CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

PROYECTO: "MEJORAMIENTO DE LAS PRINCIPALES VIAS DE ACCESO AL HOSPITAL ESSALUD DE TARAPOTO Y MORALES, PROVINVIA DE SAN MARTIN, DEPARTAMENTO DE SAN MARTIN" - CODIGO
SNIP: 305453
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 MES 09
01 OBRAS PRELIMINARES 13,315.78
01.01 CARTEL DE OBRA DE 3.60 x 8.50 m. und 2.00 1,485.15 2,970.30 2,970.30
01.02 MOVILIZACION Y DESMOVILIZACION GLB 1.00 4,790.00 4,790.00 4,790.00
01.03 DEMOLICION VEREDAS EXISTENTES m3 198.41 28.00 5,555.48 5,555.48
02 PAVIMENTO ASFALTICO 2,517,017.92
02.01 TRAZO, NIVELACION Y REPLANTEO m2 23,607.04 1.04 24,551.32 24,167.71 383.61
02.02 CORTE DE TERRENO NATURAL C/MAQUINARIA m3 11,085.58 4.53 50,217.68 50,217.68
02.03 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 13,302.70 9.22 122,650.89 122,650.89
02.04 PERFILADO Y COMPACTADO DE SUBRASANTE m2 23,607.04 1.62 38,243.40 38,243.40
02.05 SUB BASE GRANULAR m3 5,901.76 93.13 549,630.91 549,630.91
02.06 BASE GRANULAR m3 4,131.23 105.35 435,225.08 365,278.19 69,946.89
02.07 IMPRIMACION ASFALTICA m2 23,607.04 6.68 157,695.03 157,695.03
02.08 CARPETA ASFALTICA EN CALIENTE E=0.05m m2 23,607.04 48.24 1,138,803.61 1,138,803.61
03 VEREDAS, RAMPA Y MARTILLOS 648,952.56
03.01 LIMPIEZA DE TERRENO MANUAL m2 10,159.75 0.79 8,026.20 8,026.20
03.02 TRAZO, NIVELACION Y REPLANTEO m2 10,159.75 1.04 10,566.14 10,566.14
03.03 EXCAVACION DE VEREDAS m3 2,031.95 29.68 60,308.28 60,308.28
03.04 BASE GRANULAR e=0.10 m m3 1,015.98 131.21 133,306.74 32,493.52 100,813.22
03.05 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 2,438.34 9.22 22,481.49 2,458.91 20,022.58
03.06 CONCRETO SIMPLE F'C=175 KG/CM2, EN VEREDAS INC. BRUÑADO m3 1,015.98 378.62 384,670.35 384,670.35
03.07 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 585.64 28.01 16,403.78 10,416.40 5,987.38
03.08 JUNTA ASFALTICA EN VEREDAS m 2,438.00 5.41 13,189.58 1,154.09 12,035.49
04 SARDINELES 236,766.06
04.01 LIMPIEZA DE TERRENO MANUAL m2 462.79 0.79 365.60 365.60
04.02 TRAZO, NIVELACION Y REPLANTEO m2 462.79 1.04 481.30 481.30
04.03 EXCAVACION DE SARDINELES m3 208.26 29.68 6,181.16 6,181.16
04.04 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 249.91 9.22 2,304.17 2,304.17
04.05 CONCRETO ARMADO FC=210 KG/CM2 EN SARDINELES m3 277.68 430.70 119,596.78 17,192.04 102,404.74
04.06 ACERO DE REFUERZO fy=4,200 Kg/m2 EN SARDINELES kg 3,858.49 4.76 18,366.41 18,366.41
04.07 ENCOFRADO Y DESENCOFRADO DE SARDINELES m2 3,702.34 23.49 86,967.97 34,352.35 52,615.62
04.08 JUNTA ASFALTICA EN SARDINELES m 462.60 5.41 2,502.67 2,502.67
05 CUNETAS 1,124,284.97
05.01 LIMPIEZA DE TERRENO MANUAL m2 3,917.70 0.79 3,094.98 3,094.98
05.02 TRAZO, NIVELACION Y REPLANTEO m2 3,917.70 1.04 4,074.41 4,074.41
05.03 EXCAVACION MANUAL PARA ESTRUCTURAS m3 2,986.01 29.68 88,624.78 88,624.78
05.04 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 3,583.22 9.22 33,037.29 33,037.29
05.05 CONCRETO SIMPLE F'C=175 KG/CM2, EN CUNETA m3 1,140.59 378.62 431,850.19 40,485.96 391,364.23
05.06 CONCRETO SIMPLE F'C=100 KG/CM2, PARA SOLADOS m3 123.40 243.83 30,088.62 6,268.46 23,820.16
05.07 CONCRETO ARMADO FC=210 KG/CM2 PARA CUNETAS m3 338.48 411.49 139,281.14 60,587.30 78,693.84
