Documentos de Académico
Documentos de Profesional
Documentos de Cultura
VOLUMENES
PROGRESIVA
TRAMO PROGRESIVAS MEDIA
Sector A 0+000 2+720 1+360
Sector B 2+720 4+660 3+690
Sector C 4+660 7+020 5+840
Sector D 7+020 9+580 8+300
Sector E 9+580 13+000 11+290
200 Dias
8 hrs diarias
PARA COMPENSACIÓN m
SECTOR A -B 2365
SECTOR B-C 960.26
SECTOR E-D 4550
PARA BOTADERO m
SECTOR B 3130
SECTOR C 990
SECTOR D 2260
IMPRIMADOR(m)
8720
6450
9060
5780
6400
4300
4620
7220
6620
7620
10200
9620
10620
MAQUINAS A UTILIZAR
UTILIZACION PARA: MAQUINAS MARCA Y MODELO
Caterpillar D7R LGP serie II
TRACTOR (hoja S)
Equipo de excavacion CARGADOR FRONTAL Caterpillar 950G
VOLQUETAS Mercedes benz atego 1823
MOTONIVELADORA Caterpillar 16 H
COMPACTADOR Caterpillar CS - 573E
Capa sub-base CAMION AGUATERO Mercedes Benz 2228
CARGADOR FRONTAL Caterpillar 950G
VOLQUETAS VOLVO FM12
MOTONIVELADORA Caterpillar 16 H
COMPACTADOR Caterpillar CS - 573E
Capa base CAMION AGUATERO Mercedes Benz 2228
CARGADOR FRONTAL Caterpillar 950G
VOLQUETAS VOLVO FM12
PLANTA DE ASFALTOS CIFALI DMC-2
COMPACTADOR Caterpillar CB - 634D
CAMION IMPRIMADOR Mercedes Benz L1620/51
Capa asfaltica
CARGADOR FRONTAL Caterpillar 950G
PAVIMENTADORA VOGELE SUPER 1803-2
VOLQUETA VOLVO FM12
MARCA Y MODELO
terpillar D7R LGP serie II
oja S)
terpillar 950G
ercedes benz atego 1823
terpillar 16 H
terpillar CS - 573E
ercedes Benz 2228
terpillar 950G
OLVO FM12
terpillar 16 H
terpillar CS - 573E
ercedes Benz 2228
terpillar 950G
OLVO FM12
FALI DMC-2
terpillar CB - 634D
ercedes Benz L1620/51
terpillar 950G
OGELE SUPER 1803-2
OLVO FM12
CALCULO DE PRODUCTIVIDAD DEL TRACTOR
DATOS DE LA MAQUINA
CONDICIONES DE TRABAJO
COMPUTOS
DATOS DE LA MAQUINA
CONDICIONES DE TRABAJO
COMPUTOS
DATOS DE LA MAQUINA
CONDICIONES DE TRABAJO
COMPUTOS
DATOS DE LA MAQUINA
CONDICIONES DE TRABAJO
COMPUTOS
Producción por ciclo q = 0,48 a² * L 3.38
Duración del ciclo T = 2d/A + D/A + (d+D 0.81
PRODUCTIVIDAD Q = 60*q*E*Fh*m*p/T( 124.14
PRODUCTIVIDAD EN BANCO Qb = Q * Fv 105.52
PRODUCTIVIDAD COMPACTADA Qc = Q * F 89.69
DATOS DE LA MAQUINA
CONDICIONES DE TRABAJO
COMPUTOS
MAQUINAC.FRONTAL
: MARCA : caterpillar 950G
MODELO 950G
: POTENCIA : 183
COMPUTOS
PRODUCTIVIDAD Q= 127.93
OS PRODUCTIVIDAD EN Qb = 110.02
PRODUCTIVIDAD CO Qc = 93.51
(M3)
(min)
M3(s)/Hra
M3(b)/Hra
M3(c)/Hra
EQUIPO
VOLUMEN DE PRODUCTIVIDAD Nº DE MAQ.
PLAZO
TRABAJO (Hrs)
TRACTOR 48000.0m3 106.76m3/hr 2 240
C.FRONTAL 48000.0m3 110.02m3/hr 2 240
MAQUINAC.FRONTAL
: MARCA : caterpillar 950G
MODELO 950G
: POTENCIA : 183
COMPUTOS
PRODUCTIVIDAD Q= 127.93
OS PRODUCTIVIDAD EN Qb = 110.02
PRODUCTIVIDAD CO Qc = 93.51
(M3)
(min)
M3(s)/Hra
M3(b)/Hra
M3(c)/Hra
CALC+I88:Q95ULO DE
PRODUCTIVIDAD DE VOLUMEN DE PRODUCTIVIDAD Nº DE MAQ.
PLAZO
VOLQUETAS+AG194: TRABAJO (Hrs)
AL231
TRACTOR 65000.0m3 106.76m3/hr 3 240
C.FRONTAL 65000.0m3 110.02m3/hr 3 240
VOLQUETA(B-B) 4246.15m3 57.83m3/hr 1 240
VOLQUETA (B-C) 32000.0m3 47.57m3/hr 3 240
VOLQUETA(B-BOT) 4407.70m3 25.75m3/hr 1 240
MAQUINAC.FRONTAL
: MARCA : caterpillar 950G
MODELO 950G
: POTENCIA : 183
COMPUTOS
PRODUCTIVIDAD Q= 127.93
OS PRODUCTIVIDAD EN Qb = 108.74
PRODUCTIVIDAD CO Qc = 0.00
(M3)
(min)
M3(s)/Hra
M3(b)/Hra
M3(c)/Hra
EQUIPO
VOLUMEN DE PRODUCTIVIDAD Nº DE MAQ.
