CONSTRUCCIONES Y REMODELACIONES : VICTOR HUAPAYA RAMOS

EMPRESA : HR CONSTRUCCIONES Y ACABADOS


RUC: 10154271703
TELEFONOS: 986372064

PRESUPUESTO MANO DE OBRA

CLIENTE: ORDEN DE TRABAJO


PROYECTO : MONITOR - 2do PISO FECHA: 23/12/2022 DIFERENCIA
UBICACIÓN : LA PERLA MONTO VALORIZADO S/ 7,172.80 ADELANTO S/ 4,950.00 S/ 2,222.80
VALORIZACION 1 2do PISO % AVANCE 0.00%

Valorizacion anterior Valorizacion actual (2/11/2022- Valorizacion acumulada saldo a valorizar


ITEN DESCRIPCION UNIDAD CANT P.U P.PARCIAL
metrado parcial avance (%) metrado parcial avance (%) metrado parcial avance (%) metrado parcial avance (%)
1 alquiler de andamio glb 1 S/ 410.00 S/ 410.00 S/0.00 0.00% 1.00 S/410.00 100.00% 1.00 S/410.00 100.00% 0.00 S/0.00 0%
2 Desmontaje de ventaje de ventanas glb 1 S/ 250.00 S/ 250.00 S/0.00 0.00% 0.00 S/0.00 0.00% 0.00 S/0.00 0.00% 1.00 S/250.00 100%
3 eliminacion de desmonte glb 1 S/ 450.00 S/ 450.00 S/0.00 0.00% 0.00 S/0.00 0.00% 0.00 S/0.00 0.00% 1.00 S/450.00 100%
4 embolsado de desmonte glb 1 S/ 450.00 S/ 450.00 S/0.00 0.00% 0.50 S/225.00 50.00% 0.50 S/225.00 50.00% 0.50 S/225.00 50%
5 acarreo de desmonte y materiales glb 1 S/ 400.00 S/ 400.00 S/0.00 0.00% 0.50 S/200.00 50.00% 0.50 S/200.00 50.00% 0.50 S/200.00 50%
6 alquiler de maquinaria glb 1 S/ 345.50 S/ 345.50 S/0.00 0.00% 1.00 S/345.50 100.00% 1.00 S/345.50 100.00% 0.00 S/0.00 0%
7 transporte glb 1 S/ 450.00 S/ 450.00 S/0.00 0.00% 0.50 S/225.00 50.00% 0.50 S/225.00 50.00% 0.50 S/225.00 50%
8 demolicion ml 17 S/ 55.00 S/ 935.00 S/0.00 0.00% 0.50 S/27.50 2.94% 0.50 S/27.50 2.94% 16.50 S/907.50 97%
9 alquiler de puntales ( 1 soles el dia x 30 dias ) und 50 S/ 30.00 S/ 1,500.00 S/0.00 0.00% 50.00 S/1,500.00 100.00% 50.00 S/1,500.00 100.00% 0.00 S/0.00 0%
10 Colocacion de puntales y retirado glb 1 S/ 750.00 S/ 750.00 S/0.00 0.00% 0.50 S/375.00 50.00% 0.50 S/375.00 50.00% 0.50 S/375.00 50%
11 encofrado m2 9 S/ 55.00 S/ 495.00 S/0.00 0.00% 7.20 S/396.00 80.00% 7.20 S/396.00 80.00% 1.80 S/99.00 20%
12 acero kg 300 S/ 10.20 S/ 3,060.00 S/0.00 0.00% 240.00 S/2,448.00 80.00% 240.00 S/2,448.00 80.00% 60.00 S/612.00 20%
13 concreto m3 2.2 S/ 580.00 S/ 1,276.00 S/0.00 0.00% 1.76 S/1,020.80 80.00% 1.76 S/1,020.80 80.00% 0.44 S/255.20 20%
14 tarrajeo m2 27.3 S/ 45.00 S/ 1,228.50 S/0.00 0.00% 0.00 S/0.00 0.00% 0.00 S/0.00 0.00% 27.30 S/1,228.50 100%
SUB TOTAL S/IGV S/ 12,000.00 S/ - 0.00% S/ 7,172.80 59.77% S/ 7,172.80 59.77% S/ 4,827.20 40.23%