05.08 ACERO DE REFUERZO fy=4,200 Kg/cm2 PARA CUNETAS kg 33,863.49 4.76 161,190.21 161,190.21
05.09 ENCOFRADO Y DESENCOFRADO DE CUNETAS m2 7,792.95 28.44 221,631.50 6,464.25 215,167.25
05.10 JUNTA ASFALTICA PARA CUNETAS m 2,109.40 5.41 11,411.85 11,411.85
06 ALCANTARILLA DE CRUCE 341,391.32
06.01 LIMPIEZA DE TERRENO MANUAL m2 636.53 0.79 502.86 502.86
06.02 TRAZO, NIVELACION Y REPLANTEO m2 636.53 1.04 661.99 661.99
06.03 EXCAVACION MANUAL PARA ESTRUCTURAS m3 815.45 29.68 24,202.56 24,202.56
06.04 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 978.54 9.22 9,022.14 9,022.14
06.05 CONCRETO SIMPLE F'C=100 KG/CM2, PARA SOLADOS m3 63.65 243.83 15,519.78 15,519.78
06.06 CONCRETO ARMADO FC=210 KG/CM2 PARA ALCANTARILLAS m3 269.10 411.49 110,731.96 40,659.39 70,072.57
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: "MEJORAMIENTO DE LAS PRINCIPALES VIAS DE ACCESO AL HOSPITAL ESSALUD DE TARAPOTO Y MORALES, PROVINVIA DE SAN MARTIN, DEPARTAMENTO DE SAN MARTIN" - CODIGO
SNIP: 305453
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 MES 09
06.07 ACERO DE REFUERZO fy=4,200 Kg/cm2 PARA ALCANTARILLAS kg 23,606.80 4.76 112,368.37 112,368.37
06.08 ENCOFRADO Y DESENCOFRADO DE ALCANTARILLA m2 2,214.86 28.44 62,990.62 37,400.68 25,589.94
06.09 JUNTA ASFALTICA PARA ALCANTARILLAS m 379.40 5.41 2,052.55 2,052.55
06.10 TAPAS DE INSPECCION DE ALCANTARILLAS und 57.00 58.57 3,338.49 3,338.49
07 TOMAS LATERALES 98,252.82
07.01 LIMPIEZA DE TERRENO MANUAL m2 203.41 0.79 160.69 160.69
07.02 TRAZO, NIVELACION Y REPLANTEO m2 203.41 1.04 211.55 211.55
07.03 EXCAVACION MANUAL PARA ESTRUCTURAS m3 213.58 29.68 6,339.05 6,339.05
07.04 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 256.30 9.22 2,363.09 2,363.09
07.05 CONCRETO SIMPLE F'C=100 KG/CM2, PARA SOLADOS m3 20.34 243.83 4,959.50 4,959.50
07.06 CONCRETO ARMADO FC=210 KG/CM2 PARA TOMAS LATERALES m3 81.36 419.20 34,106.11 34,106.11
07.07 ACERO DE REFUERZO fy=4,200 Kg/cm2 PARA TOMAS LATERALES kg 5,849.88 4.76 27,845.43 19,392.35 8,453.08
07.08 ENCOFRADO Y DESENCOFRADO DE TOMAS LATERALES m2 752.62 28.67 21,577.62 21,577.62
07.09 JUNTA ASFALTICA PARA TOMAS LATERALES m 127.50 5.41 689.78 689.78
08 BERMAS LATERALES 298,365.90
08.01 LIMPIEZA DE TERRENO MANUAL m2 3,474.93 0.79 2,745.19 2,745.19
08.02 TRAZO, NIVELACION Y REPLANTEO m2 3,474.93 1.04 3,613.93 3,613.93
08.03 EXCAVACION MANUAL H=0.25m m3 868.73 29.68 25,783.91 24,333.57 1,450.34
08.04 BASE GRANULAR e=0.10 m m3 347.49 131.21 45,594.16 45,594.16
08.05 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 1,042.48 9.22 9,611.67 9,611.67
08.06 ENCOFRADO Y DESENCOFRADO NORMAL EN BERMA m2 282.13 29.03 8,190.23 6,768.32 1,421.91
08.07 CONCRETO SIMPLE F'C=175 KG/CM2, BERMAS m3 521.24 378.62 197,351.89 197,351.89
08.08 JUNTA ASFALTICA EN BERMAS m 1,012.00 5.41 5,474.92 5,474.92
09 SEÑALIZACION VIAL 35,302.44
09.01 SEÑALIZACION VERTICAL und 46.00 317.81 14,619.26 14,619.26
09.02 MARCAS CON PINTURA DE TRANSITO m2 1,770.82 11.68 20,683.18 20,683.18
10 ARBORIZACION Y JARDINERIA 94,736.28
10.01 GRASS AMERICANO m2 6,717.27 13.65 91,690.74 91,690.74
10.02 SEMBRADO DE PLANTAS ORNAMENTALES und 263.00 11.58 3,045.54 3,007.47 38.07
