Está en la página 1de 25

ANALISIS DE PRECIOS UNITARIOS

RUBRO: RETIRO DE MALLA UNIDAD:


DETALLE: TRABAJO ACADEMICO RENDIMIENTO
CODIGO: 1 FECHA:

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA
VOLQUETA 13 TON. 1 15 15
RETROEXCAVADORA 1 25 25
Herramienta menor (5% MDO) GLB.
PARCIAL M
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO HORA
MAESTRO MAYOR (ESTR. OCU. C1) 0.10 4.09 0.409
PEON (ESTR. OCU. E2) 2.00 4.05 8.100
CHOFER (ESTR. OCU. C1) 1.00 5.95 5.950
OPERADOR EQUIPO PESADO (ESTR. OCU. C1) 1.00 4.55 4.550
PARCIAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO
DISCO saco 3.0000 3.42

PARCIAL O
TOTAL COSTOS DIRECTOS X=(M+N+O)
COSTOS INDIRECTOS 20.00%
COSTO TOTAL DEL RUBRO
VALOR PROPUESTO
m
0.2 h/m3

COSTO %
3.00 13.5%
5.00 22.5%
0.19 0.9%
8.19 0.9%

COSTO %
0.08 0.4%
1.62 7.3%
1.19 5.3%
0.91 4.1%
3.80 17.1%

COSTO %
10.26 46.1%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
10.26 46.1%
22.25 64.0%
4.45
26.70
26.70
ANALISIS DE PRECIOS UNITARIOS
RUBRO: DERROCAMIENTO MUROS UNIDAD:
DETALLE: TRABAJO ACADEMICO RENDIMIENTO
CODIGO: 2 FECHA:

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA
RETROEXCAVADORA 1 25.000 25.000
Herramienta menor (5% MDO) GLB.
PARCIAL M
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO HORA
MAESTRO MAYOR (ESTR. OCU. C1) 0.10 4.09 0.409
OPERADOR EQUIPO PESADO G1 (ESTR. OCU. C1) 1.00 4.55 4.550
PEON E2 (ESTR. OCU. E2) 2.00 4.05 8.100
PARCIAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO

PARCIAL O
TOTAL COSTOS DIRECTOS X=(M+N+O)
COSTOS INDIRECTOS 20.00%
COSTO TOTAL DEL RUBRO
VALOR PROPUESTO
m3
0.5 h/m3

COSTO %
12.50 64.6%
0.33 1.7%
12.83 66.3%

COSTO %
0.20 1.0%
2.28 11.8%
4.05 20.9%
6.53 33.7%

COSTO %
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
19.36 100.0%
3.87
23.23
23.23
ANALISIS DE PRECIOS UNITARIOS
RUBRO: EXCAVACION MAQUINA 0 - 2 UNIDAD:
DETALLE: TRABAJO ACADEMICO RENDIMIENTO
CODIGO: 3 FECHA:

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA
VOLQUETA 1 15 15
RETROEXCAVADORA 1 25 25
Herramienta menor (5% MDO) GLB.
PARCIAL M
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO HORA
MAESTRO MAYOR (ESTR. OCU. C1) 0.10 4.09 0.409
OPERADOR EQUIPO PESADO G1 (ESTR. OCU. C1) 1.00 4.55 4.550
PEON E2 (ESTR. OCU. E2) 2.00 4.05 8.100
PARCIAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO

PARCIAL O
TOTAL COSTOS DIRECTOS X=(M+N+O)
COSTOS INDIRECTOS 20.00%
COSTO TOTAL DEL RUBRO
VALOR PROPUESTO
m3
0.06 h/m3

COSTO %
0.90 28.0%
1.50 46.6%
0.04 1.2%
2.44 47.8%

COSTO %
0.02 0.6%
0.27 8.4%
0.49 15.2%
0.78 24.2%

COSTO %
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
3.22 72.0%
0.64
3.86
3.86
ANALISIS DE PRECIOS UNITARIOS
RUBRO: EXCAVACION A MANO UNIDAD:
DETALLE: TRABAJO ACADEMICO RENDIMIENTO
CODIGO: 4 FECHA:

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA
Herramienta menor (5% MDO) GLB.
PARCIAL M
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO HORA
MAESTRO MAYOR (ESTR. OCU. C1) 0.10 4.09 0.409
ALBAÑIL (ESTR. OCU. D2) 1.00 4.10 4.100
PEON E2 (ESTR. OCU. E2) 2.00 4.05 8.100
PARCIAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO

