OBRA:
"MEJORAMIENTO DE LAS CALLES: RAMÓN CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALÉN, ANGOSTURA,
MICAELA BASTIDAS, TÚPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELASCO ALVARADO, EN LA ASOCIACIÓN DE
VIVIENDA ANGOSTURA, DISTRITO DE SAYLLA, PROVINCIA DE CUSCO - CUSCO”
RESIDENTE DE OBRA:
ING. JUAN ROLANDO MONTOYA CONCHA
SUPERVISIÓN:
ING. MIGUEL ANGEL CAJIGAS GRAJEDA
OBRA "MEJORAMIENTO DE LAS CALLES: RAMÓN CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALÉN, ANGOSTURA,
MICAELA BASTIDAS, TÚPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELASCO ALVARADO, EN LA
ASOCIACIÓN DE VIVIENDA ANGOSTURA, DISTRITO DE SAYLLA, PROVINCIA DE CUSCO - CUSCO”
UBICACIÓN
REGION CUSCO
PROVINCIA CUSCO
DISTRITO SAYLLA
LOCALIDAD ASOCIACIÓN DE VIVIENDA ANGOSTURA
OBRA
PRESUPUESTO EXPEDIENTE TECNICO
PRESUPUESTO COSTO DIRECTO S/ 4,486,728.93
GASTOS GENERALES (7%) S/ 314,071.03
UTILIDAD (6.00%) S/ 269,203.74
SUB TOTAL S/ 5,070,003.70
IGV S/ 912,600.67
PRESUPUESTO REFERENCIAL DE OBRA S/ 5,982,604.37
GASTOS DE SUPERVISION (3%) S/ 134,601.87
PRESUPUESTO EXPEDIENTE TECNICO S/ 6,117,206.24
UNIDAD EJECUTORA
SECTOR GOBIERNOS LOCALES
PLIEGO MUNICIPALIDAD DISTRITAL DE SAYLLA
ENTIDAD MUNICIPALIDAD DISTRITAL DE SAYLLA
CODIGO UNICO 380600
MODALIDAD DE EJECUCION Por administración Indirecta - por contrata.
RESPONSABLES TECNICOS DE LA EJECUCION DE LA OBRA
SUPERVISION
SUPERVISOR DE OBRA ING. MIGUEL ANGEL CAJIGAS GRAJEDA
C.I.P 69591
CONTRATISTA
RESIDENTE DE OBRA ING. JUAN ROLANDO MONTOYA CONCHA
C.I.P 36215
PLAZOS DE EJECUCION DE LA OBRA
PLAZOS DE EJECUCION
FECHA DE ENTREGA DE TERRENO 8/25/2022
FECHA DE INICIO DEL PLAZO CONTRATO PRINCIPAL 8/26/2022
PLAZO CONTRACTUAL (DIAS CALENDARIOS) 270.00
FECHA DE TERMINO CONTRACTUAL 5/24/2022
FECHA DE SUSPENSION Nº 01 1/31/2023
FECHA DE REINICIO DE OBRA 4/17/2023
FECHA DE TERMINO REAL 8/6/2023
DEL PLAZO TOTAL DE EJECUCION
PLAZO TOTAL DE EJECUCION 270 DIAS CALENDARIO
RESUMEN DE LA VALORIZACION
AÑO 2023
MES INFORMADO AGOSTO
NUMERO DE INFORME 11
DIA INICIO DE REPORTE 1
DIA FINAL DE REPORTE 31
PERIODO DE VALORIZACIÓN DEL 1 AL 31 DE AGOSTO DE 2023
MONTO DE LA VALORIZACIÓN ACTUAL 66,670.40 Incluye IGV del 18%
MONTO DE LA VALORIZACIÓN ACUMULADA 5,324,590.42 Incluye IGV del 18%
DATOS E INFORMACION GENERAL DEL PROYECTO
OBRA "MEJORAMIENTO DE LAS CALLES: RAMÓN CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALÉN, ANGOSTURA,
MICAELA BASTIDAS, TÚPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELASCO ALVARADO, EN LA
ASOCIACIÓN DE VIVIENDA ANGOSTURA, DISTRITO DE SAYLLA, PROVINCIA DE CUSCO - CUSCO”
DE LOS REAJUSTES
SE PRESENTARÁ EN LA LIQUIDACIÓN
DE LAS AMORTIZACIONES
ADELANTO EN EFECTIVO NO SE SOLICITO
MONTO DEL ADELANTO CON IGV 0.00
MONTO DEL ADELANTO SIN IGV 0.00
FECHA DE ENTREGA DE ADELANTO DIRECTO 0.00
ADELANTO POR MATERIALES NO SE SOLICITO
MONTO DEL ADELANTO CON IGV 0.00
MONTO DEL ADELANTO SIN IGV 0.00
FECHA PAGO DEL ADELANTO MATERIALES 0.00
VIGENCIA DE CARTA DE FIANZA
CARTA DE FIANZA DE FIEL CUMPLIMIENTO N° 959801
MONTO 591,959.12
01 TRABAJOS PROVISIONALES 60,571.46 60,493.32 99.87% 78.14 0.13% 60,571.46 100.00% 0.00 0.00%
SEGURIDAD Y SALUD EN
02 122,094.31 122,052.98 99.97% 41.33 0.03% 122,094.31 100.00% 0.00 0.00%
OBRA
03 TRABAJOS PRELIMINARES 47,950.07 47,950.07 100.00% -5,197.83 -10.84% 42,752.24 89.16% 5,197.83 10.84%
04 DEMOLICIONES 25,960.82 25,960.82 100.00% 0.00 0.00% 25,960.82 100.00% 0.00 0.00%
05 PAVIMENTO RÍGIDO 2,318,505.06 2,275,687.31 98.15% 7,912.25 0.34% 2,283,599.56 98.49% 34,905.50 1.51%
06 VEREDAS 652,377.56 562,427.27 86.21% -2,698.80 -0.41% 559,728.47 85.80% 92,649.09 14.20%
07 CUNETAS LATERALES CON TAPA 868,091.76 596,059.26 68.66% -3,319.07 -0.38% 592,740.18 68.28% 275,351.58 31.72%
08 SEÑALIZACION 48,547.62 0.00 0.00% 48,547.62 100.00% 48,547.62 100.00% 0.00 0.00%
09 VARIOS 140,965.30 103,265.74 73.26% 3,271.86 2.32% 106,537.60 75.58% 34,427.70 24.42%
10 MITIGACIÓN DE IMPACTO AMBIENTAL 14,000.00 13,650.00 97.50% 350.00 2.50% 14,000.00 100.00% 0.00 0.00%
11 ACERO 140,407.49 135,696.05 96.64% 1,014.80 0.72% 136,710.85 97.37% 3,696.64 2.63%
COSTO DIRECTO 4,439,471.45 3,943,242.86 88.82% 50,000.30 1.13% 3,993,243.15 89.95% 446,228.33 10.05%
GASTOS GENERALES 310,763.00 276,027.00 3,500.02 279,527.02 31,235.98
UTILIDAD 266,368.29 236,594.57 3,000.02 239,594.59 26,773.70
SUB TOTAL 5,016,602.74 4,455,864.43 88.82% 56,500.34 1.13% 4,512,364.76 89.95% 504,238.01 10.05%
IGV (18%) 902,988.49 802,055.60 10,170.06 812,225.66 90,762.84
TOTAL OBRA 5,919,591.23 5,257,920.03 88.82% 66,670.40 1.13% 5,324,590.42 89.95% 595,000.85 10.05%
VAL ANTERIOR VAL ACTUAL VAL ACUMULADO SALDO PENDIENTE
FICHA DE IDENTIFICACIÓN DE OBRA
2.00 UBICACIÓN
REGION : CUSCO
PROVINCIA : CHUMBIVILCAS
DISTRITO : VELILLE
LOCALIDAD : SECTOR CASA BLANCA
6.00 FINANCIAMIENTO :
7.00 PROCESO DE SELECCIÓN : LICITACIÓN PUBLICA Nº009-2023-MDV-CS-1
8.00 CONTRATO DE OBRA : N° 007-2023-MDV/CS-1
9.00 FECHA DE FIRMA DE CONTRATO : 14 DE SEPTIEMBRE DEL 2023
10.00 MODALIDAD DE EJECUCIÓN : CONTRATA
SISTEMA DE CONTRATACIÓN : COSTOS UNITARIOS
Para efectos de mostrar el porcentaje de avance de obra real, se realiza las valorizacion respecto al presupuesto de ejecucion de obra, dado
que el monto contractual incluye tambien el pago del expediente tecnico.
RESUMEN DE PRESUPUESTO
PRESUPUESTO TOTAL S/.
PRESUPUESTO COSTO DIRECTO 4,486,728.93
GASTOS GENERALES (7%) 314,071.03
UTILIDAD (6.00%) 269,203.74
SUB TOTAL 5,070,003.70
IGV 912,600.67
PRESUPUESTO REFERENCIAL DE OBRA 5,982,604.37
TOTAL MONTO CONTRATADO 5,919,591.23
2.- UBICACIÓN
Distrito Saylla,
Provincia : Cusco,
Region : Cusco.
