7 -1.15 2.10 -2.42 1 -2.42
P8 -0.90 2.10 -1.89 1 -1.89
V2 -0.43 0.90 -0.39 1 -0.39
Baño 1 8.99 0.50 4.49 1 4.49
P9 -0.80 2.10 -1.68 1 -1.68
Baño 2 9.50 0.50 4.75 1 4.75
P10 -0.80 2.10 -1.68 1 -1.68
Gradas-HALL 21.52 2.50 53.79 1 53.79
P11 -0.90 2.10 -1.89 1 -1.89
P12 -0.80 2.10 -1.68 1 -1.68
P13 -0.90 2.10 -1.89 1 -1.89
P14 -0.80 2.10 -1.68 1 -1.68
Bloque 1 - Vivienda 1 - Planta altillo.
Estar familiar-gradas 21.92 2.40 52.60 1 52.60
V4 -1.84 1.80 -3.31 1 -3.32
V6 -1.67 0.50 -0.83 1 -0.83
Baño 3 8.99 2.40 21.57 1 21.57
P14 -0.80 2.10 -1.68 1 -1.68
V7 -0.80 0.90 -0.72 1 -0.72
Total PINTURA EN INTERIORES LATEX O SIMILARES (DOS MANOS). - 1 Casa (m2)= 299.05
Total PINTURA EN INTERIORES LATEX O SIMILARES (DOS MANOS). - 2 Casa (m2)= 598.10

30 PINTURA EN EXTERIORES LATEX O SIMILAR (DOS MANOS) Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Planta baja.
Rev 1 6.82 2.6 17.72 1 17.72
V1 0.83 1.7 1.41 1 1.42
P1 -1.00 2.3 -2.30 1 -2.30
Rev 2 4.21 2.6 10.96 1 10.96
P2 -2.59 2.3 -5.95 1 -5.95
Rev 3 3.44 2.6 8.94 1 8.94
Rev 4 0.60 2.6 1.55 1 1.55
Rev 5 2.93 2.6 7.60 1 7.61
P2 -1.90 2.3 -4.37 1 -4.37
Rev 6 2.20 2.6 5.71 1 5.71
Rev 7 1.84 2.6 4.79 1 4.79
Planta Primer Piso
Rev 1 7.16 2.6 18.63 1 18.63
V3 -0.73 1.7 -1.23 1 -1.23
V3 -1.81 2.1 -3.81 1 -3.81
P6 -0.80 1.7 -1.36 1 -1.36
Rev 2 2.94 2.6 7.65 2 15.29
Rev 3 0.92 2.6 2.39 1 2.40
Rev 4 3.03 2.6 7.88 1 7.88
P9 -2.00 2.1 -4.20 1 -4.20
Rev 5 1.20 2.9 3.48 1 3.48
Rev 6 4.13 2.6 10.75 2 21.49
P12 -1.15 2.1 -2.42 1 -2.42
P13 -0.43 1.7 -0.74 1 -0.74
Rev 7 0.75 0.7 0.52 1 0.53
Rev 8 4.23 0.7 2.96 1 2.96
Rev 9 4.13 0.7 2.89 1 2.89
Rev 10 0.62 0.7 0.43 1 0.43
PLANTA ALTILLO
Balcón 13.07 0.70 9.15 1 9.15
Exterior 6.68 0.70 4.68 1 4.68
Total PINTURA EN EXTERIORES LATEX O SIMILAR (DOS MANOS) - 1 Casa (m2)= 122.13
Total PINTURA EN EXTERIORES LATEX O SIMILAR (DOS MANOS) - 2 Casa (m2)= 244.25

31 PROV Y COLOC CHAPA PUERTA PRINCIPAL Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
Prinicipal 1 1
Bloque 1 - Vivienda 1 - Planta primer piso.
Prinicipal 0 0
Bloque 1 - Vivienda 1 - Planta altillo.
Prinicipal 0 0
Total PROV Y COLOC CHAPA PUERTA PRINCIPAL - 1 Casa (Pza)= 1.00
Total PROV Y COLOC CHAPA PUERTA PRINCIPAL - 2 Casa (Pza)= 2.00

32 PROV Y COLOC CHAPA PUERTAS INTERIORES Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
Interiores 1 1
Bloque 1 - Vivienda 1 - Planta primer piso.
Interiores 3 3
Bloque 1 - Vivienda 1 - Planta altillo.
Interiores 0 0
Total PROV Y COLOC CHAPA PUERTAS INTERIORES - 1 Casa (Pza)= 4.00
Total PROV Y COLOC CHAPA PUERTAS INTERIORES - 2 Casa (Pza)= 8.00

