Está en la página 1de 14

PT.

TO
SIT
KABUPATEN BO
WORK SCHEDULE - DIVISI

NO NAME KM JM SB MN SN SL RB KM JM
1 2 3 4 5 6 7 8 9
1 ANDI SUKMONO 18 19 20 21 22 23 24 25 26
2 ZULKIFLI 11 12 13 14 15 16 17 18 19
3 TAKDIR 1 2 3 4 5 6 7 8 9
4 M. AGUNG IZZUKHAK CP CP CP CP CP 1 2 3 4
5 FERI IRAWAN 38 39 40 41 42 CP CP CP CP
6 M. AHBAR 31 32 33 34 35 36 37 38 39
7 AWONG GRAGE 6 7 8 9 10 11 12 13 14
8 I MADE ARTANA 17 18 19 20 21 22 23 24 25
9 FARHAN CP CP CP 1 2 3 4 5 6
10 ZUL FAILIN 33 34 35 36 37 38 39 40 41
11 EKO PRASETYO 40 41 42 CP CP CP CP CP CP
12 TEGAR SAPUTRA 26 27 28 29 30 31 32 33 34
14 MUHAMMAD ADREZAL 4 5 6 7 8 9 10 11 12
15 YAYAT SETIAWAN CP CP CP 1 2 3 4 5 6
16 ABD. SALAM 40 41 42 CP CP CP CP CP CP
17 ANDI HIDAYAT 33 34 35 36 37 38 39 40 41
18 SUWARMAN 26 27 28 29 30 31 32 33 34
19 BIMA DIAN SUPRIADI 19 20 21 22 23 24 25 26 27

Keterangan:
OFF/Change Shift
Cuti Periodik (CP)
Cuti Tahunan (CT)
Trip (T)

PT.
S
KABUPATEN
WORK SCHEDULE - DIVI

NO NAME SB MN SN SL RB KM JM SB MN
1 2 3 4 5 6 7 8 9
1 ANDI SUKMONO C C 1 2 3 4 5 6 7
2 ZULKIFLI 41 42 CP CP CP CP CP CP CP
3 TAKDIR 31 32 33 34 35 36 37 38 39
4 M. AGUNG IZZUKHAK 26 27 28 29 30 31 32 33 34
5 FERI IRAWAN 20 21 22 23 24 25 26 27 28
6 M. ASBAR 12 13 14 15 16 17 18 19 20
7 AWONG GRAGE 36 37 38 39 40 41 42 CP CP
8 I MADE ARTANA CP CP CP 1 2 3 4 5 6
9 FARHAN 28 29 30 31 32 33 34 35 36
10 ZUL FAILIN 14 15 16 17 18 19 20 21 22
11 EKO PRASETYO 21 22 23 24 25 26 27 28 29
14 MUHAMMAD ADREZAL 34 35 36 37 38 39 40 41 42
15 YAYAT SETIAWAN 28 29 30 31 32 33 34 35 36
16 ABD. SALAM 21 22 23 24 25 26 27 28 29
17 ANDI HIDAYAT 14 15 16 17 18 19 20 21 22
18 SUWARMAN 7 8 9 10 11 12 13 14 15
19 BIMA DIAN SUPRIADI CP 1 2 3 4 5 6 7 8

Keterangan:
OFF/Change Shift
Cuti Periodik (CP)
Cuti Tahunan (CT)
PT.
S
KABUPATEN
WORK SCHEDULE - DIVI

NO NAME SL RB KM JM SB MN SN SL SL
1 2 3 4 5 6 7 8 9
1 ANDI SUKMONO 30 31 32 33 34 35 36 37 38
2 ZULKIFLI 23 24 25 26 27 28 29 30 31
3 TAKDIR 13 14 15 16 17 18 19 20 21
4 M. AGUNG IZZUKHAK 6 7 8 9 10 11 12 13 14
5 FERI IRAWAN CP CP CP CP CP CP CP 1 2
6 M. ASBAR 43 44 45 46 47 48 49 CP CP
7 AWONG GRAGE 18 19 20 21 22 23 24 25 26
8 I MADE ARTANA 29 30 31 32 33 34 35 36 37
9 FARHAN 11 12 13 14 15 16 17 18 19
10 ZUL FAILIN CP CP CP CP CP 1 2 3 4
11 EKO PRASETYO 3 4 5 6 7 8 9 10 11
11 DIMAS SAPUTRA 22 23 24 25 26 CP CP CP CP
14 MUHAMMAD ADREZAL 16 17 18 19 20 21 22 23 24
15 YAYAT SETIAWAN 10 11 12 13 14 15 16 17 18
16 ABD. SALAM 3 4 5 6 7 8 9 10 11
17 ANDI HIDAYAT CP CP CP CP CP 1 2 3 4
18 SUWARMAN 38 39 40 41 42 CP CP CP CP
19 BIMA DIAN SUPRIADI 31 32 33 34 35 36 37 38 39