MEMORIA DESCRIPTIVA
INFORME MENSUAL N°11
2.2 DESCRIPCION DEL PROYECTO
METAS DEL PROYECTO
01 Descripción Unidad Metrado
01 TRABAJOS PROVISIONALES
01.01 CARTEL DE OBRA INC/ SUMINISTRO E INSTALACIÓN und 1.00
01.02 CASETA DE GUARDIANÍA Y ALMACÉN m2 300.00
01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y est 1.00
MAQUINARIAS
01.04 FLETE TERRESTRE glb 1.00
02 SEGURIDAD Y SALUD EN OBRA - -
02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00
02.02 EQUIPOS DE PROTECCION INDIVIDUAL und 40.00
02.03 EQUIPOS DE PROTECCION COLECTIVA mes 7.00
02.04 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD glb 1.00
02.05 CAPACITACION DE SEGURIDAD Y SALUD glb 1.00
02.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD glb 1.00
02.07 PROTOCOLO PARA LA VIGILANCIA, PREVENCION Y CONTROL DE LA SALUD DE LOS TRABAJADORES CON RIESGO DE EXPOS glb 1.00
03 TRABAJOS PRELIMINARES - -
03.01 TRAZO Y REPLANTEO DURANTE LA EJECUCIÓN DE LA OBRA m2 24,464.32
03.02 LIMPIEZA DE TERRENO MANUAL m2 24,464.32
04 DEMOLICIONES - -
04.01 DEMOLICION DE VEREDAS EXISTENTES m2 1,155.19
04.02 ELIMINACION DE MATERIAL EXCEDENTE D=25.5 km m3 150.17
05 PAVIMENTO RÍGIDO - -
05.01 MOVIMIENTO DE TIERRAS HASTA NIVEL DE SUB RASANTE - -
05.01.01 CORTE DE TERRENO A NIVEL DE SUBRASANTE m3 9,953.87
05.01.02 PERFILADO Y COMPACTADO DE SUB-RASANTE m2 13,174.87
05.01.03 ELIMINACION DE MATERIAL EXCEDENTE D=25.5 km m3 12,442.34
05.02 BASE GRANULAR - -
05.02.01 EXTRACCIÓN Y APILAMIENTO DE MATERIAL BASE EN CANTERA m3 4,742.95
05.02.02 ZARANDEADO DE MATERIAL DE PRESTAMO PARA BASE m3 4,742.95
05.02.03 CARGUIO Y TRANSPORTE DE MATERIAL DE PRESTAMO PARA BASE m3 4,742.95
05.02.04 CONFORMACIÓN DE MATERIAL BASE GRANULAR e=0.30 m m2 13,174.87
05.03 LOSA DE CONCRETO ARMADO e=0.20 m - -
05.03.01 ENCOFRADO Y DESENCOFRADO DE LOSA DE CONCRETO m2 1,917.37
05.03.02 CONCRETO f'c=210 kg/cm2 PARA LOSA DE CONCRETO e=0.20 m m3 2,634.97
05.03.03 CURADO DE CONCRETO CON ADITIVO m2 13,174.87
05.03.04 JUNTAS DE DILATACIÓN CON ASFALTO m 6,262.81
06 VEREDAS - -
06.01 CORTE DE TERRENO MANUAL m3 1,140.02
06.02 PERFILADO Y COMPACTADO DE SUBRASANTE m2 5,700.12
06.03 BASE GRANULAR PARA VEREDAS H=0.10 m m2 5,700.12
06.04 ELIMINACION DE MATERIAL EXCEDENTE D=25.5 km m3 1,425.03
06.05 ENCOFRADO Y DESENCOFRADO NORMAL EN VEREDAS m2 1,035.12
06.06 CONCRETO f'c=175 kg/cm2 EN VEREDAS m3 660.94
06.07 ACABADO SEMI PULIDO, BRUÑADO CON OCRE m2 5,700.12
06.08 JUNTAS ASFALTICAS m 1,473.60
06.09 CURADO DE CONCRETO CON ADITIVO m2 5,860.50
07 CUNETAS LATERALES CON TAPA - -
07.01 TRAZO, NIVELACION Y REPLANTEO INICIAL m2 2,030.49
07.02 EXCAVACION DE ZANJAS PARA CUNETAS m3 1,349.62
07.03 PERFILADO Y COMPACTADO DE FONDO DE CUNETA m2 2,030.58
07.04 ELIMINACION DE MATERIAL EXCEDENTE D=25.5 km m3 1,687.03
07.05 ENCOFRADO Y DESENCOFRADO DE CUNETAS m2 7,773.27
07.06 CONCRETO f'c=210 kg/cm2 PARA CUNETAS m3 779.10
07.07 TAPA DE CONCRETO ARMADO DE 0.10X0.40X1.50 M und 2,209.00
07.08 REJILLA SUMIDERO-PLAT 1 1/4"X1/4"@1/2" Y MARCO "L" 1 1/4" m2 8.40
08 SEÑALIZACION - -
08.01 SEÑALIZACION HORIZONTAL - -
08.01.01 PINTURA DE TRAFICO EN CRUCES PEATONALES m2 533.00
08.01.02 PINTURA DE TRAFICO EN BORDE DE VEREDAS m 3,338.92
08.01.03 PINTURA DE TRAFICO EN LINEAS CONTINUAS Y DISCONTINUAS m 1,615.55
08.01.04 MARCAS EN EL PAVIMENTO m2 60.12
08.02 SEÑALIZACION VERTICAL - -
08.02.01 SEÑALES VERTICALES PREVENTIVAS 0.60 x 0.60 m und 2.00
09 VARIOS - -
09.01 NIVELACIÓN DE TAPA DE BUZÓN und 21.00
09.02 NIVELACION DE CAJAS DE BUZONES DE AGUA Y DESAGUE und 124.00
09.03 GRASS EN CHAMPA m2 3,781.10
09.04 LIMPIEZA FINAL DE OBRA m2 24,464.42
09.05 REPOSICION DE TUBERIA DESAGUE EN PVC GLB 1.00
09.06 ACCESORIOS RED DE INSTALACION DOMICILIARIA PVC DE 1/2" PARA AGUAS glb 1.00
09.07 ACCESORIOS RED DE INSTALACION DOMICILIARIA PVC DE 4" PARA DESAGUE GLB 1.00
09.08 MONITOREO ARQUEOLOGICO SER 1.00
10 MITIGACIÓN DE IMPACTO AMBIENTAL - -
10.01 SENSIBILIZACION glb 1.00
10.02 TRATAMIENTO DE BOTADEROS glb 1.00
11 ACERO - -
11.01 ACERO CORRUGADO f'y= 4200 kg/cm2 GRADO 60 PARA PAVIMENTO RÍGIDO kg 8,210.63
11.02 ACERO CORRUGADO f'y= 4200 kg/cm2 GRADO 60 PARA PAVIMENTO RÍGIDO kg 1,629.36
11.03 ACERO LISO f'y= 4200 kg/cm2 GRADO 60 PARA PAVIMENTO RÍGIDO kg 13,957.89
CONSORCIO SAYLLA , mi representada realiza el control de materiales a traves de cada uno de los profesionales especialistas en su área ,en el
presente periodo se realizo el material de concreto in-situ a traves de la prueba de SLUMP para ver la trabajabilidad del concreto asi como
tambien se tomo muestras de briqueta para luego ser ensayos y determinar su compresión, teniendo como resultados que superan la
resistencia requerida.
En cuanto a la sub rasante, del canal lateral se realizo los ensayos de densidad de campo.
En cuanto a la actividad de curado de concreto se uso el aditivo curador , adicionalmente a eso se efectuo post- construcción el curado de los
elementos vaciados durante 7 dias.
EL CONSORCIO SAYLLA, ha realizado contratacion de personal obrero de la mano de obra no calificada del lugar para los trabajos a realizarse
desde inicios de la obra, asi como tambien personal de obra calificado en trabajos especializados.
Para cuestiones administrativas propias de la empresa, se han realizado anotaciones y control de asistencia del personal obrero. Asimismo se
realiza la capacitacion del personal obrero para los frentes de trabajo a realizarse durante el mes.
Se ha utilizado, equipo de topografia estacion total para trabajos de replanteo inicial de obra realizados en campo con ello se define los
siguientes trabajos: nivelacion y compactado en veredas y cunetas y vaciado de concreto en veredas y cunetas
* 01 Estacion Total
* 02 Nivel de Ingeniero + 01 estacion total
* 02 Volquetes
* 01 Retroexcavadora
* 01 Bobcat
* 02 Compactadoras manual
* 01 mini cargador
* Vibradora
* Cortadora de concreto
4.3 CONTROL DE HERRAMIENTAS.
Se utilizaron de acuerdo a la necesidad de los trabajos realizados como son:
* Palas.
* Picos.
* Barretas de Acero.
* Otros herramientas menores, de uso individual.
4.4 CONTROL DE CALIDAD.
EL CONSORCIO SAYLLA, reliza el control de calidad con los profesionales en campo donde ellos dan la capacitacion a los jefes de cuadrillas y
personal obrero de mano de obra calificada y no calificada sobre los correctos precedimientos constructivos de acuerdo a las especificaciones
tecnicas del expediente tecnico aprobado para con ello ejecutar una calidad de obra y cumpliendo los trabajos de acuerdo al planos, asi mismo
se realiza el control de la sub base y base atravez de proctor y la densidad de campo que se viene realizando insitu
AVANCES %
AVANCE FISICO MES ANTERIOR 88.82%
AVANCE FISICO ACTUAL AL COSTO DIRECTO 1.13%
AVANCE MENSUAL ACUMULADO 89.95%
SALDO POR EJECUTAR 10.05%
Entre el 1 y el 31 de AGOSTO del 2023. Se ha realizado la ejecucion física en una avance porcentual del mes que, de acuerdo a la programación
mensual.
Asi mismo en el presente periodo se culmino con los trabajos del contenido contractual de acuerdo alas metas programadas asi mismo se
ejecuto partidas adicionales de mayores metrados, habiendose presentado ala Supervision los respectivos expedientes tecnicos psra su
revision y aprobacion.