33 PROV Y COLOC CHAPA BAÑOS Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
Baños 1 1
Bloque 1 - Vivienda 1 - Planta primer piso.
Baños 2 2
Bloque 1 - Vivienda 1 - Planta altillo.
Baños 1 1
Total PROV Y COLOC CHAPA PUERTAS INTERIORES - 1 Casa (Pza)= 4.00
Total PROV Y COLOC CHAPA PUERTAS INTERIORES - 2 Casa (Pza)= 8.00

34 ZOCALOS DE CERAMICA Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(ml) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
Cocina, living, comedor, gradas 38.52 1 38.52
P3 -1.00 1 -1.00
P2 -0.80 1 -0.80
P4 -1.90 1 -1.90
P5 -2.59 1 -2.59
Despensa 6.29 1 6.29
P3 -0.80 1 -0.80
Bloque 1 - Vivienda 1 - Planta primer piso.
Balcon 1 9.72 1 9.72
P6 -1.83 1 -1.83
Dormitorio 1, Vestidor 22.43 1 22.43
P6 -1.83 1 -1.83
P8 -0.90 1 -0.90
P7 -0.80 1 -0.80
hall 15.12 1 15.12
P9 -0.80 1 -0.80
P8 -0.90 3 -2.70
ESCALERAS -1.90 1 -1.90
Dormitorio 2 14.57 1 14.57
P11 -0.90 1 -0.90
P13 -2.00 1 -2.00
Dormitorio 3 15.18 1 15.18
P10 -0.90 1 -0.90
P12 -1.15 1 -1.15
Balcon 2 9.97 1 9.97
P13 -1.15 1 -1.15
Bloque 1 - Vivienda 1 - Planta altillo.
Estar familiar , gradas 21.92 1 21.92
P14 -0.80 1 -0.80
Total ZOCALOS DE CERAMICA - 1 Casa (ml)= 128.96
Total ZOCALOS DE CERAMICA - 2 Casa (ml)= 257.92

35 CIELO RASO ENLUCIDO DE YESO Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
Ingreso-garaje 21.50 1 21.50
Living, comedor, gradas 36.01 1 36.01
Despensa 2.22 1 2.22
Patio trasero 8.21 1 8.21
Bloque 1 - Vivienda 1 - Planta primer piso.
Balcon 1 3.50 1 3.50
HALL 20.39 1 20.39
Balcon 2 3.33 1 3.33
Bloque 1 - Vivienda 1 - Planta altillo.
Estar familiar, Gradas 21.48 1 21.48
Total CIELO RASO ENLUCIDO DE YESO - 1 Casa (m2)= 116.64
Total CIELO RASO ENLUCIDO DE YESO - 2 Casa (m2)= 233.29

36 CIELO FALSO DRYWALL COCINA Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
Cocina 9.72 1 9.72
Total CIELO FALSO DRYWALL COCINA - 1 Casa (m2)= 9.72
Total CIELO FALSO DRYWALL COCINA - 2 Casa (m2)= 19.43

37 CIELO FALSO PVC Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
Baño pb 2.33 1 2.33
Bloque 1 - Vivienda 1 - Planta primer piso.
Baño 1 4.64 1 4.64
Vestidor 4.67 1 4.67
Dormitorio 1 12.49 1 12.49
Baño 2 4.59 1 4.59
Dormitorio 2 13.48 1 13.48
Dormitorio 3 12.21 1 12.21
Bloque 1 - Vivienda 1 - Planta altillo.
Baño 3 4.80 1 4.80
Total CIELO FALSO PVC - 1 Casa (m2)= 59.21
Total CIELO FALSO PVC - 2 Casa (m2)= 118.42

38 VENTANA DE ALUMINIO Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
V1 1.55 1.7 2.64 1 2.64
V2 0.83 1.7 1.41 1 1.41
V3 2.59 2 5.17 1 5.17
Bloque 1 - Vivienda 1 - Planta primer piso.
V4 2.00 1.7 3.40 1 3.40
V5 0.73 1.7 1.23 1 1.23
Bloque 1 - Vivienda 1 - Planta altillo.
V6 1.84 1.7 3.13 1 3.13
V7 1.67 0.85 1.42 1 1.42
V8 0.80 1 0.80 1 0.80
V9 1.65 1.7 2.80 1 2.80
Total VENTANA DE ALUMINIO - 1 Casa (m2)= 22.00
Total VENTANA DE ALUMINIO - 2 Casa (m2)= 44.01