11 VARIOS 61,290.22
11.01 NIVELACIÓN DE TAPA PARA CAJA DOMICILIARIA DE AGUA und 297.00 60.95 18,102.15 527.98 17,574.17
11.02 NIVELACIÓN DE TAPA PARA CAJA DOMICILIARIA DE DESAGUE und 297.00 125.97 37,413.09 1,091.22 36,321.87
11.03 NIVELACION DE TAPAS DE BUZONES und 39.00 137.82 5,374.98 587.89 4,787.09
11.04 PLACA RECORDATORIA und 1.00 400.00 400.00 400.00
COSTO DIRECTO 5,469,676.27 124,709.92 152,610.03 586,910.31 525,650.01 953,520.88 314,082.31 283,640.16 1,003,753.79 1,524,798.86
GASTOS GENERALES 8%CD 437,574.10 9,976.79 12,208.80 46,952.82 42,052.00 76,281.67 25,126.58 22,691.21 80,300.31 121,983.92
UTILIDAD 7%CD 382,877.34 8,729.69 10,682.70 41,083.72 36,795.50 66,746.46 21,985.76 19,854.81 70,262.77 106,735.93
SUB TOTAL 6,290,127.71 143,416.40 175,501.53 674,946.85 604,497.51 1,096,549.01 361,194.65 326,186.18 1,154,316.87 1,753,518.71
IGV 18% 1,132,222.99 25,814.95 31,590.28 121,490.43 108,809.55 197,378.82 65,015.04 58,713.51 207,777.04 315,633.37
COSTO DE OBRA 7,422,350.70 169,231.35 207,091.81 796,437.28 713,307.06 1,293,927.83 426,209.69 384,899.69 1,362,093.91 2,069,152.08
PORCENTAJE 100% 2.28% 2.79% 10.73% 9.61% 17.43% 5.74% 5.19% 18.35% 27.88%
PORCENTAJE ACUMULADO 2.28% 5.07% 15.80% 25.41% 42.84% 48.59% 53.77% 72.12% 100.00%
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS URBANAS EN LA URBANIZACIÓN 15 DE AGOSTO EN EL BARRIO HUAYCO, DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTIN - DEPARTAMENTO DE SAN MARTIN",
CUI: 2519696
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08
01 OBRAS PROVISIONALES
01.01 CARTEL DE OBRA DE 3.60x4.80m und 1.00 S/ 2,171.27 S/ 2,171.27 S/ 2,168.60
01.02 SERVICIOS HIGIENICOS PROVISIONALES mes 8.00 S/ 4,500.00 S/ 36,000.00 S/ 4,500.00 S/ 4,500.00 S/ 4,500.00 S/ 4,500.00 S/ 4,500.00 S/ 4,500.00 S/ 4,500.00 S/ 4,500.00
02 OBRAS PRELIMINARES
02.01 ALQUILER DE ALMACEN Y/O DEPOSITO PARA OBRA mes 8.00 S/ 5,000.00 S/ 40,000.00 S/ 40,000.00
02.02 MOVILIZACION Y DESMOVILIZACIÓN DE MAQUINARIAS Y EQUIPOS est 1.00 S/ 10,500.00 S/ 10,500.00 S/ 10,500.00
02.03 REUBICACION DE POSTES DE CONCRETO und 17.00 S/ 2,000.00 S/ 34,000.00 S/ 34,000.00
02.04 TALA DE ARBOLES ORNAMENTALES und 111.00 S/ 82.03 S/ 9,105.33 S/ 1,874.88 S/ 355.89 S/ 3,866.94 S/ 195.30 S/ 2,812.32
03 SALUD Y SEGURIDAD OCUPACIONAL
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE
03.01 glb 1.00 S/ 10,500.00 S/ 10,500.00 S/ 10,500.00
SEGURIDAD Y SALUD EN EL TRABAJO
03.02 EQUIPO DE PROTECCION INDIVIDUAL glb 1.00 S/ 15,440.00 S/ 15,440.00 S/ 15,440.00
03.03 EQUIPO DE PROTECCION COLECTIVA glb 1.00 S/ 1,520.00 S/ 1,520.00 S/ 1,520.00
03.04 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 S/ 3,215.10 S/ 3,215.10 S/ 3,215.10
03.05 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 S/ 3,200.00 S/ 3,200.00 S/ 3,200.00
RECURSOS P/RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y
03.06 glb 1.00 S/ 6,400.00 S/ 6,400.00 S/ 6,400.00
SALUD DURANTE EL TRABAJO
PLAN PARA LA VIGILANCIA, PREVENCION Y CONTROL DE COVID-19 EN
03.07 glb 1.00 S/ 25,000.00 S/ 25,000.00 S/ 3,125.00 S/ 3,125.00 S/ 3,125.00 S/ 3,125.00 S/ 3,125.00 S/ 3,125.00 S/ 3,125.00 S/ 3,125.00
EL TRABAJO
04 PAVIMENTO FLEXIBLE