VALORIZACION
VALORIZACION
VALORIZACION VALORIZACION PROGRAMADA EJECUTADA
EJECUTADA
ACUMULADO
9.- OBSERVACIONES:
* Por la deficiencia en la elaboracion del expediente técnico la ejecucion de la obra requierre y tiene la necesidad de ejecutar obras adicionales
paraEntidad
La el cumplimiento de las metas,
viene incumpliendo conmotivo porde
los pagos el las
cualvalorizaciones
mi representada oportunamente
motivo por el cual ha
se presentado
ha PROCEDIDOel expediente
CON LA de SUSPENSION
los trabajos adicionales
DE LA Nº
* OBRA.
Se ha culminado con la ejecucion de todas la partidas del expediente de adicional de obra Nº 01, deductivo vinculante
*
Se recomienda a la Entidad, que a futuro como parte de la elaboracion del expediente tecnico, contratar a los correctos profesionales
especialistas para dicha elaboración de posteriores expedientes, puesto que en este proyecto se tiene innumerables contradicciones a nivel de
*
planos e inclusive en presupuesto los cuales fueron anotados en el cuaderno de obra digital, esto se corrobora con la cantidad de
documentación generada y entregada a la entidad y supervisión.
Se recomienda a la Entidad absolver referente a la aprobacion del adicional de obra Nº 02, y aprobacion del adicional Nº 05, deductivo
vinculante Nº 04. con un acto resolutivo. Para poder hacer entrega la ejecucion de la obra.
*
El incumplimiento de pago trae como consecuencia intereses a favor de mi representada y perjuicio a la Entidad por lo que debera tomar
acciones con la finalidad que en lo posterior perjudique a la entidad.
*
VALORIZACION MENSUAL DE OBRA N° 11 - CONTRATO PRINCIPAL DE OBRA
(DEL 1 AL 31 DE AGOSTO DE 2023)
: "MEJORAMIENTO DE LAS CALLES: RAMÓN CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALÉN, ANGOSTURA, MICAELA
OBRA BASTIDAS, TÚPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELASCO ALVARADO, EN LA ASOCIACIÓN DE VIVIENDA ANGOSTURA, PRESP. CONTRATO PRINCIPAL DE OB S/. 4,439,471.45
DISTRITO DE SAYLLA, PROVINCIA DE CUSCO - CUSCO”
EJECUTO: MUNICIPALIDAD DISTRITAL DE SAYLPLAZO DE EJECUCION: 270 Dias calendarios MONTOS VALORIZADOS
CONTRATCONSORCIO CCOLLANA INICIO DE OBRA: 26 de agosto de 2022 AVANCE FISICO ANTERIOR : S/. 3,943,242.86 88.82%
RESIDEN: ING. JUAN ROLANDO MONTOYA C UBICACIÓN: LUGAR DISTRITO PROVINCIA REGION AVANCE FISICO ACTUAL : S/. 50,000.30 1.13%
ASOCIACIÓN DE VIVIENDA
SUPERVIING. MIGUEL ANGEL CAJIGAS GRAJE ANGOSTURA SAYLLA CUSCO CUSCO AVANCE FISICO ACUMULADO : S/. 3,993,243.16 89.95%
PRESUPUESTO EXPEDIENTE AVANCES
SALDO PENDIENTE
ITEM PARTIDAS UND P. UNIT PRESUPUESTO ANTERIOR ACTUAL ACUMULADO
METRADO
S/. S/. METRADO VALORIZ. % METRADO VALORIZ. % METRADO VALORIZ. % METRADO VALORIZ. %
01 TRABAJOS PROVISIONALES 60,571.46 60,493.32 78.14 60,571.46 0.00
01.01 CARTEL DE OBRA INC/ SUMINISTRO und OK 1.00 1,183.66 1,183.66 1.00 1,183.66 100.00% 0.00 0.00 0.00% 1.00 1,183.66 100.00% 0.00 0.00 0.00%
01.02 CASETA DE GUARDIANÍA Y ALMACÉ m2 OK 300.00 18.58 5,574.00 300.00 5,574.00 100.00% 0.00 0.00 0.00% 300.00 5,574.00 100.00% 0.00 0.00 0.00%
MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y
01.03 est OK 1.00 7,813.80 7,813.80 0.99 7,735.66 95.00% 0.01 78.14 1.00% 1.00 7,813.80 100.00% 0.00 0.00 0.00%
MAQUINARIAS
01.04 FLETE TERRESTRE glb OK 1.00 46,000.00 46,000.00 1.00 46,000.00 100.00% 0.00 0.00 0.00% 1.00 46,000.00 100.00% 0.00 0.00 0.00%
02 SEGURIDAD Y SALUD
ELABORACION, EN OBRA
IMPLEMENTACION OK 122,094.31 122,052.98 41.33 122,094.31 0.00
Y ADMINISTRACION DEL PLAN DE
02.01 glb OK 1.00 8,550.00 8,550.00 1.00 8,550.00 100.00% 0.00 0.00 0.00% 1.00 8,550.00 100.00% 0.00 0.00 0.00%
SEGURIDAD Y SALUD EN EL
02.02 TRABAJO
EQUIPOS DE PROTECCION INDIVIDU und OK 40.00 293.42 11,736.80 40.00 11,736.80 100.00% 0.00 0.00 0.00% 40.00 11,736.80 100.00% 0.00 0.00 0.00%
02.03 EQUIPOS DE PROTECCION COLECTIV mes OK 7.00 69.05 483.35 7.00 483.35 100.00% 0.00 0.00 0.00% 7.00 483.35 100.00% 0.00 0.00 0.00%
02.04 SEÑALIZACIÓN TEMPORAL DE SEGU glb OK 1.00 7,191.44 7,191.44 1.00 7,191.44 90.00% 0.00 0.00 0.00% 1.00 7,191.44 100.00% 0.00 0.00 0.00%
02.05 CAPACITACION DE SEGURIDAD Y SA glb OK 1.00 2,340.00 2,340.00 0.99 2,316.60 93.00% 0.01 23.40 1.00% 1.00 2,340.00 100.00% 0.00 0.00 0.00%
RECURSOS PARA RESPUESTAS
02.06 ANTE EMERGENCIAS EN glb OK 1.00 1,792.72 1,792.72 0.99 1,774.79 93.00% 0.01 17.93 1.00% 1.00 1,792.72 100.00% 0.00 0.00 0.00%
SEGURIDAD
PROTOCOLOYPARA
SALUD
LA VIGILANCIA,
PREVENCION Y CONTROL DE LA
02.07 SALUD DE LOS TRABAJADORES glb OK 1.00 90,000.00 90,000.00 1.00 90,000.00 98.00% 0.00 0.00 0.00% 1.00 90,000.00 100.00% 0.00 0.00 0.00%
CON RIESGO DE EXPOSICION A
03 COVID-19
TRABAJOS PRELIMINARES OK 47,950.07 47,950.07 -5,197.83 42,752.25 5,197.83
03.01 TRAZO Y REPLANTEO DURANTE LA m2FALTA
24,464.32 1.50 36,696.48 24,464.32 36,696.48 100.00% -2,651.95 -3,977.93 -10.84% 21,812.37 32,718.56 89.16% 2,651.95 3,977.93 10.84%
03.02 LIMPIEZA DE TERRENO MANUAL m2FALTA
24,464.32 0.46 11,253.59 24,464.32 11,253.59 100.00% -2,651.95 -1,219.90 -10.84% 21,812.37 10,033.69 89.16% 2,651.95 1,219.90 10.84%
04 DEMOLICIONES OK 25,960.82 25,960.82 0.00 25,960.82 0.00
04.01 DEMOLICION DE VEREDAS EXISTENT m2 OK 1,155.19 16.21 18,725.63 1,155.19 18,725.63 100.00% 0.00 0.00 0.00% 1,155.19 18,725.63 100.00% 0.00 0.00 0.00%
04.02 ELIMINACION DE MATERIAL EXCEDE m3 OK 150.17 48.18 7,235.19 150.17 7,235.19 100.00% 0.00 0.00 0.00% 150.17 7,235.19 100.00% 0.00 0.00 0.00%
05 PAVIMENTO RÍGIDO OK
VALORIZACION MENSUAL DE OBRA N° 11 - CONTRATO PRINCIPAL DE OBRA
(DEL 1 AL 31 DE AGOSTO DE 2023)
: "MEJORAMIENTO DE LAS CALLES: RAMÓN CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALÉN, ANGOSTURA, MICAELA
OBRA BASTIDAS, TÚPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELASCO ALVARADO, EN LA ASOCIACIÓN DE VIVIENDA ANGOSTURA, PRESP. CONTRATO PRINCIPAL DE OB S/. 4,439,471.45
DISTRITO DE SAYLLA, PROVINCIA DE CUSCO - CUSCO”
EJECUTO: MUNICIPALIDAD DISTRITAL DE SAYLPLAZO DE EJECUCION: 270 Dias calendarios MONTOS VALORIZADOS
CONTRATCONSORCIO CCOLLANA INICIO DE OBRA: 26 de agosto de 2022 AVANCE FISICO ANTERIOR : S/. 3,943,242.86 88.82%