PARCIAL O
TOTAL COSTOS DIRECTOS X=(M+N+O)
COSTOS INDIRECTOS 20.00%
COSTO TOTAL DEL RUBRO
VALOR PROPUESTO
m3
0.4 h/m3

COSTO %
0.25 4.7%
0.25 4.7%

COSTO %
0.16 3.0%
1.64 31.0%
3.24 61.2%
5.04 95.3%

COSTO %
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
0.00 0.0%
5.29 100.0%
1.06
6.35
6.35
ANALISIS DE PRECIOS UNITARIOS
RUBRO: MURO DE CIMENTACION HORMIGON CICLOPEO UNIDAD:
DETALLE: TRABAJO ACADEMICO RENDIMIENTO
CODIGO: 5 FECHA:

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA
CONCRETERA 1 SACO 0.35 1.5 1.5
VIBRADOR DE MANGUERA 0.35 0.5 0.5
Herramienta menor (5% MDO) GLB.
PARCIAL M
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO HORA
MAESTRO MAYOR (ESTR. OCU. C1) 0.20 4.09 0.818
PEON (ESTR. OCU. E2) 0.35 4.05 1.418
ALBAÑIL (ESTR. OCU. D2) 0.70 4.10 2.870
PARCIAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO

Cemento Fuerte Tipo GU Saco 50 Kg - Holcim DISENSA saco 0.36 7.68

ARENA M3 0.02 13.50


RIPIO M3 0.03 18.00
AGUA M3 0.01 0.85
PARCIAL O
TOTAL COSTOS DIRECTOS X=(M+N+O)
COSTOS INDIRECTOS 20.00%
COSTO TOTAL DEL RUBRO
VALOR PROPUESTO
m
0.35 h/m3

COSTO %
0.53 8.6%
0.18 2.9%
0.09 1.5%
0.80 1.5%

COSTO %
0.29 4.7%
0.50 8.1%
1.00 16.2%
1.79 29.0%

COSTO %

2.76 44.7%

0.27 4.4%
0.54 8.8%
0.01 0.2%
3.58 58.0%
6.17 88.5%
1.23
7.40
7.40
ANALISIS DE PRECIOS UNITARIOS
RUBRO: MURO DE CIMENTACION HORMIGON SIMPLE 210 UNIDAD:
DETALLE: TRABAJO ACADEMICO RENDIMIENTO
CODIGO: 6 FECHA:

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA
CONCRETERA 1 SACO 1 1.5 1.5
Herramienta menor (5% MDO) GLB.
PARCIAL M
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO HORA
MAESTRO MAYOR (ESTR. OCU. C1) 2.00 4.09 8.180
PEON (ESTR. OCU. E2) 6.00 4.05 24.300
ALBAÑIL (ESTR. OCU. D2) 3.00 4.10 12.300
OPERADOR EQUIPO LIVIANO (ESTR. OCU. D2) 1.00 4.10 4.100
CARPINTERO (ESTR. OCU. D2) 2.00 4.10 8.200
PARCIAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO

Cemento Fuerte Tipo GU Saco 50 Kg - Holcim DISENSA saco 7.20 7.68

ARENA M3 0.65 13.50


RIPIO M3 0.95 18.00
AGUA M3 0.23 0.85
PARCIAL O
TOTAL COSTOS DIRECTOS X=(M+N+O)
COSTOS INDIRECTOS 20.00%
COSTO TOTAL DEL RUBRO
VALOR PROPUESTO
m
0.35 h/m3

COSTO %
0.53 0.5%
1.00 1.0%
1.53 1.0%

COSTO %
2.86 2.8%
8.51 8.3%
4.31 4.2%
1.44 1.4%
2.87 2.8%
19.99 19.4%

COSTO %

55.30 53.7%

8.78 8.5%
17.10 16.6%
0.20 0.2%
81.38 79.1%
102.90 99.5%
20.58
123.48
123.48
ANALISIS DE PRECIOS UNITARIOS
RUBRO: ENCOFRADO DE MUROS UNIDAD:
DETALLE: TRABAJO ACADEMICO RENDIMIENTO
CODIGO: 7 FECHA:

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA
Herramienta menor (5% MDO) GLB.
PARCIAL M
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO HORA
MAESTRO MAYOR (ESTR. OCU. C1) 0.08 4.09 0.327
PEON (ESTR. OCU. E2) 0.32 4.05 1.296
CARPINTERO (ESTR. OCU. D2) 1.82 4.10 7.462
PARCIAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO
TABLA DURA DE ENCOFRADO DE 0.3 m U 4.18 5.50
ALAMBRE GALVANIZADO No. 18 KG 0.080 2.54
CLAVOS 2'', 2 1/2'', 3'', 3 1/2'' KG 0.22 1.03
PARCIAL O
TOTAL COSTOS DIRECTOS X=(M+N+O)
COSTOS INDIRECTOS 20.00%
COSTO TOTAL DEL RUBRO
VALOR PROPUESTO
m
0.48 h/m3

COSTO %
0.22 0.8%
0.22 0.8%

COSTO %
0.16 0.6%
0.62 2.2%
3.58 12.8%
4.36 15.6%

COSTO %
22.99 82.1%
0.20 0.7%
0.23 0.8%
23.42 83.6%
28.00 100.0%
5.60
33.60
33.60
ANALISIS DE PRECIOS UNITARIOS
RUBRO: ENCOFRADO DE CADENAS UNIDAD:
DETALLE: TRABAJO ACADEMICO RENDIMIENTO
CODIGO: 8 FECHA:

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA
Herramienta menor (5% MDO) GLB.
PARCIAL M
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO HORA
MAESTRO MAYOR (ESTR. OCU. C1) 0.08 4.09 0.327
PEON (ESTR. OCU. E2) 0.40 4.05 1.620
ALBAÑIL (ESTR. OCU. D2) 0.40 4.10 1.640
PARCIAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO
TABLA DURA DE ENCOFRADO DE 0.3 m U 3.75 5.50
PINGOS M 0.500 1.10
TIRAS U 1.50 1.45
CLAVOS 2'', 2 1/2'', 3'', 3 1/2'' KG 0.50 1.03
PARCIAL O
TOTAL COSTOS DIRECTOS X=(M+N+O)
COSTOS INDIRECTOS 20.00%
COSTO TOTAL DEL RUBRO
VALOR PROPUESTO
m
0.4 h/m3

COSTO %
0.07 0.3%
0.07 0.3%

COSTO %
0.13 0.5%
0.65 2.6%
0.66 2.6%
1.44 5.7%

COSTO %
20.63 81.3%
0.55 2.2%
2.18 8.6%
0.52 2.0%
23.88 94.1%
25.39 100.0%
5.08
30.47
30.47
ANALISIS DE PRECIOS UNITARIOS
RUBRO: VIGA V5 - V7 UNIDAD:
DETALLE: TRABAJO ACADEMICO RENDIMIENTO
CODIGO: 9 FECHA:

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA
AMOLADORA 1 1.38 1.38
Herramienta menor (5% MDO) GLB.
PARCIAL M
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO HORA
MAESTRO MAYOR (ESTR. OCU. C1) 1.00 4.09 4.090
PEON (ESTR. OCU. E2) 4.00 4.05 16.200
PARCIAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO
VIGA V5 - V7 U 1.00 29.71
ALAMBRE RECOCIDO 1.25 mm KG 0.020 2.21
DISCO DE CORTE U 2.00 2.34
PARCIAL O
TOTAL COSTOS DIRECTOS X=(M+N+O)
COSTOS INDIRECTOS 20.00%
COSTO TOTAL DEL RUBRO
VALOR PROPUESTO
m
0.5 h/m3

COSTO %
0.69 1.5%
0.51 1.1%
1.20 1.1%

COSTO %
2.05 4.5%
8.10 17.7%
10.15 22.2%

COSTO %
29.71 64.9%
0.04 0.1%
4.68 10.2%
34.43 75.2%
45.78 98.5%
9.16
54.94
54.94
ANALISIS DE PRECIOS UNITARIOS
RUBRO: POSTE 2'' CON GUIA PARA ALAMBRE PUAS UNIDAD:
DETALLE: TRABAJO ACADEMICO RENDIMIENTO
CODIGO: 10 FECHA:

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA
AMOLADORA 1 1.38 1.38
Herramienta menor (5% MDO) GLB.
PARCIAL M
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO HORA
MAESTRO MAYOR (ESTR. OCU. C1) 0.10 4.09 0.409
PEON (ESTR. OCU. E2) 2.00 4.05 8.100
PARCIAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO
TUBO DE CERRAMIENTO GALVANIZADO U 1.50 25.05
PARCIAL O
TOTAL COSTOS DIRECTOS X=(M+N+O)
COSTOS INDIRECTOS 20.00%
COSTO TOTAL DEL RUBRO
VALOR PROPUESTO
m
0.3 h/m3