04.01 OBRAS PRELIMINARES
04.01.01 LIMPIEZA DE TERRENO MANUAL m2 8,967.40 S/ 0.82 S/ 7,353.27 S/ 7,353.27
04.01.02 TRAZO, NIVELACION Y REPLANTEO m2 8,967.40 S/ 2.30 S/ 20,625.02 S/ 14,496.91 S/ 6,128.11
04.02 MOVIMIENTO DE TIERRAS
04.02.01 EXCAVACION MASIVA CON MAQUINARIA EN MATERIAL COMUN m3 4,539.51 S/ 20.92 S/ 94,966.55 S/ 69,448.99 S/ 25,517.56
04.02.02 RELLENO CON MATERIAL PROPIO CON MAQUINARIA m3 5.73 S/ 11.34 S/ 64.98 S/ 64.98
04.02.03 ELIMINACION MATERIAL EXCEDENTE (D=5KM) m3 5,440.53 S/ 27.69 S/ 150,648.28 S/ 68,732.71 S/ 81,915.57
04.02.04 PERFILADO Y COMPACTADO DE SUB-RASANTE m2 8,967.40 S/ 4.91 S/ 44,029.93 S/ 44,029.93
04.03 PAVIMENTO
04.03.01 SUB BASE GRANULAR E=0.25M m2 8,967.40 S/ 31.61 S/ 283,459.51 S/ 104,852.25 S/ 178,607.26
04.03.02 BASE GRANULAR E=0.20M m2 8,967.40 S/ 31.69 S/ 284,176.91 S/ 141,235.25 S/ 142,941.66
04.03.03 IMPRIMACION m2 8,967.40 S/ 14.81 S/ 132,807.19 S/ 75,422.25 S/ 55,811.69 S/ 1,573.25
04.03.04 CARPETA ASFALTICA 0.05M m2 8,967.40 S/ 102.48 S/ 918,979.15 S/ 215,425.15 S/ 351,488.25 S/ 352,065.75
04.04 SEÑALIZACION
04.04.01 SEÑALES REGLAMENTARIAS VERTICALES und 23.00 S/ 250.00 S/ 5,750.00 S/ 5,750.00
04.04.02 MARCAS RETROREFLECTIVAS EN EL PAVIMENTO m2 739.28 S/ 46.26 S/ 34,199.09 S/ 34,199.09
04.05 VARIOS
04.05.01 NIVELACION DE TAPAS DE BUZONES und 26.00 S/ 486.55 S/ 12,650.30 S/ 12,650.30
05 BERMAS DE CONCRETO
05.01 OBRAS PRELIMINARES
05.01.01 LIMPIEZA DE TERRENO MANUAL m2 199.97 S/ 0.82 S/ 163.98 S/ 163.98
05.01.02 TRAZO, NIVELACION Y REPLANTEO m2 199.97 S/ 2.30 S/ 459.93 S/ 459.93
05.02 MOVIMIENTO DE TIERRAS
05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL EN BERMAS m3 74.57 S/ 53.64 S/ 3,999.93 S/ 3,398.22 S/ 601.71
05.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 89.48 S/ 32.19 S/ 2,880.36 S/ 2,880.36
05.02.03 PERFILADO Y COMPACTADO EN BERMAS m2 199.97 S/ 4.67 S/ 933.86 S/ 933.86
05.03 CONCRETO
05.03.01 MATERIAL GRANULAR e=0.05m m2 199.97 S/ 8.88 S/ 1,775.73 S/ 1,775.73
05.03.02 CONCRETO FC=210 KG/CM2 EN BERMAS m3 39.60 S/ 673.74 S/ 26,680.10 S/ 18,542.25 S/ 8,137.85
05.03.03 ENCOFRADO Y DESENCOFRADO EN BERMAS m2 91.38 S/ 48.34 S/ 4,417.31 S/ 4,417.31
05.03.04 JUNTA ASFALTICA EN BERMAS m 98.50 S/ 53.32 S/ 5,252.02 S/ 5,252.02
06 VEREDAS, RAMPAS Y MARTILLOS Y ACCESOS
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS URBANAS EN LA URBANIZACIÓN 15 DE AGOSTO EN EL BARRIO HUAYCO, DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTIN - DEPARTAMENTO DE SAN MARTIN",
CUI: 2519696
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08
06.01 VEREDAS DE CONCRETO
06.01.01 OBRAS PRELIMINARES
06.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 3,946.88 S/ 0.82 S/ 3,236.44 S/ 268.76 S/ 2,967.68
06.01.01.02 TRAZO, NIVELACION Y REPLANTEO m2 3,946.88 S/ 2.30 S/ 9,077.82 S/ 5,475.25 S/ 3,602.57
06.01.02 MOVIMIENTO DE TIERRAS
06.01.02.01 DEMOLICION DE ESTRUCTURAS EXISTENTES m3 96.11 S/ 54.45 S/ 5,233.19 S/ 5,233.19
06.01.02.02 EXCAVACION MANUAL EN TERRENO NORMAL EN VEREDAS m3 699.51 S/ 53.64 S/ 37,521.72 S/ 5,623.35 S/ 25,655.35 S/ 6,243.02
06.01.02.03 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURA m3 216.85 S/ 40.15 S/ 8,706.53 S/ 2,649.24 S/ 6,057.29