PLAZO
TRABAJO (Hrs)
TRACTOR 80000.0m3 105.52m3/hr 4 240
C.FRONTAL 80000.0m3 108.74m3/hr 4 240
VOLQUETA 80000.0m3 46.48m3/hr 8 240
MAQUINAC.FRONTAL
: MARCA : caterpillar 950G
COMPUTOS
PRODUCTIVIDAD Q= 127.93
OS PRODUCTIVIDAD EN Qb = 108.74
PRODUCTIVIDAD CO Qc = 92.43
(M3)
(min)
M3(s)/Hra
M3(b)/Hra
M3(c)/Hra
EQUIPO
VOLUMEN DE PRODUCTIVIDAD Nº DE MAQ.
PLAZO
TRABAJO (Hrs)
TRACTOR 31500.0m3 105.52m3/hr 2 240
C.FRONTAL 31500.0m3 108.74m3/hr 2 240
MAQUINAC.FRONTAL
: MARCA : caterpillar 950G
MODELO 950G
: POTENCIA : 183
PRODUCTIVIDAD Q= 127.93
OS PRODUCTIVIDAD EN Qb = 108.74
PRODUCTIVIDAD CO Qc = 94.60
(M3)
(min)
M3(s)/Hra
M3(b)/Hra
M3(c)/Hra
EQUIPO
VOLUMEN DE PRODUCTIVIDAD Nº DE MAQ.
PLAZO
TRABAJO (Hrs)
TRACTOR 65000.0m3 106.76m3/hr 3 240
C.FRONTAL 65000.0m3 108.74m3/hr 3 240
CONDICIONES DE TRABAJO
COMPUTOS
TRAMO B
CONDICIONES DE TRABAJO
COMPUTOS
HORAS Nº de ciclos del equipo de carga para llenar la volqueta
8
IMPRODUCTI n = Pv/(qc*K*ds)
PRODUCTIVA
VA Producción por ciclo de la volqueta C = n*qc 16
203 37 Duración del ciclo T = n*Tc+tF+D/Vc+D/Vr 9.27
197 43 PRODUCTIVIDAD Q = 60*C*E*r*p/T(1+h) 67.25
74 166 PRODUCTIVIDAD EN BANCO Qb = Q * Fv 57.83
225 15 PRODUCTIVIDAD COMPACTADA Qc = Q * Fv * Fc 49.16
172 68
TRAMO C
CONDICIONES DE TRABAJO
COMPUTOS
TRAMO D
CONDICIONES DE TRABAJO
COMPUTOS
TRAMO E
CONDICIONES DE TRABAJO
COMPUTOS
DATOS DE LA MAQUINA
O CONDICIONES DE TRABAJO
COMPUTOS
DATOS DE LA MAQUINA
O CONDICIONES DE TRABAJO
COMPUTOS
Nº de ciclos del equipo de carga para llenar la volque
8
n = Pv/(qc*K*ds)
M3 Producción por ciclo de la volqueta C = n*qc 16 M3
(min) Duración del ciclo T = n*Tc+tF+D/Vc+D/Vr 11.27 (min)
M3(s)/Hra PRODUCTIVIDAD Q = 60*C*E*r*p/T(1+h) 55.31 M3(s)/Hra
M3(b)/Hra PRODUCTIVIDAD EN BANCO Qb = Q * Fv 47.57 M3(b)/Hra
M3(c)/Hra PRODUCTIVIDAD COMPACTADA Qc = Q * Fv * Fc 40.44 M3(c)/Hra
VOLQUETAS
S Y BOTADEROS
HP
(Ton)
(min)
(m)
(m/min)
(m/min)
ARGA
(Ton/M3)
(M3)
(min)
metros
M3
(min)
M3(s)/Hra
M3(b)/Hra
M3(c)/Hra
VOLQUETAS
S Y BOTADEROS
HP
(Ton)
(min)
(m)
(m/min)
(m/min)
ARGA
(Ton/M3)
(M3)
(min)
metros
M3
(min)
M3(s)/Hra
M3(b)/Hra
M3(c)/Hra
DATOS DE LA MAQUINA
O CONDICIONES DE TRABAJO
COMPUTOS
HP
(Ton)
(min)
(m)
(m/min)
(m/min)
GA
(Ton/M3)
(M3)
(min)
metros
M3
(min)
M3(s)/Hra
M3(b)/Hra
a
DATOS DE LA MAQUINA
CONDICIONES DE TRABAJO
COMPUTOS
Nº de ciclos del equipo de carga para llenar la volqueta
8
n = Pv/(qc*K*ds)
Producción por ciclo de la volqueta C = n*qc 16 M3
Duración del ciclo T = n*Tc+tF+D/Vc+D/Vr 20.83 (min)
PRODUCTIVIDAD Q = 60*C*E*r*p/T(1+h) 29.94 M3(s)/Hra
PRODUCTIVIDAD EN BANCO Qb = Q * Fv 25.75 M3(b)/Hra
PRODUCTIVIDAD COMPACTADA Qc = Q * Fv * Fc 21.88 M3(c)/Hra
CALCULO DE PRODUCTIVIDAD DE VOLQUETAS
TRANSPORTE DE VOL. DE CORTE A RELLENOS Y BOTADEROS
DATOS DE LA MAQUINA
CONDICIONES DE TRABAJO
COMPUTOS
TRAMO 1 0+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 2 1+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 3 2+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 4 3+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 5 4+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 6 5+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 7 6+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 8 7+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 9 8+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 10 9+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 11 10+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 12 11+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 13 12+000
VOLUMEN = 3675 m3
DENSIDAD(s) = 1650 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.13 m N=
V = 3200 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
9030 m T= 59.09min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 9.77m3/hr
792 m/min Qc = 8.99 m3/hr
1.45 min
HORAS
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
6507.63 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
8.99 m3/hr 5 90 82 8
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
6700 m T= 44.21min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 13.06m3/hr
792 m/min Qc = 12.02 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
6287.8 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
12.02 m3/hr 4 90 77 13
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
9310 m T= 60.87min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 9.49m3/hr
792 m/min Qc = 8.73 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
6434.39 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
8.73 m3/hr 5 90 85 5
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
6030 m T= 39.94min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 14.46m3/hr
792 m/min Qc = 12.0 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
6457.75 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
12.0 m3/hr 4 90 77 13
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
6650 m T= 43.89min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 13.16m3/hr
