Está en la página 1de 15

PRESUPUESTO CIVIL

PROCESO DE
COMPRA

DESCRIPCION: CISTERNA DE 1.5X1.5X2.80 RECEPTORA DE TUBERIA DE 8" DE AGUA DULCE

PLANTA: COISHCO

RAZON SOCIAL: GRUPO WEWAR SAC

RUC: 20536093410
FECHA: Tuesday, October 3, 2023

PRECIO TOTAL/
ÍTEM DESCRIPCIÓN DE LA PARTIDA UNIDAD METRADO
UNITARIO SUBTOTAL
1.00 OBRAS PROVISIONALES 5,136.00
1.01 SEGURIDAD INDUSTRIAL, EMO´S, PÓLIZAS Y SEÑALIZACION GLB 1.00 1,276.00 1,276.00
1.02 GASTOS COVID 19, EPP SANITARIOS Y OTROS. GLB 1.00 600.00 600.00
1.03 ALIMENTACION DE PERSONAL DIA 8.00 100.00 800.00
1.04 MOVILIZACION DE MATERIALES Y HERRAMIENTAS GLB 1.00 300.00 300.00
1.05 PREVENCIONISTA DIA 8.00 120.00 960.00
1.06 SUPERVISOR DE OBRA DIA 8.00 150.00 1,200.00
2.00 TRABAJOS PRELIMINARES 4,495.40
2.01 HABILITACION DE PERSONAL, EQUIPOS Y HERRAMIENTAS GLB 1.00 100.00 100.00
2.02 TRAZO Y NIVELACION GLB 1.00 100.00 100.00
2.03 DEMOLICIONES 1,050.00
2.03.01 DEMOLICION DE PISO E= 20 CM GLB 1.00 800.00 800.00
2.03.02 ACARREO DE DESMONTE GLB 1.00 100.00 100.00
2.03.03 ELIMINACION DE DESMONTE GLB 1.00 150.00 150.00
2.0400 EXCAVACION MANUAL M3 9.72 45.00 437.40
2.0500 ACARREO DE DESMONTE M3 12.15 35.00 425.25
2.0600 ELIMINACION DE DESMONTE M3 12.15 45.00 546.75
2.0700 ENTIBADO h=3.0 M M2 21.60 85.00 1,836.00

3.00 CONCRETO ARMADO 10,405.03


3.01 ACERO 3/8" FY 4200KG/CM2 KG 279.00 8.50 2,371.50
3.01 ENCOFRADO Y DESENCOFRADO M2 35.28 84.00 2,963.52
CONCRETO ARMADO E=0.15 CM, FC=280 KG/CM2 + ACELERANTE E
3.02 M3 3.51 690.00
IMPERMEABILIZANTE SIKA1 2,425.00
3.03 TARRAJEO IMPERMEABILIZADO 1:1.5 CON SIKA1 M2 22.79 65.00
1,481.41
3.03 CURADO DE CONCRETO CON ADITIVO M2 22.79 7.88 179.59
3.04 JUNTA DE FRIA SELLADO ML 12.00 82.00 984.00
4.00 VARIOS 3,040.00
4.01 LIMPIEZA FINAL Y HABILITACION DE ÁREA GLB 1.00 150.00 150.00
4.02 DISEÑO DE MEZCLA UND 1.00 350.00 350.00
4.03 ROTURA DE PROBETA UND 4.00 60.00 240.00
4.04 TAPA METALICA DE 0.6X0.6M X 3/16" ESTRILLADA/ INC INSTALADA GLB 1.00 950.00 950.00
4.05 ESCALERA DE 0.6MX2.0 EN TUBO LISO DE 5/8" FEN/ INC PINTADO GLB 1.00 1,200.00 1,200.00
4.05 INFORME FINAL DE OBRA UND 1.00 150.00 150.00
COSTO DIRECTO DE OBRA S/ 23,076.43
GASTOS GENERALES 10.0% 2,307.64
UTILIDAD 8.0% 1,846.11
COSTO TOTAL S/ 27,230.19
IMPUESTO GENERAL A LAS VENTAS 18.0% 4,901.43
COSTO TOTAL S/ 32,131.63

PROGRAMACION DE P

1ER PAGO
2DO PAGO
3ER PAGO
2.85 35.2941176 100.588235 11.1764706 12.2941176 13 VALIRAS
6 15 90 10 11 12 VARILLAS
33X5 165 25 VARILLAS
40X6 240 25
405
226.395 7.5
32 48 5.33333333 6
9
54

249.0345
16.8

4.5

21.3
3.195
3.5145

22%
PROGRAMACION DE PAGOS DE LOSA Y PODIOS COISHCO

SABADO 02 MARTES 04 VIERNES 8


9500
11500
9600
9500 10500 9600
29600
9 225