Keterangan:
OFF/Change Shift
Cuti Periodik (CP)
Cuti Tahunan (CT)

PT. TO
SIT
KABUPATEN BO
WORK SCHEDULE - DIVISI

NO NAME JM SB MN SN SL RB KM JM SB
1 2 3 4 5 6 7 8 9
1 ANDI SUKMONO 15 16 17 18 19 20 21 22 23
2 ZULKIFLI 5 6 7 8 9 10 11 12 13
3 TAKDIR CP CP CP CP CP CP 1 2 3
4 M. AGUNG IZZUKHAK 37 38 39 40 41 42 43 44 45
5 FERI IRAWAN 25 26 27 28 29 30 31 32 33
6 M. ASBAR 18 19 20 21 22 23 24 25 26
7 AWONG GRAGE 2 3 4 5 6 7 8 9 10
8 I MADE ARTANA 11 12 13 14 15 16 17 18 19
9 FARHAN 41 42 CP CP CP CP CP CP CP
10 ZUL FAILIN 27 28 29 30 31 32 33 34 35
11 EKO PRASETYO 34 35 36 37 38 39 40 41 42
11 DIMAS SAPUTRA 20 21 22 23 24 25 26 27 28
14 MUHAMMAD ADREZAL 3 4 5 6 7 8 9 10 11
15 YAYAT SETIAWAN 41 42 CP CP CP CP CP CP CP
16 ABD. SALAM 34 35 36 37 38 39 40 41 42
17 ANDI HIDAYAT 27 28 29 30 31 32 33 34 35
18 SUWARMAN 20 21 22 23 24 25 26 27 28
19 BIMA DIAN SUPRIADI 13 14 15 16 17 18 19 20 21

Keterangan:
OFF/Change Shift
Cuti Periodik (CP)
Cuti Tahunan (CT)
PT. TONIA MITRA SEJAHTERA
SITE LENGORA PANTAI
KABUPATEN BOMBANA - SULAWESI TENGGARA
CHEDULE - DIVISI EKSPLORASI - DEPARTEMEN ENGINEERING
JUNE 2023
SB MN SN SL RB KM JM SB MN SN SL RB KM JM
10 11 12 13 14 15 16 17 18 19 20 21 22 23
27 28 29 30 31 32 33 34 35 36 37 38 39 40
20 21 22 23 24 25 26 27 28 29 30 31 32 33
10 11 12 13 14 15 16 17 18 19 20 21 22 23
5 6 7 8 9 10 11 12 13 14 15 16 17 18
CP CP CP 1 2 3 4 5 6 7 8 9 10 11
40 41 42 CP CP CP CP CP CP CP 1 2 3 4
15 16 17 18 19 20 21 22 23 24 25 26 27 28
26 27 28 29 30 31 32 33 34 35 36 37 38 39
7 8 9 10 11 12 13 14 15 16 17 18 19 20
42 CP CP CP CP CP CP CP 1 2 3 4 5 6
CP 1 2 3 4 5 6 7 8 9 10 11 12 13
35 36 37 38 39 40 41 42 CP CP CP CP CP CP
13 14 15 16 17 18 19 20 21 22 23 24 25 26
7 8 9 10 11 12 13 14 15 16 17 18 19 20
CP 1 2 3 4 5 6 7 8 9 10 11 12 13
42 CP CP CP CP CP CP CP 1 2 3 4 5 6
35 36 37 38 39 40 41 42 CP CP CP CP CP CP
28 29 30 31 32 33 34 35 36 37 38 39 40 41