792 m/min Qc = 12.1 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
6300.18 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
12.1 m3/hr 4 90 76 14
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
4550 m T= 30.49min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 18.94m3/hr
792 m/min Qc = 17.43 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
5911.63 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
17.43 m3/hr 3 90 71 19
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
4870 m T= 32.53min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 17.75m3/hr
792 m/min Qc = 16.33 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
5842.59 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
16.33 m3/hr 3 90 76 14
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
7470 m T= 49.13min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 11.76m3/hr
792 m/min Qc = 10.82 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
5456.25 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
10.82 m3/hr 4 90 85 5
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
6870 m T= 45.3min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 12.75m3/hr
792 m/min Qc = 11.73 m3/hr
1.45 min
HORAS
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
5570.16 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
11.73 m3/hr 4 90 79 11
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
7870 m T= 51.68min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 11.17m3/hr
792 m/min Qc = 10.28 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
5382.86 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
10.28 m3/hr 4 90 90 0
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
10450 m T= 68.15min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 8.47m3/hr
792 m/min Qc = 7.8 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
6476.04 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
7.8 m3/hr 6 90 79 11
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
9870 m T= 64.45min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 8.96m3/hr
792 m/min Qc = 8.24 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
6631.65 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
8.24 m3/hr 5 90 90 0
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 186.88 m3/hr
0.75 Qc = 142.7 m3c/hr
Caterpillar CS - 573E
10 Q = 140.97 m3/hr `
0.75
Qc = 107.65m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 132.53 m3/hr
VOLVO FM12
10870 m T= 70.83min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 8.15m3/hr
792 m/min Qc = 7.5 m3/hr
1.45 min
HORAS
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
142.7 m3/hr 1 90 90 0
107.65 m3/hr 1 90 35 55
6367.84 m3/hr 1 90 1 89
132.53 m3/hr 1 90 28 62
7.5 m3/hr 6 90 82 8
90 Hrs
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
OLUMEN CAPA SUBBASE 3675 m3
ESPESOR LONGITUD
0.35 m 1000 m
MAQUINARIA PARA CAPA B
MOTONIVELADORA
COMPACTADOR
CAMION AGUATERO
CARGADOR FRONTAL
VOLQUETAS
TRAMO 1 0+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 2 1+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 3 2+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 4 3+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 5 4+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 6 5+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 7 6+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 8 7+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 9 8+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 10 9+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 11 10+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 12 11+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
TRAMO 13 12+000
VOLUMEN = 1900 m3
DENSIDAD(s) = 1670 Kg/m3
ALTURA m.s.n.m = 2500 m
MOTONIVELADORA
d= 1000 m L =
Va = 70 m/min P=
Vr = 98 m/min Fh =
tf = 1 min E=
COMPACTADOR
L = 2.31 m N=
V = 12000 m/hr E=
CAMION AGUATERO
C = 25000 Lt D=
J = 850 Vc =
Jv = 500 Vr =
r = 0.9 tf =
P= 1 E=
CARGADOR FRONTAL
q= 3.1 m3 P=
k= 0.95 E=
Tipo de cargado = V
VOLQUETAS
D =
Cap. Volq = 21.6 ton
Tc =
n= 4 Vc =
qc = 3.1m3 Vr =
kc = 0.95 tf =
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
9030 m T= 59.09min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 9.77m3/hr
792 m/min Qc = 8.89 m3/hr
1.45 min
HORAS
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
6507.63 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
8.89 m3/hr 3 90 72 18
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
6700 m T= 44.21min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 13.06m3/hr
792 m/min Qc = 11.89 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
6287.8 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
11.89 m3/hr 2 90 80 10
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
9310 m T= 60.87min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 9.49m3/hr
792 m/min Qc = 8.63 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
6434.39 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
