Está en la página 1de 5

PROGRAMACION DE CRONOGRAMA VALORIZADO DE ADICIONAL DE OBRA N°01- ACTUALIZADO

: "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE SAN JUAN DE LICUPIS – PROVINCIA DE CHOTA - REGION CAJAMARCA"
CLIENTE : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS
LUGAR : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA
FECHA : DICIEMBRE DE 2022

PRESUPUESTO BASE MES 1 - 2020 MES 2 - 2020 MES 3 - 2020 MES 4 - 2021 MES 5 - 2021 MES 6 - 2021 MES 7 - 2021 MES 8 - 2021 MES 9 - 2022 MES 10 - 2022 MES 11 - 2022 MES 12 - 2022
ITEM DESCRIPCION UNID METRADO
P.U. PARCIAL OCTUBRE: 19-31 NOVIEMBRE:01-30 DICIEMBRE:01-08 JULIO:21-31 AGOSTO:01-31 SEPTIEMBRE:01-30 OCTUBRE:01-31 NOVIEMBRE:01-28 SETIEMBRE:24-30 OCTUBRE:01-30 31 OCT AL 30 NOV. 22 01 DIC. AL 31 DIC. 22
(S/.) (S/.) AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO

01 ADICIONAL - SISTEMA DE AGUA POTABLE 196,275.03


01.01 RESERVORIO CIRCULAR ( V = 20 M3) 1,499.41
01.01.01 CERCO PERIMETRICO METALICO 1,499.41
01.01.01.01 MOVIMIENTO DE TIERRAS 230.91
01.01.01.01.01 EXCAVACIÓN MANUAL CERCO PERIMETRICO m3 3.08 42.14 129.79 100.00% 129.79
01.01.01.01.02 ACARREO DE MATERIAL EXCEDENTE HASTA D. Prom. = 30 m m3 4.00 25.28 101.12 100.00% 101.12
01.01.01.02 OBRAS DE CONCRETO SIMPLE 1,268.50
01.01.01.02.01 CONCRETO F'C=175 KG/CM2 + 30%PM-CERCO PERIMETRICO m3 3.19 397.65 1,268.50 - 0.00% - 0.00% - 33.33% 422.83 66.77% 846.99
01.02 MEJ. RESERVORIO CIRULAR APO. EXIST. V=5M3 y 2.5M3 16,103.67 - -
01.02.01 TRABAJOS PRELIMINARES 54.63 - -
01.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 12.50 2.14 26.75 100.00% 26.75 - - -
01.02.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 12.50 2.23 27.88 100.00% 27.88 - - -
01.02.02 MOVIMIENTO DE TIERRAS 3,494.87 - -
01.02.02.01 DEMOLICION DE TARRAJEO INTERIOR Y EXTERIOR m2 44.24 71.98 3,184.40 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 3,184.40
01.02.02.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 4.14 42.14 174.46 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 174.46
01.02.02.03 ACARREO DE MATERIAL EXCEDENTE HASTA D. Prom. = 30 m m3 5.38 25.28 136.01 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 136.01
01.02.03 OBRAS DE CONCRETO SIMPLE 1,644.80 - -
01.02.03.01 VEREDA DE PROTECCION m3 2.36 415.56 980.72 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 980.72
01.02.03.02 CONCRETO F'C=175 KG/CM2 + 30%PM-CERCO PERIMETRICO m3 1.67 397.65 664.08 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 664.08
01.02.04 REVOQUES Y ENLUCIDOS 2,338.95 - -
01.02.04.01 TARRAJEO CON IMPERMEABILIZANTE MEZCLA 1:1, e=1.5 cm m2 23.84 52.30 1,246.83 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 1,246.83
01.02.04.02 TARRAJEO EN EXTERIORES1:5 m2 38.55 28.33 1,092.12 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 1,092.12
01.02.05 VÁLVULAS Y ACCESORIOS 3,341.58 - -
01.02.05.01 VALVULAS Y ACCESORIOS PARA CASETA DE RESERVORIO GLB 2.00 1,670.79 3,341.58 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 3,341.58
01.02.06 CARPINTERIA METALICA, HERRERIA. 1,323.42 - -
01.02.06.01 TAPA METALICA 0.60X0.60+ MARCO METAL GLB 2.00 309.90 619.80 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 619.80
01.02.06.02 PINTURA ANTICORROSIVA ESMALTE PARA METALES m2 0.77 9.59 7.38 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 7.38
01.02.06.03 ESCALERA METALICA DE RESERVORIO und 2.00 348.12 696.24 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 696.24
01.02.07 CERCO PERIMETRICO 3,356.10 - -
01.02.07.01 CERCO PERIMETRICO m 49.03 68.45 3,356.10 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 3,356.10
01.02.08 VARIOS 549.32 - -
01.02.08.01 PINTADO LATEX 02 MANOS, PAREDES EXTERIORES m2 42.55 12.91 549.32 0.00% 0.00% 0.00% - 0.00% - 0.00% - 33.33% 183.11 66.68% 366.26
PASE AEREO L= Variable (12 UNIDADES)
01.03 76518.73 - -
01.03.01 TRABAJO PRILIMINARES 354.50 - -