RESIDEN: ING. JUAN ROLANDO MONTOYA C UBICACIÓN: LUGAR DISTRITO PROVINCIA REGION AVANCE FISICO ACTUAL : S/. 50,000.30 1.13%
ASOCIACIÓN DE VIVIENDA
SUPERVIING. MIGUEL ANGEL CAJIGAS GRAJE ANGOSTURA SAYLLA CUSCO CUSCO AVANCE FISICO ACUMULADO : S/. 3,993,243.16 89.95%
PRESUPUESTO EXPEDIENTE AVANCES
SALDO PENDIENTE
ITEM PARTIDAS UND P. UNIT PRESUPUESTO ANTERIOR ACTUAL ACUMULADO
METRADO
S/. S/. METRADO VALORIZ. % METRADO VALORIZ. % METRADO VALORIZ. % METRADO VALORIZ. %
05.01 MOVIMIENTO DE TIERRAS HASTA NIVEL OK
D 2,318,505.06 2,275,687.32 7,912.25 2,283,599.56 34,905.49
05.01.01 CORTE DE TERRENO A NIVEL DE SU m3 OK 9,953.87 8.61 85,702.82 9,953.77 85,701.96 100.00% 0.10 0.86 0.00% 9,953.87 85,702.82 100.00% 0.00 0.00 0.00%
05.01.02 PERFILADO Y COMPACTADO DE SUB m2FALTA
13,174.87 2.83 37,284.88 13,174.87 37,284.88 100.00% -276.98 -783.85 -2.10% 12,897.89 36,501.03 97.90% 276.98 783.85 2.10%
05.01.03 ELIMINACION DE MATERIAL EXCEDE m3 OK12,442.34 48.18 599,471.94 12,442.34 599,471.94 100.00% 0.00 0.00 0.00% 12,442.34 599,471.94 100.00% 0.00 0.00 0.00%
05.02 BASE GRANULAR OK
05.02.01 EXTRACCIÓN Y APILAMIENTO DE M m3FALTA
4,742.95 7.21 34,196.67 4,742.95 34,196.67 100.00% -99.71 -718.91 -2.10% 4,643.24 33,477.76 97.90% 99.71 718.91 2.10%
05.02.02 ZARANDEADO DE MATERIAL DE PR m3FALTA 4,742.95 5.02 23,809.61 4,742.95 23,809.61 100.00% -99.71 -500.54 -2.10% 4,643.24 23,309.06 97.90% 99.71 500.54 2.10%
CARGUIO Y TRANSPORTE DE
05.02.03 MATERIAL DE PRESTAMO PARA m3FALTA
4,742.95 34.00 161,260.30 4,742.95 161,260.30 100.00% -99.71 -3,390.14 -2.10% 4,643.24 157,870.16 97.90% 99.71 3,390.14 2.10%
BASE
05.02.04 CONFORMACIÓN DE MATERIAL BASE m2FALTA 13,174.87 3.76 49,537.51 13,174.87 49,537.51 100.00% -276.98 -1,041.44 -2.10% 12,897.89 48,496.07 97.90% 276.98 1,041.44 2.10%
05.03 LOSA DE CONCRETO ARMADO e=0.20 m OK
05.03.01 ENCOFRADO Y DESENCOFRADO DE m2FALTA
1,917.37 43.61 83,616.51 1,855.51 80,918.79 96.63% 14.20 619.26 0.74% 1,869.71 81,538.05 97.51% 47.66 2,078.45 2.49%
05.03.02 CONCRETO f'c=210 kg/cm2 PARA LOS m3FALTA
2,634.97 454.15 1,196,671.63 2,549.97 1,158,068.88 96.65% 29.61 13,447.38 1.12% 2,579.58 1,171,516.26 97.90% 55.39 25,155.37 2.10%
05.03.03 CURADO DE CONCRETO CON ADITIV m2FALTA 13,174.87 1.13 14,887.60 12,749.66 14,407.12 96.62% 148.23 167.50 1.13% 12,897.89 14,574.62 97.90% 276.98 312.99 2.10%
05.03.04 JUNTAS DE DILATACIÓN CON ASFAL mFALTA 6,262.81 5.12 32,065.59 6,060.48 31,029.66 18.37% 21.90 112.13 0.35% 6,082.38 31,141.79 97.12% 180.43 923.80 2.88%
06 VEREDAS OK 652,377.56 562,427.29 -2,698.80 559,728.48 92,649.07
06.01 CORTE DE TERRENO MANUAL m3FALTA
1,140.02 46.03 52,475.12 1,140.02 52,475.12 100.00% -67.10 -3,088.61 -5.89% 1,072.92 49,386.51 94.11% 67.10 3,088.61 5.89%
06.02 PERFILADO Y COMPACTADO DE SU m2FALTA
5,700.12 6.52 37,164.78 5,573.08 36,336.48 97.77% -208.50 -1,359.42 -3.66% 5,364.58 34,977.06 94.11% 335.54 2,187.72 5.89%
06.03 BASE GRANULAR PARA VEREDAS H=0 m2FALTA 5,700.12 14.09 80,314.69 5,571.89 78,507.93 97.75% -207.31 -2,921.00 -3.64% 5,364.58 75,586.93 94.11% 335.54 4,727.76 5.89%
06.04 ELIMINACION DE MATERIAL EXCEDE m3FALTA 1,425.03 48.18 68,657.95 1,425.03 68,657.95 100.00% -83.89 -4,041.82 -5.89% 1,341.14 64,616.13 94.11% 83.89 4,041.82 5.89%
06.05 ENCOFRADO Y DESENCOFRADO NOR m2FALTA 1,035.12 58.29 60,337.14 948.81 55,306.13 88.01% 25.30 1,474.74 2.44% 974.11 56,780.87 94.11% 61.01 3,556.27 5.89%
06.06 CONCRETO f'c=175 kg/cm2 EN VERED m3FALTA660.94 420.00 277,594.80 605.85 254,457.00 88.03% 16.17 6,791.40 2.45% 622.02 261,248.40 94.11% 38.92 16,346.40 5.89%
06.07 ACABADO SEMI PULIDO, BRUÑADO m2FALTA
5,700.12 10.11 57,628.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,700.12 57,628.21 100.00%
06.08 JUNTAS ASFALTICAS mFALTA1,473.60 7.86 11,582.50 1,350.70 10,616.50 88.25% 36.10 283.75 2.45% 1,386.80 10,900.25 94.11% 86.80 682.25 5.89%
06.09 CURADO DE CONCRETO CON ADITIV m2FALTA 5,860.50 1.13 6,622.37 5,371.84 6,070.18 89.93% 143.50 162.16 2.45% 5,515.34 6,232.33 94.11% 345.16 390.03 5.89%
07 CUNETAS LATERALES CON TAPA OK 868,091.76 596,059.27 -3,319.07 592,740.21 275,351.55
07.01 TRAZO, NIVELACION Y REPLANTEO I m2FALTA 2,030.49 1.42 2,883.30 2,030.49 2,883.30 100.00% 63.36 89.97 3.12% 2,093.85 2,973.27 103.12% -63.36 -89.97 -3.12%
07.02 EXCAVACION DE ZANJAS PARA CUN m3FALTA 1,349.62 46.03 62,123.01 1,258.94 57,949.01 93.28% 102.06 4,697.82 7.56% 1,361.00 62,646.83 100.84% -11.38 -523.82 -0.84%
07.03 PERFILADO Y COMPACTADO DE FON m2FALTA 2,030.58 6.52 13,239.38 2,030.58 13,239.38 74.77% 63.27 412.52 3.12% 2,093.85 13,651.90 103.12% -63.27 -412.52 -3.12%
07.04 ELIMINACION DE MATERIAL EXCEDE m3FALTA 1,687.03 48.18 81,281.11 1,573.68 75,819.90 93.28% 127.57 6,146.32 7.56% 1,701.25 81,966.23 100.84% -14.22 -685.12 -0.84%
07.05 ENCOFRADO Y DESENCOFRADO DE m2FALTA
7,773.27 25.00 194,331.75 7,773.27 194,331.75 74.77% 239.20 5,980.00 3.08% 8,012.47 200,311.75 103.08% -239.20 -5,980.00 -3.08%
07.06 CONCRETO f'c=210 kg/cm2 PARA CUN m3FALTA779.10 433.46 337,708.69 580.99 251,835.93 74.57% -47.63 -20,645.70 -6.11% 533.36 231,190.23 68.46% 245.74 106,518.46 31.54%
07.07 TAPA DE CONCRETO ARMADO DE 0.10 undFALTA 2,209.00 75.00 165,675.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,209.00 165,675.00 100.00%
07.08 REJILLA SUMIDERO-PLAT 1 1/4"X1/4"@ m2FALTA 8.40 1,291.61 10,849.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.40 10,849.52 100.00%
VALORIZACION MENSUAL DE OBRA N° 11 - CONTRATO PRINCIPAL DE OBRA
(DEL 1 AL 31 DE AGOSTO DE 2023)
: "MEJORAMIENTO DE LAS CALLES: RAMÓN CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALÉN, ANGOSTURA, MICAELA
OBRA BASTIDAS, TÚPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELASCO ALVARADO, EN LA ASOCIACIÓN DE VIVIENDA ANGOSTURA, PRESP. CONTRATO PRINCIPAL DE OB S/. 4,439,471.45
DISTRITO DE SAYLLA, PROVINCIA DE CUSCO - CUSCO”
EJECUTO: MUNICIPALIDAD DISTRITAL DE SAYLPLAZO DE EJECUCION: 270 Dias calendarios MONTOS VALORIZADOS
CONTRATCONSORCIO CCOLLANA INICIO DE OBRA: 26 de agosto de 2022 AVANCE FISICO ANTERIOR : S/. 3,943,242.86 88.82%