8.63 m3/hr 3 90 74 16
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
6030 m T= 39.94min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 14.46m3/hr
792 m/min Qc = 13.16 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
6457.75 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
13.16 m3/hr 2 90 73 17
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
6650 m T= 43.89min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 13.16m3/hr
792 m/min Qc = 11.97 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
6300.18 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
11.97 m3/hr 2 90 80 10
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
4550 m T= 30.49min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 18.94m3/hr
792 m/min Qc = 17.24 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
5911.63 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
17.24 m3/hr 2 90 56 34
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
4870 m T= 32.53min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 17.75m3/hr
792 m/min Qc = 16.15 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
5842.59 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
16.15 m3/hr 2 90 59 31
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
7470 m T= 49.13min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 11.76m3/hr
792 m/min Qc = 10.7 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
5456.25 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
10.7 m3/hr 2 90 89 1
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
6870 m T= 45.3min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 12.75m3/hr
792 m/min Qc = 11.6 m3/hr
1.45 min
HORAS
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
5570.16 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
11.6 m3/hr 2 90 82 8
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
7870 m T= 51.68min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 11.17m3/hr
792 m/min Qc = 10.17 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
5382.86 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
10.17 m3/hr 3 90 63 27
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
10450 m T= 68.15min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 8.47m3/hr
792 m/min Qc = 7.71 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
6476.04 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
7.71 m3/hr 3 90 83 7
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
9870 m T= 64.45min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 8.96m3/hr
792 m/min Qc = 8.15 m3/hr
1.45 min
HORAS
Nº DE PLAZO
PRODUCTIVIDAD MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
6631.65 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
8.15 m3/hr 3 90 78 12
90 Hrs
Caterpillar 16 H
4.88 m N= 10
1 T = 25.49 min
0.85 Q= 106.79 m3/hr
0.75 Qc = 86.49 m3c/hr
Caterpillar CS - 573E
10 Q = 330.26 m3/hr `
0.75
Qc = 267.48m3/hr
Caterpillar 950G
1 T= 0.8 min
0.75
Qs = 144.05 m3/hr
Qc = 131.08 m3/hr
VOLVO FM12
10870 m T= 70.83min
0.8 min C= 12.4 m3/hr
625 m/min Qs = 8.15m3/hr
792 m/min Qc = 7.42 m3/hr
1.45 min
HORAS
PRODUCTIVIDAD Nº DE PLAZO
MAQ. (Hrs) PRODUCTIVA IMPRODUCTIVA
86.49 m3/hr 1 90 90 0
267.48 m3/hr 1 90 8 82
6367.84 m3/hr 1 90 1 89
131.08 m3/hr 1 90 15 75
7.42 m3/hr 3 90 86 4
90 Hrs
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
VOLUMEN CAPA BASE 1900 m3
ESPESOR LONGITUD
0.2 m 1000 m
MAQUINARIA PARA PAVIMENTO FLEXIBLE
PLANTA DE ASFALTOS CIFALI DMC-2
COMPACTADOR Caterpillar CB - 634D
CAMION IMPRIMADOR Mercedes Benz L1620/
CARGADOR FRONTAL Caterpillar 950G
PAVIMENTADORA VOGELE SUPER 1803-
VOLQUETA VOLVO FM12
TRAMO 1
0+000 - 1+000
VOLUMEN = 1125 m3 Fv = 0.00
DENSIDAD(s) = 2050 Kg/m3 FC = 0.90
ALTURA m.s.n.m = 2500 m h= 0.15
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
Nº DE
EQUIPO VOLUMEN DE TRABAJO PRODUCTIVIDAD MAQ.
Planta de Asfalto 1125 m3 29.27m3/hr 1
Caterpillar CB - 634D 1125 m3 149.15m3/hr 1
Mercedes Benz L1620/5 1125 m3 2006.85m3/hr 1
Caterpillar 950G 1125 m3 129.64m3/hr 1
VOGELE SUPER 1803-2 1125 m3 233.61m3/hr 1
VOLVO FM12 1125 m3 8.8m3/hr 4
plazo 39.0Hrs
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
Nº DE
EQUIPO VOLUMEN DE TRABAJO PRODUCTIVIDAD
MAQ.
Planta de Asfalto 1125 m3 29.27m3/hr 1
Caterpillar CB - 634D 1125 m3 149.15m3/hr 1
Mercedes Benz L1620/5 1125 m3 2135.08m3/hr 1
Caterpillar 950G 1125 m3 129.64m3/hr 1
VOGELE SUPER 1803-2 1125 m3 233.61m3/hr 1
VOLVO FM12 1125 m3 11.76m3/hr 3
plazo 39.0Hrs
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
Nº DE
EQUIPO VOLUMEN DE TRABAJO PRODUCTIVIDAD
MAQ.
Planta de Asfalto 1125 m3 29.27m3/hr 1
Caterpillar CB - 634D 1125 m3 149.15m3/hr 1
Mercedes Benz L1620/5 1125 m3 1988.96m3/hr 1
Caterpillar 950G 1125 m3 129.64m3/hr 1
VOGELE SUPER 1803-2 1125 m3 233.61m3/hr 1
VOLVO FM12 1125 m3 8.54m3/hr 4
plazo 39.0Hrs
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
Nº DE
EQUIPO VOLUMEN DE TRABAJO PRODUCTIVIDAD
MAQ.