01.03.01.01 LIMPIEZA DE TERRENO MANUAL m2 81.12 2.14 173.60 16.66% 28.93 0.00% 0.00% 0.00% - 0.00% - 0.00% - 83.34% 144.67
01.03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 81.12 2.23 180.90 16.67% 30.15 0.00% 0.00% 0.00% - 0.00% - 0.00% - 83.33% 150.75
01.03.02 MOVIMIENTO DE TIERRAS 7,866.63 - -
01.03.02.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 105.48 42.14 4,444.93 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 4,444.93
01.03.02.02 RELLENO CON MATERIAL PROPIO m3 3.84 21.21 81.45 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 81.45
01.03.02.03 ACARREO DE MATERIAL EXCEDENTE HASTA D. Prom. = 30 m m3 132.13 25.28 3,340.25 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 3,340.25
01.03.03 OBRAS DE CONCRETO SIMPLE 19,204.56 - -
01.03.03.01 CONCRETO CAMARAS DE ANCLAJE FC=140 KG/CM2 + 70 % PM. m3 52.68 353.50 18,622.38 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 18,622.38
01.03.03.02 SOLADO e= 4" m3 2.04 285.38 582.18 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 582.18
01.03.04 OBRAS DE CONCRETO ARMADO 22,923.82 - -
01.03.04.01 CONCRETO FC=210 kg/cm2 m3 24.84 471.58 11,714.05 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 11,714.05
01.03.04.02 ACERO F'Y=4200 kg/cm2 kg 1,283.76 5.42 6,957.98 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 6,957.98
01.03.04.03 ENCOFRADO Y DESENCOFRADO m2 89.08 47.73 4,251.79 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 4,251.79
01.03.05 REVOQUES Y ENLUCIDOS 1,639.74 - -
01.03.05.01 TARRAJEO EN COLUMNAS m2 57.88 28.33 1,639.74 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 1,639.74
01.03.06 PROTECCION DE TUBERIA 21,933.16 - -
01.03.06.01 SUMINISTRO E INSTALACION DE TUBERIA HDPE 1 1/2" m 68.25 21.65 1,477.61 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 1,477.61
01.03.06.02 SUMINISTRO E INSTALACION DE TUBERIA HDPE 1 " m 40.25 15.95 641.99 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 641.99
01.03.06.03 SUMINISTRO E INSTALACION DE TUBERIA HDPE 3/4 " m 253.00 14.77 3,736.81 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 3,736.81
01.03.06.04 SUMINISTRO E INSTALACION DE TUBERIA HDPE 1/2 " m 86.25 13.76 1,186.80 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 1,186.80
01.03.06.05 CABLE TIPO BOA D=3/8" m 531.50 17.23 9,157.75 0.00% 0.00% 0.00% - 0.00% - 0.00% - 65.85% 6,030.50 34.15% 3,127.25
01.03.06.06 PÉNDOLA DE FIERRO LISO 1/4" m 252.52 22.70 5,732.20 0.00% 0.00% 0.00% - 0.00% - 0.00% - 63.36% 3,632.00 36.64% 2,100.20
01.03.07 ACCESORIOS 2,596.32 - -
01.03.07.01 ACCESORIOS PASE AEREO GLB 12.00 216.36 2,596.32 0.00% 0.00% 0.00% - 0.00% - 0.00% - 66.67% 1,730.88 33.33% 865.44
01.04 CAMARA ROMPE PRESION T- 7 31791.79 - -
01.04.01 TRABAJOS PRELIMINARES 100.94 - -
01.04.01.01 LIMPIEZA DE TERRENO MANUAL m2 23.10 2.14 49.43 28.57% 14.12 0.00% 0.00% 0.00% - 0.00% - 21.42% 10.59 50.01% 24.72
01.04.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 23.10 2.23 51.51 28.58% 14.72 0.00% 0.00% 0.00% - 0.00% - 21.43% 11.04 49.99% 25.75
01.04.02 MOVIMIENTO DE TIERRAS 789.53 - - -
01.04.02.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 10.71 42.14 451.32 0.00% 0.00% 0.00% - 0.00% - 50.00% 225.66 50.00% 225.66
01.04.02.02 RELLENO CON MATERIAL PROPIO m3 1.19 21.21 25.24 0.00% 0.00% 0.00% - 0.00% - 50.00% 12.62 50.00% 12.62
01.04.02.03 ACARREO DE MATERIAL EXCEDENTE HASTA D. Prom. = 30 m m3 12.38 25.28 312.97 0.00% 0.00% 0.00% - 0.00% - 50.00% 156.48 50.00% 156.49
01.04.03 OBRAS DE CONCRETO SIMPLE 957.52 - -
01.04.03.01 SOLADO e= 4" m3 0.70 285.38 199.77 0.00% 0.00% 0.00% - 0.00% - 50.00% 99.88 50.00% 99.89
PROGRAMACION DE CRONOGRAMA VALORIZADO DE ADICIONAL DE OBRA N°01- ACTUALIZADO
: "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE SAN JUAN DE LICUPIS – PROVINCIA DE CHOTA - REGION CAJAMARCA"
CLIENTE : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS
LUGAR : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA
FECHA : DICIEMBRE DE 2022