RESIDEN: ING. JUAN ROLANDO MONTOYA C UBICACIÓN: LUGAR DISTRITO PROVINCIA REGION AVANCE FISICO ACTUAL : S/. 50,000.30 1.13%
ASOCIACIÓN DE VIVIENDA
SUPERVIING. MIGUEL ANGEL CAJIGAS GRAJE ANGOSTURA SAYLLA CUSCO CUSCO AVANCE FISICO ACUMULADO : S/. 3,993,243.16 89.95%
PRESUPUESTO EXPEDIENTE AVANCES
SALDO PENDIENTE
ITEM PARTIDAS UND P. UNIT PRESUPUESTO ANTERIOR ACTUAL ACUMULADO
METRADO
S/. S/. METRADO VALORIZ. % METRADO VALORIZ. % METRADO VALORIZ. % METRADO VALORIZ. %
08 SEÑALIZACION OK 48,547.62 0.00 48,547.62 48,547.62 0.00
08.01 SEÑALIZACION HORIZONTAL OK
08.01.01 PINTURA DE TRAFICO EN CRUCES P m2 OK 533.00 15.49 8,256.17 0.00 0.00 0.00% 533.00 8,256.17 100.00% 533.00 8,256.17 100.00% 0.00 0.00 0.00%
08.01.02 PINTURA DE TRAFICO EN BORDE DE V m OK 3,338.92 7.65 25,542.74 0.00 0.00 0.00% 3,338.92 25,542.74 100.00% 3,338.92 25,542.74 100.00% 0.00 0.00 0.00%
08.01.03 PINTURA DE TRAFICO EN LINEAS CON m OK 1,615.55 7.95 12,843.62 0.00 0.00 0.00% 1,615.55 12,843.62 100.00% 1,615.55 12,843.62 100.00% 0.00 0.00 0.00%
08.01.04 MARCAS EN EL PAVIMENTO m2 OK 60.12 23.55 1,415.83 0.00 0.00 0.00% 60.12 1,415.83 100.00% 60.12 1,415.83 100.00% 0.00 0.00 0.00%
08.02 SEÑALIZACION VERTICAL OK
08.02.01 SEÑALES VERTICALES PREVENTIVAS 0und OK 2.00 244.63 489.26 0.00 0.00 0.00% 2.00 489.26 100.00% 2.00 489.26 100.00% 0.00 0.00 0.00%
09 VARIOS OK 140,965.30 103,265.74 3,271.86 106,537.60 34,427.71
09.01 NIVELACIÓN DE TAPA DE BUZÓN und OK 21.00 186.94 3,925.74 21.00 3,925.74 100.00% 0.00 0.00 0.00% 21.00 3,925.74 100.00% 0.00 0.00 0.00%
09.02 NIVELACION DE CAJAS DE BUZONES und OK 124.00 35.00 4,340.00 124.00 4,340.00 100.00% 0.00 0.00 0.00% 124.00 4,340.00 100.00% 0.00 0.00 0.00%
09.03 GRASS EN CHAMPA m2FALTA3,781.10 9.00 34,029.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,781.10 34,029.90 100.00%
09.04 LIMPIEZA FINAL DE OBRA m2FALTA
24,464.42 0.15 3,669.66 0.00 0.00 0.00% 21,812.37 3,271.86 89.16% 21,812.37 3,271.86 89.16% 2,652.05 397.81 10.84%
09.05 REPOSICION DE TUBERIA DESAGUE GLB OK 1.00 15,000.00 15,000.00 1.00 15,000.00 100.00% 0.00 0.00 0.00% 1.00 15,000.00 100.00% 0.00 0.00 0.00%
09.06 ACCESORIOS RED DE INSTALACION D glb OK 1.00 20,000.00 20,000.00 1.00 20,000.00 100.00% 0.00 0.00 0.00% 1.00 20,000.00 100.00% 0.00 0.00 0.00%
09.07 ACCESORIOS RED DE INSTALACION GLB OK 1.00 25,000.00 25,000.00 1.00 25,000.00 100.00% 0.00 0.00 0.00% 1.00 25,000.00 100.00% 0.00 0.00 0.00%
09.08 MONITOREO ARQUEOLOGICO SER OK 1.00 35,000.00 35,000.00 1.00 35,000.00 100.00% 0.00 0.00 0.00% 1.00 35,000.00 100.00% 0.00 0.00 0.00%
10 MITIGACIÓN DE IMPACTO AMBIENTAL OK 14,000.00 13,650.00 350.00 14,000.00 0.00
10.01 SENSIBILIZACION glb OK 1.00 5,000.00 5,000.00 0.93 4,650.00 86.00% 0.07 350.00 7.00% 1.00 5,000.00 100.00% 0.00 0.00 0.00%
10.02 TRATAMIENTO DE BOTADEROS glb OK 1.00 9,000.00 9,000.00 1.00 9,000.00 100.00% 0.00 0.00 0.00% 1.00 9,000.00 100.00% 0.00 0.00 0.00%
11 ACERO OK 140,407.49 135,696.05 1,014.80 136,710.85 3,696.65
11.01 ACERO CORRUGADO f'y= 4200 kg/cm kgFALTA8,210.63 5.90 48,442.72 8,210.63 48,442.72 100.00% 172.00 1,014.80 2.09% 8,382.63 49,457.52 102.09% -172.00 -1,014.80 -2.09%
11.02 ACERO CORRUGADO f'y= 4200 kg/cm kg OK 1,629.36 5.90 9,613.22 1,629.36 9,613.22 100.00% 0.00 0.00 0.00% 1,629.36 9,613.22 100.00% 0.00 0.00 0.00%
11.03 ACERO LISO f'y= 4200 kg/cm2 GRAD kgFALTA
13,957.89 5.90 82,351.55 13,159.34 77,640.11 94.28% 0.00 0.00 0.00% 13,159.34 77,640.11 94.28% 798.55 4,711.45 5.72%
COSTO DIRECTO 4,439,471.45 3,943,242.86 88.82% 50,000.30 1.13% 3,993,243.16 89.95% 446,228.32 10.05%
GASTOS GENERALES 7.00% 310,763.00 276,027.00 88.82% 3,500.02 1.13% 279,527.02 89.95% 31,235.98 10.05%
UTILIDAD 6.00% 266,368.29 236,594.57 88.82% 3,000.02 1.13% 239,594.59 89.95% 26,773.70 10.05%
SUB TOTAL 5,016,602.74 4,455,864.43 88.82% 56,500.34 1.13% 4,512,364.77 89.95% 504,238.00 10.05%
I.G.V. 18% 18.00% 902,988.49 802,055.60 88.82% 10,170.06 1.13% 812,225.66 89.95% 90,762.84 10.05%
PRESUPUESTO DE OBRA 5,919,591.23 5,257,920.03 88.82% 66,670.40 1.13% 5,324,590.43 89.95% 595,000.84 10.05%
VAL ACTUAL VAL ACUMULADO SALDO PENDIENTE
CURVA DE CONTROL "S"
OBRA
"MEJORAMIENTO DE LAS CALLES: RAMÓN CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALÉN, ANGOSTURA, MICAELA BASTIDAS, TÚPAC CATARI, AGUSTÍN GAMARRA, Y AV.
JUAN VELASCO ALVARADO, EN LA ASOCIACIÓN DE VIVIENDA ANGOSTURA, DISTRITO DE SAYLLA, PROVINCIA DE CUSCO - CUSCO”
100.00%
100.00%
81.75% 89.81%
87.66%
86.67% 88.82%
80.00% 74.73% 74.73% 74.73% 82.74%
74.73% 74.73% 74.73% 75.98% 76.97%
68.74%
68.74%
60.00% 54.19%
54.19%
40.00%
36.56%
26.24% 36.56%
20.00% 8.06%
26.24%
0.00%
0.00% 0.00% 8.06%
44799 AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO
Column F Column J
La valorización fÍsica se observa en linea roja, y la programación de obra en linea azul. Asi tambien en el diagrama de barras abajo.
AVANCE DE OBRA
110.00%
90.00%
88.82% 89.95%
86.67%
70.00% 74.73% 74.73% 74.73% 75.98% 81.75%
68.74%
% DE AVANCE
50.00% 54.19%
30.00% 36.56%
26.24%
10.00%
8.06%
AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO
VALORIZACION EJECUTADA 8.06% 26.24% 36.56% 54.19% 68.74% 74.73% 74.73% 74.73% 75.98% 81.75% 86.67% 88.82% 89.95%
VALORIZACION PROGRAMADA 8.06% 26.24% 36.56% 54.19% 68.74% 74.73% 74.73% 74.73% 76.97% 82.74% 87.66% 89.81% 100.00%
MESES VALORIZADOS
SITUACION ACTUAL
ATRASADA
EN
-0.99%
CONSORCIO SAYLLA
CALENDARIO DE AVANCE DE OBRA VALORIZADO - ACTUALIZADO
ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE SAYLLA
NOMBRE DE
MEJORAMIENTO DE LAS CALLES, RAMON CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALEN, ANGOSTURA, MICAELA BASTIDAS, TUPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELAZCO ALVARADO DEN LA ASOCIACIÓN DE VIVIENDA ANGOSTURA
PROYECTO
UBICACIÓN SAYLLA - CUSCO - CUSCO AMPLIACION DE PLAZO N°03 15 DIAS
CONTRATISTA CONSORCIO SAYLLA AMPLIACION DE PLAZO N°04 20 DIAS
AMPLIACIÓN DE
PLAZO DE EJECUCIÓN 270 DIAS CALENDARIO
PLAZO N°04
AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO AGOSTO
(del 05 hasta el 24)
Item Descripción Unidad. Metrado Precio S/. Parcial S/.
