CIMBRA DE MADERA DE PINO DE SEGUNDA PARA TRABE. 3 A-B 11.5 0.90 2 20.70
INCLUYE PUNTALES, PATAS D/GALLO, JUNQUILLOS, 3 B-C 5 0.90 2 9.00
M2
CONTRAVENTEOS, MANO DE OBRA. HERRAMIENTA Y 3 C-D 11.5 0.90 2 20.70
TODO LO NECESARIO PARA SU CORRECTA EJECUCION 4 A-B 11.5 0.90 2 20.70
4 B-C 5 0.90 2 9.00
4 C-D 11.5 0.90 2 20.70
5 A-B 11.5 0.90 2 20.70
5 B-C 5 0.90 2 9.00
5 C-D 11.5 0.90 2 20.70
6 A-B 11.5 0.90 2 20.70
6 B-C 5 0.90 2 9.00
6 C-D 11.5 0.90 2 20.70
TOTAL 741.60
Página 2 de 7
CONCRETO F´C_250 KG/CM2 PREMEZCLADO PARA
COLUMNAS. REVENIMIENTO MAXIMO DE 8 A 12 CM Y
TAMAÑO MAXIMO DEL AGREGADO DE 3/4¨. INCLUYE:
ELABORACION, ACARREO, COLADO, NIVELADO, VIBRADO, M3
CURADO, LIMPIEZA DE MATERIAL SOBRANTE,
DESPERDICIOS, MANO DE OBRA, HERRAMIENTA, EQUIPO
Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION
ANALISIS DE NUMEROS GENERADORES
AREA :
OBRA : Biblioteca ELABORO : EQUIPO 1
PARTIDA : CIMENTACION Y ESTRUCTURA
CLAVE CONCEPTO UNIDAD EJE TRAMO LARGO ANCHO ALTO PIEZAS SUBTOTAL OBSERVACIONES
D 6 0.50 0.60 7.35 2.20
TOTAL 52.92
A 1-6 36.6 1.00 0.5 18.30
B 1-6 36.6 1.00 0.5 18.30
C 1-6 36.6 1.00 0.5 18.30
D 1-6 36.6 1.00 0.5 18.30
1 A-B 11.5 0.60 0.3 2.07
1 B-C 5 0.60 0.3 0.90
1 C-D 11.5 0.60 0.3 2.07
2 A-B 11.5 0.60 0.3 2.07
2 B-C 5 0.60 0.3 0.90
CONCRETO F´C_250 KG/CM2 PREMEZCLADO PARA 2 C-D 11.5 0.60 0.3 2.07
TRABES REVENIMIENTO MAXIMO DE 8 A 12 CM Y TAMAÑO 3 A-B 11.5 0.60 0.3 2.07
MAXIMO DEL AGREGADO DE 3/4¨. INCLUYE: 3 B-C 5 0.60 0.3 0.90
M3
ELABORACION, ACARREO, COLADO, NIVELADO, VIBRADO, 3 C-D 11.5 0.60 0.3 2.07
CURADO, LIMPIEZA DE MATERIAL SOBRANTE, 4 A-B 11.5 0.60 0.3 2.07
DESPERDICIOS, MANO DE OBRA, HERRAMIENTA, EQUIPO 4 B-C 5 0.60 0.3 0.90
Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION 4 C-D 11.5 0.60 0.3 2.07
5 A-B 11.5 0.60 0.3 2.07
5 B-C 5 0.60 0.30 0.90
5 C-D 11.5 0.60 0.30 2.07
6 A-B 11.5 0.60 0.30 2.07
6 B-C 5 0.60 0.30 0.90
6 C-D 11.5 0.60 0.30 2.07
TOTAL 103.44
Página 3 de 7
HABILITADO Y ARMADO DE ACERO DE REFUERZO #12 EN
COLUMNAS FY=4200 KG/CM2. INCLUYE SUMINISTRO,
BULBOS, SILLETAS, GANCHOS, DESPERDICIOS Y TODO LO
NECESARIO PARA SU CORRECTA EJECUCION.