06.01.02.04 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 694.52 S/ 32.19 S/ 22,356.60 S/ 8,482.50 S/ 5,452.25 S/ 8,421.85
06.01.02.05 PERFILADO Y COMPACTADO EN VEREDAS m2 3,946.88 S/ 4.67 S/ 18,431.93 S/ 9,322.16 S/ 9,109.77
06.01.03 CONCRETO
06.01.03.01 MATERIAL GRANULAR e=0.05m m2 3,946.88 S/ 8.88 S/ 35,048.29 S/ 18,665.65 S/ 16,382.64
06.01.03.02 CONCRETO FC=175 KG/CM2 PARA VEREDAS, INC. BRUÑADO m3 558.07 S/ 582.87 S/ 325,282.26 S/ 108,225.25 S/ 115,262.25 S/ 101,794.76
06.01.03.03 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 1,829.76 S/ 48.34 S/ 88,450.60 S/ 46,800.21 S/ 14,102.56 S/ 27,547.83
06.01.03.04 JUNTA ASFALTICA EN VEREDAS m 1,494.80 S/ 53.32 S/ 79,702.74 S/ 35,425.25 S/ 31,584.25 S/ 12,693.24
06.01.04 VARIOS
06.01.04.01 NIVELACION DE CAJA DE REGISTRO DE AGUA und 100.00 S/ 179.36 S/ 17,936.00 S/ 17,936.00
06.01.04.02 NIVELACION DE CAJA DE REGISTRO DESAGUE und 112.00 S/ 227.36 S/ 25,464.32 S/ 25,464.32
06.02 VEREDAS DE ADOQUIN
06.02.01 OBRAS PRELIMINARES
06.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 615.37 S/ 0.82 S/ 504.60 S/ 504.60
06.02.01.02 TRAZO, NIVELACION Y REPLANTEO m2 615.37 S/ 2.30 S/ 1,415.35 S/ 1,415.35
06.02.02 MOVIMIENTO DE TIERRAS
06.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL EN ADOQUIN m3 99.81 S/ 26.82 S/ 2,676.90 S/ 651.22 S/ 2,025.68
06.02.02.02 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURA m3 25.92 S/ 40.15 S/ 1,040.69 S/ 1,040.69
06.02.02.03 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 88.67 S/ 32.19 S/ 2,854.29 S/ 814.70 S/ 2,039.59
06.02.02.04 PERFILADO Y COMPACTADO EN ADOQUIN m2 615.37 S/ 4.67 S/ 2,873.78 S/ 2,873.78
06.02.03 ADOQUIN
06.02.03.01 BASE GRANULAR EN ADOQUIN m3 91.48 S/ 165.10 S/ 15,103.35 S/ 15,103.35
06.02.03.02 COLCHON DE ARENA E=4.0 CM m2 615.37 S/ 6.42 S/ 3,950.68 S/ 3,950.68
06.02.03.03 ADOQUINADO DE CONCRETO E=6.00 CM m2 573.83 S/ 165.27 S/ 94,836.88 S/ 54,825.35 S/ 32,249.94 S/ 7,761.59
06.02.03.04 ADOQUINADO DE CONCRETO E=8.00 CM m2 41.54 S/ 186.27 S/ 7,737.66 S/ 7,737.66
06.02.03.05 COMPACTACION INICIAL DE PISO ADOQUINADO m2 615.37 S/ 1.60 S/ 984.59 S/ 984.59
06.02.03.06 SELLADO Y COMPACTADO FINAL DE PISO ADOQUINADO m2 615.37 S/ 2.24 S/ 1,378.43 S/ 1,378.43
06.02.04 VARIOS
06.02.04.01 BANCA COLONIAL EN FIERRO FUNDIDO Y MADERA und 57.00 S/ 1,093.19 S/ 62,311.83 S/ 55,135.13 S/ 7,176.70
06.02.04.02 APARATO GIMNASIA Y RECREACION TIPO I und 6.00 S/ 850.50 S/ 5,103.00 S/ 5,103.00
06.02.04.03 APARATO GIMNASIA Y RECREACION TIPO II und 8.00 S/ 850.50 S/ 6,804.00 S/ 6,804.00
06.03 MARTILLOS
06.03.01 OBRAS PRELIMINARES
06.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 972.64 S/ 0.82 S/ 797.56 S/ 569.87 S/ 227.69
06.03.01.02 TRAZO, NIVELACION Y REPLANTEO m2 972.64 S/ 2.30 S/ 2,237.07 S/ 2,237.07
06.03.02 MOVIMIENTO DE TIERRAS
06.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL EN MARTILLOS m3 176.91 S/ 26.82 S/ 4,744.73 S/ 713.94 S/ 4,030.79
06.03.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 212.29 S/ 32.19 S/ 6,833.62 S/ 778.50 S/ 4,628.12 S/ 1,427.00
06.03.02.03 PERFILADO Y COMPACTADO EN MARTILLOS m2 972.64 S/ 4.67 S/ 4,542.23 S/ 4,542.23
06.03.03 CONCRETO