6 30 31 30 31 31 0 0 14 31 30 30 6 19
6 36 67 97 128 159 159 159 173 204 234 264 270 289
01 TRABAJOS PROVISIONALES
01.01 CARTEL DE OBRA INC/ SUMINISTRO E INSTALACIÓN und 1.00 1,183.66 1,183.66 1,183.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02 CASETA DE GUARDIANÍA Y ALMACÉN m2 300.00 18.58 5,574.00 5,574.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARI est 1.00 7813.80 7,813.80 3,906.90 0.00 781.38 781.38 781.38 781.38 390.69 0.00 390.69 312.55 -312.55
01.04 FLETE TERRESTRE glb 1.00 46000.00 46,000.00 4,600.00 9,200.00 4,600.00 9,200.00 4,600.00 4,600.00 4,600.00 4,600.00 4,600.00 0.00 -4,600.00
02 SEGURIDAD Y SALUD EN OBRA
02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLA glb 1.00 8550.00 8,550.00 8,550.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02 EQUIPOS DE PROTECCION INDIVIDUAL und 40.00 293.42 11,736.80 5,868.40 2,934.20 0.00 0.00 0.00 0.00 0.00 2,934.20 0.00 0.00
02.03 EQUIPOS DE PROTECCION COLECTIVA mes 7.00 69.05 483.35 69.05 69.05 69.05 69.05 69.05 69.05 0.00 69.05 0.00 0.00
02.04 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD glb 1.00 7191.44 7,191.44 719.14 719.14 719.14 719.14 719.14 719.14 1,078.72 719.14 719.14 719.14 -359.55
02.05 CAPACITACION DE SEGURIDAD Y SALUD glb 1.00 2340.00 2,340.00 234.00 234.00 234.00 234.00 234.00 234.00 351.00 257.40 257.40 140.40 -70.20
02.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURID glb 1.00 1792.72 1,792.72 179.27 179.27 179.27 179.27 179.27 179.27 268.91 197.20 197.20 107.56 -53.77
02.07 PROTOCOLO PARA LA VIGILANCIA, PREVENCION Y CONTROL DE glb 1.00 90000.00 90,000.00 9,000.00 27,000.00 9,000.00 9,000.00 9,000.00 9,000.00 9,000.00 4,500.00 1,800.00 1,800.00 250.00 650.00
03 TRABAJOS PRELIMINARES
03.01 TRAZO Y REPLANTEO DURANTE LA EJECUCIÓN DE LA OBRA m2 24464.32 1.50 36,696.48 36,696.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02 LIMPIEZA DE TERRENO MANUAL m2 24464.32 0.46 11,253.59 2,512.98 8,619.47 0.00 0.00 0.00 0.00 0.00 0.00 121.14 0.00
04 DEMOLICIONES 0.00
04.01 DEMOLICION DE VEREDAS EXISTENTES m2 1155.19 16.21 18,725.63 3,160.95 15,564.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02 ELIMINACION DE MATERIAL EXCEDENTE D=25.5 km m3 150.17 48.18 7,235.19 2,442.73 4,792.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05 PAVIMENTO RÍGIDO
05.01 MOVIMIENTO DE TIERRAS HASTA NIVEL DE SUB RASANTE
05.01.01 CORTE DE TERRENO A NIVEL DE SUBRASANTE m3 9953.87 8.61 85,702.82 28,232.19 53,886.98 3,582.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.86
05.01.02 PERFILADO Y COMPACTADO DE SUB-RASANTE m2 13174.87 2.83 37,284.88 25,824.06 11,460.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.03 ELIMINACION DE MATERIAL EXCEDENTE D=25.5 km m3 12442.34 48.18 599,471.94 197,477.78 389,328.10 12,666.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.03
CONSORCIO SAYLLA
CALENDARIO DE AVANCE DE OBRA VALORIZADO - ACTUALIZADO
ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE SAYLLA
NOMBRE DE
MEJORAMIENTO DE LAS CALLES, RAMON CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALEN, ANGOSTURA, MICAELA BASTIDAS, TUPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELAZCO ALVARADO DEN LA ASOCIACIÓN DE VIVIENDA ANGOSTURA
PROYECTO
UBICACIÓN SAYLLA - CUSCO - CUSCO AMPLIACION DE PLAZO N°03 15 DIAS
CONTRATISTA CONSORCIO SAYLLA AMPLIACION DE PLAZO N°04 20 DIAS
AMPLIACIÓN DE
PLAZO DE EJECUCIÓN 270 DIAS CALENDARIO
PLAZO N°04
AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO AGOSTO
(del 05 hasta el 24)
Item Descripción Unidad. Metrado Precio S/. Parcial S/.
05.02 BASE GRANULAR
05.02.01 EXTRACCIÓN Y APILAMIENTO DE MATERIAL BASE EN CANTE m3 4742.95 7.21 34,196.67 12,709.36 12,457.58 9,029.73 0.00 0.00 0.00 0.00 0.00 0.00
05.02.02 ZARANDEADO DE MATERIAL DE PRESTAMO PARA BASE m3 4742.95 5.02 23,809.61 8,848.95 8,673.66 6,287.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.03 CARGUIO Y TRANSPORTE DE MATERIAL DE PRESTAMO PARA m3 4742.95 34.00 161,260.30 59,933.16 58,745.88 42,581.26 0.00 0.00 0.00 0.00 0.00 0.00
05.02.04 CONFORMACIÓN DE MATERIAL BASE GRANULAR e=0.30 m m2 13174.87 3.76 49,537.51 21,029.68 15,427.28 13,080.55 0.00 0.00 0.00 0.00 0.00 0.00
05.03 LOSA DE CONCRETO ARMADO e=0.20 m
05.03.01 ENCOFRADO Y DESENCOFRADO DE LOSA DE CONCRETO m2 1917.37 43.61 83,616.51 0.00 34,158.40 28,756.43 11,988.39 3,000.37 4,531.95 0.00 118.62 0.00 1,062.35
05.03.02 CONCRETO f'c=210 kg/cm2 PARA LOSA DE CONCRETO e=0.20 m m3 2634.97 454.15 1,196,671.63 0.00 447,596.62 402,036.29 207,941.66 34,197.50 64,752.71 0.00 1,544.11 0.00 38,602.74
05.03.03 CURADO DE CONCRETO CON ADITIVO m2 13174.87 1.13 14,887.60 0.00 5,568.47 5,568.47 2,586.97 419.51 660.60 0.00 22.61 60.97
05.03.04 JUNTAS DE DILATACIÓN CON ASFALTO m 6262.81 5.12 32,065.59 0.00 0.00 0.00 5,890.05 0.00 0.00 0.00 25,139.61 1,035.93
06 VEREDAS
06.01 CORTE DE TERRENO MANUAL m3 1140.02 46.03 52,475.12 48,820.34 3,654.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02 PERFILADO Y COMPACTADO DE SUBRASANTE m2 5700.12 6.52 37,164.78 3,488.07 22,091.06 10,757.35 0.00 0.00 828.30 0.00 0.00 0.00 0.00
06.03 BASE GRANULAR PARA VEREDAS H=0.10 m m2 5700.12 14.09 80,314.69 7,113.20 47,739.74 18,751.68 4,903.32 0.00 1,806.76 0.00 0.00 0.00 0.00 -0.01
06.04 ELIMINACION DE MATERIAL EXCEDENTE D=25.5 km m3 1425.03 48.18 68,657.95 63,875.84 4,781.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.24
06.05 ENCOFRADO Y DESENCOFRADO NORMAL EN VEREDAS m2 1035.12 58.29 60,337.14 35,864.67 8,677.63 4,470.26 1,319.10 5,657.04 1,428.11 1,340.67 2,205.69 0.00 -626.03
06.06 CONCRETO f'c=175 kg/cm2 EN VEREDAS m3 660.94 420.00 277,594.80 160,322.40 35,952.00 18,522.00 4,027.80 23,333.52 19,714.80 5,821.20 10,096.80 0.00 -195.72
06.07 ACABADO SEMI PULIDO, BRUÑADO CON OCRE m2 5700.12 10.11 57,628.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57,628.21
06.08 JUNTAS ASFALTICAS m 1473.60 7.86 11,582.50 0.00 0.00 0.00 2,784.01 0.00 0.00 7,438.00 394.49 966.00
06.09 CURADO DE CONCRETO CON ADITIVO m2 5860.50 1.13 6,622.37 3,828.67 841.12 433.30 108.31 519.03 615.17 129.26 114.36 33.15
07 CUNETAS LATERALES CON TAPA
07.01 TRAZO, NIVELACION Y REPLANTEO INICIAL m2 2030.49 1.42 2,883.30 945.10 1,806.79 0.00 0.00 0.00 0.00 131.41 131.41 0.00 0.00 0.00 -131.41
07.02 EXCAVACION DE ZANJAS PARA CUNETAS m3 1349.62 46.03 62,123.01 19,915.80 38,033.37 0.00 0.00 0.00 0.00 3,314.16 0.00 0.00 0.00 0.00 859.68
07.03 PERFILADO Y COMPACTADO DE FONDO DE CUNETA m2 2030.58 6.52 13,239.38 0.00 758.93 1,306.61 0.00 782.40 3,338.24 4,494.89 3,340.72 0.00 -782.41
07.04 ELIMINACION DE MATERIAL EXCEDENTE D=25.5 km m3 1687.03 48.18 81,281.11 26,057.67 49,762.32 0.00 0.00 0.00 0.00 4,336.20 0.00 0.00 0.00 0.00 1,124.92
CONSORCIO SAYLLA
CALENDARIO DE AVANCE DE OBRA VALORIZADO - ACTUALIZADO
ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE SAYLLA
NOMBRE DE
MEJORAMIENTO DE LAS CALLES, RAMON CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALEN, ANGOSTURA, MICAELA BASTIDAS, TUPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELAZCO ALVARADO DEN LA ASOCIACIÓN DE VIVIENDA ANGOSTURA
PROYECTO
UBICACIÓN SAYLLA - CUSCO - CUSCO AMPLIACION DE PLAZO N°03 15 DIAS
CONTRATISTA CONSORCIO SAYLLA AMPLIACION DE PLAZO N°04 20 DIAS
AMPLIACIÓN DE
PLAZO DE EJECUCIÓN 270 DIAS CALENDARIO
PLAZO N°04
AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO JUNIO JULIO AGOSTO AGOSTO
(del 05 hasta el 24)
Item Descripción Unidad. Metrado Precio S/. Parcial S/.