CLAVE CONCEPTO UNIDAD EJE TRAMO LARGO ANCHO ALTO PIEZAS SUBTOTAL OBSERVACIONES
Página 4 de 7
PLANTILLA DE CONCRETO HECHO EN OBRA RESISTENCIA M2ANALISIS DE NUMEROS GENERADORES
F'c=100 KG/CM2 DE 5 CM DE ESPESOR, AGREGADO
MAXIMO 3/4". INCLUYE: VACIADO, NIVELADO, APISONADO AREA :
OBRA : Biblioteca
DE SUPERFICIE, MATERIALES, FABRICACIÓN DE ELABORO : EQUIPO 1
PARTIDA : CIMENTACION Y ESTRUCTURA
CONCRETO, VIBRADO, LIMPIEZA DE MATERIAL SOBRANTE
UBICACIÓN : Y ACARREO A 20 MTS DE DISTANCIA. NIVEL : PROYECTO EJECUTIVO FECHA : 10/5/2023
CLAVE CONCEPTO UNIDAD EJE TRAMO LARGO ANCHO ALTO PIEZAS SUBTOTAL OBSERVACIONES
D 1-6 5.30 0.30 0.05 5.00 0.40
1 A-D 17.20 0.30 0.05 1.00 0.26
2 A-D 17.20 0.30 0.05 1.00 0.26
3 A-D 17.20 0.30 0.05 1.00 0.26
4 A-D 17.20 0.30 0.05 1.00 0.26
5 A-D 17.20 0.30 0.05 1.00 0.26
6 A-D 17.20 0.30 0.05 1.00 0.26
1 A-B 15.00 1.00 0.05 1.00 0.75
6 A-B 15.00 1.00 0.05 1.00 0.75
1 C-D 15.25 1.00 0.05 1.00 0.76
D 3-4 15.50 1.00 0.05 1.00 0.78
D' 5-6 11.00 1.00 0.05 1.00 0.55
5-6' 25.10 1.00 0.05 1.00 1.26
TOTAL 12.78
CONCEPTO UNIDAD EJE TRAMO LARGO ANCHO ALTO PIEZAS SUBTOTAL OBSERVACIONES
CIMBRA COMUN EN CIMENTACION (ZAPATAS Y TRABES M2 A 1-6 2.00 0.15 24.00 7.20 DISEÑO Z-1
DE LIGA) CON MADERA DE PINO DE 1era, ACABADO B 1-6 2.00 0.15 24.00 7.20 DISEÑO Z-1
CEPILLADO, INCLUYE: HABILITADO, CIMBRADO, C 1-6 2.00 0.15 24.00 7.20 DISEÑO Z-1
DESCIMBRADO, SUMINISTRO DE MATERIAL, TRAZO, D 1-6 2.00 0.15 24.00 7.20 DISEÑO Z-1
TROQUELADO, HERRAMIENTA, MANO DE OBRA Y TODO
A 1-6 5.30 1.20 10.00 63.60 CONTRA-TRABE
LO NECESARIO PARA SU REALIZACION.
B 1-6 5.30 1.20 10.00 63.60 CONTRA-TRABE
C 1-6 5.30 1.20 10.00 63.60 CONTRA-TRABE
D 1-6 5.30 1.20 10.00 63.60 CONTRA-TRABE
1 A-D 17.20 1.20 6.00 123.84 CONTRA-TRABE
2 A-D 17.20 1.20 6.00 123.84 CONTRA-TRABE
3 A-D 17.20 1.20 6.00 123.84 CONTRA-TRABE
4 A-D 17.20 1.20 6.00 123.84 CONTRA-TRABE
5 A-D 17.20 1.20 6.00 123.84 CONTRA-TRABE
6 A-D 17.20 1.20 6.00 123.84 CONTRA-TRABE
1 A-B 15.00 0.59 2.00 17.70 DISEÑO Z-2
6 A-B 15.00 0.59 2.00 17.70 DISEÑO Z-2
1 C-D 15.25 0.59 2.00 17.99 DISEÑO Z-2
D 3-4 15.50 0.59 2.00 18.29 DISEÑO Z-2
D' 5-6 11.00 0.59 2.00 12.98 DISEÑO Z-2
5-6' 25.10 0.59 2.00 29.62 DISEÑO Z-2
O LA MITAD PARA COLAR EN 2
TOTAL 1,140.52
PARTES
HABILITADO Y ARMADO DE ACERO DE REFUERZO KG EJE TRAMO LARGO VARILLA PESO PIEZAS SUBTOTAL OBSERVACIONES
CORRUGADO PARA ZAPATAS Y TRABES DE LIGA EN A 1-6 2.20 44.00 0.996 6.00 578.48 DISEÑO Z-1
CIMENTACION RESISTENCIA F`y=4200 KG/CM2, DE B 1-6 2.20 44.00 0.996 6.00 578.48 DISEÑO Z-1