Planta de Asfalto 1125 m3 29.27m3/hr 1
Caterpillar CB - 634D 1125 m3 149.15m3/hr 1
Mercedes Benz L1620/5 1125 m3 2138.09m3/hr 1
Caterpillar 950G 1125 m3 129.64m3/hr 1
VOGELE SUPER 1803-2 1125 m3 233.61m3/hr 1
VOLVO FM12 1125 m3 11.84m3/hr 3
plazo 39.0Hrs
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
Nº DE
EQUIPO VOLUMEN DE TRABAJO PRODUCTIVIDAD MAQ.
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
Nº DE
EQUIPO VOLUMEN DE TRABAJO PRODUCTIVIDAD
MAQ.
Planta de Asfalto 1125 m3 29.27m3/hr 1
Caterpillar CB - 634D 1125 m3 149.15m3/hr 1
Mercedes Benz L1620/5 1125 m3 2089.79m3/hr 1
Caterpillar 950G 1125 m3 129.64m3/hr 1
VOGELE SUPER 1803-2 1125 m3 233.61m3/hr 1
VOLVO FM12 1125 m3 10.58m3/hr 3
plazo 39.0Hrs
TRAMO 9 8+000 - 9+000
VOLUMEN = 1125 m3 Fv = 0.00
DENSIDAD(s) = 2050 Kg/m3 FC = 0.90
ALTURA m.s.n.m = 2500 m h= 0.15
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
Nº DE
EQUIPO VOLUMEN DE TRABAJO PRODUCTIVIDAD MAQ.
Planta de Asfalto 1125 m3 29.27m3/hr 1
Caterpillar CB - 634D 1125 m3 149.15m3/hr 1
Mercedes Benz L1620/5 1125 m3 2124.91m3/hr 1
Caterpillar 950G 1125 m3 129.64m3/hr 1
VOGELE SUPER 1803-2 1125 m3 233.61m3/hr 1
VOLVO FM12 1125 m3 11.47m3/hr 3
plazo 39.0Hrs
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
Nº DE
EQUIPO VOLUMEN DE TRABAJO PRODUCTIVIDAD
MAQ.
Planta de Asfalto 1125 m3 29.27m3/hr 1
Caterpillar CB - 634D 1125 m3 149.15m3/hr 1
Mercedes Benz L1620/5 1125 m3 2067.01m3/hr 1
Caterpillar 950G 1125 m3 129.64m3/hr 1
VOGELE SUPER 1803-2 1125 m3 233.61m3/hr 1
VOLVO FM12 1125 m3 10.06m3/hr 3
plazo 39.0Hrs
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
Nº DE
EQUIPO VOLUMEN DE TRABAJO PRODUCTIVIDAD MAQ.
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
COMPACTADOR Caterpillar CB - 63
L = 1.74m N= 10
V = 11000.0m/hr E= 0.75
w= 1.54
VOLUMEN CARPETA
1+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 2006.85 m3/hr
Caterpillar CB - 634D
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 59.09min
C= 12.4 m3/hr
Qs = 9.77m3/hr
Qc = 8.8 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 32 7
39.0Hrs
VOLUMEN CARPETA
2+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 2135.08 m3/hr
Caterpillar 950G
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 44.21min
C= 12.4 m3/hr
Qs = 13.06m3/hr
Qc = 11.76 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 32 7
39.0Hrs
VOLUMEN CARPETA
3+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 1988.96 m3/hr
Caterpillar 950G
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 60.87min
C= 12.4 m3/hr
Qs = 9.49m3/hr
Qc = 8.54 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 33 6
39.0Hrs
VOLUMEN CARPETA
4+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 2176.12 m3/hr
Caterpillar 950G
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 39.94min
C= 12.4 m3/hr
Qs = 14.46m3/hr
Qc = 13.01 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 29 10
39.0Hrs
VOLUMEN CARPETA
5+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 2138.09 m3/hr
Caterpillar 950G
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 43.89min
C= 12.4 m3/hr
Qs = 13.16m3/hr
Qc = 11.84 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 32 7
39.0Hrs
VOLUMEN CARPETA
6+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 2272.61 m3/hr
Caterpillar 950G
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 30.49min
C= 12.4 m3/hr
Qs = 18.94m3/hr
Qc = 17.05 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 33 6
39.0Hrs
VOLUMEN CARPETA
7+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 2251.03 m3/hr
Caterpillar 950G
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 32.53min
C= 12.4 m3/hr
Qs = 17.75m3/hr
Qc = 15.98 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 36 3
39.0Hrs
VOLUMEN CARPETA