07.05 ENCOFRADO Y DESENCOFRADO DE CUNETAS m2 7773.27 25.00 194,331.75 0.00 5,820.00 10,580.00 0.00 700.00 60,125.00 68,770.00 49,036.75 0.00 -700.00
07.06 CONCRETO f'c=210 kg/cm2 PARA CUNETAS m3 779.10 433.46 337,708.69 0.00 17,060.99 33,809.88 0.00 3,988.92 79,323.18 121,641.88 0.00 0.00 81,883.84
07.07 TAPA DE CONCRETO ARMADO DE 0.10X0.40X1.50 M und 2209.00 75.00 165,675.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 165,675.00
07.08 REJILLA SUMIDERO-PLAT 1 1/4"X1/4"@1/2" Y MARCO "L" 1 1/4" m2 8.40 1291.61 10,849.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,849.52
08 SEÑALIZACION
08.01 SEÑALIZACION HORIZONTAL
08.01.01 PINTURA DE TRAFICO EN CRUCES PEATONALES m2 533.00 15.49 8,256.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,256.17
08.01.02 PINTURA DE TRAFICO EN BORDE DE VEREDAS m 3338.92 7.65 25,542.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25,542.74
08.01.03 PINTURA DE TRAFICO EN LINEAS CONTINUAS Y DISCONTINU m 1615.55 7.95 12,843.62 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12,843.62
08.01.04 MARCAS EN EL PAVIMENTO m2 60.12 23.55 1,415.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,415.83
08.02 SEÑALIZACION VERTICAL
08.02.01 SEÑALES VERTICALES PREVENTIVAS 0.60 x 0.60 m und 2.00 244.63 489.26 0.00 0.00 0.00 489.26
09 VARIOS
09.01 NIVELACIÓN DE TAPA DE BUZÓN und 21.00 186.94 3,925.74 0.00 2,056.34 934.70 0.00 934.70 186.94 0.00 0.00 0.00 -186.94
09.02 NIVELACION DE CAJAS DE BUZONES DE AGUA Y DESAGUE und 124.00 35.00 4,340.00 2,604.00 1,736.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.03 GRASS EN CHAMPA m2 3781.10 9.00 34,029.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 34,029.90
09.04 LIMPIEZA FINAL DE OBRA m2 24464.42 0.15 3,669.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,669.66
09.05 REPOSICION DE TUBERIA DESAGUE EN PVC GLB 1.00 15000.00 15,000.00 6,000.00 6,000.00 3,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.06 ACCESORIOS RED DE INSTALACION DOMICILIARIA PVC DE 1/2" glb 1.00 20000.00 20,000.00 8,000.00 8,000.00 4,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.07 ACCESORIOS RED DE INSTALACION DOMICILIARIA PVC DE 4" P GLB 1.00 25000.00 25,000.00 15,000.00 5,000.00 5,000.00 0.00 0.00 0.00 0.00 0.00 0.00
09.08 MONITOREO ARQUEOLOGICO SER 1.00 35000.00 35,000.00 35,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 MITIGACIÓN DE IMPACTO AMBIENTAL
10.01 SENSIBILIZACION glb 1.00 5000 5,000.00 500.00 500.00 0.00 0.00 500.00 1,000.00 0.00 1,100.00 700.00 350.00 350.00
10.02 TRATAMIENTO DE BOTADEROS glb 1.00 9,000.00 9,000.00 6,300.00 2,700.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 ACERO
11.01 ACERO CORRUGADO f'y= 4200 kg/cm2 GRADO 60 PARA PAVIMENT kg 8,210.63 5.90 48,442.72 0.00 37,668.08 10,774.64 0.00 0.00 0.00 0.00 0.00 0.00
11.02 ACERO CORRUGADO f'y= 4200 kg/cm2 GRADO 60 PARA PAVIMENT kg 1,629.36 5.90 9,613.22 0.00 4,653.15 4,960.07 0.00 0.00 0.00 0.00 0.00 0.00
11.03 ACERO LISO f'y= 4200 kg/cm2 GRADO 60 PARA PAVIMENTO RÍGID kg 13,957.89 5.90 82,351.55 0.00 22,794.24 26,878.28 12,664.65 0.00 6,942.65 0.00 0.00 0.00 13,071.73
COSTO DIRECTO 4,439,471.45 357,826.09 807,051.34 458,400.83 782,338.24 645,995.63 265,893.78 0.00 0.00 99,639.14 256,127.75 218,421.47 95,443.41 695.25 451,638.51
% Valorizado Mensual 8.06% 18.18% 10.33% 17.62% 14.55% 5.99% 0.00% 0.00% 2.24% 5.77% 4.92% 2.15% 0.02% 10.17%
% Valorizado Acumulado 8.06% 26.24% 36.56% 54.19% 68.74% 74.73% 74.73% 74.73% 76.97% 82.74% 87.66% 89.81% 89.83% 100.00%
CONTROL
CONTROLDE
DEPAGO
PAGODE
DEVALORIZACIONES
VALORIZACIONES
CONTRATO DE OBRA N° 007-2023-MDV/CS-1
OBRA "MEJORAMIENTO DE LAS CALLES: RAMÓN
CASTILLA, TOMASA TITO CONDEMAYTA,
JERUSALÉN, ANGOSTURA, MICAELA BASTIDAS,
TÚPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN
VELASCO ALVARADO, EN LA ASOCIACIÓN DE
VIVIENDA ANGOSTURA, DISTRITO DE SAYLLA,
ENTIDAD : MUNICIPALIDAD DISTRITAL DE SAYLLA
CONTRATISTA : CONSORCIO SYLLA
RESIDENTE DE OBRA ING. JUAN ROLANDO MONTOYA CONCHA
INSPECTOR DE OBRA ING. MIGUEL ANGEL CAJIGAS GRAJEDA
MONTO MONTO
MONTO
DESCRIPCIÓN PAGADO O PENDIENTE POR
VALORIZADO
DEPOSITADO PAGAR
|
VALORIZACION N° 01 (MES DE AGOSTS/. 477,125.32 S/. 477,125.32 S/. 0.00
VALORIZACION N° 02 (MES DE SEPTIES/. 1,076,122.25 S/. 1,076,122.25 S/. 0.00
VALORIZACION N° 03 (MES DE OCTUBS/. 611,231.69 S/. 611,231.69 S/. 0.00
VALORIZACION N° 04 (MES DE NOVIE S/. 1,043,169.81 S/. 1,043,169.81 S/. 0.00
VALORIZACION N° 05 (MES DE DICIEMS/. 861,370.57 S/. 861,370.57 S/. 0.00
VALORIZACION N° 06 (MES DE ENERO)S/. 354,542.76 S/. 354,542.76 S/. 0.00
VALORIZACION N° 07 (MES DE ABRIL)S/. 74,329.44 S/. 74,329.44 S/. 0.00
VALORIZACION N° 08 (MES DE MAYO)S/. 341,520.74 S/ - S/. 341,520.74
VALORIZACION N° 09 (MES DE JUNIO) S/. 291,243.19 S/ - S/. 291,243.19
VALORIZACION N° 10 (MES DE JULIO) S/. 127,264.24 S/ - S/. 127,264.24
VALORIZACION N° 11 (MES DE AGOSTS/. 66,670.40 S/ - S/. 66,670.40
TOTAL PAGADO S/. 5,324,590.41 S/. 4,423,562.40 S/. 0.00
RESUMEN DE METRADOS EJECUTADOS CONTRATO PRINCIPAL
(DEL 1 AL 31 DE AGOSTO DE 2023)
: "MEJORAMIENTO DE LAS CALLES: RAMÓN CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALÉN, ANGOSTURA,
OBRA MICAELA BASTIDAS, TÚPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELASCO ALVARADO, EN LA ASOCIACIÓN
DE VIVIENDA ANGOSTURA, DISTRITO DE SAYLLA, PROVINCIA DE CUSCO - CUSCO”
METRADO
METRADO METRAD
ITEM DESCRIPCION (SEGÚN PARTIDA) EXP. METRAD
MENSUAL O ACUM.