PRESUPUESTO BASE MES 1 - 2020 MES 2 - 2020 MES 3 - 2020 MES 4 - 2021 MES 5 - 2021 MES 6 - 2021 MES 7 - 2021 MES 8 - 2021 MES 9 - 2022 MES 10 - 2022 MES 11 - 2022 MES 12 - 2022
ITEM DESCRIPCION UNID METRADO
P.U. PARCIAL OCTUBRE: 19-31 NOVIEMBRE:01-30 DICIEMBRE:01-08 JULIO:21-31 AGOSTO:01-31 SEPTIEMBRE:01-30 OCTUBRE:01-31 NOVIEMBRE:01-28 SETIEMBRE:24-30 OCTUBRE:01-30 31 OCT AL 30 NOV. 22 01 DIC. AL 31 DIC. 22
(S/.) (S/.) AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO

01.04.03.02 CONCRETO F'C=175 kg/cm2 m3 0.77 437.36 336.77 0.00% 0.00% 0.00% - 0.00% - 50.00% 168.38 50.00% 168.39
01.04.03.03 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS PARA CAJA m2 8.82 47.73 420.98 0.00% 0.00% 0.00% - 0.00% - 50.00% 210.49 50.00% 210.49
PROGRAMACION DE CRONOGRAMA VALORIZADO DE ADICIONAL DE OBRA N°01- ACTUALIZADO
: "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE SAN JUAN DE LICUPIS – PROVINCIA DE CHOTA - REGION CAJAMARCA"
CLIENTE : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS
LUGAR : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA
FECHA : DICIEMBRE DE 2022