8+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 2089.79 m3/hr
Caterpillar 950G
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 49.13min
C= 12.4 m3/hr
Qs = 11.76m3/hr
Qc = 10.58 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 36 3
39.0Hrs
VOLUMEN CARPETA
9+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 2124.91 m3/hr
Caterpillar 950G
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 45.3min
C= 12.4 m3/hr
Qs = 12.75m3/hr
Qc = 11.47 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 33 6
39.0Hrs
VOLUMEN CARPETA
10+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 2067.01 m3/hr
Caterpillar 950G
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 51.68min
C= 12.4 m3/hr
Qs = 11.17m3/hr
Qc = 10.06 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 38 1
39.0Hrs
VOLUMEN CARPETA
11+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 1931.23 m3/hr
Caterpillar 950G
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 68.15min
C= 12.4 m3/hr
Qs = 8.47m3/hr
Qc = 7.63 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 37 2
39.0Hrs
VOLUMEN CARPETA
12+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 1960.18 m3/hr
Caterpillar 950G
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 64.45min
C= 12.4 m3/hr
Qs = 8.96m3/hr
Qc = 8.07 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 35 4
39.0Hrs
VOLUMEN CARPETA
13+000 ASFALTICA 1125 m3
e= 0.15 m ANCHO ESPESOR LONGITUD
p= 1 7.5 m 0.15 m 1000 m
CIFALI DMC-2
Qc = 29.27m3/hr
Caterpillar CB - 634D
Q = 165.72 m3/hr
Qc = 149.15m3/hr
Qc = 1910.8 m3/hr
Caterpillar 950G
T= 0.8 min
Qs = 144.05 m3/hr
Qc = 129.64 m3/hr
Qc = 233.61m3/hr
VOLVO FM12
T= 70.83min
C= 12.4 m3/hr
Qs = 8.15m3/hr
Qc = 7.34 m3/hr
HORAS
PLAZO (Hrs) IMPRODUC
PRODUCTIVA TIVA
39 39 0
39 8 31
1 1 0
39 9 30
39 5 34
39 39 0
39.0Hrs
MAQUINARIA PARA CORTE Y RELLENO
TRAMO = SECTOR A # DE MAQ HORAS
TRACTOR CAT D7R LGP 2 225
C.FRONTAL CAT 950G 2 219
VOLQUETA Mercedes Benz Atego 1823 3 206
VOLQUETA Mercedes Benz Atego 1823 5 201
MOTONIVELADORA Caterpillar 16 H 1 16
MOTONIVELADORA Caterpillar 16 H 1 16
MOTONIVELADORA Caterpillar 16 H 1 16
MOTONIVELADORA Caterpillar 16 H 1 16
MOTONIVELADORA Caterpillar 16 H 1 16
MOTONIVELADORA Caterpillar 16 H 1 16
COMPACTADOR Caterpillar CS - 573E 1 12
C. AGUATERO Mercedes Benz 2228 1 1
C.FRONTAL Caterpillar 950G 1 14
VOLQUETA VOLVO FM12 3 16
MOTONIVELADORA Caterpillar 16 H 1 16
SUBBASE MAQUINAR
CONSUMO( CONSUM0(L) TRAMO = 0 + 000 - 1 + 000
L/HR)
MOTONIVELADORA Caterpillar 16 H
90 1440
35 420 COMPACTADOR Caterpillar CS - 573E
1 1 C. AGUATERO Mercedes Benz 2228
28 392 C.FRONTAL Caterpillar 950G
82 6560 VOLQUETA VOLVO FM12
CONSUMO(
L/HR) CONSUM0(L) TRAMO = 1 + 000 - 2 + 000
MOTONIVELADORA Caterpillar 16 H
90 1440
35 420 COMPACTADOR Caterpillar CS - 573E
1 1 C. AGUATERO Mercedes Benz 2228
28 392 C.FRONTAL Caterpillar 950G
85 6800 VOLQUETA VOLVO FM12
CONSUMO(
L/HR) CONSUM0(L) TRAMO = 3 + 000 - 4 + 000
MOTONIVELADORA Caterpillar 16 H
90 1440
35 420 COMPACTADOR Caterpillar CS - 573E
1 1 C. AGUATERO Mercedes Benz 2228
28 392 C.FRONTAL Caterpillar 950G
77 4928 VOLQUETA VOLVO FM12
CONSUMO( CONSUM0(L) TRAMO = 4 + 000 - 5 + 000
L/HR)
MOTONIVELADORA Caterpillar 16 H
90 1440
35 420 COMPACTADOR Caterpillar CS - 573E
1 1 C. AGUATERO Mercedes Benz 2228
28 392 C.FRONTAL Caterpillar 950G
76 4864 VOLQUETA VOLVO FM12
CONSUMO(
L/HR) CONSUM0(L) TRAMO = 5 + 000 - 6 + 000
MOTONIVELADORA Caterpillar 16 H
90 1440
35 420 COMPACTADOR Caterpillar CS - 573E
1 1 C. AGUATERO Mercedes Benz 2228
28 392 C.FRONTAL Caterpillar 950G
71 3408 VOLQUETA VOLVO FM12
CONSUMO(
CONSUM0(L) TRAMO = 6 + 000 - 7 + 000
L/HR)
MOTONIVELADORA Caterpillar 16 H
90 1440
35 420 COMPACTADOR Caterpillar CS - 573E
1 1 C. AGUATERO Mercedes Benz 2228
28 392 C.FRONTAL Caterpillar 950G
76 3648 VOLQUETA VOLVO FM12