TECNICO O SALDO
01 TRABAJOS PROVISIONALES
01.01 CARTEL DE OBRA INC/ SUMINISTRO E INSTALACIÓN und 1.00 0.00 1.00 0.00
01.02 CASETA DE GUARDIANÍA Y ALMACÉN m2 300.00 0.00 300.00 0.00
01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS est 1.00 0.01 1.00 0.00
01.04 FLETE TERRESTRE glb 1.00 0.00 1.00 0.00
02 SEGURIDAD Y SALUD EN OBRA
02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 0.00 1.00 0.00
02.02 EQUIPOS DE PROTECCION INDIVIDUAL und 40.00 0.00 40.00 0.00
02.03 EQUIPOS DE PROTECCION COLECTIVA mes 7.00 0.00 7.00 0.00
02.04 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD glb 1.00 0.00 1.00 0.00
02.05 CAPACITACION DE SEGURIDAD Y SALUD glb 1.00 0.01 1.00 0.00
02.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD glb 1.00 0.01 1.00 0.00
PROTOCOLO PARA LA VIGILANCIA, PREVENCION Y CONTROL DE LA SALUD DE LOS TRABAJADORES CON RIESGO
02.07
DE EXPOSICION A COVID-19
glb 1.00 0.00 1.00 0.00
03 TRABAJOS PRELIMINARES
03.01 TRAZO Y REPLANTEO DURANTE LA EJECUCIÓN DE LA OBRA m2 24464.32 -2651.95 21,812.37 2,651.95
03.02 LIMPIEZA DE TERRENO MANUAL m2 24464.32 -2651.95 21,812.37 2,651.95
04 DEMOLICIONES
05.02.01 EXTRACCIÓN Y APILAMIENTO DE MATERIAL BASE EN CANTERA m3 4742.95 -99.71 4,643.24 99.71
05.02.02 ZARANDEADO DE MATERIAL DE PRESTAMO PARA BASE m3 4742.95 -99.71 4,643.24 99.71
CARGUIO Y TRANSPORTE DE MATERIAL DE PRESTAMO PARA
05.02.03
BASE
m3 4742.95 -99.71 4,643.24 99.71
05.02.04 CONFORMACIÓN DE MATERIAL BASE GRANULAR e=0.30 m m2 13174.87 -276.98 12,897.89 276.98
05.03 LOSA DE CONCRETO ARMADO e=0.20 m
08.02.01 SEÑALES VERTICALES PREVENTIVAS 0.60 x 0.60 m und 2.00 2.00 2.00 0.00
09 VARIOS
11.01 ACERO CORRUGADO f'y= 4200 kg/cm2 GRADO 60 PARA PAVIMENTO RÍGIDO kg 8210.63 172.00 8,382.63 -172.00
11.02 ACERO CORRUGADO f'y= 4200 kg/cm2 GRADO 60 PARA PAVIMENTO RÍGIDO kg 1629.36 0.00 1,629.36 0.00
11.03 ACERO LISO f'y= 4200 kg/cm2 GRADO 60 PARA PAVIMENTO RÍGIDO kg 13957.89 0.00 13,159.34 798.55
MONTO A PAGAR POR VALORIZACION DE OBRA N° 11
CORRESPONDIENTE AL MES DE AGOSTO DE 2023
RETENCION 0% S/.0.00
01 TRABAJOS PROVISIONALES 60,571.46 60,493.32 99.87% 78.14 0.13% 60,571.46 100.00% 0.00 0.00%
SEGURIDAD Y SALUD EN
02 122,094.31 122,052.98 99.97% 41.33 0.03% 122,094.31 100.00% 0.00 0.00%
OBRA
03 TRABAJOS PRELIMINARES 47,950.07 47,950.07 100.00% -5,197.83 -10.84% 42,752.24 89.16% 5,197.83 10.84%
04 DEMOLICIONES 25,960.82 25,960.82 100.00% 0.00 0.00% 25,960.82 100.00% 0.00 0.00%
05 PAVIMENTO RÍGIDO 2,318,505.06 2,275,687.32 98.15% 7,912.25 0.34% 2,283,599.57 98.49% 34,905.49 1.51%
06 VEREDAS 652,377.56 562,427.29 86.21% -2,698.80 -0.41% 559,728.49 85.80% 92,649.07 14.20%
07 CUNETAS LATERALES CON TAPA 868,091.76 596,059.27 68.66% -3,319.07 -0.38% 592,740.20 68.28% 275,351.56 31.72%
08 SEÑALIZACION 48,547.62 0.00 0.00% 48,547.62 100.00% 48,547.62 100.00% 0.00 0.00%
09 VARIOS 140,965.30 103,265.74 73.26% 3,271.86 2.32% 106,537.60 75.58% 34,427.70 24.42%
10 MITIGACIÓN DE IMPACTO AMBIENTAL 14,000.00 13,650.00 97.50% 350.00 2.50% 14,000.00 100.00% 0.00 0.00%
11 ACERO 140,407.49 135,696.05 96.64% 1,014.80 0.72% 136,710.85 97.37% 3,696.64 2.63%
COSTO DIRECTO 4,439,471.45 3,943,242.86 88.83% 50,000.30 1.13% 3,993,243.19 89.95% 446,228.28 10.05%
GASTOS GENERALES 310,763.00 276,027.00 3,500.02 279,527.02 31,235.98
UTILIDAD 266,368.29 236,594.57 3,000.02 239,594.59 26,773.70
SUB TOTAL 5,016,602.74 4,455,864.43 88.83% 56,500.34 1.13% 4,512,364.80 89.95% 504,237.96 10.05%
IGV (18%) 902,988.49 802,055.60 10,170.06 812,225.66 90,762.83
TOTAL OBRA 5,919,591.23 5,257,920.03 88.83% 66,670.40 1.13% 5,324,590.46 89.95% 595,000.79 10.05%
VAL ANTERIOR VAL ACTUAL VAL ACUMULADO SALDO PENDIENTE
Página 24 de 703900166.xlsx
CONSORCIO SAYLLA
CALENDARIO DE AVANCE DE OBRA VALORIZADO
ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE SAYLLA
NOMBRE DE PROYECTO MEJORAMIENTO DE LAS CALLES, RAMON CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALEN, ANGOSTURA, MICAELA BASTIDAS, TUPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELAZCO ALVARADO DEN LA ASOCIACIÓN DE VIVIENDA ANGOSTURA
Item Descripción Unidad. Metrado Precio S/. Parcial S/. 6 36 67 97 128 159 173 204 234 264 270
01 TRABAJOS PROVISIONALES
01.01 CARTEL DE OBRA INC/ SUMINISTRO E INSTALACIÓN und 1.00 1,183.66 1,183.66 1,183.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02 CASETA DE GUARDIANÍA Y ALMACÉN m2 300.00 18.58 5,574.00 3,096.67 2,477.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS est 1.00 7813.80 7,813.80 7,813.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.04 FLETE TERRESTRE glb 1.00 46846.53 46,846.53 6,246.20 40,600.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02 SEGURIDAD Y SALUD EN OBRA
02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE glb 1.00 8550.00 8,550.00 8,550.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02 EQUIPOS DE PROTECCION INDIVIDUAL und 40.00 293.42 11,736.80 11,736.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03 EQUIPOS DE PROTECCION COLECTIVA mes 7.00 69.05 483.35 48.34 362.51 72.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.04 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD glb 1.00 7191.44 7,191.44 0.00 0.00 7,191.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.05 CAPACITACION DE SEGURIDAD Y SALUD glb 1.00 2340.00 2,340.00 0.00 0.00 2,340.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y glb 1.00 1792.72 1,792.72 0.00 0.00 1,792.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.07 PROTOCOLO PARA LA VIGILANCIA, PREVENCION Y CONTROL DE LA S glb 1.00 90284.32 90,284.32 0.00 0.00 90,284.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03 TRABAJOS PRELIMINARES
03.01 TRAZO Y REPLANTEO DURANTE LA EJECUCIÓN DE LA OBRA m2 24464.32 1.50 36,696.48 0.00 4,493.45 23,216.14 8,986.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02 LIMPIEZA DE TERRENO MANUAL m2 24464.32 0.46 11,253.59 0.00 823.43 4,254.41 4,117.17 2,058.58 0.00 0.00 0.00 0.00 0.00 0.00
04 DEMOLICIONES
04.01 DEMOLICION DE VEREDAS EXISTENTES m2 1155.19 16.21 18,725.63 0.00 4,681.41 14,044.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02 ELIMINACION DE MATERIAL EXCEDENTE D=25.5 km m3 150.17 48.18 7,235.19 0.00 0.00 7,235.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05 PAVIMENTO RÍGIDO
CONSORCIO SAYLLA
CALENDARIO DE AVANCE DE OBRA VALORIZADO
ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE SAYLLA
NOMBRE DE PROYECTO MEJORAMIENTO DE LAS CALLES, RAMON CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALEN, ANGOSTURA, MICAELA BASTIDAS, TUPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELAZCO ALVARADO DEN LA ASOCIACIÓN DE VIVIENDA ANGOSTURA
NOMBRE DE PROYECTO MEJORAMIENTO DE LAS CALLES, RAMON CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALEN, ANGOSTURA, MICAELA BASTIDAS, TUPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELAZCO ALVARADO DEN LA ASOCIACIÓN DE VIVIENDA ANGOSTURA
NOMBRE DE PROYECTO MEJORAMIENTO DE LAS CALLES, RAMON CASTILLA, TOMASA TITO CONDEMAYTA, JERUSALEN, ANGOSTURA, MICAELA BASTIDAS, TUPAC CATARI, AGUSTÍN GAMARRA, Y AV. JUAN VELAZCO ALVARADO DEN LA ASOCIACIÓN DE VIVIENDA ANGOSTURA
COSTO DIRECTO 4,486,728.93 38,675.47 53,438.46 309,297.03 489,198.84 787,491.07 598,336.83 0.00 0.00 322,272.60 841,289.35 667,948.29 363,592.69 15,188.32
% Valorizado Mensual 0.86% 1.19% 6.89% 10.90% 17.55% 13.34% 0.00% 0.00% 7.18% 18.75% 14.89% 8.10% 0.34%
% Valorizado Acumulado 0.86% 2.05% 8.95% 19.85% 37.40% 50.74% 50.74% 50.74% 57.92% 76.67% 91.56% 99.66% 100.00%