PRESUPUESTO BASE MES 1 - 2020 MES 2 - 2020 MES 3 - 2020 MES 4 - 2021 MES 5 - 2021 MES 6 - 2021 MES 7 - 2021 MES 8 - 2021 MES 9 - 2022 MES 10 - 2022 MES 11 - 2022 MES 12 - 2022
ITEM DESCRIPCION UNID METRADO
P.U. PARCIAL OCTUBRE: 19-31 NOVIEMBRE:01-30 DICIEMBRE:01-08 JULIO:21-31 AGOSTO:01-31 SEPTIEMBRE:01-30 OCTUBRE:01-31 NOVIEMBRE:01-28 SETIEMBRE:24-30 OCTUBRE:01-30 31 OCT AL 30 NOV. 22 01 DIC. AL 31 DIC. 22
(S/.) (S/.) AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO

01.04.04 OBRAS DE CONCRETO ARMADO 6,783.32 -


01.04.04.01 CONCRETO F'C=210 KG/CM2 PARA MURO m3 2.94 471.58 1,386.45 0.00% 0.00% 0.00% - 0.00% - 50.00% 693.22 50.00% 693.23
01.04.04.02 CONCRETO F'C=210 KG/CM2 LOSA DE FONDO m3 1.47 471.58 693.22 0.00% 0.00% 0.00% - 0.00% - 50.00% 346.61 50.00% 346.61
01.04.04.03 ACERO F'Y=4200 kg/cm2 kg 395.64 5.42 2,144.37 0.00% 0.00% 0.00% - 0.00% - 50.00% 1,072.18 50.00% 1,072.19
01.04.04.04 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 53.62 47.73 2,559.28 0.00% 0.00% 0.00% - 0.00% - 50.00% 1,279.64 50.00% 1,279.64
01.04.05 REVOQUES Y ENLUCIDOS 2,759.58 - -
01.04.05.01 TARRAJEO CON IMPERMEABILIZANTES MEZCLA 1:2, e=1.5 cm m2 24.36 52.30 1,274.03 0.00% 0.00% 0.00% - 0.00% - 50.00% 637.01 50.00% 637.02
01.04.05.02 TARRAJEO CON MORTERO 1:5 m2 43.96 28.33 1,245.39 0.00% 0.00% 0.00% - 0.00% - 50.00% 622.69 50.00% 622.70
01.04.05.03 MORTERO PENDIENTE FONDO m2 4.20 57.18 240.16 0.00% 0.00% 0.00% - 0.00% - 50.00% 120.08 50.00% 120.08
01.04.06 SUMINISTRO E INSTALACION DE VALVULAS Y ACCESORIOS 16,041.92 - -
01.04.06.01 SUMINISTRO E INST. DE VALV. Y ACCES. EN CRP-7 GLB 1.00 16,041.92 16,041.92 0.00% 0.00% 0.00% - 0.00% - 50.00% 8,020.96 50.00% 8,020.96
01.04.07 TAPA METALICA 3,918.60 - -
01.04.07.01 TAPA METALICA 0.60X0.60+ MARCO METAL GLB 7.00 309.90 2,169.30 0.00% 0.00% 0.00% - 0.00% - 50.00% 1,084.65 50.00% 1,084.65
01.04.07.02 TAPA METALICA 0.40X0.40+ MARCO METAL GLB 7.00 249.90 1,749.30 0.00% 0.00% 0.00% - 0.00% - 50.00% 874.65 50.00% 874.65
01.04.08 PINTURA 440.38 - -
01.04.08.01 PINTURA ANTICORROSIVA ESMALTE PARA METALES m2 7.28 9.59 69.82 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 69.82
01.04.08.02 PINTURA CON ESMALTE m2 38.64 9.59 370.56 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 370.56
01.03 OTROS 70,361.43 - -
01.03.01 FLETE TERRESTRE DESDE CHICLAYO GLB 1.00 48,943.95 48,943.95 25.00% 12,235.99 25.00% 12,235.99 0.00% 0.00% 0.00% - 0.00% - 25.00% 12,235.99 25.00% 12,235.98
01.03.02 FLETE RURAL AGUA P. GLB 1.00 21,417.48 21,417.48 25.00% 5,354.37 25.00% 5,354.37 0.00% 0.00% 0.00% - 0.00% - 25.00% 5,354.37 25.00% 5,354.37
-
02 ADICIONAL - PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES 33,945.60 -
02.01 CERCO PERIMETRICO DE PTAR 15,396.23 -