CONSUMO( CONSUM0(L) TRAMO = 7 + 000 - 8 + 000
L/HR)
MOTONIVELADORA Caterpillar 16 H
90 1440
35 420 COMPACTADOR Caterpillar CS - 573E
1 1 C. AGUATERO Mercedes Benz 2228
28 392 C.FRONTAL Caterpillar 950G
85 5440 VOLQUETA VOLVO FM12
CONSUMO(
CONSUM0(L) TRAMO = 8 + 000 - 9 + 000
L/HR)
90 1440 MOTONIVELADORA Caterpillar 16 H
35 420 COMPACTADOR Caterpillar CS - 573E
1 1 C. AGUATERO Mercedes Benz 2228
28 392 C.FRONTAL Caterpillar 950G
79 5056 VOLQUETA VOLVO FM12
CONSUMO(
L/HR) CONSUM0(L) TRAMO = 9 + 000 - 10 + 000
TOTAL EN (L)
103337
A ASFALTICA
CONSUMO(
CONSUM0(L)
L/HR)
9 351
16.5 132
20 20
16.25 146.25
22 110
25 3200
CONSUMO(
L/HR) CONSUM0(L)
9 351
8 64
9.5 9.5
25 225
22 110
20 1920
CONSUMO(
L/HR) CONSUM0(L)
9 351
8 64
9.5 9.5
25 225
22 110
20 2640
CONSUMO(
L/HR) CONSUM0(L)
9 351
8 64
9.5 9.5
25 450
22 110
20 580
CONSUMO(
L/HR) CONSUM0(L)
9 351
8 64
9.5 9.5
25 225
22 110
20 1920
CONSUMO(
CONSUM0(L)
L/HR)
9 351
8 64
9.5 9.5
25 225
22 110
20 1320
CONSUMO( CONSUM0(L)
L/HR)
9 351
8 64
9.5 9.5
25 225
22 110
20 1440
CONSUMO(
CONSUM0(L)
L/HR)
9 351
8 64
9.5 9.5
25 225
22 110
20 2160
CONSUMO( CONSUM0(L)
L/HR)
9 351
8 64
9.5 9.5
25 225
22 110
20 1980
CONSUMO(
L/HR) CONSUM0(L)
9 351
8 64
9.5 9.5
25 225
22 110
20 2280
CONSUMO(
L/HR) CONSUM0(L)
9 351
8 64
9.5 9.5
25 225
22 110
20 2960
CONSUMO(
CONSUM0(L)
L/HR)
9 351
8 64
9.5 9.5
25 225
22 110
20 2800
CONSUMO(
L/HR) CONSUM0(L)
9 198
8 198
9.5 198
25 198
22 198
20 198
TOTAL EN (L)
35726.75
CONSUMO
ROYECTO DIESEL(LTS)
COSTO (SUS)
16 H
1 90 29 2610
CS - 573E 1 8 14 112
Benz 2228 1 1 23 23
950G 1 15 16.25 243.75
12 3 72 25 5400
16 H
1 90 29 2610
CS - 573E 1 8 14 112
Benz 2228 1 1 23 23
950G 1 15 16.25 243.75
12 3 74 25 5550
16 H
1 90 29 2610
CS - 573E 1 8 14 112
Benz 2228 1 1 23 23
950G 1 15 16.25 243.75
12 2 73 25 3650
16 H
1 90 29 2610
CS - 573E 1 8 14 112
Benz 2228 1 1 23 23
950G 1 15 16.25 243.75
12 2 80 25 4000
16 H
1 90 29 2610
CS - 573E 1 8 14 112
Benz 2228 1 1 23 23
950G 1 15 16.25 243.75
12 2 56 25 2800
16 H
1 90 29 2610
CS - 573E 1 8 14 112
Benz 2228 1 1 23 23
950G 1 15 16.25 243.75
12 2 59 25 2950
16 H
1 90 29 2610
CS - 573E 1 8 14 112
Benz 2228 1 1 23 23
950G 1 15 16.25 243.75
12 2 89 25 4450
16 H 1 90 29 2610
CS - 573E 1 8 14 112
Benz 2228 1 1 23 23
950G 1 15 16.25 243.75
12 2 82 25 4100
16 H 1 90 29 2610
CS - 573E 1 8 14 112
Benz 2228 1 1 23 23
950G 1 15 16.25 243.75
12 3 63 25 4725
16 H 1 90 29 2610
CS - 573E 1 8 14 112
Benz 2228 1 1 23 23
950G 1 15 16.25 243.75
12 3 83 25 6225
16 H 1 90 29 2610
CS - 573E 1 8 14 112
Benz 2228 1 1 23 23
950G 1 15 16.25 243.75
12 3 78 25 5850
16 H 1 90 29 2610
CS - 573E 1 8 14 112
Benz 2228 1 1 23 23
950G 1 15 16.25 243.75
12 3 86 25 6450
TOTAL EN (L)
83476.25
PLANILLA DNR
Interes= 12%
r=20%
SECTOR A
SECTOR B
SECTOR C
SECTOR D
SECTOR E
COSTO DE OPERACIÓN
TRAMO 0+000 -
N° Total Hrs. Trabajadas Costo Horario de operación
EQUIPO
Maq.
Produc Improduc Product
CAPA SUBBASE
MOTONIVELADORA Caterpillar 16 H 1 90 0 63.64
COMPACTADOR Caterpillar CS - 573E 1 35 55 32.16
CAMION AGUATERO Mercedes Benz 2228 1 1 89 44.14
CARGADOR FRONTAL Caterpillar 950G 1 28 62 47.37
VOLQUETAS VOLVO FM12 5 82 8 53.71
CAPA BASE
MOTONIVELADORA Caterpillar 16 H 1 90 0 63.64
COMPACTADOR Caterpillar CS - 573E 1 8 82 32.16
CAMION AGUATERO Mercedes Benz 2228 1 1 89 44.14
CARGADOR FRONTAL Caterpillar 950G 1 15 75 47.37
VOLQUETAS VOLVO FM12 3 72 18 53.71
CARPETA ASFALTICA
PLANTA DE ASFALTOS CIFALI DMC-2 1 39 0 57.13
COMPACTADOR Caterpillar CB - 634D 1 8 31 31.25
CAMION IMPRIMADOR Mercedes Benz L1620/51 1 1 0 38.10
CARGADOR FRONTAL Caterpillar 950G 1 9 30 47.37
PAVIMENTADORA VOGELE SUPER 1803-2 1 5 34 32.66
VOLQUETA VOLVO FM12 4 32 7 53.71
TRAMO 1+000 -
TRAMO 2+000 -
TRAMO 3+000 -
N° Total Hrs. Trabajadas Costo Horario de operación
EQUIPO
Maq.