DIFERENTES DIAMETROS, INCLUYE DOBLECES, C 1-6 2.20 44.00 0.996 6.00 578.48 DISEÑO Z-1
ANCLAJES, COLOCACION, AMARRES, TRASLAPES,
D 1-6 2.20 44.00 0.996 6.00 578.48 DISEÑO Z-1
CONEXIONES MECANICAS, GANCHOS, SILLETAS,
DESPERDICIOS, SUMINISTRO DE MATERIAL, ACARREOS A 1-6 37.40 12.00 3.975 1.00 1,783.98 CONTRA-TRABE
DENTRO Y FUERA DE LA OBRA, MANO DE OBRA Y 1-6 0.25 150.00 0.996 1.00 37.35 CONTRA-TRABE (ESTRIBOS)
HERRAMIENTA. 1-6 24.00 4.00 2.250 1.00 216.00 CONTRA-TRABE (REFUERZOS)
B 1-6 37.40 12.00 3.975 1.00 1,783.98 CONTRA-TRABE
1-6 0.25 146.00 0.996 1.00 36.35 CONTRA-TRABE (ESTRIBOS)
1-6 24.00 4.00 2.250 1.00 216.00 CONTRA-TRABE (REFUERZOS)
C 1-6 37.40 12.00 3.975 1.00 1,783.98 CONTRA-TRABE
1-6 0.25 146.00 0.996 1.00 36.35 CONTRA-TRABE (ESTRIBOS)
1-6 24.00 4.00 2.250 1.00 216.00 CONTRA-TRABE (REFUERZOS)
D 1-6 37.40 12.00 3.975 1.00 1,783.98 CONTRA-TRABE
1-6 0.25 146.00 0.996 1.00 36.35 CONTRA-TRABE (ESTRIBOS)
1-6 24.00 4.00 2.250 1.00 216.00 CONTRA-TRABE (REFUERZOS)
1 A-D 23.80 12.00 3.975 1.00 1,135.26 CONTRA-TRABE
Página 5 de 7
DIFERENTES DIAMETROS, INCLUYE DOBLECES,
ANCLAJES, COLOCACION, AMARRES, TRASLAPES,
CONEXIONES MECANICAS, GANCHOS, SILLETAS,
DESPERDICIOS, SUMINISTRO DE MATERIAL, ACARREOS
DENTRO Y FUERA DE LA OBRA, MANO DE OBRA Y
HERRAMIENTA.
CLAVE CONCEPTO UNIDAD EJE TRAMO LARGO ANCHO ALTO PIEZAS SUBTOTAL OBSERVACIONES
A-D 0.25 93 0.996 1.00 23.11 CONTRA-TRABE (ESTRIBOS)
A-D 15.60 4.00 2.250 1.00 140.40 CONTRA-TRABE (REFUERZOS)
2 A-D 23.80 12.00 3.975 1.00 1,135.26 CONTRA-TRABE
A-D 0.25 93 0.996 1.00 23.11 CONTRA-TRABE (ESTRIBOS)
A-D 15.60 4.00 2.250 1.00 140.40 CONTRA-TRABE (REFUERZOS)
3 A-D 23.80 12.00 3.975 1.00 1,135.26 CONTRA-TRABE
A-D 0.25 93 0.996 1.00 23.11 CONTRA-TRABE (ESTRIBOS)
A-D 15.60 4.00 2.250 1.00 140.40 CONTRA-TRABE (REFUERZOS)
4 A-D 23.80 12.00 3.975 1.00 1,135.26 CONTRA-TRABE
A-D 0.25 93 0.996 1.00 23.11 CONTRA-TRABE (ESTRIBOS)
A-D 15.60 4.00 2.250 1.00 140.40 CONTRA-TRABE (REFUERZOS)
5 A-D 23.80 12.00 3.975 1.00 1,135.26 CONTRA-TRABE
A-D 0.25 93 0.996 1.00 23.11 CONTRA-TRABE (ESTRIBOS)
A-D 15.60 4.00 2.250 1.00 140.40 CONTRA-TRABE (REFUERZOS)
6 A-D 23.80 12.00 3.975 1.00 1,135.26 CONTRA-TRABE
A-D 0.25 93 0.996 1.00 23.11 CONTRA-TRABE (ESTRIBOS)
A-D 15.60 4.00 2.250 1.00 140.40 CONTRA-TRABE (REFUERZOS)
1 A-B 15.00 78.00 0.557 1.00 651.69 DISEÑO Z-2
A-B 15.00 120.00 0.966 1.00 1,738.80 CONTRA-TRABE
A-B 0.20 75.00 0.557 1.00 8.36 CONTRA-TRABE (ESTRIBOS)
