OBRAS DE PROTECCION Y RECUPERACION DEL MALECON DE LA PLAYA EN CENAIM

Cronograma Valorado
Rubro Cantidad Precio Unitario Precio Total Periodo 1(30 DIAS) Periodo 2(60 DIAS) Periodo 3(90 DIAS) Periodo 4(120 DIAS) Periodo 5(150 DIAS) Periodo 6(180 DIAS) % Total
OBRA DE PROTECCION
PRELIMINARES 1
TRAZADO Y REPLANTEO 2281 $1.12 $2,554.72 $2,554.72 100
DERROCAMIENTO DE ESTRUCTURA EXISTENTE 13.17 $47.64 $627.42 $627.42 100
LIMPIEZA Y DESBROCE DEL TERRENO 2281 $0.41 $935.21 $935.21 100
MOVIMIENTOADE
EXCAVACION TIERRA 1INCLUYE DESALOJO
MAQUINA
(DMT = 15KM)E INSTALACION DE
SUMINISTRO 10762 $5.91 $63,603.42 $31,801.71 $31,801.71 100
GEOMEMBRANA
RELLENO CON MATERIAL PEDRAPLEN, 5449.5 $6.67 $36,348.17 $18,174.08 $18,174.08 100
INCLUYE TRANSPORTE 3934.54 $28.89 $113,668.86 $56,834.43 $56,834.43 100
MORTERO
TRANSPORTECONDEARENA
MATERIALDE SITIO
DE PROTECCION 210 $32.46 $6,816.60 $2,272.20 $2,272.20 $2,272.20 100
DE RIBERAS
COLOCACION DMT 30KM
DE ROCAS D=0.85 M 122745 $0.26 $31,913.70 $10,637.90 $10,637.90 $10,637.90 100
MATERIAL ROCOSO D=0.85M PARA
(PROTECCION)
PROTECCION (NO INCLUYE TRANSPORTE NI 4091.5 $30.50 $124,790.75 $62,395.38 $62,395.38 100
INSTALACION)
RELLENO COMPACTADO CON MATERIAL 4091.5 $13.11 $53,639.57 $26,819.78 $26,819.78 100
LOCAL 1538.55 $7.80 $12,000.69 $6,000.35 $6,000.35 100
PLAN DE MANEJO
ALQUILER AMBIENTAL
DE BATERIA 1.
SANITARIA/SERVICIO
PUBLICO 2 $185.45 $370.90 $61.82 $61.82 $61.82 $61.82 $61.82 $61.82 100
PROTECCION PARA TRABAJADOR
CINTAS PLASTICAS DE SEGURIDAD (COLOR 10 $26.57 $265.70 $44.28 $44.28 $44.28 $44.28 $44.28 $44.28 100
REFLECTIVO)
LETRERO DE OBRA - INC. ESTRUCTURA 500 $0.23 $115.00 $19.17 $19.17 $19.17 $19.17 $19.17 $19.17 100
METALICA DE SOPORTE 1 $1,198.36 $1,198.36 $199.73 $199.73 $199.73 $199.73 $199.73 $199.73 100
LIMPIEZA FINAL (INC. DESALOJO) 3785 $0.61 $2,308.85 $2,308.85 100
TANQUE DE RECEPCION DE SOLIDOS
ESTRUCTURAS DE HORMIGON
HORMIGON ESTRUC. CLASE C 2.
F´C=150KG/CM2 (E=0.10M
HORMIGON SIMPLE EN TANQUE REPLANTILLO)
F´C=280 1.27 $209.44 $265.99 $265.99 100
KG/CM2 14.44 $370.07 $5,343.81 $2,671.91 $2,671.91 100
ACERO DE REFUERZO 1
ACERO ESTRUCTURAL F´C=4200 KG/CM2 2400 $2.44 $5,856.00 $2,928.00 $2,928.00 100
CARPINTERIA EMETAL
SUMINISTRO MECANICA
INSTALACION 1
DE TAPA
METALICA 0.90 X 0.80 8 $111.44 $891.52 $891.52 100
INSTALACIONES HDROSANITARIAS
SUMINISTRO E INSTALACION DE TUBERIA
160MM
SUMINISTRO E INSTALACION DE TUBERIA 2.4 $18.81 $45.14 $45.14 100
350MM
SUMINISTRO E INSTALACION DE REJILLA DE 1.2 $49.00 $58.80 $58.80 100
ACERO INOXIDABLE 3.28 $154.85 $507.91 $507.91 100
ESCALERA DECICLOPEO
HORMIGON INGRESO F´C=180KG/CM2
AL CENAIM (INC.