39 PROV. Y COLOCADO ROPEROS MELAMINA 18MM Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta primer piso.
Vestidor dorm 1 1.95 2.45 4.78 1 4.78
Vestidor dorm 1 0.89 2.45 2.17 1 2.17
Vestidor dorm 2 2.00 2.45 4.90 1 4.90
Vestidor dorm 3 1.83 2.45 4.49 1 4.49
Total PROV. Y COLOCADO ROPEROS MELAMINA 18MM - 1 Casa (m2)= 16.34
Total PROV. Y COLOCADO ROPEROS MELAMINA 18MM - 2 Casa (m2)= 32.67

40 PROV. Y COLOCADO CAJONERIA BAJA COCINA Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
MESÓN 1.60 0.9 1.44 1 1.44
COCINA 2.85 0.68 1.94 1 1.94
Total PROV. Y COLOCADO ROPEROS MELAMINA 18MM - 1 Casa (m2)= 3.38
Total PROV. Y COLOCADO ROPEROS MELAMINA 18MM - 2 Casa (m2)= 6.76

41 PROV. Y COLOCADO CAJONERIA ALTA COCINA Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
CAJONERIA BAJA 2.85 0.7 1.99 1 1.99
Total PROV. Y COLOCADO CAJONERIA ALTA COCINA - 1 Casa (m2)= 1.99
Total PROV. Y COLOCADO CAJONERIA ALTA COCINA - 2 Casa (m2)= 3.99

42 BARANDA TUBO REDONDO D =50MM Y D=45MM Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
BARANDA 4.25 0.9 3.83 1 3.83
Total BARANDA TUBO REDONDO D =50MM Y D=45MM - 1 Casa (m2)= 3.83
Total BARANDA TUBO REDONDO D =50MM Y D=45MM - 2 Casa (m2)= 7.65

43 RELLENO Y COMPACTADO CON MATERIAL RIPIO E=10CM Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
Fila 1 8.50 1 0.1 0.85 1 0.85
Fila 2 8.27 1 0.1 0.83 1 0.83
Fila 3 7.92 1 0.1 0.79 1 0.79
Fila 4 7.70 1 0.1 0.77 1 0.77
Fila 5 7.49 1 0.1 0.75 1 0.75
Fila 6 7.27 1 0.1 0.73 1 0.73
Fila 7 6.91 1 0.1 0.69 1 0.69
Fila 8 6.69 1 0.1 0.67 1 0.67
Total RELLENO Y COMPACTADO CON MATERIAL RIPIO E=10CM - 2 Casa (m3)= 6.08

44 ADOQUINES DE HORMIGON Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m2) (m2)
Bloque 1 - Vivienda 1 - Planta baja.
Fila 1 8.50 1 8.50 1 8.50
Fila 2 8.27 1 8.27 1 8.27
Fila 3 7.92 1 7.92 1 7.92
Fila 4 7.70 1 7.70 1 7.70
Fila 5 7.49 1 7.49 1 7.49
Fila 6 7.27 1 7.27 1 7.27
Fila 7 6.91 1 6.91 1 6.91
Fila 8 6.69 1 6.69 1 6.69
Total ADOQUINES DE HORMIGON E=10CM - 2 Casa (m2)= 60.75
M3