06.03.03.01 MATERIAL GRANULAR e=0.05m m2 972.64 S/ 8.88 S/ 8,637.04 S/ 8,415.69 S/ 221.35
06.03.03.02 CONCRETO FC=175 KG/CM2 EN RAMPAS, INC. BRUÑADO m3 128.31 S/ 582.87 S/ 74,788.05 S/ 32,545.25 S/ 42,242.80
06.03.03.03 ENCOFRADO Y DESENCOFRADO DE MARTILLOS m2 347.19 S/ 48.34 S/ 16,783.16 S/ 10,068.94 S/ 6,714.22
06.04 RAMPAS
06.04.01 OBRAS PRELIMINARES
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS URBANAS EN LA URBANIZACIÓN 15 DE AGOSTO EN EL BARRIO HUAYCO, DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTIN - DEPARTAMENTO DE SAN MARTIN",
CUI: 2519696
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08
06.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 70.80 S/ 0.82 S/ 58.06 S/ 58.06
06.04.01.02 TRAZO, NIVELACION Y REPLANTEO m2 70.80 S/ 2.30 S/ 162.84 S/ 162.84
06.04.02 MOVIMIENTO DE TIERRAS
06.04.02.01 EXCAVACION MANUAL EN TERRENO NORMAL EN RAMPAS m3 15.74 S/ 26.82 S/ 422.15 S/ 422.15
06.04.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 18.89 S/ 32.19 S/ 608.07 S/ 608.07
06.04.02.03 PERFILADO Y COMPACTADO EN MARTILLOS m2 70.80 S/ 4.67 S/ 330.64 S/ 330.64
06.04.03 CONCRETO
06.04.03.01 MATERIAL GRANULAR e=0.05m m2 70.80 S/ 8.88 S/ 628.70 S/ 628.70
06.04.03.02 CONCRETO FC=175 KG/CM2 EN RAMPAS, INC. BRUÑADO m3 12.13 S/ 582.87 S/ 7,070.21 S/ 7,070.21
06.04.03.03 ENCOFRADO Y DESENCOFRADO DE RAMPAS m2 56.15 S/ 48.34 S/ 2,714.29 S/ 2,714.29
06.05 ACCESO PEATONAL
06.05.01 OBRAS PRELIMINARES
06.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 75.00 S/ 0.82 S/ 61.50 S/ 61.50
06.05.01.02 TRAZO, NIVELACION Y REPLANTEO m2 75.00 S/ 2.30 S/ 172.50 S/ 172.50
06.05.02 CONCRETO
06.05.02.01 CONCRETO FC=210 KG/CM2 PARA ACCESOS m3 10.98 S/ 673.74 S/ 7,397.67 S/ 5,485.46 S/ 1,912.21
06.05.02.02 ENCOFRADO Y DESENCOFRADO EN ACCESOS m2 54.52 S/ 48.34 S/ 2,635.50 S/ 2,635.50
06.05.02.03 ACERO F'Y=4200 KG/CM2 EN ACCESOS kg 491.89 S/ 9.32 S/ 4,584.41 S/ 4,584.41
07 DRENAJE PLUVIAL SUPERFICIAL
07.01 DRENAJE TAPADO DE CONCRETO ARMADO
07.01.01 OBRAS PRELIMINARES
07.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,128.36 S/ 0.82 S/ 925.26 S/ 925.26
07.01.01.02 TRAZO, NIVELACION Y REPLANTEO m2 1,128.36 S/ 2.30 S/ 2,595.23 S/ 2,595.23
07.01.02 MOVIMIENTO DE TIERRAS
07.01.02.01 DEMOLICION DE ESTRUCTURAS EXISTENTES m3 1.84 S/ 54.45 S/ 100.19 S/ 100.19
07.01.02.02 EXCAVACION MANUAL EN TERRENO NORMAL m3 1,124.16 S/ 40.23 S/ 45,224.96 S/ 25,362.25 S/ 12,362.25 S/ 7,500.46
07.01.02.03 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 1,351.20 S/ 32.19 S/ 43,495.13 S/ 12,532.36 S/ 18,362.35 S/ 12,600.42
07.01.02.04 PERFILADO Y COMPACTADO EN DRENAJE m2 1,128.36 S/ 4.67 S/ 5,269.44 S/ 5,269.44
07.01.03 CONCRETO
07.01.03.01 SOLADOS EN CUNETAS, CONCRETO F'C=100 KG/CM2 m2 1,128.36 S/ 33.79 S/ 38,127.28 S/ 15,362.54 S/ 22,764.74
07.01.03.02 CONCRETO FC=210 KG/CM2 EN DRENAJE m3 603.91 S/ 673.74 S/ 406,878.32 S/ 267,083.28 S/ 81,953.33 S/ 57,841.71
07.01.03.03 ENCOFRADO Y DESENCOFRADO EN DRENAJE m2 4,853.59 S/ 48.34 S/ 234,622.54 S/ 80,652.65 S/ 75,254.15 S/ 78,715.74
07.01.03.04 ACERO F'Y=4200 KG/CM2 EN DRENAJE kg 35,257.68 S/ 9.32 S/ 328,601.58 S/ 82,542.35 S/ 84,581.77 S/ 75,365.55 S/ 86,111.91
07.01.03.05 JUNTA DE DILATACION CON WATER STOP m 435.80 S/ 16.60 S/ 7,234.28 S/ 7,234.28