Produc Improduc Product
CAPA SUBBASE
MOTONIVELADORA Caterpillar 16 H 1 90 0 63.64
COMPACTADOR Caterpillar CS - 573E 1 35 55 32.16
CAMION AGUATERO Mercedes Benz 2228 1 1 89 44.14
CARGADOR FRONTAL Caterpillar 950G 1 28 62 47.37
VOLQUETAS VOLVO FM12 4 77 13 53.71
CAPA BASE
MOTONIVELADORA Caterpillar 16 H 1 90 0 63.64
COMPACTADOR Caterpillar CS - 573E 1 8 82 32.16
CAMION AGUATERO Mercedes Benz 2228 1 1 89 44.14
CARGADOR FRONTAL Caterpillar 950G 1 15 75 47.37
VOLQUETAS VOLVO FM12 2 73 17 53.71
CARPETA ASFALTICA
PLANTA DE ASFALTOS CIFALI DMC-2 1 39 0 57.13
COMPACTADOR Caterpillar CB - 634D 1 8 31 31.25
CAMION IMPRIMADOR Mercedes Benz L1620/51 1 1 0 38.10
CARGADOR FRONTAL Caterpillar 950G 1 9 30 47.37
PAVIMENTADORA VOGELE SUPER 1803-2 1 5 34 32.66
VOLQUETA VOLVO FM12 3 29 10 53.71
TRAMO 4+000 -
TRAMO 5+000 -
TRAMO 6+000 -
TRAMO 7+000 -
TRAMO 8+000 -
TRAMO 9+000 -
TRAMO 10+000 -
TRAMO 11+000 -
TRAMO 12+000 -
26.10 29893.12
17.97 23489.94
10.61 34272.73
10.61 56043.79
26.10 42292.75
17.97 30310.48
10.61 5735.44
10.61 36729.25
10.61 9958.95
26.10 54383.65
17.97 38885.17
10.61 94841.69
26.10 24104.63
17.97 17149.38
10.61 56905.72
26.10 42292.75
17.97 30575.08
10.61 19400.73
10.61 49661.89
10.61 119845.02
1+000
osto Horario de operación Costo total de
Operaciones
Improduct ($us)
24.40 5727.53
9.62 1654.52
8.84 831.01
17.97 2440.08
10.61 22444.01
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 12173.50
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 7171.49
2+000
24.40 5727.53
9.62 1654.52
8.84 831.01
17.97 2440.08
10.61 17093.27
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 8805.21
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 5378.61
3+000
24.40 5727.53
9.62 1654.52
8.84 831.01
17.97 2440.08
10.61 23090.46
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 12432.08
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 7343.87
4+000
osto Horario de operación Costo total de
Operaciones
Improduct ($us)
24.40 5727.53
9.62 1654.52
8.84 831.01
17.97 2440.08
10.61 17093.27
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 8201.86
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 4990.74
5+000
24.40 5727.53
9.62 1654.52
8.84 831.01
17.97 2440.08
10.61 16920.88
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 8805.21
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 5378.61
6+000
24.40 5727.53
9.62 1654.52
8.84 831.01
17.97 2440.08
10.61 12044.20
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 6736.56
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 3671.94
7+000
24.40 5727.53
9.62 1654.52
8.84 831.01
17.97 2440.08
10.61 12690.66
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 6995.14
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 3930.52
8+000
24.40 5727.53
9.62 1654.52
8.84 831.01
17.97 2440.08
10.61 18472.37
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 9580.96
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 5895.78
9+000
24.40 5727.53
9.62 1654.52
8.84 831.01
17.97 2440.08
10.61 17438.04
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 8977.60
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 5507.90
10+000
24.40 5727.53
9.62 1654.52
8.84 831.01
17.97 2440.08
10.61 19334.31
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 11009.88
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 6154.36
11+000
24.40 5727.53
9.62 1654.52
8.84 831.01
17.97 2440.08
10.61 26157.06
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 13595.69
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 8033.42
12+000
24.40 5727.53
9.62 1654.52
8.84 831.01
17.97 2440.08
10.61 24167.88
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 12949.24
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 7688.65
13+000
24.40 5727.53
9.62 1046.03
8.84 831.01
17.97 2057.88
10.61 13983.57
19.66 2228.23
9.34 539.42
9.97 38.10
17.97 965.25
8.13 439.85
10.61 8378.20
CAPA SUBBASE
MOTONIVELA 1 8 0 71.190
COMPACTADO 2 8 0 25.520
ACIÓN
27.320 569.5200
8.690 408.3200
RESUMEN GENERAL
MOVIMIENTO DE TIERRAS
TRAMO SECTOR A SECTOR B SECTOR C SECTOR D SECTOR E
PLAZO (Hrs) 240 240 240 240 240
COSTO GRAL. 143699.57 125026.87 188110.51 98159.74 261775.47
Hrs.
Hrs.
Hrs.
Hrs.