COSTO %
0.41 1.0%
0.13 0.3%
0.54 0.3%

COSTO %
0.12 0.3%
2.43 6.0%
2.55 6.3%

COSTO %
37.58 92.4%
37.58 92.4%
40.67 99.0%
8.13
48.80
48.80
ANALISIS DE PRECIOS UNITARIOS
RUBRO: MALLA CERRAMIENTO H = 2 M SUM INST UNIDAD:
DETALLE: TRABAJO ACADEMICO RENDIMIENTO
CODIGO: 11 FECHA:

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA
SOLDADORA ELECTRICA 300 A 1 2.83 2.83
Herramienta menor (5% MDO) GLB.
PARCIAL M
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO HORA
MAESTRO MAYOR (ESTR. OCU. C1) 0.10 4.09 0.409
PEON (ESTR. OCU. E2) 3.00 4.05 12.150
SOLDADOR EN CONSTRUCCION (ESTR. OCU. C3) 1.00 4.16 4.160
PARCIAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO
ALAMBRE GALVANIZADO No.14 KG 0.10 2.50
TUBO NEGRO L = 6 M PORTE 2'' U 0.180 36.73
ELECTRODO AGA 6011 KG 0.30 4.40
PLATINA 12 X 3 mm, PESO = 1.70 KG M 0.09 244.00
MALLA DE CERRAMIENTO 50 / 10 M2 2.10 2.57
PARCIAL O
TOTAL COSTOS DIRECTOS X=(M+N+O)
COSTOS INDIRECTOS 20.00%
COSTO TOTAL DEL RUBRO
VALOR PROPUESTO
M2
1 h/m3

COSTO %
2.83 5.1%
0.84 1.5%
3.67 1.5%

COSTO %
0.41 0.7%
12.15 21.7%
4.16 7.4%
16.72 29.9%

COSTO %
0.25 0.4%
6.61 11.8%
1.32 2.4%
21.96 39.3%
5.40 9.7%
35.54 63.5%
55.93 94.9%
11.19
67.12
67.12
ANALISIS DE PRECIOS UNITARIOS
RUBRO: ALAMBRE PUAS UNIDAD:
DETALLE: TRABAJO ACADEMICO RENDIMIENTO
CODIGO: 12 FECHA:

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA
Herramienta menor (5% MDO) GLB.
PARCIAL M
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO HORA
PEON (ESTR. OCU. E2) 0.50 4.05 2.025
SOLDADOR EN CONSTRUCCION (ESTR. OCU. C3) 0.25 4.16 1.040
PARCIAL N
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO
ALAMBRES DE PUAS FORT (ROLLO = 200 M) ROLLO 0.01 21.22
PARCIAL O
TOTAL COSTOS DIRECTOS X=(M+N+O)
COSTOS INDIRECTOS 20.00%
COSTO TOTAL DEL RUBRO
VALOR PROPUESTO
M2
0.25 h/m3

COSTO %
0.04 3.9%
0.04 3.9%

COSTO %
0.51 50.0%
0.26 25.5%
0.77 75.5%

COSTO %
0.21 20.6%
0.21 20.6%
1.02 100.0%
0.20
1.22
1.22
PRECIO PRECIO
No. RUBRO CANTIDAD
UNITARIO GLOBAL
1 RETIRO DE MALLA 60 26.70 1602
2 DERROCAMIENTO MUROS 50.4 23.23 1170.792
3 EXCAVACION MAQUINARIA 0 - 2 M 7.36 3.86 28.4096
4 EXCAVACION A MANO 2 6.35 12.7
5 MURO CIMENTACION H. CICLOPEO 7.36 7.40 54.464
6 MURO CERRAMIENTO H. SIMPLE 210 14.51 123.48 1791.6948
7 ENCOFRADO MUROS 29.02 33.60 975.072
8 ENCOFRADO CADENAS 12.74 30.47 388.1878
9 VIGA V5 - V7 52.69 54.94 2894.7886
10 POSTE 2'' CON GUIA PARA ALAMBRE PUAS 63.3 48.80 3089.04
11 MALLA CERRAMIENTO H = 2M SUM INST 58.88 67.12 3952.0256
12 ALAMBRE PUAS 88.32 1.22 107.7504
SUBTOTAL 16066.9248