02.01.01 MOVIMIENTO DE TIERRAS 12,902.96 -
02.01.01.01 EXCAVACIÓN MANUAL CERCO PERIMETRICO m3 172.03 42.14 7,249.34 0.00% 0.00% 0.00% - 0.00% - 100.00% 7,249.34
02.01.01.02 ACARREO DE MATERIAL EXCEDENTE HASTA D. Prom. = 30 m m3 223.64 25.28 5,653.62 0.00% 0.00% 0.00% - 0.00% - 100.00% 5,653.62
02.01.02 OBRAS DE CONCRETO SIMPLE 2,493.27 - -
02.01.02.01 CONCRETO F'C=175 KG/CM2 + 30%PM-CERCO PERIMETRICO m3 6.27 397.65 2,493.27 0.00% 0.00% 0.00% - 0.00% - 0.00% 59.97% 1,495.16 40.03% 998.10
02.02 LECHO DE SECADO DE LODOS 15,447.64 -
02.02.01 OBRAS DE CONCRETO ARMADO 978.54 - -
02.02.01.01 CONCRETO FC=210 kg/cm2 m3 0.34 471.58 160.34 100.00% 160.34 - -
02.02.01.02 ENCOFRADO Y DESENCOFRADO m2 8.77 51.27 449.64 100.00% 449.64 - -
02.02.01.03 ACERO F'Y=4200 kg/cm2 kg 68.00 5.42 368.56 100.00% 368.56 - -
02.02.02 REVOQUES Y ENLUCIDOS 249.30 - -
02.02.02.01 TARRAJEO DE COLUMNETAS m2 8.80 28.33 249.30 100.00% 249.30 - -
02.02.03 VARIOS 14,219.80 - -
02.02.03.01 COBERTURA DE PLANCHA CALAMINA N° 030 - PTAR m2 80.22 177.26 14,219.80 0.00% 0.00% 0.00% - 0.00% - 0.00% - 100.00% 14,219.80
02.03 FLETE TERRESTRE 0.00 3,101.73 - -
02.03.01 FLETE TERRESTRE - SISTEMA ALCANTARILLADO est 1.00 3,101.73 3,101.73 50.00% 1,550.87 20.00% 620.35 0.00% 0.00% 0.00% - 0.00% - 0.00% - 30.00% 930.52
- -
03 ADICIONAL - UNIDADES BASICA DE SENEAMIENTO 742,885.84 - -
03.01 FLETE 311,196.81
03.01.01 FLETE TERRESTRE UBS est 1.00 231,004.32 231,004.32 40.00% 92,401.73 10.00% 23,100.43 10.00% 23,100.43 15.00% 34,650.65 5.00% 11,550.22 5.00% 11,550.22 10.00% 23,100.43 0.00% - 5.00% 11,550.22
03.01.02 FLETE RURAL UBS est 1.00 80,192.49 80,192.49 40.00% 32,077.00 10.00% 8,019.25 10.00% 8,019.25 15.00% 12,028.87 5.00% 4,009.62 5.00% 4,009.62 10.00% 8,019.25 0.00% - 5.00% 4,009.62
03.02 MODULO DE SSHH - EDIFICACIONES 291,642.40 - -
03.02.01 OBRAS DE CONCRETO SIMPLE 153,986.23 - -
03.02.01.01 CIMIENTO CORRIDO MEZCLA 1:10 + 30%PG. m3 187.00 361.59 67,617.33 20.71% 14,003.59 17.75% 12,003.08 11.83% 8,002.05 11.83% 8,002.05 14.79% 10,002.56 5.92% 4,001.03 7.10% 4,801.23 0.00% - 10.06% 6,801.51
03.02.01.02 SOBRECIMIENTOS CONCRETO 1:8 + 25 % PM. m3 73.25 390.21 28,582.88 20.71% 5,919.53 17.75% 5,073.88 11.83% 3,382.59 11.83% 3,382.59 14.79% 4,228.24 5.92% 1,691.29 7.10% 2,029.55 0.00% - 10.06% 2,875.85
03.02.01.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTO m2 1,415.63 40.82 57,786.02 20.71% 11,967.52 17.75% 10,257.87 11.83% 6,838.58 11.83% 6,838.58 14.79% 8,548.23 5.92% 3,419.29 7.10% 4,103.15 0.00% - 10.06% 5,812.77
03.02.02 OBRAS DE CONCRETO ARMADO 60,240.23 - -
03.02.02.01 VIGA COLLARIN 60,240.23 - -
03.02.02.01.01 CONCRETO VIGA COLLARIN F'C=175 kg/cm2 m3 39.35 437.36 17,210.12 45.53% 7,835.50 4.07% 699.60 10.98% 1,888.92 12.20% 2,098.79 4.07% 699.60 9.35% 1,609.08 8.13% 1,399.20 0.00% - 5.69% 979.69