Observación

ML

Observación

M2

Observación

Descuento
Descuento
Descuento

Descuento
Descuento
Descuento

Descuento

Descuento

Descuento

Descuento

Descuento

Descuento
Descuento

Descuento
Descuento

Descuento
Descuento
Descuento
Descuento

Descuento
Descuento

M2

Observación

Descuento
Descuento
Descuento
Descuento
Descuento

Descuento
Descuento

Descuento

Descuento

Descuento
Descuento
Descuento
Descuento
Descuento

Descuento
Descuento

Descuento
Descuento
Descuento

Descuento

Descuento

Descuento
Descuento
Descuento
Descuento

Descuento
Descuento

Descuento
Descuento

PZA

Observación

PZA

Observación
PZA

Observación

M2

Observación

M2

Observación

M2

Observación
M2

Observación

Descuento

Descuento
Descuento

Descuento

Descuento
Descuento

M2

Observación

M2

Observación
M2

Observación

M2

Observación

M2

Observación

Descuento
Descuento

Descuento

Descuento
Descuento
Descuento
Descuento

Descuento

Descuento
Descuento

M2

Observación

Descuento
Descuento
Descuento
Descuento
Descuento

Descuento
Descuento

Descuento

Descuento

Descuento
Descuento
Descuento
Descuento
Descuento

Descuento
Descuento

Descuento
Descuento
Descuento

Descuento

Descuento

Descuento
Descuento
Descuento
Descuento

Descuento
Descuento

Descuento
Descuento

M2

Observación

Descuento
Descuento

Descuento

Descuento
Descuento
Descuento
Descuento

Descuento

Descuento
Descuento

PZA

Observación

PZA

Observación
PZA

Observación

ml

Observación

Descuento
Descuento
Descuento
Descuento

Descuento

Descuento

Descuento
Descuento
Descuento

Descuento
Descuento
Descuento

Descuento
Descuento
Descuento
Descuento

Descuento

Descuento

m2

Observación

m2

Observación

m2

Observación
m2

Observación

m2

Observación

m2

Observación
m2

Observación

m2

Observación

m3

Observación

m3

Observación
MODULO 4: INSTALACION HIDROSANITARIA
45 EXCAVACION DE 0 A 1 M TERRENO SEMIDURO Unid:
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Vivienda tipo A
Tr. 1 8.81 0.50 0.70 3.08 1.00 3.08
Tr. 2 5.36 0.50 0.70 1.88 1.00 1.88
Tr. 3 0.19 0.50 0.70 0.07 1.00 0.07
Tr. 4 3.83 0.50 0.70 1.34 1.00 1.34
Tr. 5 0.19 0.50 0.70 0.07 1.00 0.07
Tr. 6 5.24 0.50 0.70 1.83 1.00 1.83
Tr. 18 5.02 0.50 0.70 1.76 1.00 1.76
Tr. 20 1.55 0.50 0.70 0.54 1.00 0.54
Tr. 41 0.50 0.20 0.40 0.04 1.00 0.04
Tr. 42 2.99 0.20 0.40 0.24 1.00 0.24
Tr. 45 5.05 0.20 0.40 0.40 1.00 0.40
TOTAL EXCAVACION DE 0 A 1 M TERRENO SEMID M3 1 CASA 11.25
TOTAL EXCAVACION DE 0 A 1 M TERRENO SEMID M3 2 CASA 22.50
49 PROVISION Y TENDIDO TUBERIA PVC D=1 1/2" Unid:
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(mL) (mL)
Vivienda tipo A
Tr. 15 0.23 1.00 0.23
Tr. 16 0.14 1.00 0.14
Tr. 17 0.60 1.00 0.60
Tr. 28 0.23 1.00 0.23
Tr. 29 1.31 1.00 1.31
Tr. 30 0.60 1.00 0.60
Tr. 38 0.55 1.00 0.55
Tr. 39 0.11 1.00 0.11
Tr. 40 0.60 1.00 0.60
TOTAL PROVISION Y TENDIDO TUBERIA PVC D=1 1ML 1 CASA 4.37
TOTAL PROVISION Y TENDIDO TUBERIA PVC D=1 1ML 2 CASA 8.74
46 CAMA DE MATERIAL CERNIDO E=5cm Unid:
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Vivienda tipo A
Tr. 1 8.81 0.50 0.05 0.22 1.00 0.22
Tr. 2 5.36 0.50 0.05 0.13 1.00 0.13
Tr. 3 0.19 0.50 0.05 0.00 1.00 0.00
Tr. 4 3.83 0.50 0.05 0.10 1.00 0.10
Tr. 5 0.19 0.50 0.05 0.00 1.00 0.00
Tr. 6 5.24 0.50 0.05 0.13 1.00 0.13
Tr. 18 5.02 0.50 0.05 0.13 1.00 0.13
Tr. 20 1.55 0.50 0.05 0.04 1.00 0.04
Tr. 41 0.50 0.20 0.05 0.01 1.00 0.01
Tr. 42 2.99 0.20 0.05 0.03 1.00 0.03
Tr. 45 5.05 0.20 0.05 0.05 1.00 0.05
TOTAL CAMA DE MATERIAL CERNIDO E=5cm M3 1 CASA 0.84
TOTAL CAMA DE MATERIAL CERNIDO E=5cm M3 2 CASA 1.68
51 RELLENO Y APISONADO MANUAL TIERRA CERNIDA Unid:
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Vivienda tipo A
Tr. 1 8.81 0.50 0.20 0.88 1.00 0.88
Tr. 2 5.36 0.50 0.20 0.54 1.00 0.54
Tr. 3 0.19 0.50 0.20 0.02 1.00 0.02
Tr. 4 3.83 0.50 0.20 0.38 1.00 0.38
Tr. 5 0.19 0.50 0.20 0.02 1.00 0.02
Tr. 6 5.24 0.50 0.20 0.52 1.00 0.52
Tr. 18 5.02 0.50 0.20 0.50 1.00 0.50
Tr. 20 1.55 0.50 0.20 0.16 1.00 0.16
Tr. 41 0.50 0.20 0.20 0.02 1.00 0.02
Tr. 42 2.99 0.20 0.20 0.12 1.00 0.12
Tr. 45 5.05 0.20 0.20 0.20 1.00 0.20
TOTAL RELLENO Y APISONADO MANUAL TIERRA M3 1 CASA 3.36
TOTAL RELLENO Y APISONADO MANUAL TIERRA M3 2 CASA 6.72
52 RELLENO Y COMPACTADO CON TIERRA COMUN Unid:
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Vivienda tipo A
Tr. 1 8.81 0.50 0.60 2.64 1.00 2.64
Tr. 2 5.36 0.50 0.60 1.61 1.00 1.61
Tr. 3 0.19 0.50 0.60 0.06 1.00 0.06
Tr. 4 3.83 0.50 0.60 1.15 1.00 1.15
Tr. 5 0.19 0.50 0.60 0.06 1.00 0.06
Tr. 6 5.24 0.50 0.60 1.57 1.00 1.57
Tr. 18 5.02 0.50 0.60 1.51 1.00 1.51
Tr. 20 1.55 0.50 0.60 0.46 1.00 0.46
Tr. 41 0.50 0.20 0.20 0.02 1.00 0.02
Tr. 42 2.99 0.20 0.20 0.12 1.00 0.12
Tr. 45 5.05 0.20 0.20 0.20 1.00 0.20
TOTAL RELLENO Y COMPACTADO CON TIERRA C M3 1 CASA 9.40
TOTAL RELLENO Y COMPACTADO CON TIERRA C M3 2 CASA 18.80
M3