ENCOFRADO H.S. 60%
HORMIGON SIMPLE ENP.MURO
40% 16 $150.71 $2,411.36 $2,411.36 100
F¨C=280KG/CM2 8 $370.07 $2,960.56 $2,960.56 100
CANAL LATERAL Y ESTABILIZACION DEL TALUD LINDERO POSTERIOR
PRELIMINARES 2
TRAZADO Y REPLANTEO 1504 $1.12 $1,684.48 $842.24 $842.24 100
EXCAVACION MANUAL
EXCAVACION A MAQUINA INCLUYE DESALOJO 323.11 $8.37 $2,704.43 $1,352.22 $1,352.22 100
(DMT = 15KM) 1855 $5.91 $10,963.05 $5,481.53 $5,481.53 100
MURO GAVIONES
HORMIGON CICLOPEO F´C=180KG/CM2 (INC. 860 $46.61 $40,084.60 $20,042.30 $20,042.30 100
ENCOFRADO H.S. 60% P. 40% 205 $150.71 $30,895.55 $15,447.78 $15,447.78 100
PASO SOBRE TUBERIA
PRELIMINARES 3
TRAZADO Y REPLANTEO 59.45 $1.12 $66.58 $66.58 100
MOVIMIENTO
EXCAVACION ADE TIERRA 2INCLUYE DESALOJO
MAQUINA
(DMT = 15KM)
RELLENO CON MATERIAL PEDRAPLEN, 33.34 $5.91 $197.04 $197.04 100
INCLUYE TRANSPORTE 20.37 $28.89 $588.49 $588.49 100
RELLENO COMPACTADO MECANICAMENTE
MORTERO CON DE
CON MATERIAL ARENA DE SITIOIMPORTADO
PRESTAMO 3 $32.46 $97.38 $97.38 100
(DMT=15KM) 29.65 $25.92 $768.53 $384.26 $384.26 100
ESTRUCTURAS
HORMIGON DE HORMIGON
ESTRUC. CLASE C 3.
F´C=150KG/CM2
HORMIGON CICLOPEO(E=0.10M REPLANTILLO)(INC.
F´C=180KG/CM2 1.09 $209.44 $228.29 $114.14 $114.14 100
ENCOFRADO H.S. 60% P.
HORMIGON SIMPLE EN VIGAS 40% 3.08 $150.71 $464.19 $232.09 $232.09 100
F´C=240KG/CM2 0.45 $337.64 $151.94 $75.97 $75.97 100
HORMIGON
HORMIGON SIMPLE
SIMPLE ENEN LOSA F´C=240KG/CM2
ESTRIBO 3.5 $315.54 $1,104.39 $552.20 $552.20 100
F´C=280KG/CM2
PAV. HORM. CEM. PORT. MOD. FLEX 4.5 5.46 $383.95 $2,096.37 $1,048.18 $1,048.18 100
MPA/28D SIMPLE EN ZAPATAS
HORMGON 7.8 $246.79 $1,924.96 $962.48 $962.48 100
F´C=280KG/CM2 3.25 $324.15 $1,053.49 $526.74 $526.74 100
ACERO DE REFUERZO 2.
ACERO ESTRUCTURAL
MALLA ELECTROSOLDADA F´C=4200
DE 5.5KG/CM2
MM C/15 1112.2 $2.44 $2,713.77 $1,356.88 $1,356.88 100
CM 40 $7.04 $281.60 $140.80 $140.80 100
CARPINTERIA METAL MECANICA 2
SUMINISTRO E INSTALACION DE GUARDAVIA 10 $102.91 $1,029.10 $514.55 $514.55 100
GARITA
PRELIMINARES 4
TRAZADO Y REPLANTEO 59.43 $1.12 $66.56 $33.28 $33.28 100
MOVIMIENTO
EXCAVACION ADE TIERRA 3INCLUYE DESALOJO
MAQUINA
RELLENO COMPACTADO MECANICAMENTE
(DMT = 15KM) DE PRESTAMO IMPORTADO
CON MATERIAL 24 $5.91 $141.84 $70.92 $70.92 100
(DMT=15KM) 18 $25.92 $466.56 $466.56 100
ESTRUCTURAS DE HORMIGON 4.