07.01.04 VARIOS
07.01.04.01 TAPA DE DRENAJE TAPADO und 101.00 S/ 95.57 S/ 9,652.57 S/ 8,388.58 S/ 1,263.99
07.01.04.02 REJILLA METALICA PARA CUNETA TAPADA und 41.00 S/ 327.45 S/ 13,425.45 S/ 10,849.38 S/ 2,576.07
07.02 DESEMBOCADURA
07.02.01 OBRAS PRELIMINARES
07.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 49.54 S/ 0.82 S/ 40.62 S/ 40.62
07.02.01.02 TRAZO, NIVELACION Y REPLANTEO m2 49.54 S/ 2.30 S/ 113.94 S/ 113.94
07.02.02 MOVIMIENTO DE TIERRAS
07.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 17.64 S/ 40.23 S/ 709.66 S/ 709.66
07.02.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 21.17 S/ 32.19 S/ 681.46 S/ 681.46
07.02.02.03 PERFILADO Y COMPACTADO EN DRENAJE m2 49.54 S/ 4.67 S/ 231.35 S/ 231.35
07.02.03 CONCRETO
07.02.03.01 SOLADOS EN CUNETAS, CONCRETO F'C=100 KG/CM2 m2 49.54 S/ 33.79 S/ 1,673.96 S/ 1,673.96
07.02.03.02 CONCRETO FC=210 KG/CM2 EN DRENAJE m3 6.88 S/ 673.74 S/ 4,635.33 S/ 4,635.33
07.02.03.03 ENCOFRADO Y DESENCOFRADO EN DRENAJE m2 38.24 S/ 48.34 S/ 1,848.52 S/ 1,848.52
07.02.03.04 ACERO F'Y=4200 KG/CM2 EN DRENAJE kg 235.72 S/ 9.32 S/ 2,196.91 S/ 2,196.91
07.02.03.05 JUNTA ASFALTICA EN DRENAJE m 17.04 S/ 53.32 S/ 908.57 S/ 908.57
07.02.03.06 EMPEDRADO CON CONCRETO FC=210 KG/CM2 m2 27.60 S/ 229.94 S/ 6,346.34 S/ 6,346.34
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS URBANAS EN LA URBANIZACIÓN 15 DE AGOSTO EN EL BARRIO HUAYCO, DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTIN - DEPARTAMENTO DE SAN MARTIN",
CUI: 2519696
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08
07.02.03.07 COLOCACION DE PIEDRAS GRANDE DE 10" m3 10.80 S/ 92.87 S/ 1,003.00 S/ 1,003.00
07.03 DRENAJE ABIERTO DE CONCRETO SIMPLE
07.03.01 OBRAS PRELIMINARES
07.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 352.52 S/ 0.82 S/ 289.07 S/ 289.07
07.03.01.02 TRAZO, NIVELACION Y REPLANTEO m2 352.52 S/ 2.30 S/ 810.80 S/ 810.80
07.03.02 MOVIMIENTO DE TIERRAS
07.03.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 227.06 S/ 40.23 S/ 9,134.62 S/ 2,929.50 S/ 4,530.96 S/ 1,674.16
07.03.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 272.47 S/ 32.19 S/ 8,770.81 S/ 1,544.71 S/ 4,530.96 S/ 2,695.14
07.03.02.03 PERFILADO Y COMPACTADO EN DRENAJE m2 352.52 S/ 4.67 S/ 1,646.27 S/ 1,646.27
07.03.03 CONCRETO
07.03.03.01 CONCRETO FC=210 KG/CM2 EN DRENAJE m3 124.05 S/ 673.74 S/ 83,577.45 S/ 25,262.25 S/ 35,625.36 S/ 22,689.84
07.03.03.02 ENCOFRADO Y DESENCOFRADO EN DRENAJE m2 919.77 S/ 48.34 S/ 44,461.68 S/ 29,576.84 S/ 14,115.01 S/ 769.83
07.03.03.03 JUNTA ASFALTICA EN DRENAJE m 202.20 S/ 53.32 S/ 10,781.30 S/ 10,781.30
08 SARDINEL Y MUROS DE CONCRETO
08.01 OBRAS PRELIMINARES
08.01.01 LIMPIEZA DE TERRENO MANUAL m2 289.36 S/ 0.82 S/ 237.28 S/ 237.28
08.01.02 TRAZO, NIVELACION Y REPLANTEO m2 289.36 S/ 2.30 S/ 665.53 S/ 665.53
08.02 MOVIMIENTO DE TIERRAS
08.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 113.90 S/ 40.23 S/ 4,582.20 S/ 1,935.85 S/ 2,646.35
08.02.02 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURA m3 26.52 S/ 40.15 S/ 1,064.78 S/ 1,064.78
08.02.03 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 104.86 S/ 32.19 S/ 3,375.44 S/ 3,085.74 S/ 289.70