Observación

ML

Observación

M3

Observación
M3

Observación

M3

Observación
61 CAJA DE DERIVACION CIRCULAR PVC. Unid:
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
-ESTIMACIÓN 1 POR AMBIENTE-
Living comedor 1 1
cocina despensa 1 1
baño1 1 1
gradas 1 1
Bloque 1 - Vivienda 1 - Planta primer piso.
Dormitorio 1 1 1
Dormitorio 2 1 1
Dormitorio 3 1 1
Baño 2 vestidor 1 1
Baño 3 1 1
Gradas 1 1
Bloque 1 - Vivienda 1 - Planta altillo
Sala - grada 1 1
baño 1 1
TOTAL CAJA DE DERIVACION CIRCULAR PVC. PZA 1 CASA 12.00
TOTAL CAJA DE DERIVACION CIRCULAR PVC. PZA 2 CASA 24.00

62 PUNTO DE ILUMINACION Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 23 23
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 26 26
Bloque 1 - Vivienda 1 - Planta altillo
P2 12 12
TOTAL PUNTO DE ILUMINACION PTO 1 CASA 61.00
TOTAL PUNTO DE ILUMINACION PTO 2 CASA 122.00

63 LUMINARIA LED Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 18 18
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 13 13
Bloque 1 - Vivienda 1 - Planta altillo
P2 3 3
TOTAL LUMINARIA LED Pza 1 CASA 34.00
TOTAL LUMINARIA LED Pza 2 CASA 68.00

65 LUMINARIA SPOT LED Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 5 5
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 13 13
Bloque 1 - Vivienda 1 - Planta altillo
P2 9 9
TOTAL LUMINARIA SPOT LED Pza 1 CASA 27.00
TOTAL LUMINARIA SPOT LED Pza 2 CASA 54.00