CONTRAPISO H.S. 180 KG/CM2, E=10CM 17.45 $21.31 $371.86 $371.86 100
HORMIGON ESTRUC. CLASE C
F´C=150KG/CM2
HORMIGON (E=0.10M
SIMPLE REPLANTILLO)
EN PLINTOS Y RIOSTRAS F 0.19 $209.44 $39.79 $39.79 100
´C=240KG/CM2
HORMIGON SIMPLE COLUMNAS F´C=240 1.22 $309.06 $377.05 $377.05 100
KG/CM2 0.98 $319.42 $313.03 $313.03 100
HORMIGON SIMPLE EN LOSA F´C=240KG/CM2 1.85 $315.54 $583.75 $583.75 100
ACERO DE REFUERZO 3
ACERO
MALLA ESTRUCTURAL
ELECTROSOLDADA F´C=4200
DE 5.5KG/CM2
MM C/15 337.25 $2.44 $822.89 $822.89 100
CM 17.45 $7.04 $122.85 $122.85 100
MAMPOSTERIA YDERECUBRIMIENTOS
MAMPOSTERIA BLOQUE ALIVIANADO 1
E=10 CM 23.51 $16.15 $379.69 $379.69 100
ENLUCIDO VERTICAL
SUMINISTRO LISO
E INSTALACION DE CERAMICA 108 $8.29 $895.32 $895.32 100
20X20 PARED PISO 21.89 $29.34 $642.25 $642.25 100
PINTURA
SUMINISTRO E INSTALACION ALUCOBOND 108 $6.64 $717.12 $717.12 100
E=4MM 23.51 $63.66 $1,496.65 $1,496.65 100
CARPINTERIA EMETAL
SUMINISTRO MECANICA
INSTALACION DE 3
POLICARBONATO
CABLE 7/8´´ ASTMA E=6MM
A 603 CLASS A ZINC 186.59 $56.76 $10,590.85 $3,530.28 $3,530.28 $3,530.28 100
COATED
SUMINISTRO E INSTALACION DE PUERTA 46.88 $45.75 $2,144.76 $714.92 $714.92 $714.92 100
METALICA 0.80X2.00 MTS 1.6 $154.04 $246.46 $123.23 $123.23 100
VENTANA CORREDIZA DE ALUMINIO Y VIDRIO 6.44 $84.08 $541.48 $270.74 $270.74 100
APARATOS SANITARIOS
SUMINISTRO E INSTALACION DE LAVAMANOS
CON GRIFERIAE INSTALACION DE INODORO
SUMINISTRO 1 $82.47 $82.47 $41.24 $41.24 100
SENCILLO 1 $107.17 $107.17 $53.59 $53.59 100
JARDINERIA
JARDIN ARIDO DE ACUERDO A LOS PLANOS 1 $1,500.00 $1,500.00 $750.00 $750.00 100
INSTALACION ELECTRICA
PUNTO DE ALUMBRADO 127V 8 $37.82 $302.56 $151.28 $151.28 100
PUNTO DE TOMACORRINETE 127 V NORMAL 5 $38.03 $190.15 $95.08 $95.08 100
LUMINARIAS 1
LUMINARIA OJO E BUEY 56W-127V 4 $68.92 $275.68 $137.84 $137.84 100
LUMINARIA APLIQUE
LUMINARIA DE PARED
DE EMERGENCIA 60W
TIPO OJO- 127
DE V 4 $83.33 $333.32 $166.66 $166.66 100
CANGREJO
LUMINARIA18W - 127V DE PISO 70W -
REFLECTOR 1 $62.50 $62.50 $31.25 $31.25 100
127/270V 4 $97.59 $390.36 $390.36 100
CIRCUITOS DERIVADOS
PUNTO
PUNTO DE
DE TOMACORRINETE
TOMACORRIENTE 127 PARA V EQUIPO
NORMAL 6 $38.03 $228.18 $228.18 100
DE AACC 1 $47.81 $47.81 $47.81 100