Lengora Pa

( Aris
Dept. H

PT. TONIA MITRA SEJAHTERA


SITE LENGORA PANTAI
KABUPATEN BOMBANA - SULAWESI TENGGARA
K SCHEDULE - DIVISI EKSPLORASI - DEPARTEMEN ENGINEERING
JULY 2023
SN SL RB KM JM SB MN SN SL RB KM JM SB MN
10 11 12 13 14 15 16 17 18 19 20 21 22 23
8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 2 3 4 5 6 7 8 9 10 11 12 13 14
40 41 42 CP CP CP CP CP CP CP 1 2 3 4
35 36 37 38 39 40 41 42 43 44 CP CP CP CP
29 30 31 32 33 34 35 36 37 38 39 40 41 42
21 22 23 24 25 26 27 28 29 30 31 32 33 34
CP CP CP CP CP 1 2 3 4 5 6 7 8 9
7 8 9 10 11 12 13 14 15 16 17 18 19 20
37 38 39 40 41 42 CP CP CP CP CP CP CP 2
23 24 25 26 27 28 29 30 31 32 33 34 35 36
30 31 32 33 34 35 36 37 38 39 40 41 42 CP
CP CP CP CP CP CP CP 1 2 3 4 5 6 7
37 38 39 40 41 42 CP CP CP CP CP CP CP 1
30 31 32 33 34 35 36 37 38 39 40 41 42 CP
23 24 25 26 27 28 29 30 31 32 33 34 35 36
16 17 18 19 20 21 22 23 24 25 26 27 28 29
9 10 11 12 13 14 15 16 17 18 19 20 21 22

Lengora P

( Aris
Dept. H
PT. TONIA MITRA SEJAHTERA
SITE LENGORA PANTAI
KABUPATEN BOMBANA - SULAWESI TENGGARA
K SCHEDULE - DIVISI EKSPLORASI - DEPARTEMEN ENGINEERING
AUGUST 2023
RB KM JM SB MN SN SL SL RB KM JM SB MN SN
10 11 12 13 14 15 16 17 18 19 20 21 22 23
39 CP CP CP CP CP CP CP 1 2 3 4 5 6
32 33 34 35 36 37 38 39 40 41 42 CP CP CP
22 23 24 25 26 27 28 29 30 31 32 33 34 35
15 16 17 18 19 20 21 22 23 24 25 26 27 28
3 4 5 6 7 8 9 10 11 12 13 14 15 16
CP CP CP CP CP 1 2 3 4 5 6 7 8 9
27 28 29 30 31 32 33 34 35 36 37 38 39 40
38 39 40 41 42 CP CP CP CP CP CP CP 1 2
20 21 22 23 24 25 26 27 28 29 30 31 32 33
5 6 7 8 9 10 11 12 13 14 15 16 17 18
12 13 14 15 16 17 18 19 20 21 22 23 24 25
CP 1 2 3 4 5 6 7 8 9 10 11 12 13
25 26 27 28 29 30 31 32 33 34 35 36 37 38
19 20 21 22 23 24 25 26 27 28 29 30 31 32
12 13 14 15 16 17 18 19 20 21 22 23 24 25
5 6 7 8 9 10 11 12 13 14 15 16 17 18
CP CP CP 1 2 3 4 5 6 7 8 9 10 11
40 41 42 CP CP CP CP CP CP CP 1 2 3 4

Lengora Pan

( Aris
Dept. H

PT. TONIA MITRA SEJAHTERA


SITE LENGORA PANTAI
KABUPATEN BOMBANA - SULAWESI TENGGARA
CHEDULE - DIVISI EKSPLORASI - DEPARTEMEN ENGINEERING
SEPTEMBER 2023
MN SN SL RB KM JM SB MN SN SL RB KM JM SB
10 11 12 13 14 15 16 17 18 19 20 21 22 23
24 25 26 27 28 29 30 31 32 33 34 35 36 37
14 15 16 17 18 19 20 21 22 23 24 25 26 27
4 5 6 7 8 9 10 11 12 13 14 15 16 17
CP CP CP CP CP CP CP 1 2 3 4 5 6 7
34 35 36 37 38 39 40 CP CP CP CP CP CP CP
27 28 29 30 31 32 33 34 35 36 37 38 39 40
11 12 13 14 15 16 17 18 19 20 21 22 23 24
20 21 22 23 24 25 26 27 28 29 30 31 32 33
1 2 3 4 5 6 7 8 9 10 11 12 13 14
36 37 38 39 40 41 42 CP CP CP CP CP CP CP
CP CP CP CP CP CP CP 1 2 3 4 5 6 7
29 30 31 32 33 34 35 36 37 38 39 40 41 42
12 13 14 15 16 17 18 19 20 21 22 23 24 25
2 3 4 5 6 7 8 9 10 11 12 13 14 15
CP CP CP CP CP CP CP 2 3 4 5 6 7 8
36 37 38 39 40 41 42 CP CP CP CP CP CP CP
29 30 31 32 33 34 35 36 37 38 39 40 41 42
22 23 24 25 26 27 28 29 30 31 32 33 34 35