66 LUMINARIA DE EXTERIOR Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 0 0
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 0 0
Bloque 1 - Vivienda 1 - Planta altillo
P2 0 0
TOTAL LUMINARIA DE EXTERIOR Pza 1 CASA 0.00
TOTAL LUMINARIA DE EXTERIOR Pza 2 CASA 0.00

67 INTERRUPTOR SIMPLE Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 5 5
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 9 9
Bloque 1 - Vivienda 1 - Planta altillo
P2 5 5
TOTAL INTERRUPTOR SIMPLE Pza 1 CASA 19.00
TOTAL INTERRUPTOR SIMPLE Pza 2 CASA 38.00

68 INTERRUPTOR DOBLE Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 3 3
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 2 2
Bloque 1 - Vivienda 1 - Planta altillo
P2 0 0
TOTAL INTERRUPTOR DOBLE Pza 1 CASA 5.00
TOTAL INTERRUPTOR DOBLE Pza 2 CASA 10.00
69 INTERRUPTOR CONMUTADOR SIMPLE Unid:
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 1 1
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 2 2
Bloque 1 - Vivienda 1 - Planta altillo
P2 1 1
TOTAL INTERRUPTOR CONMUTADOR SIMPLE Pza 1 CASA 4.00
TOTAL INTERRUPTOR CONMUTADOR SIMPLE Pza 2 CASA 8.00

70 INTERRUPTOR CONMUTADOR DOBLE Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 0 0
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 3 3
Bloque 1 - Vivienda 1 - Planta altillo
P2 0 0
TOTAL INTERRUPTOR CONMUTADOR DOBLE Pza 1 CASA 3.00
TOTAL INTERRUPTOR CONMUTADOR DOBLE Pza 2 CASA 6.00

71 CABLEADO ALAMBRE Nº12 AWG TW INC/DUCTEADO Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
ESTIMACIÓN 3M POR PUNTO
Bloque 1 - Vivienda 1 - Planta baja.
PB 3 23 69
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 3 26 78
Bloque 1 - Vivienda 1 - Planta altillo
P2 3 12 36
TOTAL CABLEADO ALAMBRE Nº12 AWG TW INC/ ML 1 CASA 183.00
TOTAL CABLEADO ALAMBRE Nº12 AWG TW INC/ ML 2 CASA 366.00

72 CABLEADO ALAMBRE Nº 10 AWG TW INC/DUCTEADO Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
ESTIMACIÓN 3M POR PUNTO
TOTAL 1 VIVI 3 78 234
TOTAL CABLEADO ALAMBRE Nº 10 AWG TW INC/ ML 1 CASA 234.00
TOTAL CABLEADO ALAMBRE Nº 10 AWG TW INC/ ML 2 CASA 468.00

73 PUNTO DE TV CABLE Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 0 0
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 4 4
Bloque 1 - Vivienda 1 - Planta altillo
P2 1 1
TOTAL PUNTO DE TV CABLE PTO 1 CASA 5.00
TOTAL PUNTO DE TV CABLE PTO 2 CASA 10.00

74 PUNTO DE TELEFONO Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 1 1
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 1 1
Bloque 1 - Vivienda 1 - Planta altillo
P2 0 0
TOTAL PUNTO DE TELEFONO PTO 1 CASA 2.00
TOTAL PUNTO DE TELEFONO PTO 2 CASA 4.00

75 PUNTO DE DATOS Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 0 0
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 3 3
Bloque 1 - Vivienda 1 - Planta altillo
P2 1 1
TOTAL PUNTO DE DATOS PTO 1 CASA 4.00
TOTAL PUNTO DE DATOS PTO 2 CASA 8.00

76 TABLERO DE DISTRIBUCION DE CIRCUITOS ESPECIALES Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 1 1
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 0 0
Bloque 1 - Vivienda 1 - Planta altillo
P2 0 0
TOTAL TABLERO DE DISTRIBUCION DE CIRCUITOSPZA 1 CASA 1.00
TOTAL TABLERO DE DISTRIBUCION DE CIRCUITOSPZA 2 CASA 2.00
77 TABLERO DE DISTRIBUCION P/5 TERMICOS BIPOLAR Unid:
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 1 1
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 0 0
Bloque 1 - Vivienda 1 - Planta altillo
P2 0 0
TOTAL TABLERO DE DISTRIBUCION P/5 TERMICOSPZA 1 CASA 1.00
TOTAL TABLERO DE DISTRIBUCION P/5 TERMICOSPZA 2 CASA 2.00