6 A-B 15.00 78.00 0.557 1.00 651.69 DISEÑO Z-2
A-B 15.00 120.00 0.966 1.00 1,738.80 CONTRA-TRABE
A-B 0.20 75.00 0.557 1.00 8.36 CONTRA-TRABE (ESTRIBOS)
1 C-D 15.25 79.00 0.557 1.00 671.05 DISEÑO Z-2
C-D 15.25 122.00 0.966 1.00 1,797.24 CONTRA-TRABE
C-D 0.20 0.557 1.00 0.00 CONTRA-TRABE (ESTRIBOS)
D 3-4 15.50 79.00 0.557 1.00 682.05 DISEÑO Z-2
3-4 15.50 124.00 0.966 1.00 1,856.65 CONTRA-TRABE
3-4 0.20 77.50 0.557 1.00 8.63 CONTRA-TRABE (ESTRIBOS)
D' 5-6 11.00 57.00 0.557 1.00 349.24 DISEÑO Z-2
5-6 11.00 88.00 0.966 1.00 935.09 CONTRA-TRABE
5-6 0.20 55.00 0.557 1.00 6.13 CONTRA-TRABE (ESTRIBOS)
D' 5-6' 25.10 128.00 0.557 1.00 1,789.53 DISEÑO Z-2
5-6' 25.10 200.80 0.966 1.00 4,868.72 CONTRA-TRABE
5-6' 0.20 125.50 0.557 1.00 13.98 CONTRA-TRABE (ESTRIBOS)
TOTAL 36,028.83
CONCEPTO UNIDAD EJE TRAMO LARGO ANCHO ALTO PIEZAS SUBTOTAL OBSERVACIONES
CONCRETO F'C=250KG/CM2 PREMEZCLADO, PARA M3 A 1-6 2.00 2.00 0.15 6.00 3.60 DISEÑO Z-1
ZAPATAS Y TRABES DE LIGA EN CIMENTACION, B 1-6 2.00 2.00 0.15 6.00 3.60 DISEÑO Z-1
REVENIMIENTO MAXIMO DE 8 A 12 CM Y TAMAÑO MAXIMO C 1-6 2.00 2.00 0.15 6.00 3.60 DISEÑO Z-1
DEL AGREGADO DE 3/4". INCLUYE: ELABORACION, D 1-6 2.00 2.00 0.15 6.00 3.60 DISEÑO Z-1
ACARREO, COLADO, NIVELADO, APISONADO, VIBRADO,
A 1-6 5.30 0.30 1.20 5.00 9.54 CONTRA-TRABE
CURADO, LIMPIEZA DE MATERIAL SOBRANTE,
DESPERDICIOS, MANO DE OBRA, EQUIPO, HERRAMIENTA B 1-6 5.30 0.30 1.20 5.00 9.54 CONTRA-TRABE
Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN. C 1-6 5.30 0.30 1.20 5.00 9.54 CONTRA-TRABE
D 1-6 5.30 0.30 1.20 5.00 9.54 CONTRA-TRABE
1 A-D 17.20 0.30 1.20 1.00 6.19 CONTRA-TRABE
2 A-D 17.20 0.30 1.20 1.00 6.19 CONTRA-TRABE
3 A-D 17.20 0.30 1.20 1.00 6.19 CONTRA-TRABE
4 A-D 17.20 0.30 1.20 1.00 6.19 CONTRA-TRABE
5 A-D 17.20 0.30 1.20 1.00 6.19 CONTRA-TRABE
6 A-D 17.20 0.30 1.20 1.00 6.19 CONTRA-TRABE
1 A-B 15.00 1.30 0.59 1.00 11.51 DISEÑO Z-2
6 A-B 15.00 1.30 0.59 1.00 11.51 DISEÑO Z-2
1 C-D 15.25 1.30 0.59 1.00 11.70 DISEÑO Z-2
D 3-4 15.50 1.30 0.59 1.00 11.89 DISEÑO Z-2
Página 6 de 7
DEL AGREGADO DE 3/4". INCLUYE: ELABORACION,
ACARREO, COLADO, NIVELADO, APISONADO, VIBRADO,
CURADO, LIMPIEZA DE MATERIAL SOBRANTE,
DESPERDICIOS, MANO DE OBRA, EQUIPO, HERRAMIENTA
Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN.
CLAVE CONCEPTO UNIDAD EJE TRAMO LARGO ANCHO ALTO PIEZAS SUBTOTAL OBSERVACIONES
D' 5-6 11.00 1.30 0.59 1.00 8.44 DISEÑO Z-2
5-6' 25.10 1.30 0.59 1.00 19.25 DISEÑO Z-2
TOTAL 164.00
Página 7 de 7