CENTRODEDEDISTRIBUCION
PANEL CARGA DE DISTRIBUCION
MONOFASICO 08
POLOS 1 $60.41 $60.41 $60.41 100
TABLERO DE DISTRIBUCION
TABLERO CONTROL DE LUCES 1 $1,524.23 $1,524.23 $762.12 $762.12 100
CONSTRUCCION DE NUEVO PIT DE BOMBEO NO INCLUYE CASETA
PRELIMINAR 5
TRAZADO Y REPLANTEO 78.86 $1.12 $88.32 $88.32 100
MOVIMIENTO
EXCAVACION ADE TIERRA 4- EN AREA DE
MAQUINA
RELLENO COMPACTADO MECANICAMENTE
PLAYA
CON MATERIAL DE PRESTAMO IMPORTADO 446.12 $13.48 $6,013.70 $6,013.70 100
(DMT=15KM) 157.92 $25.92 $4,093.29 $4,093.29 100
ESTRUCTURAS DE HORMIGON 5
CONTRAPISO H.S. 180CLASE
HORMIGON ESTRUC. KG/CM2,
C E=10CM 47.36 $21.31 $1,009.24 $504.62 $504.62 100
F´C=150KG/CM2
HORMIGON (E=0.10M
SIMPLE REPLANTILLO)
EN PLINTOS Y RIOSTRAS F 1.61 $209.44 $337.20 $337.20 100
´C=240KG/CM2
HORMIGON SIMPLE COLUMNAS F´C=240 7.07 $309.06 $2,185.05 $2,185.05 100
KG/CM2
HORMIGON SIMPLE EN VIGAS 5.72 $319.42 $1,827.08 $1,827.08 100
F´C=240KG/CM2 6.52 $337.64 $2,201.41 $2,201.41 100
MAMPOSTERIA
MAMPOSTERIA YDERECUBRIMIENTOS
BLOQUE ALIVIANADO 2
E=10 CM 62.4 $16.15 $1,007.76 $503.88 $503.88 100
ENLUCIDO VERTICAL LISO 204.48 $8.29 $1,695.14 $847.57 $847.57 100
PINTURA
MAMPOSTERIA DE BLOQUE 10 CM 204.48 $6.64 $1,357.75 $678.87 $678.87 100
(ESTRUCTURAL) 79.68 $21.67 $1,726.67 $863.33 $863.33 100
CAPTACION DE
SUMINISTRO AGUA DE MARDE TUBERIA DE
E INSTALACION
PVC DE PRESION
SUMINISTRO D=4´´ 1.25 MPA
E INSTALACION DE CODOS DE 410 $44.80 $18,368.00 $6,122.67 $6,122.67 $6,122.67 100
PVC DE PRESION D=4´´ PEGABLE
SUMINISTRO E INSTALACION DE PUNTA - 44 $28.15 $1,238.60 $412.87 $412.87 $412.87 100
FILTRO DE ABSORCION
SUMINISTRO E INSTALACION DE BOMBA DE 60 $46.55 $2,793.00 $1,396.50 $1,396.50 100
5HP
SUMINISTRO E INSTALACION DE UNION 1 $1,983.61 $1,983.61 $991.81 $991.81 100
UNIVERSAL
SUMINISTRO E INSTALACION DE VALVULA DE 2 $34.87 $69.74 $34.87 $34.87 100
CONTROL DE EPVC
SUMINISTRO D=3´´
INSTALACION DE VALVULA DE 20 $69.23 $1,384.60 $692.30 $692.30 100
RETENCION DE PVC D=3´´ 4 $94.12 $376.48 $188.24 $188.24 100
SUMINISTRO E INSTALACION DE TEE 90 D=4 18 $20.70 $372.60 $186.30 $186.30 100
TABLERO CONTROL DE BOMBAS 1 $7,518.85 $7,518.85 $3,759.43 $3,759.43 100
CONSTRUCCION DE CASETA DE PIT DE BOMBEO