03.02.02.01.02 ENCOFRADO Y DESENCOFRADO m2 570.33 51.27 29,240.82 45.53% 13,312.89 4.07% 1,188.65 10.98% 3,209.36 12.20% 3,565.95 4.07% 1,188.65 9.35% 2,733.90 8.13% 2,377.30 0.00% - 5.69% 1,664.22
03.02.02.01.03 ACERO F'Y=4200 kg/cm2 kg 2,544.15 5.42 13,789.29 45.53% 6,278.05 4.07% 560.54 10.98% 1,513.46 12.20% 1,681.62 4.07% 560.54 9.35% 1,289.24 8.13% 1,121.08 0.00% - 5.69% 784.76
03.02.03 CUBIERTAS 49,310.39 - -
03.02.03.01 CORREAS DE MADERA 2" X 2" m 2,778.05 17.75 49,310.39 41.46% 20,445.77 4.07% 2,004.49 11.38% 5,612.56 12.20% 6,013.46 4.07% 2,004.49 13.01% 6,414.36 13.41% 6,614.81 0.00% - 0.41% 200.40
03.02.04 REVOQUES Y ENLUCIDOS 28,105.55 0.00%
03.02.04.01 TARRAJEO PULIDO EN DUCHA m2 945.36 29.73 28,105.55 17.24% 4,845.78 5.75% 1,615.26 14.94% 4,199.68 17.24% 4,845.78 5.75% 1,615.26 19.54% 5,491.89 18.97% 5,330.36 0.00% - 0.57% 161.43
03.03 SISTEMA DE TRATAMIENTO DE AGUAS RESIDUALES 140,046.63 - -
03.03.01 CAJA DE RECOLECCION DE LODOS 85,899.60 - -
03.03.01.01 TRABAJOS PRELIMINARES 1,251.00 - -
03.03.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 286.27 2.14 612.62 52.82% 323.57 7.04% 43.14 3.52% 21.57 10.56% 64.71 14.08% 86.28 7.04% 43.14 0.00% - 4.93% 30.20
03.03.01.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 286.27 2.23 638.38 52.82% 337.17 7.04% 44.96 3.52% 22.48 10.56% 67.43 14.08% 89.91 7.04% 44.96 0.00% - 4.93% 31.47
03.03.01.02 MOVIMIENTO DE TIERRAS 10,669.25 - -
03.03.01.02.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 134.44 42.14 5,665.30 45.77% 2,593.27 3.52% 199.48 3.52% 199.48 3.52% 199.48 12.32% 698.19 15.85% 897.67 8.80% 498.71 0.00% - 6.69% 378.84
03.03.01.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 174.78 28.63 5,003.95 45.77% 2,290.54 3.52% 176.20 3.52% 176.20 3.52% 176.20 12.32% 616.68 15.85% 792.88 8.80% 440.49 0.00% - 6.69% 334.68
03.03.01.03 OBRAS DE CONCRETO 58,866.71 - - -
03.03.01.03.01 CONCRETO F'C=175 kg/cm2 m3 81.00 437.36 35,426.16 45.77% 16,216.20 3.52% 1,247.40 3.52% 1,247.40 3.52% 1,247.40 12.32% 4,365.90 15.85% 5,613.30 8.80% 3,118.50 0.00% - 6.69% 2,370.49
03.03.01.03.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 459.90 47.73 21,951.03 45.77% 10,048.01 3.52% 772.92 3.52% 772.92 3.52% 772.92 12.32% 2,705.23 15.85% 3,478.16 8.80% 1,932.31 0.00% - 6.69% 1,468.65
PROGRAMACION DE CRONOGRAMA VALORIZADO DE ADICIONAL DE OBRA N°01- ACTUALIZADO
: "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE SAN JUAN DE LICUPIS – PROVINCIA DE CHOTA - REGION CAJAMARCA"
CLIENTE : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS
LUGAR : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA
FECHA : DICIEMBRE DE 2022