08.02.04 PERFILADO Y COMPACTADO EN SARDINEL Y MUROS m2 289.36 S/ 4.67 S/ 1,351.31 S/ 1,351.31
08.03 CONCRETO
08.03.01 SOLADOS EN SARDINEL, CONCRETO F'C=100 KG/CM2 m2 212.24 S/ 33.79 S/ 7,171.59 S/ 7,171.59
08.03.02 CONCRETO FC=175 KG/CM2 PARA SARDINEL Y MUROS m3 136.19 S/ 592.42 S/ 80,681.68 S/ 38,542.25 S/ 33,313.44 S/ 8,825.99
08.03.03 ENCOFRADO Y DESENCOFRADO EN SARDINEL Y MUROS m2 1,528.95 S/ 48.34 S/ 73,909.44 S/ 42,369.72 S/ 14,568.74 S/ 14,098.78 S/ 2,872.20
08.03.04 ACERO F'Y=4200 KG/CM2 EN SARDINEL Y MUROS kg 3,724.72 S/ 9.32 S/ 34,714.39 S/ 33,291.04 S/ 1,423.35
08.03.05 JUNTA ASFALTICA EN SARDINEL Y MUROS m 255.40 S/ 53.32 S/ 13,617.93 S/ 8,542.25 S/ 5,075.68
09 AREAS VERDES
09.01 OBRAS PRELIMINARES
09.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,858.22 S/ 0.82 S/ 1,523.74 S/ 1,523.74
09.01.02 TRAZO, NIVELACION Y REPLANTEO m2 1,858.22 S/ 2.30 S/ 4,273.91 S/ 4,273.91
09.02 MOVIMIENTO DE TIERRAS
09.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 8.60 S/ 40.23 S/ 345.98 S/ 345.98
09.02.02 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURA m3 2.60 S/ 40.15 S/ 104.39 S/ 104.39
09.02.03 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 7.20 S/ 32.19 S/ 231.77 S/ 231.77
09.03 MOVIMIENTO DE TIERRAS
09.03.01 SEMBRADO DE GRASS m2 1,858.22 S/ 12.12 S/ 22,521.63 S/ 22,521.63
09.03.02 SEMBRADO DE PLANTONES ORNAMENTALES und 208.00 S/ 22.48 S/ 4,675.84 S/ 4,675.84
10 MITIGACION DE IMPACTOS AMBIENTALES
10.01 RIEGO CONTINUO EN OBRA m2 16,448.33 S/ 0.84 S/ 13,816.60 S/ 1,973.80 S/ 1,973.80 S/ 1,973.80 S/ 1,973.80 S/ 1,973.80 S/ 1,973.80 S/ 1,973.80
10.02 CILINDROS METALICOS PARA DISPOSICION DE RESIDUOS und 25.00 S/ 80.00 S/ 2,000.00 S/ 500.00 S/ 1,000.00 S/ 500.00
11 VARIOS
11.01 PLAN DE MONITOREO ARQUEOLOGICO glb 1.00 S/ 13,000.00 S/ 13,000.00 S/ 2,600.00 S/ 2,600.00 S/ 2,600.00 S/ 2,600.00 S/ 2,600.00
11.02 LIMPIEZA FINAL DE OBRA m2 18,476.52 S/ 0.33 S/ 6,097.25 S/ 6,097.25
COSTO DIRECTO S/ 4,871,536.14 S/ 186,450.98 S/ 106,955.80 S/ 174,102.97 S/ 633,637.74 S/ 1,098,325.50 S/ 1,290,891.59 S/ 867,005.82 S/ 514,165.74
GASTOS GENERALES 10%CD S/ 487,153.61 S/ 18,645.10 S/ 10,695.58 S/ 17,410.30 S/ 63,363.77 S/ 109,832.55 S/ 129,089.16 S/ 86,700.58 S/ 51,416.57
UTILIDAD 5%CD S/ 243,576.81 S/ 9,322.55 S/ 5,347.79 S/ 8,705.15 S/ 31,681.89 S/ 54,916.28 S/ 64,544.58 S/ 43,350.29 S/ 25,708.29
SUB TOTAL S/ 5,602,266.56 S/ 214,418.63 S/ 122,999.17 S/ 200,218.42 S/ 728,683.40 S/ 1,263,074.33 S/ 1,484,525.33 S/ 997,056.69 S/ 591,290.60
IGV 18% S/ 1,008,407.98 S/ 38,595.35 S/ 22,139.85 S/ 36,039.32 S/ 131,163.01 S/ 227,353.38 S/ 267,214.56 S/ 179,470.20 S/ 106,432.31
COSTO DE OBRA S/ 6,610,674.54 S/ 253,013.98 S/ 145,139.02 S/ 236,257.74 S/ 859,846.41 S/ 1,490,427.71 S/ 1,751,739.89 S/ 1,176,526.89 S/ 697,722.91
PORCENTAJE 100% 3.83% 2.20% 3.57% 13.01% 22.55% 26.50% 17.80% 10.55%
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS URBANAS EN LA URBANIZACIÓN 15 DE AGOSTO EN EL BARRIO HUAYCO, DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTIN - DEPARTAMENTO DE SAN MARTIN",
CUI: 2519696
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08
PORCENTAJE ACUMULADO 3.83% 6.02% 9.60% 22.60% 45.15% 71.65% 89.45% 100.00%