Lengora Panta

( Aris
Dept. H
SB MN SN SL RB KM JM
24 25 26 27 28 29 30
41 42 C C C C C
34 35 36 37 38 39 40
24 25 26 27 28 29 30
19 20 21 22 23 24 25
12 13 14 15 16 17 18
5 6 7 8 9 10 11
29 30 31 32 33 34 35
40 41 42 CP CP CP CP
21 22 23 24 25 26 27
7 8 9 10 11 12 13
14 15 16 17 18 19 20
CP 1 2 3 4 5 6
27 28 29 30 31 32 33
21 22 23 24 25 26 27
14 15 16 17 18 19 20
7 8 9 10 11 12 13
CP 1 2 3 4 5 6
42 CP CP CP CP CP CP

Lengora Pantai, 01 Juni 2023

( Aris Munandar )
Dept. Head Engineering
SN SL RB KM JM SB MN SN
24 25 26 27 28 29 30 31
22 23 24 25 26 27 28 29
15 16 17 18 19 20 21 22
5 6 7 8 9 10 11 12
CP CP CP 1 2 3 4 5
43 44 45 CP CP CP CP CP
35 36 37 38 39 40 41 42
10 11 12 13 14 15 16 17
21 22 23 24 25 26 27 28
3 4 5 6 7 8 9 10
37 38 39 40 41 42 CP CP
CP CP CP CP CP CP 1 2
8 9 10 11 12 13 14 15
2 3 4 5 6 7 8 9
CP CP CP CP CP CP 1 2
37 38 39 40 41 42 CP CP
30 31 32 33 34 35 36 37
23 24 25 26 27 28 29 30

Lengora Pantai, 01 Juli 2023

( Aris Munandar )
Dept. Head Engineering
SL SL RB KM JM SB MN SN
24 25 26 27 28 29 30 31
7 8 9 10 11 12 13 14
CP CP CP CP 1 2 3 4
36 37 38 39 40 41 42 CP
29 30 31 32 33 34 35 36
17 18 19 20 21 22 23 24
10 11 12 13 14 15 16 17
CP CP CP CP CP CP CP 1
3 4 5 6 7 8 9 10
34 35 36 37 38 39 40 41
19 20 21 22 23 24 25 26
26 27 28 29 30 31 32 33
14 15 16 17 18 19 20 21
39 40 41 CP CP CP CP CP
33 34 35 36 37 38 39 40
26 27 28 29 30 31 32 33
19 20 21 22 23 24 25 26
12 13 14 15 16 17 18 19
5 6 7 8 9 10 11 12

Lengora Pantai, 01 August 2023

( Aris Munandar )
Dept. Head Engineering
MN SN SL RB KM JM SB
24 25 26 27 28 29 30
38 39 40 41 42 CP CP
28 29 30 31 32 33 34
18 19 20 21 22 23 24
8 9 10 11 12 13 14
1 2 3 4 5 6 7
CP CP CP CP CP CP CP
25 26 27 28 29 30 31
34 35 36 37 38 39 40
15 16 17 18 19 20 21
1 2 3 4 5 6 7
8 9 10 11 12 13 14
CP CP CP CP CP CP CP
26 27 28 29 30 31 32
16 17 18 19 20 21 22
9 10 11 12 13 14 15
2 3 4 5 6 7 8
CP CP CP CP CP CP CP
36 37 38 39 40 41 42

Lengora Pantai, 01 September 2023

( Aris Munandar )
Dept. Head Engineering