PRESUPUESTO BASE MES 1 - 2020 MES 2 - 2020 MES 3 - 2020 MES 4 - 2021 MES 5 - 2021 MES 6 - 2021 MES 7 - 2021 MES 8 - 2021 MES 9 - 2022 MES 10 - 2022 MES 11 - 2022 MES 12 - 2022
ITEM DESCRIPCION UNID METRADO
P.U. PARCIAL OCTUBRE: 19-31 NOVIEMBRE:01-30 DICIEMBRE:01-08 JULIO:21-31 AGOSTO:01-31 SEPTIEMBRE:01-30 OCTUBRE:01-31 NOVIEMBRE:01-28 SETIEMBRE:24-30 OCTUBRE:01-30 31 OCT AL 30 NOV. 22 01 DIC. AL 31 DIC. 22
(S/.) (S/.) AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO

03.03.01.03.03 ACERO F'Y=4200 kg/cm2 kg 274.82 5.42 1,489.52 45.77% 681.82 3.52% 52.45 3.52% 52.45 3.52% 52.45 12.32% 183.57 15.85% 236.02 8.80% 131.12 0.00% - 6.69% 99.67
PROGRAMACION DE CRONOGRAMA VALORIZADO DE ADICIONAL DE OBRA N°01- ACTUALIZADO
: "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE SAN JUAN DE LICUPIS – PROVINCIA DE CHOTA - REGION CAJAMARCA"
CLIENTE : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS
LUGAR : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA
FECHA : DICIEMBRE DE 2022

PRESUPUESTO BASE MES 1 - 2020 MES 2 - 2020 MES 3 - 2020 MES 4 - 2021 MES 5 - 2021 MES 6 - 2021 MES 7 - 2021 MES 8 - 2021 MES 9 - 2022 MES 10 - 2022 MES 11 - 2022 MES 12 - 2022
ITEM DESCRIPCION UNID METRADO
P.U. PARCIAL OCTUBRE: 19-31 NOVIEMBRE:01-30 DICIEMBRE:01-08 JULIO:21-31 AGOSTO:01-31 SEPTIEMBRE:01-30 OCTUBRE:01-31 NOVIEMBRE:01-28 SETIEMBRE:24-30 OCTUBRE:01-30 31 OCT AL 30 NOV. 22 01 DIC. AL 31 DIC. 22
(S/.) (S/.) AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO AVANCE MONTO