CASETA PIT DE BOMBEO
CONSTRUCCION DE CASETA DE PIT DE
BOMBEO 1 $8,087.73 $8,087.73 $8,087.73 100
CONSTRUCCION DE CERRAMIENTOS Y AREA DE MALECON EN GAZEBO
PRELIMINARES 6
TRAZADO Y REPLANTEO 2436 $1.12 $2,728.32 $1,364.16 $1,364.16 100
LIMPIEZA Y DESBROCE DEL TERRENO 2436 $0.41 $998.76 $998.76 100
MOVIMIENTO
EXCAVACION DE TIERRA 5
A MAQUINAMECANICAMENTE
INCLUYE DESALOJO
RELLENO COMPACTADO
(DMT=15
CON KM) DE PRESTAMO IMPORTADO
MATERIAL 225.31 $5.91 $1,331.58 $1,331.58 100
RELLENO CON BASE CLASI I H=0.15 MTS
(DMT=15KM)
(PARA ADOQUINADO PEATONAL), 166.02 $25.92 $4,303.24 $4,303.24 100
(DMT=15KMS) 35.6 $27.84 $991.10 $991.10 100
ESTRUCTURAS DE HORMIGON 6
HORMIGON ESTRUC. CLASE C
F´C=150KG/CM2
HORMIGON SIMPLE(E=0.10M REPLANTILLO)
EN PLINTOS Y RIOSTRAS F 7.45 $209.44 $1,560.33 $1,560.33 100
´C=240KG/CM2
HORMIGON SIMPLE COLUMNAS F´C=240 37 $309.06 $11,435.22 $11,435.22 100
KG/CM2
HORMIGON SIMPLE DE ESCALINATAS F 15.77 $319.42 $5,037.25 $5,037.25 100
´C=240KG/CM2
HORMIGON SIMPLE EN VIGAS 4.76 $337.65 $1,607.21 $1,607.21 100
F´C=240KG/CM2
HORMIGON SIMPLE EN DUCTO CAJON F 8.45 $337.64 $2,853.06 $2,853.06 100
´C=280KG/CM2 24 $370.07 $8,881.68 $4,440.84 $4,440.84 100
BORDILLO JARDINERA
BORDILLO DE CONFINAMIENTO 0.15X0.30 F 30 $19.07 $572.10 $572.10 100
´C=210KG/CM2 PARA ADOQUINES 132 $15.88 $2,096.16 $2,096.16 100
ACERO DE REFUERZO 4
ACERO ESTRUCTURAL F´C=4200 KG/CM2 4897.6 $2.44 $11,950.14 $5,975.07 $5,975.07 100
MAMPOSTERIA YDERECUBRIMIENTOS
MAMPOSTERIA BLOQUE ALIVIANADO 3
E=10 CM 879.2 $16.15 $14,199.08 $7,099.54 $7,099.54 100
ENLUCIDO VERTICAL LISO 1758.4 $8.29 $14,577.14 $7,288.57 $7,288.57 100
PINTURA
SUMINSTRO E INSTALACION DE PIEDRA DE 1758.4 $6.64 $11,675.78 $5,837.89 $5,837.89 100
ENCHAPE 43.2 $45.99 $1,986.77 $1,986.77 100
CERRAMIENTO DE
CERRAMIENTO DE PLASTICO
ESTACAS DERECICLADO
PLASTICO 360 $33.56 $12,081.60 $12,081.60 100
RECICLADO
ADOQUIN PEATONAL, INCLUYE 3CMS DE 120 $24.45 $2,934.00 $2,934.00 100
ARENA 232 $26.39 $6,122.48 $6,122.48 100
CARPINTERIA
PERGOLA DE MADERADE
RECTANGULAR 1 MADERA CON
MADEROL
BANCAS DEY H,A.
LACAY PROTECTORA
MADERA CON6.05X2.20
MADEROL Y 5 $1,361.65 $6,808.25 $6,808.25 100
PUERTA DE INGRESO PRINCIPAL
LACA PROTECTORA-(INC.