78 INTERRUPTOR MAGNETOTERMICO BIPOLAR 32A Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
COCINA 1 1
TOTAL INTERRUPTOR MAGNETOTERMICO BIPOLAR
PZA 1 CASA 1.00
TOTAL INTERRUPTOR MAGNETOTERMICO BIPOLAR
PZA 2 CASA 2.00

79 INTERRUPTOR MAGNETOTERMICO BIPOLAR 25A Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
TOMA CORRIENTE 2 2
BOMBA 1 1
TOTAL INTERRUPTOR MAGNETOTERMICO BIPOLAR
PZA 1 CASA 3.00
TOTAL INTERRUPTOR MAGNETOTERMICO BIPOLAR
PZA 2 CASA 6.00

80 INTERRUPTOR MAGNETOTERMICO BIPOLAR 16A Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
ILUMINACIÓN 1 1
INTERRUPTOR 1 1
TOTAL INTERRUPTOR MAGNETOTERMICO BIPOLAR
PZA 1 CASA 2.00
TOTAL INTERRUPTOR MAGNETOTERMICO BIPOLAR
PZA 2 CASA 4.00

81 TOMACORRIENTE SIMPLE TIPO SCHUKO Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 4 4
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 0 0
Bloque 1 - Vivienda 1 - Planta altillo
P2 0 0
TOTAL TOMACORRIENTE SIMPLE TIPO SCHUKO PZA 1 CASA 4.00
TOTAL TOMACORRIENTE SIMPLE TIPO SCHUKO PZA 2 CASA 8.00
82 TOMACORRIENTE DOBLE ESTILO EUROAMERICANO Unid:
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 14 14
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 16 16
Bloque 1 - Vivienda 1 - Planta altillo
P2 5 5
TOTAL TOMACORRIENTE DOBLE ESTILO EUROAMPZA 1 CASA 35.00
TOTAL TOMACORRIENTE DOBLE ESTILO EUROAMPZA 2 CASA 70.00

83 INSTALACION DE TIMBRE Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 1 1
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 0 0
Bloque 1 - Vivienda 1 - Planta altillo
P2 0 0
TOTAL INSTALACION DE TIMBRE PTO 1 CASA 1.00
TOTAL INSTALACION DE TIMBRE PTO 2 CASA 2.00

84 ACOMETIDA ELECTRICA INC/PUESTA TIERRA Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 1 1
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 0 0
Bloque 1 - Vivienda 1 - Planta altillo
P2 0 0
TOTAL ACOMETIDA ELECTRICA INC/PUESTA TIERGLB 1 CASA 1.00
TOTAL ACOMETIDA ELECTRICA INC/PUESTA TIERGLB 2 CASA 2.00

85 EXTRACTOR DE AIRE PARA BAÑOS Unid:


Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant.
(m3) (m3)
Bloque 1 - Vivienda 1 - Planta baja.
PB 1 1
Bloque 1 - Vivienda 1 - Planta primer piso.
P1 2 2
Bloque 1 - Vivienda 1 - Planta altillo
P2 1 1
TOTAL EXTRACTOR DE AIRE PARA BAÑOS PZA 1 CASA 4.00
TOTAL EXTRACTOR DE AIRE PARA BAÑOS PZA 2 CASA 8.00
PZA

Observación

PTO

Observación

Pza

Observación

Pza
Observación

Pza

Observación

Pza

Observación

Pza

Observación
Pza

Observación

Pza

Observación

ML

Observación

ML

Observación

PTO
Observación

PTO

Observación

PTO

Observación

PZA

Observación
PZA

Observación

PZA

Observación

PZA

Observación

PZA

Observación

PZA

Observación
PZA

Observación

PTO

Observación

GLB

Observación

PZA

Observación
85 GAS DOMICILIARIO Unid: ML
Volumen Vol. Total
Elemento L(m) A(m) H(m) Cant. Observación
(mL) (mL)
Vivienda tipo A
Tr. 1 0.60 1.00 0.60
Tr. 2 5.29 1.00 5.29
Tr. 3 14.13 1.00 14.13
Tr. 4 5.21 1.00 5.21
Tr. 5 1.10 1.00 1.10
Tr. 6 2.21 1.00 2.21
Tr. 7 7.36 1.00 7.36
Tr. 8 1.20 1.00 1.20
TOTAL GAS DOMICILIARIO ML 1 CASA 37.10
TOTAL GAS DOMICILIARIO ML 2 CASA 74.20