PROYECTO : “MANTENIMIENTO CORRECTIVO BASICO DE LA INFRAESTRUCTURA UNIDAD EDUCATIVA FISCAL LUIS PAUTA RODRIGUEZ
PLAZO REFERENCIAL : 30 DIAS AMIE: 09H02617
316 LLAVE ANGULAR 1/2" PARA INODORO, INCLUYE MANGUERA DE ABASTO $ 94.20 94.20
SUBTOTALES 61727.71560
FLUJO MENSUAL PARCIAL (NO INCLUYE IVA) 61727.71560 17,850.47 21,153.55 15,877.28 5,682.17 1,164.25
PORCENTAJE PARCIAL 28.92% 34.27% 25.72% 9.21% 1.89%
FLUJO ACUMULADO (NO INCLUYE IVA) $17,850.47 $39,004.02 $54,881.30 $60,563.47 $61,727.72
PORCENTAJE ACUMULADO 28.92% 63.19% 88.91% 98.11% 100.00%
ELABORADO POR: RECIBIDO POR :