MTS MADERA CON MADEROL MONTAJE)
Y LACA 10 $139.17 $1,391.70 $1,391.70 100
PROTECTORA - INCLUYE INSTALACION 1 $913.41 $913.41 $913.41 100
JARDINERIA 2
JARDINERIAS 1 $2,000.00 $2,000.00 $2,000.00 100
TUBERIA DE PVC 1D=2´´ (PARA CANALIZADOR
CANALIZACION
DE ALIMENTADORESSUBTERRANEA
DE BAJA TENSION Y
ALUMBRADO) 2200 $2.61 $5,742.00 $5,742.00 100
CAJA DE PASO 0.60X0.60X0.60 DE H.S. 21 $143.27 $3,008.67 $3,008.67 100
ACOMETIDA EN
ACOMETIDA PARABAJA TENSION
BOMBAS (3#12+T#12
THHN)
ACOMETIDA PARA CIRCUITO DE ALUMBRADO 80 $4.73 $378.40 $378.40 100
(2#10+T#12
ACOMETIDATHHN)
PARA CIRCUITO DE ALUMBRADO 30 $5.64 $169.20 $169.20 100
(2#8+T#10 THNHN)
ACOMETIDA PARA CIRCUITOS DE 720 $7.52 $5,414.40 $5,414.40 100
ALUMBRADOPARA
ACOMETIDA (2#6+T#8
BAJATHHN)
TENSION (2#6+N#6 + 650 $12.37 $8,040.50 $8,040.50 100
T#8 THHN) PARA BAJA TENSION (3#1/0 +
ACOMETIDA 160 $15.63 $2,500.80 $2,500.80 100
N#1/0 + T#4 THHN)
ACOMETIDA PARA BAJA TENSION (2#2 +N#2 + 90 $72.22 $6,499.80 $6,499.80 100
T#6 THHN) 80 $49.01 $3,920.80 $3,920.80 100
LUMINARIAS
LUMINARIA DE 2 PISO LED PARA COLUMNA
12W - 220V 67 $146.11 $9,789.37 $9,789.37 100
CIRCUITOS DERIVADOS
PUNTO DE ALUMBRADO 127V 13 $37.82 $491.66 $491.66 100
PUNTO DE ALUMBRADO 220 V. 85 $85.79 $7,292.15 $7,292.15 100
POSTESFIBRA
POSTE DE ALUMBRADO
DE VIDRIO DE 4.5 MTS - LED
70W 127/270V 18 $339.20 $6,105.60 $6,105.60 100
PLAN DE MANEJO
ALQUILER AMBIENTAL
DE BATERIA 2
SANITARIA/SERVICIO
PUBLICO 6 $185.45 $1,112.70 $185.45 $185.45 $185.45 $185.45 $185.45 $185.45 100
PROTECCION PARADE
CINTAS PLASTICAS TRABAJADOR
SEGURIDAD (COLOR 15 $26.57 $398.55 $66.43 $66.43 $66.43 $66.43 $66.43 $66.43 100
REFLECTIVO)
LETRERO DE OBRA - INC. ESTRUCTURA 500 $0.23 $115.00 $19.17 $19.17 $19.17 $19.17 $19.17 $19.17 100
METALICA DE SOPORTE 1 $1,198.36 $1,198.36 $199.73 $199.73 $199.73 $199.73 $199.73 $199.73 100
LIMPIEZA FINAL (INC. DESALOJO) 600 $0.61 $366.00 $366.00 100
SEGURIDAD
SISTEMA DE SEGURIDAD
TUBERIA DE PVC 1/2´´ TIPO PESADO 620 $0.85 $527.00 $527.00 100
CAJA DE PASO DE 15 c 69 $1.20 $82.80 $41.40 $41.40 100
CABLE UTP CATEGORIA 5A (305M) 2 $250.00 $500.00 $250.00 $250.00 100
CABLE GEMELO 2X27 - 50 M CADA BOBINA 13 $38.00 $494.00 $247.00 $247.00 100
TOMACORRIENTE SIMPLE 4 $2.50 $10.00 $10.00 100
CAMARAS TIPO TUBO SELLADO 700 TVL 4 $139.76 $559.04 $559.04 100
BALUMS 8 $4.81 $38.48 $38.48 100
TRANSFORMADORES 4 $4.81 $19.24 $19.24 100
GRABADOR DE DVR DE 8 CANALES 1 $750.00 $750.00 $750.00 100
INSTALACION DE CAMARAS 1 $3,000.02 $3,000.02 $3,000.02 100
INVERSION $125,414.01 $175,294.55 $188,682.92 $172,919.88 $106,356.80 $91,291.38
AVANCE PARCIAL EN % 14.58% 20.38% 21.94% 20.11% 12.37% 10.62%
INVERSION ACUMULADA $125,414.01 $300,708.57 $489,391.48 $662,311.36 $768,668.16 $859,959.54
AVANCE ACUMULADO EN % 14.58% 34.97% 56.91% 77.02% 89.38% 100.00%
TOTAL COSTOS DIRECTOS +INDIRECTOS $859,959.54