03.03.01.04 REVOQUES Y ENLUCIDOS 15,112.64 - - -


03.03.01.04.01 TARRAJEO CON MORTERO 1:5 m2 533.45 28.33 15,112.64 26.41% 3,991.01 15.85% 2,394.61 8.80% 1,330.34 8.80% 1,330.34 12.32% 1,862.47 12.32% 1,862.47 8.80% 1,330.34 0.00% - 6.69% 1,011.10
03.03.02 POZO PERCOLADOR 54,147.03 - -
03.03.02.01 OBRAS DE CONCRETO SIMPLE 19,395.97 - -
03.03.02.01.01 CIMIENTOS CORRIDOS CONCRETO 1:8 + 25 % PM. m3 50.67 382.79 19,395.97 43.31% 8,399.83 3.94% 763.62 11.81% 2,290.86 3.94% 763.62 6.30% 1,221.79 13.39% 2,596.31 9.84% 1,909.05 0.00% - 7.48% 1,450.77
03.03.02.02 CONCRETO ARMADO 34,751.06 - - -
03.03.02.02.01 CONCRETO F'C=175 KG/CM2 POZO PERCOLADOR m3 28.29 590.53 16,706.09 43.31% 7,234.92 3.94% 657.72 9.84% 1,644.30 3.94% 657.72 7.87% 1,315.44 13.78% 2,302.02 9.84% 1,644.30 0.00% - 7.49% 1,251.92
03.03.02.02.02 ENCOFRADO Y DESENCOFRADO m2 202.27 42.08 8,511.52 43.31% 3,686.09 3.94% 335.10 9.84% 837.75 3.94% 335.10 7.87% 670.20 13.78% 1,172.85 9.84% 837.75 0.00% - 7.48% 636.67
03.03.02.02.03 ACERO F'Y=4200 kg/cm2 kg 1,758.94 5.42 9,533.45 43.31% 4,128.66 3.94% 375.33 13.78% 1,313.67 7.87% 750.67 7.87% 750.67 5.91% 563.00 9.84% 938.33 0.00% - 7.48% 713.11

TOTAL COSTO DIRECTO (A) S/ 973,106.47 289,760.98 89,708.59 75,720.35 89,438.29 58,929.69 61,900.79 71,765.36 46,140.15 154,413.36 16,473.43 2,788.98 16,066.50
GASTOS GENERALES (B) 7.40% S/ 72,009.88 21,442.31 6,638.44 5,603.31 6,618.43 4,360.80 4,580.66 5,310.64 3,414.37 11,426.59 1,219.03 206.37 1,188.93
UTILIDAD (C) 4.60% S/ 44,762.90 13,329.01 4,126.60 3,483.14 4,114.16 2,710.77 2,847.44 3,301.21 2,122.45 7,103.01 757.78 128.27 739.06
SUBTOTAL (A+B+C) S/ 1,089,879.25 324,532.30 100,473.63 84,806.80 100,170.88 66,001.26 69,328.89 80,377.21 51,676.97 172,942.96 18,450.24 3,123.62 17,994.49
IGV (18.00%) S/ 196,178.27 58,415.81 18,085.25 15,265.22 18,030.76 11,880.23 12,479.20 14,467.90 9,301.85 31,129.73 3,321.03 562.28 3,239.01
TOTAL PRESUPUESTO CON IGV S/ 1,286,057.52 382,948.11 118,558.88 100,072.02 118,201.64 77,881.49 81,808.09 94,845.11 60,978.82 204,072.69 21,771.27 3,685.90 21,233.50
MONTO ACUMULADO 382,948.11 501,506.99 601,579.01 719,780.65 797,662.14 879,470.23 974,315.34 1,035,294.16 1,239,366.85 1,261,138.12 1,264,824.02 1,286,057.52

AVANCE PARCIAL 29.78% 9.22% 7.78% 9.19% 6.06% 6.36% 7.37% 4.74% 15.87% 1.69% 0.29% 1.65%
AVANCE ACUMULADO 29.78% 39.00% 46.78% 55.97% 62.02% 68.38% 75.76% 80.50% 96.37% 98.06% 96.66% 99.71%